Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Size: px
Start display at page:

Download "Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection"

Transcription

1 Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i

2 EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection service from UNS Electric (UNSE) to integrate its proposed Kingman area photovoltaic generation project (KAPVGP or Project) to the UNSE 69 kv transmission system located in the vicinity of Kingman and Golden Valley in Mohave County, Arizona. The project would provide up to 150 MW of photovoltaic resource generation with in-service date of May The project would consist of one to three units of 50 MW each. The Customer and the UNSE have discussed three options of interconnecting the project. These interconnecting options are via: A 69 kv radial line to the UNSE s Industrial 69 kv Substation, $885k. A 69 kv radial line to the UNSE s Boriana Junction 69 kv Substation, $8,755k. A 69 kv radial line to the UNSE s West Golden Valley 69 kv Substation, $9,055k. All three of the above, $10,405k Estimates provided by UNSE/TEP Substation Engineering include all representative direct costs and overheads, but do not include any income tax gross-up that may be required to be collected. Any tax gross-ups will be calculated, collected and refunded in accordance with UNS Electric s Rules & Regulations.. The cost estimates are nonbinding and do not include mitigation of issues on other affected systems. The study evaluated a single 50 MW plant operating alone and all three plants operating concurrently at each of the three locations. Based on the feasibility analysis which evaluated the steady-state response of the UNSE transmission system to the proposed project subject to normal (N-0), single (N-1) as well as multiple (N-2) contingencies, each of the three interconnection options were found to be technically capable of interconnecting the proposed generation additions to the UNSE 69 kv system with appropriate interconnection and mitigation facilities in-place. From the short circuit analysis, performed by UNSE/TEP Protection group, there appear to be no post-project conditions that appreciably increase fault duty beyond the interrupting capability of existing fault interrupting devices on the 69 kv systems out of Griffith or Hilltop substations. The Industrial 69 kv interconnection option was found to be the lowest cost among the alternatives studied. No transmission facility overload was identified under normal as well as contingency conditions following the interconnection of the proposed 50 MW generating plant at Industrial 69 kv substation. The other alternatives however would require an additional 230/69 kv transformer at Griffith station and addition of approximately six miles of new 69 kv circuit between Griffith and the vicinity of Boriana Junction. In the case of plants at Boriana Junction, West Golden Valley or both, a 69 kv switching station near Boriana Junction would also be required to provide adequate protection coordination with the Black Mountain Generating Station. October 2009 ii

3 BACKGROUND UNSE elected a third party contractor, PDS Consulting, PLC (PDS) to perform the interconnection feasibility study for the KAPVGP project. The analysis was performed using WECC approved 2012 heavy summer and 2013 light winter base cases provided by the UNSE. The scope of the analysis was to: Identify the feasibility of interconnecting the KAPVGP project as individual points of interconnection for 50 MW generating plants in the Kingman and Golden Valley area at each of the three locations and as a three 50 MW plants operating concurrently at the three locations. Identify the transmission system impacts caused solely by the addition of the KAPVGP project for normal operating conditions (N-0) as well as single (N-1) and multiple (N-2) contingencies. Studies performed included power flow and short circuit analysis. Transient stability analysis will be conducted in the System Impact Study phase if the Customer elects to continue the interconnection process. The studies described in this report demonstrated the feasibility of interconnecting each of the three 50 MW plants in the KAPVGP to the UNSE transmission system via: A 69 kv radial line to the UNSE s Industrial 69 kv Substation. A 69 kv radial line to the UNSE s Boriana Junction 69 kv Substation. A 69 kv radial line to the UNSE s West Golden Valley 69 kv Substation. The study indicates that the addition of the KAPVGP and the subsequent schedule of its output to the Palo Verde generation hub will not cause any new transmission facility overloads under normal or contingency operating conditions if the project is connected to the UNSE s Industrial 69 kv substation. However, if the project is connected to the UNSE Boriana Junction 69 kv substation, a second 80 MVA 230/69 kv transformer would be required at Griffith. Additionally, a new 69 kv circuit would have to be built to reduce the complexity of relay coordination involving other generation on the existing 69 kv system out of Griffith substation. Interconnection to the UNSE s West Golden Valley or Boriana Junction 69 kv substations would also trigger the need for an additional 80 MVA 230/69 kv transformer at Griffith. Interconnection of the proposed project at Boriana Junction, West Golden Valley or both, would also require the installation of a 69 kv switching station in the vicinity of Boriana Junction to further improve reliability and relay coordination out of Griffith substation to accommodate the Black Mountain Generating Station. The study also indicated that the addition of the KAPVGP caused up to three 230 kv transmission line to overload following multiple outages. There were also several existing transmission facility overloads exacerbated by the addition of the project. To mitigate the identified overloads under multiple outages the project may be required to participate in existing operational procedures or may be included in a new operational procedure. Detailed analysis of impacts to the overlying HV and EHV October 2009 iii

4 transmission system will involve Western Area Power Administration and will be dealt with in the System Impact Study phase. The power flow analysis prior to the interconnection of the KAPVGP did not indicate any transmission facility overloads under normal operating conditions. The study however found six transmission facility overloads under single element outages and two 230 kv transmission line overloads following multiple outages. October 2009 iv

5 CONTENTS Introduction... 1 Project and Interconnection Information... 1 Study Base Case Description and Assumptions... 3 Study Methodology and Evaluation Criteria...4 Study Results....5 Mitigation Plan Cost Estimating Appendix A: Power Flow Maps...18 Appendix B: Summary of Power Flow Study Results Appendix C: Power Flow Contingency List...43 Appendix D: Single-line Diagrams...51 Appendix E: Cost Estimating...55 October 2009 v

6 INTRODUCTION Customer has requested network resource interconnection service from UNS Electric (UNSE) to integrate its proposed Kingman area photovoltaic generation project (KAPVGP or Project) to the UNSE 69 kv transmission system located in the vicinity of Kingman and Golden Valley in Mohave County, Arizona. The project would provide up to 150 MW of photovoltaic resource generation with in-service date of May The project would consist of up to three units of 50 MW each. The Customer and the UNSE have discussed three options of interconnecting the project. These interconnecting options are via: A 69 kv radial line to the UNSE s Industrial 69 kv Substation. A 69 kv radial line to the UNSE s Boriana Junction 69 kv Substation. A 69 kv radial line to the UNSE s West Golden Valley 69 kv Substation. This study evaluated a single 50 MW plant operating alone and all three plants operating concurrently at each of the three locations. UNSE elected a third party contractor, PDS Consulting, PLC (PDS) to perform the interconnection feasibility study for the KAPVGP project. Only power flow analysis was performed. The analysis was performed using WECC approved 2012 heavy summer and 2013 light winter base cases provided by the UNSE. The scope of the analysis was to: Identify the feasibility of interconnecting the KAPVGP project as a single 50 MW plant in the Kingman area at each of the three locations and as three 50 MW plants operating concurrently at the three locations. Identify the transmission system impacts caused solely by the addition of the KAPVGP project for normal operating conditions (N-0) as well as single (N-1) and multiple (N-2) contingencies. PROJECT AND INTERCONNECTION INFORMATION Table 1 provides the general project and interconnection information about the KAPVGP. Project Location Mohave County, Arizona Type of Generation Resource Photovoltaic generating plant Maximum Generator Output 50 MW per plant, 150 MW net project size Power Factor Unity Step-up Transformer (s) Three (3), 30/40/50 MVA, 35/69 kv transformer, Z=7.5% Interconnection Configuration See Figure 1 & 2. Interconnection Voltage 69 kv Table 1: The KAPVGP Project General Information October

