1 ATTACHMENT - DFO STATEMENT OF NEED

2

3 Table of Contents Executive Summary Description of the Area Geographic Study Area Current System Configuration Distributed Generation Equipment Ratings Area Loading Load Growth Development Load Forecast Customer Sites Distribution System Performance Standard Distribution Point of Delivery (POD) Substations Risk Assessment Distribution Load at Risk Customer Count Impact Load at Risk Frequency Alternatives Alternative 1: Do Nothing Alternative 2: Add Distribution System Capacity Alternative 3: Install Second Autotransformer (Spare) at No.21 Sub Alternative 4: Upgrade 36.5TR (Spare) Alternative 5: Install New 36.5TR Autotransformer Capital Cost Estimates Alternative 1: Do Nothing Alternative 2: Add Distribution System Capacity Alternative 3: Install Second Autotransformer (Spare) at No.21 Sub Alternative 4: Upgrade 36.5TR (Spare) Alternative 5: Install New 36.5TR Auto Proposed System Development Preferred Alternative Load-at-Risk Preferred Alternative 4 Implemented In-Service Date

4 Executive Summary ENMAX Power Corporation (EPC) Distribution Facility Owner (DFO), in its capacity as the legal owner of the electric distribution system, is submitting a request for system access service to the Alberta Electric System Operator (AESO). The request for system access service includes a request for upgrades at EPC No. 36 substation in order to satisfy ENMAX DFO Distribution System Performance Standard. At the present time, there is no request for change to the current Demand Transmission Service (DTS) contract at No. 36 Substation as part of the request for system access. The North 69 kv Subsystem supplies distribution commercial, institutional and residential communities in northwest Calgary, including major distribution customers such as Alberta Children s Hospital, the University of Calgary, LRT stations, Market Mall and the Foothills Medical Centre (refer to Figure 1 for North 69 kv Subsystem distribution customer geographic area). For purposes of obtaining transmission maintenance outages in the North 69 kv Subsystem, radial transmission reconfigurations (resulting in four radially supplied substations) and distribution load transfers are required due to subsystem overloads under the next contingency. ENMAX DFO has identified that these transmission reconfigurations and distribution load transfers result in more than two radially fed substations and an increased risk of prolonged distribution outages (distribution customer load at risk) in the event of the next transmission or distribution contingency. Based on 2016 customer site counts, planned and unplanned outages on in-feed autotransformers and transmission lines supplying the North 69 kv Subsystem distribution POD substations will place roughly 28,313 metered distribution customer sites at risk of a prolonged outage. The worst case North 69 kv Subsystem radial transmission reconfigurations, shown in Figure 3, result in a customer load at risk that cannot be restored in the event of the next autotransformer or transmission line outage. In 2016, the worst case load at risk was found to be 23 MVA 1, with the 10 year forecasted load at risk increasing to 25 MVA. Presently, the Distribution Point of Delivery substations in the North 69 kv Subsystem do not meet the EPC Distribution System Performance standard pertaining to the planning and operation of a reliable distribution system when performing maintenance activities on the transmission system: Distribution Point of Delivery (POD) substations shall be planned, designed and operated to ensure no more than two POD substations are supplied radially as a result of a planned transmission circuit or autotransformer outage 2. Pre-system reconfigurations that require distribution load transfers to alleviate transmission system overloads are not acceptable due to the increased customer outage risk under the next distribution contingency. Remedial Action Schemes (RAS) that involve customer load shedding to alleviate transmission system overloads are not acceptable. 1 Combined No. 15 Sub and No. 34 Sub load at risk. 2 Three or more POD Substations supplied by separate radial configurations are considered a violation of condition. 3

5 ENMAX DFO has considered implementing changes and additions to the existing distribution infrastructure and found the distribution alternatives to be in violation of the EPC Distribution System Performance Standard, cost prohibitive and unable to address the identified deficiency. As a result, ENMAX DFO, in consultation with the ENMAX Transmission Facility Owner (TFO), explored alternatives that will address the DFO reliability requirements. The preferred Alternative 4 involves the upgrade of the autotransformer at No.36 Substation (36.5TR) and is the most viable and cost effective engineering solution to address the Distribution System Performance violation. Upon implementation of Alternative 4, performing in-feed autotransformer and transmission line maintenance outages that supply the North 69 kv Subsystem POD substations will no longer need transmission reconfigurations that create a load at risk to distribution customers and increase their exposure to prolonged outages. The estimated capital cost for the preferred Alternative 4 is $1.9M (+/- 30%), including Interest During Construction (IDC) and Administrative Overhead (AOH), with a requested in-service date of Q

6 1. Description of the Area 1.1 Geographic Study Area The North 69 kv Subsystem comprises the kv autotransformers 36.5TR at No. 36 Sub, 13.4TR at No. 13 Sub and 21.4TR at No. 21 Sub, which are the three supply sources to the North 69 kv transmission facilities supplying the kv Point of Delivery (POD) No. 15, 16, 27, and 34 Substations. The POD substations serve the distribution 13.8 kv facilities supplying load in the following commercial and residential communities: Banff Trail Bowness Brentwood Cambrian Heights Capitol Hill Charleswood Collingwood Dalhousie Highland Park Highwood Huntington Hills Montgomery Major distribution customers include: Mount Pleasant North Haven North Haven Upper Nose Hill Park Parkdale Point McKay Rosemont Silversprings Thorncliffe University District Varsity Alberta Children s Hospital Foothills Medical Centre Four Calgary Light Rail Transit (LRT) traction power substations: Dalhousie, Northland, Brentwood, University University of Calgary Market Mall The North 69 kv Subsystem Distribution Customer Load Area is shown in Figure 1. 5

