See Part 3 for the Introduction for Article 314

Size: px
Start display at page:

Download "See Part 3 for the Introduction for Article 314"

Transcription

1 See Part 3 for the Introduction for Article Covers and Canopies When the installation is complete, each outlet box must be provided with a cover or faceplate, unless covered by a fixture canopy, lampholder, or similar device. See Figure Boxes and Conduit Bodies for Conductors 4 AWG and Larger. Boxes and conduit bodies containing conductors 4 AWG and larger must be sized so the conductor insulation will not be damaged. Author s Comments: The requirements for sizing boxes and conduit bodies containing conductors 6 AWG and smaller are contained in Where conductors 4 AWG or larger enter a box or other enclosure, a fitting that provides a smooth, rounded, insulating surface, such as a bushing or adapter, is required to protect the conductors from abrasion during and after installation [300.4(F)]. Figure Figure (A) Nonmetallic or Metallic. Nonmetallic covers or plates are permitted on any box, but metallic faceplates, where used, must be bonded to an effective ground-fault current path in accordance with [250.4(A)(3)]. See (C). Author s Comment: Switch faceplates must be grounded (bonded) to an effective ground-fault current path [404.9(B)], and receptacle faceplates must be grounded (bonded) to an effective ground-fault current path [406.5(A)]. Figure Mike Holt Enterprises, Inc NEC.Code 139

2 Top 101 Rules of Understanding the NEC, Volume 1 Part 4: Rules (A) Minimum Size. For raceways containing conductors 4 AWG or larger, the minimum dimensions of boxes and conduit bodies must comply with the following: (1) Straight Pulls. The minimum distance from where the conductors enter to the opposite wall cannot be less than eight times the trade size of the largest raceway. Figure U Pulls. When a conductor enters and leaves from the same wall, the distance from where the raceways enter to the opposite wall cannot be less than six times the trade size of the largest raceway, plus the sum of the trade sizes of the remaining raceways on the same wall and row. Figure Figure Figure (2) Angle and U Pulls. Angle Pulls. The distance from the raceway entry to the opposite wall cannot be less than six times the trade size of the largest raceway, plus the sum of the trade sizes of the remaining raceways on the same wall and row. Figure Figure Rows. Where there are multiple rows of raceway entries, each row is calculated individually and the row with the largest distance must be used. Distance Between Raceways. The distance between raceways enclosing the same conductor cannot be less than six times the trade size of the largest raceway, measured from the raceway s nearest edge-to-nearest edge. See Figure Exception: When conductors enter an enclosure with a removable cover, such as a conduit body or wireway, the distance from where the conductors enter to the removable cover cannot be less than the bending distance as listed in Table 312.6(A) for one wire per terminal. Figure (3) Smaller Dimensions. Boxes or conduit bodies of dimensions less than those required in (A)(1) and (A)(2) are permitted, if the enclosure is permanently marked with the maximum number and maximum size of conductors permitted. (C) Covers. All pull boxes, junction boxes, and conduit bodies must have a cover that is suitable for the conditions. Nonmetallic covers or plates are permitted on any box, but metallic faceplates, where used, must be grounded (bonded) to an effective ground-fault current path in accordance with [250.4(A)(3)]. See (A). Mike Holt Enterprises, Inc NEC.Code 140

3 Top 101 Rules of Understanding the NEC, Volume 1 Part 4: Rules Figure Wiring to be Accessible Figure Boxes, conduit bodies, and handhole enclosures must be installed so that the wiring is accessible without removing any part of the building, sidewalks, paving, or earth. Figure Exception: Listed boxes and handhole enclosures can be buried if covered by gravel, light aggregate, or noncohesive granulated soil, and their location is effectively identified and accessible for excavation. Mike Holt Enterprises, Inc NEC.Code 141

4 Article 320 Introduction Armored cable is an assembly of insulated conductors, 14 AWG through 1 AWG, that are individually wrapped within waxed paper. The conductors are contained within a flexible spiral metal (steel or aluminum) sheath that interlocks at the edges. AC cable has an outside appearance like flexible metal conduit. Many electricians call this metal cable BX Uses Permitted Type AC cable is permitted only where not subject to physical damage in the following locations, and in other locations and conditions not prohibited by or elsewhere in the Code: (1) Exposed and concealed, (2) Cable trays, (3) Dry locations, (4) Embedded in plaster or brick, except in damp or wet locations, and (5) Air voids where not exposed to excessive moisture or dampness Uses Not Permitted Type AC cable cannot be installed in the following locations: (1) In theaters and similar locations, except as permitted by 518.4(A), (2) In motion picture studios, (3) In any hazardous (classified) location, except as permitted by (B)(3), (B)(3), and , (4) Where exposed to corrosive fumes or vapors, (5) Embedded in plaster finish on brick or other masonry in damp or wet locations. Author s Comment: Type AC cable is permitted in other environmental air spaces [300.22(C)(1)]. Mike Holt Enterprises, Inc NEC.Code 142

5 Article 330 Introduction Metal-clad cable encloses one or more insulated conductors in a metal sheath of either corrugated or smooth copper or aluminum tubing, or spiral interlocked steel or aluminum. The physical characteristics of MC cable make it a versatile wiring method that can be used in almost any location and for almost any application. The most common type of MC cable is the interlocking type, which looks similar to armored cable or flexible metal conduit Uses Permitted (A) General Uses. Type MC cable is permitted only where not subject to physical damage, and in other locations and conditions not prohibited by , or elsewhere in the Code: (1) In branch circuits, feeders and services. (2) In power, lighting, control, and signal circuits. (3) Indoors or outdoors. (4) Exposed or concealed. (5) Directly buried (if identified for the purpose). (6) In a cable tray. (7) In a raceway. (8) As aerial cable on a messenger. (9) In hazardous (classified) locations as permitted in (B), (B), and (10) Embedded in plaster or brick. (11) In wet locations, if one or more of the following are met: a. The metallic covering is impervious to moisture. b. A lead sheath or moisture-impervious jacket is provided under the metal covering. c. The insulated conductors under the metallic covering are listed for use in wet locations. (12) Where single-conductor cables are used, all ungrounded conductors and, where used, the grounded neutral conductor must be grouped together to minimize induced voltage on the sheath [300.3(B)]. (B) Specific Uses. Type MC cable can be installed in compliance with Parts II and III of Article 725 and as applicable, and in accordance with (1) through (4). (1) Cable Tray. Type MC cable installed in cable tray must comply with 392.3, 392.4, 392.6, and through (2) Direct Buried. Direct-buried cable must comply with or , as appropriate. (3) Installed as Service-Entrance Cable. Type MC cable is permitted for service entrances, when installed in accordance with (4) Installed Outside of Buildings or as Aerial Cable. Type MC cable installed outside of buildings must comply with the requirements contained in , , and Author s Comment: Type MC cable is permitted in other environmental air spaces [300.22(C)(1)] Uses Not Permitted Type MC cable cannot be used where exposed to the following destructive or corrosive conditions, unless the metallic sheath is suitable for the conditions or is protected by material suitable for the conditions: (1) Subject to physical damage. (2) Direct burial in the earth, if not identified for this purpose [330.10(A)(5)]. (3) In concrete. FPN: Type MC cable identified for direct burial is suitable for installation in concrete. (4) Where subject to cinder fills, strong chlorides, caustic alkalis, or vapors of chlorine or of hydrochloric acids. Mike Holt Enterprises, Inc NEC.Code 143

6 Article 334 Introduction Nonmetallic-sheathed cable is a wiring type enclosing two or three insulated conductors, 14 AWG through 2 AWG, within a nonmetallic outer cover. Because this cable is nonmetallic, it contains a separate equipment grounding conductor.nm cable is a common wiring method used for residential and commercial branch circuits. Many electricians call this wiring Romex Uses Permitted Type NM and Type NMC cables can be used in the following: (1) One- and two-family dwellings. Figure Figure (3) Other structures permitted to be of Types III, IV, and V construction, except as prohibited in Cables must be concealed within walls, floors, or ceilings that provide a thermal barrier of material with at least a 15-minute finish rating as identified in listings of fire-rated assemblies. Figure Figure Figure (2) Multifamily dwellings permitted to be of Types III, IV, and V construction. Figure Author s Comment: See Article 100 for the definition of Concealed. Mike Holt Enterprises, Inc NEC.Code 144