7 Figure 1 depicts the KAPVGP Project interconnection options and the existing transmission system at the interconnection vicinity. A one-line diagram of the basic KAPVGP layout is shown in Figure 2. to WATERFIELD 50 MW PV W GOLDEN VALLEY to JAGERSON 50 MW PV INDUSTRIAL to ARCO BREAKER (NO) to CASSON EASTERN NO to BOUNDARY CONE 50 MW PV BORIANA JCT 352 HILLTOP 69 kv GRIFFITH 69 kv SACRAMENTO BLACK MOUNTAIN YUCCA Figure 1: The KAPVGP Project Interconnection Options 69 kv Bus 34.5 kv Bus 480 V Bus 500 kw PV Sub-array 480 V Bus Distribution Bus kw PV Sub-array Figure 2: Typical One-Line Diagram of the KAPVGP 50 MW Plant October

8 STUDY BASE CASE DESCRIPTION AND ASSUMPTIONS This analysis was conducted using two power flow base cases: Western Electricity Coordination Council (WECC) approved 2012 heavy summer (12hs2a.sav) and 2013 light winter (13lw1s.sav) base cases. The 2012 heavy summer base case was adjusted to reflect 2011 heavy summer forecasted operating conditions in the study area. The 2013 light winter case was modified to reflect forecasted UNSE s lowest daytime peak conditions in winter of Generation dispatch modeled in the WECC base cases was not modified. The benchmark (pre-project) base cases were tested to ensure that all transmission facilities in the study area are within their normal operating limits. While it is impossible to study all combinations of system load and generation levels during all seasons, these two pre-project base cases represent extreme loading and generation conditions for the study area. However, UNSE cannot guarantee that the KAPVGP can operate at maximum rated output year round without impacting the transmission system during times and seasons not studied. Four post-project base cases were developed from each of the pre-project cases. The post-project base cases modeled the proposed KAPVGP for the interconnections depicted in Figure 1. The output of KAPVGP project was dispatched to replace merchant generators at Palo Verde/Hassayampa generation hub for this study. Table 2 provides descriptions of all the pre- and post-project base cases developed for the feasibility study. Pre- /Post- Base Case Description Base Cases Pre-project Case A Approved WECC 2012 Heavy summer pre-project base case. Models 2011 forecasted load in the study area. Pre-project Case B Approved WECC 2013 light winter pre-project base case. Models 2011 forecasted load in the study area. Post-project Case A1 Developed from Pre-project Case A and models the 50 MW KAPVGP project connected to UNSE s Industrial 69 kv substation. Post-project Case A2 Developed from Pre-project Case A and models the 50 MW KAPVGP project connected to UNSE s Boriana 69 kv substation. Developed from Pre-project Case A and models the 50 MW KAPVGP project Post-project Case A3 connected to UNSE s W. Golden Valley 69 kv substation. Developed from Pre-project Case A and models the 150 MW KAPVGP project Post-project Case A4 distributed equally at UNSE s Industrial, Boriana and W. Golden Valley 69 kv substations. Developed from Pre-project Case B and models the 50 MW KAPVGP project Post-project Case B1 connected to UNSE s Industrial 69 kv substation. Developed from Pre-project Case B and models the 50 MW KAPVGP project Post-project Case B2 connected to UNSE s Boriana 69 kv substation. Post-project Case B3 Developed from Pre-project Case B and models the 50 MW KAPVGP project Post-project Case B4 connected to UNSE s W. Golden Valley 69 kv substation. Developed from Pre-project Case B and models the 150 MW KAPVGP project distributed equally at UNSE s Industrial, Boriana and W. Golden Valley 69 kv substations. Table 2: Pre-/Post-project Base Cases October

9 STUDY METHODOLOGY AND EVALUATION CRITERIA Power flow analysis was performed on both the pre-project and post-project cases to determine the impact of the KAPVGP Project on the UNSE sub-transmission system and the interconnected facilities within the study area. Specific studies conducted and their evaluation criteria are outlined below: Power Flow Analysis Power flow analysis was performed on both the pre-project and post-project base cases detailed in Table 2. The base cases were used to simulate the impact of the Project during normal operating conditions (N-0) as well as single (N-1) and multiple contingency conditions. The contingencies simulated included: All single sub-transmission and transmission circuit outages within the study area (N-1). All single transformer outages within the study, excluding transformers serving only distribution load (N-1). All Tie Lines to adjacent connecting immediately outside the study area (N-1). All pairs of the above single outages (N-2) The WECC/NERC and UNSE planning standards will be used to assess the adequacy of the study results. The power flow analysis related evaluation criteria that will be used are summarized below: Pre-contingency bus voltage outside the study area must be between 0.95 per unit and 1.05 per unit. Post-contingency 69 kv voltages must be between 0.95 and 1.05 per unit. Study area transmission voltages >1.00 pu. Fictitious buses to model transformer terminated lines are not subject to this criterion. Pre-contingency UNSE 69 kv bus voltages between 0.95 and pu Maximum voltage deviation allowed at all buses under contingency conditions will be 5% for all contingencies. Pre-disturbance loading to remain within continuous ratings of all equipment and line conductors Post-disturbance loading to remain within emergency ratings of all equipment and line conductors. Post-project representation of the KAPVGP maintained unity power factor at the plant's point of interconnection to the UNSE system October

10 Short Circuit Analysis Short circuit studies were performed to evaluate the impact of the addition of the KAPVGP on selected UNSE-Mohave substation breaker duties. STUDY RESULTS Pre-Project Power Flow Analysis Results Power flow analysis was performed on both the 2012 heavy summer and 2013 light winter base cases. Power flow maps for both base cases can be found in Appendix A. Key findings from the power flow analysis using both the heavy summer and light winter pre-project base cases are: No transmission facility overload was identified under normal operating conditions prior to the addition of KAPVGP. Six (6) transmission facility overloads were identified following selected single element (N-1) outages. Two (2) 230 kv transmission lines were found to be overloaded under multiple outages during the summer operating condition. (See Appendix B, Table B1 for the identified overloads) No bus voltage deviation violation was identified. Industrial 69 kv Interconnection Power Flow Analysis Results a) 2012 Heavy Summer Base Case Power flow Maps for 2012 heavy summer post-project base case A1 developed for the Industrial 69 kv interconnection can be found at Appendix A. Difference power flow maps between the pre- and post-project base case A1 can also be found at Appendix A. Power flow solutions were achieved for all the outages simulated. Appendix B, Table B1 provides a summary of the results of the power flow analysis. Key findings from the power flow studies using the 2012 heavy summer base cases are: No transmission facility overload was identified under normal operating condition following the interconnection of the KAPVGP to the Industrial 69 kv substation. No transmission facility overload attributable to the project was identified under N-1 contingency conditions. No transmission facility overload solely due the proposed project following multiple outages. However, two existing 230 kv transmission line contingency overloads were exacerbated following the addition of the KAPVGP. (See Appendix B, Table B1 for the identified overloads) No bus voltage deviation violation was identified. October

