1 MECKLENBURG COUNTY Land Use and Environmental Service Agency Code Enforcement 2/8/12 ELECTRICAL CONSISTENCY MEETING Code Consistency Questions 1. I am inspecting a building addition. They have a 480V to 120/208V 150 KVA step down transformer with two 225 amp panels being fed from it, but now have more circuits than these two panelboards can handle. Can they tap an additional 100 amp panel off of this transformer? The 100 ampere panel would be 15 feet away. If the primary side is protected at 125% of the transformer rating and the secondary panel satisfy grouping and tap rules, then this installation is code compliant If the primary side is protected at greater than 125%, then this installation does not comply with the NEC. 2. What is the maximum length of raceway I can use where the conductor ampacity is not required to be adjusted for conductor bundling? See Note 4 to Table 1 of Chapter 9 that states Where conduit or tubing nipples having a maximum length not to exceed 600 mm (24 in.) are installed between boxes, cabinets, and similar enclosures, the nipples shall be permitted to be filled to 60 percent of their total cross-sectional area, and (B)(2)(a) adjustment factors need not apply to this condition. See also (B)(2(a) Exception No. 3 that states Derating factors shall not apply to conductors in nipples having a length not exceeding 600 mm (24 in.). 3. We have a 400A, 3-phase feeder that we want to wire with two parallel sets of 3/0 AWG conductors in the same raceway. Is this acceptable?

2 Page 2 of 6 Yes, see (A) and (C) as there is nothing wrong with this installation. However, derating will be required. See (B)(2) Adjustment Factors, (a) More Than Three Current-Carrying Conductors in a Raceway or Cable. Where the number of currentcarrying conductors in a raceway or cable exceeds three, or where single conductors or multiconductor cables are installed without maintaining spacing for a continuous length longer than 600 mm (24 in.) and are not installed in raceways, the allowable ampacity of each conductor shall be reduced as shown in Table (B)(2)(a). 4. Our utility requires a non-fused disconnect upstream of the meter and service disconnect for certain services. Is this legal? If this is the first disconnect, do we separate the grounded and grounding conductors at this point? See (3) that states Meter disconnect switches nominally rated not in excess of 600 volts that have a short-circuit current rating equal to or greater than the available short-circuit current, provided all metal housings and service enclosures are grounded in accordance with Part VII and bonded in accordance with Part V of Article 250. A meter disconnect switch shall be capable of interrupting the load served. These are used because self-contained meters and internal meter bypass switches may not be able to safely disconnect 277/480 volt services under load. This is not the service disconnecting means, so for Article 250 purposes, pretend that this switch does not exist. 5. If structural steel is used as a grounding electrode for the electrical service, is it also necessary to supplement the steel electrode with an additional electrode such as a ground rod? If structural steel is high and dry can it be converted to a grounding electrode? Specific answer - No, once structural steel in established as an electrode, it does not have to be further supplemented by an additional electrode. Also an answer - No, if (10 ft) or more of a single structural metal member is in direct contact with the earth or encased in concrete that is in direct contact with the earth. For the 2008 NEC, connecting the metal frame of the building to an additional electrode such as a ground rod would make the metal frame of the building an

3 Page 3 of 6 electrode. This has been revised for the 2011 NEC. The Article 100 definition of a grounding electrode is a conducting object through which a direct connection to earth is established. For correct application of this definition, the structure metal members of a building or structure needs to be the conducting object with a direct connection to the earth Grounding Electrodes. (2008 NEC) (A) Electrodes Permitted for Grounding. (2) Metal Frame of the Building or Structure. The metal frame of the building or structure that is connected to the earth by any of the following methods: (1) 3.0 m (10 ft) or more of a single structural metal member in direct contact with the earth or encased in concrete that is in direct contact with the earth (2) Connecting the structural metal frame to the reinforcing bars of a concreteencased electrode as provided in (A)(3) or ground ring as provided in (A)(4) (3) Bonding the structural metal frame to one or more of the grounding electrodes as defined in (A)(5) or (A)(7) that comply with (4) Other approved means of establishing a connection to earth Grounding Electrodes. (2011 NEC) (A) Electrodes Permitted for Grounding (2) Metal Frame of the Building or Structure. The metal frame of the building or structure that is connected to the earth by one or more of the following methods: (1) At least one structural metal member that is in direct contact with the earth for 3.0 m (10 ft) or more, with or without concrete encasement. (2) The hold-down bolts securing the structural steel column are connected to a concrete encased electrode that complies with (A)(3) located in the support footing or foundation. The hold-down bolts shall be connected to the concreteencased electrode by welding, exothermic welding, the usual steel tie wires, or other approved means. 6. When a conduit leaves a Class I, Division 1 classified paint spray room and goes under the concrete floor into a cabinet in the motor control room that is non-classified, is one sealing fitting in the paint mix room sufficient, or is an additional sealing fitting required in the nonclassified area as well? sends us to Article 501 or 505 for wiring methods (A)(4) contains the sealing rules. If it can be located to minimize the communication of fumes in the

4 Page 4 of 6 conduit one will suffice. 7. A service equipment panel-board has a 400 amp main which feeds a bus that has double barrel lugs at the bottom, and then feeds two 200 ampere disconnects. Is it permissible to tap directly from the double barrel lugs of a service equipment panel-board? Yes, see and (C). The tap rules are covered in and the termination requirements in (C). As long as the conductors are being terminated in accordance with the permitted markings for the lugs and the appropriate tap rule is being followed with a 400A breaker protecting the feeder, there is no violation to supply tap conductors from a sub-feed lug on the panelboard. It would appear that either the 10ft or 25 ft tap would be permitted in this installation. 8. We have motors that are interlocked, preventing them from being on at the same time. Do we still have to add them all up for service and feeder calculations? No. See , Exception No. 3 that states Where the circuitry is interlocked so as to prevent operation of selected motors or other loads at the same time, the conductor ampacity shall be permitted to be based on the summation of the currents of the motors and other loads to be operated at the same time that results in the highest total current. For service ampacity, Minimum Size and Rating (A) General, references Part III of Article 220. Section Motors refers to as shown above. Also see that states Where it is unlikely that two or more noncoincident loads will be in use simultaneously, it shall be permissible to use only the largest load(s) that will be used at one time for calculating the total load of a feeder or service. 9. I was doing a swimming pool job that included a motor, wet niche fixture, and metal forming shell. When installing the equipotential bonding grid, I split bolted a #8 copper jumper from the forming shell to the light niche and one from the forming shell to the motor. The inspector turned me down saying the grid could not be a component in bonding the niche to the other metal parts. Is she correct? Equipotential Bonding.

