1 Lakeside Terrace Development City of Barrie, County of Simcoe Traffic Brief for: Type of Document: Final Report Project Number: JDE 1617 Date Submitted: April 29 th, 216 4/29/16 John Northcote, P.Eng. Professional License #: JD Northcote Engineering Inc. 86 Cumberland Street Barrie, ON

2 Legal Notification This report was prepared by JD Northcote Engineering Inc. for the account of Little Lake Senior Community Group. Any use which a third party makes of this report, or any reliance on or decisions to be made based on it, are the responsibility of such third parties. JD Northcote Engineering Inc. accepts no responsibility for damages, if any, suffered by any third party as a result of decisions made or actions based on this project. ii

3 Table of Contents 1 Introduction Background Study Scope and Objectives Information Gathering Street and Intersection Characteristics Traffic Counts Site Traffic Development Status Medical Office Building Traffic Retirement Home Traffic Total Approved Site Traffic Redistribution of Medical Office Building Traffic Total (216) Traffic Volumes Parking Access Analysis Introduction Sight Distance Review Summary List of Tables Table 1 Traffic Count Data... 7 Table 2 Estimated Traffic Generation of Retirement Home... 9 Table 3 Estimated Traffic Distribution for Total Approved Site Traffic Table 4 Level of Service Criteria for Intersections Table 5 Intersection Operation for Total (216) Traffic Volumes List of Figures Figure 1 Proposed Site Location and Study Area... 6 Figure 2 Existing (216) Peak Hour Traffic Volumes... 7 Figure 3 Medical Office Building Peak Hour Traffic Volumes (85% Occupancy)... 8 Figure 4 Medical Office Building Peak Hour Traffic Volumes (Unoccupied 15%)... 9 Figure 5 Retirement Home Peak Hour Traffic Volumes... 1 Figure 6 Approved Site Development Peak Hour Traffic Volumes (Full-Occupancy) Figure 7 Redistribution of Medical Office Building Peak Hour Traffic (Full-Occupancy) Figure 8 Total (216) Peak Hour Traffic Volumes iii

4 List of Appendices APPENDIX A Site Plan APPENDIX B Traffic Counts APPENDIX C Previous Study Excerpts APPENDIX D Synchro Results iv

5 1 Introduction 1.1 Background The subject site is located at the intersection of J.C. Massie Way and Little Lake Drive in the City of Barrie [City]. The next phase of this existing development includes a relocation of a temporary parking lot (currently located in the middle of their lands) to lands that the City are considering deeming surplus and some additional lands owned by the Ontario Ministry of Transportation, which have become available as a result of the reconstruction of the Duckworth Street interchange with Highway 4 [Surplus Lands]. As a result of the existing grades in the Surplus Lands, the proposed parking lot design includes two parking lots that are separated by a retaining wall. The eastern parking lot is referred to as the Upper Parking Lot and the smaller western parking lot is referred to as the Lower Parking Lot. A total of 139 parking spaces are provided in the Upper Parking Lot (99 parking spaces) and Lower Parking Lot (4 parking spaces). The proposed parking supply is similar to the parking supply in the existing temporary parking lot, which will be removed. The subject site currently provides a single full-movement access at the southeast corner of the intersection of J.C. Massie Way and Little Lake Drive [Existing Access]. As part of the proposed works, the Existing Access is to be reconfigured along with the intersection of J.C. Massie Way and Little Lake Drive to provide a more defined entrance, which will be moved slightly to the northwest. The Upper Parking Lot includes a full-movement connection to the Existing Access driveway. The Lower Parking Lot is accessed via a proposed full-movement driveway onto J.C. Massie Way. Figure 1 illustrates the location of the subject site as well as the location of the proposed site access. The proposed development site plan is shown in Appendix A. This study builds on the previous Updated Analysis Traffic Impact and Parking Study (Cole Engineering Group Ltd., February 213) for the subject site [Cole Study]. [the Developer] has retained JD Northcote Engineering Inc. [JD Engineering] to prepare this traffic brief in support of the Zoning Bylaw Amendment and OPA Applications. 1.2 Study Scope and Objectives Based on discussions with the City Transportation Department, the purpose of this traffic brief is to assess the operation of the proposed site access configuration for the approved development. The analysis includes a review of the traffic volumes generated by full occupancy of the medical office building (Condominium Block A ) and full occupancy of the retirement home (Condominium Block C ). Our analysis includes the existing 216 traffic volumes (with the above-noted development within the subject site) during the weekday morning [AM] and mid-day [MID] peak hour, which will be the peak traffic generation periods for the subject site. 5

6 Figure 1 Proposed Site Location and Study Area 2 Information Gathering 2.1 Street and Intersection Characteristics J.C. Massie Way is a local road with a two-lane urban cross-section, under the jurisdiction of the City. There is a sidewalk on the north side of the road. J.C. Massie Way has an assumed (unsigned) speed limit of 5km/h. No bus service is provided along J.C. Massie Way. Little Lake Drive is a local road with a two-lane urban cross-section, under the jurisdiction of the City. There is a sidewalk on the west side of the road, near the subject site. Little Lake Drive has an assumed (unsigned) speed limit of 5km/h. No bus service is provided along Little Lake Drive. According to the City of Barrie Multi-Modal Active Transportation Master Plan [MMATMP], there are no planned road improvements on J.C. Massie Way or Little Lake Drive up to the 231 horizon year. 2.2 Traffic Counts Detailed traffic and pedestrian counts were completed on J.C. Massie Way at the subject site. Table 1 summarizes the traffic count data collection information. 6

7 Table 1 Traffic Count Data Location Count Date AM Peak Hour MID Peak Hour PM Peak Hour J.C. Massie Way / Little Lake Drive / Existing Access March 3 th, 216 8: - 9: 12:3-13:3 16: - 17: Detailed traffic count data can be found in Appendix B. The peak hours of traffic generation for the study area intersections generally aligned with the anticipated peak hour of traffic generation by the proposed development. Heavy vehicle percentages from the traffic count data have also been included in the Synchro analysis. Figure 2 illustrates the existing (216) AM and MID peak hour traffic volumes at the site access. Figure 2 Existing (216) Peak Hour Traffic Volumes 3 Site Traffic 3.1 Development Status Approved development within the subject site includes a medical office building (4,38 sq.m. GFA), located at the southeast corner of the intersection of J.C. Massie Way and Little Lake Drive and a retirement home (14 suites), located at the east end of the subject site. Based on our discussions 7

8 with the owner, on March 3 th, 216 (date of the traffic counts), the medical office building was 85% occupied and the retirement home was unoccupied. It is anticipated that the medical office building and the retirement home will be fully-occupied by the end of Medical Office Building Traffic The existing traffic volume entering and exiting the subject site has been assumed to be attributed to the 85% occupancy of the medical office building. It is anticipated that some of this traffic is actually attributed to the construction of the retirement home; however, we conservatively ignored the impact of the construction traffic, as it is expected to be relatively minor. Figure 3 illustrates the existing site traffic volumes, with the pass-by traffic on J.C. Massie Way and Little Lake Drive removed. Figure 3 Medical Office Building Peak Hour Traffic Volumes (85% Occupancy) We have estimated the additional traffic which will be generated by the full-occupancy of the medical office building by assuming the existing traffic volumes account for 85% of the total site traffic volumes. Figure 4 illustrates the estimated peak hour traffic generation for the unoccupied (15%) component of the existing medical office building 1. 1 Values have been calculated using the following formula [(Site Traffic Volume /.85) Site Traffic Volume]. 8

9 Figure 4 Medical Office Building Peak Hour Traffic Volumes (Unoccupied 15%) 3.3 Retirement Home Traffic The traffic generated by the retirement home has been taken from the Cole Study (excerpt attached in Appendix C), which was based on trip generation data summarized in the Trip Generation Manual, 8 th Edition, published by ITE, Land Use Code 255 (Continuing Care Retirement Community). The trip generation calculations from this report are summarized in Table 2. Table 2 Estimated Traffic Generation of Retirement Home Size Continuing Care Retirement Community (14 suites) Parametres AM Peak Hour PM Peak Hour IN OUT TOTAL IN OUT TOTAL Gross Trips Gross Trip Rates Total New Vehicular Trips We have assumed that the traffic generation from the retirement home will only include trips to and from J.C. Massie Way. Figure 5 illustrates the estimated peak hour traffic generation for the retirement home. 9

10 Figure 5 Retirement Home Peak Hour Traffic Volumes 3.4 Total Approved Site Traffic The total peak hour traffic generation from all approved development within the subject site has been calculated by adding the traffic volumes in Figures 3, 4 and 5. Figure 6 illustrates the assumed total peak hour traffic generation for full-occupancy of all approved development within the subject site. 1

11 Figure 6 Approved Site Development Peak Hour Traffic Volumes (Full-Occupancy) 3.5 Redistribution of Medical Office Building Traffic The scope of the proposed site work includes a relocation of the temporary parking lot into a permanent location within the Surplus Lands. The traffic volumes in Figure 3 and 4 assume that all traffic generated by the medical office building will use the Existing Access. The proposed parking configuration will result in a redistribution of the medical office building traffic to the Upper Parking Lot Access and Lower Parking Lot Access. We have assumed that the distribution of traffic to each parking lot will be proportionate to the number of parking spaces. Table 3 summarizes the calculation of the medical office building (full-occupancy) trip distribution for each parking lot, based on the proposed parking supply in each lot. Parking Lot Access Table 3 Estimated Traffic Distribution for Total Approved Site Traffic Office Building Parking Supply Percent of Total Parking Supply AM Peak Hour PM Peak Hour IN OUT TOTAL IN OUT TOTAL Existing Access 91 4% Upper Parking Lot Access 99 43% Lower Parking Lot Access 4 17% Total 23 1% It is assumed that the traffic generated by the retirement home will only use the Existing Access, as illustrated in Figure 5. 11