7 DALHOUSIE LRT SUB 16.63L 16.61L NORTHLAND LRT SUB BRENTWOOD LRT SUB 13.60L MARKET MALL 15.62L 16.60L 16.60L ALBERTA CHILDREN S HOSPITAL 21.61L UNIVERSITY LRT SUB FOOTHILLS MEDICAL CENTRE 15.60L 21.61L Figure 1: North 69 kv Subsystem Distribution Customer Load Area 6

8 1.2 Current System Configuration The North 69 kv Subsystem is supplied from three in-feed sources at No. 13, No. 21 and No. 36 Substations through the following kv step-down autotransformers: 13.4TR 112 MVA (located at No.13 Substation) 21.4TR 112 MVA (located at No.21 Substation) 36.5TR 50 MVA (located at No.36 Substation) These sources supply a network of seven 69 kv transmission lines: 13.60L 15.60L 15.62L 16.60L 16.61L 16.63L 21.61L These sources and transmission lines further supply four kv Point of Delivery substations to support the local area distribution load (refer to Figure 1 for geographic representation of distribution load area). The four kv POD Substations are: No.15 Substation No.16 Substation No.27 Substation No.34 Substation Figure 2 depicts the in-feed sources and the transmission lines supplying the North 69 kv POD substations as well as the POD substations in the North 69 kv Subsystem that supply the 13.8 kv distribution customer load. 7

9 Figure 2: North 69 kv Subsystem 16.63L 16.61L 13.60L TR 50 MVA 15.62L 16.60L 13.4TR 112 MVA L 21.61L LEGEND 138 kv 21.4TR 112 MVA 69 kv Substation /69 kv Autotransformer 8

10 1.3 Distributed Generation POD No. 34 Substation supplies the load of University of Calgary. In addition to consuming load, the University of Calgary (U of C) has a 15 MW cogeneration plant 1 connected to the ENMAX distribution system. Depending on time of day load demand at University of Calgary, the U of C cogeneration plant may backfeed onto the ENMAX distribution system. Historical performance of U of C cogeneration plant indicates that the plant may be shut down for maintenance for prolonged periods at various times throughout the year. For the purposes of the distribution load at risk assessment in section 5.1, the cogeneration plant is assumed to be off in the study. As well, the coincident load forecast for the North 69 kv Subsystem (refer to Section 3.2) does not incorporate the generation from U of C as it is not considered a reliable generation supply

11 2. Equipment Ratings The summer and winter ratings of the major transmission equipment identified in Section 1.2 are outlined in Table 1. These ratings, provided by ENMAX TFO, define the operating limits of major equipment in the North 69 kv Subsystem. In addition, each transmission line has an approved 10-minute emergency rating at which the equipment can be operated, also shown in Table 1. If equipment is overloaded during an emergency event, ENMAX Operators will take immediate action to reduce the loading below normal equipment ratings. Autotransformers do not have an approved emergency rating and can only be operated to the manufacturer nameplate rating. Equipment Table 1: North 69 kv Subsystem Major Transmission Equipment Ratings Nominal Voltage (kv) Summer Normal Rating (MVA) Winter Normal Rating (MVA) Summer Emergency Rating (MVA) 1 Winter Emergency Rating (MVA) TR NA NA 21.4TR NA NA 36.5TR NA NA 13.60L L L L L L L Emergency ratings are available for up to 30 minutes. 2 Emergency ratings are available for up to 30 minutes. 10

12 3. Area Loading The 2011 to 2017 actual coincident loading in the North 69 kv Subsystem is shown in the table below. Sub Total 1 Peak Season S W S W S W S W S W Table 2: North 69 kv System POD Coincident Peak Load Actuals (MVA) Power Actual Load (MVA) Factor N/A N/A Load Growth Development The major subdivision developments and the associated distribution load growth for the next 20 years are listed in Table 3. The load growth shown below has been integrated into the overall area load forecast, shown in Table 5, but at a coincident level. Table 3: North 69 kv Subsystem Major Area Anticipated Load Additions ( ) Description of New Load Addition Substation Forecasted Load (MVA) Northland Village Redevelopment 16 4 University District (West Campus) Brentwood Redevelopment 34 8 Montgomery/Bowness Redevelopment 15 5 Major Institutions Upgrade 15/34 15 Total Area Load Growth (Non-Coincident) 52 1 Totals influenced by rounding. 11

13 3.2 Load Forecast The load forecast for the kv POD substations No.15, 16, 27 and 34 in the North 69 kv Subsystem is shown in Table Customer Sites The North 69 kv Subsystem supplies roughly 28,313 metered distribution customer sites. A detailed customer site breakdown by substation is shown in Table 4. Table 4: North 69 kv Subsystem Total Distribution Customer Count Breakdown Substation Number of Metered Customer Sites , , , ,890 Total 28,313 The University of Calgary (supplied from 34 Sub) which supports roughly 33,400 students and staff, consists of only a few metered sites in the total distribution customer count. Distribution customer counts are based on the total number of metered sites even though some large institutions or commercial operations might service multiple floors or buildings. 1 Total North 69 kv Subsystem metered customer sites as of

