El Paso Electric Company

Size: px
Start display at page:

Download "El Paso Electric Company"

Transcription

1 Feasibility Study XXXXXX Solar Generation Prepared for El Paso Electric Company Prepared by TRC Engineers, LLC 249 Eastern Avenues Augusta, ME (207) Project Number: May 2013

2 FOREWORD This report was prepared for the project Interconnection Customer, by System Planning at El Paso Electric Company. Any correspondence concerning this document, including technical and commercial questions should be referred to: Dennis Malone Director System Planning Department El Paso Electric Company 100 North Stanton El Paso, Texas Phone: (915) Fax: (915) Or David Gutierrez Principal Engineer El Paso Electric Company 100 North Stanton El Paso, Texas Phone: (915) Fax: (915) Project i

3 Table of Contents EXECUTIVE SUMMARY INTRODUCTION PERFORMANCE CRITERIA STUDY METHODOLOGY ASSUMPTIONS PROCEDURE Development and Description of Cases XXXXXX Solar PV Generation Modeling Contingency List STEADY STATE POWER FLOW ANALYSIS PRE-PROJECT POWER FLOW EVALUATION Pre-Project N-0 Flow Violations Pre-Project N-1 Flow Violations POST-PROJECT POWER FLOW EVALUATION Post-Project N-0 Power Flow Analysis Post-Project N-1 Power Flow Analysis POWER FLOW ANALYSIS CONCLUSION STEADY STATE VOLTAGE ANALYSIS SHORT CIRCUIT ANALYSIS SHORT CIRCUIT ANALYSIS MODELING SHORT CIRCUIT ANALYSIS PROCEDURE SHORT CIRCUIT ANALYSIS RESULTS SHORT CIRCUIT ANALYSIS CONCLUSIONS DISTRIBUTION ANALYSIS GENERAL REQUIREMENTS IEEE Standards Noise and Harmonics VOLTAGE FLICKER ANALYSIS TRANSIENT STABILITY ANALYSIS Transient Stability Study Case Development Transient Stability Analysis Results Transient Stability Analysis Conclusion COST ESTIMATES GENERAL COST ASSUMPTIONS DISCLAIMER CONCLUSIONS Project ii

4 List of Figures Figure IEEE Flicker Curve List of Tables Table 0-1 Cost Estimate... 3 Table 3-1 Pre-Project 2014 N-1 Flow Violations... 9 Table N-1 Post-project Power Flow Analysis Results Table 5-1 Generator Short Circuit Modeling Data Table 5-2 Distribution Line Table XXXXXX Solar Generation Short Circuit Summary Results Table 6-1 Voltage Flicker at the POI Due to Project Table 6-2 Frequency of Voltage Flicker Due to PV Output Changes Table 6-3 Generator Models Used for Studies Table 6-4 Stability Post-Project Case Scenarios Table Stability Analysis Results for both Peak and Off-Peak Cases Appendices Appendix A Appendix B Appendix C XXXXXX Solar Feasibility Study Statement of Work Power Flow Contingency List Stability Plots Project iii

5 EXECUTIVE SUMMARY The objective of this Feasibility Study (Study) was to determine the impact that the proposed XXXXXX Solar generation (the Project) for 10 MW (net output) of Photovoltaic (PV) generation, interconnecting to the 13.8 kv bus of the future Patriot 115/13.8 kv substation, would have on the El Paso Electric Company (EPE) and Southern New Mexico transmission systems, as well as the EPE future Patriot Substation distribution system. The requested Commercial Operation date for this project is July 15, Three (3) interconnection projects in the EPE study queue that have signed Interconnection Agreements (IA) with EPE were included in this Study. The three (3) interconnection projects included in this SIS are: 1. Montana Power Station: 420 MW gas fired combustion turbine project with varying inservice dates located 2 miles east of the Caliente 345/115 kv substation. 2. DS92S: 92 MW solar powered project interconnected to the Diablo-Santa Teresa 115 kv line, 5.7 miles from Diablo 115 kv station. 3. AA100W: 100 MW wind powered project interconnected to the Amrad-Artesia 345 kv line, 65 miles east of Amrad 345 kv substation. The generation from the DS92S project was modeled as delivered to all entities in the Western Electricity Coordinating Council (WECC) except EPE, while the generation from the AA100W was modeled to deliver to all WECC entities except EPE and New Mexico. The Montana Power Station project was modeled as delivered to local EPE network load. The Study Area was limited to the WECC Area 11 - EPE (TX) and Area 10 - PNM (NM). Steady State Transmission Results The power flow analysis was conducted using 2014 peak and off peak load conditions. The off peak load conditions were modeled as fifty percent (50%) of the peak load. The Arroyo Phase Shifter was modeled as being out of service in both peak and off peak cases. The power flow analysis results showed that the addition of the 10 MW of Project generation would not require any network upgrades to the EPE and Southern New Mexico transmission systems, as modeled in the 2014 peak and off peak load flow cases. The 10 MW of Project generation will be used primarily to feed the load (9.8 MW under 2014 Peak conditions) at the future 13.8 kv Patriot bus, therefore there will be very little export to the 115 kv EPE transmission system in the area. The analysis showed that the XXXXXX Solar generation does not have an adverse impact on the EPE and Southern New Mexico transmission systems. Project