12 Figure 7 illustrates the assumed redistribution of the peak hour traffic, generated from the fulloccupancy of the medical office building. Figure 7 Redistribution of Medical Office Building Peak Hour Traffic (Full-Occupancy) 3.6 Total (216) Traffic Volumes The total peak hour traffic volumes within the study area has been calculated by adding the pass-by traffic on J.C. Massie Way and Little Lake Drive, the retirement home traffic from Figure 5 and the redistribution of the full-occupancy of the medical office building traffic from Figure 7. The estimated total (216) traffic volumes with full-occupancy of the approved development within the subject site is illustrated in Figure 8. 12

13 Figure 8 Total (216) Peak Hour Traffic Volumes 4 Parking Access Analysis 4.1 Introduction An operational analysis was completed for the Total (216) peak hour traffic volumes using the traffic analysis software, Synchro 9, a deterministic model that employs Highway Capacity Manual and Intersection Capacity Utilization methodologies for analyzing intersection operations. These procedures are accepted by provincial and municipal agencies throughout North America. Synchro 9 enables the study area to be graphically defined in terms of streets and intersections, along with their geometric and traffic control characteristics. The user is able to evaluate both signalized and unsignalized intersections in relation to each other, thus not only providing level of service for the individual intersections, but also enabling an assessment of the impact the various intersections in a network have on each other in terms of spacing, traffic congestion, delay, and queuing. Individual turning movements with a volume-to-capacity [V/C] ratio of.85 or greater are considered to be critical movements and have been highlighted in the LOS tables. The intersection operations were also evaluated in terms of the LOS. LOS is a common measure of the quality of performance at an intersection and is defined in terms of vehicular delay. This delay includes deceleration delay, queue move-up time, stopped delay, and acceleration delay. LOS is expressed on a scale of A through F, where LOS A represents very little delay (i.e. less than 1 seconds per vehicle) and LOS F represents very high delay (i.e. greater than 5 seconds per vehicle 13

14 for a stop sign controlled intersection and greater than 8 seconds per vehicle for a signalized intersection). The LOS criteria for signalized and stop sign controlled intersections are shown in Table 4. A description of traffic performance characteristics is included for each LOS. Table 4 Level of Service Criteria for Intersections Control Delay (seconds per vehicle) LOS LOS Description Signalized Intersections Stop Controlled Intersections A Very low delay; most vehicles do not stop (Excellent) less than 1. less than 1. B Higher delay; more vehicles stop (Very Good) between 1. and 2. between 1. and 15. C D E F Higher level of congestion; number of vehicles stopping is significant, although many still pass through intersection without stopping (Good) Congestion becomes noticeable; vehicles must sometimes wait through more than one red light; many vehicles stop (Satisfactory) Vehicles must often wait through more than one red light; considered by many agencies to be the limit of acceptable delay This level is considered to be unacceptable to most drivers; occurs when arrival flow rates exceed the capacity of the intersection (Unacceptable) between 2. and 35. between 15. and 25. between 35. and 55. between 25. and 35. between 55. and 8. between 35. and 5. greater than 8. greater than 5. The operational analysis was completed using the proposed site access configuration. The results of the analysis for the total (216) peak hour traffic volumes can be found below in Table 5. Detailed output of the Synchro analysis can be found in Appendix D. Table 5 Intersection Operation for Total (216) Traffic Volumes Location Weekday AM Peak Hour Weekday PM Peak Hour (E-W Street / N-S Street) V/C Delay (s) LOS V/C Delay (s) LOS J.C. Massie Way / Lower Parking Lot Access -.3 A -.6 A NB A B J.C. Massie Way / Little Lake Drive / Existing Access A A NWB A B Existing Access / Upper Parking Lot Access - 1. A A NB A B The results of the LOS analysis indicate that all individual turning movements in the study area are operating at a very good level of service or better during the AM and MID peak hour. The 95 th percentile queue length for the critical northwest bound egress movements from the reconfigured Existing Access is 1.3 metres in the AM peak hour and 4.7 metres in the PM peak hour. This indicates that during the critical MID peak hour, 95% of the time the queue length will be one vehicle or less. There will be situations where more than one vehicle will be queuing to turn onto J.C. Massie Way or Little Lake Drive. In these rare events, northbound vehicles at the Upper Parking Lot Access will not be able to make the left turn movement onto the Existing Access driveway; however, the frequency of this scenario is relatively rare and the impact of an additional delay for northbound left turn 14

15 movements at the Upper Parking Lot Driveway will not impact driver behavior or cause any operational issues. A review of the passenger turning movements was completed to ensure that the proposed site access configuration can function as intended. No operational issues are anticipated as a result of the proposed site access configuration. Based on this review, the proposed configuration of the Lower Parking Lot Access, Upper Parking Lot Access and Existing Access will safely and efficiently convey the anticipated traffic in the study area. An emergency access is proposed at the southwest corner of the Upper Parking Lot onto Cundles Road East. This driveway will be gated at the edge of the right-of-way, to prevent use by nonemergency vehicles. This access will need to be maintained by the owner of the subject site. This includes snow removal up to the paved surface of Cundles Road East. The proposed configuration of the emergency access is not anticipated to result in any operational issues. 4.2 Sight Distance Review A review of the available sight distance was completed at the Existing Access and Lower Parking Lot Access based on the Transportation Association of Canada Guidelines for Canadian Roads [TAC Guidelines]. For the Existing Access, the sight distance north on Little Lake Drive and west on J.C. Massie Way is well in excess of the TAC Guidelines minimum sight stopping distance for a design speed of 6km/h (85 metres). For the Lower Parking Lot Access, the sight distance west on J.C. Massie Way is well in excess of the TAC Guidelines minimum sight stopping distance for a design speed of 6km/h (85 metres). The sight distance north on Little Lake Drive is currently 5 metres, which meets the TAC minimum sight stopping distance for a design speed of 4km/h. As a result of the back-to-back spiral curves on Little Lake Drive, north of J.C. Massie Way, it is anticipated the vehicles travelling southbound on Little Lake Drive and westbound on J.C. Massie Way, across the frontage of the subject site, will be travelling less than 4 km/h. This assumption was based on our driving field test. Regardless, it is recommended that Hidden Entrance warning signage is provided for southbound traffic on Little Lake Drive, north of J.C. Massie Way. It is also recommended that the existing cedar trees are limbed within the right-of-way to minimize the sight obstructions. 5 Summary The Developer retained JD Engineering to complete a Traffic Brief in support of the Official Plan Amendment and Zoning By-law Amendment for the proposed relocation of the temporary parking lot onto the Surplus Lands located southwest of the existing intersection of J.C. Massie Way / Little Lake Drive, in the City of Barrie. The proposed site plan is shown in Appendix A. This chapter summarizes the conclusions and recommendations from the study. 1. The Developer is proposing to relocate the temporary parking lot located near the middle of the subject site. The proposed parking lot is to be constructed on lands that the City are deeming surplus and some additional lands owned by the Ontario Ministry of Transportation, which have become available as a result of the reconstruction of the Duckworth Street interchange with Highway 4 [Surplus Lands]. 2. The existing site access [Existing Access] is to be reconfigured along with the existing intersection of J.C. Massie Way and Little Lake Drive to provide a more defined entrance, which will involve a slight relocation to the northwest. 15

16 3. The proposed parking area will be divided into two parking lots which will be separated by a retaining wall, as a result of the existing grades in the area. 4. The smaller western parking lot [Lower Parking Lot] will have 4 parking spaces and a fullmovement access onto J.C. Massie Way, 35 metres (measured centre of intersection to centre of intersection) west of the existing intersection of J.C. Massie Way / Little Lake Drive. 5. The larger eastern parking lot [Upper Parking Lot] will have 99 parking spaces and a fullmovement access onto the Existing Access driveway 19 metres (measured centre of intersection to centre of intersection) west of the existing intersection of J.C. Massie Way / Little Lake Drive. 6. Background traffic and pedestrian counts, collected on March 3th, 216, at the existing intersection of J.C. Massie Way / Little Lake Drive / Existing Access were commissioned by JD Engineering. 7. The traffic volumes for full-occupancy of the approved development within the subject site were calculated using a combination of the traffic count data and the previous Updated Analysis Traffic Impact and Parking Study (Cole Engineering Group Ltd., February 213) for the subject site [Cole Study]. The full-occupancy of the approved development within the subject site is expected to generate a total of 174 AM and 314 MID peak hour trips. 8. The proposed development will have a negligible impact on the existing traffic flow on J.C. Massie Way and Little Lake Drive. 9. The proposed site access configuration will operate effectively as an unsignalized driveway access with one-way stop control at the following locations: Northbound Lower Parking Lot Access at J.C. Massie Way; Northbound Upper Parking Lot Access at Existing Access driveway; and Northwestbound Existing Access at J.C. Massie Way / Little Lake Drive. 1. The proposed configuration of the emergency access is not anticipated to result in any operational issues. 11. One egress lane and one ingress lane will provide the necessary capacity to service the subject site at all site access driveways. 16