14 Table 5: North 69 kv System POD Coincident Peak Load Forecast (MVA) Sub Total 1 Peak Season Power Factor Forecast Load (MVA) S W S W S W S W S W M Totals influenced by rounding. 2 Maintenance season considered to be 75% of summer peak. 13

15 4. Distribution System Performance Standard The purpose of the EPC Distribution System Performance Standard EPC-ARBP-DSP-ST-0001 is to ensure that a reliable distribution system is planned and can be operated to meet specific performance and customer reliability requirements. The applicable section of the EPC Distribution System Performance Standard is shown below and it pertains to the planning and operation of a reliable distribution system when performing maintenance activities on the transmission system. 4.1 Distribution Point of Delivery (POD) Substations Distribution Point of Delivery (POD) substations shall be planned, designed and operated to ensure no more than two POD substations are supplied radially as a result of a planned transmission circuit or autotransformer outage 1. Pre-system reconfigurations that require distribution load transfers to alleviate transmission system overloads are not acceptable due to the increased customer outage risk under the next distribution contingency. Remedial Action Schemes (RAS) that involve customer load shedding to alleviate transmission system overloads are not acceptable. 1 Three or more POD Substations supplied by separate radial configurations are considered a violation of condition. 14

16 5. Risk Assessment The risk assessment explores a typical North 69 kv reconfiguration when ENMAX TFO is performing maintenance activities on 13.60L or 13.4TR. The impacts of the next contingency occurring when performing transmission maintenance activities and its resulting distribution capacity deficiency, the number of customers impacted and the frequency of these reconfigurations occurring were studied. The results of these studies are summarized in this section. Based on Table 5, under the planned outage on 13.4TR followed by the next Category B Outage on 21.4TR (N-1-1), 36.5 TR will be the only supply for the North 69 kv Subsystem. It is anticipated that the power flow on 36.5TR would exceed the transformer rating under this N- 1-1 event. In this N-1-1 event, ENMAX forecasts that there will be 15 MVA of load at risk in 2018 increasing to 21 MVA of load at risk in Distribution Load at Risk ENMAX TFO typically schedules transmission maintenance activities in two week periods where the system loading averages 75% of the summer coincident peak loading level. A typical reconfiguration of the North 69 kv Subsystem is shown in figure 3 and occurs when ENMAX TFO performs maintenance activities on 13.60L transmission line or 13.4TR autotransformer resulting in four radially fed substations, with two substations No. 16 and No. 27 Sub supplied radially via 16.63L transmission line and fed via single element 36.5TR autotransformer at No. 36 Substation, and the other two substations No. 15 and No. 34 Sub are supplied radially via a single element 21.4TR autotransformer from No. 21 Substation. The four radially supplied substations resulting from the transmission radial reconfigurations of the North 69 kv Subsystem during an N-1 maintenance outage are in violation of the EPC Distribution System Performance Standard (refer to Section 4.1), which requires no more than two radially fed POD substations as a result of a transmission maintenance outage. The ENMAX distribution system is planned and built with POD transformer and feeder capacity to sustain a single N-1 POD transformer or feeder loss. An N-1-1 transmission loss on the North 69 kv subsystem results in the loss of multiple substations, which the distribution system cannot back up. The following distribution capacity study is provided to the AESO to highlight the capacity deficiency the distribution system will have under an N-1-1 transmission contingency and is for information only. A distribution capacity study was performed on this typical reconfiguration to assess the impacts of the next transmission contingency resulting in multiple POD substations losing supply. 15

17 Figure 3: Radial Configuration for a 13.60L or 13.4TR Outage 16.63L 16.61L 13.60L TR 15.62L 16.60L 13.4TR L 21.61L LEGEND Out of Service Element 138 kv 21.4TR kv Substation 138/69 kv Autotransformer In the event of the next N-1-1 transmission contingency occurring during a planned N-1 North 69 kv maintenance outage, there exists distribution customer load that cannot be restored without customers experiencing a prolonged outage. This is defined as Load at Risk (LAR) and it is the distribution customer load (MVA) that cannot be returned to service until the North 69 kv transmission system is returned to an N-1 state. Total tie-away capacity is defined as the maximum distribution capacity available to effectively transfer load should an entire Point of Delivery Substation incur a loss of supply Sub Combined Loading Sub Total Tie Away Capacity (Adjacent Feeders outside of North 69 kv Subsystem) Sub Load at Risk Table 7: Distribution Load at Risk (MVA) Impacts During a 13.60L or 13.4TR Outage Season* M M M Season* POD Combined Loading M Sub Total Tie Away Capacity (Adjacent Feeders outside of North M kv Subsystem) Sub Load at Risk M * Maintenance (M) season is considered 75% of loading of North 69kV Subsystem summer coincident peak 16