5 Page 5 of 6 (A) Performance. The equipotential bonding required by this section shall be installed to reduce voltage gradients in the pool area. (B) Bonded Parts. The parts specified in (B)(1) through (B)(7) shall be bonded together using solid copper conductors, insulated covered, or bare, not smaller than 8 AWG or with rigid metal conduit of brass or other identified corrosion-resistant metal. Connections to bonded parts shall be made in accordance with An 8 AWG or larger solid copper bonding conductor provided to reduce voltage gradients in the pool area shall not be required to be extended or attached to remote panelboards, service equipment, or electrodes. 10. I understand the Code allows me to use Type AC cable with an equipment grounding (bonding) conductor for branch circuits serving patient care areas. Can I use Type MC Cable with an equipment grounding (bonding) conductor for luminaires located above 7.5 feet in a patient care area? Yes, see , Grounding of Receptacles and Fixed Electrical Equipment in Patient Care Areas, that states Wiring in patient care areas shall comply with (A) and (B). Section (A) Wiring Methods states All branch circuits serving patient care areas shall be provided with an effective ground-fault current path by installation in a metal raceway system, or a cable having a metallic armor or sheath assembly. The metal raceway system, or metallic cable armor, or sheath assembly shall itself qualify as an equipment grounding conductor in accordance with What is the maximum number of bathroom receptacles that can be placed on the 20A, 120V bathroom receptacle circuit in a single-family dwelling? Could you elaborate on other options for bathroom receptacles requirements. Question 1 There is no maximum. See (C)(3) that states In addition to the number of branch circuits required by other parts of this section, at least one 20-ampere branch circuit shall be provided to supply bathroom receptacle outlet(s). Such circuits shall have no other outlets. The see (J) and (J)(1) that states one-family, two-family, and multifamily dwellings the outlets specified in (J)(1), (J)(2), and (J)(3) are included in the general lighting load calculations of No additional load calculations shall be required for such outlets (J)(1) states All general-use receptacle outlets of 20-ampere rating or less, including receptacles connected to the circuits in (C)(3).

6 Page 6 of What sections of the NEC would apply to piers and docks at single family dwellings? Would Article 682 apply? All of the normal sections that apply to single family dwellings would apply to piers and docks at single family dwellings. Article 682 could apply since it is not specifically excluded Ground-Fault Circuit-Interrupter Protection for Personnel. FPN: See for ground-fault circuit-interrupter protection for personnel on feeders. (A) Dwelling Units. All 125-volt, single-phase, 15- and 20-ampere receptacles installed in the locations specified in (1) through (8) shall have ground-fault circuit-interrupter protection for personnel. (3) Outdoors (C) Boat Hoists. GFCI protection shall be provided for outlets not exceeding 240 volts that supply boat hoists installed in dwelling unit locations.

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 9/14/11 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 9/14/11 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions MECKLENBURG COUNTY Land Use and Environmental Service Agency Code Enforcement 9/14/11 ELECTRICAL CONSISTENCY MEETING Code Consistency Questions 1. I recently installed a 45-KVA transformer, 480-volt primary

More information

CHAPTER V RESIDENTIAL WIRING

CHAPTER V RESIDENTIAL WIRING CHAPTER V RESIDENTIAL WIRING 5.1. THE SERVICE ENTRANCE Buildings and other structures receive the electrical energy through the service entrance. In residential wiring, the electric company supply this

More information

Have You Been Grounded Lately

Have You Been Grounded Lately Have You Been Grounded Lately Thurs, Oct. 26, 2017 9:15-10:15 Phil Simmons Author, Electrical Grounding and Bonding Author Cengage Learning Phil Simmons Have You Been Grounded Lately 2017 NEC Changes Relative

More information

Spring Test 10 due 05/11/2013

Spring Test 10 due 05/11/2013 Spring Test 10 due 05/11/2013 Multiple Choice Identify the letter of the choice that best completes the statement or answers the question. 1. When installed in an agricultural building that houses livestock

More information

9/16/2010. Chapter , The McGraw-Hill Companies, Inc. TRANSMISSION SYSTEMS. 2010, The McGraw-Hill Companies, Inc.