7 Top 101 Rules of Understanding the NEC, Volume 1 Part 4: Rules FPN No. 1: Building constructions are defined in NFPA 220, Standard on Types of Building Construction, the applicable building code, or both. FPN No. 2: See Annex E for determination of building types [NFPA 220, Table 3-1]. (4) Cable trays, where the cables are identified for this use. FPN: See for temperature limitation of conductors Uses Not Permitted (A) Types NM and NMC. (1) In any dwelling or structure not specifically permitted in (1), (2), and (3). (2) Exposed in dropped or suspended ceilings in other than one- and two-family and multifamily dwellings. Figure (3) As service-entrance cable. (4) In commercial garages having hazardous (classified) locations as defined in (5) In theaters and similar locations, except where permitted in 518.4(B). (6) In motion picture studios. (7) In storage battery rooms. (8) In hoistways or on elevators or escalators. (9) Embedded in poured cement, concrete, or aggregate. (10) In hazardous (classified) locations, except where permitted by the following: a (B)(3) b (B)(3) c (B) Type NM. Type NM cables cannot be used under the following conditions or in the following locations: (1) Where exposed to corrosive fumes or vapors. (2) Where embedded in masonry, concrete, adobe, fill, or plaster. (3) In a shallow chase in masonry, concrete, or adobe and covered with plaster, adobe, or similar finish. (4) Where subject or exposed to excessive moisture or dampness. Author s Comment: Type NM cable isn t permitted in ducts, plenums, or other environmental air spaces [300.22] or for wiring in patient care areas [517.13]. Figure Mike Holt Enterprises, Inc NEC.Code 145

8 Article 338 Introduction Service-entrance cable can be a single conductor or multiconductor assembly with an overall covering. This cable is used primarily for services not over 600V, but can also be used for feeders and branch circuits Uses Permitted (A) Service-Entrance Conductors. Service-entrance cable used as service-entrance conductors must be installed in accordance with Article 230. Type USE used for underground service laterals can emerge from the ground if protected in accordance with 300.5(D). (B) Branch Circuits or Feeders. (1) Insulated Conductors. Type SE cable is permitted in wiring systems where all of the circuit conductors of the cable are of the rubber-covered or thermoplastic type. (2) Uninsulated Conductor. Type SE cable is permitted for use where the insulated conductors are used for circuit wiring and the uninsulated conductor is only used for equipment grounding (bonding). Figure Exception: The uninsulated conductor can be used for the grounded neutral conductors when in compliance with , , and through Author s Comment: USE cable cannot be used for interior wiring because it doesn t have flame-retardant insulation. (3) Temperature Limitations. Type SE cable used to supply appliances cannot be subjected to conductor temperatures exceeding its insulation rating. (4) Installation Methods for Branch Circuits and Feeders. Type SE cable used for branch circuits or feeders must comply with (a) and (b). (a) Interior Installations. Type SE cable used for interior branch circuit of feeder wiring must be installed in accordance with Parts I and II of Article 334, excluding Author s Comment: This means that when Type SE cables are used for interior branch circuits or feeders, the 60 C ampacity limitation of Type NM cable contained in doesn t apply and the conductors can be sized to the terminal ratings in accordance with (C). Figure Figure Figure Mike Holt Enterprises, Inc NEC.Code 146

9 Top 101 Rules of Understanding the NEC, Volume 1 Part 4: Rules Question: What size Type SE cable is required to supply a 10 kw, 240V single-phase fixed space heater with a 3A blower motor? The terminals are rated 75 C. (a) 2 AWG (b) 4 AWG (c) 6 AWG (d) 8 AWG Answer: (b) 4 AWG Step 1: Step 2: Determine the Total Load in Amperes I = VA/E I = 10,000W/240V + 3A I = 44.67A Size Conductor and Protection. According to 424.3(B), the ungrounded conductors and overcurrent protection device for electric space-heating equipment must be sized no less than 125 percent of the total heating load A x 1.25 = 56A 6 AWG, rated 65A at 75 C would be required with a 60A protection device (b) Exterior Installations. Service-entrance cable used for exterior branch circuits or feeders must be installed in accordance with Article 225. Author s Comment: Type SE cable isn t permitted in ducts, plenums, other environmental air spaces [300.22], or in patient care areas [517.13]. FPN: See for temperature limitation of conductors. Mike Holt Enterprises, Inc NEC.Code 147

10 Article 362 Introduction Electrical nonmetallic tubing is a pliable, corrugated, circular raceway made of polyvinyl chloride (PVC). In some parts of the country, this raceway is called Smurf pipe, because when it originally came out, at the height of popularity of the children s characters the Smurfs, it was available only in blue Uses Not Permitted (1) In hazardous (classified) locations, except as permitted by and (A)(1). (2) For the support of luminaires or equipment. See (3) Where the ambient temperature exceeds 50 C (122 F). (4) To contain conductors that operate at a temperature above the temperature rating of the raceway. Figure (6) As a wiring method for systems over 600V. (7) Exposed in buildings over three floors, except as permitted by (2) and (5) Ex. (8) In assembly occupancies or theaters, except as permitted by and (9) Exposed to the direct rays of the sun for an extended period, unless listed as sunlight resistant. Author s Comment: Exposing electrical nonmetallic tubing to direct rays of the sun for an extended time may result in the product becoming brittle, unless listed to resist the effects of ultraviolet (UV) radiation. Figure Figure Figure Exception: Conductors rated at a temperature above the electrical nonmetallic tubing temperature rating are permitted, provided the conductors do not operate at a temperature above the electrical nonmetallic tubing listed temperature rating. (5) For direct earth burial. Author s Comment: Electrical nonmetallic tubing can be encased in concrete [362.10(6)]. (10) Where subject to physical damage. Author s Comment: Electrical nonmetallic tubing is prohibited as a wiring method in ducts, plenums, and other environmental air handling spaces [300.22] and for patient care area circuits in health care facilities [517.13(A)]. Mike Holt Enterprises, Inc NEC.Code 148

11 Article 376 Introduction A metal wireway is a sheet metal trough with hinged or removable covers. Conductors and cables are placed in it after the wireway has been installed as a complete system.rule Uses Not Permitted. (1) Subject to severe physical damage. (2) Subject to corrosive environments. Mike Holt Enterprises, Inc NEC.Code 149

12 Article 404 Introduction The requirements of Article 404 apply to switches of all types, such as snap (toggle) switches, dimmers, fan switches, knife switches, circuit breakers used as switches, and automatic switches such as time clocks and timers, including switches and circuit breakers used for disconnecting means Switch Cover Plates (Faceplate) (A) Mounting. Faceplates for switches must be installed so that they completely cover the outlet box opening, and where flush mounted, the faceplate must seat against the wall surface. (B) Grounding (Bonding). The metal mounting yokes for switches, dimmers, and similar control switches, must be grounded (bonded) to an effective ground-fault current path, whether or not a metal faceplate is installed. The metal mounting yoke must be grounded (bonded) by one of the following means: Figure (1) Mounting Screw. The switch is mounted with metal screws to a metal box. Figure Author s Comment: Direct metal-to-metal contact between the device yoke of a switch and the box isn t required. (2) Equipment Bonding Conductor. An equipment grounding (bonding) conductor, or equipment bonding jumper is connected to the grounding terminal of the metal mounting yoke. Figure Exception: The metal mounting yoke of a replacement switch isn t required to be bonded to an effective ground-fault current path at an existing installation where no bonding means exists in the outlet box, but only if the switch faceplate is nonmetallic or the replacement switch is GFCI protected. Figure Mike Holt Enterprises, Inc NEC.Code 150

13 Article 406 Introduction This Article contains requirements for the rating, type, and installation of receptacles, cord connectors, and attachment plugs (cord caps) Receptacles in Damp or Wet Locations (A) Damp Locations. Receptacles installed outdoors under roofed open porches, canopies, marquees, and the like, and not subject to beating rain or water runoff or in other damp locations, must be installed in an enclosure that is weatherproof when the attachment plug cap isn t inserted and receptacle covers are closed. Figure (B) Receptacles in Wet Locations. (1) 15 and 20A Receptacles. All 15 and 20A, 125V and 250V receptacles installed in a wet location must be within an enclosure that is weatherproof even when an attachment plug is inserted. Figures and Figure Figure A receptacle installed within an enclosure that is weatherproof when an attachment plug is inserted is also suitable for a damp location. Author s Comment: See Article 100 for the definition of Location, Damp. Figure Mike Holt Enterprises, Inc NEC.Code 151

14 Top 101 Rules of Understanding the NEC, Volume 1 Part 4: Rules (2) Other Receptacles. Receptacles rated other than 15 or 20A, 125V and 250V installed in a wet location must comply with (a) or (b): (a) Wet Location Cover. A receptacle installed in a wet location, where the load isn t attended while in use, must have an enclosure that is weatherproof with the attachment plug cap inserted or removed. (b) Damp Location Cover. A receptacle installed in a wet location for use with portable tools can have an enclosure that is weatherproof when the attachment plug is removed. (C) Bathtub and Shower Space. Receptacles must not be installed within or directly over a bathtub or shower stall. Figure Author s Comment: Receptacles must be located no less than 5 ft from any spas or hot tubs [680.22(A)(1) and (A)(1)]. Hydromassage bathtubs are treated like bathtubs [680.70]. Figure (E) Flush Mounting with Faceplate. The enclosure for a receptacle installed in an outlet box that is flush-mounted on a finished surface must be made weatherproof by a weatherproof faceplate that provides a watertight connection between the plate and the finished surface. Mike Holt Enterprises, Inc NEC.Code 152