18 Although Table 7 shows a large amount of available Total Tie-Away Capacity, from operational point of view, it is not practical to transfer that magnitude of load through switching due to the following reasons: - Large number of feeders impacted and switching required for the load transfer, causing increased safety risk to ENMAX field staff performing live line work; - Large number of feeders, therefore customers experiencing abnormal state of supply resulting in inability to restore customer services should a distribution outage occur; - Uncertainty of the availability of the feeder tie-away capacity due to construction work, maintenance work or unplanned outages on the feeders, resulting in more customer load at risk With expected load growth in the study area of 52MVA over the next twenty years, the impact of the next N-1-1 transmission contingency to customers supplied from North 69 kv Subsystem will only worsen. Typical reconfigurations required to obtain North 69 kv Subsystem maintenance outages place four substations on radial transmission supply placing customers at risk of experiencing outages under the next transmission system contingency. These reconfigurations are in violation of the EPC Distribution System Performance Standard (refer to Section 4.1). The following section correlates the distribution load at risk to the number of customers that will experience prolonged outages as a result of the next contingency. 17

19 5.2 Customer Count Impact Further to the risk assessment study in 5.1, an assessment was done to quantify the number of customers impacted as a result of the next transmission contingency (N-1-1) occurring on the radially reconfigured North 69 kv Subsystem during an N TR or 13.60L maintenance outage (refer to Fig 4 for radial reconfiguration). The resulting customer outage impacts, represented by the number of metered sites, are shown in Table 8. Table 8: (N-1-1) Contingency impacts during a planned (N-1) 13.60L or 13.4TR maintenance outage Contingency N-1-1 Sub(s) Impacted Load Loss (MVA) 1 Number of Metered Sites L , TR 15, , L , L or 36.5TR 16, ,345 - LRT 21.61L ,890 Major Customers - Primarily residential - LRT - University of Calgary - Market Mall - LRT - Alberta Children s Hospital (main feeder) - Foothills Hospital (alternate feeder) - University of Calgary - Market Mall - Alberta Children s Hospital (main feeder) - University of Calgary - Market Mall - LRT Notes - Risk exists regardless of radial configuration - Restoration of 15.62L to 15 Sub possible - Restoration of 16.60L to 34 Sub not possible due to 36.5TR capacity constraints - University of Calgary accommodates approx. 33,400 students and staff daily - University of Calgary accommodates approx. 33,400 students and staff daily - Restoration of 15.62L and 16.60L to 16 Sub and 27 Sub possible - University of Calgary accommodates approx. 33,400 students and staff daily 1 Based on 2017 substation maintenance loading levels (75% of 2017 actual substation summer peak load). 2 Total North 69 kv Subsystem metered customer sites as of

20 5.3 Load at Risk Frequency In order to adequately maintain equipment in the North 69 kv Subsystem, outages on elements 13.4TR, 21.4TR, 36.5TR, 13.60L, 15.60L, 15.62L, 16.60L, 16.61L, 16.63L and 21.61L are routinely required. Maintenance outages can range in duration from one day to several weeks and include: Line and substation washing Breaker inspections Switch maintenance Motorized Disconnect (MD) maintenance Transformer and surge arrestor testing Based on existing loading levels in the North 69 kv Subsystem, planned outages are not possible for the majority of regular maintenance activities without implementing radial reconfigurations. Furthermore, the North 69 kv Subsystem has experienced an increased number of unplanned outages mainly due to equipment failures. These unplanned outages include cable, pothead, transformer and pole failures which require extended emergency outages to replace the failed equipment. As EPC proactively plans to replace the aging assets, longer duration outages will be required. EPC is currently evaluating pole and framing replacements on 16.63L, and a full rebuild of 16.61L. Construction schedules for these capital replacement activities can take several months and will require implementation of radial configurations to accommodate these longer duration outages, consequently increasing the reliability risk to EPC customers in the North 69 kv Subsystem. 19

21 6 Alternatives The existing transmission system configuration in the study area is presently unable to meet the EPC Distribution System Performance Standard (refer to section 4.1). In consultation with the ENMAX TFO, ENMAX DFO has explored alternatives and their abilities to resolve the identified system deficiency of having more than two POD substations supplied radially during a planned transmission circuit or autotransformer outage. 6.1 Alternative 1: Do Nothing This alternative involves leaving the North 69 kv Subsystem as currently configured without performing any capacity upgrades to mitigate the reliability risk. This alternative was dismissed for the following reasons: Existing North 69 kv Subsystem infrastructure cannot support maintenance outage requirements due to the distribution load at risk in the event of the next transmission contingency. Radial configurations during maintenance activities, as outlined in Section 4.1, will still be required, thus increasing the reliability risk to EPC customers and would be in violation of EPC Distribution System Performance Standard. 6.2 Alternative 2: Add Distribution System Capacity This alternative is provided for information only as it does not meet the EPC Distribution System Performance Standard. The alternative involves installing additional substation transformer and distribution breaker capacity at No. 14 and 20 Substations and adding new 13kV distribution feeders to be utilized for backup during substation contingencies in the North 69 kv Subsystem. This alternative was dismissed as it does not meet the EPC Distribution System Performance Standard. 20