11 b) 2013 Light Winter Base Case Summary of the results of the pre- project base and post-project base case A1 can be found at Appendix B, Table B2. Power flow Maps for 2012 light winter pre- and postproject base cases can also be found at Appendix A. Key findings from the power flow studies are: No transmission facility overload was identified under normal operating condition following the interconnection of the KAPVGP to the Industrial 69 kv substation. No transmission facility overload solely due to the project under N-1 or N-2 contingency conditions. No bus voltage deviation violation was identified. Boriana Junction 69 kv Interconnection Power Flow Analysis Results a) 2012 Heavy Summer Base Case Power flow Maps for both 2012 heavy summer pre- and post-project base case A2 can be found at Appendix A. Difference power flow maps can also be found at Appendix A. Power flow solutions were achieved for all the outages simulated. Appendix B, Table B3 provides a summary of the results of the power flow analysis. Key findings from the power flow studies are: Two (2) new transmission facility overloads attributable to the KAPVGP project were identified under normal (N-0) operating condition. The GRIFFITH 230/69 kv transformer loaded up to 122% of the transformer s normal rating following the interconnection of the project to Boriana 69 kv substation. Also the BORIANA-BORIANA TAP 69 kv line loaded up to 103% of the line s normal rating. Two (2) new transmission facility overloads identified following selected N-1 outages. See Table 5 for the identified transmission facility overloads. Two (2) new 230 kv transmission lines were overloaded following multiple outages. Also two existing 230 kv transmission line contingency overloads were exacerbated following the addition of the KAPVGP. (See Appendix B, Table B3 for the identified overloads) No bus voltage deviation violation was identified. b) 2013 Light Winter Base Case Summary of the results of the pre- project base and post-project base case A2 can be found at Appendix B, Table B4. Power flow Maps for 2012 light winter pre- and postproject base cases can also be found at Appendix A. Key findings from the power flow studies are: October

12 Two (2) new transmission facility overloads attributable to the KAPVGP project were identified under normal operating condition. The GRIFFITH 230/69 kv transformer loaded up to 163% of the transformer s normal rating following the interconnection of the project to Boriana 69 kv substation. Also the BORIANA- BORIANA TAP 69 kv line loaded up to 105% of the line s normal rating. Two (2) new transmission facility overloads identified following selected N-1 outages. See Table 5 for the identified transmission facility overloads. No bus voltage deviation violation was identified. W. Golden Valley 69 kv Interconnection Power Flow Analysis Results a) 2012 Heavy Summer Base Case Power flow Maps for both 2012 heavy summer pre- and post-project base case A3 developed for the W. Golden Valley 69 kv interconnection can be found at Appendix A. Difference power flow maps can also be found at Appendix A. Power flow solutions were achieved for all the outages simulated. Appendix B, Table B5 provides a summary of the results of the power flow analysis. Key findings from the power flow studies are: One (1) new transmission facility overload was identified under normal operating condition. The GRIFFITH 230/69 kv transformer loaded up to 121% of the transformer s normal rating following the interconnection of the project to W. Golden Valley 69 kv substation. Two (2) new transmission facility overloads were identified under N-1 contingency conditions. See Table 5 for the identified transmission facility overloads. Two (2) new 230 kv transmission line was overloaded following multiple outages. Two existing 230 kv transmission line contingency overloads were exacerbated following the addition of the KAPVGP. (See Appendix B, Table B5 for the identified overloads) No bus voltage deviation violation was identified. b) 2013 Light Winter Base Case The power flow results using 2013 light winter base cases were similar to the results obtained during heavy summer operating conditions. The results are summarized in Table B6, Appendix B. Power flow Maps are provided in Appendix A. Key findings from the power flow studies are: One (1) new transmission facility overload was identified under normal operating condition. The GRIFFITH 230/69 kv transformer loaded up to 162% of the transformer s normal rating following the interconnection of the project to W. Golden Valley 69 kv substation. Two (2) new transmission facility overloads were identified under N-1 contingency conditions. See Table 5 for the identified transmission facility October

13 overloads. No bus voltage deviation violation was identified. All 3 69 kv Substation Locations Power Flow Analysis Results a) 2012 Heavy Summer Base Case Key findings from the power flow studies provided in Appendix B, Table B7 are: Two (2) new transmission facility overloads attributable to the KAPVGP project were identified under normal operating condition. The GRIFFITH 230/69 kv transformer loaded up to 185% of the transformer s normal rating and the BORIANA-BORIANA TAP 69 kv line loaded up to 105% of the line s normal rating. Two (2) new transmission facility overloads identified following selected N-1 outages. See Table 5 for the identified transmission facility overloads. Three (2) new 230 kv transmission line was overloaded following multiple outages. Two existing 230 kv transmission line contingency overloads were exacerbated following the addition of the KAPVGP. (See Appendix B, Table B7 for the identified overloads) No bus voltage deviation violation was identified. b) 2013 Light Winter Base Case Summary of the results of the pre- project base and post-project base case A4 can be found at Appendix B, Table B8. Power flow Maps for 2012 light winter pre- and postproject base cases can also be found at Appendix A. Key findings from the power flow studies are: Two (2) new transmission facility overloads attributable to the KAPVGP project were identified under normal operating condition. The GRIFFITH 230/69 kv transformer loaded up to 227% of the transformer s normal rating and the BORIANA-BORIANA TAP 69 kv line loaded up to 107% of the line s normal rating. Two (2) new transmission facility overloads identified following selected N-1 outages. See Table 5 for the identified transmission facility overloads. No bus voltage deviation violation was identified. October

14 Short Circuit Analysis To perform the short circuit study, the 50 MW photovoltaic generation additions were modeled in the TEP short circuit base case using the ASPEN One-Liner software. This case originated from the post-project for the proposed Bowie Power Station project. The following data was used to prepare the short circuit case: 1. ASSUMED PV INVERTERS ARE A CONSTANT SOURCE = LOAD CURRENT 2. ASSUME 50 PAD MOUNT TRANSFORMERS FOR TOTAL GEN= 50MW PV EQ 0.265kV 0.0P P-90 50MWPV INVERTER X''d= 1.0 ( EQUIV. SUBTRANSIENT REACTANCE) S= 50MVA PV MV PV HV 50 TRANSFORMERS-- 35.kV 69.kV PAD MOUNT TRANSFORMER 0.0P P-75 EQUIVALENT 50 MVA Z EQ= 7.5%/50 = 0.15%, X/R= 5.48 INTERTIE TRANSFORMER S= 50 MVA Z= 7 % ASSUME X/R= P P P P P-90 BORIANA, INDUSTRIAL 3- PHASE FAULT WEST GOLDEN VALLEY INTERCONNETS Table 3 summarizes the short circuit magnitude for three-phase and single-line-toground faults for the pre-project and post-project conditions. Fault duty data in Table 3 is sorted from the highest incremental three-phase current at the Point of Interconnection (POI) to the lowest in order of magnitude for the regional buses. There appear to be no post-project conditions that appreciably increase fault duty beyond the pre-project values. Mitigation of any fault duty in excess of circuit breaker interrupting capability pre-project may cover mitigation of these issues post-project. The available margin at the regional buses was not available at the time of this report; however, it is expected that due to the magnitude of the incremental fault duty and the relatively new age of the breakers with higher interrupting capability in this region that the interconnection of the BPGS CSP may not require mitigation of any breakers. October