15 Article 408 introduction This Article contains requirements for switchboards, panelboards, and distribution boards that control light and power circuits Circuit Directory or Circuit Identification Unused Openings Unused openings for circuit breakers and switches must be closed using identified closures, or other means approved by the authority having jurisdiction, that provide protection substantially equivalent to the wall of the enclosure. Figure All circuits and circuit modifications must be legibly identified as to their clear, evident, and specific purpose. The identification must include sufficient detail to allow each circuit to be distinguished from all others, and the identification must be on a circuit directory located on the face or inside of the door of a panelboard. See Figure Figure Figure Mike Holt Enterprises, Inc NEC.Code 153

16 Article 422 Introduction This Article contains requirements for electric appliances used in any occupancy Permanently Connected Appliance Disconnect (A) Appliance Rated at Not Over 300 VA or 1 8 Horsepower. The branch-circuit overcurrent device, such as a plug fuse or circuit breaker, can serve as the appliance disconnect. (B) Appliance Rated Over 300 VA or 1 8 Horsepower. A switch or circuit breaker located within sight from the appliance can serve as the appliance disconnecting means. If the switch or circuit breaker is capable of being locked in the open position, it does not need to be within sight if the provision for locking or adding a lock is on the disconnecting means. Figure Cord-and-Plug Connected Appliance Disconnect (A) Attachment Plug and Receptacle. An accessible plug and receptacle can serve as the disconnecting means for a cordand-plug connected appliance. Figure (B) Cord-and-Plug Connected Range. The plug and receptacle of a cord-and-plug connected household electric range can serve as the range disconnecting means if the plug is accessible from the front of the range by the removal of a drawer. Figure Figure Figure Author s Comment: Within sight is visible and not more than 50 ft from one to the other [Article 100]. Figure Mike Holt Enterprises, Inc NEC.Code 154

17 Article 430 Introduction This is the motor Article. It contains the specific rules for motor installations, addressing such issues as conductor sizing, overcurrent protection, control circuit conductors, motor controllers, and disconnecting means. Installation requirements for motor control centers are covered in , and air-conditioning and refrigerating equipment are covered in Article Table FLC Versus Motor Nameplate Current Rating (A) General Requirements. (1) Table Full-Load Current (FLC). The motor full-load current ratings listed in Tables , , and are used to determine the conductor ampacity [430.22], the branch-circuit short-circuit and ground-fault protection device size [ and 62], and the ampere rating of disconnecting switches [ ]. Author s Comment: The actual current rating on the motor nameplate full-load amperes (FLA) [430.6(A)(2)] is not permitted to be used to determine the conductor ampacity, the branchcircuit short-circuit and ground-fault protection device size, nor the ampere rating of disconnecting switches. Figure Motors built to operate at less than 1,200 RPM or that have high torques may have higher full-load currents, and multispeed motors will have full-load current varying with speed, in which case the nameplate current ratings must be used. Exception 3: For a listed motor-operated appliance, the motor full-load current marked on the nameplate of the appliance must be used instead of the horsepower rating on the appliance nameplate to determine the ampacity or rating of the disconnecting means, the branch-circuit conductors, the controller, and the branch-circuit short-circuit and ground-fault protection. (2) Motor Nameplate Current Rating (FLA). Overload devices must be sized based on the motor nameplate current rating in accordance with Author s Comment: The motor nameplate full-load ampere rating is identified as full-load amperes (FLA). The FLA rating is the current in amperes that the motor draws while producing its rated horsepower load at its rated voltage, based on its rated efficiency and power factor. Figure Figure Figure Mike Holt Enterprises, Inc NEC.Code 155

18 Top 101 Rules of Understanding the NEC, Volume 1 Part 4: Rules The actual current drawn by the motor depends upon the load on the motor and on the actual operating voltage at the motor terminals. That is, if the load increases, the current also increases, or if the motor operates at a voltage below its nameplate rating, the operating current will increase. Caution: To prevent damage to motor windings from excessive heat (caused by excessive current), never load a motor above its horsepower rating and/or be sure the voltage source matches the motor s voltage rating Single Motor Conductor Size (A) Conductor Size. Conductors to a single motor must be sized not smaller than 125 percent of the motor FLC rating as listed in: Figure Figure Note: The branch-circuit short-circuit and ground-fault protection device using an inverse-time breaker is sized at: 22A x 2.5 = 55A, next size up = 60A [240.6(A) and (C)(1) Exception 1] Branch-Circuit Short-Circuit and Ground-Fault Protection (A) General. The motor branch-circuit short-circuit and ground-fault protective device must comply with (B) and (C). Figure (B) All Motors. A motor branch-circuit short-circuit and ground-fault protective device must be capable of carrying the motor s starting current. (C) Rating or Setting. Table Direct Current Motors Table Single-Phase Motors Table Three-phase motors Question: What size branch-circuit conductor is required for a hp, 230V three-phase motor? Figure (a) 14 AWG (c) 10 AWG Answer: (c) 10 AWG (b) 12 AWG (d) none of these Motor FLC = 22A [Table ] Conductor s Size = 22A x 1.25 Conductor s Size = 27.5A, 10 AWG, rated 30A at 75 C [Table ] (1) Table Each motor branch circuit must be protected against short circuit and ground faults by a protection device sized no greater than the following percentages listed in Table Table Circuit Nontime Dual-Element Inverse- Motor Type Delay Fuse Time Breaker Wound Rotor 150% 150% 150% Direct Current 150% 150% 150% All Other Motors 300% 175% 250% Mike Holt Enterprises, Inc NEC.Code 156

19 Top 101 Rules of Understanding the NEC, Volume 1 Part 4: Rules Question: What size conductor and inverse-time circuit breaker are required for a 2 hp, 230V single-phase motor? Figure (a) 14 AWG, 30A breaker (c) 14 AWG, 40A breaker (b) 14 AWG, 35A breaker (d) none of these Question: What size conductor and inverse-time circuit breaker are required for a hp, 230V three-phase motor? Figure (a) 10 AWG, 50A breaker (c) a or b (b) 10 AWG, 60A breaker (d) none of these Figure Figure Answer: (a) 14 AWG, 30A breaker Step 1. Step 2. Branch-Circuit Conductor [Table , (A), and Table ] 12A x 1.25 = 15A, 14 AWG, rated 20A at 75 C [Table ] Branch-Circuit Protection [240.6(A), (C)(1), and Table ] 12A x 2.5 = 30A Author s Comment: I know it bothers many in the electrical industry to see a 14 AWG conductor protected by a 30A circuit breaker, but branch-circuit conductors are protected against overloads sized between 115 and 125 percent of the motor nameplate current rating [430.32]. See 240.4(A) and 240.4(G) for details. Exception 1: Where the motor short-circuit and ground-fault protection device values derived from Table don t correspond with the standard overcurrent device ratings listed in 240.6(A), the next higher protection device rating can be used. Answer. (c) 10 AWG, 50 or 60A breaker Step 1. Branch-Circuit Conductor [Table , (A), and Table ] 22A x 1.25 = 27.5A, 10 AWG, rated 30A at 75 C [Table ] Step 2. Branch-Circuit Protection [240.6(A), (C)(1) Exception 1, and Table ] 22A x 2.5 = 55A, next size up = 60A Disconnect for Control Circuit (A) Control Circuit Disconnect. Motor control circuit conductors must have a disconnecting means that opens all sources of supply when the disconnecting means is in the open position. If the control circuit conductors are tapped from the controller disconnect, the controller disconnecting means can serve as the disconnecting means for the control circuit conductors [ (A)]. If the control circuit conductors aren t tapped from the controller disconnect, a separate disconnecting means is required for the control circuit conductors, and it must be located adjacent to the controller disconnect. Figure Mike Holt Enterprises, Inc NEC.Code 157

20 Top 101 Rules of Understanding the NEC, Volume 1 Part 4: Rules The controller disconnecting means must simultaneously open all ungrounded conductors of the circuit [ ]. Figure Figure Figure Disconnect Requirement (A) Controller Disconnect. A disconnecting means is required for each motor controller and it must be located within sight from the controller. Figure Author s Comment: The controller disconnecting means can serve as the disconnecting means for the motor control circuit conductors [430.74], as well as for the motor [ (B)]. (B) Motor Disconnect. A disconnecting means is required for each motor and it must be located in sight from the motor location and the driven machinery location. Figure Figure Figure Author s Comment: Within sight is visible and not more than 50 ft from each other [Article 100]. Mike Holt Enterprises, Inc NEC.Code 158

21 Top 101 Rules of Understanding the NEC, Volume 1 Part 4: Rules Exception: A motor disconnecting means isn t required to be within sight from the motor under either condition (a) or (b), if the controller disconnecting means [ (A)] is capable of being locked in the open position and the provision for locking or adding a lock is permanently installed on the controller disconnect. Figure (a) Where locating the disconnecting means is impracticable or introduces additional or increased hazards to persons or property. (b) In industrial installations, with written safety procedures, where conditions of maintenance and supervision ensure that only qualified persons will service the equipment. Author s Comment: See Article 100 for the definition of Within Sight. FPN 2: For information on lockout/tagout procedures, see NFPA 70E, Standard for Electrical Safety in the Workplace. Figure Mike Holt Enterprises, Inc NEC.Code 159