9/16/2010. Chapter , The McGraw-Hill Companies, Inc. TRANSMISSION SYSTEMS. 2010, The McGraw-Hill Companies, Inc. Chapter 3 TRANSMISSION SYSTEMS 1 Transmitting large amounts of electric energy over long distances is accomplished most efficiently by using high-voltages. Without transformers the widespread distribution

More information

9/7/2010. Objectives. Article 90. Introduction NEC Significant Changes. Review significant revisions in the 2011 NEC

9/7/2010. Objectives. Article 90. Introduction NEC Significant Changes. Review significant revisions in the 2011 NEC 2011 NEC Significant Changes Courtesy of NJATC Courtesy of NFPA Presented By: Michael J. Johnston Executive Director of Standards and Safety, NECA Objectives Review significant revisions in the 2011 NEC

More information

Mecklenburg County Common Code Defects

Mecklenburg County Common Code Defects Electrical Code Defects Improper Over Current Protection Code Description 310.15 Ampacities for s Rated 0 2000 Volts. (A) General. (1) Tables or Engineering Supervision. Ampacities for conductors shall

More information

CHAPTER 10 ELECTRICAL. Notes:

CHAPTER 10 ELECTRICAL. Notes: CHAPTER 10 ELECTRICAL 1001.0 General Requirements. Electrical wiring and equipment shall comply with the requirements of NFPA 70, National Electrical Code (NEC), or local ordinances. 1002.0 Solar Photovoltaic

More information

SUPPLEMENTAL CORRECTION SHEET FOR SOLAR PHOTOVOLTAIC SYSTEMS - ELECTRICAL

SUPPLEMENTAL CORRECTION SHEET FOR SOLAR PHOTOVOLTAIC SYSTEMS - ELECTRICAL SUPPLEMENTAL CORRECTION SHEET FOR SOLAR PHOTOVOLTAIC SYSTEMS - ELECTRICAL This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly.

More information

Chapter 8 Interior Wiring and Lighting

Chapter 8 Interior Wiring and Lighting Chapter 8 Interior Wiring and Lighting Review Questions 1. What tool if any, is used to remove a fuse that is to be replaced? 1. Pliers 2. Screwdriver 3. Fuse puller 4. None 2. OSHA has established specific

More information

Arc Fault Circuit Interrupter (AFCI) FACT SHEET

Arc Fault Circuit Interrupter (AFCI) FACT SHEET Arc Fault Circuit Interrupter (AFCI) FACT SHEET THE AFCI The AFCI is an arc fault circuit interrupter. AFCIs are newly-developed electrical devices designed to protect against fires caused by arcing faults

More information

Pretest Module 24 Three-phase Service Entrance

Pretest Module 24 Three-phase Service Entrance Pretest Module 24 Three-phase Service Entrance 1. What is the most widely used three-phase service entrance system? 2. What are the three most common voltage combinations for three-phase, four-wire systems?

More information

Chapter 2 Wiring and Protection Article 200 Use and Identification of Grounded Neutral Conductor Chapter 1 General...9

Chapter 2 Wiring and Protection Article 200 Use and Identification of Grounded Neutral Conductor Chapter 1 General...9 Article 90 Introduction...1 90.1 Purpose of the NEC...1 90.2 Scope of the NEC...2 90.3 Code Arrangement...4 90.4 Enforcement...5 90.5 Mandatory Requirements and Explanatory Material...6 90.6 Formal Interpretations...6

More information

Overcurrent Protection According to the 2011 NEC

Overcurrent Protection According to the 2011 NEC Overcurrent Protection According to the 2011 NEC Utah Electrical License This course will cover overcurrent protection according to the 2011 NEC. The key sections of Article 240 will be discussed. Overcurrent

More information

90.2 Scope. The installation of electrical conductors, equipment and raceways for:

90.2 Scope. The installation of electrical conductors, equipment and raceways for: NEC Generator Primer Rules on the installation of generators and transfer switches 1 90.2 Scope The installation of electrical conductors, equipment and raceways for: public and private premises Conductors

More information

Fee $20 Course: NEC Changes 1 This course is valid for these credentials: Credential Description Cred Code Credit Hours

Fee $20 Course: NEC Changes 1 This course is valid for these credentials: Credential Description Cred Code Credit Hours www.garyklinka.com Page 1 of 18 Instructions: Fee $20 1. Print these pages. 2. Circle the correct answers and transfer them to the answer sheet. 3. Page down to the last page for the verification forms

More information

Spring Test 7 due 05/03/2013

Spring Test 7 due 05/03/2013 Spring Test 7 due 05/03/2013 Multiple Choice Identify the choice that best completes the statement or answers the question. 1. A raceway contains two 3-phase, 3-wire circuits that supply 38 ampere continuous

More information

SINGLE PHASE WIRING SPECIFICATIONS

SINGLE PHASE WIRING SPECIFICATIONS SINGLE PHASE WIRING SPECIFICATIONS 1-866-MEC-ELEC (1-866-632-3532) Office Locations: Hondo Office 237 Hwy 173 N Hondo, TX 78661-0370 Fax 830.426.3335 Dilley Office 1718 W. FM 117 Dilley, TX 78017 Fax 830.965.1425

More information

Electrical Tech Note 111 Biosystems & Agricultural Engineering Department Michigan State University

Electrical Tech Note 111 Biosystems & Agricultural Engineering Department Michigan State University Electrical Tech Note 111 Biosystems & Agricultural Engineering Department Michigan State University Electrical Code Changes in Michigan 1 (Based on Part 8, P.A. 230, the 2005 NEC and the 2003 MRC) This

More information

THREE PHASE WIRING SPECIFICATIONS

THREE PHASE WIRING SPECIFICATIONS THREE PHASE WIRING SPECIFICATIONS 1-866-MEC-ELEC (1-866-632-3532) Office Locations: Hondo Office 237 Hwy 173 N Hondo, TX 78661-0370 Fax 830.426.3335 Dilley Office 1718 W. FM 117 Dilley, TX 78017 Fax 830.965.1425

More information

2016 Photovoltaic Solar System Plan Review List

2016 Photovoltaic Solar System Plan Review List Building Division 555 Santa Clara Street Vallejo CA 94590 707.648.4374 2016 Photovoltaic Solar System Plan Review List GENERAL PROJECT INFORMATION PLAN CHECK NO DATE JOB ADDRESS CITY ZIP REVIEWED BY PHONE

More information

See Part 3 for the Introduction for Article 314

See Part 3 for the Introduction for Article 314 See Part 3 for the Introduction for Article 314 76 314.25 Covers and Canopies When the installation is complete, each outlet box must be provided with a cover or faceplate, unless covered by a fixture

More information

This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly.