17 Appendix A Site Plan 17

18

19

20 Appendix B Traffic Counts 18

21 Ontario Traffic Inc Morning Peak Diagram Specified Period From: 7:: To: 1:: One Hour Peak From: 8:: To: 9:: Municipality: Site #: Intersection: TFR File #: Count date: Barrie Little Lake Dr & J.C. Massie Way 5 3-Mar-16 Weather conditions: Person(s) who counted: ** Non-Signalized Intersection ** Major Road: Little Lake Dr runs W/E North Leg Total: 43 Heavys 1 1 Heavys East Leg Total: 13 North Entering: 22 Trucks 1 1 Trucks 1 East Entering: 34 North Peds: 3 Cars Cars 2 East Peds: 5 Peds Cross: Totals 21 1 Totals 21 Peds Cross: Heavys Trucks Cars Totals Little Lake Dr Heavys Trucks Cars Totals J.C. Massie Way N W E S J.C. Massie Way Cars Trucks Heavys Totals Office Building Driveway Cars Trucks Heavys Totals Peds Cross: Cars Cars Peds Cross: West Peds: Trucks Trucks South Peds: West Entering: 114 Heavys Heavys South Entering: West Leg Total: 167 Totals Totals South Leg Total: Comments

22 Ontario Traffic Inc Mid-day Peak Diagram Specified Period From: 11:: To: 14:: One Hour Peak From: 12:3: To: 13:3: Municipality: Site #: Intersection: TFR File #: Count date: Barrie Little Lake Dr & J.C. Massie Way 5 3-Mar-16 Weather conditions: Person(s) who counted: ** Non-Signalized Intersection ** Major Road: Little Lake Dr runs W/E North Leg Total: 38 Heavys 1 1 Heavys 2 East Leg Total: 237 North Entering: 22 Trucks 1 1 Trucks East Entering: 93 North Peds: 3 Cars Cars 14 East Peds: 8 Peds Cross: Totals 19 3 Totals 16 Peds Cross: Heavys Trucks Cars Totals Little Lake Dr Heavys Trucks Cars Totals J.C. Massie Way N W E S J.C. Massie Way Cars Trucks Heavys Totals Office Building Driveway Cars Trucks Heavys Totals Peds Cross: Cars 4 Cars Peds Cross: West Peds: 2 Trucks Trucks South Peds: 1 West Entering: 16 Heavys Heavys South Entering: West Leg Total: 271 Totals 4 Totals South Leg Total: 4 Comments

23 Ontario Traffic Inc Afternoon Peak Diagram Specified Period From: 16:: To: 19:: One Hour Peak From: 16:: To: 17:: Municipality: Site #: Intersection: TFR File #: Count date: Barrie Little Lake Dr & J.C. Massie Way 5 3-Mar-16 Weather conditions: Person(s) who counted: ** Non-Signalized Intersection ** Major Road: Little Lake Dr runs W/E North Leg Total: 63 Heavys Heavys East Leg Total: 95 North Entering: 34 Trucks 1 1 Trucks East Entering: 79 North Peds: Cars Cars 29 East Peds: 2 Peds Cross: Totals 34 Totals 29 Peds Cross: Heavys Trucks Cars Totals Little Lake Dr Heavys Trucks Cars Totals J.C. Massie Way N W E S J.C. Massie Way Cars Trucks Heavys Totals Office Building Driveway Cars Trucks Heavys Totals Peds Cross: Cars Cars Peds Cross: West Peds: 5 Trucks Trucks South Peds: West Entering: 44 Heavys Heavys South Entering: West Leg Total: 156 Totals Totals South Leg Total: Comments

24 Total Count Diagram Ontario Traffic Inc Municipality: Site #: Intersection: TFR File #: Count date: Barrie Little Lake Dr & J.C. Massie Way 5 3-Mar-16 Weather conditions: Person(s) who counted: ** Non-Signalized Intersection ** Major Road: Little Lake Dr runs W/E North Leg Total: 355 Heavys 3 3 Heavys 3 East Leg Total: 11 North Entering: 178 Trucks Trucks 3 East Entering: 493 North Peds: 17 Cars Cars 171 East Peds: 34 Peds Cross: Totals Totals 177 Peds Cross: Heavys Trucks Cars Totals Little Lake Dr Heavys Trucks Cars Totals J.C. Massie Way N W E S J.C. Massie Way Cars Trucks Heavys Totals Office Building Driveway Cars Trucks Heavys Totals Peds Cross: Cars 4 Cars Peds Cross: West Peds: 14 Trucks Trucks South Peds: 4 West Entering: 671 Heavys Heavys South Entering: West Leg Total: 1315 Totals 4 Totals South Leg Total: 4 Comments

25 Appendix C Previous Study Excerpts 19

26 Brimanor Construction Services Ltd. Page 6 of 13 February 27, 213 Updated Analysis Traffic Impact and Parking Study Highway 4 and Duckworth Street City of Barrie The future (215) background results reflect that the signalized intersection of Cundles Road East / Duckworth Road is expected to operate at acceptable level of services (LOS) during the morning peak period; however, it is expected to operate above capacity during the afternoon peak period. This is due to the heavy vehicles along Cundles Road East / Duckworth Road. This is as a result of the background development and growth within the study area. However, for the ultimate build-out, the future (215) background analysis reveals that the signalized intersection of Cundles Road East / Highway 4 N E-W off-ramp is expected to operate at acceptable overall LOS during the morning peak period and afternoon peak period. The Cundles Road East / Little Lake Drive (JC Massey Way) intersection is expected to continue to operate at acceptable LOS with no individual movements operating above capacity. The unsignalized intersection of Little Lake re-alignment / Little Lake Drive is expected to continue to operate at excellent LOS. 3. Site Traffic The Full Build-Out of the proposed senior community development will consist of approximately 14 retirement residential suits. Ultimately, the proposed site access will be aligned with Little Lake Drive re-alignment (JC Massey Way) Trip Generation Based on the trip generation data summarized in the Trip Generation Manual, 8th Edition, published by ITE, Land Use Code 255 (Continuing Care Retirement Community) was used to determine the new trips generated by the proposed development. To be conservative, the average rate for the land use was applied and the trip generation for the proposed development is summarized in Table 3.1. Size Table 3.1 Site Trip Generation Parameters Weekday AM Peak Hour Weekday PM Peak Hour IN OUT TOTAL IN OUT TOTAL Continuing Care Gross Trips Retirement Community 14 suits Gross Trip Rates Total New Vehicular Trips As summarized, the proposed development at full build-out is expected to generate 25 new vehicular two-way trips in the morning peak hour (16 trips in / nine (9) trips out) and 41 new vehicular two-way trips in the afternoon peak hour (2 trips in / 21 trips out).

27 Appendix D Synchro Results 2

28 Lakeside Terrace HCM Unsignalized Intersection Capacity Analysis 1: Lower Parking Access & J.C. Massie Way Total (216) AM Peak Hour Movement EBT EBR WBL WBT NBL NBR Lane Configurations Traffic Volume (veh/h) Future Volume (Veh/h) Sign Control Free Free Stop Grade % % % Peak Hour Factor Hourly flow rate (vph) Pedestrians Lane Width (m) Walking Speed (m/s) Percent Blockage Right turn flare (veh) Median type None None Median storage veh) Upstream signal (m) px, platoon unblocked vc, conflicting volume vc1, stage 1 conf vol vc2, stage 2 conf vol vcu, unblocked vol tc, single (s) tc, 2 stage (s) tf (s) p queue free % cm capacity (veh/h) Direction, Lane # EB 1 WB 1 NB 1 Volume Total Volume Left 8 Volume Right 22 csh Volume to Capacity.1..1 Queue Length 95th (m)...2 Control Delay (s) Lane LOS A Approach Delay (s) Approach LOS A Intersection Summary Average Delay.3 Intersection Capacity Utilization 17.9% ICU Level of Service A Analysis Period (min) 15 Synchro 9 Report JD Engineering 12/4/216

29 Lakeside Terrace HCM Unsignalized Intersection Capacity Analysis 2: J.C. Massie Way/Little Lake Drive & Existing Access Total (216) AM Peak Hour Movement NWL NWR NET NER SWL SWT Lane Configurations Traffic Volume (veh/h) Future Volume (Veh/h) Sign Control Stop Free Free Grade % % % Peak Hour Factor Hourly flow rate (vph) Pedestrians 5 3 Lane Width (m) Walking Speed (m/s) Percent Blockage Right turn flare (veh) Median type None None Median storage veh) Upstream signal (m) px, platoon unblocked vc, conflicting volume vc1, stage 1 conf vol vc2, stage 2 conf vol vcu, unblocked vol tc, single (s) tc, 2 stage (s) tf (s) p queue free % cm capacity (veh/h) Direction, Lane # NW 1 NE 1 SW 1 Volume Total Volume Left 47 1 Volume Right csh Volume to Capacity.6.9. Queue Length 95th (m) Control Delay (s) Lane LOS A A Approach Delay (s) Approach LOS A Intersection Summary Average Delay 2.1 Intersection Capacity Utilization 19.9% ICU Level of Service A Analysis Period (min) 15 Synchro 9 Report JD Engineering 12/4/216