6 Short Circuit Results A short circuit analysis was performed to determine if the addition of the XXXXXX Solar generation to the EPE transmission system would cause any of the existing substation circuit breakers on EPE s transmission system to exceed their interrupting capability ratings. The results of this short circuit study showed that the maximum fault currents with the XXXXXX Solar project in service did not exceed any of the breaker interrupting capabilities on the EPE transmission system. Distribution Results Several analyses were performed to determine if the addition of the XXXXXX Solar generation would have any adverse effects on El Paso s underlining distribution system in the immediate Study Area. These analyses included a closer look at the requirements necessary to interconnect and model PV generation under IEEE standards, the impact of changes in sun exposure at the solar farm, and a transient stability analysis on the distribution system in the immediate Project Area. The analysis showed that the XXXXXX Solar generation does not have an adverse impact on the immediate EPE distribution system in the project area. Cost Estimates Good faith cost estimates are presented. The cost estimates are in 2013 dollars (no escalation applied) and are based upon typical construction costs in the area. These costs include all estimated applicable labor and overheads associated with the engineering, design, and construction of any new EPE facilities. These estimates did not include the Generator Interconnection Costs 1 for any other Interconnection Customer owned equipment or associated design and engineering except for the Point of Interconnection (POI) facilities. The estimated total cost for the required upgrades is $635,000. This breaks down to $635,000 for the EPE Interconnection Costs 2 and $0 for Network Upgrades Cost 3. Generator Interconnection Costs have not been estimated as part of this study. Table 0-1 details the cost per facility. 1 Generator Interconnection Costs: cost of facilities paid for by Interconnection Customer and owned and operated by the Interconnection Customer from the generator facilities to the Change of Ownership Point, which is typically on the first dead-end at the Point of Interconnection substation. Not subject to transmission credits. 2 EPE Interconnection Costs: cost of facilities paid for by Interconnection Customer but owned and operated by EPE from the Change of Ownership Point to the Point of Interconnection. Not subject to transmission credits. 3 Network Upgrades Cost: Cost of facilities from the Point of Interconnection outward, paid for by the interconnector but owned and operated by EPE. Subject to transmission credits. Project

7 Table 0-1 Cost Estimate Facility Patriot 13.8 kv Station Construction (Including: Voltage Regulators; Switchgear Expansion; Breakers; and Labor) Construction of a 1.5 mile 13.8 kv line connecting the Project to the future Patriot 13.8 kv Bus Distribution: Metering, Switches; Protective Equipment Underground Getaway and Material Generator Interconnection Cost EPE Interconnection Cost Network Upgrade Cost Total N/A $230,000 N/A $230,000 N/A $290,000 N/A $290,000 N/A $85,000 N/A $85,000 N/A $30,000 N/A $30,000 TOTAL N/A $635,000 $0 $635,000 The estimated time frame for Engineering, Procurement, and Construction of Network Upgrades is approximately 12 months upon notice to proceed with construction from the Interconnection Customers. Project

