90.2 Scope. The installation of electrical conductors, equipment and raceways for:
|
|
- Eleanore Joseph
- 5 years ago
- Views:
Transcription
1 NEC Generator Primer Rules on the installation of generators and transfer switches Scope The installation of electrical conductors, equipment and raceways for: public and private premises Conductors and equipment that connect to the supply of electricity Generators and transfer switches are equipment 2 Article 445 Generators 3 1
2 Generators shall be of a type suitable for the locations in which they are installed. They also shall satisfy Generators shall be located such that: Adequate ventilation can be provided Maintenance can be readily accomplished Generators to have a nameplate giving: Manufacturer Frequency, PF and phases Subtransient and transient impedances Rating in kw or kva Voltage and ampere rating and rpm Insulation system class Rated ambient temperature or temperature rise Time rating
3
4 Generator Rating Definitions Standby Rating: Applicable for supplying emergency power for the duration of normal power interruption. No sustained overload capability is available for this rating. Prime (Unlimited Running Time) Rating: Applicable for supplying power in lieu of commercially purchased power. Prime power is the maximum power available at a variable load for an unlimited number of hours. A 10% overload capability is available for limited time. Base Load (Continuous) Rating: Applicable for supplying power continuously to a constant load up to the full output rating for unlimited hours. No sustained overload capability is available for this rating
5 Overcurrent Protection (A) Constant voltage generators shall be protected from overload by Inherent design Circuit breakers Fuses Protective relays Other identified means suitable for the conditions of use
6 Overcurrent Definition: Any current in excess of the rated current of equipment or the ampacity of a conductor. It may result from overload, short circuit or ground fault Overcurrent Protection, Location in Circuit (G) Conductors from Generator Terminals. Conductors from generator terminals that meet the size requirement in shall be permitted to be protected against overload by the generator overload protective device(s) required by
7 Ampacity of Conductors Shall be 115% of the nameplate current rating It is permitted to derate neutral per for the maximum unbalanced load Conductors that carry ground fault currents shall not be smaller than required by (A)
8 Disconnecting Means Required for Generators Generators shall be equipped with disconnect(s), lockable in the open position to disconnect entirely the generator and all protective devices and control apparatus Exceptions: If the driving means can be readily shut down, and If the generator is not arranged to operate in parallel with another generator or other source of power
9 Wiring, Emergency System (B) wiring from an emergency source to emergency loads shall be kept entirely independent of all other loads with some exceptions IBC Chapter 27, Electrical Emergency loads: Egress lighting Exit signs Voice alarm communications in places of assembly Semiconductor fabrication facilities High-rise and underground buildings Prisons and jails Storage or manufacture of: Hazardous material Highly toxic material Pyrophoric materials 27 9
10 Emergency and Legally Required Standby Electrical Power Sources NFPA 110 Referenced by Informational Note in Referenced by IBC (required to be used) Requires a remote manual stop station Located outside the room housing the prime mover Requires an audible alarm Requires battery powered emergency lighting Requires an initial acceptance test with AHJ Prime movers to comply with NFPA 37 NFPA 37 Engine rooms located within structures to have minimum 1 hour walls, floor and ceiling. Engines on roofs shall be minimum 5 feet from openings and any combustible structures or walls. Engines located outdoors shall be a minimum 5 feet from openings and any combustible structures or walls. NFPA s opinion A generator is considered a source of ignition as it contains an internal combustion engine
11 Clearances from Propane Clearances from propane Is a propane optional standby generator considered a source of ignition at a residential dwelling? ANSWER: YES If the propane generator is considered a source of ignition, how far from the generator should the gas regulator be installed? ANSWER: The issue is not the regulator location but the discharge from the regulator which needs to be 5 feet from a source of ignition. How far from the generator should the relief valve be installed? ANSWER: See answer #2 What is the distance that the propane generator should be located from the propane tank? ANSWER: 10 Feet JOHN DOUCETTE OFFICE OF STATE FIRE MARSHAL Photo Contributed by Joseph Summers
12 Clearances from air intake IRC and IMC require a clearance of 2 feet above any mechanical air intake opening within 10 feet of the exhaust pipe discharge Includes windows that open, fresh air and combustion air intakes 2011 NEC Generators Supplying Multiple Loads Shall be permitted to supply either: A vertical switchboard with separate sections Individual enclosures with overcurrent protection tapped from a single feeder for load separation and distribution if provided with OC protection
13 Article 702 Optional Standby Systems
14 702.1 Scope The systems covered by Article 702 consist of those that are permanently installed, including prime movers, and those that are arranged for a connection to a premises wiring system from a portable alternate power supply
15 702.1 Scope A portable generator used for temporary power, like those used on construction sites, doesn't fall within the scope of Article 702 unless the generator is connected to the premises wiring Definition Optional Standby Systems. Optional standby systems are intended to supply power to public or private facilities or property where life safety doesn't depend on the performance of the system