22 Article 440 introduction This Article applies to electrically driven air-conditioning and refrigeration equipment that has a hermetic refrigerant motor-compressor. The rules in this Article are in addition to, or amend, the rules in Article 430 and other Articles Short-Circuit and Ground-Fault Protection Device Size Short-circuit and ground-fault protection for air-conditioning and refrigeration equipment must be sized no larger than identified on the equipment s nameplate. Figure (A) One Motor-Compressor. The short-circuit and groundfault protection device must not be greater than 175 percent of the motor-compressor current rating. If the protection device sized at 175 percent isn t capable of carrying the starting current of the motor-compressor, the next size larger protection device can be used, but in no case can it exceed 225 percent of the motor-compressor current rating. Question: What size conductor and protection is required for a 24A motorcompressor connected to a 240V circuit? Figure (a) 10 AWG, 40A (c) a or b (b) 10 AWG, 60A (d) none of these Figure Answer: (a) 10 AWG, 40A Figure If the equipment doesn t have a nameplate specifying the size and type of protection device, then the protection device must be sized in accordance with (A) or (B). Step 1. Branch-Circuit Conductor [Table and ] 24A x 1.25 = 30A, 10 AWG, rated 30A at 75 C [Table ] Step 2. Branch-Circuit Protection [240.6(A) and (A)] 24A x 1.75 = 42A, next size down = 40A If the 40A protection device isn t capable of carrying the starting current, then the protection device can be sized up to 225 percent of the equipment load current rating. 24A x 2.25 = 54A, next size down 50A (B) Rating for Equipment. Where the equipment incorporates more than one hermetic refrigerant motor-compressor, or a hermetic refrigerant motor-compressor and other motors Mike Holt Enterprises, Inc NEC.Code 160

23 Top 101 Rules of Understanding the NEC, Volume 1 Part 4: Rules or other loads, the equipment short-circuit and ground-fault protection must be sized as follows: (1) Motor-Compressor Largest Load. The rating of the branch-circuit short-circuit and ground-fault protective device must not be greater than the largest motor-compressor short-circuit ground-fault protection device, plus the sum of the rated-load currents of the other compressors. Author s Comment: The branch-circuit conductors are sized at 125 percent of the larger motor-compressor current, plus the sum of the rated-load currents of the other compressors [440.33] Conductor Size One Motor-Compressor If equipment doesn t have a nameplate identifying the minimum circuit ampacity, the branch-circuit conductors to a single motor-compressor must have an ampacity not less than 125 percent of the motor-compressor rated-load current or the branch-circuit selection current, whichever is greater. Author s Comments: In accordance with (A), branch-circuit conductors must have branch-circuit protection sized between 175 percent and 225 percent of the rated-load current to provide protection against short circuits and ground faults. In accordance with (A), branch-circuit conductors must have branch-circuit protection sized between 175 percent and 225 percent of the rated-load current to provide protection against short circuits and ground faults. Question: What size conductor and protection device is required for an 18A motor compressor? Figure (a) 12 AWG, 30A (c) a or b (b) 10 AWG, 50A (d) none of these Figure Answer: (a) 12 AWG, 30A Step 1: Branch-Circuit Conductor [Table and ] 18A x 1.25 = 22.5A, 12 AWG, rated 25A at 75 C [Table ] Step 2.: Branch-Circuit Protection [240.6(A) and (A)] 18A x 1.75 = 31.5A, next size down = 30A If the 30A protection device isn t capable of carrying the starting current, then the protection device can be sized up to 225 percent of the equipment load current rating. 18A x 2.25 = 40.5A, next size down 40A Author s Comment: A 30A or 40A protection device is permitted to protect a 12 AWG conductor. See 240.4(A) and 240.4(G) for details. Mike Holt Enterprises, Inc NEC.Code 161

24 Article 450 Introduction This Article contains requirements for the installation of all transformers Overcurrent Protection Overcurrent protection of the primary winding of a transformer not exceeding 600V must comply with (B). FPN 2: 4-wire three-phase 120/208V or 277/480V systems that supply nonlinear line-to-neutral loads can overheat because of triplen harmonic currents (3rd, 9th, 15th, 21st, etc.) [450.9 FPN 2]. Figure Table 450.3(B) Primary Protection only Primary Current Rating Maximum Protection 9A or More 125%, see Note 1 Less Than 9A 167% Less Than 2A 300% Note 1. Where 125 percent of the primary current doesn t correspond to a standard rating of a fuse or nonadjustable circuit breaker, the next higher rating is permitted [240.6(A)]. Question: What is the primary protection device rating and conductor size required for a 45 kva, three-phase, 480V 120/208V transformer that is fully loaded? Terminals are rated 75 C. Figure (a) 8 AWG, 40A (c) 6 AWG, 60A (b) 6 AWG, 50A (d) 4 AWG, 70A Figure Author s Comment: For more information on this subject, visit (B) Overcurrent Protection for Transformers Not Over 600V. The primary winding of a transformer must be protected against overcurrent in accordance with the percentages listed in Table 450.3(B) and all applicable notes. Figure Mike Holt Enterprises, Inc NEC.Code 162

25 Top 101 Rules of Understanding the NEC, Volume 1 Part 4: Rules Answer: (d) 70A Step 1: Step 2: Step 3: Step 4: Primary current I = VA/(E x 1.732) I = 45,000 VA/(480V x 1.732) I = 54A The primary protection device rating [240.6(A)] 54A x 1.25 = 68A, next size up 70A, Note 1 The primary conductor must be sized to carry 54A continuously (54A x 1.25 = 68A) [215.2(A)(1)] and be protected by a 70A protection device [240.4(A)]. A 4 AWG conductor rated 85A at 75 C meets all of the requirements [110.14(C)(1) and ]. Secondary current I = VA/(E x 1.732) I = 45,000 VA/ (208V x 1.732), = 125A Author s Comment: Secondary conductors having a maximum length of 25 ft that terminate in an overcurrent protection device that doesn t exceed the ampacity of the conductors, must be sized at 125 percent of the continuous load [215.2(A)(1) and (C)(6)]. Question: What is the secondary conductor size required for a 45 kva, three-phase, 480V 120/208V transformer, that supplies a 200A lighting and appliance panelboard that is fully loaded? Terminals are rated 75 C. Figure (a) 1 AWG (b) 1/0 AWG (c) 2/0 AWG (d) 3/0 AWG Answer: (c) 2/0 AWG Step 1: Secondary current I = VA/(E x 1.732) I = 45,000 VA/(208V x 1.732) I = 125A Figure Step 2: Secondary conductors must be sized to 125 percent of the continuous load [215.2(A)(1)]. 125A x 1.25 = 156A, 2/0 AWG rated 175A at 75 C termination Secondary conductors must terminate in an overcurrent protection device that doesn t exceed the ampacity of the conductors [240.21(C)(6)]. 2/0 AWG, rated 175A at 75 C, terminating on a 175A protection device meets this requirement. Mike Holt Enterprises, Inc NEC.Code 163

Chapter 2 Wiring and Protection Article 200 Use and Identification of Grounded Neutral Conductor Chapter 1 General...9

Chapter 2 Wiring and Protection Article 200 Use and Identification of Grounded Neutral Conductor Chapter 1 General...9 Article 90 Introduction...1 90.1 Purpose of the NEC...1 90.2 Scope of the NEC...2 90.3 Code Arrangement...4 90.4 Enforcement...5 90.5 Mandatory Requirements and Explanatory Material...6 90.6 Formal Interpretations...6

More information

Continued from Part 2 Rules

Continued from Part 2 Rules Continued from Part 2 Rules 26 50. 51 250.94 Grounding (Bonding) of Communications Systems An accessible bonding point must be provided at service equipment or the disconnecting means of separate buildings

More information

NEC 2011 Code Changes

NEC 2011 Code Changes NEC 2011 Code Changes Articles 280.21-300.50 CHANGES FROM 2008 TO 2011 CODE ARE IN RED Chapter 2 - Wiring and Protection ARTICLE 280 Surge Arresters, Over 1kV III. Connecting Surge Arresters 280.21 Connection

More information

NEC 2014 Code Changes

NEC 2014 Code Changes NEC 2014 Code Changes Articles 310 310.120 CHANGES FROM 2011 TO 2014 CODE ARE IN RED ARTICLE 310 Conductors for General Wiring I. General 310.2 Definitions Electrical Ducts Electrical conduits, or other

More information

2011 NEC Code Updates Part 3

2011 NEC Code Updates Part 3 www.garyklinka.com Page 1 of 22 Instructions: Fee $35 1. Print these pages. 2. Circle the correct answers and transfer them to the answer sheet. 3. Page down to the last page for the verification forms