22 6.3 Alternative 3: Install Second Autotransformer (Spare) at No.21 Sub This alternative involves installing a second 75/100/112 MVA, 69/138 kv autotransformer at No.21 Substation using a spare unit, installation of bus tie breakers on the 138 kv and 69 kv buses. This alternative will eliminate the need to reconfigure the North 69 kv Subsystem into a radial configuration, therefore mitigating the violation of the EPC Distribution System Performance Standard. Bus-tie breakers will also be required on the 69 kv and 138 kv busses in order to isolate the transformers during a transformer or bus fault event. Advantages: Radial configurations during maintenance activities, as outlined in Section 4.1, will no longer be required, thus reducing the reliability risk to EPC customers. Distribution load transfers to alleviate potential transmission system overloads (which are in violation of the EPC Distribution System Performance Standard) will no longer be required. Provides operational maintenance flexibility during peak loading periods. Utilization of an existing spare 75/100/112 MVA, 69/138 kv autotransformer reduces the cost of the upgrade. Alleviates immediate North 69 kv Subsystem capacity constraints during N-1-1 events and ensures compliance with EPC Distribution System Performance Standard. Disadvantages: Spare autotransformer at risk of requiring replacement due to age (42 years old). High cost alternative. This alternative is technically acceptable, but it was dismissed due to it being the highest cost alternative with marginal advantages it provides over Alternative 4. 21

23 6.4 Alternative 4: Upgrade 36.5TR (Spare) This alternative involves upgrading 36.5TR autotransformer to a capacity of 75/100/112 MVA using a spare unit. This alternative will eliminate the need to reconfigure the North 69 kv Subsystem into a radial configuration, therefore mitigating the violation of the EPC Distribution System Performance Standard. Advantages: Radial configurations during maintenance activities, as outlined in Section 4.1, will no longer be required, thus reducing the reliability risk to EPC customers. Distribution load transfers to alleviate potential transmission system overloads (which are in violation of the EPC Distribution System Performance Standard) will no longer be required. Alleviates immediate North 69 kv Subsystem capacity constraints during N-1-1 events and ensures compliance with the EPC Distribution System Performance Standard. Aligns with the EPC strategy for the North 69kV Subsystem. Lowest cost alternative. Disadvantages: Spare autotransformer at risk of requiring replacement due to age (42 years old). The spare autotransformer in Alternative 4 is a 42 year old unit, with 36 years in service. It was last rebuilt and rewound in As such, the unit is in serviceable condition, with minimal risk of failure. Alternative 4 is the preferred alternative as it provides a cost-effective solution to address the identified North 69 kv Subsystem deficiencies. 22

24 6.5 Alternative 5: Install New 36.5TR Autotransformer This alternative involves upgrading 36.5TR autotransformer to capacity of 75/100/112 MVA with a new transformer. This alternative will eliminate the need to reconfigure the North 69 kv Subsystem into a radial configuration, therefore mitigating the violation of the EPC Distribution System Performance Standard. Advantages: Radial configurations during maintenance activities, as outlined in Section 4.1, will no longer be required, thus reducing the reliability risk to EPC customers. Distribution load transfers to alleviate potential transmission system overloads (which are in violation of the EPC Distribution System Performance Standard) will no longer be required Alleviates immediate North 69 kv Subsystem capacity constraints during N-1-1 events and ensures compliance with the EPC Distribution System Performance Standard. Aligns with the EPC strategy for the North 69kV Subsystem. Disadvantages: Costlier than the preferred Alternative 4, as it requires a new autotransformer. Alternative 5 was dismissed due to higher cost than Alternative 4. This alternative would have the same impact on the North 69 kv Subsystem during an N-1-1 event, as alternative 4. 23

25 7 Capital Cost Estimates Alternative cost estimates were prepared in consultation with ENMAX TFO and discussed in further detail in the following sections. Alternative estimates are based on +/-30% accuracy and include IDC and AOH, except for Alternative 2 estimate which was limited to +/-50% accuracy due to not meeting the EPC Distribution System Performance Standard (refer to Section 4.1) and excessive costs relative to other alternatives. 7.1 Alternative 1: Do Nothing There were no capital cost estimates prepared for Alternative 1 as this option does not address the North 69 kv Subsystem deficiencies. 7.2 Alternative 2: Add Distribution System Capacity There is no estimate provided for this alternative as it does not meet the EPC Distribution System Performance Standard (refer to Section 4.1). 7.3 Alternative 3: Install Second Autotransformer (Spare) at No.21 Sub Project Details Capital Cost Estimate (+/- 30%) Transmission: Upgrade substation equipment at No.21 Substation with the addition of a second 75/100/112 MVA kv autotransformer using a spare unit and new bus-tie breakers on the 69 kv and 138 kv busses. $8.4M Distribution: $0 Total: $8.4M 7.4 Alternative 4: Upgrade 36.5TR (Spare) Project Details Transmission: Upgrade substation equipment at No.36 Substation with the replacement of existing 36.5TR with a 75/100/112 MVA kv autotransformer using a spare unit. Capital Cost Estimate (+/- 30%) $1.9M Distribution: $0 Total: $1.9M 24

26 7.5 Alternative 5: Install New 36.5TR Auto Project Details Transmission: Upgrade substation equipment at No.36 Substation with the replacement of existing 36.5TR with a new 75/100/112 MVA autotransformer. Capital Cost Estimate (+/- 30%) $3.9M Distribution: $0 Total: $3.9M 25