16 702.2 Definition Optional standby systems typically provide electric power for processes that, when stopped could cause discomfort, economic loss, serious interruption of the process, or damage to the product or process Definition Can be either manual or automatic, selected, partial or total loads IBC Chapter 27, Electrical Lists when Emergency and Legally required standby systems are required All other systems are optional standby
17 2011 NEC Capacity and Rating An optional standby system must have adequate capacity to carry safely all loads that are expected to operate simultaneously. The user of the optional standby system can select the loads connected to the system. 49 Choose the loads straight from the panel NEC HANDBOOK The standby source must have the capacity to supply all of the loads connected to it, unless an automatic load management system is used to ensure that the transferred load does not overload the source. This requirement applies only to systems where the switching between power sources occurs automatically
18 2011 NEC Section If an automatic transfer switch is used: Standby source must be capable of handling the full load to be transferred, OR An automatic load shedding capability shall be installed to limit the load to that the standby source can handle 54 18
19 Transfer Equipment Equipment shall be suitable for the intended use A transfer switch is required for all fixed or portable optional standby power systems
20 702.5 Transfer Equipment Ex: Transfer switch not required for temporary connection, where written safety procedures and conditions of maintenance and supervision ensure that only qualified persons will service the installation if: The normal supply is physically isolated by a lockable disconnecting means or The normal supply conductors are disconnected Wiring The optional standby system wiring can occupy the same raceways, cables, boxes, and cabinets with other general wiring
21 Portable Generators When the portable generator is a separately derived system, the generator(s) must be grounded and bonded in accordance with
22 Outdoor Generator Sets Where an outdoor-housed generator is equipped with a readily accessible disconnecting means that is located within sight of the building or structure, an additional disconnecting means isn't required for the generator feeder conductors that serve or pass through the building or structure. Article 250 on Grounding Generators
23 250.34(A) Portable Generators (B) Vehicle-mounted Frames are not required to be connected to a grounding electrode if: Only cord connected equipment is energized, or Only generator mounted equipment is energized, or both, and The non-current carrying metal parts and the grounding terminals of receptacles are connected to the frame Vehicle frame not required to be connected to a grounding electrode if: Frame of generator is bonded to the vehicle frame, and Only equipment on the vehicle or cord connected loads are energized, and The non-current carrying metal parts and the grounding terminals of receptacles are connected to the frame 69 23
24 250.34(C) Grounded Conductor Bonding With both portable and vehicle mounted generators: A system conductor (i.e. neutral) is required to be grounded. It shall be connected to the generator frame where the generator is a component of a separately derived system
25 Grounding Separately Derived AC Systems In addition to (A), grounded systems shall also comply with , , and tells which systems must be grounded tells which systems might not be grounded tells which circuits must not be grounded tells which conductor must be grounded With most voltages over 50 volts and most systems, the neutral is the conductor to be grounded Article Definitions The definition of a Separately Derived System was amended and simplified for clarity Separately Derived System. A premises wiring system whose power is derived from a source of electric energy or equipment other than a service Such systems have no direct electrical connection from circuit conductors of one system to circuit conductors of another system, other than connections through the earth, metal enclosures, metallic raceways, or equipment grounding conductors including a solidly connected grounded circuit conductor, to supply conductors originating in another system (B) AC Systems to be grounded 240/120 volt systems that supply premises wiring are required to be grounded. Neutral is required to be grounded Article 100: Grounded Connected to ground or to a conductive body that extends the ground connection. If the generator neutral is not bonded to the frame it is not a separately derived system The service GES provides the conductive body that extends the ground connection
26 250.30(A) Grounded Systems Please note no generator frame ground connection A separately derived system shall have: An unspliced system bonding jumper which shall be connected at any point from the source to the first disconnecting means 78 26
27 Please note generator frame grounding connection CONDITIONS WHERE GROUNDING THE GENERATOR FRAME TO GROUNDING ELECTRODE SYSTEM IS REQUIRED: 1. The generator is not part of a separately derived system, OR 2. It has its neutral conductor solidly interconnected to a service-supplied system neutral, OR 3. It supplies auxiliary power output (115 volts AC / 230 volts AC) by means other than cord-and-plug connection through receptacles mounted on the generator, such as connections to internal terminals on the generator hard wired (see equipment Owner s Manual for grounding instructions)
28 CONDITIONS WHERE GROUNDING THE GENERATOR FRAME TO A GROUNDING ELECTRODE SYSTEM IS NOT REQUIRED: 1. The generator has auxiliary power output (115 volts AC or 230 volts AC) and the generator receptacles have a ground pin outlet available for the equipment that plugs into the receptacle, AND 2. The generator is portable or mounted on a truck or trailer, AND 3. The auxiliary power is used by cord-and plugconnection means through receptacles mounted on the generator, AND 4. The generator is mounted on a vehicle and the generator frame is bonded to the vehicle frame. 82 The decision is based on what you do with your auxiliary power: If you just plug equipment into the receptacles, connection to the vehicle frame is fine. If you hard wire the auxiliary power into another electrical system, then you must connect the generator frame to a grounding electrode system 83 Article 225 on Generators 84 28