More information

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 2/8/12 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 2/8/12 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions MECKLENBURG COUNTY Land Use and Environmental Service Agency Code Enforcement 2/8/12 ELECTRICAL CONSISTENCY MEETING Code Consistency Questions 1. I am inspecting a building addition. They have a 480V to

More information

ECET Circuit Design Motor Loads. Branch Circuits. Article 210

ECET Circuit Design Motor Loads. Branch Circuits. Article 210 ECET 4520 Industrial Distribution Systems, Illumination, and the NEC Circuit Design Motor Loads Branch Circuits Article 210 210.1 Scope This article covers branch circuits except for those that supply

More information

CHAPTER V RESIDENTIAL WIRING

CHAPTER V RESIDENTIAL WIRING CHAPTER V RESIDENTIAL WIRING 5.1. THE SERVICE ENTRANCE Buildings and other structures receive the electrical energy through the service entrance. In residential wiring, the electric company supply this

More information

Mecklenburg County Common Code Defects

Mecklenburg County Common Code Defects Electrical Code Defects Improper Over Current Protection Code Description 310.15 Ampacities for s Rated 0 2000 Volts. (A) General. (1) Tables or Engineering Supervision. Ampacities for conductors shall

More information

TABLE OF CONTENTS CHAPTER 1 ELECTRICAL THEORY About This Textbook...xi. Passing Your Exam...xiv. How to Use the National Electrical Code...

TABLE OF CONTENTS CHAPTER 1 ELECTRICAL THEORY About This Textbook...xi. Passing Your Exam...xiv. How to Use the National Electrical Code... TABLE OF CONTENTS About This Textbook...xi Passing Your Exam...xiv How to Use the National Electrical Code... 1 CHAPTER 1 ELECTRICAL THEORY... 7 Unit 1 Electrician s Math and Basic Electrical Formulas...

More information

Spring Test 10 due 05/11/2013

Spring Test 10 due 05/11/2013 Spring Test 10 due 05/11/2013 Multiple Choice Identify the letter of the choice that best completes the statement or answers the question. 1. When installed in an agricultural building that houses livestock

More information

TEMPORARY ELECTRIC WIRING FOR CARNIVALS, CONVENTIONS, EXHIBITIONS, FAIRS AND SIMILAR USES

TEMPORARY ELECTRIC WIRING FOR CARNIVALS, CONVENTIONS, EXHIBITIONS, FAIRS AND SIMILAR USES INFORMATION BULLETIN / PUBLIC - ELECTRICAL CODE REFERENCE NO.: LAMC 93.0230 Effective: 3-24-69 DOCUMENT NO. P/EC 2002-006 Revised: 11-17-00 Previously Issued As: RGA #7-69 TEMPORARY ELECTRIC WIRING FOR

More information

CHAPTER 10 ELECTRICAL. Notes:

CHAPTER 10 ELECTRICAL. Notes: CHAPTER 10 ELECTRICAL 1001.0 General Requirements. Electrical wiring and equipment shall comply with the requirements of NFPA 70, National Electrical Code (NEC), or local ordinances. 1002.0 Solar Photovoltaic

More information

TABLE OF CONTENTS. About the Mike Holt Enterprises Team... xviii CHAPTER 1 ELECTRICAL THEORY... 1

TABLE OF CONTENTS. About the Mike Holt Enterprises Team... xviii CHAPTER 1 ELECTRICAL THEORY... 1 TABLE OF CONTENTS Introduction...xv About the Mike Holt Enterprises Team... xviii CHAPTER 1 ELECTRICAL THEORY... 1 Unit 1 Electrician s Math and Basic Electrical Formulas... 1 Part A Electrician s Math...

More information

Spring Test 7 due 05/03/2013

Spring Test 7 due 05/03/2013 Spring Test 7 due 05/03/2013 Multiple Choice Identify the choice that best completes the statement or answers the question. 1. A raceway contains two 3-phase, 3-wire circuits that supply 38 ampere continuous

More information

Have You Been Grounded Lately

Have You Been Grounded Lately Have You Been Grounded Lately Thurs, Oct. 26, 2017 9:15-10:15 Phil Simmons Author, Electrical Grounding and Bonding Author Cengage Learning Phil Simmons Have You Been Grounded Lately 2017 NEC Changes Relative

More information

Table of Contents. Unit 3 Magnetism Unit 1 Matter Unit 4 Electricity Unit 2 Electron Theory Unit 5 Electromagnetism...

Table of Contents. Unit 3 Magnetism Unit 1 Matter Unit 4 Electricity Unit 2 Electron Theory Unit 5 Electromagnetism... Introduction...x How to Use This Textbook...xi About the Author...xii About the Graphic Illustrator...xiii Mike Holt Enterprises Team...xiv Chapter 1 Electrical Fundamentals... 1 Unit 1 Matter... 3 Introduction...

More information

Electrical Tech Note 111 Biosystems & Agricultural Engineering Department Michigan State University

Electrical Tech Note 111 Biosystems & Agricultural Engineering Department Michigan State University Electrical Tech Note 111 Biosystems & Agricultural Engineering Department Michigan State University Electrical Code Changes in Michigan 1 (Based on Part 8, P.A. 230, the 2005 NEC and the 2003 MRC) This

More information

SUPPLEMENTAL CORRECTION SHEET FOR SOLAR PHOTOVOLTAIC SYSTEMS - ELECTRICAL

SUPPLEMENTAL CORRECTION SHEET FOR SOLAR PHOTOVOLTAIC SYSTEMS - ELECTRICAL SUPPLEMENTAL CORRECTION SHEET FOR SOLAR PHOTOVOLTAIC SYSTEMS - ELECTRICAL This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly.

More information

2014 NEC Changes Part 4

2014 NEC Changes Part 4 www.garyklinka.com Page 1 of 14 Instructions: Fee $25 1. Print these pages. 2. Circle the correct answers and transfer them to the answer sheet. 3. Page down to the last page for the verification forms

More information

Table of Contents. CHAPTER 1 ElECTRiCAl THEoRY Mike Holt enterprises, inc neC.Code ( )

Table of Contents. CHAPTER 1 ElECTRiCAl THEoRY Mike Holt enterprises, inc neC.Code ( ) CHAPTER 1 ElECTRiCAl THEoRY... 1 UniT 1 electrician s MaTH and BasiC electrical formulas... 3 Introduction to Unit 1... 3 Part A Electrician s Math... 3 Introduction... 3 1.1 Whole Numbers... 3 1.2 Decimals...

More information

2016 Photovoltaic Solar System Plan Review List

2016 Photovoltaic Solar System Plan Review List Building Division 555 Santa Clara Street Vallejo CA 94590 707.648.4374 2016 Photovoltaic Solar System Plan Review List GENERAL PROJECT INFORMATION PLAN CHECK NO DATE JOB ADDRESS CITY ZIP REVIEWED BY PHONE

More information

WIRING DESIGN & PROTECTION REQUIREMENTS CHECKLIST

WIRING DESIGN & PROTECTION REQUIREMENTS CHECKLIST WIRING DESIGN & PROTECTION REQUIREMENTS CHECKLIST Use & Identification of Grounded and Grounding Conductors YES NO N/A Grounded conductors are identifiable and distinguishable from all other conductors.

More information

(The actual state exam will be closer to 50 questions in 4 hours time) Master Electrician Practice Test

(The actual state exam will be closer to 50 questions in 4 hours time) Master Electrician Practice Test (The actual state exam will be closer to 50 questions in 4 hours time) Master Electrician Practice Test 1. Accessible as applied to wiring methods means capable of being removed or exposed without damaging

More information

90.2 Scope. The installation of electrical conductors, equipment and raceways for:

90.2 Scope. The installation of electrical conductors, equipment and raceways for: NEC Generator Primer Rules on the installation of generators and transfer switches 1 90.2 Scope The installation of electrical conductors, equipment and raceways for: public and private premises Conductors

More information

Western Section 101 st Annual Meeting Hot Springs, Arkansas September 21, 2005 Charlie Trout Code Breakfast

Western Section 101 st Annual Meeting Hot Springs, Arkansas September 21, 2005 Charlie Trout Code Breakfast Western Section 101 st Annual Meeting Hot Springs, Arkansas September 21, 2005 Charlie Trout Code Breakfast 1.Question: An add on unit for a hydromassage bathtub consists of a small 1-gallon water heater

More information

SINGLE PHASE WIRING SPECIFICATIONS

SINGLE PHASE WIRING SPECIFICATIONS SINGLE PHASE WIRING SPECIFICATIONS 1-866-MEC-ELEC (1-866-632-3532) Office Locations: Hondo Office 237 Hwy 173 N Hondo, TX 78661-0370 Fax 830.426.3335 Dilley Office 1718 W. FM 117 Dilley, TX 78017 Fax 830.965.1425

