1 19 May 2015 BY Manor Park Management 231 Brittany Drive, Suite D Ottawa, ON K1K 0R8 Attention: Mr. Anand Aggarwal RE: 3605 Paul Anka Drive Addendum #2 to the December 2012 Traffic Impact Study 1. INTRODUCTION From the information provided, we understand you will be pursuing a Rezoning and Site Plan Application for a development proposal on the above-noted site located just south of Hunt Club Road. We are advised that the intent is to now pursue a 99-suite extended stay hotel instead of the previously proposed 69 unit apartment building. The current Site Plan is depicted in Figure 1. In discussing this file with Wally Dubyk of the City, he is aware of the traffic issues in the immediate area, potentially due to recent development of the adjacent sites, and the City has recently installed speed bumps on Dean Martin Crescent to slow traffic, and a curb extension on Paul Anka at its Wisteria intersection to improve sight lines. Given the sensitivity of the area residents and Ward Councillor to these traffic issues, it was agreed that current counts at key intersections on these local street are needed as a basis on which to assess the impacts/requirements, if any, of the extended stay hotel proposal. Based on the foregoing, we have prepared this Addendum to both our previous Traffic Impact Study (TIS) and Addendum #1 to support the requested Rezoning and Site Plan. 2. NET CHANGE IN PEAK HOUR TRAFFIC GENERATION Consistent with the TIS we used ITE trip generation rates and then adjusted these to account for local characteristics, with regard to vehicle occupancy, transit ridership and bike/walk travel modes. Included in Attachment #1 are the resultant new vehicle trips for both the previous 69 unit apartment proposal and the current 99 room suite hotel proposal. The following Table 1 compares the peak hour vehicle trip generation of these two land uses.

2 Figure 1: Site Plan Page 2

3 Page 3 Table 1: Vehicle Trip Generation Comparison Vph Two-way Total Land Use AM Peak Hour PM Peak Hour 69 unit apartment 30 vph 44 vph 99 suite hotel 32 vph 46 vph Net Difference +2 vph +2 vph As can be seen from review of Attachment # 1 and Table 1, the peak hour vehicle trip generation of the previous proposed 69 unit apartment and the currently proposed 99 suite hotel are effectively the same. As such, the related findings, conclusions and recommendations of the TIS remain valid. 3. SITE PLAN OVERVIEW A review of the Figure 1: Site Plan indicates that the dimensions for the parking spaces and circulation aisles meet By-law requirements. With regard to site access/egress, it is the same as per the approved Site Plan, and is therefore considered acceptable. There will be one driveway connection to Paul Anka Drive, located between Wisteria Crescent and Hunt Club Road, and also a driveway connection through to the adjacent recently developed site that will provide access/egress to Gibford. Because of these connections, which provide quite direct access to both Hunt Club and Uplands Drive, it is estimated that very little of the Table 1 sitegenerated traffic will travel on the sections of Paul Anka and Dean Martin between Wisteria and Gibford. 4. EXISTING TRAFFIC CONDITIONS We are advised of community concerns regarding cut-through traffic using the Paul Anka/ Dean Martin/ Gibford link as a by-pass to the signalized Hunt Club/ Uplands intersection. To assist in either reducing the volume of cut through traffic and/or reduce its speed, we have been advised that the City has recently installed speed bumps on Dean Martin Crescent. To assist in quantifying the current traffic volumes using Paul Anka, Dean Martin and Gibford, Parsons conducted morning and afternoon perk hour traffic counts at these intersections on May 12 and 13, The count summaries are included as Attachment #2. In review of these counts, it can be seen that at the Paul Anka/Wisteria intersection, the significant majority of peak hour traffic is to/from Wisteria with only a small percentage being through traffic on Paul Anka. At the Wisteria intersection, 75% to 80% of the traffic is to/from Wisteria and only 20% to 25% is through traffic. Table 2: Wisteria/ Paul Anka Traffic Summary AM Peak Hour PM Peak Hours Two-way Traffic on Wisteria 77 vph 87 vph Though Traffic on Paul Anka 28 vph 23 vph Total 105 vph 110 vph At the Dean Martin/Gibford intersection, peak hour volumes were very low as summarized in Attachment #2 and in the following Table 3.

4 Page 4 Table 3: Dean Martin/Gibford Traffic Summary AM Peak Hour PM Peak Hours Two-way Traffic on Dean Martin 39 vph 49 vph Two-way Traffic on Gibford North of Dean Martin 51 vph 35 vph Two-way Traffic on Gibford South of Dean Martin 62 vph 74 vph As demonstrated in Table 2, the current peak hour traffic volumes on Dean Martin are quite low at approximately 1 vehicle every 1 to 2 minutes during peak hours. During the rest of the day, they would be even less. This volume of traffic is considered very appropriate for and compatible with local streets. Observed Driver Behaviour While conducting the aforementioned traffic counts, the following driver behaviour was observed at the two intersections Wisteria/ Paul Anka Intersection: Poor compliance to the STOP sign on Wisteria. Numerous drivers on Wisteria treated the STOP sign as a Yield sign, and as such only slowed down before continuing into the intersection, but did not stop. Often the driver had to break hard because a car was travelling on Paul Anka, which the Wisteria driver was not anticipating (given the low volume of though traffic on Paul Anka). There is a school bus drop off on Dean Martin. We observed a few vehicles from Wisteria parking in the no parking/no stopping zone on the Paul Anka/Dean Martin curve waiting for children to depart from the school bus. Once the bus left and the children were in the cars, U-turns were performed with the vehicles then turning back into Wisteria. Gibford/Dean Martin Intersection: STOP sign compliance was much better at this intersection, with few rolling stops. As the traffic is more evenly balanced between all-movements (unlike at Wisteria) this is conducive to most drivers stopping correctly. Dean Martin Speed Humps: The two speed humps on Dean Martin appear to be effective for this stretch of road, as these was very little vehicle breaking as cars travelled over the humps. This usually indicates that the design and spacing of the humps is in keeping with the desired travel speed for the road. 5. FINDINGS, CONCLUSIONS AND RECOMMENDATIONS. Based on the foregoing analysis, the findings, conclusions and recommendations of this Addendum are as follows. Findings and Conclusions The property is seeking a SPA to change the use from a 69 unit apartment building to a 99 unit suite hotel; Comparison of the projected peak hour vehicle trips between the two uses indicates that they are effectively the same (± 2 vph difference); With the exception of the addition of a passenger drop-off lane at the hotel front door and a garbage/loading facility at the east end of the building, the on-site transportation and site access/egress is the same;