30 Lakeside Terrace HCM Unsignalized Intersection Capacity Analysis 3: Upper Parking Lot Access & Existing Access Total (216) AM Peak Hour Movement EBT EBR WBL WBT NBL NBR Lane Configurations Traffic Volume (veh/h) Future Volume (Veh/h) Sign Control Free Free Stop Grade % % % Peak Hour Factor Hourly flow rate (vph) Pedestrians Lane Width (m) Walking Speed (m/s) Percent Blockage Right turn flare (veh) Median type None None Median storage veh) Upstream signal (m) px, platoon unblocked vc, conflicting volume vc1, stage 1 conf vol vc2, stage 2 conf vol vcu, unblocked vol tc, single (s) tc, 2 stage (s) tf (s) p queue free % cm capacity (veh/h) Direction, Lane # EB 1 WB 1 NB 1 Volume Total Volume Left 2 Volume Right 58 csh Volume to Capacity.8..2 Queue Length 95th (m)...5 Control Delay (s) Lane LOS A Approach Delay (s) Approach LOS A Intersection Summary Average Delay 1. Intersection Capacity Utilization 16.2% ICU Level of Service A Analysis Period (min) 15 Synchro 9 Report JD Engineering 12/4/216

31 Lakeside Terrace HCM Unsignalized Intersection Capacity Analysis 1: Lower Parking Access & J.C. Massie Way Total (216) MID Peak Hour Movement EBT EBR WBL WBT NBL NBR Lane Configurations Traffic Volume (veh/h) Future Volume (Veh/h) Sign Control Free Free Stop Grade % % % Peak Hour Factor Hourly flow rate (vph) Pedestrians Lane Width (m) Walking Speed (m/s) Percent Blockage Right turn flare (veh) Median type None None Median storage veh) Upstream signal (m) px, platoon unblocked vc, conflicting volume vc1, stage 1 conf vol vc2, stage 2 conf vol vcu, unblocked vol tc, single (s) tc, 2 stage (s) tf (s) p queue free % cm capacity (veh/h) Direction, Lane # EB 1 WB 1 NB 1 Volume Total Volume Left 24 Volume Right 37 csh Volume to Capacity Queue Length 95th (m)...9 Control Delay (s) Lane LOS B Approach Delay (s) Approach LOS B Intersection Summary Average Delay.6 Intersection Capacity Utilization 2.9% ICU Level of Service A Analysis Period (min) 15 Synchro 9 Report JD Engineering 12/4/216

32 Lakeside Terrace HCM Unsignalized Intersection Capacity Analysis 2: J.C. Massie Way/Little Lake Drive & Existing Access Total (216) MID Peak Hour Movement NWL NWR NET NER SWL SWT Lane Configurations Traffic Volume (veh/h) Future Volume (Veh/h) Sign Control Stop Free Free Grade % % % Peak Hour Factor Hourly flow rate (vph) Pedestrians 8 3 Lane Width (m) Walking Speed (m/s) Percent Blockage 1 Right turn flare (veh) Median type None None Median storage veh) Upstream signal (m) px, platoon unblocked vc, conflicting volume vc1, stage 1 conf vol vc2, stage 2 conf vol vcu, unblocked vol tc, single (s) tc, 2 stage (s) tf (s) p queue free % cm capacity (veh/h) Direction, Lane # NW 1 NE 1 SW 1 Volume Total Volume Left Volume Right 1 23 csh Volume to Capacity Queue Length 95th (m) Control Delay (s) Lane LOS B A Approach Delay (s) Approach LOS B Intersection Summary Average Delay 3.8 Intersection Capacity Utilization 25.3% ICU Level of Service A Analysis Period (min) 15 Synchro 9 Report JD Engineering 12/4/216

33 Lakeside Terrace HCM Unsignalized Intersection Capacity Analysis 3: Upper Parking Lot Access & Existing Access Total (216) MID Peak Hour Movement EBT EBR WBL WBT NBL NBR Lane Configurations Traffic Volume (veh/h) Future Volume (Veh/h) Sign Control Free Free Stop Grade % % % Peak Hour Factor Hourly flow rate (vph) Pedestrians Lane Width (m) Walking Speed (m/s) Percent Blockage Right turn flare (veh) Median type None None Median storage veh) Upstream signal (m) px, platoon unblocked vc, conflicting volume vc1, stage 1 conf vol vc2, stage 2 conf vol vcu, unblocked vol tc, single (s) tc, 2 stage (s) tf (s) p queue free % cm capacity (veh/h) Direction, Lane # EB 1 WB 1 NB 1 Volume Total Volume Left 6 Volume Right 94 csh Volume to Capacity Queue Length 95th (m).. 2. Control Delay (s) Lane LOS B Approach Delay (s) Approach LOS B Intersection Summary Average Delay 1.8 Intersection Capacity Utilization 19.1% ICU Level of Service A Analysis Period (min) 15 Synchro 9 Report JD Engineering 12/4/216

886 March Road McDonald's Transportation Study

886 March Road McDonald's Transportation Study McDonald's Restaurants of Canada Limited March 2013 886 March Road McDonald's Transportation Study Submitted by: HDR Corporation 100 York Boulevard, Suite 300 Richmond Hill, ON L4B 1J8 (905) 882-4100 www.hdrinc.com

More information

RESPONSE TO TRAFFIC IMPACT STUDY COMMENTS

RESPONSE TO TRAFFIC IMPACT STUDY COMMENTS RESPONSE TO TRAFFIC IMPACT STUDY COMMENTS Proposed Gas Station 40 Arthur Street (Highway 26), Town of the Blue Mountains (Thornbury), County of Grey, Ontario AUGUST 2013 August 27, 2013 MR. REG RUSSWURM

More information

L1TILE BEARS DAY CARE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO MAY Prepared for:

L1TILE BEARS DAY CARE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO MAY Prepared for: L1TILE BEARS DAY CARE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO MAY 2012 Prepared for: Hillside Construction, Inc. 216 Hemlock Street, Suite B Fort Collins, CO 80534 Prepared by: DELICH ASSOCIATES

More information

MEMORANDUM. Date: November 4, Cheryl Burrell, Pebble Beach Company. Rob Rees, P.E. Inclusionary Housing Transportation Analysis WC

MEMORANDUM. Date: November 4, Cheryl Burrell, Pebble Beach Company. Rob Rees, P.E. Inclusionary Housing Transportation Analysis WC MEMORANDUM Date: November 4, 2013 To: From: Subject: Cheryl Burrell, Pebble Beach Company Rob Rees, P.E. Inclusionary Housing Transportation Analysis As requested, Fehr & Peers is providing clarification

More information

Re: Addendum No. 4 Transportation Overview 146 Mountshannon Drive Ottawa, Ontario

Re: Addendum No. 4 Transportation Overview 146 Mountshannon Drive Ottawa, Ontario April 18 th, 2017 Mr. Kevin Yemm Vice President, Land Development Richraft Group of Companies 2280 St. Laurent Boulevard, Suite 201 Ottawa, Ontario (Tel: 613.739.7111 / e-mail: keviny@richcraft.com) Re:

More information

Traffic Impact Study Proposed Commercial Development Ballwin, Missouri. Technical Memorandum for Traffic Impact Study

Traffic Impact Study Proposed Commercial Development Ballwin, Missouri. Technical Memorandum for Traffic Impact Study Traffic Impact Study Proposed Commercial Development Ballwin, Missouri Technical Memorandum for Traffic Impact Study Crawford, Bunte, Brammeier May 1, 2009 MEMORANDUM Date: April 24, 2009 To: From: Subject:

More information

Sugarland Crossing Gwinnett County, Georgia

Sugarland Crossing Gwinnett County, Georgia Sugarland Crossing Gwinnett County, Georgia S IGNAL W ARRANT A NALYSIS For the Intersection of: Sugarloaf Parkway / Richards Middle School Driveway / Sugarland Crossing Main Site Driveway Prepared for:

More information

Bennett Pit. Traffic Impact Study. J&T Consulting, Inc. Weld County, Colorado. March 3, 2017

Bennett Pit. Traffic Impact Study. J&T Consulting, Inc. Weld County, Colorado. March 3, 2017 Bennett Pit Traffic Impact Study J&T Consulting, Inc. Weld County, Colorado March 3, 217 Prepared By: Sustainable Traffic Solutions, Inc. http://www.sustainabletrafficsolutions.com/ Joseph L. Henderson,

More information

Barrhaven Honda Dealership. Dealership Drive, Ottawa, ON. Transportation Brief

Barrhaven Honda Dealership. Dealership Drive, Ottawa, ON. Transportation Brief Barrhaven Honda Dealership Dealership Drive, Ottawa, ON Transportation Brief Prepared By: NOVATECH Suite 200, 240 Michael Cowpland Drive Ottawa, Ontario K2M 1P6 September, 2015 File: 115136 Ref: R-2015-152

More information

STANDARD LIMITATIONS

STANDARD LIMITATIONS STANDARD LIMITATIONS This report was prepared by MMM Group (MMM) for the account of Spire Construction Inc. (the Client). The disclosure of any information contained in this report is the sole responsibility

More information

Village of Richmond Transportation Brief

Village of Richmond Transportation Brief Village of Richmond Transportation Brief GENIVAR Project Number 111-18482-00 June 21 st, 2011 www.genivar.com GENIVAR 15 Fitzgerald Road, Suite 100 Ottawa, Ontario, CANADA K2H 9G1 Telephone: 613-829-2800

More information

CastleGlenn Consultants Inc.