This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly. SUPPLEMENTAL CORRECTION SHEET FOR SOLAR PHOTOVOLTAIC SYSTEMS (ELEC) This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly.

More information

Electrical Tech Note 105 Agricultural Engineering Department Michigan State University

Electrical Tech Note 105 Agricultural Engineering Department Michigan State University Electrical Tech Note 105 Agricultural Engineering Department Michigan State University Journey Exam Study Guide and Sample Questions 1 Based on the 2002 NEC, Part 8 of PA 230, and the 2003 MRC The Journey

More information

Electrical Tech Note 106

Electrical Tech Note 106 Electrical Tech Note 106 Biosystems & Agricultural Engineering Department Michigan State University Master Exam Study Guide and Sample Questions 1 Based on the 2014 NEC, Part 8 of PA 230, PA 407, and the

More information

Corrections most seen on plan review October 18, 2017 David Rankin Seattle Department of Construction and Inspections

Corrections most seen on plan review October 18, 2017 David Rankin Seattle Department of Construction and Inspections Corrections most seen on plan review October 18, 2017 David Rankin Seattle Department of Construction and Inspections One-Line / Riser Diagrams Drawings are not reviewed prior to submission. Because of

More information

TRANSMISSION SYSTEMS

TRANSMISSION SYSTEMS TRANSMISSION SYSTEMS Transmitting large amounts of electric energy over long distances is accomplished most efficiently by using high-voltages. Without transformers the widespread distribution of electric

More information

PART A General Conductor Requirements

PART A General Conductor Requirements PART A General Conductor Requirements 6.1 Conductor Insulation Property Table 310.13 of the NEC provides information on conductor properties such as permitted use, maximum operating temperature, and other

More information

Chapter 1 Electrical Theory...1

Chapter 1 Electrical Theory...1 Electrical Formulas with Sample Calculations Table of Contents Chapter 1 Electrical Theory...1 Unit 1 Electrician s Math and Basic Electrical Formulas...3 Part A Electrician s Math...3 1 1 Fractions...3

More information

Definitions of and have been revised. a. automatic b. nonautomatic c. none of the above d. both a and b

Definitions of and have been revised. a. automatic b. nonautomatic c. none of the above d. both a and b www.garyklinka.com Page 1 of 12 Instructions: Fee $25 1. Print these pages. 2. Circle the correct answers and transfer them to the answer sheet. 3. Page down to the last page for the verification forms

More information

Solar PV Standard Electrical Plan

Solar PV Standard Electrical Plan *** Provide this document to the inspector along with ALL system installation instructions *** Project Address: Permit Number: SCOPE: Standard plan for installation of solar PV systems utilizing 2 wire

More information

Photovoltaic Solar Plan Review

Photovoltaic Solar Plan Review PAIGE B. VAUGHAN, CBO Director of Building and Safety Phone (310) 605-5509 Fax Line (310) 605-5598 E-mail:lbutler@comptoncity.org Building & Safety Department Photovoltaic Solar Plan Review Plan Check

More information

Western Section IAEI Code Panel Questions

Western Section IAEI Code Panel Questions Western Section IAEI 2013 Code Panel Questions 1. Do the factory wings that many fluorescent troffers have designed to fold out over the grid meet the requirements for securely fastened to the framing?

More information

NEC 2014 Code Changes

NEC 2014 Code Changes NEC 2014 Code Changes Articles 310 310.120 CHANGES FROM 2011 TO 2014 CODE ARE IN RED ARTICLE 310 Conductors for General Wiring I. General 310.2 Definitions Electrical Ducts Electrical conduits, or other

More information

Overcurrent Protection (2014 NEC) (Homestudy)

Overcurrent Protection (2014 NEC) (Homestudy) Overcurrent Protection (2014 NEC) (Homestudy) Oregon Electrical License The key sections of Article 240 will be discussed. Overcurrent protection for panelboards, appliances, motors, motor compressors,

More information

Understanding National Electric Code (NEC) tap rules How do they apply to circuit breaker terminals?

Understanding National Electric Code (NEC) tap rules How do they apply to circuit breaker terminals? White paper Understanding National Electric Code (NEC) tap rules How do they apply to circuit breaker terminals? Darryl Moser, Business Development Manager, DEM Sales, ABB, Electrification Products Division

More information

Electrical Design/Build Guide

Electrical Design/Build Guide 2017 Electrical Design/Build Guide Based on the 2017 National Electrical Code Copyright Durand & Associates 1986-2016 60 C Copper Ampacity 4 - Wire Fill - (Non-Current Carrying Neutral) 4 or 5 - Parallel

More information

Section 6 Electric Metering: Residential

Section 6 Electric Metering: Residential Section 6 Electric Metering: Residential 6.1. Scope This section provides specific information for residential metering that is not covered by the basic requirements in Section 5, Electric Metering: General.

More information

(The actual state exam will be closer to 50 questions in 4 hours time) Master Electrician Practice Test

(The actual state exam will be closer to 50 questions in 4 hours time) Master Electrician Practice Test (The actual state exam will be closer to 50 questions in 4 hours time) Master Electrician Practice Test 1. Accessible as applied to wiring methods means capable of being removed or exposed without damaging

More information

TEMPORARY ELECTRIC WIRING FOR CARNIVALS, CONVENTIONS, EXHIBITIONS, FAIRS AND SIMILAR USES

TEMPORARY ELECTRIC WIRING FOR CARNIVALS, CONVENTIONS, EXHIBITIONS, FAIRS AND SIMILAR USES INFORMATION BULLETIN / PUBLIC - ELECTRICAL CODE REFERENCE NO.: LAMC 93.0230 Effective: 3-24-69 DOCUMENT NO. P/EC 2002-006 Revised: 11-17-00 Previously Issued As: RGA #7-69 TEMPORARY ELECTRIC WIRING FOR