5 Page 5 Current peak hour traffic volumes on Paul Anka, Dean Martin and Gibford are relatively low and in keeping with their local road description; The recently installed speed humps on Dean Martin Crescent appear to be effective in controlling vehicle speed for this section of roadway; At the Wisteria/Paul Anka intersection the following was observed; - The significant majority of traffic (70% to 75%) using this intersection during peak hour is to/from Wisteria. Through traffic is a significant minority (20%-25%); - A noticeable number of vehicles travelling eastbound on Wisteria and approaching the STOP sign on Paul Anka, do not stop, but instead roll though the STOP sign and then only stop (abruptly) if there is a car travelling on Paul Anka; and - Residents of Wisteria Crescent were observed to park illegally on the bend of Paul Anka and Dean Martin to wait for their children to come home on the school bus. Once the children are in the car, a U-turn is made and the vehicle returns to Wisteria Crescent. Adherence to the STOP signs at the Dean Martin/Gibford intersection was high; and Given the location of the site driveway connections to Paul Anka and Gibford, very little site-generated traffic is expected to travel on the section of Paul Anka Drive or Dean Martin Crescent between Wisteria and Gibford. Recommendations As there is effectively no change in site-generated traffic between the previous and current proposed land uses, and as the on-site circulation is also effectively the same, the proposed Site Plan is recommended from a transportation perspective. Please call if you have any questions of the foregoing. Sincerely, Ronald M. Jack, P.Eng. Vice President Manager Ottawa Operations Attachments

6 Attachment #1: Projected Vehicle Trips - 69 unit apartment - 99 suite hotel

7 Trip Generation - 99 Room Hotel 19/05/2015 8:54 AM ITE Vehicle Trip Generation Rates Land Use Data Source Trip Rate AM Peak PM Peak Hotel ITE Modified Person Trip Generation Rates Land Use Data Source Person Trip Rate AM Peak PM Peak Hotel ITE Note: 1.3 factor to account for typical North American auto occupancy values of approximately 1.15 and combined transit and non-motorized modal shares of less than 10% ITE Fitted Curve Equations Land Use Data Source Fitted Curve Equation AM Peak PM Peak Hotel ITE 310 Ln(T)= 1.24Ln(x) N/A 0.00(x) Modified Person Trip Generation Land Use Data Source Area AM Peak (Person Trips/hr) PM Peak (Person Trips/hr) In Out Total In Out Total Total Site Units 61% 39% 53% 47% Hotel ITE du Total Total Site Trip Generation Travel Mode Mode Share AM Peak (Person Trips/hr) PM Peak (Person Trips/hr) In Out Total In Out Total Auto Driver 60% Auto Passenger 25% Transit 10% Non-motorized 5% Total Person Trips 100% Total 'New' Auto Trips Total Site Vehicle Trip Generation Travel Mode AM Peak (veh/hr) PM Peak (veh/hr) In Out Total In Out Total Total Site Trip Generation Total 'New' Auto Trips Prepared by Andre Sponder Page 1 1

8 Trip Generation - 69 Apartments 19/05/2015 8:56 AM ITE Vehicle Trip Generation Rates Land Use Data Source Trip Rate AM Peak PM Peak Apartments ITE Modified Person Trip Generation Rates Land Use Data Source Person Trip Rate AM Peak PM Peak Apartments ITE Note: 1.3 factor to account for typical North American auto occupancy values of approximately 1.15 and combined transit and non-motorized modal shares of less than 10% ITE Fitted Curve Equations Land Use Data Source Fitted Curve Equation AM Peak PM Peak Apartments ITE 220 T= 0.49(x) T= 0.55(x) Modified Person Trip Generation Land Use Data Source Area AM Peak (Person Trips/hr) PM Peak (Person Trips/hr) In Out Total In Out Total Total Site Units 20% 80% 65% 35% Apartments ITE du Total Total Site Trip Generation Travel Mode Mode Share AM Peak (Person Trips/hr) PM Peak (Person Trips/hr) In Out Total In Out Total Auto Driver 60% Auto Passenger 25% Transit 10% Non-motorized 5% Total Person Trips 100% Total 'New' Auto Trips Total Site Vehicle Trip Generation Travel Mode AM Peak (veh/hr) PM Peak (veh/hr) In Out Total In Out Total Total Site Trip Generation Total 'New' Auto Trips Prepared by Andre Sponder Page 1 1

9 Attachment #2: Current 2015 Traffic Counts - Paul Anka/Wisteria - Dean Martin/Gibford

10 Intersection: Date: Observer: Weather: Time: Paul Anka Dr & Wisteria Cres May 12, 2015 Alex Buck Overcast 7:30 AM - 8:30 AM Paul Anka 6 12 Wisteria 63 4 Wisteria 4 16 Paul Anka TIME NBL NBT NBR SBL SBT SBR EBL EBT EBR WBL WBT WBR 7:30 AM :45 AM :00 AM :15 AM TOTAL Notes: {

11 Intersection: Date: Observer: Weather: Time: Paul Anka Dr & Wisteria Cres May 12, 2015 Alex Buck Overcast 4:00 PM - 5:00 PM Paul Anka Wisteria 26 2 Wisteria 4 10 Paul Anka TIME NBL NBT NBR SBL SBT SBR EBL EBT EBR WBL WBT WBR 4:00 PM :15 PM :30 PM :45 PM TOTAL Notes: {

12 Intersection: Date: Observer: Weather: Time: Dean Martin Cres & Gibford Dr May 13, 2015 Alex Buck Overcast 7:30 AM - 8:30 AM Gibford 4 17 Dean Martin Dean Martin Gibford TIME NBL NBT NBR SBL SBT SBR EBL EBT EBR WBL WBT WBR 7:30 AM :45 AM :00 AM :15 AM TOTAL Notes: {

13 Intersection: Date: Observer: Weather: Time: Dean Martin Cres & Gibford Dr May 13, 2015 Alex Buck Sunny, Clear 4:00 PM - 5:00 PM Gibford 2 5 Dean Martin 3 21 Dean Martin Gibford TIME NBL NBT NBR SBL SBT SBR EBL EBT EBR WBL WBT WBR 4:06 PM :15 PM :30 PM :45 PM TOTAL Notes: {

The Re:Queen and Sparks Traffic Brief - Addendum #2

The Re:Queen and Sparks Traffic Brief - Addendum #2 June 11, 2015 Ashcroft Homes 18 Antares Drive Ottawa, ON K2E 1A9 EMAIL: mpham@ashcrofthomes.com Attention: May Pham Development Planner Dear May, Re: The Re:Queen and Sparks Traffic Brief - Addendum #2

More information

Re: Sainte-Geneviève Elementary School (2198 Arch Street) Transportation Overview

Re: Sainte-Geneviève Elementary School (2198 Arch Street) Transportation Overview 2 March 2015 OUR REF: TO3205TOB00 Conseil des écoles catholiques du Centre-Est (CECCE) 4000 rue Labelle Ottawa, Ontario K1J 1A1 Attention: Maguy Eustache Dear Maguy: Re: Sainte-Geneviève Elementary School