CastleGlenn Consultants Inc. CastleGlenn Consultants Inc. Engineers, Project Managers & Planners March 11 th, 2013 Domenic Idone, P. Eng Planning Manager R.W. Tomlinson Ltd. 5597 Power Road Ottawa, Ontario K1G 3N4 Dear Mr. Idone:

More information

April Salvation Army Barrhaven Church 102 Bill Leathem Drive Transportation Brief

April Salvation Army Barrhaven Church 102 Bill Leathem Drive Transportation Brief April 26 Salvation Army Barrhaven Church 2 Bill Leathem Drive Transportation Brief Salvation Army Barrhaven Church 2 Bill Leathem Drive Transportation Brief prepared for: The Salvation Army 2 Overlea Blvd.

More information

Table 1 - Land Use Comparisons - Proposed King s Wharf Development. Retail (SF) Office (SF) 354 6,000 10, Land Uses 1

Table 1 - Land Use Comparisons - Proposed King s Wharf Development. Retail (SF) Office (SF) 354 6,000 10, Land Uses 1 Ref. No. 171-6694 Phase 2 November 23, 217 Mr. David Quilichini, Vice President Fares & Co. Developments Inc. 31 Place Keelson Sales Centre DARTMOUTH NS B2Y C1 Sent Via Email to David@faresinc.com RE:

More information

ZINFANDEL LANE / SILVERADO TRAIL INTERSECTION TRAFFIC ANALYSIS

ZINFANDEL LANE / SILVERADO TRAIL INTERSECTION TRAFFIC ANALYSIS ZINFANDEL LANE / SILVERADO TRAIL INTERSECTION TRAFFIC ANALYSIS UPDATED TRAFFIC STUDY FOR THE PROPOSED RAYMOND VINEYARDS WINERY USE PERMIT MODIFICATION #P11-00156 AUGUST 5, 2014 PREPARED BY: OMNI-MEANS,

More information

Traffic Impact Study Hudson Street Parking Garage MC Project No.: A Table of Contents

Traffic Impact Study Hudson Street Parking Garage MC Project No.: A Table of Contents Traffic Impact Study Hudson Street Parking Garage MC Project No.: 15001714A Table of Contents Table of Contents I. INTRODUCTION... 1 II. EXISTING CONDITIONS... 4 III. 2015 EXISTING TRAFFIC CONDITIONS...

More information

MERIVALE PRIORITY SQUARE 2852 MERIVALE ROAD CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: ONT Inc. 25 Winding Way Nepean, Ontario K2C 3H1

MERIVALE PRIORITY SQUARE 2852 MERIVALE ROAD CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: ONT Inc. 25 Winding Way Nepean, Ontario K2C 3H1 MERIVALE PRIORITY SQUARE 2852 MERIVALE ROAD CITY OF OTTAWA TRANSPORTATION BRIEF Prepared for: 2190986ONT Inc. 25 Winding Way Nepean, Ontario K2C 3H1 October 6, 2010 110-502 Report_1.doc D. J. Halpenny

More information

830 Main Street Halifax Regional Municipality

830 Main Street Halifax Regional Municipality 830 Main Street Halifax Regional Municipality Traffic Impact Statement Final Report Prepared by: GRIFFIN transportation group inc. 30 Bonny View Drive Fall River, NS B2T 1R2 www.griffininc.ca Prepared

More information

RICHMOND OAKS HEALTH CENTRE 6265 PERTH STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: Guycoki (Eastern) Limited.

RICHMOND OAKS HEALTH CENTRE 6265 PERTH STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: Guycoki (Eastern) Limited. RICHMOND OAKS HEALTH CENTRE 6265 PERTH STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: Guycoki (Eastern) Limited June 16, 2016 116-638 Brief_1.doc D. J. Halpenny & Associates Ltd. Consulting

More information

DEVELOPMENT PROPERTY 1627 MAXIME STREET CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for: Subhas Bhargava. July 9, Overview_1.

DEVELOPMENT PROPERTY 1627 MAXIME STREET CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for: Subhas Bhargava. July 9, Overview_1. DEVELOPMENT PROPERTY 1627 MAXIME STREET CITY OF OTTAWA TRANSPORTATION OVERVIEW Prepared for: Subhas Bhargava July 9, 2015 115-620 Overview_1.doc D. J. Halpenny & Associates Ltd. Consulting Transportation

More information

Traffic Impact Study Proposed Residential Development (Watson Parkway North - Starwood Drive Node, City of Guelph)

Traffic Impact Study Proposed Residential Development (Watson Parkway North - Starwood Drive Node, City of Guelph) Traffic Impact Study Proposed Residential Development (Watson Parkway North - Starwood Drive Node, City of Guelph) Prepared By: 332 Lorne Avenue East Stratford ON N5A 6S4 Prepared for: Paul Kemper, President

More information

Wellington Street West

Wellington Street West Transportation Brief prepared for: 185 Davenport Road Suite 300 Toronto, ON M5R 1J1 prepared by: 1223 Michael Street Suite 100 Ottawa, ON K1J 7T2 November 5, 2013 TO3131TOH Transportation Brief November

More information

MEMO. McCORMICK RANKIN CORPORATION. File FROM: Keyur Shah DATE: February 1, 2010 COPIES: OUR FILE: SUBJECT: TO:

MEMO. McCORMICK RANKIN CORPORATION. File FROM: Keyur Shah DATE: February 1, 2010 COPIES: OUR FILE: SUBJECT: TO: McCORMICK RANKIN CORPORATION 2655 North Sheridan Way Mississauga, Ontario, L5K 2P8 Tel: (905)823-8500 Fax: (905) 823-8503 E-mail: mrc@mrc.ca Website: www.mrc.ca MEMO TO: File FROM: Keyur Shah DATE: February

More information

Ryan Coyne, PE City Engineer City of Rye 1051 Boston Post Road Rye, NY Boston Post Road Realignment and Roundabout Design Report

Ryan Coyne, PE City Engineer City of Rye 1051 Boston Post Road Rye, NY Boston Post Road Realignment and Roundabout Design Report March 6, 2015 Ryan Coyne, PE City Engineer City of Rye 1051 Boston Post Road Rye, NY 10580 RE: JMC Project 14108 Boston Post Road Roundabout Boston Post Road and Parsons Street City of Rye, NY Dear Ryan:

More information

Ref. No Task 3. April 28, Mr. Cesar Saleh, P. Eng. VP Planning and Design W.M. Fares Group th

Ref. No Task 3. April 28, Mr. Cesar Saleh, P. Eng. VP Planning and Design W.M. Fares Group th Ref. No. 151-00564 Task 3 April 28, 2015 Mr. Cesar Saleh, P. Eng. VP Planning and Design W.M. Fares Group th 3480 Joseph Howe Drive, 5 Floor HALIFAX NS B3L 4H7 Sent via Email to ceasr.saleh@wmfares.com

More information

Trafalgar Road & Lower Base Line Transportation Study Ontario Inc.

Trafalgar Road & Lower Base Line Transportation Study Ontario Inc. Trafalgar Road & Lower Base Line Transportation Study 1255723 Ontario Inc. Trafalgar Road & Lower Base Line Transportation Study 1255723 Ontario Inc. 1465 Pickering Parkway Suite 200 Pickering ON L1V 7G7

More information

267 O Connor Street Residential Development

267 O Connor Street Residential Development M a y 2014 267 O Connor Street Residential Development Transportation Brief Google 2014 Bing 2014 Prepared for: MASTERCRAFT STARWOOD Prepared by: Study 267 O'Connor Type Street May 2014 Study Residential

More information

MMM Group Limited. Communities. Transportation. Buildings. Infrastructure

MMM Group Limited. Communities. Transportation. Buildings. Infrastructure MMM Group Limited Traffic Study CASA MIA Community Care Facility Vancouver, BC Communities Transportation Buildings Infrastructure February 2013 5011001-033 STANDARD LIMITATIONS This report was prepared

More information

INTERSECTION ANALYSIS PARK AVENUE AND BRADDOCK ROAD (FROSTBURG, MD) FOR LENHART TRAFFIC CONSULTING, INC.

INTERSECTION ANALYSIS PARK AVENUE AND BRADDOCK ROAD (FROSTBURG, MD) FOR LENHART TRAFFIC CONSULTING, INC. INTERSECTION ANALYSIS FOR PARK AVENUE AND BRADDOCK ROAD (FROSTBURG, MD) Prepared for: City of Frostburg, Maryland & Allegany County Commissioners Prepared by: LENHART TRAFFIC CONSULTING, INC. TRAFFIC ENGINEERING

More information

MURRIETA APARTMENTS TRAFFIC IMPACT ANALYSIS CITY OF MURRIETA, CALIFORNIA

MURRIETA APARTMENTS TRAFFIC IMPACT ANALYSIS CITY OF MURRIETA, CALIFORNIA MURRIETA APARTMENTS TRAFFIC IMPACT ANALYSIS CITY OF MURRIETA, CALIFORNIA SEPTEMBER 20, 2012 Prepared for: Golden Eagle Multi-Family Properties, LLC 6201 Oak Canyon Rd., Suite 250 Irvine, CA 92618 Prepared

More information

BARRHAVEN FELLOWSHIP CRC 3058 JOCKVALE ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for:

BARRHAVEN FELLOWSHIP CRC 3058 JOCKVALE ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: BARRHAVEN FELLOWSHIP CRC 3058 JOCKVALE ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: Barrhaven Fellowship CRC 3058 Jockvale Road Ottawa, ON K2J 2W7 December 7, 2016 116-649 Report_1.doc D. J.

More information

Clean Harbors Canada, Inc.