29 Number of Supplies (A) Special Conditions. Additional feeders shall be permitted for: Fire pumps Emergency systems Legally required standby systems Optional standby systems Parallel power production systems Multiple sources of supply Disconnecting Means Means shall be provided to disconnect all ungrounded conductors that supply or pass through the building or structure Location The disconnecting means shall be installed at a readily accessible location nearest the point of entrance of the conductors
30 Suitable for Service Disconnect Identification The disconnecting means specified in shall be suitable for use as service equipment. A permanent plaque or directory shall be installed at each disconnect location denoting all other services, feeders or branch circuits supplying that building or structure Article 230 on Generators
31 230.2 Number of Services Marking 100 Definition Service Equipment (E) Identification Where a building is supplied by a combination of feeders and services, a permanent plaque or directory shall be installed at each service disconnect location denoting all other sources supplying the building or structure Service equipment shall be marked to identify it as being suitable for use as service equipment. All service equipment shall be listed. The necessary equipment connected to the load end of service conductors to a building or structure
32 Equipment Connected to the Supply Side of Service Disconnect Only the following equipment is allowed: (3) Meter disconnect switches with short circuit ratings equal to or greater than the available short-circuit rating Official Word The Generlink has been approved for use jointly by the CT DCP and Connecticut Light and Power. There are rules:
33 CL and P rules for Generlink Home owners are suggested to have a EC do the work OR must do paperwork to disconnect power get inspection approved and then arrange for a reconnection of power Pre-approved EC allowed to remove and put meter back in after install. Must have permit and CSR prior to installation Inspector has nothing to see when installed Only the paper trail Suggest electrical contractor take pictures Equipment Connected to the Supply Side of Service Disconnect Only the following equipment is allowed: (5) Taps used only to supply.circuits for standby power systems If provided with service equipment and installed in accordance with requirements for service entrance conductors. Standby power systems are allowed to be connected ahead of the normal service disconnecting means only if it is provided with a separate disconnecting means and overcurrent protection. 98 TS Connected Ahead of Main Must be listed and marked as suitable for use as service equipment (230.66) Must match ampacity and voltage of service (230.90) Must be adequate for available fault current (110.9) Service ends at first disconnect on building Grounding of grounded conductor must occur on the line side of or in same enclosure as disconnect (250.24(A)(1), (A)) 99 33
34 Overcurrent Protection Synchronous Generators Article 705 Interconnected Electric Power Production Sources Part III Generators Conductors to be protected per Article 240 Equipment and conductors to have OC protection to protect from all sources Generators to be protected per Parallel production generators shall have the necessary equipment to establish and maintain a synchronous condition
35
MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 9/14/11 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions
MECKLENBURG COUNTY Land Use and Environmental Service Agency Code Enforcement 9/14/11 ELECTRICAL CONSISTENCY MEETING Code Consistency Questions 1. I recently installed a 45-KVA transformer, 480-volt primary
More informationNEC REQUIREMENTS FOR GENERATORS
PROFESSIONAL DEVELOPMENT SEMINAR SERIES NEC REQUIREMENTS FOR GENERATORS (Based on NEC 2005 with limited 2008 commentary) AIA certified Continuing Education Units (CEU) Available GPS-140 National Electric
More informationCHAPTER 10 ELECTRICAL. Notes:
CHAPTER 10 ELECTRICAL 1001.0 General Requirements. Electrical wiring and equipment shall comply with the requirements of NFPA 70, National Electrical Code (NEC), or local ordinances. 1002.0 Solar Photovoltaic
More informationOptimizing Emergency Power Systems for Health Care Applications
2018 Annual Conference Optimizing Emergency Power Systems for Health Care Applications aka: Using the latest code changes to improve system reliability and maybe even save some $$$... Overview Michigan
More informationCorrections most seen on plan review October 18, 2017 David Rankin Seattle Department of Construction and Inspections
Corrections most seen on plan review October 18, 2017 David Rankin Seattle Department of Construction and Inspections One-Line / Riser Diagrams Drawings are not reviewed prior to submission. Because of
More informationWIRING DESIGN & PROTECTION REQUIREMENTS CHECKLIST
WIRING DESIGN & PROTECTION REQUIREMENTS CHECKLIST Use & Identification of Grounded and Grounding Conductors YES NO N/A Grounded conductors are identifiable and distinguishable from all other conductors.
More informationSINGLE PHASE WIRING SPECIFICATIONS
SINGLE PHASE WIRING SPECIFICATIONS 1-866-MEC-ELEC (1-866-632-3532) Office Locations: Hondo Office 237 Hwy 173 N Hondo, TX 78661-0370 Fax 830.426.3335 Dilley Office 1718 W. FM 117 Dilley, TX 78017 Fax 830.965.1425
More informationSUPPLEMENTAL CORRECTION SHEET FOR SOLAR PHOTOVOLTAIC SYSTEMS - ELECTRICAL
SUPPLEMENTAL CORRECTION SHEET FOR SOLAR PHOTOVOLTAIC SYSTEMS - ELECTRICAL This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly.
More informationTHREE PHASE WIRING SPECIFICATIONS
THREE PHASE WIRING SPECIFICATIONS 1-866-MEC-ELEC (1-866-632-3532) Office Locations: Hondo Office 237 Hwy 173 N Hondo, TX 78661-0370 Fax 830.426.3335 Dilley Office 1718 W. FM 117 Dilley, TX 78017 Fax 830.965.1425
More informationThis is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly.
SUPPLEMENTAL CORRECTION SHEET FOR SOLAR PHOTOVOLTAIC SYSTEMS (ELEC) This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly.