More information

Re: 233 Armstrong Street Residential Condominium Traffic Brief

Re: 233 Armstrong Street Residential Condominium Traffic Brief 1223 Michael Street, Suite 100, Ottawa, ON K1J 7T2 Tel: 613.738.4160 Fax: 613.739.7105 www.delcan.com August 8, 2008 TO3031TOP00 BY E-MAIL: gerry.lalonde@rogers.com Spencedale Properties 7 Cobb Court Ottawa,

More information

Re: Cyrville Road Car Dealership

Re: Cyrville Road Car Dealership 1223 Michael Street, Suite 100, Ottawa, ON K1J 7T2 Tel: 613.738.4160 Fax: 613.739.7105 www.delcan.com February 25, 2013 OUR REF: TO3098TOE Mark Motors of Ottawa 611 Montreal Road Ottawa, ON K1K 0T8 Attention:

More information

Table 1 - Land Use Comparisons - Proposed King s Wharf Development. Retail (SF) Office (SF) 354 6,000 10, Land Uses 1

Table 1 - Land Use Comparisons - Proposed King s Wharf Development. Retail (SF) Office (SF) 354 6,000 10, Land Uses 1 Ref. No. 171-6694 Phase 2 November 23, 217 Mr. David Quilichini, Vice President Fares & Co. Developments Inc. 31 Place Keelson Sales Centre DARTMOUTH NS B2Y C1 Sent Via Email to David@faresinc.com RE:

More information

Re: Residential Development - Ogilvie/Cummings Transportation Overview

Re: Residential Development - Ogilvie/Cummings Transportation Overview 1223 Michael Street, Suite 100, Ottawa, ON K1J 7T2 Tel: 613.738.4160 Fax: 613.739.7105 www.delcan.com March 28, 2012 OUR REF: TO3088TOY Barry J. Hobin & Architects 63 Pamilla Street Ottawa, ON K1S 3K7

More information

700 Hunt Club Road. Transportation Impact Study - Addendum #1. Submitted by:

700 Hunt Club Road. Transportation Impact Study - Addendum #1. Submitted by: 700 Hunt Club Road Transportation Impact Study - Addendum #1 Submitted by: 14 June 2013 1223 Michael Street, Suite 100, Ottawa, ON K1J 7T2 Tel: 613.738.4160 Fax: 613.739.7105 www.delcan.com 14 June 2013

More information

370 Queen Elizabeth Drive Transportation Overview

370 Queen Elizabeth Drive Transportation Overview December 8, 2014 OUR REF: TO3193TOA BY EMAIL: Ashley@rocahomes.ca 2253644 Ontario Inc. c/o BassCon 24 George Street West Ottawa, ON K1S 3J2 Attention: Ashley Lepine Dear Ashley: Re: 370 Queen Elizabeth

More information

April Salvation Army Barrhaven Church 102 Bill Leathem Drive Transportation Brief

April Salvation Army Barrhaven Church 102 Bill Leathem Drive Transportation Brief April 26 Salvation Army Barrhaven Church 2 Bill Leathem Drive Transportation Brief Salvation Army Barrhaven Church 2 Bill Leathem Drive Transportation Brief prepared for: The Salvation Army 2 Overlea Blvd.

More information

RE: Taggart Retail Site Plan: Kanata West Proposal for Traffic Impact Study: Addendum #2

RE: Taggart Retail Site Plan: Kanata West Proposal for Traffic Impact Study: Addendum #2 1223 Michael Street, Suite 100, Ottawa, Ontario K1J 7T2 Tel: 613.738.4160 Fax: 613.739.7105 www.delcan.com July 9, 2014 OUR REF: TO3073TOK00 BY EMAIL: jparkes@taggart.ca/aturner@taggart.ca Taggart Commercial

More information

Provide an overview of the development proposal including projected site traffic volumes;

Provide an overview of the development proposal including projected site traffic volumes; December 19, 2013 File: 163600935 Attention: Troy Elliott Carl Elliott Limited 15-1831 Robertson Road PO Box 11117 Nepean, Ontario K1H 7T8 Dear Mr. Elliott, Reference: 2235 and 2265 Robertson Road Transportation

More information

267 O Connor Street Residential Development

267 O Connor Street Residential Development M a y 2014 267 O Connor Street Residential Development Transportation Brief Google 2014 Bing 2014 Prepared for: MASTERCRAFT STARWOOD Prepared by: Study 267 O'Connor Type Street May 2014 Study Residential

More information

Wellington Street West

Wellington Street West Transportation Brief prepared for: 185 Davenport Road Suite 300 Toronto, ON M5R 1J1 prepared by: 1223 Michael Street Suite 100 Ottawa, ON K1J 7T2 November 5, 2013 TO3131TOH Transportation Brief November

More information

Re: Addendum No. 4 Transportation Overview 146 Mountshannon Drive Ottawa, Ontario

Re: Addendum No. 4 Transportation Overview 146 Mountshannon Drive Ottawa, Ontario April 18 th, 2017 Mr. Kevin Yemm Vice President, Land Development Richraft Group of Companies 2280 St. Laurent Boulevard, Suite 201 Ottawa, Ontario (Tel: 613.739.7111 / e-mail: keviny@richcraft.com) Re:

More information

Traffic Analysis For Approved Uses within the St. Lucie West DRI Aldi Port St. Lucie, FL Prepared for: Bohler Engineering, LLC 1000 Corporate Drive Suite 250 Fort Lauderdale, FL 33334 Prepared by: 10795

More information

MEMO. McCORMICK RANKIN CORPORATION. File FROM: Keyur Shah DATE: February 1, 2010 COPIES: OUR FILE: SUBJECT: TO:

MEMO. McCORMICK RANKIN CORPORATION. File FROM: Keyur Shah DATE: February 1, 2010 COPIES: OUR FILE: SUBJECT: TO: McCORMICK RANKIN CORPORATION 2655 North Sheridan Way Mississauga, Ontario, L5K 2P8 Tel: (905)823-8500 Fax: (905) 823-8503 E-mail: mrc@mrc.ca Website: www.mrc.ca MEMO TO: File FROM: Keyur Shah DATE: February

More information

Ref. No Task 3. April 28, Mr. Cesar Saleh, P. Eng. VP Planning and Design W.M. Fares Group th

Ref. No Task 3. April 28, Mr. Cesar Saleh, P. Eng. VP Planning and Design W.M. Fares Group th Ref. No. 151-00564 Task 3 April 28, 2015 Mr. Cesar Saleh, P. Eng. VP Planning and Design W.M. Fares Group th 3480 Joseph Howe Drive, 5 Floor HALIFAX NS B3L 4H7 Sent via Email to ceasr.saleh@wmfares.com