Clean Harbors Canada, Inc. Clean Harbors Canada, Inc. Proposed Lambton Landfill Expansion Environmental Assessment Terms of Reference Transportation Assessment St. Clair Township, Ontario September 2009 itrans Consulting Inc. 260

More information

JRL consulting. March Hartland Developments Limited 1993 Hammonds Plains Road Hammonds Plains, NS B4B 1P3

JRL consulting. March Hartland Developments Limited 1993 Hammonds Plains Road Hammonds Plains, NS B4B 1P3 March 2015 Prepared for Hartland Developments Limited 1993 Hammonds Plains Road Hammonds Plains, NS B4B 1P3 JRL consulting JRL consulting TABLE OF CONTENTS 1 INTRODUCTION... 2 1.1 BACKGROUND... 2 2 EXISTING

More information

One Harbor Point Residential

One Harbor Point Residential Residential Gig Harbor, WA Transportation Impact Analysis January 23, 2017 Prepared for: Neil Walter Company PO Box 2181 Tacoma, WA 98401 Prepared by: TENW Transportation Engineering NorthWest 11400 SE

More information

(A) Project Manager, Infrastructure Approvals

(A) Project Manager, Infrastructure Approvals February 14th, 2014 BY E-MAIL: wally.dubyk@ottawa.ca City of Ottawa Planning and Growth Management Branch 110 Laurier Ave. W., 4 th Floor, Ottawa, Ontario K1P 1J1 Attention: Wally Dubyk, C.E.T (A) Project

More information

Provide an overview of the development proposal including projected site traffic volumes;

Provide an overview of the development proposal including projected site traffic volumes; December 19, 2013 File: 163600935 Attention: Troy Elliott Carl Elliott Limited 15-1831 Robertson Road PO Box 11117 Nepean, Ontario K1H 7T8 Dear Mr. Elliott, Reference: 2235 and 2265 Robertson Road Transportation

More information

Re: Residential Development - Ogilvie/Cummings Transportation Overview

Re: Residential Development - Ogilvie/Cummings Transportation Overview 1223 Michael Street, Suite 100, Ottawa, ON K1J 7T2 Tel: 613.738.4160 Fax: 613.739.7105 www.delcan.com March 28, 2012 OUR REF: TO3088TOY Barry J. Hobin & Architects 63 Pamilla Street Ottawa, ON K1S 3K7

More information

Parking/Traffic Assessment Study

Parking/Traffic Assessment Study Brock Road Industrial Mall 985 Brock Road South City of Pickering Parking/Traffic Assessment Study Prepared by: Tranplan Associates, Toronto Toronto 416-670-2005 Sudbury 705-522-0272 Peterborough 705-874-3638

More information

Technical Memorandum. To: From: Date: October 14 th, 2018 Project #: 1302 Project Name: Subject: Distribution:

Technical Memorandum. To: From: Date: October 14 th, 2018 Project #: 1302 Project Name: Subject: Distribution: Technical Memorandum To: Tom Hanrahan Jeff Sharp From: Date: October 14 th, 2018 Project #: 1302 Project Name: Subject: Distribution: Barrie Lockhart Road LP Conformity Review Scott Young Sorbara Group

More information

MEMO. McCORMICK RANKIN CORPORATION. File Mark VanderSluis, Keyur Shah DATE: October 26, 2009 COPIES: OUR FILE: TO: FROM: Jack Thompson

MEMO. McCORMICK RANKIN CORPORATION. File Mark VanderSluis, Keyur Shah DATE: October 26, 2009 COPIES: OUR FILE: TO: FROM: Jack Thompson McCORMICK RANKIN CORPORATION 2655 North Sheridan Way Mississauga, Ontario, L5K 2P8 Tel: (95)823-85 Fax: (95) 823-853 E-mail: mrc@mrc.ca Website: www.mrc.ca MEMO TO: FROM: File Mark VanderSluis, Keyur Shah

More information

Traffic Analysis For Approved Uses within the St. Lucie West DRI Aldi Port St. Lucie, FL Prepared for: Bohler Engineering, LLC 1000 Corporate Drive Suite 250 Fort Lauderdale, FL 33334 Prepared by: 10795

More information

LOST LAKE CORRIDOR REVIEW

LOST LAKE CORRIDOR REVIEW LOST LAKE CORRIDOR REVIEW Prepared for: Prepared by: Broadview Developments Inc. c/o Westbrook Consulting Watt Consulting Group Our File: 2064.B01 Date: October 31, 2016 TABLE OF CONTENTS 1.0 INTRODUCTION...

More information

RE: A Traffic Impact Statement for a proposed development on Quinpool Road

RE: A Traffic Impact Statement for a proposed development on Quinpool Road James J. Copeland, P.Eng. GRIFFIN transportation group inc. 30 Bonny View Drive Fall River, NS B2T 1R2 May 31, 2018 Ellen O Hara, P.Eng. Project Engineer DesignPoint Engineering & Surveying Ltd. 200 Waterfront

More information

770 SOMERSET STREET RESIDENTIAL DEVELOPMENT

770 SOMERSET STREET RESIDENTIAL DEVELOPMENT Downtown North York by PFHLai / CC-BY-3. September 217 77 SOMERSET STREET RESIDENTIAL DEVELOPMENT Transportation Impact Assessment 77 Somerset Street Residential Development Transportation Impact Assessment

More information

Proposed Pit Development

Proposed Pit Development July 5, 2017 via email: sam@greenwoodconst.ca CCTA File 114239 Sam Greenwood Greenwood Aggregates 205467 County Road 109 Amaranth, ON L9W 0V1 Re: Proposed Violet Hill Gravel Pit, Town of Mono Traffic Review

More information

Oakbrook Village Plaza City of Laguna Hills

Oakbrook Village Plaza City of Laguna Hills Oakbrook Village Plaza City of Laguna Hills Traffic Impact Analysis Prepared by: HDR Engineering 3230 El Camino Real, Suite 200 Irvine, CA 92602 October 2012 Revision 3 D-1 Oakbrook Village Plaza Laguna

More information

Re: Cyrville Road Car Dealership

Re: Cyrville Road Car Dealership 1223 Michael Street, Suite 100, Ottawa, ON K1J 7T2 Tel: 613.738.4160 Fax: 613.739.7105 www.delcan.com February 25, 2013 OUR REF: TO3098TOE Mark Motors of Ottawa 611 Montreal Road Ottawa, ON K1K 0T8 Attention:

More information

Weaver Road Senior Housing Traffic Impact Analysis

Weaver Road Senior Housing Traffic Impact Analysis Gibson Traffic Consultants, Inc. 2813 Rockefeller Avenue Suite B Everett, WA 9821 425.339.8266 Weaver Road Senior Housing Traffic Impact Analysis Jurisdiction: City of Snohomish January 218 GTC #17-37

More information

105 Toronto Street South, Markdale Transportation Impact Study. Paradigm Transportation Solutions Limited

105 Toronto Street South, Markdale Transportation Impact Study. Paradigm Transportation Solutions Limited 105 Toronto Street South, Markdale Transportation Impact Study Paradigm Transportation Solutions Limited December 2016 Project Summary Project Number 162060 December 2016 Client Zelinka Priamo Ltd 318

More information

Dartmouth, NS B3B 1X7 Tel: WSP. Canada Inc.

Dartmouth, NS B3B 1X7 Tel: WSP. Canada Inc. Traffic Impact Study: Proposed Residential Development Herring Cove Road Halifax, NS Presented to: FH Construction Ltd. 1 Spectacle Lake Drive Dartmouth, NS B3B 1X7 Tel: 902 835 9955 Fax: 902 835 1645

More information

King Soopers #116 Thornton, Colorado

King Soopers #116 Thornton, Colorado Traffic Impact Study King Soopers #116 Thornton, Colorado Prepared for: Galloway & Company, Inc. T R A F F I C I M P A C T S T U D Y King Soopers #116 Thornton, Colorado Prepared for Galloway & Company

More information

LAWRENCE TRANSIT CENTER LOCATION ANALYSIS 9 TH STREET & ROCKLEDGE ROAD / 21 ST STREET & IOWA STREET LAWRENCE, KANSAS

LAWRENCE TRANSIT CENTER LOCATION ANALYSIS 9 TH STREET & ROCKLEDGE ROAD / 21 ST STREET & IOWA STREET LAWRENCE, KANSAS LAWRENCE TRANSIT CENTER LOCATION ANALYSIS 9 TH STREET & ROCKLEDGE ROAD / 21 ST STREET & IOWA STREET LAWRENCE, KANSAS TRAFFIC IMPACT STUDY FEBRUARY 214 OA Project No. 213-542 TABLE OF CONTENTS 1. INTRODUCTION...