More information

Western Section 101 st Annual Meeting Hot Springs, Arkansas September 21, 2005 Charlie Trout Code Breakfast

Western Section 101 st Annual Meeting Hot Springs, Arkansas September 21, 2005 Charlie Trout Code Breakfast Western Section 101 st Annual Meeting Hot Springs, Arkansas September 21, 2005 Charlie Trout Code Breakfast 1.Question: An add on unit for a hydromassage bathtub consists of a small 1-gallon water heater

More information

Installing a Downstream Distribution Panelboard

Installing a Downstream Distribution Panelboard Job Sheet 5 Installing a Downstream Distribution Panelboard OBJECTIVE To install a downstream distribution panelboard (DDP) on the Mobile Workstation. To mechanically and electrically connect the DDP to

More information

2011 NEC Code Updates Part 3

2011 NEC Code Updates Part 3 www.garyklinka.com Page 1 of 22 Instructions: Fee $35 1. Print these pages. 2. Circle the correct answers and transfer them to the answer sheet. 3. Page down to the last page for the verification forms

More information

TABLE OF CONTENTS CHAPTER 1 ELECTRICAL THEORY About This Textbook...xi. Passing Your Exam...xiv. How to Use the National Electrical Code...

TABLE OF CONTENTS CHAPTER 1 ELECTRICAL THEORY About This Textbook...xi. Passing Your Exam...xiv. How to Use the National Electrical Code... TABLE OF CONTENTS About This Textbook...xi Passing Your Exam...xiv How to Use the National Electrical Code... 1 CHAPTER 1 ELECTRICAL THEORY... 7 Unit 1 Electrician s Math and Basic Electrical Formulas...

More information

SECTION 1: Field Inspection Guide for Rooftop Photovoltaic (PV) Systems

SECTION 1: Field Inspection Guide for Rooftop Photovoltaic (PV) Systems COUNTY OF SANTA CRUZ PLANNING DEPARTMENT 701 OCEAN STREET, 4 th FLOOR, SANTA CRUZ, CA 95060 (831) 454-2580 FAX: (831) 454-2131 TDD: (831) 454-2123 KATHLEEN MOLLOY PREVISICH, PLANNING DIRECTOR Photovoltaic

More information

UNIT 1 ELECTRICIAN S MATH AND BASIC ELECTRICAL FORMULAS...1 Introduction...1. UNIT 2 ELECTRICAL CIRCUITS...49 Introduction...49

UNIT 1 ELECTRICIAN S MATH AND BASIC ELECTRICAL FORMULAS...1 Introduction...1. UNIT 2 ELECTRICAL CIRCUITS...49 Introduction...49 UNIT 1 ELECTRICIAN S MATH AND BASIC ELECTRICAL FORMULAS...1 Introduction...1 PART A ELECTRICIAN S MATH...1 Introduction...1 1.1 Whole Numbers...1 1.2 Decimal...1 1.3 Fractions...1 1.4 Percentages...2 1.5

More information

PHOTOVOLTAIC ELECTRICAL POWER SYSTEMS INSPECTOR/INSTALLER CHECKLIST

PHOTOVOLTAIC ELECTRICAL POWER SYSTEMS INSPECTOR/INSTALLER CHECKLIST PHOTOVOLTAIC ELECTRICAL POWER SYSTEMS INSPECTOR/INSTALLER CHECKLIST The following checklist is an outline of the general requirements found in the 2005 National Electrical Code (NEC) Article 690 for Photovoltaic

More information

The 84 th NC Electrical Institute Code Questions April 9 th & 10 th 2013 North Raleigh Hilton Raleigh, NC

The 84 th NC Electrical Institute Code Questions April 9 th & 10 th 2013 North Raleigh Hilton Raleigh, NC The 84 th NC Electrical Institute Code Questions April 9 th & 10 th 2013 North Raleigh Hilton Raleigh, NC www.ncdoi.com www.ncbeec.org NC DEPARTMENT OF INSURANCE NC STATE BOARD OF EXAMINERS OF ELECTRICAL

More information

FOR ALL STAKEHOLDERS TO

FOR ALL STAKEHOLDERS TO Our Goal is FOR ALL STAKEHOLDERS TO HAVE A SUCCESSFUL PROJECT with us and that together we keep people and structures safe and buildings economically viable to serve the needs of our community. We strive

More information

Western Section IAEI Code Panel Questions

Western Section IAEI Code Panel Questions Western Section IAEI 2013 Code Panel Questions 1. Do the factory wings that many fluorescent troffers have designed to fold out over the grid meet the requirements for securely fastened to the framing?

More information

A Look at the 2017 NEC Significant Changes

A Look at the 2017 NEC Significant Changes A Look at the 2017 NEC Significant Changes A Look at the 2017 NEC Significant Changes Michael J. Johnston NECA James T. Dollard Local 98 Philadelphia Electrical JATC This session is eligible for 1 Continuing

More information

ELECTRICAL CONSISTENCY MEETING

ELECTRICAL CONSISTENCY MEETING ELECTRICAL CONSISTENCY MEETING Date: 10/14/2015 Our Goal is FOR ALL STAKEHOLDERS TO HAVE A SUCCESSFUL PROJECT with us and that together we keep people and structures safe and economically viable to serve

More information

Data Bulletin. Wire Temperature Ratings and Terminations INTRODUCTION WHY ARE TEMPERATURE RATINGS IMPORTANT?