More information

CENTRAL VIRGINIA LONG RANGE TRANSPORTATION PLAN. Appendix F

CENTRAL VIRGINIA LONG RANGE TRANSPORTATION PLAN. Appendix F Data Collection Traffic turning movement data were obtained from the Virginia Department of Transportation (VDOT) Southwestern Region Lynchburg District Traffic Engineering Section. However, 12-hour traffic

More information

Alpine Highway to North County Boulevard Connector Study

Alpine Highway to North County Boulevard Connector Study Alpine Highway to North County Boulevard Connector Study prepared by Avenue Consultants March 16, 2017 North County Boulevard Connector Study March 16, 2017 Table of Contents 1 Summary of Findings... 1

More information

1012 & 1024 McGarry Terrace

1012 & 1024 McGarry Terrace December 217 112 & 124 McGarry Terrace Transportation Impact Study 112 & 124 McGarry Terrace Transportation Impact Study prepared for: Lépine Corporation 32 March Road Kanata, ON K2K 2E3 prepared by: 1223

More information

1140 Wellington Street West Transportation Brief

1140 Wellington Street West Transportation Brief 1140 Wellington Street West Transportation Brief October 2013 Study 1140 Wellington Type Street West October 2013 Study Transportation Name Brief February 2011 TB Check List TIS / TB/ CTS Check List prepared

More information

700 Hunt Club Road. Transportation Impact Study. Submitted by:

700 Hunt Club Road. Transportation Impact Study. Submitted by: 700 Hunt Club Road Transportation Impact Study Submitted by: December 2012 700 Hunt Club Road Transportation Impact Study prepared for: Lone Star Group of Companies 472 Morden Road Unit 101 Oakville, ON

More information

Bennett Pit. Traffic Impact Study. J&T Consulting, Inc. Weld County, Colorado. March 3, 2017

Bennett Pit. Traffic Impact Study. J&T Consulting, Inc. Weld County, Colorado. March 3, 2017 Bennett Pit Traffic Impact Study J&T Consulting, Inc. Weld County, Colorado March 3, 217 Prepared By: Sustainable Traffic Solutions, Inc. http://www.sustainabletrafficsolutions.com/ Joseph L. Henderson,

More information

CitiGate Retail Development

CitiGate Retail Development CitiGate Retail Development Transportation Impact Study prepared for: Trinity Development Group Inc. Sun Life Financial Centre, East Tower 3250 Bloor Street West, Suite 1000 Toronto, ON M8X 2X9 prepared

More information

L1TILE BEARS DAY CARE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO MAY Prepared for:

L1TILE BEARS DAY CARE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO MAY Prepared for: L1TILE BEARS DAY CARE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO MAY 2012 Prepared for: Hillside Construction, Inc. 216 Hemlock Street, Suite B Fort Collins, CO 80534 Prepared by: DELICH ASSOCIATES

More information

Proposed Hotel and Restaurant Development

Proposed Hotel and Restaurant Development Traffic Impact Study Proposed Hotel and Restaurant Development Marbledale Road Tuckahoe, NY PREPARED FOR BILLWIN DEVELOPMENT AFFILIATES, LLC 365 WHITE PLAINS ROAD EASTCHESTER, NY. 10709 PREPARED BY Engineering

More information

APPENDIX G. Traffic Data

APPENDIX G. Traffic Data APPENDIX G Traffic Data HCM Signalized Intersection Capacity Analysis 2: Duanesburg Road & I-88 Ramps 10/7/2004 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Ideal Flow (vphpl)

More information

Appendix H: Construction Impacts H-2 Transportation

Appendix H: Construction Impacts H-2 Transportation Appendix H: Construction Impacts H-2 Transportation \ AECOM 71 W. 23 rd Street New York, NY 10010 www.aecom.com 212 366 6200 tel 212 366 6214 fax Memorandum To CC Subject Robert Conway Donald Tone Construction

More information

MEMO. McCORMICK RANKIN CORPORATION. File Mark VanderSluis, Keyur Shah DATE: October 26, 2009 COPIES: OUR FILE: TO: FROM: Jack Thompson

MEMO. McCORMICK RANKIN CORPORATION. File Mark VanderSluis, Keyur Shah DATE: October 26, 2009 COPIES: OUR FILE: TO: FROM: Jack Thompson McCORMICK RANKIN CORPORATION 2655 North Sheridan Way Mississauga, Ontario, L5K 2P8 Tel: (95)823-85 Fax: (95) 823-853 E-mail: mrc@mrc.ca Website: www.mrc.ca MEMO TO: FROM: File Mark VanderSluis, Keyur Shah

More information

MEMORANDUM. Date: November 4, Cheryl Burrell, Pebble Beach Company. Rob Rees, P.E. Inclusionary Housing Transportation Analysis WC

MEMORANDUM. Date: November 4, Cheryl Burrell, Pebble Beach Company. Rob Rees, P.E. Inclusionary Housing Transportation Analysis WC MEMORANDUM Date: November 4, 2013 To: From: Subject: Cheryl Burrell, Pebble Beach Company Rob Rees, P.E. Inclusionary Housing Transportation Analysis As requested, Fehr & Peers is providing clarification

More information

Traffic Impact Analysis Farmington Center Village

Traffic Impact Analysis Farmington Center Village Traffic Impact Analysis Farmington Center Village Route 4 (Farmington Avenue) Farmington, Connecticut Prepared for: The Town of Farmington, CT Prepared By: BL Companies Meriden, Connecticut December 2016

More information

RE: 67/71 Marquette Avenue Redevelopment Transportation Overview

RE: 67/71 Marquette Avenue Redevelopment Transportation Overview 1223 Michael Street, Suite 100, Ottawa, Ontario K1J 7T2 Tel: 613.738.4160 Fax: 613.739.7105 www.delcan.com April 23, 2014 OUR REF: TO3157TOA00 BY EMAIL: mark.larose@urbanrisedevelopment.com Urban Rise

More information

Ingraham High School Parking and Traffic Analysis

Ingraham High School Parking and Traffic Analysis Parking and Traffic Analysis Seattle, WA Prepared for: URS Corporation 1501 4th Avenue, Suite 1400 Seattle, WA 98101-1616 Mirai Transportation Planning & Engineering 11410 NE 122nd Way, Suite 320 Kirkland,

More information

RE: A Traffic Impact Statement for a proposed development on Quinpool Road

RE: A Traffic Impact Statement for a proposed development on Quinpool Road James J. Copeland, P.Eng. GRIFFIN transportation group inc. 30 Bonny View Drive Fall River, NS B2T 1R2 May 31, 2018 Ellen O Hara, P.Eng. Project Engineer DesignPoint Engineering & Surveying Ltd. 200 Waterfront

More information

One Harbor Point Residential

One Harbor Point Residential Residential Gig Harbor, WA Transportation Impact Analysis January 23, 2017 Prepared for: Neil Walter Company PO Box 2181 Tacoma, WA 98401 Prepared by: TENW Transportation Engineering NorthWest 11400 SE