More information

WISCONSIN ELECTRICIANS

WISCONSIN ELECTRICIANS Wisconsin Contractors Institute 2017 PART 2 3 CONTINUING EDUCATION FOR WISCONSIN ELECTRICIANS 2017 NEC Code Change Part 2 8 Hours WISCONSIN CONTRACTORS INSTITUTE N16 W23217 Stone Ridge Drive, Suite 290

More information

PART A General Conductor Requirements

PART A General Conductor Requirements PART A General Conductor Requirements 6.1 Conductor Insulation Property Table 310.13 of the NEC provides information on conductor properties such as permitted use, maximum operating temperature, and other

More information

Electrical Tech Note 106

Electrical Tech Note 106 Electrical Tech Note 106 Biosystems & Agricultural Engineering Department Michigan State University Master Exam Study Guide and Sample Questions 1 Based on the 2014 NEC, Part 8 of PA 230, PA 407, and the

More information

Preface...x Chapter 1 Electrical Fundamentals

Preface...x Chapter 1 Electrical Fundamentals Preface...x Chapter 1 Electrical Fundamentals Unit 1 Matter...3 Introduction...3 1.1 Matter...3 1.2 Atomic Theory...3 1.3 Law of Electrical Charges...4 1.4 Law of Atomic Charges...5 Negative Atomic Charge...5

More information

CONTINUING EDUCATION FOR OREGON ELECTRICIANS NEC Code Change Part 2 Course # Hours

CONTINUING EDUCATION FOR OREGON ELECTRICIANS NEC Code Change Part 2 Course # Hours AMERICAN ELECTRICAL INSTITUTE 2017 PART 2 3 CONTINUING EDUCATION FOR OREGON ELECTRICIANS 2017 NEC Code Change Part 2 Course #90817 8 Hours AMERICAN ELECTRICAL INSTITUTE N16 W23217 Stone Ridge Drive, Suite

More information

2011 NEC Changes Part 2 (Homestudy) (Homestudy)

2011 NEC Changes Part 2 (Homestudy) (Homestudy) 2011 NEC Changes Part 2 (Homestudy) (Homestudy) North Carolina Electrical License This course will review the second half of the most important National Electrical Code changes from the 2011 NEC. Changes

More information

THREE PHASE WIRING SPECIFICATIONS

THREE PHASE WIRING SPECIFICATIONS THREE PHASE WIRING SPECIFICATIONS 1-866-MEC-ELEC (1-866-632-3532) Office Locations: Hondo Office 237 Hwy 173 N Hondo, TX 78661-0370 Fax 830.426.3335 Dilley Office 1718 W. FM 117 Dilley, TX 78017 Fax 830.965.1425

More information

This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly.

This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly. SUPPLEMENTAL CORRECTION SHEET FOR SOLAR PHOTOVOLTAIC SYSTEMS (ELEC) This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly.

More information

Fee $20 Course: NEC Changes 1 This course is valid for these credentials: Credential Description Cred Code Credit Hours

Fee $20 Course: NEC Changes 1 This course is valid for these credentials: Credential Description Cred Code Credit Hours www.garyklinka.com Page 1 of 18 Instructions: Fee $20 1. Print these pages. 2. Circle the correct answers and transfer them to the answer sheet. 3. Page down to the last page for the verification forms

More information

CHAPTER 10 ELECTRICAL

CHAPTER 10 ELECTRICAL 1001.0 General Requirements. 1001.1 Electrical Wiring and Equipment. Electrical wiring and equipment shall comply with the requirements of NFPA 70, National Electrical Code (NEC), or local ordinances.

More information

Definitions of and have been revised. a. automatic b. nonautomatic c. none of the above d. both a and b

Definitions of and have been revised. a. automatic b. nonautomatic c. none of the above d. both a and b www.garyklinka.com Page 1 of 12 Instructions: Fee $25 1. Print these pages. 2. Circle the correct answers and transfer them to the answer sheet. 3. Page down to the last page for the verification forms

More information

Electrical Tech Note 105 Agricultural Engineering Department Michigan State University

Electrical Tech Note 105 Agricultural Engineering Department Michigan State University Electrical Tech Note 105 Agricultural Engineering Department Michigan State University Journey Exam Study Guide and Sample Questions 1 Based on the 2002 NEC, Part 8 of PA 230, and the 2003 MRC The Journey

More information

Mike Holt s Illustrated Guide to SOLAR PV SYSTEMS

Mike Holt s Illustrated Guide to SOLAR PV SYSTEMS Mike Holt s Illustrated Guide to Directory, Identification, Label, Marking, Plaque, and Sign Requirements for SOLAR PV SYSTEMS Extracted From Mike Holt s Illustrated Guide to Understanding NEC Requirements

More information

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 9/14/11 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 9/14/11 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions MECKLENBURG COUNTY Land Use and Environmental Service Agency Code Enforcement 9/14/11 ELECTRICAL CONSISTENCY MEETING Code Consistency Questions 1. I recently installed a 45-KVA transformer, 480-volt primary

More information

Table of Contents. CHAPTER 1 BASIC ELECTRICAL THEORY (Essential for Journeyman and Master s Licensing Exams)... 1

Table of Contents. CHAPTER 1 BASIC ELECTRICAL THEORY (Essential for Journeyman and Master s Licensing Exams)... 1 Introduction... x About This Textbook...xi Passing Your Exam...xiv How to Use the National Electrical Code... xviii About the Author...xxi About the Graphic Illustrator...xxii Mike Holt Enterprises Team...

More information

Chapter 8 Interior Wiring and Lighting

Chapter 8 Interior Wiring and Lighting Chapter 8 Interior Wiring and Lighting Review Questions 1. What tool if any, is used to remove a fuse that is to be replaced? 1. Pliers 2. Screwdriver 3. Fuse puller 4. None 2. OSHA has established specific

More information

Pretest Module 24 Three-phase Service Entrance

Pretest Module 24 Three-phase Service Entrance Pretest Module 24 Three-phase Service Entrance 1. What is the most widely used three-phase service entrance system? 2. What are the three most common voltage combinations for three-phase, four-wire systems?

More information

Chapter 1 Electrical Theory...1

Chapter 1 Electrical Theory...1 Electrical Formulas with Sample Calculations Table of Contents Chapter 1 Electrical Theory...1 Unit 1 Electrician s Math and Basic Electrical Formulas...3 Part A Electrician s Math...3 1 1 Fractions...3

More information

SECTION 1: Field Inspection Guide for Rooftop Photovoltaic (PV) Systems

SECTION 1: Field Inspection Guide for Rooftop Photovoltaic (PV) Systems COUNTY OF SANTA CRUZ PLANNING DEPARTMENT 701 OCEAN STREET, 4 th FLOOR, SANTA CRUZ, CA 95060 (831) 454-2580 FAX: (831) 454-2131 TDD: (831) 454-2123 KATHLEEN MOLLOY PREVISICH, PLANNING DIRECTOR Photovoltaic

More information

Chapter 5. Imagine That Engineering Inc. Assured Equipment Grounding Conductor Program (AEGCP) Ground Fault Circuit Interrupter (GFCI)

Chapter 5. Imagine That Engineering Inc. Assured Equipment Grounding Conductor Program (AEGCP) Ground Fault Circuit Interrupter (GFCI) Chapter 5 Imagine That Engineering Inc. Assured Equipment Grounding Conductor Program (AEGCP) Ground Fault Circuit Interrupter (GFCI) Imagine That Engineering Inc. has adopted this program for equipment

More information

Generator Fire Safety: Generator assemblies should be located outside the building.

Generator Fire Safety: Generator assemblies should be located outside the building. SECTION 33 70 00 - ELECTRICAL DISTRIBUTION PACKAGED GENERATOR ASSEMBLIES Generator Fire Safety: Generator assemblies should be located outside the building. All fuel piping from the outside of the building

More information

Overcurrent Protection According to the 2011 NEC

Overcurrent Protection According to the 2011 NEC Overcurrent Protection According to the 2011 NEC Utah Electrical License This course will cover overcurrent protection according to the 2011 NEC. The key sections of Article 240 will be discussed. Overcurrent

More information

Photovoltaic Solar Plan Review

Photovoltaic Solar Plan Review PAIGE B. VAUGHAN, CBO Director of Building and Safety Phone (310) 605-5509 Fax Line (310) 605-5598 E-mail:lbutler@comptoncity.org Building & Safety Department Photovoltaic Solar Plan Review Plan Check

More information

Introduction. Nexans wire and cable. Contact us for all your wire and cable needs

Introduction. Nexans wire and cable. Contact us for all your wire and cable needs Introduction Nexans is one of the largest wire and cable manufacturers in the world, and in North America. In North America we manufacture in locations across the United States and Canada. We design and

More information

9/7/2010. Objectives. Article 90. Introduction NEC Significant Changes. Review significant revisions in the 2011 NEC