Data Bulletin. Wire Temperature Ratings and Terminations INTRODUCTION WHY ARE TEMPERATURE RATINGS IMPORTANT? Data Bulletin March 2002 Lexington, KY, USA Wire Temperature Ratings and Terminations INTRODUCTION WHY ARE TEMPERATURE RATINGS IMPORTANT? Table 1: Insulation Type Figure 1: Figure 2: Ampacity of a 1/0

More information

Continued from Part 2 Rules

Continued from Part 2 Rules Continued from Part 2 Rules 26 50. 51 250.94 Grounding (Bonding) of Communications Systems An accessible bonding point must be provided at service equipment or the disconnecting means of separate buildings

More information

TABLE OF CONTENTS. About the Mike Holt Enterprises Team... xviii CHAPTER 1 ELECTRICAL THEORY... 1

TABLE OF CONTENTS. About the Mike Holt Enterprises Team... xviii CHAPTER 1 ELECTRICAL THEORY... 1 TABLE OF CONTENTS Introduction...xv About the Mike Holt Enterprises Team... xviii CHAPTER 1 ELECTRICAL THEORY... 1 Unit 1 Electrician s Math and Basic Electrical Formulas... 1 Part A Electrician s Math...

More information

2011 NEC Changes Part 2 (Homestudy) (Homestudy)

2011 NEC Changes Part 2 (Homestudy) (Homestudy) 2011 NEC Changes Part 2 (Homestudy) (Homestudy) North Carolina Electrical License This course will review the second half of the most important National Electrical Code changes from the 2011 NEC. Changes

More information

The following are specific provisions of 1910(a)(2) that could be seen in the LBM sector

The following are specific provisions of 1910(a)(2) that could be seen in the LBM sector Know the Rules on Temporary Wiring OSHA Standard 1910.305, Wiring methods, components, and equipment for general use, addresses wiring methods, components, and equipment for general use as one of several

More information

SECTION LOW VOLTAGE DISTRIBUTION EQUIPMENT

SECTION LOW VOLTAGE DISTRIBUTION EQUIPMENT SECTION 16400 LOW VOLTAGE DISTRIBUTION EQUIPMENT A. General 1. The University does not accept Series-Rated equipment for power distribution switchboards, distribution panels and branch circuit panelboards.

More information

2014 NEC Changes Part 4

2014 NEC Changes Part 4 www.garyklinka.com Page 1 of 14 Instructions: Fee $25 1. Print these pages. 2. Circle the correct answers and transfer them to the answer sheet. 3. Page down to the last page for the verification forms

More information

SOLAR PV STANDARD PLAN - COMPREHENSIVE Central/String Inverter Systems for One and Two Family Dwellings

SOLAR PV STANDARD PLAN - COMPREHENSIVE Central/String Inverter Systems for One and Two Family Dwellings SCOPE: Use this plan ONLY for utility-interactive central/string inverter systems not exceeding a total combined system ac inverter output rating of 10kW on the roof of a one- or two-family dwelling or

More information

Solar PV Standard Electric Plan

Solar PV Standard Electric Plan *** Provide this document to the inspector along with ALL system installation instructions *** SCOPE: Standard plan for the installation of microinverter solar PV systems, not exceeding a total AC output

More information

COMMERCIAL QUICK REFERENCE

COMMERCIAL QUICK REFERENCE COMMERCIAL QUICK REFERENCE PROVO CITY POWER STANDARDS ELECTRICAL ENGINEERING UPDATED: 2016 SPECIFICATIONS SUBJECT TO CHANGE WITHOUT NOTIFICATION. 18" MIN. OF TAIL. (NEUTRAL CONDUCTOR MUST BE WHITE OR

More information

The Reliable Choice. Field Pocket Guide

The Reliable Choice. Field Pocket Guide The Reliable Choice Field Pocket Guide Allowable Ampacities of STABILOY Brand XHHW-2 and Copper 75 C (167 F) 90 C (194 F) 75 C (167 F) 90 C (194 F) Conductor Size (AWG or kcmil) Types RHW, THHW, THW, THWN,

More information

DIVISION 311 MISCELLANEOUS ELECTRICAL RULES

DIVISION 311 MISCELLANEOUS ELECTRICAL RULES DIVISION 311 MISCELLANEOUS ELECTRICAL RULES 918-311-0000 Design, Planning and Lay Out of Electrical Installations by Supervising Electricians A licensed supervising electrician may design, plan and lay

More information

INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE

INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE SAFETY BULLETIN #23 GUIDELINES FOR WORKING WITH LIGHTING SYSTEMS AND OTHER ELECTRICAL EQUIPMENT All electrical systems and electrically energized equipment

More information

2011/2008/2005 NATIONAL ELECTRICAL CODE SOLAR PV CODE COMPLIANCE REFERENCE

2011/2008/2005 NATIONAL ELECTRICAL CODE SOLAR PV CODE COMPLIANCE REFERENCE 2011/2008/2005 NATIONAL ELECTRICAL CODE SOLAR PV CODE COMPLIANCE REFERENCE PAGE 1 OF 5 This Reference provides a very comprehensive list of aspects of a solar PV installation that could be reviewed, clarifying

More information

ENTRANCE EQUIPMENT ER D PAGE 1 OF 5

ENTRANCE EQUIPMENT ER D PAGE 1 OF 5 PAGE 1 OF 5 USE: Requirements for entrance equipment. PREVIOUS REVISION 07-01-98 ORIGINATED 03-94 PREVIOUS NUMBER ER 100 (12-01-81) LATEST REVISION: Updated meter socket labeling specification and instrument

More information

2011 NEC Significant Changes Part 1 The following course will summarize many of the important changes to the NEC code.

2011 NEC Significant Changes Part 1 The following course will summarize many of the important changes to the NEC code. 2 PART 1 American Electrical Institute 2013 2011 NEC Significant Changes Part 1 The following course will summarize many of the important changes to the NEC code. The 2011 Code has added 3 new articles:

More information

SECTION PANELBOARDS

SECTION PANELBOARDS SECTION 16470 PANELBOARDS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. The general provisions of the contract including General and Special Conditions and General Requirements shall apply to all work under

More information

CHAPTER 10 ELECTRICAL

CHAPTER 10 ELECTRICAL 1001.0 General Requirements. 1001.1 Electrical Wiring and Equipment. Electrical wiring and equipment shall comply with the requirements of NFPA 70, National Electrical Code (NEC), or local ordinances.