More information

Addendum to Traffic Impact Analysis for Port Marigny Site Mandeville, LA

Addendum to Traffic Impact Analysis for Port Marigny Site Mandeville, LA Addendum to Traffic Impact Analysis for Port Marigny Site Mandeville, LA (St. Tammany Parish Mandeville, LA) Prepared For The Pittman Companies Michael N Pittman, MD 328 East Boston St Covington, LA 70433

More information

APPENDIX C1 TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS

APPENDIX C1 TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS APPENDIX C1 TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS February 2018 Highway & Bridge Project PIN 6754.12 Route 13 Connector Road Chemung County February 2018 Appendix

More information

APPENDIX E. Traffic Analysis Report

APPENDIX E. Traffic Analysis Report APPENDIX E Traffic Analysis Report THIS PAGE INTENTIONALLY BLANK EAGLE RIVER TRAFFIC MITIGATION PHASE I OLD GLENN HIGHWAY/EAGLE RIVER ROAD INTERSECTION IMPROVEMENTS TRAFFIC ANALYSIS Eagle River, Alaska

More information

D & B COMMERCIAL TRAFFIC IMPACT ANALYSIS

D & B COMMERCIAL TRAFFIC IMPACT ANALYSIS D & B COMMERCIAL TRAFFIC IMPACT ANALYSIS TABLE OF CONTENTS I. Introduction...3 II. Project Description...3 III. Existing Conditions...3 IV. Future Traffic Conditions...8 V. Conclusions and Mitigation...14

More information

TRAFFIC IMPACT STUDY FOR ST. JOSEPH'S ELEMENTARY SCHOOL ADDITION

TRAFFIC IMPACT STUDY FOR ST. JOSEPH'S ELEMENTARY SCHOOL ADDITION CATHOLIC DISTRICT SCHOOL BOARD OF EASTERN ONTARIO P.O. 61992 TRAFFIC IMPACT STUDY FOR ST. JOSEPH'S ELEMENTARY SCHOOL ADDITION SEPTEMBER 5, 218 TRAFFIC IMPACT STUDY FOR ST. JOSEPH'S ELEMENTARY SCHOOL ADDITION

More information

Prepared For: Toronto Transit Commission 1138 Bathurst Street Toronto, Ontario M5R 3H2. Prepared By:

Prepared For: Toronto Transit Commission 1138 Bathurst Street Toronto, Ontario M5R 3H2. Prepared By: TRAFFIC IMPACT STUDY FOR THE TTC MCNICOLL BUS GARAGE CITY OF TORONTO Prepared For: Toronto Transit Commission 1138 Bathurst Street Toronto, Ontario M5R 3H2 Prepared By: Canada Inc. 4th Floor, 3 Leek Crescent

More information

Traffic Impact Analysis Update

Traffic Impact Analysis Update Willow Bend Traffic Impact Analysis Update TABLE OF CONTENTS Page I. INTRODUCTION -------------------------------------------------------------------------------------------- 1 II. EXISTING CONDITIONS

More information

JOHNSON RANCH RAPID CITY, SOUTH DAKOTA TRAFFIC IMPACT ANALYSIS

JOHNSON RANCH RAPID CITY, SOUTH DAKOTA TRAFFIC IMPACT ANALYSIS JOHNSON RANCH RAPID CITY, SOUTH DAKOTA TRAFFIC IMPACT ANALYSIS Prepared for: KTM Design Solutions 528 Kansas City Street, Suite 1 Rapid City, SD 57701 Prepared by: Felsburg Holt & Ullevig 6300 South Syracuse

More information

TRAFFIC DATA. Existing Derousse Ave./River Rd. AM LOS Analysis Existing Derousse Ave./River Rd. PM LOS Analysis

TRAFFIC DATA. Existing Derousse Ave./River Rd. AM LOS Analysis Existing Derousse Ave./River Rd. PM LOS Analysis Appendix E NJ TRANSIT Pennsauken Junction Transit Center and Park & Ride RiverLINE and Atlantic City Line Pennsauken Township, Camden County, New Jersey TRAFFIC DATA Background Traffic Information for

More information

1140 Wellington Street West Transportation Brief

1140 Wellington Street West Transportation Brief 1140 Wellington Street West Transportation Brief October 2013 Study 1140 Wellington Type Street West October 2013 Study Transportation Name Brief February 2011 TB Check List TIS / TB/ CTS Check List prepared

More information

TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION

TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION DECEMBER 24 UPDATED

More information

King County Metro. Columbia Street Transit Priority Improvements Alternative Analysis. Downtown Southend Transit Study. May 2014.

King County Metro. Columbia Street Transit Priority Improvements Alternative Analysis. Downtown Southend Transit Study. May 2014. King County Metro Columbia Street Transit Priority Improvements Alternative Analysis Downtown Southend Transit Study May 2014 Parametrix Table of Contents Introduction... 1 Methodology... 1 Study Area...

More information

MEMO VIA . Ms. Amy Roth DPS Director, City of Three Rivers. To:

MEMO VIA  . Ms. Amy Roth DPS Director, City of Three Rivers. To: MEMO To: Ms. Amy Roth DPS Director, City of Three Rivers VIA EMAIL From: Michael J. Labadie, PE Julie M. Kroll, PE, PTOE Brandon Hayes, PE, P.Eng. Fleis & VandenBrink Date: January 5, 2017 Re: Proposed

More information

Proposed Hotel and Restaurant Development

Proposed Hotel and Restaurant Development Traffic Impact Study Proposed Hotel and Restaurant Development Marbledale Road Tuckahoe, NY PREPARED FOR BILLWIN DEVELOPMENT AFFILIATES, LLC 365 WHITE PLAINS ROAD EASTCHESTER, NY. 10709 PREPARED BY Engineering

More information

Vanier Parkway and Presland Road Residential Development Transportation Impact Study

Vanier Parkway and Presland Road Residential Development Transportation Impact Study Vanier Parkway and Presland Road Residential Development Transportation Impact Study Final Report (Revised) March 2011 Submitted to: Groupe Lépine Ottawa Project No. 09-1613 Submitted by: Groupe Lépine

More information

TRAFFIC IMPACT ANALYSIS

TRAFFIC IMPACT ANALYSIS TRAFFIC IMPACT ANALYSIS Emerald Isle Commercial Development Prepared by SEPI Engineering & Construction Prepared for Ark Consulting Group, PLLC March 2016 I. Executive Summary A. Site Location The Emerald

More information

APPENDICES. APPENDIX D Synchro Level of Service Output Sheets

APPENDICES. APPENDIX D Synchro Level of Service Output Sheets APPENDICES APPENDIX D Synchro Level of Service Output Sheets Lanes, Volumes, Timings NO BUILD 2016 PM 8: 10th St & Thain Rd 10/05/2016 Lane Group NBL NBT NBR SBL SBT SBR SEL SET SER NWL NWT NWR

More information

Proposed location of Camp Parkway Commerce Center. Vicinity map of Camp Parkway Commerce Center Southampton County, VA

Proposed location of Camp Parkway Commerce Center. Vicinity map of Camp Parkway Commerce Center Southampton County, VA Proposed location of Camp Parkway Commerce Center Vicinity map of Camp Parkway Commerce Center Southampton County, VA Camp Parkway Commerce Center is a proposed distribution and industrial center to be

More information

TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA

TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA PREPARED FOR: UNIVERSITY OF PENNSYLVANIA HEALTH SYSTEM 34 CIVIC CENTER BOULEVARD PHILADELPHIA, PA 1987 (61)

More information

Appendix I: The Project Traffic Impact Study report by TJKM Transportation Consultants

Appendix I: The Project Traffic Impact Study report by TJKM Transportation Consultants Appendix I: The Project Traffic Impact Study report by TJKM Transportation Consultants TJKM Transportation Consultants Draft Report Traffic Impact Study for the Residential Development at 4659 Proctor

More information

West Hills Shopping Centre Lowe s Expansion Traffic Impact Study

West Hills Shopping Centre Lowe s Expansion Traffic Impact Study West Hills Shopping Centre Lowe s Expansion Traffic Impact Study Prepared for: Armel Corporation January 2015 Paradigm Transportation Solutions Ltd. 22 King Street South, Suite 300 Waterloo ON N2J 1N8

More information

EXECUTIVE SUMMARY. The following is an outline of the traffic analysis performed by Hales Engineering for the traffic conditions of this project.

EXECUTIVE SUMMARY. The following is an outline of the traffic analysis performed by Hales Engineering for the traffic conditions of this project. EXECUTIVE SUMMARY This study addresses the traffic impacts associated with the proposed Shopko redevelopment located in Sugarhouse, Utah. The Shopko redevelopment project is located between 1300 East and

More information

Environmental Assessment Derry Road and Argentia Road Intersection

Environmental Assessment Derry Road and Argentia Road Intersection Air and Noise Study Environmental Assessment Derry Road and Argentia Road Intersection Project 11-4295 City of Mississauga, Region of Peel October 17, 2014 1 Region of Peel Environmental Assessment for

More information

TECHNICAL MEMORANDUM Upper Broadway Road Diet Summary of Findings

TECHNICAL MEMORANDUM Upper Broadway Road Diet Summary of Findings TECHNICAL MEMORANDUM Summary of Findings Date: June 17, 2014 Project #: 17121.15 To: Si Lau, P.E.; City of Oakland, CA From: Erin Ferguson, P.E.; Aaron Elias, P.E.; Daphne Dethier; and Mark Bowman, P.E.;

More information

Traffic Impact Analysis. Alliance Cole Avenue Residential Site Dallas, Texas. Kimley-Horn and Associates, Inc. Dallas, Texas.

Traffic Impact Analysis. Alliance Cole Avenue Residential Site Dallas, Texas. Kimley-Horn and Associates, Inc. Dallas, Texas. Traffic Impact Analysis Alliance Cole Avenue Residential Site Dallas, Texas February 15, 2018 Kimley-Horn and Associates, Inc. Dallas, Texas Project #064524900 Registered Firm F-928 Traffic Impact Analysis

More information

Paisley & Whitelaw - Paisley Park OPA / ZBA for Mixed Density Residential Use

Paisley & Whitelaw - Paisley Park OPA / ZBA for Mixed Density Residential Use Paisley & Whitelaw - Paisley Park OPA / ZBA for Mixed Density Residential Use Transportation Impact Study City of Guelph Prepared for: Armel Corporation August 2018 Table of Contents 1 Introduction...