27 8 Proposed System Development Preferred Alternative 4 The preferred solution, Alternative 4, involves upgrading the existing 50 MVA, 69/138 kv autotransformer at No. 36 Substation (36.5TR) using a spare 75/100/112 MVA, 69/138 kv autotransformer. The existing No. 36 Substation configuration is shown in Figure 9 with the proposed development additions shown in Figure 10. This alternative will eliminate the need to reconfigure the North 69 kv Subsystem into a radial configuration, therefore mitigating the identified violation of the EPC Distribution System Performance Standard. The requested in service date for the proposed system development of the North 69 kv Subsystem upgrade is Q In the interim, EPC customers will be taking increased risk during planned and unplanned outages. The estimated capital cost of the proposed system development is $1.9M (+/- 30%), including IDC and AOH. 26

28 Figure 4: No.36 Substation Existing Configuration Legend Existing To 16 Sub 16.63L Bus Line Dist. Feeder Switch Motor. Disc. 69 kv 36.5TR 37.5/50 MVA Breaker Transformer To 7 Sub 7.84L To 14 Sub 14.83L 138 kv To Bearspaw 36.81L 36.2TR 18/24/30 MVA 22.5 MVA 36.1TR 20/27/33.6 MVA 36.3TR 30/40/50 MVA 25 kv To GIS 13.8 kv 13.8 kv Figure 5: Proposed No. 36 Substation Preferred Configuration (Alternative 4) Legend Proposed Existing To 16 Sub 16.63L Bus Line Dist. Feeder Switch Motor. Disc. 69 kv 36.5TR 75/100/112 MVA Breaker Transformer To 7 Sub 7.84L To 14 Sub 14.83L 138 kv To Bearspaw 36.81L 36.2TR 18/24/30 MVA 22.5 MVA 36.1TR 20/27/33.6 MVA 36.3TR 30/40/50 MVA 25 kv To GIS 13.8 kv 13.8 kv

29 9 Load-at-Risk Preferred Alternative 4 Implemented The preferred alternative eliminates the need to place more than two POD substations in a radial configuration and is therefore in compliance with the EPC Distribution System Performance Standard. As a result, an N-1-1 transmission contingency does not result in multiple POD substations losing supply. If the North 69 kv Subsystem substations do not lose supply, then there is also no load at risk, as the POD substations themselves remain in normal operating condition and are able to supply load with no customer disruption. Table 9: Distribution Load at Risk (MVA) Impacts During a 13.60L or 13.4TR Outage Sub Combined Loading Sub Total Tie Away (Adjacent Feeders outside of North 69 kv Subsystem) Sub Load at Risk Season* M M Not applicable as the DFO standard is met and the Load at Risk is mitigated M POD Combined Loading Sub Total Tie Away (Adjacent Feeders outside of North 69 kv Subsystem) Sub Load at Risk Season* M M Not applicable as the DFO standard is met and the Load at Risk is mitigated M * Maintenance (M) season is considered 75% of loading of North 69kV Subsystem summer coincident peak 10 In-Service Date The requested in service date for the upgrade of the existing autotransformer at No. 36 Substation is Q At the present time, there is no request for change to the current Demand Transmission Service (DTS) contract at No. 36 Substation. 28

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

North Oregon Coast Area Study. Adam Lint

North Oregon Coast Area Study. Adam Lint North Oregon Coast Area Study Adam Lint PAGE 2 North Oregon Coast System Overview - Clatsop Study Covers: Transmission Switching Stations (Clatsop District): Astoria Lewis and Clark 115 kv Distribution

More information

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Connection Engineering Study Report for AUC Application: AESO Project # 1674 APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test: Salisbury Substation 11kV Feeders DISCLAIMER The purpose of this document is to inform customers, Interested Parties,

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents APPENDIX A CONNECTION ASSESSMENT : FortisAlberta Inc. Plamondon 5S Capacity Increase Contents Executive Summary.... Introduction... 6. Project... 6.. Project Overview... 6.. Load Component... 6.. Generation

More information

Design Criteria Implementation for the Network Development Plan Hursthill Substation

Design Criteria Implementation for the Network Development Plan Hursthill Substation Design Criteria Implementation for the Network Development Plan Hursthill Substation Presenter : Riaan Swanepoel PRTechEng 1 Introduction The City of Johannesburg is embarking on a new spatial vision for

More information

Building a 21 st Century Electric Grid. February 23, 2018

Building a 21 st Century Electric Grid. February 23, 2018 Building a 21 st Century Electric Grid February 23, 2018 1 DTE strives to provide customers with a 21 st century electric grid that is safe, highly reliable, affordable and accessible 2 Our investment

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND

More information

The Energy Queensland Group Notice of no non-network options

The Energy Queensland Group Notice of no non-network options The Energy Queensland Group Notice of no non-network options 24 September 2018 MCE Mount Crosby East Establish new substation to replace Mount Crosby Substation (SSMTC) Page 1 of 1 DISCLAIMER While care

More information

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007 High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study ` Dunvegan Hydroelectric Project For Glacier Power Limited Preliminary Interconnection Study Prepared by Pung Toy, P. Eng. and Ata Rehman, P. Eng. September 24, 2004 Table of Contents Table of Contents...