More information2016 Photovoltaic Solar System Plan Review List
Building Division 555 Santa Clara Street Vallejo CA 94590 707.648.4374 2016 Photovoltaic Solar System Plan Review List GENERAL PROJECT INFORMATION PLAN CHECK NO DATE JOB ADDRESS CITY ZIP REVIEWED BY PHONE
More informationPhotovoltaic Solar Plan Review
PAIGE B. VAUGHAN, CBO Director of Building and Safety Phone (310) 605-5509 Fax Line (310) 605-5598 E-mail:lbutler@comptoncity.org Building & Safety Department Photovoltaic Solar Plan Review Plan Check
More informationWISCONSIN ELECTRICIANS
Wisconsin Contractors Institute 2017 PART 2 3 CONTINUING EDUCATION FOR WISCONSIN ELECTRICIANS 2017 NEC Code Change Part 2 8 Hours WISCONSIN CONTRACTORS INSTITUTE N16 W23217 Stone Ridge Drive, Suite 290
More informationMECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 2/8/12 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions
MECKLENBURG COUNTY Land Use and Environmental Service Agency Code Enforcement 2/8/12 ELECTRICAL CONSISTENCY MEETING Code Consistency Questions 1. I am inspecting a building addition. They have a 480V to
More informationCONTINUING EDUCATION FOR OREGON ELECTRICIANS NEC Code Change Part 2 Course # Hours
AMERICAN ELECTRICAL INSTITUTE 2017 PART 2 3 CONTINUING EDUCATION FOR OREGON ELECTRICIANS 2017 NEC Code Change Part 2 Course #90817 8 Hours AMERICAN ELECTRICAL INSTITUTE N16 W23217 Stone Ridge Drive, Suite
More informationChapter 5. Imagine That Engineering Inc. Assured Equipment Grounding Conductor Program (AEGCP) Ground Fault Circuit Interrupter (GFCI)
Chapter 5 Imagine That Engineering Inc. Assured Equipment Grounding Conductor Program (AEGCP) Ground Fault Circuit Interrupter (GFCI) Imagine That Engineering Inc. has adopted this program for equipment
More information9/16/2010. Chapter , The McGraw-Hill Companies, Inc. TRANSMISSION SYSTEMS. 2010, The McGraw-Hill Companies, Inc.
Chapter 3 TRANSMISSION SYSTEMS 1 Transmitting large amounts of electric energy over long distances is accomplished most efficiently by using high-voltages. Without transformers the widespread distribution
More informationChapter 2 Wiring and Protection Article 200 Use and Identification of Grounded Neutral Conductor Chapter 1 General...9
Article 90 Introduction...1 90.1 Purpose of the NEC...1 90.2 Scope of the NEC...2 90.3 Code Arrangement...4 90.4 Enforcement...5 90.5 Mandatory Requirements and Explanatory Material...6 90.6 Formal Interpretations...6
More informationFee $20 Course: NEC Changes 1 This course is valid for these credentials: Credential Description Cred Code Credit Hours
www.garyklinka.com Page 1 of 18 Instructions: Fee $20 1. Print these pages. 2. Circle the correct answers and transfer them to the answer sheet. 3. Page down to the last page for the verification forms
More information9/7/2010. Objectives. Article 90. Introduction NEC Significant Changes. Review significant revisions in the 2011 NEC
2011 NEC Significant Changes Courtesy of NJATC Courtesy of NFPA Presented By: Michael J. Johnston Executive Director of Standards and Safety, NECA Objectives Review significant revisions in the 2011 NEC
More informationSpring Test 7 due 05/03/2013
Spring Test 7 due 05/03/2013 Multiple Choice Identify the choice that best completes the statement or answers the question. 1. A raceway contains two 3-phase, 3-wire circuits that supply 38 ampere continuous
More informationCHAPTER 10 ELECTRICAL
1001.0 General Requirements. 1001.1 Electrical Wiring and Equipment. Electrical wiring and equipment shall comply with the requirements of NFPA 70, National Electrical Code (NEC), or local ordinances.
More informationTEMPORARY ELECTRIC WIRING FOR CARNIVALS, CONVENTIONS, EXHIBITIONS, FAIRS AND SIMILAR USES
INFORMATION BULLETIN / PUBLIC - ELECTRICAL CODE REFERENCE NO.: LAMC 93.0230 Effective: 3-24-69 DOCUMENT NO. P/EC 2002-006 Revised: 11-17-00 Previously Issued As: RGA #7-69 TEMPORARY ELECTRIC WIRING FOR
More informationCHAPTER V RESIDENTIAL WIRING
CHAPTER V RESIDENTIAL WIRING 5.1. THE SERVICE ENTRANCE Buildings and other structures receive the electrical energy through the service entrance. In residential wiring, the electric company supply this
More information2014 NEC Changes Part 4
www.garyklinka.com Page 1 of 14 Instructions: Fee $25 1. Print these pages. 2. Circle the correct answers and transfer them to the answer sheet. 3. Page down to the last page for the verification forms
More informationTechnical Summary of Battery Energy Storage Systems
Technical Summary of Battery Energy Storage Systems Based on the 2017 Massachusetts Electrical Code This document summarizes the new Article 706 in the Massachusetts Electrical Code (MEC). Article 706
More informationDefinitions of and have been revised. a. automatic b. nonautomatic c. none of the above d. both a and b
www.garyklinka.com Page 1 of 12 Instructions: Fee $25 1. Print these pages. 2. Circle the correct answers and transfer them to the answer sheet. 3. Page down to the last page for the verification forms
More informationENGINEERING SPECIFICATION
December 206 ENGINEERING SPECIFICATION No. of 6 DATE: 2-9-6 CATEGORY SUBJECT TABLE OF CONTENTS. Overview... 2 2. General Requirements for Service... 3 3. Definitions... 3 4. Abbreviations... 5 5. References
More informationTRANSMISSION SYSTEMS
TRANSMISSION SYSTEMS Transmitting large amounts of electric energy over long distances is accomplished most efficiently by using high-voltages. Without transformers the widespread distribution of electric
More informationDISCONNECT SWITCH REQUIREMENTS FOR DISTRIBUTED GENERATION CUSTOMERS
Prepared by: SXZO DISCONNECT SWITCH REQUIREENTS FOR DISTRIBUTED GENERATION CUSTOERS 060559 Department: Electric Distribution Section: Design and Construction Approved by: D.Jantz (DWJ7) Date: 8/15/17 Rev.