8 Figure 0-1 Below details the interconnection. Figure 0-1: XXXXXX Solar POI and Future Patriot 13.8 Substation One-line Unit 1 10 MW PV Patriot Solar PV Generating Site Change of Ownership 0.69 kv 13.8 kv 13.8/0.69 kv Wye-Grounded/Wye-Grounded 10 MVA Transformer (Six 1.5 MVA and One 1 MVA) Disconnect Switch Revenue Metering M 13.8 kv 1.5 Mile Express Line EPE Load 13.8 kv Point of Interconnection To Cromo Color Code Network Upgrades Existing Facilities 115 kv To Newman Patriot Substation EPE Interconnection Facilities Interconnection Customer Equipment Conclusion This Feasibility Study showed that the proposed XXXXXX Solar generation will not have an adverse impact on the EPE and Southern New Mexico transmission systems or the EPE Patriot distribution system. Project

9 1.0 INTRODUCTION The Interconnection Customer proposed the interconnection of 10 MW of solar PV generation to the 13.8 kv bus of EPE s future Patriot 115/13.8 kv substation. The FERC Open Access Transmission Tariff (OATT), under the Small Generator Interconnection Procedures (SGIP), requires that a Feasibility Study be performed for Interconnection Customers who desire to interconnect their generation facilities to a Transmission Provider s transmission system. The proposed Commercial Operation date for the XXXXXX Solar project is July 15, Performance Criteria The Study was performed according to Western Electricity Coordinating Council (WECC), North American Electric Reliability Corporation (NERC), and EPE standards. The EPE local reliability standards can be found in Section 4 of EPE s FERC Form No The steady state analysis was performed using the GE PSLF Version 18 software. Transformer tap and phase-shifting transformer angle movement, as well as static VAR device switching were allowed to move for the steady state pre-contingency analysis. All regulating equipment such as transformer controls and switched shunts were fixed at pre-contingency positions when the contingency analysis was performed. All facility loadings, as well as bus voltages 69 kv and greater, were monitored within the El Paso, New Mexico and Arizona control areas. Pre-contingency flows on lines and transformers were required to remain at or below the normal rating, while post-contingency flows on lines and transformers were required to remain at or below the emergency rating. Flows above 100% of an element s rating, either pre- or post-contingency, were considered violations. Post-project voltage criteria violations that did not exacerbate or improve an existing pre-project violation were not considered an adverse impact to the system. The performance criteria utilized in identifying violations in the study area are shown in Table 1. Project

10 Table 1-1 EPE and New Mexico Performance Criteria Area Conditions Loading Limits EPEC PNM Tri- State Normal (ALIS) Contingency Normal (ALIS) Contingency N-1 Contingency N-2 Normal ALIS Contingency N-1 Contingency N-2 Normal Rating Emergency Rating Voltage (p.u.) Voltage Drop Application kv and above Artesia 345 kv Arroyo 345 kv PST source side Alamo, Sierra Blanca and Van Horn 69 kv % 60 kv to 115 kv % Artesia 345 kv % Arroyo 345 kv PST source side Alamo, Sierra Blanca and Van Horn 69 kv % Hidalgo, Luna, or other 345 kv buses Normal Rating kv and above* Emergency Rating Emergency Rating *** 6 %** 46 kv to 115 kv *** 6 %** 230 kv and above *** 10 % 46 kv and above* Normal Rating All buses Emergency Rating Emergency Rating % % % * Taiban Mesa and Guadalupe 345 kv bus voltage must be between 0.95 and 1.10 p.u. under normal and contingency conditions. ** For PNM buses in southern New Mexico, the allowable N-1 voltage drop is 7%. *** Provided operator action can be utilized to adjust voltages back down to 1.05 Tri-State buses in the PNM Service Area (list provided by Tri-State) Tri-State buses in southern and northeastern New Mexico (list provided by Tri-State) All buses Project