9/7/2010. Objectives. Article 90. Introduction NEC Significant Changes. Review significant revisions in the 2011 NEC 2011 NEC Significant Changes Courtesy of NJATC Courtesy of NFPA Presented By: Michael J. Johnston Executive Director of Standards and Safety, NECA Objectives Review significant revisions in the 2011 NEC

More information

UNIT 1 ELECTRICIAN S MATH AND BASIC ELECTRICAL FORMULAS...1 Introduction...1. UNIT 2 ELECTRICAL CIRCUITS...49 Introduction...49

UNIT 1 ELECTRICIAN S MATH AND BASIC ELECTRICAL FORMULAS...1 Introduction...1. UNIT 2 ELECTRICAL CIRCUITS...49 Introduction...49 UNIT 1 ELECTRICIAN S MATH AND BASIC ELECTRICAL FORMULAS...1 Introduction...1 PART A ELECTRICIAN S MATH...1 Introduction...1 1.1 Whole Numbers...1 1.2 Decimal...1 1.3 Fractions...1 1.4 Percentages...2 1.5

More information

Overcurrent Protection (2014 NEC) (Homestudy)

Overcurrent Protection (2014 NEC) (Homestudy) Overcurrent Protection (2014 NEC) (Homestudy) Oregon Electrical License The key sections of Article 240 will be discussed. Overcurrent protection for panelboards, appliances, motors, motor compressors,

More information

2014 NEC Analysis Part 2

2014 NEC Analysis Part 2 www.garyklinka.com Page 1 of 24 Instructions: Fee $65 1. Print these pages. 2. Circle the correct answers and transfer them to the answer sheet. 3. Page down to the last page for the verification forms

More information

Volume 2 Charts, Formulas, and Other Useful Information

Volume 2 Charts, Formulas, and Other Useful Information Volume 2 Charts, Formulas, and Other Useful Information Aluminum Conductor Conductor Terminations 61 Compact Aluminum (Conduit Fill Tables) 68-79 Ampacity Dwelling Services 48 1-phase Loads on a 3-phase

More information

UNDERGROUND SERVICES - SECONDARY

UNDERGROUND SERVICES - SECONDARY UNDERGROUND SERVICES - SECONDARY Contents - Underground Services... U-1 General Requirements for Underground Service...U-2 Names of Parts for Underground Service... U-3 Service Termination in a Service

More information

The Reliable Choice. Field Pocket Guide

The Reliable Choice. Field Pocket Guide The Reliable Choice Field Pocket Guide Allowable Ampacities of STABILOY Brand XHHW-2 and Copper 75 C (167 F) 90 C (194 F) 75 C (167 F) 90 C (194 F) Conductor Size (AWG or kcmil) Types RHW, THHW, THW, THWN,

More information

A Look at the 2017 NEC Significant Changes

A Look at the 2017 NEC Significant Changes A Look at the 2017 NEC Significant Changes A Look at the 2017 NEC Significant Changes Michael J. Johnston NECA James T. Dollard Local 98 Philadelphia Electrical JATC This session is eligible for 1 Continuing

More information

FOR ALL STAKEHOLDERS TO

FOR ALL STAKEHOLDERS TO Our Goal is FOR ALL STAKEHOLDERS TO HAVE A SUCCESSFUL PROJECT with us and that together we keep people and structures safe and buildings economically viable to serve the needs of our community. We strive

More information

Corflex. Continuous Corrugated Aluminum Sheathed PL, MC and MV Industrial Cables. Introduction Applications... 3

Corflex. Continuous Corrugated Aluminum Sheathed PL, MC and MV Industrial Cables. Introduction Applications... 3 Corflex Continuous Corrugated Aluminum Sheathed PL, MC and MV Industrial Cables Introduction................................. 2 Applications................................. 3 Corflex PL 300V Instrumentation

More information

Load Side PV Connections

Load Side PV Connections Perspectives on PV Load Side PV Connections 705.12(D) in the 2014 NEC by John Wiles Through the exceptional efforts of the members of NFPA NEC Code-Making Panel 4 working with the proposals and comments

More information

An average of one worker is electrocuted on the job every day There are four main types of electrical injuries:

An average of one worker is electrocuted on the job every day There are four main types of electrical injuries: Electrical Safety Introduction An average of one worker is electrocuted on the job every day There are four main types of electrical injuries: Electrocution (death due to electrical shock) Electrical shock

More information

9. Non-Residential Services (Commercial, Industrial, and Agricultural)

9. Non-Residential Services (Commercial, Industrial, and Agricultural) Section 9 2016 Electric Service Requirements, 3rd Edition Section 9 Non-Residential Services Directory Page 9.1 General Requirements 68 9.2 Direct-Connect Metering, Single Installations 69 9.3 Direct-Connect

More information

SOME REVIEW - QUESTIONS 2011 NATIONAL ELECTRICAL CODE

SOME REVIEW - QUESTIONS 2011 NATIONAL ELECTRICAL CODE SOME REVIEW - QUESTIONS 2011 NATIONAL ELECTRICAL CODE J & W Educational Services 1340 Hickory Hill Dr. Watkinsville, Ga 30677 Jim Allison (706) 769-7112 jandw@uga.edu http://www.ugaed.com What is the Code

More information

A. This Section includes ac, enclosed controllers rated 600 V and less, of the following types:

A. This Section includes ac, enclosed controllers rated 600 V and less, of the following types: SECTION 262913 600 VOLT ENCLOSED CONTROLLERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 0 Specification

More information

Corrections most seen on plan review October 18, 2017 David Rankin Seattle Department of Construction and Inspections

Corrections most seen on plan review October 18, 2017 David Rankin Seattle Department of Construction and Inspections Corrections most seen on plan review October 18, 2017 David Rankin Seattle Department of Construction and Inspections One-Line / Riser Diagrams Drawings are not reviewed prior to submission. Because of

More information

ELECTRICAL. 60 Minutes

ELECTRICAL. 60 Minutes ELECTRICAL 60 Minutes AGENDA Electrical definitions Electrical shocks, burns and secondary injuries Electrical hazards in the workplace Safety devices and prevention steps Do s and Don ts INTRODUCTORY

More information

9/16/2010. Chapter , The McGraw-Hill Companies, Inc. TRANSMISSION SYSTEMS. 2010, The McGraw-Hill Companies, Inc.

9/16/2010. Chapter , The McGraw-Hill Companies, Inc. TRANSMISSION SYSTEMS. 2010, The McGraw-Hill Companies, Inc. Chapter 3 TRANSMISSION SYSTEMS 1 Transmitting large amounts of electric energy over long distances is accomplished most efficiently by using high-voltages. Without transformers the widespread distribution

More information

AGRICULTURAL UNDERGROUND SERVICE 500 HP OR LESS

AGRICULTURAL UNDERGROUND SERVICE 500 HP OR LESS Prepared by: ABB1 AGRICULTURAL UNDERGROUND SERVICE 500 HP OR LESS 05619 Asset Type: Electric Metering Function: Design and Construction Issued by: Lisseth Villareal (LDV2) Date: 07-31-15 Rev. #10: This

More information

Electrical Safety. Electrical Safety Webinar. Electrical. Printing Industries Alliance Printing Industries Alliance 1

Electrical Safety. Electrical Safety Webinar. Electrical. Printing Industries Alliance Printing Industries Alliance 1 Webinar 1 Electrical 2 1 Webinar Introduction An average of one worker is electrocuted on the job every day There are four main types of electrical injuries: Electrocution (death due to electrical shock)

More information

ARKANSAS ELECTRICIANS

ARKANSAS ELECTRICIANS CONTINUING EDUCATION FOR ARKANSAS ELECTRICIANS 2014 NEC Code Change 8 Hours AMERICAN ELECTRICAL INSTITUTE N16 W23217 Stone Ridge Drive, Suite 290 Waukesha, WI 53188 855-780-5046 www.aeitraining.com DISCLAIMER

More information

Arc Fault Circuit Interrupter (AFCI) FACT SHEET

Arc Fault Circuit Interrupter (AFCI) FACT SHEET Arc Fault Circuit Interrupter (AFCI) FACT SHEET THE AFCI The AFCI is an arc fault circuit interrupter. AFCIs are newly-developed electrical devices designed to protect against fires caused by arcing faults

More information

Busway Construction. Bus Bars

Busway Construction. Bus Bars Busway Construction Bus Bars A better understanding of what busway is can be gained by examining its construction. A typical Siemens Sentron busway section has three or four formed aluminum or copper bars

More information

SECTION PANELBOARDS

SECTION PANELBOARDS SECTION 16470 PANELBOARDS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. The general provisions of the contract including General and Special Conditions and General Requirements shall apply to all work under

More information

BASIC ELECTRICAL ENGINEERING FOR CE

BASIC ELECTRICAL ENGINEERING FOR CE EE24 BASIC ELECTRICAL ENGINEERING FOR CE LECTURE NO. B-2 Residential Motor Loads Full Load Current of Motors 2 Example #1 Engr. Oliver Dy and Engr. Mechelle Perez bought an airconditioner for Engr. Marijo

More information

NEC REQUIREMENTS FOR GENERATORS

NEC REQUIREMENTS FOR GENERATORS PROFESSIONAL DEVELOPMENT SEMINAR SERIES NEC REQUIREMENTS FOR GENERATORS (Based on NEC 2005 with limited 2008 commentary) AIA certified Continuing Education Units (CEU) Available GPS-140 National Electric

More information

2. DEFINITIONS. 2.3 APPROVED Acceptable to the authority enforcing the National Electric Code

2. DEFINITIONS. 2.3 APPROVED Acceptable to the authority enforcing the National Electric Code 2. DEFINITIONS 2.1 ACCEPTABLE Acceptable to the Company. 2.2 ADVANCED METER A meter that is capable of remote reading, and is capable of storing electric consumption data at specified time intervals of

More information

Contents. Obtaining Electric Service from Your Cooperative...1. Bonding Frames of Major Appliances...4. Voltage Drop...8. Drawings...