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8 Header Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations RT 007-11 Balhannah and Uraidla - Final Draft Page 1 of 8 DISCLAIMER The purpose of this document is to inform customers,

More information

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN SPN High Value Project PO Route RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN Document History Version Date Details Originator V0.1 20/06/2013 Initial version Chris Winch V0.2

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

West Station-West Cañon 115 kv Transmission Project

West Station-West Cañon 115 kv Transmission Project West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Network. ENMAX Power Corporation Network Planning & Design November 4, 2011

Network. ENMAX Power Corporation Network Planning & Design November 4, 2011 Network ENMAX Power Corporation Network Planning & Design November 4, 2011 ENMAX Fast Facts Service area of 1,044 square kilometers 1,738MVA Peak load (2009) Transmission System 266 km overhead 15km underground

More information

Facilities Study for Alberta to US Available Transfer Capability

Facilities Study for Alberta to US Available Transfer Capability Facilities Study for Alberta to US Available Transfer Capability Report No: NPP2002-05 June 3, 2002 System Planning & Grid Operations, Transmission Line of Business Engineering Services Executive Summary

More information

Functional Specification Revision History

Functional Specification Revision History Functional Specification Revision History Revision Description of Revision Author Date B0 For comments Yale Zhou January 26, 2016 B1 Updated as per comments Yale Zhou February 1, 2016 Final issuance Yale

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

Maine Medical Center Campus-Wide Parking Study

Maine Medical Center Campus-Wide Parking Study Overview Maine Medical Center (MMC) retained VHB to conduct a campus-wide parking study that includes an analysis of demand and supply for patient, visitor, and employee parking on MMC s Bramhall Campus.

More information

Pump Station 7 Improvements

Pump Station 7 Improvements Project Business Case ID: C04 2/18/2017 Pump Station 7 Project Purpose: The purpose of this project is to ensure that Pump Station 7 continues to operate in an efficient and effective manner following

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design Presented at the 2018 Transmission and Substation Design and Operation Symposium Revision presented at the

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd 2016-20 Electricity Distribution Price Review Regulatory Proposal Revocation and substitution submission Attachment 7-14 Revised Flemington network development strategy

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

Diane Lindsey CenterPoint Energy SWEDE 2010

Diane Lindsey CenterPoint Energy SWEDE 2010 Diane Lindsey CenterPoint Energy SWEDE 2010 Agenda Background Pre Hurricane Ike Dredge Evaluation Aftermath of Hurricane Ike in 2008 Temporary West Galveston Mobile Substation Post Hurricane Ike Dredge

More information

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study XXXX Knob Hill Wind Farm Project Report No. August 2010 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All rights reserved.. DISCLAIMER OF WARRANTY, LIMITATION

More information

Emerald Reactive Support Alternative Solution Expressions of interest

Emerald Reactive Support Alternative Solution Expressions of interest Emerald Reactive Support Alternative Solution Expressions of interest Publishing Date 21/02/2017 Closing Date 21/03/2017 1. Executive Summary Ergon Energy Corporation Limited (EECL) is seeking expressions

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

Cost Benefit Analysis of Faster Transmission System Protection Systems

Cost Benefit Analysis of Faster Transmission System Protection Systems Cost Benefit Analysis of Faster Transmission System Protection Systems Presented at the 71st Annual Conference for Protective Engineers Brian Ehsani, Black & Veatch Jason Hulme, Black & Veatch Abstract

More information

Pike County Light & Power Company Summer Reliability Outlook

Pike County Light & Power Company Summer Reliability Outlook Pike County Light & Power Company 2013 Summer Reliability Outlook June 28, 2013 System Overview Pike County Light & Power Company ( PCL&P or the Company ) is an electric distribution company ( EDC ) which

More information

CRITICAL ISSUES DOWNTOWN CONTINGENCY PORTFOLIO

CRITICAL ISSUES DOWNTOWN CONTINGENCY PORTFOLIO EB-0-0 Tab Schedule Page of CRITICAL ISSUES DOWNTOWN CONTINGENCY PORTFOLIO THESL s DOWNTOWN CONTINGENCY WORK PROGRAM The purpose of this portfolio is to provide distribution load transfer capability from

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

2015 Grid of the Future Symposium

2015 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,

More information

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE RATES IN EFFECT AS OF APRIL 1, 2018 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description Page D100 Distribution Tariff Residential

More information

FOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT

FOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT FOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT Proposed 138kV Transmission Line Photo courtesy of The City of Calgary Project Overview The demand for power is increasing as Calgary continues

More information

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection

More information

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PSE&G System Characteristics New Jersey utility characterized by densely populated

More information

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE Rates in effect as of September 1, 2015 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description Page D100 Distribution Tariff

More information

FOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT

FOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT FOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT Proposed 138kV Transmission Line Photo courtesy of The City of Calgary Project Overview The demand for power is increasing as Calgary continues

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Local Transmission Plan. October 11, 2013 Revised August 25, 2014 Local Transmission Plan October 11, 2013 Revised August 25, 2014 2 Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated

More information

EVSE Load Balancing VS Load Shedding 1: Largest number of 30 Amps EVSEs that can be fed as per the code from the 600 volts feeder

EVSE Load Balancing VS Load Shedding 1: Largest number of 30 Amps EVSEs that can be fed as per the code from the 600 volts feeder EVSE Load Balancing VS Load Shedding 1: Largest number of 30 Amps EVSEs that can be fed as per the code from the 1600A @ 600 volts feeder The schematics shows that the 1600A feeder is split in 7 branches