More informationHave You Been Grounded Lately
Have You Been Grounded Lately Thurs, Oct. 26, 2017 9:15-10:15 Phil Simmons Author, Electrical Grounding and Bonding Author Cengage Learning Phil Simmons Have You Been Grounded Lately 2017 NEC Changes Relative
More informationCOMMERCIAL QUICK REFERENCE
COMMERCIAL QUICK REFERENCE PROVO CITY POWER STANDARDS ELECTRICAL ENGINEERING UPDATED: 2016 SPECIFICATIONS SUBJECT TO CHANGE WITHOUT NOTIFICATION. 18" MIN. OF TAIL. (NEUTRAL CONDUCTOR MUST BE WHITE OR
More informationSOLAR PV STANDARD PLAN - COMPREHENSIVE Central/String Inverter Systems for One and Two Family Dwellings
SCOPE: Use this plan ONLY for utility-interactive central/string inverter systems not exceeding a total combined system ac inverter output rating of 10kW on the roof of a one- or two-family dwelling or
More informationPretest Module 24 Three-phase Service Entrance
Pretest Module 24 Three-phase Service Entrance 1. What is the most widely used three-phase service entrance system? 2. What are the three most common voltage combinations for three-phase, four-wire systems?
More informationSOLAR PHOTOVOLTAIC SYSTEMS INSPECTOR CHECKLIST
SOLAR PHOTOVOLTAIC SYSTEMS INSPECTOR CHECKLIST The following checklist is an outline of the general requirements found in the 1999 National Electrical Code (NEC) Article 690 for Photovoltaic (PV) Power
More informationMike Holt s Illustrated Guide to SOLAR PV SYSTEMS
Mike Holt s Illustrated Guide to Directory, Identification, Label, Marking, Plaque, and Sign Requirements for SOLAR PV SYSTEMS Extracted From Mike Holt s Illustrated Guide to Understanding NEC Requirements
More informationManaging Electric Vehicle Supply Equipment (EVSE) Installations
Managing Electric Vehicle Supply Equipment (EVSE) Installations Introduction to Electric Vehicle EVSE Electric vehicles create a need to build an infrastructure that will supply the added load of charging.
More information2011/2008/2005 NATIONAL ELECTRICAL CODE SOLAR PV CODE COMPLIANCE REFERENCE
2011/2008/2005 NATIONAL ELECTRICAL CODE SOLAR PV CODE COMPLIANCE REFERENCE PAGE 1 OF 5 This Reference provides a very comprehensive list of aspects of a solar PV installation that could be reviewed, clarifying
More informationELECTRIC SERVICE RULES DISTRIBUTED GENERATION Issued Jan 2016
DISTRIBUTED GENERATION CHAPTER 5 500. SCOPE This chapter includes distributed or customer-owned generation connected in parallel and operating with Alliant Energy s electric distribution system. For all
More informationECET Circuit Design Motor Loads. Branch Circuits. Article 210
ECET 4520 Industrial Distribution Systems, Illumination, and the NEC Circuit Design Motor Loads Branch Circuits Article 210 210.1 Scope This article covers branch circuits except for those that supply
More informationENTRANCE EQUIPMENT ER D PAGE 1 OF 5
PAGE 1 OF 5 USE: Requirements for entrance equipment. PREVIOUS REVISION 07-01-98 ORIGINATED 03-94 PREVIOUS NUMBER ER 100 (12-01-81) LATEST REVISION: Updated meter socket labeling specification and instrument
More informationPHOTOVOLTAIC ELECTRICAL POWER SYSTEMS INSPECTOR/INSTALLER CHECKLIST
PHOTOVOLTAIC ELECTRICAL POWER SYSTEMS INSPECTOR/INSTALLER CHECKLIST The following checklist is an outline of the general requirements found in the 2005 National Electrical Code (NEC) Article 690 for Photovoltaic
More informationSolar PV Standard Electrical Plan
*** Provide this document to the inspector along with ALL system installation instructions *** Project Address: Permit Number: SCOPE: Standard plan for installation of solar PV systems utilizing 2 wire
More information2014 NEC Changes (Homestudy)
2014 NEC Changes (Homestudy) Idaho Electrical License This course will review the most important National Electrical Code changes from the 2014 NEC. Changes in Articles 100 - Chapter 9 will be covered.