15 October

16 October

17 October

18 October

19 MITIGATION PLANS Provided in Table 5 below are the recommended corrective mitigation plans for the identified transmission facility overload solely due to the addition of the KAPVGP. For any existing overloads exacerbated with the addition of the KAPVGP, the project could be included in the existing mitigation plan or be made to participate in any new mitigation plan designed for such an overload. Outage Overloaded Facility Rating Overload Recommended Mitigation Industrial 69 kv Interconnection N-0 ALL LINES IN SERVICE None N/A N/A None N-1 None None N/A N/A None Boriana Junction 69 kv Interconnection N-0 80 MVA 163% Add second 80 MW, 230/69 kv transformer ALL LINES IN SERVICE GRIFFITH 230/69 kv transformer BORIANA BORIANATP 69 KV LINE 368 A 105% Bypass overloaded segment by constructing new 69 kv circuit between Griffith and a 69 kv switching station in the vicinity of Boriana Junction (see Appendix D1 & D2) N-1 BKMTMTP1 BLK_MTN 69 KV LINE GRIFFITH GRIFTAP3 69 KV LINE 912 A 119% Bypass overloaded segment by GRIFFITH GRIFTAP3 69 KV LINE BKMTMTP1 BLK_MTN 69 KV LINE 912 A 118% constructing new 69 kv circuit between Griffith and a 69 kv switching station in the vicinity of Boriana Junction (see Appendix D1 & D2) Table 5: Overloaded transmission facilities and associated recommended mitigation plans October

20 Outage Overloaded Facility Rating Overload (%) Recommended Mitigation W. Golden Valley 69 kv Interconnection N-0 ALL LINES IN SERVICE GRIFFITH 230/69 kv transformer 80 MVA 162% Add second 80 MW, 230/69 kv transformer N-1 BKMTMTP1 BLK_MTN 69 KV LINE GRIFFITH GRIFTAP3 69 KV LINE GRIFFITH GRIFTAP3 69 KV LINE BKMTMTP1 BLK_MTN 69 KV LINE 912 A 912 A 119% 118% Bypass overloaded segment by constructing new 69 kv circuit between Griffith and a 69 kv switching station in the vicinity of Boriana Junction (see Appendix D1 & D2) All 3 69 kv Substation Interconnection N-0 ALL LINES IN SERVICE GRIFFITH 230/69 kv transformer 80 MVA 227% Add second and third 80 MW, 230/69 kv transformers BORIANA BORIANATP 69 KV LINE 368 A 107% Bypass overloaded segment by constructing new 69 kv circuit between Griffith and a 69 kv switching station in the vicinity of Boriana Junction (see Appendix D1 & D2) N-1 BKMTMTP1 BLK_MTN 69 KV LINE GRIFFITH GRIFTAP3 69 KV LINE GRIFFITH GRIFTAP3 69 KV LINE BKMTMTP1 BLK_MTN 69 KV LINE 912 A 912 A 153% 152% Bypass overloaded segment by constructing new 69 kv circuit between Griffith and a 69 kv switching station in the vicinity of Boriana Junction (see Appendix D1 & D2) Table 5: Overloaded transmission facilities and associated recommended mitigation plans (Continued) October

21 COST ESTIMATES (see Appendices D & E for details) The following cost estimates are non-binding and do not include mitigation of issues on other affected systems. These costs include direct costs and UNSE overheads, but do not include any income tax gross-up required to be collected by UNSE to the receipt of a taxable contribution in aid of construction. Pursuant to its Rules & Regulations, UNSE is required to collect an income tax gross-up on any taxable contribution in aid of construction in excess of $500,000. UNS Electric s current gross-up factor is 65.37%. A portion of the income tax gross-up is refunded annually based on the federal income tax depreciation tables applicable to the plant assets received by UNSE. At the end of the fifth year in service, the remaining gross-up will be refunded at a discounted amount using UNS Electric s authorized rate of return over the remaining tax life. The estimating is broken into the connection cost and the mitigation cost for each option. For the Feasibility Study it includes only construction costs associated with the 69 kv system and does not include 69 kv right-of-way costs. This estimating does not include any of the costs to mitigate impacts to the overlying Western Area Power Administration HV and EHV transmission system, as Western has said that they will provide these costs once the study moves to the System Impact Study phase. As such, the costs for each interconnection option are as follows: Industrial: $885k Connection Cost: $825k Includes a 69 kv circuit breaker, switches and protection and an estimated 1 mile of line extension with fiber optic ground wire (OPGW) from the 69 kv point of interconnection on the Transmission Provider s 69 kv system to a high-side disconnect switch at the Interconnection Customers Interconnection Facilities. Protection and communications over new OPGW from Hilltop to Industrial for direct transfer trip to isolate the PV generating plant for faults external to the lateral line extension. A conceptual single-line diagram for the interconnection to Industrial substation is included in Appendix D1 and D2. Mitigation Cost: $60k Includes upgrades to the Hilltop 652 breaker bay to accommodate updating to SEL relaying, addition of direct transfer trip to Industrial and addition of power quality metering. Boriana Junction: $8,755k Connection Cost: $825k Includes a 69 kv circuit breaker, switches and protection at a new five position 69 kv ring bus at Boriana Junction and an estimated 1 mile of line extension with fiber optic October

22 ground wire (OPGW) from the 69 kv point of interconnection on the Transmission Provider s 69 kv system to a high-side disconnect switch at the Interconnection Customers Interconnection Facilities, and protection at Boriana Junction to isolate the PV generating plant for faults external to the lateral line extension. A conceptual singleline diagram for the interconnection to Boriana Junction substation is included in Appendix D1. Mitigation Cost: $7,930k Mitigation includes a new 69 kv breaker bay breaker at Griffith, a 6 mile long 69 kv circuit out of Griffith substation to the vicinity of Boriana Junction, a new five position 69 kv ring bus at Boriana Junction and addition of an 80 MVA, 230/69 kv transformer at Griffith. West Golden Valley: $9055k Connection Cost: $825k Includes a 69 kv circuit breaker, switches and protection and an estimated 1 mile of line extension with fiber optic ground wire (OPGW) from the 69 kv point of interconnection on the Transmission Provider s 69 kv system to a high-side disconnect switch at the Interconnection Customers Interconnection Facilities.. Protection and communications over new OPGW from a ring bus at Boriana Junction to West Golden Valley for direct transfer trip to isolate the PV generating plant for faults external to the lateral line extension. A conceptual single-line diagram for the interconnection to West Golden Valley substation is included in Appendix D1. Mitigation Cost: $8230k Mitigation includes a new 69 kv breaker bay breaker at Griffith, a 6 mile long 69 kv circuit out of Griffith substation to the vicinity of Boriana Junction, a new five position 69 kv ring bus at Boriana Junction and addition of an 80 MVA, 230/69 kv transformer at Griffith. All Projects: $10,405k Connection Cost: $2,475k Includes 1 mile of line extension with fiber optic ground wire (OPGW) to each of the three projects, a 69 kv circuit breaker, switches and protection from the existing 69 kv point of interconnection to a high-side disconnect switch at the point-of-interconnection for the W. Golden Valley and Industrial projects. Interconnection cost for the Boriana Junction project is imbedded in the cost for a five position 69 kv ring bus required as part of mitigation if all three projects are constructed. Protection and communications over new OPGW from Griffith to Boriana Junction and West Golden Valley for direct transfer trip to isolate the PV generating plant for faults external to the lateral line October