Contents. Obtaining Electric Service from Your Cooperative...1. Bonding Frames of Major Appliances...4. Voltage Drop...8. Drawings... Contents Obtaining Electric Service from Your Cooperative...1 Bonding Frames of Major Appliances...4 Voltage Drop...8 Drawings...14 Agricultural Buildings...23 Optional Standby Systems...42 Grounding &

More information

INSTALL SERVICE- ENTRANCE SYSTEMS

INSTALL SERVICE- ENTRANCE SYSTEMS SUBCOURSE EN5141 EDITION B US ARMY ENGINEER SCHOOL INSTALL SERVICE- ENTRANCE SYSTEMS INSTALL SERVICE- ENTRANCE SYSTEMS Subcourse Number EN5141 EDITION B United States Army Engineer School Fort Leonard

More information

2014 NEC Update RV

2014 NEC Update RV PLEASE DO NOT BOOKMARK ANY ANYTIMECE WEBPAGES! Our system will remember the last page you viewed when logging out and back in but please DO NOT exit out when taking a test. Your place will NOT be saved.

More information

MC122IG 12/2 WG MC Solid-Isolated Ground, Steel Armor. Features. Material, Color, and Finish. Dimensions and Weight.

MC122IG 12/2 WG MC Solid-Isolated Ground, Steel Armor. Features. Material, Color, and Finish. Dimensions and Weight. 3804 South Street 75964-7263, TX Nacogdoches Phone: 936-569-7941 Fax: 936-560-4685 AllenWatson@elliottelectric.com Catalog Number Manufacturer Description Weight per unit Product Category MC122IG 12/2

More information

SECTION ENCLOSED SWITCHES AND CIRCUIT BREAKERS

SECTION ENCLOSED SWITCHES AND CIRCUIT BREAKERS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 29 21 ENCLOSED SWITCHES AND CIRCUIT BREAKERS SPEC WRITE NOTE: Delete between // // if not applicable to project. Also delete any other item or paragraph not

More information

DIRECTORY, IDENTIFICATION, LABEL, MARKING, PLAQUE, AND SIGN REQUIREMENTS FOR SOLAR PV SYSTEMS

DIRECTORY, IDENTIFICATION, LABEL, MARKING, PLAQUE, AND SIGN REQUIREMENTS FOR SOLAR PV SYSTEMS Mike Holt s Illustrated Guide to DIRECTORY, IDENTIFICATION, LABEL, MARKING, PLAQUE, AND SIGN REQUIREMENTS FOR SOLAR PV SYSTEMS Based on the 2014 NEC Articles 690 and 705 Extracted from Mike Holt s Understanding

More information

The following are specific provisions of 1910(a)(2) that could be seen in the LBM sector

The following are specific provisions of 1910(a)(2) that could be seen in the LBM sector Know the Rules on Temporary Wiring OSHA Standard 1910.305, Wiring methods, components, and equipment for general use, addresses wiring methods, components, and equipment for general use as one of several

More information

PRODUCTS COMMERCIAL BUILDING WIRE & CABLE

PRODUCTS COMMERCIAL BUILDING WIRE & CABLE PRODUCTS COMMERCIAL BUILDING WIRE & CABLE Table of content About Nexans 3 Commercial Building Wire & Cable 4 Armored 5 ENERGEX AC-HCF - Green Striped Armor 6 ENERGEX AC 9 ENERGEX MC 120 Aluminum Armored

More information

Section 6 Electric Metering: Residential

Section 6 Electric Metering: Residential Section 6 Electric Metering: Residential 6.1. Scope This section provides specific information for residential metering that is not covered by the basic requirements in Section 5, Electric Metering: General.

More information

Fig. 1. Sample calculation for determining the proper conductor size needed to serve a motor controller and avoid voltage drop problems.

Fig. 1. Sample calculation for determining the proper conductor size needed to serve a motor controller and avoid voltage drop problems. Power to the Pump By Mike Holt, NEC Consultant Why some fire pump requirements are "backward" One of the principal NEC requirements for circuit protection is that you shut down the equipment rather than

More information

REQUIREMENTS FOR ELECTRICAL INSTALLATIONS

REQUIREMENTS FOR ELECTRICAL INSTALLATIONS ARTICLE 110 REQUIREMENTS FOR ELECTRICAL INSTALLATIONS Introduction to Article 110 Requirements for Electrical Installations Article 110 sets the stage for how you ll implement the rest of the NEC. This

More information

Pentahead bolts See note 2. Conduit run as specified. Company facility. Refer to drawing SS8.6-2 or SS8.6-3 STANDARD SERVICE INSTALLATION

Pentahead bolts See note 2. Conduit run as specified. Company facility. Refer to drawing SS8.6-2 or SS8.6-3 STANDARD SERVICE INSTALLATION PULL BOX F SECONDARY SYSTEM Typical grade Pentahead bolts See note 2 Conduit run as specified Plastic or fiberglass for grass areas or Polymer concrete for light duty areas (see notes 2, 3, & 4) Company

More information

SECTION ENCLOSED SWITCHES AND CIRCUIT BREAKERS

SECTION ENCLOSED SWITCHES AND CIRCUIT BREAKERS SECTION 26 28 16 ENCLOSED SWITCHES AND PART 1 - GENERAL 1.1 SUMMARY A. Section includes the following individually mounted, enclosed switches and circuit breakers rated 600V AC and less: 1. Fusible switches.

More information

DEWALT Electrical Licensing Exam Guide CONTENTS

DEWALT Electrical Licensing Exam Guide CONTENTS DEWALT Electrical Licensing Exam Guide v ONTENTS How to Prepare for the Exam................................................ 2 How to Study.............................................................

More information

TRANSMISSION SYSTEMS

TRANSMISSION SYSTEMS TRANSMISSION SYSTEMS Transmitting large amounts of electric energy over long distances is accomplished most efficiently by using high-voltages. Without transformers the widespread distribution of electric

More information

COMMERCIAL QUICK REFERENCE

COMMERCIAL QUICK REFERENCE COMMERCIAL QUICK REFERENCE PROVO CITY POWER STANDARDS ELECTRICAL ENGINEERING UPDATED: 2016 SPECIFICATIONS SUBJECT TO CHANGE WITHOUT NOTIFICATION. 18" MIN. OF TAIL. (NEUTRAL CONDUCTOR MUST BE WHITE OR

More information

Western Section IAEI Code Panel Questions

Western Section IAEI Code Panel Questions Western Section IAEI 2013 Code Panel Questions 1. Do the factory wings that many fluorescent troffers have designed to fold out over the grid meet the requirements for securely fastened to the framing?

More information

ELECTRICAL - GENERAL REQUIREMENTS SELF INSPECTION CHECKLIST

ELECTRICAL - GENERAL REQUIREMENTS SELF INSPECTION CHECKLIST Name of School: OPTIONAL INFORMATION Date of Inspection: Vocational Program/Course/Room: Signature of Inspector: ELECTRICAL - GENERAL REQUIREMENTS SELF INSPECTION CHECKLIST Guidelines: This checklist covers

More information

INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE

INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE SAFETY BULLETIN #23 GUIDELINES FOR WORKING WITH LIGHTING SYSTEMS AND OTHER ELECTRICAL EQUIPMENT All electrical systems and electrically energized equipment

More information

A. This section includes unit capacitors for power factor correction.

A. This section includes unit capacitors for power factor correction. PART 1: GENERAL 1.01 Wiring Devices A. This section of the standard includes design requirements for wiring connections, including receptacles and switches to equipment specified in other sections. 1.02

More information

Commercial & Industrial Wiring (2014 NEC) (Homestudy)

Commercial & Industrial Wiring (2014 NEC) (Homestudy) Commercial & Industrial Wiring (2014 NEC) (Homestudy) Montana Electrical License This course will review the 2014 National Electrical Code requirements for installing commercial and industrial wiring systems

More information

Manufacturing quality. Delivering service. Single Conductors DESCRIPTION: Single copper conductor, tinned stranded insulated with moisture and heat resistant, chemically cross-linked polyethylene insulation

More information