More information

Michigan State University Construction Standards SECONDARY UNIT SUBSTATIONS PAGE

Michigan State University Construction Standards SECONDARY UNIT SUBSTATIONS PAGE PAGE 261116-1 SECTION 261116 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

ELECTRIC VEHICLE CHARGING FOR BUILDINGS

ELECTRIC VEHICLE CHARGING FOR BUILDINGS PLANNING & DEVELOPMENT SERVICES Office of the Chief Building Official BULLETIN 2015-004-BU/EL June 25, 2015 ELECTRIC VEHICLE CHARGING FOR BUILDINGS This bulletin provides clarification of requirements

More information

Service Entrance Methods

Service Entrance Methods Service Section Typical switchboards consist of a service section, also referred to as the main section, and one or more distribution sections. The service section can be fed directly from the utility

More information

ROCKY MOUNTAIN CHAPTER IAEI MARCH 15-16, 2012

ROCKY MOUNTAIN CHAPTER IAEI MARCH 15-16, 2012 ROCKY MOUNTAIN CHAPTER IAEI MARCH 15-16, 2012 1) Can a switched outlet be on a small appliance branch circuit for dining room lighting? No, a switched outlet on a general purpose branch circuit may be

More information

Table of Contents. CHAPTER 1 BASIC ELECTRICAL THEORY (Essential for Journeyman and Master s Licensing Exams)... 1

Table of Contents. CHAPTER 1 BASIC ELECTRICAL THEORY (Essential for Journeyman and Master s Licensing Exams)... 1 Introduction... x About This Textbook...xi Passing Your Exam...xiv How to Use the National Electrical Code... xviii About the Author...xxi About the Graphic Illustrator...xxii Mike Holt Enterprises Team...

More information

Fee $100 Course: NEC Proposed Changes Part 1 This course is valid for these credentials: Credential Description Cred Code Credit Hours

Fee $100 Course: NEC Proposed Changes Part 1 This course is valid for these credentials: Credential Description Cred Code Credit Hours www.garyklinka.com Page 1 of 31 Instructions: Fee $100 1. Print these pages. 2. Circle the correct answers and transfer them to the answer sheet. 3. Page down to the last page for the verification forms

More information

STOUGHTON UTILITIES ELECTRIC SERVICE RULES AND INFORMATION

STOUGHTON UTILITIES ELECTRIC SERVICE RULES AND INFORMATION CHAPTER 1 - GENERAL INFORMATION 100. Purpose 101. Codes and rules 102. Continuity of service 103. Frequency, Voltage, and Amperage Limitations 104. High voltages 105. Unusual capacity requirements 106.

More information

WISCONSIN ELECTRICIANS

WISCONSIN ELECTRICIANS Wisconsin Contractors Institute 2017 PART 2 3 CONTINUING EDUCATION FOR WISCONSIN ELECTRICIANS 2017 NEC Code Change Part 2 8 Hours WISCONSIN CONTRACTORS INSTITUTE N16 W23217 Stone Ridge Drive, Suite 290

More information

Solar Photovoltaic Power. Overarching Objectives. How many questions? 9/16/2012. From plan review to Final Inspection

Solar Photovoltaic Power. Overarching Objectives. How many questions? 9/16/2012. From plan review to Final Inspection Solar Photovoltaic Power From plan review to Final Inspection Overarching Objectives A understandable and predictable process for both the Installer and the Inspector. The installation of safe, efficient,

More information

10. METERING General Requirements

10. METERING General Requirements 10. METERING 10.1 General Requirements A. The Company will not supply service to a Customer whose wiring is designed for resale of electricity through submetering except for recreational campgrounds, marinas,

More information

Volume 2 Charts, Formulas, and Other Useful Information

Volume 2 Charts, Formulas, and Other Useful Information Volume 2 Charts, Formulas, and Other Useful Information Aluminum Conductor Conductor Terminations 61 Compact Aluminum (Conduit Fill Tables) 68-79 Ampacity Dwelling Services 48 1-phase Loads on a 3-phase

More information

SOME REVIEW - QUESTIONS 2011 NATIONAL ELECTRICAL CODE

SOME REVIEW - QUESTIONS 2011 NATIONAL ELECTRICAL CODE SOME REVIEW - QUESTIONS 2011 NATIONAL ELECTRICAL CODE J & W Educational Services 1340 Hickory Hill Dr. Watkinsville, Ga 30677 Jim Allison (706) 769-7112 jandw@uga.edu http://www.ugaed.com What is the Code

More information

ADVANCED CALCULATIONS

ADVANCED CALCULATIONS ADVANCED CALCULATIONS 101. Why is it permissible in some cases to fuse a #14 AWG motor conductor with a 60 amp breaker when normally a #14 AWG should only be fused at 15 amps? a) the motor can't start

More information

Learning Module 10: Loadcenters. 101 Basic Series

Learning Module 10: Loadcenters. 101 Basic Series Learning Module 10: Loadcenters 101 Basic Series What You Will Learn We ll step through each of these topics in detail: What Does a Loadcenter Do? 4 Applications 4 Basic Circuitry and Wiring 5 Residential

More information

2000 Cooper Bussmann, Inc. Page 1 of 9 10/04/00

2000 Cooper Bussmann, Inc. Page 1 of 9 10/04/00 DO YOU KNOW THE FACTS ABOUT SINGLE-POLE INTERRUPTING RATINGS? YOU MAY BE IN TROUBLE! Typical plant electrical systems use three-phase distribution schemes. As an industry practice, short-circuit calculations

More information

Table of Contents. CHAPTER 1 ElECTRiCAl THEoRY Mike Holt enterprises, inc neC.Code ( )

Table of Contents. CHAPTER 1 ElECTRiCAl THEoRY Mike Holt enterprises, inc neC.Code ( ) CHAPTER 1 ElECTRiCAl THEoRY... 1 UniT 1 electrician s MaTH and BasiC electrical formulas... 3 Introduction to Unit 1... 3 Part A Electrician s Math... 3 Introduction... 3 1.1 Whole Numbers... 3 1.2 Decimals...