23 extension. Mitigation Cost: $7,930k Mitigation includes a new 69 kv breaker bay breaker at Griffith, a 6 mile long 69 kv circuit out of Griffith substation to the vicinity of Boriana Junction, a new five position 69 kv ring bus at Boriana Junction and addition of an 80 MVA, 230/69 kv transformer at Griffith. A conceptual single-line diagram for the interconnection of al the projects is included in Appendix D1. October

24 Appendix A Power Flow Maps October

25 Section 1: Heavy Summer Pre-Project Base Case-Power Flow Map (All Lines in Service) October

26 Section 2: Heavy Summer Post-Project Base Case A1 (Industrial 69 kv) - Power Flow Map (All Lines in Service) October

27 Section 3: Difference Power Flow Map B/N Heavy Summer Pre- & Post-Project Base Case A1 (Industrial 69 kv) October

28 Section 4: Heavy Summer Post-Project Base Case A2 (Boriana 69 kv)-power Flow Map (All Lines in Service) October

29 Section 5: Difference Power Flow Map B/N Heavy Summer Pre- & Post- Project Base Case A2 (Boriana 69 kv) October

30 Section 6: Heavy Summer Post-Project Base Case A3 (Golden Vly 69 kv)-power Flow Map (All Lines in Service) October

31 Section 7: Difference Power Flow Map B/N Heavy Summer Pre- & Post- Project Base Case A3 (Golden Vly 69 kv) October

32 Section 8: Heavy Summer Post-Project Base Case A4 (All 3 Locations)-Power Flow Map (All Lines in Service) October

33 Section 9: Difference Power Flow Map B/N Heavy Summer Pre- & Post- Project Base Case A4 (All 3 Locations) October

34 Section 10: Light Winter Pre-Project Base Case -Power Flow Map (All Lines in Service) October

35 Section 11: Light Winter Post-Project Base Case A1 (Industrial 69 kv) - Power Flow Map (All Lines in Service) October

36 Section 12: Light Winter Post-Project Base Case A2 (Boriana 69 kv) - Power Flow Map (All Lines in Service) October

37 Section 13: Light Winter Post-Project Base Case A3 (Golden Vly 69 kv) - Power Flow Map (All Lines in Service) October

38 Section 14: Light Winter Post-Project Base Case A4 (All 3 Locations) - Power Flow Map (All Lines in Service) October

39 Appendix B Summary of Power Flow Analysis Results October

40 Table B1: Summary of Power Flow Study Results for Heavy Summer Base Case A1 (Industrial 69 kv) Worst Outage Overloaded Facility Applicable Rating Category A Normal Overloads Pre- Project Case A Loading (%) Post- Project Case A1 Comments ALL LINES IN SERVICE NONE N/A N/A N/A None Category B Contingencies BKMTNTP1 BLK_MTN 69 KV LINE SACROSUB - GRIFTAP3 69 KV LINE 661 A SACROSUB BKMTNTP2 69 KV LINE 661 A BKMTNTP2 BLK_MTN 69 KV LINE GRIFFITH YUCCATAP 69 KV LINE 661 A SACROSUB BKMTNTP2 69 KV LINE YUCCATAP BKMTNTP1 69 KV LINE 661 A BLK MESA #1 230/69 KV TRANSFORMER BLK MESA #2 230/69 KV TRANSFORMER MCCONICO-DAVIS 230 KV LINE & PEACOCK 345/230 KV TRANSFORMER BLK MESA #2 230/69 KV TRANSFORMER BLK MESA #1 230/69 KV TRANSFORMER Category C/D Contingencies 45 MVA MVA Overload not attributable to the addition of the proposed project PRSCOTWA RNDVLYTP 230 KV LINE 897 A Overload exacerbated by PEACOCK-RNDVLYTP 230 KV LINE 897 A the addition of proposed project October

41 Table B2: Summary of Power Flow Study Results for Light Winter Base Case A1 (Industrial 69 kv) Worst Outage Overloaded Facility Applicable Rating Category A Normal Overloads Pre- Project Case A Loading (%) Post- Project Case A1 Loading (%) Comments ALL LINES IN SERVICE NONE N/A N/A N/A None Category B Contingencies BKMTNTP1 BLK_MTN 69 KV LINE SACROSUB - GRIFTAP3 69 KV LINE 661 A SACROSUB BKMTNTP2 69 KV LINE 661 A BKMTNTP2 BLK_MTN 69 KV LINE GRIFFITH YUCCATAP 69 KV LINE 661 A YUCCATAP BKMTNTP1 69 KV LINE 661 A Category C/D Contingencies Overload not due to the addition of proposed project NONE NONE N/A N/A N/A Same facility overloads as recorded under category B contingencies October

42 Table B3: Summary of Power Flow Study Results for Heavy Summer Base Case A2 (Boriana 69 kv) Worst Outage Overloaded Facility Applicable Rating ALL LINES IN SERVICE Category A Normal Overloads Pre- Project Case A Loading (%) Post- Project Case A2 Comments GRIFFITH 230/69 KV TRANSFORMER 80 MVA Replace transformer with a 150 MVA rated one BORIANA BORIANATP 69 KV LINE 368 A Rebuild line Category B Contingencies GRIFFITH GRIFTAP3 69 KV LINE BKMTMTP1 BLK_MTN 69 KV LINE 912 A Overload due to GRIFFITH GRIFTAP3 69 KV LINE 912 A KAPVGP.Rebuild the overloaded lines BKMTNTP1 BLK_MTN 69 KV LINE SACROSUB - GRIFTAP3 69 KV LINE 661 A SACROSUB BKMTNTP2 69 KV LINE 661 A Overload exacerbated by GRIFFITH GRIFTAP3 69 KV LINE GRIFFITH YUCCATAP 69 KV LINE 661 A the addition of proposed project GRIFFITH GRIFTAP3 69 KV LINE YUCCATAP BKMTMTP1 69 KV LINE 661 A BLK MESA #1 230/69 KV TRANSFORMER BLK MESA #2 230/69 KV TRANSFORMER GRIFFITH PEACOCK & HILLTOP- MCCONICO 230 KV LINES GRIFFITH PEACOCK & DAVIS- MCCONICO 230 KV LINES MCCONICO-DAVIS 230 KV LINE & PEACOCK 345/230 KV TRANSFORMER BLK MESA #2 230/69 KV TRANSFORMER BLK MESA #1 230/69 KV TRANSFORMER Category C/D Contingencies 45 MVA MVA Overload not attributable to the addition of the proposed project MCCONICO DAVIS 230 KV LINE 1336 A Overload due to the addition of proposed project HILLTOP-MCCONICO 230 KV LINE 1336 A PRSCOTWA RNDVLYTP 230 KV LINE 897 A Overload exacerbated by PEACOCK-RNDVLYTP 230 KV LINE 897 A the addition of proposed project October