More information

Half Moon Bay North Apartment Block Transportation Impact Assessment. Full Report. March 15, Prepared for: Mattamy Homes.

Half Moon Bay North Apartment Block Transportation Impact Assessment. Full Report. March 15, Prepared for: Mattamy Homes. Half Moon Bay North Apartment Block Transportation Impact Assessment Full Report March 15, 2018 Prepared for: Mattamy Homes Prepared by: Stantec Consulting Ltd. Table of Contents 1.0 SCREENING... 1 1.1

More information

Lacey Gateway Residential Phase 1

Lacey Gateway Residential Phase 1 Lacey Gateway Residential Phase Transportation Impact Study April 23, 203 Prepared for: Gateway 850 LLC 5 Lake Bellevue Drive Suite 02 Bellevue, WA 98005 Prepared by: TENW Transportation Engineering West

More information

HCM Unsignalized Intersection Capacity Analysis 6: Brian Street & LC 111 5/26/2009

HCM Unsignalized Intersection Capacity Analysis 6: Brian Street & LC 111 5/26/2009 6: Brian Street & LC 111 5/26/2009 Movement EBL EBR NBL NBT SBT SBR Volume (veh/h) 116 20 8 405 137 56 Sign Control Stop Free Free Grade 0% 0% 0% Peak Hour Factor 0.81 0.81 0.67 0.67 0.89 0.89 Hourly flow

More information

Craigieburn Employment Precinct North and English Street

Craigieburn Employment Precinct North and English Street Craigieburn Employment Precinct North and English Street METROPOLITAN PLANNING AUTHORITY Intersection Analyses 7 February 2014 Intersection Analyses Craigieburn Employment Precinct North and English Street

More information

LATSON INTERCHANGE DEVELOPMENT TRAFFIC STUDIES. Genoa Township, Livingston County, MI

LATSON INTERCHANGE DEVELOPMENT TRAFFIC STUDIES. Genoa Township, Livingston County, MI LATSON INTERCHANGE DEVELOPMENT TRAFFIC STUDIES Genoa Township, Livingston County, MI DRAFT TRAFFIC STUDY FOR I-96 AT LATSON RD INTERCHANGE Livingston County CS 47065 JN 101622C Submitted to: Michigan Department

More information

To: File From: Adrian Soo, P. Eng. Markham, ON File: Date: August 18, 2015

To: File From: Adrian Soo, P. Eng. Markham, ON File: Date: August 18, 2015 Memo To: From: Adrian Soo, P. Eng. Markham, ON : 165620021 Date: Reference: E.C. Row Expressway, Dominion Boulevard Interchange, Dougall Avenue Interchange, and Howard 1. Review of Interchange Geometry

More information

TRANSPORTATION ANALYSIS. Wawa US 441 and Morningside Drive. Prepared for: Brightwork Real Estate, Inc.

TRANSPORTATION ANALYSIS. Wawa US 441 and Morningside Drive. Prepared for: Brightwork Real Estate, Inc. TRANSPORTATION ANALYSIS Wawa US 441 and Morningside Drive Prepared for: Brightwork Real Estate, Inc. TABLE OF CONTENTS Introduction... 1 Project Description... 1 Estimated Daily Project Traffic... 3 Estimated

More information

Alpine Highway to North County Boulevard Connector Study

Alpine Highway to North County Boulevard Connector Study Alpine Highway to North County Boulevard Connector Study prepared by Avenue Consultants March 16, 2017 North County Boulevard Connector Study March 16, 2017 Table of Contents 1 Summary of Findings... 1

More information

June 21, Mr. Jeff Mark The Landhuis Company 212 North Wahsatch Avenue, Suite 301. Colorado Springs, CO 80903

June 21, Mr. Jeff Mark The Landhuis Company 212 North Wahsatch Avenue, Suite 301. Colorado Springs, CO 80903 LSC TRANSPORTATION CONSULTANTS, INC. 545 East Pikes Peak Avenue, Suite 210 Colorado Springs, CO 80903 (719) 633-2868 FAX (719) 633-5430 E-mail: lsc@lsctrans.com Website: http://www.lsctrans.com June 21,

More information

Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. HNTB Project File: Subject

Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. HNTB Project File: Subject TECHNICAL MEMORANDUM To Kumar Neppalli Traffic Engineering Manager Town of Chapel Hill From Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. Cc HNTB Project File: 38435 Subject Obey Creek TIS 2022

More information

Traffic Impact Statement (TIS)

Traffic Impact Statement (TIS) Traffic Impact Statement (TIS) Vincentian PUDA Collier County, FL 10/18/2013 Prepared for: Global Properties of Naples Prepared by: Trebilcock Consulting Solutions, PA 2614 Tamiami Trail N, Suite 615 1205

More information

INDUSTRIAL DEVELOPMENT

INDUSTRIAL DEVELOPMENT INDUSTRIAL DEVELOPMENT Traffic Impact Study Plainfield, Illinois August 2018 Prepared for: Seefried Industrial Properties, Inc. TABLE OF CONTENTS Executive Summary 2 Introduction 3 Existing Conditions

More information

INTERCHANGE OPERTIONS STUDY Interstate 77 / Wallings Road Interchange

INTERCHANGE OPERTIONS STUDY Interstate 77 / Wallings Road Interchange INTERCHANGE OPERTIONS STUDY Interstate 77 / Wallings Road Interchange City of Broadview Heights, Cuyahoga County, Ohio Prepared For: City of Broadview Heights Department of Engineering 9543 Broadview Road

More information

Aldridge Transportation Consultants, LLC Advanced Transportation Planning and Traffic Engineering

Aldridge Transportation Consultants, LLC Advanced Transportation Planning and Traffic Engineering Aldridge Transportation Consultants, LLC Advanced Transportation Planning and Traffic Engineering John M.W. Aldridge, PE, PTOE, AICP 1082 Chimney Rock Road Colorado Registered Professional Engineer Highlands

More information

PROJECT: Wilkinson Road Corridor Improvement Traffic Management Planning Project SUBJECT: Traffic Analysis

PROJECT: Wilkinson Road Corridor Improvement Traffic Management Planning Project SUBJECT: Traffic Analysis TECHNICAL MEMORANDUM DATE: September 10, 2014 PROJECT 5861.03 NO: PROJECT: Wilkinson Road Corridor Improvement Traffic Management Planning Project SUBJECT: Traffic Analysis TO: Steve Holroyd - District

More information

MILLERSVILLE PARK TRAFFIC IMPACT ANALYSIS ANNE ARUNDEL COUNTY, MARYLAND

MILLERSVILLE PARK TRAFFIC IMPACT ANALYSIS ANNE ARUNDEL COUNTY, MARYLAND MILLERSVILLE PARK TRAFFIC IMPACT ANALYSIS ANNE ARUNDEL COUNTY, MARYLAND Prepared for: Department of Public Works Anne Arundel County Prepared by: URS Corporation 4 North Park Drive, Suite 3 Hunt Valley,

More information

Date: February 7, 2017 John Doyle, Z-Best Products Robert Del Rio. T.E. Z-Best Traffic Operations and Site Access Analysis

Date: February 7, 2017 John Doyle, Z-Best Products Robert Del Rio. T.E. Z-Best Traffic Operations and Site Access Analysis Memorandum Date: February 7, 07 To: From: Subject: John Doyle, Z-Best Products Robert Del Rio. T.E. Z-Best Traffic Operations and Site Access Analysis Introduction Hexagon Transportation Consultants, Inc.

More information

HUMC/Mountainside Hospital Redevelopment Plan

HUMC/Mountainside Hospital Redevelopment Plan Traffic and Parking Analysis HUMC/Mountainside Hospital Redevelopment Plan in Glen Ridge Borough and Montclair Township PREPARED FOR H2M 119 Cherry Hill Road, Suite 110 Parsippany, NJ 07054 862.207.5900

More information

Traffic Impact Analysis Farmington Center Village

Traffic Impact Analysis Farmington Center Village Traffic Impact Analysis Farmington Center Village Route 4 (Farmington Avenue) Farmington, Connecticut Prepared for: The Town of Farmington, CT Prepared By: BL Companies Meriden, Connecticut December 2016

More information

Salvini Consulting Inc. 459 Deer Ridge Drive Kitchener, ON N2P 0A November 8, 2017 Revised December 20, 2017

Salvini Consulting Inc. 459 Deer Ridge Drive Kitchener, ON N2P 0A November 8, 2017 Revised December 20, 2017 Salvini Consulting Inc. 459 Deer Ridge Drive Kitchener, ON N2P 0A7 519-591-0426 November 8, 2017 Revised December 20, 2017 Laurie Wills, PEng Deputy Director of Public Works Town of Cobourg 740 Division

More information

V. DEVELOPMENT OF CONCEPTS

V. DEVELOPMENT OF CONCEPTS Martin Luther King, Jr. Drive Extension FINAL Feasibility Study Page 9 V. DEVELOPMENT OF CONCEPTS Throughout the study process several alternative alignments were developed and eliminated. Initial discussion

More information

APPENDIX G. Traffic Data

APPENDIX G. Traffic Data APPENDIX G Traffic Data HCM Signalized Intersection Capacity Analysis 2: Duanesburg Road & I-88 Ramps 10/7/2004 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Ideal Flow (vphpl)

More information