More information

Generator Fire Safety: Generator assemblies should be located outside the building.

Generator Fire Safety: Generator assemblies should be located outside the building. SECTION 33 70 00 - ELECTRICAL DISTRIBUTION PACKAGED GENERATOR ASSEMBLIES Generator Fire Safety: Generator assemblies should be located outside the building. All fuel piping from the outside of the building

More information

Know the Code: PV and NEC

Know the Code: PV and NEC Know the Code: PV and NEC September 2014 PV Installer's Course ---NEC Article 690 Highlights 1 First National Electrical Code 1881 September 2014 PV Installer's Course ---NEC Article 690 Highlights 2 The

More information

CONTINUING EDUCATION FOR OREGON ELECTRICIANS NEC Code Change Part 2 Course # Hours

CONTINUING EDUCATION FOR OREGON ELECTRICIANS NEC Code Change Part 2 Course # Hours AMERICAN ELECTRICAL INSTITUTE 2017 PART 2 3 CONTINUING EDUCATION FOR OREGON ELECTRICIANS 2017 NEC Code Change Part 2 Course #90817 8 Hours AMERICAN ELECTRICAL INSTITUTE N16 W23217 Stone Ridge Drive, Suite

More information

Table of Contents. Unit 3 Magnetism Unit 1 Matter Unit 4 Electricity Unit 2 Electron Theory Unit 5 Electromagnetism...

Table of Contents. Unit 3 Magnetism Unit 1 Matter Unit 4 Electricity Unit 2 Electron Theory Unit 5 Electromagnetism... Introduction...x How to Use This Textbook...xi About the Author...xii About the Graphic Illustrator...xiii Mike Holt Enterprises Team...xiv Chapter 1 Electrical Fundamentals... 1 Unit 1 Matter... 3 Introduction...

More information

Supply-Side PV Connections

Supply-Side PV Connections Perspectives on PV Supply-Side PV Connections by John Wiles Plan reviewers and inspectors throughout the country are seeing increasing numbers of supply-side connected utility interactive photovoltaic

More information

Metering and Service Installation:

Metering and Service Installation: Table of Contents 1. Metering Installation Requirements, General... 1 2. Type of Service... 2 3. Definitions... 2 4. Who Provides Metering Equipment?... 2 5. Establishment of Service... 2 6. Meter Access...

More information

Data Bulletin. Ground-Censor Ground-Fault Protection System Type GC Class 931

Data Bulletin. Ground-Censor Ground-Fault Protection System Type GC Class 931 Data Bulletin 0931DB0101 July 2001 Cedar Rapids, IA, USA Ground-Censor Ground-Fault Protection System Type GC Class 931 09313063 GT Sensor Shunt Trip of Circuit Interrupter Window Area for Conductors GC

More information

High Reliability Power System Design

High Reliability Power System Design High Reliability Power System Design Buenos Aires, Argentina June 25 & 26, 2009 Keene M. Matsuda, P.E. Regional Electrical Manager Senior Member IEEE IEEE/PES Distinguished Lecturer ke.matsuda@ieee.org

More information

Temporarily Approved Solar Photovoltaic System Electrical Schematics

Temporarily Approved Solar Photovoltaic System Electrical Schematics March 20, 2019 Page 1 of 10 Temporarily Approved Solar Photovoltaic System Electrical Schematics This document is intended as a temporary interpretation of approved solar photovoltaic electrical schematics

More information

AGRICULTURAL UNDERGROUND SERVICE 500 HP OR LESS

AGRICULTURAL UNDERGROUND SERVICE 500 HP OR LESS Prepared by: ABB1 AGRICULTURAL UNDERGROUND SERVICE 500 HP OR LESS 05619 Asset Type: Electric Metering Function: Design and Construction Issued by: Lisseth Villareal (LDV2) Date: 07-31-15 Rev. #10: This

More information

10 Commercial, Industrial, Agricultural Services

10 Commercial, Industrial, Agricultural Services 10 Commercial, Industrial, Agricultural Services This section describes the Power Company requirements for commercial, industrial, and agricultural services. This section covers single phase and three

More information

SURFACE TRACK (120/250V) SPECIFICATIONS

SURFACE TRACK (120/250V) SPECIFICATIONS SURFACE TRACK (120/250V) SPECIFICATIONS GENERAL Lighting Track shall allow fixtures to be located anywhere along the track length. Fixtures shall be easily focused, switched, dimmed, accessorized and removed

More information

WIRING DESIGN & PROTECTION REQUIREMENTS CHECKLIST

WIRING DESIGN & PROTECTION REQUIREMENTS CHECKLIST WIRING DESIGN & PROTECTION REQUIREMENTS CHECKLIST Use & Identification of Grounded and Grounding Conductors YES NO N/A Grounded conductors are identifiable and distinguishable from all other conductors.

More information

UNDERGROUND SERVICE. Items to consider. There will be charges from ComEd if you convert from overhead to underground service.

UNDERGROUND SERVICE. Items to consider. There will be charges from ComEd if you convert from overhead to underground service. UNDERGROUND SERVCE tems to consider f your trenching route has to be dug by hand, or if a cable must be installed under a paved surface, additional charges apply. f your service cable has to be moved later

More information