More information

April 7, Mr. Blake Shutler Compass Homes Development LLC Summit Homes Construction, LLC PO Box 6539 Dillon, CO 80435

April 7, Mr. Blake Shutler Compass Homes Development LLC Summit Homes Construction, LLC PO Box 6539 Dillon, CO 80435 Compass Homes Development LLC Summit Homes Construction, LLC PO Box 6539 Dillon, CO 80435 Re: Trip Generation Comparison West Hills Townhomes Keystone, Colorado FHU Reference No. 116388-01 Dear Mr. Shutler:

More information

TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION

TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION DECEMBER 2014 UPDATED

More information

Traffic Impact Study Hudson Street Parking Garage MC Project No.: A Table of Contents

Traffic Impact Study Hudson Street Parking Garage MC Project No.: A Table of Contents Traffic Impact Study Hudson Street Parking Garage MC Project No.: 15001714A Table of Contents Table of Contents I. INTRODUCTION... 1 II. EXISTING CONDITIONS... 4 III. 2015 EXISTING TRAFFIC CONDITIONS...

More information

Paisley & Whitelaw - Paisley Park OPA / ZBA for Mixed Density Residential Use

Paisley & Whitelaw - Paisley Park OPA / ZBA for Mixed Density Residential Use Paisley & Whitelaw - Paisley Park OPA / ZBA for Mixed Density Residential Use Transportation Impact Study City of Guelph Prepared for: Armel Corporation August 2018 Table of Contents 1 Introduction...

More information

Oakbrook Village Plaza City of Laguna Hills

Oakbrook Village Plaza City of Laguna Hills Oakbrook Village Plaza City of Laguna Hills Traffic Impact Analysis Prepared by: HDR Engineering 3230 El Camino Real, Suite 200 Irvine, CA 92602 October 2012 Revision 3 D-1 Oakbrook Village Plaza Laguna

More information

(A) Project Manager, Infrastructure Approvals

(A) Project Manager, Infrastructure Approvals February 14th, 2014 BY E-MAIL: wally.dubyk@ottawa.ca City of Ottawa Planning and Growth Management Branch 110 Laurier Ave. W., 4 th Floor, Ottawa, Ontario K1P 1J1 Attention: Wally Dubyk, C.E.T (A) Project

More information

Barrhaven Honda Dealership. Dealership Drive, Ottawa, ON. Transportation Brief

Barrhaven Honda Dealership. Dealership Drive, Ottawa, ON. Transportation Brief Barrhaven Honda Dealership Dealership Drive, Ottawa, ON Transportation Brief Prepared By: NOVATECH Suite 200, 240 Michael Cowpland Drive Ottawa, Ontario K2M 1P6 September, 2015 File: 115136 Ref: R-2015-152

More information

MURRIETA APARTMENTS TRAFFIC IMPACT ANALYSIS CITY OF MURRIETA, CALIFORNIA

MURRIETA APARTMENTS TRAFFIC IMPACT ANALYSIS CITY OF MURRIETA, CALIFORNIA MURRIETA APARTMENTS TRAFFIC IMPACT ANALYSIS CITY OF MURRIETA, CALIFORNIA SEPTEMBER 20, 2012 Prepared for: Golden Eagle Multi-Family Properties, LLC 6201 Oak Canyon Rd., Suite 250 Irvine, CA 92618 Prepared

More information

RESPONSE TO TRAFFIC IMPACT STUDY COMMENTS

RESPONSE TO TRAFFIC IMPACT STUDY COMMENTS RESPONSE TO TRAFFIC IMPACT STUDY COMMENTS Proposed Gas Station 40 Arthur Street (Highway 26), Town of the Blue Mountains (Thornbury), County of Grey, Ontario AUGUST 2013 August 27, 2013 MR. REG RUSSWURM

More information

BUCKLEY ANNEX REDEVELOPMENT PLAN TRANSPORTATION ANALYSIS ADDENDUM

BUCKLEY ANNEX REDEVELOPMENT PLAN TRANSPORTATION ANALYSIS ADDENDUM BUCKLEY ANNEX REDEVELOPMENT PLAN TRANSPORTATION ANALYSIS ADDENDUM Prepared for: City and County of Denver Prepared by: Contact: Brian Bern, P.E., PTOE 303.572.0200 On Behalf of: Lowry Redevelopment Authority

More information

Minto Mahogany Stage 2

Minto Mahogany Stage 2 Minto Mahogany Stage 2 Transportation Impact Study prepared for: Minto Developments Inc 200-180 Kent Street Ottawa, ON K1P 0B6 prepared by: 1223 Michael Street Suite 100 Ottawa, ON K1J 7T2 June 27, 2017

More information

JRL consulting. March Hartland Developments Limited 1993 Hammonds Plains Road Hammonds Plains, NS B4B 1P3

JRL consulting. March Hartland Developments Limited 1993 Hammonds Plains Road Hammonds Plains, NS B4B 1P3 March 2015 Prepared for Hartland Developments Limited 1993 Hammonds Plains Road Hammonds Plains, NS B4B 1P3 JRL consulting JRL consulting TABLE OF CONTENTS 1 INTRODUCTION... 2 1.1 BACKGROUND... 2 2 EXISTING

More information

ARVADA TRIANGLE REDEVELOPMENT TRAFFIC IMPACT ANALYSIS

ARVADA TRIANGLE REDEVELOPMENT TRAFFIC IMPACT ANALYSIS ARVADA TRIANGLE REDEVELOPMENT TRAFFIC IMPACT ANALYSIS Prepared for: Arvada Urban Renewal Authority 5601 Olde Wadsworth Boulevard, Suite 210 Arvada, Colorado 80002 (720) 898-7062 Prepared by: Felsburg Holt

More information

Rockingham Ridge Plaza Commercial Development Halifax Regional Municipality

Rockingham Ridge Plaza Commercial Development Halifax Regional Municipality Rockingham Ridge Plaza Commercial Development Halifax Regional Municipality Traffic Impact Study Final Draft Report Prepared by: GRIFFIN transportation group inc. 30 Bonny View Drive Fall River, NS B2T

More information

Proposed Pit Development

Proposed Pit Development July 5, 2017 via email: sam@greenwoodconst.ca CCTA File 114239 Sam Greenwood Greenwood Aggregates 205467 County Road 109 Amaranth, ON L9W 0V1 Re: Proposed Violet Hill Gravel Pit, Town of Mono Traffic Review

More information

Traffic Impact Study Proposed Commercial Development Ballwin, Missouri. Technical Memorandum for Traffic Impact Study

Traffic Impact Study Proposed Commercial Development Ballwin, Missouri. Technical Memorandum for Traffic Impact Study Traffic Impact Study Proposed Commercial Development Ballwin, Missouri Technical Memorandum for Traffic Impact Study Crawford, Bunte, Brammeier May 1, 2009 MEMORANDUM Date: April 24, 2009 To: From: Subject:

More information

County State Aid Highway 30 (Diffley Road) and Dodd Road Intersection Study

County State Aid Highway 30 (Diffley Road) and Dodd Road Intersection Study County State Aid Highway 30 (Diffley Road) and Dodd Road Intersection Study City of Eagan, Dakota County, Minnesota Date: March 2012 Project No. 14957.000 444 Cedar Street, Suite 1500 Saint Paul, MN 55101

More information

CastleGlenn Consultants Inc.