More informationArc Fault Circuit Interrupter (AFCI) FACT SHEET
Arc Fault Circuit Interrupter (AFCI) FACT SHEET THE AFCI The AFCI is an arc fault circuit interrupter. AFCIs are newly-developed electrical devices designed to protect against fires caused by arcing faults
More informationSupply-Side PV Connections
Perspectives on PV Supply-Side PV Connections by John Wiles Plan reviewers and inspectors throughout the country are seeing increasing numbers of supply-side connected utility interactive photovoltaic
More informationINSPECTION REQUIREMENTS: PHOTOVOLTAIC (PV) RESIDENTIAL
Photovoltaic (PV) Residential Page 1 of 10 Revision Date: 07/18/2018 INSPECTION REQUIREMENTS: PHOTOVOLTAIC (PV) RESIDENTIAL INSPECTION CODE: 703 SCOPE: RESIDENTIAL APPLICABLE CODES: 2016 CBC, CRC, CPC,
More information2. DEFINITIONS. 2.3 APPROVED Acceptable to the authority enforcing the National Electric Code
2. DEFINITIONS 2.1 ACCEPTABLE Acceptable to the Company. 2.2 ADVANCED METER A meter that is capable of remote reading, and is capable of storing electric consumption data at specified time intervals of
More informationMetering and Service Installation:
Table of Contents 1. Metering Installation Requirements, General... 1 2. Type of Service... 2 3. Definitions... 2 4. Who Provides Metering Equipment?... 2 5. Establishment of Service... 2 6. Meter Access...
More informationSolar PV Standard Plan Simplified Central/String Inverter Systems for One- and Two-Family Dwellings
Your City logo here Solar PV Standard Plan Simplified Central/String Inverter Systems for One- and Two-Family Dwellings SCOPE: Use this plan ONLY for utility-interactive central/string inverter systems
More informationSolar PV Standard Plan Simplified Central/String Inverter Systems for One- and Two-Family Dwellings
PV TOOLKIT DOCUMENT #3 Solar PV Standard Plan Simplified Central/String Inverter Systems for One- and Two-Family Dwellings SCOPE: Use this plan ONLY for utility-interactive central/string inverter systems
More informationMicroinverters and AC PV modules are becoming. Microinverters and AC PV Modules. Different Beasts. Perspectives on PV.
Perspectives on PV Microinverters and AC PV Modules Are Different Beasts by John Wiles Microinverters and AC PV modules are becoming very common in residential and small commercial PV systems. See photos
More informationSECTION LOW VOLTAGE DISTRIBUTION EQUIPMENT
SECTION 16400 LOW VOLTAGE DISTRIBUTION EQUIPMENT A. General 1. The University does not accept Series-Rated equipment for power distribution switchboards, distribution panels and branch circuit panelboards.
More informationFig. 1. Sample calculation for determining the proper conductor size needed to serve a motor controller and avoid voltage drop problems.
Power to the Pump By Mike Holt, NEC Consultant Why some fire pump requirements are "backward" One of the principal NEC requirements for circuit protection is that you shut down the equipment rather than
More information2014 NEC Analysis Part 2
www.garyklinka.com Page 1 of 24 Instructions: Fee $65 1. Print these pages. 2. Circle the correct answers and transfer them to the answer sheet. 3. Page down to the last page for the verification forms
More informationPermit for Charging Equipment Installation Electric Vehicle Supply Equipment (EVSE)
Permit for Charging Equipment Installation Electric Vehicle Supply Equipment (EVSE) Town of Lake George, New York Compliance with the following permit will allow the installation and operation of electric
More informationINDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE
INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE SAFETY BULLETIN #23 GUIDELINES FOR WORKING WITH LIGHTING SYSTEMS AND OTHER ELECTRICAL EQUIPMENT All electrical systems and electrically energized equipment
More informationOvercurrent Protection (2014 NEC) (Homestudy)
Overcurrent Protection (2014 NEC) (Homestudy) Oregon Electrical License The key sections of Article 240 will be discussed. Overcurrent protection for panelboards, appliances, motors, motor compressors,
More informationGenerator Fire Safety: Generator assemblies should be located outside the building.