43 Table B4: Summary of Power Flow Study Results for Light Winter Base Case A2 (Boriana 69 kv) Worst Outage Overloaded Facility Applicable Rating ALL LINES IN SERVICE Category A Normal Overloads Pre- Project Case A Loading (%) Post- Project Case A2 Comments GRIFFITH 230/69 KV TRANSFORMER 80 MVA Overload due to addition of KAPVGP. Replace transformer with a 150 MVA rated one BORIANA BORIANATP 69 KV LINE 368 A Overload due to KAPVGP. Rebuild line Category B Contingencies BKMTMTP1 BLK_MTN 69 KV LINE GRIFFITH GRIFTAP3 69 KV LINE 912 A Overload due to KAPVGP. GRIFFITH GRIFTAP3 69 KV LINE BKMTMTP1 BLK_MTN 69 KV LINE 912 A Rebuild overloaded lines BKMTNTP1 BLK_MTN 69 KV LINE SACROSUB - GRIFTAP3 69 KV LINE 661 A SACROSUB BKMTNTP2 69 KV LINE 661 A BKMTNTP2 BLK_MTN 69 KV LINE GRIFFITH YUCCATAP 69 KV LINE 661 A YUCCATAP BKMTNTP1 69 KV LINE 661 A Category C/D Contingencies Overload exacerbated by the addition of proposed project None None N/A N/A N/A Same facility overloads as recorded under category B contingencies October

44 Table B5: Summary of Power Flow Study Results for Heavy Summer Base Case A3 (W. Golden Vly 69 kv) Worst Outage Overloaded Facility Applicable Rating Category A Normal Overloads Pre- Project Case A Loading (%) Post- Project Case A3 Comments ALL LINES IN SERVICE GRIFFITH 230/69 KV TRANSFORMER 80 MVA Overload due to addition of KAPVGP. Replace transformer with a 150 MVA rated one Category B Contingencies GRIFFITH GRIFTAP3 69 KV LINE BKMTMTP1 BLK_MTN 69 KV LINE 912 A Overload due to KAPVGP. GRIFFITH GRIFTAP3 69 KV LINE 912 A Rebuild the overloaded lines BKMTNTP1 BLK_MTN 69 KV LINE SACROSUB - GRIFTAP3 69 KV LINE 661 A Overload exacerbated by SACROSUB BKMTNTP2 69 KV LINE 661 A the addition of proposed project BKMTNTP2 BLK_MTN 69 KV LINE GRIFFITH YUCCATAP 69 KV LINE 661 A SACROSUB BKMTNTP2 69 KV LINE YUCCATAP BKMTNTP1 69 KV LINE 661 A BLK MESA #1 230/69 KV TRANSFORMER BLK MESA #2 230/69 KV TRANSFORMER PEACOCK-RNDVLYTP 230 KV LINE & PEACOCK 345/230 KV TRANSFORMER GRIFFITH PEACOCK & DAVIS- MCCONICO 230 KV LINES MCCONICO-DAVIS 230 KV LINE & PEACOCK 345/230 KV TRANSFORMER BLK MESA #2 230/69 KV TRANSFORMER BLK MESA #1 230/69 KV TRANSFORMER Category C/D Contingencies 45 MVA Overload not attributable to the addition of the proposed 45 MVA project MCCONICO DAVIS 230 KV LINE 1336 A Overload due to the addition of the proposed project HILLTOP-MCCONICO 230 KV LINE 1336 A PRSCOTWA RNDVLYTP 230 KV LINE 897 A Overload exacerbated by the addition of proposed project PEACOCK-RNDVLYTP 230 KV LINE 897 A October

45 Table B6: Summary of Power Flow Study Results for Light Winter Base Case A3 (W. Golden Vly 69 kv) Worst Outage Overloaded Facility Applicable Rating Category A Normal Overloads Pre- Project Case A Loading (%) Post- Project Case A2 Comments ALL LINES IN SERVICE GRIFFITH 230/69 KV TRANSFORMER 80 MVA Overload due to addition of KAPVGP. Replace transformer with a 150 MVA rated one Category B Contingencies BKMTMTP1 BLK_MTN 69 KV LINE GRIFFITH GRIFTAP3 69 KV LINE 912 A Overload due to addition of GRIFFITH GRIFTAP3 69 KV LINE BKMTMTP1 BLK_MTN 69 KV LINE 912 A KAPVGP. Rebuild overloaded lines BKMTNTP1 BLK_MTN 69 KV LINE SACROSUB - GRIFTAP3 69 KV LINE 661 A Overload exacerbated by SACROSUB BKMTNTP2 69 KV LINE 661 A the addition of proposed project BKMTNTP2 BLK_MTN 69 KV LINE GRIFFITH YUCCATAP 69 KV LINE 661 A YUCCATAP BKMTNTP1 69 KV LINE 661 A Category C/D Contingencies None None N/A N/A N/A Same facility overloads as recorded under category B contingencies October

46 Table B7: Summary of Power Flow Study Results for Heavy Summer Base Case A4 (All 3 Locations) Worst Outage Overloaded Facility Applicable Rating ALL LINES IN SERVICE Category A Normal Overloads Pre- Project Case A Loading (%) Post- Project Case A4 Comments GRIFFITH 230/69 KV TRANSFORMER 80 MVA Overload due to KAPVGP. Additional transformer required BORIANA BORIANATP 69 KV LINE 368 A Overload due to KAPVGP. Rebuild line Category B Contingencies GRIFFITH GRIFTAP3 69 KV LINE BKMTMTP1 BLK_MTN 69 KV LINE 912 A Overload due to KAPVGP. BKMTNTP1 BLK_MTN 69 KV LINE GRIFFITH GRIFTAP3 69 KV LINE 912 A Rebuild the overloaded lines SACROSUB - GRIFTAP3 69 KV LINE 661 A SACROSUB BKMTNTP2 69 KV LINE 661 A BKMTNTP2 BLK_MTN 69 KV LINE GRIFFITH YUCCATAP 69 KV LINE 661 A SACROSUB BKMTNTP2 69 KV LINE YUCCATAP BKMTNTP1 69 KV LINE 661 A BLK MESA #1 230/69 KV TRANSFORMER BLK MESA #2 230/69 KV TRANSFORMER BLK MESA #2 230/69 KV TRANSFORMER BLK MESA #1 230/69 KV TRANSFORMER 45 MVA MVA Overload exacerbated by the addition of proposed project Overload not attributable to the addition of the proposed project October

47 Table B7: Summary of Power Flow Study Results for Heavy Summer Base Case A4 (All 3 Locations) Continued Worst Outage Overloaded Facility Applicable Rating GRIFFITH PEACOCK & HILLTOP- MCCONICO 230 KV LINES GRIFFITH PEACOCK & DAVIS- MCCONICO 230 KV LINES MCCONICO-DAVIS 230 KV LINE & PEACOCK 345/230 KV TRANSFORMER Category C/D Contingencies Pre- Project Case A Loading (%) Post- Project Case A4 MCCONICO DAVIS 230 KV LINE 1336 A HILLTOP-MCCONICO 230 KV LINE 1336 A PEACOCK HILLTOP 230 KV LINE 1336 A Comments Overload due to the addition of proposed project PRSCOTWA RNDVLYTP 230 KV LINE 897 A Overload exacerbated by the addition of proposed project PEACOCK-RNDVLYTP 230 KV LINE 897 A Overload attributable to the addition of the proposed project October