CastleGlenn Consultants Inc. CastleGlenn Consultants Inc. Engineers, Project Managers & Planners March 11 th, 2013 Domenic Idone, P. Eng Planning Manager R.W. Tomlinson Ltd. 5597 Power Road Ottawa, Ontario K1G 3N4 Dear Mr. Idone:

More information

Freeway Weaving and Ramp Junction Analysis

Freeway Weaving and Ramp Junction Analysis TEXAS TECH UNIVERSITY Freeway Weaving and Ramp Junction Analysis Along IH 27 at Plainview, TX Hao Xu, Jared A. Squyres, Wesley Kumfer, and Hongchao Liu 7/15/2011 Table of Contents Project Description...

More information

Prepared For: Toronto Transit Commission 1138 Bathurst Street Toronto, Ontario M5R 3H2. Prepared By:

Prepared For: Toronto Transit Commission 1138 Bathurst Street Toronto, Ontario M5R 3H2. Prepared By: TRAFFIC IMPACT STUDY FOR THE TTC MCNICOLL BUS GARAGE CITY OF TORONTO Prepared For: Toronto Transit Commission 1138 Bathurst Street Toronto, Ontario M5R 3H2 Prepared By: Canada Inc. 4th Floor, 3 Leek Crescent

More information

Traffic Impact Analysis Update

Traffic Impact Analysis Update Willow Bend Traffic Impact Analysis Update TABLE OF CONTENTS Page I. INTRODUCTION -------------------------------------------------------------------------------------------- 1 II. EXISTING CONDITIONS

More information

Downtown One Way Street Conversion Technical Feasibility Report

Downtown One Way Street Conversion Technical Feasibility Report Downtown One Way Street Conversion Technical Feasibility Report As part of the City s Transportation Master Plan, this report reviews the technical feasibility of the proposed conversion of the current

More information

Wellings Communities Holding Inc and Extendicare (Canada) Inc Hazeldean Road. Transportation Impact Study. Ottawa, Ontario. Project ID

Wellings Communities Holding Inc and Extendicare (Canada) Inc Hazeldean Road. Transportation Impact Study. Ottawa, Ontario. Project ID Wellings Communities Holding Inc and Extendicare (Canada) Inc. 5731 Hazeldean Road Transportation Impact Study Ottawa, Ontario Project ID 160401195 Prepared by: Stantec Consulting Ltd. March 2016 WELLINGS

More information

Appendix B: Traffic Reports

Appendix B: Traffic Reports Appendix B: Traffic Reports 407 TRANSITWAY - KENNEDY ROAD TO BROCK ROAD MINISTRY OF TRANSPORTATION - CENTRAL REGION Report Markham Road Station Traffic Study Prepared for Ministry of Transportation, Ontario

More information

Sugarland Crossing Gwinnett County, Georgia

Sugarland Crossing Gwinnett County, Georgia Sugarland Crossing Gwinnett County, Georgia S IGNAL W ARRANT A NALYSIS For the Intersection of: Sugarloaf Parkway / Richards Middle School Driveway / Sugarland Crossing Main Site Driveway Prepared for:

More information

886 March Road McDonald's Transportation Study

886 March Road McDonald's Transportation Study McDonald's Restaurants of Canada Limited March 2013 886 March Road McDonald's Transportation Study Submitted by: HDR Corporation 100 York Boulevard, Suite 300 Richmond Hill, ON L4B 1J8 (905) 882-4100 www.hdrinc.com

More information

Weaver Road Senior Housing Traffic Impact Analysis

Weaver Road Senior Housing Traffic Impact Analysis Gibson Traffic Consultants, Inc. 2813 Rockefeller Avenue Suite B Everett, WA 9821 425.339.8266 Weaver Road Senior Housing Traffic Impact Analysis Jurisdiction: City of Snohomish January 218 GTC #17-37

More information

Traffic Impact Study Morgan Road Commerce Park Pasco County, Florida

Traffic Impact Study Morgan Road Commerce Park Pasco County, Florida Traffic Impact Study Morgan Road Commerce Park Pasco County, Florida Summary Report June 2008 Prepared by: 12909 N 56 th Street # 201 Tampa, FL 33617 Ph: (813) 988-3180 Fax: (813) 343-6854 Morgan Road

More information

Village of Richmond Transportation Brief

Village of Richmond Transportation Brief Village of Richmond Transportation Brief GENIVAR Project Number 111-18482-00 June 21 st, 2011 www.genivar.com GENIVAR 15 Fitzgerald Road, Suite 100 Ottawa, Ontario, CANADA K2H 9G1 Telephone: 613-829-2800

More information

Parking/Traffic Assessment Study

Parking/Traffic Assessment Study Brock Road Industrial Mall 985 Brock Road South City of Pickering Parking/Traffic Assessment Study Prepared by: Tranplan Associates, Toronto Toronto 416-670-2005 Sudbury 705-522-0272 Peterborough 705-874-3638

More information

2.0 Development Driveways. Movin Out June 2017

2.0 Development Driveways. Movin Out June 2017 Movin Out June 2017 1.0 Introduction The proposed Movin Out development is a mixed use development in the northeast quadrant of the intersection of West Broadway and Fayette Avenue in the City of Madison.

More information

Lakeside Terrace Development

Lakeside Terrace Development Lakeside Terrace Development City of Barrie, County of Simcoe Traffic Brief for: Type of Document: Final Report Project Number: JDE 1617 Date Submitted: April 29 th, 216 4/29/16 John Northcote, P.Eng.

More information

Traffic Impact Study. Eastern Springs. A Proposed Development in Manorville, NY. April Haas Group Inc Transportation Planners and Engineers

Traffic Impact Study. Eastern Springs. A Proposed Development in Manorville, NY. April Haas Group Inc Transportation Planners and Engineers Traffic Impact Study For Eastern Springs A Proposed Development in Manorville, NY April 2018 Haas Group Inc Transportation Planners and Engineers Table of Contents 1) Executive Summary... 2 2) Study Purpose...