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC OCTOBER 17, 2018 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent

More information

NPCC Natural Gas Disruption Risk Assessment Background. Summer 2017

NPCC Natural Gas Disruption Risk Assessment Background. Summer 2017 Background Reliance on natural gas to produce electricity in Northeast Power Coordinating Council (NPCC) Region has been increasing since 2000. The disruption of natural gas pipeline transportation capability

More information

EMERGING REQUIREMENTS

EMERGING REQUIREMENTS EB-00-0 Exhibit D Schedule Page of EMERGING REQUIREMENTS 0 EQUIPMENT STANDARDIZATION THESL plans, designs and constructs distribution system assets in accordance with approved standards. The standards

More information

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving

More information

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE Rates in effect as of January 1, 2018 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description Page D100 Distribution Tariff Residential

More information

Connection Engineering Study Report for AUC Application: EPCOR Clover Bar 25 kv Breaker Addition

Connection Engineering Study Report for AUC Application: EPCOR Clover Bar 25 kv Breaker Addition Connection Engineering Study Report for AUC Application: EPCOR Clover Bar 25 kv Breaker Addition Executive Summary Project Overview EPCOR Distribution & Transmission Inc. (EDTI), in its capacity as the

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Western Region ATSI Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map EH2741 Communication and Control in Electric Power Systems Lecture 3 Lars Nordström larsn@ics.kth.se 1 Course map 2 1 Outline 1. Repeating Power System Control 2. Power System Topologies Transmission Grids

More information

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection

More information

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta

More information

INCREASING electrical network interconnection is

INCREASING electrical network interconnection is Analysis and Quantification of the Benefits of Interconnected Distribution System Operation Steven M. Blair, Campbell D. Booth, Paul Turner, and Victoria Turnham Abstract In the UK, the Capacity to Customers

More information

III. Substation Bus Configurations & Substation Design Recommendations

III. Substation Bus Configurations & Substation Design Recommendations III. Substation Bus Configurations & Substation Design Recommendations 1.0 Introduction Pre-existing conditions, electrical arrangements or the criticality of the existing facility may limit this flexibility,

More information

New 115 kv Disconnect Switches at Bloomsburg MTS

New 115 kv Disconnect Switches at Bloomsburg MTS 115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Sub-Regional RTEP Committee PJM South

Sub-Regional RTEP Committee PJM South Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates

More information

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE Rates in effect as of July 1, 2011 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description Page D100 Distribution Tariff Residential

More information

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE Page 1 of 19 ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE RATES IN EFFECT AS OF JANUARY 1, 2017 Page 2 of 19 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description Page D100

More information

Surry Skiffes Creek Whealton Modeling and Alternatives Analysis Review

Surry Skiffes Creek Whealton Modeling and Alternatives Analysis Review Surry Skiffes Creek Whealton Modeling and Alternatives Analysis Review US Army Corps of Engineers Norfolk District Regulatory Office Received by: RLS Date: Feb 11, 2016 TOPICS Project Purpose, Need, Timeline

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd (Vic) Ltd 2016-20 Electricity Distribution Price Review Regulatory Proposal Revocation and substitution submission Attachment 7-11 WSP Parsons Brinckerhoff - Independent review of Sunbury development strategy

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.5 SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY DIVISION: Capital Programs & Construction BRIEF DESCRIPTION: Awarding San Francisco Municipal Transportation Agency

More information

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE Page 2 of 22 ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE RATES IN EFFECT AS OF APRIL 1, 2018 Page 2 of 22 Page 3 of 22 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description

More information

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION In re: Staff's Second Data Request on OUC' s Review of Electric Utility Hurricane Preparedness and Restoration Actions Docket No. 20170215-EU Filed: January

More information

High-Impedance Differential Applications With Mismatched CTs

High-Impedance Differential Applications With Mismatched CTs High-Impedance Differential Applications With Mismatched CTs Russ Franklin, Alliant Energy Hossein Nabi-Bidhendi, ABB Inc. Michael J. Thompson and Héctor J. Altuve, Schweitzer Engineering Laboratories,

More information

R.S.USHA CHIEF ENGINEER/ PLANNING & RC. Encl: Report and detailed estimate. To The Chief Engineer/D/Madurai Region

R.S.USHA CHIEF ENGINEER/ PLANNING & RC. Encl: Report and detailed estimate. To The Chief Engineer/D/Madurai Region TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION LTD ABSTRACT --------------------------------------------------------------------------------------------------------- Electricity - Madurai Region -

More information

2016 Load & Capacity Data Report

2016 Load & Capacity Data Report Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

Seabrook Substation Reliability Improvement Project

Seabrook Substation Reliability Improvement Project New England Division Seabrook Substation Reliability Improvement Project 1. Project Summary Description Seabrook Substation is critical to ISO-New England as a Pool Transmission Facility, to grid availability

More information

XXXX. Kokish River Hydroelectric Project. Interconnection System Impact Study

XXXX. Kokish River Hydroelectric Project. Interconnection System Impact Study XXXX Kokish River Hydroelectric Project Report No. August 2010 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All rights reserved.. DISCLAIMER OF WARRANTY,

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Generation Interconnection Facilities Study For

Generation Interconnection Facilities Study For Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...

More information