48 Table B8: Summary of Power Flow Study Results for Light Winter Base Case A4 (All 3 Locations) Worst Outage Overloaded Facility Applicable Rating ALL LINES IN SERVICE Category A Normal Overloads Pre- Project Case A Loading (%) Post- Project Case A4 Comments GRIFFITH 230/69 KV TRANSFORMER 80 MVA Overload due to KAPVGP. Additional transformer required BORIANA BORIANATP 69 KV LINE 368 A Overload due to KAPVGP. Rebuild line Category B Contingencies BKMTMTP1 BLK_MTN 69 KV LINE GRIFFITH GRIFTAP3 69 KV LINE 912 A Overload due to addition of GRIFFITH GRIFTAP3 69 KV LINE BKMTMTP1 BLK_MTN 69 KV LINE 912 A KAPVGP. Rebuild overloaded lines BKMTNTP1 BLK_MTN 69 KV LINE SACROSUB - GRIFTAP3 69 KV LINE 661 A Overload exacerbated by SACROSUB BKMTNTP2 69 KV LINE 661 A the addition of proposed project BKMTNTP2 BLK_MTN 69 KV LINE GRIFFITH YUCCATAP 69 KV LINE 661 A YUCCATAP BKMTNTP1 69 KV LINE 661 A Category C/D Contingencies None None N/A N/A N/A Same facility overloads as recorded under category B contingencies October

49 Appendix C Power Flow Contingency List October

50 CATEGORY A RUN 0 CATEGORY BR LINE "LIBERTY " "PEACOCK " RUN 1 CATEGORY BR LINE "PEACOCK " "MEAD " RUN 2 LINE "DAVIS " "MCCULLGH" RUN 3 LINE "DAVIS " "MEAD N " RUN 4 LINE "DAVIS " "RIVIERA " RUN 5 LINE "DAVIS " "TOPOCK " RUN 6 LINE "DAVIS " "ZORB " RUN 7 LINE "GRIFFITH" "PEACOCK " RUN 8 LINE "HARRIS " "MERCATOR" RUN 9 LINE "HILLTOP " "MCCONICO" RUN 10 LINE "MCCONICO" "DAVIS " RUN 11 LINE "MCCONICO" "GRIFFITH" RUN 12 LINE "MCCONICO" "HARRIS " RUN 13 LINE "N.HAVASU" "PARKER " RUN 14 LINE "N.HAVASU" "TOPOCK " RUN 15 LINE "PARKER " "BLK MESA" RUN 16 October

51 LINE "PARKER " "EAGLEYE " RUN 17 LINE "PARKER " "GENE " RUN 18 LINE "PARKER " "HARCUVAR" RUN 19 LINE "PARKER " "HAVASU " RUN 20 LINE "PEACOCK " "HILLTOP " RUN 21 LINE "PRESCOTT" "RNDVLYTP" RUN 22 LINE "RNDVLYTP" "PEACOCK " RUN 23 LINE "TOPOCK " "BLK MESA" RUN 24 LINE "TOPOCK " "SOPOINT " RUN 25 LINE "ZORB " "TOPOCK " RUN 26 LINE "PARKER " "BLYTHE " RUN 27 LINE "PARKER " "BOUSE " RUN 28 LINE "PARKER " "HEADGATE" RUN 29 LINE "PARKER " "PARKERAZ" RUN 30 LINE "BKMTNTP1" "BLK_MTN " RUN 31 LINE "BKMTNTP2" "BLK_MTN " RUN 32 LINE "BORIANTP" "BDRYCONE" RUN 33 October

52 LINE "BORIANTP" "BORIANA " RUN 34 LINE "CANTEX " "AIRPORT " RUN 35 LINE "CANTEX " "IVY_WIRE" RUN 36 LINE "CASSON " "CASSONTP" RUN 37 LINE "CHLORJCT" "PIERFERR" RUN 38 LINE "DUVALBOS" "DUVALRCM" RUN 39 LINE "DUVALBOS" "DUVALTAP" RUN 40 LINE "GRIFFITH" "GRIFTAP1" RUN 41 LINE "GRIFFITH" "GRIFTAP3" RUN 42 LINE "GRIFFITH" "YUCCATAP" RUN 43 LINE "GRIFTAP1" "GRIFTAP2" RUN 44 LINE "GRIFTAP2" "SKINGTAP" RUN 45 LINE "GRIFTAP3" "BORIANTP" RUN 46 LINE "GUARDIAN" "EASTERN " RUN 47 LINE "GUARDIAN" "INDUSTRL" RUN 48 LINE "GVTAP " "GOLDVALL" RUN 49 LINE "GVTAP " "SOHI " RUN 50 October

53 LINE "HIGHWAY " "WILLBECH" RUN 51 LINE "HILLTOP1" "EASTERN " RUN 52 LINE "HILLTOP2" "CASSONTP" RUN 53 LINE "JAGERSON" "AIRPORT " RUN 54 LINE "NKINGTAP" "GVTAP " RUN 55 LINE "NORTKING" "CASSONTP" RUN 56 LINE "PIERFERR" "DOLSPRNG" RUN 57 LINE "PIERFERR" "HIGHWAY " RUN 58 LINE "S.WIRE " "AIRPORT " RUN 59 LINE "S.WIRE " "INDUSTRL" RUN 60 LINE "SACROSUB" "BKMTNTP2" RUN 61 LINE "SACROSUB" "GRIFTAP3" RUN 62 LINE "SKINGTAP" "NKINGTAP" RUN 63 LINE "SKINGTAP" "SOTHKING" RUN 64 LINE "SOHI " "CHLORJCT" RUN 65 LINE "W.GDNTAP" "BORIANTP" RUN 66 LINE "W.GDNTAP" "DUVALTAP" RUN 67 October

54 LINE "W.GDNTAP" "DUVALWTR" RUN 68 LINE "W.GDNTAP" "W.GDNVLY" RUN 69 LINE "WILLBECH" "GOLDSTRK" RUN 70 LINE "YUCCASUB" "YUCCATAP" RUN 71 LINE "YUCCATAP" "BKMTNTP1" RUN 72 CATEGORY BR XFMR "MEAD " "MEAD N " RUN 73 CATEGORY BR XFMR "MEAD " "MEAD N " RUN 74 CATEGORY BR XFMR "MEAD " "MEAD N " RUN 75 CATEGORY BR XFMR "PEACOCK " "PEACOCK " RUN 76 XFMR "BLK MESA" "BLK MESA" RUN 77 XFMR "GRIFFITH" "GRIFFTH1" RUN 79 XFMR "GRIFFITH" "GRIFFTH2" RUN 80 XFMR "GRIFFITH" "GRIFFTH3" RUN 81 XFMR "SOPOINT " "SOPOINT1" RUN 82 XFMR "SOPOINT " "SOPOINT2" RUN 83 XFMR "SOPOINT " "SOPOINT3" RUN 84 XFMR "PARKER " "PARKER " RUN 85 October

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning. A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION El Paso Electric Company System Operations Department System Planning Section August 2006 I. INTRODUCTION The

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

Q85 Generation Interconnection

Q85 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q85 Generation Interconnection Interconnection Facilities Study AMENDED APS Contract No. 52386 By Arizona Public Service Company Transmission Planning

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Midway/Monument Area TTC Study

Midway/Monument Area TTC Study Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny

More information

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications Supplement to 2013-2014 ISO Transmission Plan Harry Allen-Eldorado Project Description and Functional Specifications Description and Functional Specifications of Proposed Economically Driven Harry Allen