More information

JOHNSON RANCH RAPID CITY, SOUTH DAKOTA TRAFFIC IMPACT ANALYSIS

JOHNSON RANCH RAPID CITY, SOUTH DAKOTA TRAFFIC IMPACT ANALYSIS JOHNSON RANCH RAPID CITY, SOUTH DAKOTA TRAFFIC IMPACT ANALYSIS Prepared for: KTM Design Solutions 528 Kansas City Street, Suite 1 Rapid City, SD 57701 Prepared by: Felsburg Holt & Ullevig 6300 South Syracuse

More information

Trim Road, Commercial Development, City of Ottawa

Trim Road, Commercial Development, City of Ottawa HARDEN REALTIES July 2016 Trim Road, Commercial Development, City of Ottawa Transportation Impact Study Trim Road, Commercial Development, City of Ottawa Transportation Impact Study prepared for: Harden

More information

June 21, Mr. Jeff Mark The Landhuis Company 212 North Wahsatch Avenue, Suite 301. Colorado Springs, CO 80903

June 21, Mr. Jeff Mark The Landhuis Company 212 North Wahsatch Avenue, Suite 301. Colorado Springs, CO 80903 LSC TRANSPORTATION CONSULTANTS, INC. 545 East Pikes Peak Avenue, Suite 210 Colorado Springs, CO 80903 (719) 633-2868 FAX (719) 633-5430 E-mail: lsc@lsctrans.com Website: http://www.lsctrans.com June 21,

More information

November 1, Mr. Jafar Tabrizi President, Tabrizi Rugs 180 Bedford Highway. Traffic Impact Statement BH-1 and BH-2, Southgate Drive, Bedford, NS

November 1, Mr. Jafar Tabrizi President, Tabrizi Rugs 180 Bedford Highway. Traffic Impact Statement BH-1 and BH-2, Southgate Drive, Bedford, NS 161-12598 Mr. Jafar Tabrizi President, Tabrizi Rugs 180 Bedford Highway Bedford, NS B4A 1C1 [Via Email: tabrizi@tabrizi.com] RE: Traffic Impact Statement Dear Mr. Tabrizi: Plans are being prepared for

More information

10 th Street Residences Development Traffic Impact Analysis

10 th Street Residences Development Traffic Impact Analysis Gibson Traffic Consultants, Inc. 2813 Rockefeller Avenue Suite B Everett, WA 98201 425.339.8266 10 th Street Residences Development Traffic Impact Analysis Jurisdiction: City of Snohomish September 2018

More information

This letter summarizes our observations, anticipated traffic changes, and conclusions.

This letter summarizes our observations, anticipated traffic changes, and conclusions. Mr. David Jorschumb Project Manager Boulder Valley School District Re: Review of proposed school access improvements at the Foothills Elementary School in Boulder Dear Mr. Jorschumb, At your request, the

More information

Addendum to Traffic Impact Analysis for Port Marigny Site Mandeville, LA

Addendum to Traffic Impact Analysis for Port Marigny Site Mandeville, LA Addendum to Traffic Impact Analysis for Port Marigny Site Mandeville, LA (St. Tammany Parish Mandeville, LA) Prepared For The Pittman Companies Michael N Pittman, MD 328 East Boston St Covington, LA 70433

More information

Trip Generation Study: Provo Assisted Living Facility Land Use Code: 254

Trip Generation Study: Provo Assisted Living Facility Land Use Code: 254 Trip Generation Study: Provo Assisted Living Facility Land Use Code: 254 Introduction The Brigham Young University Institute of Transportation Engineers (BYU ITE) student chapter completed a trip generation

More information

Aldridge Transportation Consultants, LLC Advanced Transportation Planning and Traffic Engineering

Aldridge Transportation Consultants, LLC Advanced Transportation Planning and Traffic Engineering Aldridge Transportation Consultants, LLC Advanced Transportation Planning and Traffic Engineering John M.W. Aldridge, PE, PTOE, AICP 1082 Chimney Rock Road Colorado Registered Professional Engineer Highlands

More information

1. INTRODUCTION 2. PROJECT DESCRIPTION CUBES SELF-STORAGE MILL CREEK TRIP GENERATION COMPARISON

1. INTRODUCTION 2. PROJECT DESCRIPTION CUBES SELF-STORAGE MILL CREEK TRIP GENERATION COMPARISON CUBES SELF-STORAGE MILL CREEK TRIP GENERATION COMPARISON 1. INTRODUCTION This report summarizes traffic impacts of the proposed CUBES Self-Storage Mill Creek project in comparison to the traffic currently

More information

Proposed Office Building Traffic Impact Study Chicago Avenue Evanston, Illinois

Proposed Office Building Traffic Impact Study Chicago Avenue Evanston, Illinois Proposed Office Building Traffic Impact Study 1714-1720 Chicago Avenue Evanston, Illinois Prepared For: HOLABIRD & ROOT, LLC Prepared by: Eriksson Engineering Associates, Ltd. 145 Commerce Drive, Ste A,

More information

Salvini Consulting Inc. 459 Deer Ridge Drive Kitchener, ON N2P 0A November 8, 2017 Revised December 20, 2017

Salvini Consulting Inc. 459 Deer Ridge Drive Kitchener, ON N2P 0A November 8, 2017 Revised December 20, 2017 Salvini Consulting Inc. 459 Deer Ridge Drive Kitchener, ON N2P 0A7 519-591-0426 November 8, 2017 Revised December 20, 2017 Laurie Wills, PEng Deputy Director of Public Works Town of Cobourg 740 Division

More information

Date: December 20, Project #:

Date: December 20, Project #: To: Craig Rottenberg Long s Jewelers 60A South Avenue Burlington, MA 01803 From: Patrick Dunford, P.E. Senior Project Manager Date: December 20, 2018 Project #: 14416.00 Re: Burlington Mall Proposed Long

More information

APPENDICES. APPENDIX D Synchro Level of Service Output Sheets

APPENDICES. APPENDIX D Synchro Level of Service Output Sheets APPENDICES APPENDIX D Synchro Level of Service Output Sheets Lanes, Volumes, Timings NO BUILD 2016 PM 8: 10th St & Thain Rd 10/05/2016 Lane Group NBL NBT NBR SBL SBT SBR SEL SET SER NWL NWT NWR

More information

Vanier Parkway and Presland Road Residential Development Transportation Impact Study

Vanier Parkway and Presland Road Residential Development Transportation Impact Study Vanier Parkway and Presland Road Residential Development Transportation Impact Study Final Report (Revised) March 2011 Submitted to: Groupe Lépine Ottawa Project No. 09-1613 Submitted by: Groupe Lépine

More information

KUM & GO 6400 WESTOWN PARKWAY WEST DES MOINES, IOWA 50266

KUM & GO 6400 WESTOWN PARKWAY WEST DES MOINES, IOWA 50266 KUM & GO #300 PECOS STREET & 88 TH AVENUE THORNTON, COLORADO TRAFFIC IMPACT STUDY REVISION 1 PREPARED FOR KUM & GO 6400 WESTOWN PARKWAY WEST DES MOINES, IOWA 50266 JANUARY 23, 2014 OA PROJECT NO. 013-1721

More information

Half Moon Bay North Apartment Block Transportation Impact Assessment. Full Report. March 15, Prepared for: Mattamy Homes.