SECTION 33 70 00 - ELECTRICAL DISTRIBUTION PACKAGED GENERATOR ASSEMBLIES Generator Fire Safety: Generator assemblies should be located outside the building. All fuel piping from the outside of the building
More informationSolar PV Standard Electric Plan
*** Provide this document to the inspector along with ALL system installation instructions *** SCOPE: Standard plan for the installation of microinverter solar PV systems, not exceeding a total AC output
More information9. Non-Residential Services (Commercial, Industrial, and Agricultural)
Section 9 2016 Electric Service Requirements, 3rd Edition Section 9 Non-Residential Services Directory Page 9.1 General Requirements 68 9.2 Direct-Connect Metering, Single Installations 69 9.3 Direct-Connect
More informationSECTION 1: Field Inspection Guide for Rooftop Photovoltaic (PV) Systems
COUNTY OF SANTA CRUZ PLANNING DEPARTMENT 701 OCEAN STREET, 4 th FLOOR, SANTA CRUZ, CA 95060 (831) 454-2580 FAX: (831) 454-2131 TDD: (831) 454-2123 KATHLEEN MOLLOY PREVISICH, PLANNING DIRECTOR Photovoltaic
More informationNEC 2011 Code Changes
NEC 2011 Code Changes Articles 280.21-300.50 CHANGES FROM 2008 TO 2011 CODE ARE IN RED Chapter 2 - Wiring and Protection ARTICLE 280 Surge Arresters, Over 1kV III. Connecting Surge Arresters 280.21 Connection
More informationDIY 15 Amp Portable Generator Transfer Switch
DIY 15 Amp Portable Generator Transfer Switch ------------------------------------------------------------------------------------------------- WARNING You MUST read these warnings before proceeding. This
More informationChapter 8 Interior Wiring and Lighting
Chapter 8 Interior Wiring and Lighting Review Questions 1. What tool if any, is used to remove a fuse that is to be replaced? 1. Pliers 2. Screwdriver 3. Fuse puller 4. None 2. OSHA has established specific
More informationSpring Test 10 due 05/11/2013
Spring Test 10 due 05/11/2013 Multiple Choice Identify the letter of the choice that best completes the statement or answers the question. 1. When installed in an agricultural building that houses livestock
More informationOvercurrent Protection According to the 2011 NEC
Overcurrent Protection According to the 2011 NEC Utah Electrical License This course will cover overcurrent protection according to the 2011 NEC. The key sections of Article 240 will be discussed. Overcurrent
More informationSolar PV Standard Plan Simplified Microinverter and ACM Systems for One- and Two-Family Dwellings
TOOLKIT DOCUMENT #4 Your City logo here Solar Standard Plan Simplified Microinverter and M Systems for One- and Two-Family Dwellings SCOPE: Use this plan ONLY for systems using utility-interactive Microinverters
More informationSolar PV Standard Plan Simplified Microinverter and ACM Systems for One- and Two-Family Dwellings
TOOLKIT DOCUMENT #4 Solar Standard Plan Simplified Microinverter and M Systems for One- and Two-Family Dwellings SCOPE: Use this plan ONLY for systems using utility-interactive Microinverters or Modules
More informationRULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)
- (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility
More information2014 NEC Changes Part 1 (Homestudy)
2014 NEC Changes Part 1 (Homestudy) Wisconsin Electrical License This course will review the first half of the most important National Electrical Code changes from the 2014 NEC. Changes in Articles 100-404.2
More informationNEC 2014 Code Changes
NEC 2014 Code Changes Articles 310 310.120 CHANGES FROM 2011 TO 2014 CODE ARE IN RED ARTICLE 310 Conductors for General Wiring I. General 310.2 Definitions Electrical Ducts Electrical conduits, or other
More information2011 NEC Code Updates Part 3
www.garyklinka.com Page 1 of 22 Instructions: Fee $35 1. Print these pages. 2. Circle the correct answers and transfer them to the answer sheet. 3. Page down to the last page for the verification forms
More informationInspector Training Workshops Module One Photovoltaic Labeling based on 2008 NEC
Inspector Training Workshops Module One Photovoltaic Labeling based on 2008 NEC NJCE Market Manager HW Construction Department Wayne, NJ Robert A. Menist Contents Site inspections with attention on Labeling
More informationSolar PV Standard Plan Simplified Microinverter and ACM Systems for Oneand Two-Family Dwellings
County of Santa Barbara Your City logo here Solar Standard Plan Simplified Microinverter and M Systems for Oneand Two-Family Dwellings SCOPE: Use this plan ONLY for systems using utility-interactive Microinverters
More informationElectrical Tech Note 111 Biosystems & Agricultural Engineering Department Michigan State University
Electrical Tech Note 111 Biosystems & Agricultural Engineering Department Michigan State University Electrical Code Changes in Michigan 1 (Based on Part 8, P.A. 230, the 2005 NEC and the 2003 MRC) This
More informationPART A General Conductor Requirements
PART A General Conductor Requirements 6.1 Conductor Insulation Property Table 310.13 of the NEC provides information on conductor properties such as permitted use, maximum operating temperature, and other
More informationData Bulletin. Ground-Censor Ground-Fault Protection System Type GC Class 931
Data Bulletin 0931DB0101 July 2001 Cedar Rapids, IA, USA Ground-Censor Ground-Fault Protection System Type GC Class 931 09313063 GT Sensor Shunt Trip of Circuit Interrupter Window Area for Conductors GC
More information2000 Cooper Bussmann, Inc. Page 1 of 9 10/04/00
DO YOU KNOW THE FACTS ABOUT SINGLE-POLE INTERRUPTING RATINGS? YOU MAY BE IN TROUBLE! Typical plant electrical systems use three-phase distribution schemes. As an industry practice, short-circuit calculations
More information2011 NEC Significant Changes Part 1 The following course will summarize many of the important changes to the NEC code.