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

PUD ELECTRIC SYSTEM INTERCONNECTION

PUD ELECTRIC SYSTEM INTERCONNECTION APPENDIX A PROCEDURES & REQUIREMENTS for OKANOGAN PUD ELECTRIC SYSTEM INTERCONNECTION Version 4.0 December 2011 Version 4.0 12/28/2011 Page 1 of 15 TABLE OF CONTENTS DEFINITIONS 1.0 Introduction 2.0 Procedures

More information

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report San Diego Gas & Electric, a Sempra Energy Utility SDGE HVDC Phase 1 Project No. 101512 Revision 01 11/29/2018 SDG&E High

More information

Q217 Generator Interconnection Project

Q217 Generator Interconnection Project Q217 Generator Interconnection System Impact Study APS Contract No. 52588 By Arizona Public Service Company Transmission Planning November 25, 2013 Version 2.0 Prepared by Utility System Efficiencies,

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Connection Engineering Study Report for AUC Application: AESO Project # 1674 APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

El Paso Electric Company

El Paso Electric Company Feasibility Study XXXXXX Solar Generation Prepared for El Paso Electric Company Prepared by TRC Engineers, LLC 249 Eastern Avenues Augusta, ME 04330 (207) 621-7000 Project Number: 202327 May 2013 FOREWORD

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

Small Generator Interconnection Program Interconnection Technical Requirements

Small Generator Interconnection Program Interconnection Technical Requirements General Program Information What is the purpose of the PGE Small Generator Interconnection Program? How do I initiate a distribution interconnection request for my project? The purpose of our Small Generator

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Western Region ATSI Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

Q87 Generation Interconnection

Q87 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Version 1.0 Q87 Generation Interconnection Interconnection Facilities Study APS Contract No. 52365 By Arizona Public Service Company Transmission Planning

More information

2012 LOCAL TRANSMISSION PLAN:

2012 LOCAL TRANSMISSION PLAN: Colorado PUC E-Filings System 2012 LOCAL TRANSMISSION PLAN: TRANSMISSION COORDINATION AND PLANNING COMMITTEE ANNUAL TRANSMISSION ASSESSMENT FOR BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, L.P., D/B/A

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents APPENDIX A CONNECTION ASSESSMENT : FortisAlberta Inc. Plamondon 5S Capacity Increase Contents Executive Summary.... Introduction... 6. Project... 6.. Project Overview... 6.. Load Component... 6.. Generation

More information

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007 High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services

More information

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study XXXX Knob Hill Wind Farm Project Report No. August 2010 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All rights reserved.. DISCLAIMER OF WARRANTY, LIMITATION

More information

Interconnection System Impact Study Final Report February 19, 2018

Interconnection System Impact Study Final Report February 19, 2018 Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen

More information

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2014 Annual Ten-Year Transmission Plan Assessment Report November 20, 2014 For information or questions regarding this Transmission Assessment Report,

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia

More information

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving

More information

Project #94. Generation Interconnection System Impact Study Report Revision

Project #94. Generation Interconnection System Impact Study Report Revision Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the

More information

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS System Operations Department System Planning Section June 2001 TABLE OF CONTENTS 1.0 Executive Summary...Page

More information

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study System Operations Department System Planning Section March 2002 Table of Contents: 1.0 EXECUTIVE SUMMARY 4 2.0 COST ESTIMATES 8 2.1 Cost

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

Q92 Asarco Interconnection

Q92 Asarco Interconnection A subsidiary of Pinnacle West Capital Corporation Q92 Asarco Interconnection Feasibility Study APS Contract No. 52239 By Arizona Public Service Company Transmission Planning July 29, 2010 Prepared by Utility

More information

Q0044 interconnection at

Q0044 interconnection at Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PSE&G System Characteristics New Jersey utility characterized by densely populated

More information

ATTACHMENT - DFO STATEMENT OF NEED

ATTACHMENT - DFO STATEMENT OF NEED ATTACHMENT - DFO STATEMENT OF NEED Table of Contents Executive Summary... 3 1. Description of the Area... 5 1.1 Geographic Study Area... 5 1.2 Current System Configuration... 7 1.3 Distributed Generation...

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04 Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

Generation Interconnection Facilities Study For

Generation Interconnection Facilities Study For Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...

More information

Verde Transmission, LLC. Verde Project. System Impact Study Report

Verde Transmission, LLC. Verde Project. System Impact Study Report Verde Transmission, LLC Verde Project System Impact Study Report March 2017 Prepared by: Public Service Company of New Mexico Foreword This report was prepared for Verde Transmission, LLC by the PNM Transmission/

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2013 Annual Ten-Year Transmission Plan Assessment Report December 1, 2013 For information or questions regarding this Transmission Assessment Report,

More information

New Mexico Transmission Expansion Concepts For Wind Resources

New Mexico Transmission Expansion Concepts For Wind Resources New Mexico Transmission Expansion Concepts For Wind Resources May 2008 Update Electric Services Transmission Operations FOREWORD This document contains PNM s latest concepts for expanding the transmission

More information

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management Southern Company Interconnection Process Dexter Lewis Research Engineer Research and Technology Management Southern Company Outline Southern Company GPC Solar Interconnection Process Application requirements

More information

PES Cook Islands KEMA Grid Study Final Report

PES Cook Islands KEMA Grid Study Final Report Integrating PV Solar and Wind generation with the TAU electric system Te Aponga Uira O Tumu-Te_Varovaro Contents 1. Executive summary... 2 2. Introduction... 5 2.1 Proposed wind turbine sites... 6 2.2

More information

SMUD 2014 Ten-Year Transmission Assessment Plan. Final. December 18, 2014

SMUD 2014 Ten-Year Transmission Assessment Plan. Final. December 18, 2014 SMUD 2014 Ten-Year Transmission Assessment Plan Final December 18, 2014 I CONTENTS Executive Summary... III 1 Introduction... 2 1.1 Reliability Criteria and Guidelines... 2 1.2 Load Forecast... 2 1.3 Demand

More information

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design Presented at the 2018 Transmission and Substation Design and Operation Symposium Revision presented at the

More information

XXXX. Kokish River Hydroelectric Project. Interconnection System Impact Study

XXXX. Kokish River Hydroelectric Project. Interconnection System Impact Study XXXX Kokish River Hydroelectric Project Report No. August 2010 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All rights reserved.. DISCLAIMER OF WARRANTY,

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC OCTOBER 17, 2018 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC

More information

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED DATE: June 28, 2011 STAFF: Brian Janonis Brian Moeck, PRPA Pre-taped staff presentation: none WORK SESSION ITEM FORT COLLINS CITY COUNCIL SUBJECT FOR DISCUSSION Electric Transmission Update. EXECUTIVE

More information

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study ` Dunvegan Hydroelectric Project For Glacier Power Limited Preliminary Interconnection Study Prepared by Pung Toy, P. Eng. and Ata Rehman, P. Eng. September 24, 2004 Table of Contents Table of Contents...

More information

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS El Paso Electric Company System Operations Department System Planning

More information

Cost Benefit Analysis of Faster Transmission System Protection Systems

Cost Benefit Analysis of Faster Transmission System Protection Systems Cost Benefit Analysis of Faster Transmission System Protection Systems Presented at the 71st Annual Conference for Protective Engineers Brian Ehsani, Black & Veatch Jason Hulme, Black & Veatch Abstract

More information

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection

More information