Half Moon Bay North Apartment Block Transportation Impact Assessment. Full Report. March 15, Prepared for: Mattamy Homes. Half Moon Bay North Apartment Block Transportation Impact Assessment Full Report March 15, 2018 Prepared for: Mattamy Homes Prepared by: Stantec Consulting Ltd. Table of Contents 1.0 SCREENING... 1 1.1

More information

1701 N. BEAUREGARD STREET NEW WEST END ELEMENTARY SCHOOL (NWEES)

1701 N. BEAUREGARD STREET NEW WEST END ELEMENTARY SCHOOL (NWEES) 0 N. BEAUREGARD STREET NEW WEST END ELEMENTARY SCHOOL (NWEES) C O TRANSPORTATION ANALYSIS STUDY March th, 0 APPLICANT: Alexandria City Public Schools Educational Facilities Department Operational & Maintenance

More information

TRAFFIC AND TRANSPORTATION TECHNICAL MEMORANDUM

TRAFFIC AND TRANSPORTATION TECHNICAL MEMORANDUM TRAFFIC AND TRANSPORTATION TECHNICAL MEMORANDUM for ENVIRONMENTAL ASSESSMENT US 460 Bypass Interchange and Southgate Drive Relocation State Project No.: 0460-150-204, P101, R201, C501, B601; UPC 99425

More information

TRAFFIC IMPACT ANALYSIS

TRAFFIC IMPACT ANALYSIS TRAFFIC IMPACT ANALYSIS Emerald Isle Commercial Development Prepared by SEPI Engineering & Construction Prepared for Ark Consulting Group, PLLC March 2016 I. Executive Summary A. Site Location The Emerald

More information

STANDARD LIMITATIONS

STANDARD LIMITATIONS STANDARD LIMITATIONS This report was prepared by MMM Group (MMM) for the account of Spire Construction Inc. (the Client). The disclosure of any information contained in this report is the sole responsibility

More information

Memorandum. 1 Short List Analysis Background. James Hinkamp and Tony Coe, City of Lafayette Steering Committee

Memorandum. 1 Short List Analysis Background. James Hinkamp and Tony Coe, City of Lafayette Steering Committee To Copies James Hinkamp and Tony Coe, City of Lafayette Steering Committee Date August 26, 2016 Reference number 243381 From Mike Iswalt, Vanessa Peers, Will Baumgardner File reference 4-05 Subject Lafayette

More information

TRAFFIC IMPACT STUDY. USD #497 Warehouse and Bus Site

TRAFFIC IMPACT STUDY. USD #497 Warehouse and Bus Site TRAFFIC IMPACT STUDY for USD #497 Warehouse and Bus Site Prepared by: Jason Hoskinson, PE, PTOE BG Project No. 16-12L July 8, 216 145 Wakarusa Drive Lawrence, Kansas 6649 T: 785.749.4474 F: 785.749.734

More information

Aldridge Transportation Consultants, LLC Advanced Transportation Planning and Traffic Engineering

Aldridge Transportation Consultants, LLC Advanced Transportation Planning and Traffic Engineering Aldridge Transportation Consultants, LLC Advanced Transportation Planning and Traffic Engineering John M.W. Aldridge, PE, PTOE, AICP 1082 Chimney Rock Road Colorado Registered Professional Engineer Highlands

More information

770 SOMERSET STREET RESIDENTIAL DEVELOPMENT

770 SOMERSET STREET RESIDENTIAL DEVELOPMENT Downtown North York by PFHLai / CC-BY-3. September 217 77 SOMERSET STREET RESIDENTIAL DEVELOPMENT Transportation Impact Assessment 77 Somerset Street Residential Development Transportation Impact Assessment

More information

Appendix J Traffic Impact Study

Appendix J Traffic Impact Study MRI May 2012 Appendix J Traffic Impact Study Level 2 Traffic Assessment Limited Impact Review Appendix J [This page was left blank intentionally.] www.sgm-inc.com Figure 1. Site Driveway and Trail Crossing

More information

Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. HNTB Project File: Subject

Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. HNTB Project File: Subject TECHNICAL MEMORANDUM To Kumar Neppalli Traffic Engineering Manager Town of Chapel Hill From Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. Cc HNTB Project File: 38435 Subject Obey Creek TIS 2022

More information

LATSON INTERCHANGE DEVELOPMENT TRAFFIC STUDIES. Genoa Township, Livingston County, MI

LATSON INTERCHANGE DEVELOPMENT TRAFFIC STUDIES. Genoa Township, Livingston County, MI LATSON INTERCHANGE DEVELOPMENT TRAFFIC STUDIES Genoa Township, Livingston County, MI DRAFT TRAFFIC STUDY FOR I-96 AT LATSON RD INTERCHANGE Livingston County CS 47065 JN 101622C Submitted to: Michigan Department

More information

6111 and 6141 Hazeldean Road Stittsville, Ontario. Proposed Residential Development Transportation Impact Study

6111 and 6141 Hazeldean Road Stittsville, Ontario. Proposed Residential Development Transportation Impact Study 6111 and 6141 Hazeldean Road Stittsville, Ontario Proposed Residential Development Transportation Impact Study Presented to: Ms. Erin O Connor Land Development Manager Minto Communities 200-180 Kent Street

More information

DEVELOPMENT PROPERTY 1627 MAXIME STREET CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for: Subhas Bhargava. July 9, Overview_1.

DEVELOPMENT PROPERTY 1627 MAXIME STREET CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for: Subhas Bhargava. July 9, Overview_1. DEVELOPMENT PROPERTY 1627 MAXIME STREET CITY OF OTTAWA TRANSPORTATION OVERVIEW Prepared for: Subhas Bhargava July 9, 2015 115-620 Overview_1.doc D. J. Halpenny & Associates Ltd. Consulting Transportation

More information

Per Revised Concept Plan Residential Condo/Townhouse. Proposed Land Use per TIS

Per Revised Concept Plan Residential Condo/Townhouse. Proposed Land Use per TIS January 2, 2018 Mr. Paul DeBotton Marple Associates, L.P. 1604 Walnut Street, 4 th Floor Philadelphia, PA 19103 RE: Langford Run Road Traffic Analysis Proposed Mid County Shopping Center Marple Township,

More information

Winnetka Avenue Bike Lanes Traffic Impact Analysis

Winnetka Avenue Bike Lanes Traffic Impact Analysis Winnetka Avenue Bike Lanes Traffic Impact Analysis January 4, 2019 Prepared by City of Los Angeles Department of Transportation Active Transportation Division Winnetka Ave Bike Lanes Traffic Impact Analysis

More information