2 PART 1 American Electrical Institute 2013 2011 NEC Significant Changes Part 1 The following course will summarize many of the important changes to the NEC code. The 2011 Code has added 3 new articles:
More informationElectrical Tech Note 106
Electrical Tech Note 106 Biosystems & Agricultural Engineering Department Michigan State University Master Exam Study Guide and Sample Questions 1 Based on the 2014 NEC, Part 8 of PA 230, PA 407, and the
More informationStandard for Installing and Maintaining Electric Vehicle Supply Equipment (EVSE)
Standard for Installing and Maintaining Electric Vehicle Supply Equipment (EVSE) Presented by: Gregory W. Massey, P. E. Overview Electric Vehicles (EVs) create a need to build an infrastructure that will
More informationCode Compliance. Perspectives on PV. Back to the Grid, Designing PV Systems for
Perspectives on PV A series of articles on photovoltaic (PV) power systems and the National Electrical Code by John Wiles Back to the Grid, Designing PV Systems for Code Compliance 20 IAEI NEWS January.February
More informationNFPA World Safety Congress & Exposition 2005 NEC Proposals Report of CMP-12
2005 NEC Proposals Report of CMP-12 NEC Code Making Panel 12 is responsible for: Articles 610, 620, 630, 640, 645, 647, 650, 660, 665, 668, 669, 670, 685, and Annex D Examples D9 and D10 2005 NEC Proposals
More informationWestern Section 101 st Annual Meeting Hot Springs, Arkansas September 21, 2005 Charlie Trout Code Breakfast
Western Section 101 st Annual Meeting Hot Springs, Arkansas September 21, 2005 Charlie Trout Code Breakfast 1.Question: An add on unit for a hydromassage bathtub consists of a small 1-gallon water heater
More informationTRI-SERVICE ELECTRICAL WORKING GROUP (TSEWG) 03/05/09 TSEWG TP-11: UFC N BEST PRACTICES
TSEWG TP-11: UFC 3-500-10N BEST PRACTICES UFC 3-500-10N was developed by NAVFAC and was used as the starting point for the tri-services development of UFC 3-500-10, Design: Electrical Engineering. UFC
More informationBusway Construction. Bus Bars
Busway Construction Bus Bars A better understanding of what busway is can be gained by examining its construction. A typical Siemens Sentron busway section has three or four formed aluminum or copper bars
More informationElectrical Design/Build Guide
2017 Electrical Design/Build Guide Based on the 2017 National Electrical Code Copyright Durand & Associates 1986-2016 60 C Copper Ampacity 4 - Wire Fill - (Non-Current Carrying Neutral) 4 or 5 - Parallel
More informationSECTION ENCLOSED SWITCHES AND CIRCUIT BREAKERS
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 29 21 ENCLOSED SWITCHES AND CIRCUIT BREAKERS SPEC WRITE NOTE: Delete between // // if not applicable to project. Also delete any other item or paragraph not
More informationARKANSAS ELECTRICIANS
CONTINUING EDUCATION FOR ARKANSAS ELECTRICIANS 2014 NEC Code Change 8 Hours AMERICAN ELECTRICAL INSTITUTE N16 W23217 Stone Ridge Drive, Suite 290 Waukesha, WI 53188 855-780-5046 www.aeitraining.com DISCLAIMER
More information10. METERING General Requirements
10. METERING 10.1 General Requirements A. The Company will not supply service to a Customer whose wiring is designed for resale of electricity through submetering except for recreational campgrounds, marinas,
More informationSECTION PANELBOARDS
SECTION 16470 PANELBOARDS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. The general provisions of the contract including General and Special Conditions and General Requirements shall apply to all work under
More informationREQUIREMENTS FOR PARALLEL OPERATION FOR CUSTOMERS WITH GENERATION NOT EXCEEDING 50 kw
REQUIREMENTS FOR PARALLEL OPERATION FOR CUSTOMERS WITH GENERATION NOT EXCEEDG 50 kw FOREWARD Requirements for Parallel Operations for Customers with Generation Not Exceeding 50 kw is intended to be used
More informationQuick Start Guide TS 910 & TS 920
Quick Start Guide TS 910 & TS 920 DANGER HAZARD OF ELECTRICAL SHOCK, EXPLOSION, OR ARC FLASH Read and understand this quick start guide before installing and operating the transfer switch The installer
More informationElectrical Tech Note 105 Agricultural Engineering Department Michigan State University
Electrical Tech Note 105 Agricultural Engineering Department Michigan State University Journey Exam Study Guide and Sample Questions 1 Based on the 2002 NEC, Part 8 of PA 230, and the 2003 MRC The Journey
More informationSolar PV Standard Plan Simplified Microinverter and ACM Systems for One- and Two-Family Dwellings
TOOLKIT DOCUMENT #4 Your City logo here Solar Standard Plan Simplified Microinverter and M Systems for One- and Two-Family Dwellings SCOPE: Use this plan ONLY for systems using utility-interactive Microinverters
More informationLoad Side PV Connections
Perspectives on PV Load Side PV Connections 705.12(D) in the 2014 NEC by John Wiles Through the exceptional efforts of the members of NFPA NEC Code-Making Panel 4 working with the proposals and comments
More informationSTOUGHTON UTILITIES ELECTRIC SERVICE RULES AND INFORMATION
CHAPTER 1 - GENERAL INFORMATION 100. Purpose 101. Codes and rules 102. Continuity of service 103. Frequency, Voltage, and Amperage Limitations 104. High voltages 105. Unusual capacity requirements 106.
More information10 Commercial, Industrial, Agricultural Services
10 Commercial, Industrial, Agricultural Services This section describes the Power Company requirements for commercial, industrial, and agricultural services. This section covers single phase and three
More informationAlternator protection, part 1: Understanding code requirements
Power topic #6002 Part 1 of 3 Technical information from Cummins Power Generation Alternator protection, part 1: Understanding code requirements > White paper By Gary Olson, Technical Counsel This paper
More information