11 2.0 STUDY METHODOLOGY 2.1 Assumptions The following assumptions are consistent for all study scenarios unless otherwise noted. This study assumed that all system expansion projects as planned by area utilities by the year under analysis are completed, and that any system improvements required by the interconnections senior to the Project generation are implemented. This study did not analyze any transmission service from the interconnection point to any specific point on the grid for the interconnections senior to the Project generation. 2.2 Procedure The Study included only Steady State Analysis as stated in Section 6.0 of the EPE Small Generator Interconnection Procedures Feasibility Study Agreement. A description of the procedures used to complete the analyses is presented below Development and Description of Cases A 2014 WECC power flow case at 100% summer peak load was used and modified, as listed below, to establish a 2014 benchmark case without the proposed XXXXXX Solar generation. The 10 MW XXXXXX Solar generation was modeled as being dispatched to serve EPE system native load. The Arroyo Phase Shifter was modeled out of service as it is not planned to be completed until after the 2014 study year. The off-peak case was created by reducing the WECC Area 11 (EPE) and Area 10 (PNM, TSGT) loads and generation by 50% and adjusting area interchange Benchmark 2014 Cases: The 2014 benchmark, peak and off-peak cases included the following existing third party generation: (a) 420 MW of generation (Montana Power Station) with varying in-service dates interconnected to the Caliente 115 kv bus and scheduled to EPE native load. (b) 92 MW of generation (DS92S) interconnected on the Diablo-Santa Teresa 115 kv line, 5.7 miles from Diablo 115 kv station and scheduled to all WECC except EPE. (c) 100 MW of generation (AA100W) interconnected on the Amrad-Artesia 345 kv, 65 miles east of Amrad 345 kv substation and scheduled to all WECC entities except EPE and New Mexico. (d) Peak and off-peak 2014 post-project cases were created from the benchmark cases as described above. Project

12 2.2.2 XXXXXX Solar PV Generation Modeling The XXXXXX Solar generation consisting of 10 MW from a yet unknown number of PV inverters, was modeled as being interconnected at a new XXXXXX Solar 13.8 kv bus (POI) via a 1.5 mile express feeder from the Patriot 13.8 kv Substation bus. The 10 MW of solar PV generation was modeled as a single 10 MW unit at 0.69 kv, stepped up to 13.8 kv at the Solar Farm (POI). The generator step-up (GSU) transformers (0.69 kv/13.8 kv) information provided (6 GSUs at 1.5 MVA and 1 GSU at 1.0 MVA are mentioned in the interconnection application) calls for an aggregate of 10 MVA normal and emergency ratings to be used. Provided that the planned Project generation operates at 10 MW, these individual GSUs will be overloaded if the Project is at maximum output and providing the required +/-0.95 Power Factor (PF) of VAR support to EPE system. EPE directed that this study was to be performed assuming a Unity PF for the Project generation. The Project output and GSU specification should be confirmed before this Project proceeds. If the EPE required +/-0.95 PF is adhered to, the individual GSU s will overload. Furthermore, the interconnection application also states that these GSU s will be Wye-Delta (low to high) configurations. This configuration will need to be changed, such that the interconnecting high side is a grounded Wye Contingency List All outages (69 kv and above within EPE) were modeled in the subsystem files. The list of contingencies used in this study is included in Appendix B. These contingencies were selected to represent a good cross section of potential contingencies that would stress the EPE and PNM s southern New Mexico systems. This study was only performed for N-0 and N-1 conditions. Project

13 3.0 STEADY STATE POWER FLOW ANALYSIS 3.1 Pre-Project Power Flow Evaluation Peak and off peak base cases were evaluated for overloaded facilities under both normal and contingency conditions prior to the addition of the XXXXXX Solar generation Pre-Project N-0 Flow Violations Power flow study analysis results showed no transmission facilities were overloaded in the EPE, PNM, or Tri-State (TSGT) areas under pre-contingency system conditions prior to the addition of the XXXXXX Solar generation Pre-Project N-1 Flow Violations Power flow contingency analysis results showed that few overloads existed in El Paso prior to the addition of the Patriot generation, as shown in Table 3-1. Table 3-1 Pre-Project 2014 N-1 Flow Violations From Bus kv To Bus kv Ckt ID DONA_ANA (*) Area Rating (MVA) 115 PICACHO JORNADA 115 ARROYO JORNADA 115 ARROYO (*) Denotes that this line is owned by Tri-State. Contingency LUNA-MIMBRES 115 kv LE1-JORNADA 115 kv LE1-ARROYO 115 kv Off Peak Peak % of Emergency Rating Post-Project Power Flow Evaluation The inclusion of the XXXXXX Solar generation showed no adverse effects to the El Paso and New Mexico areas. The post-project analysis was performed under both normal and contingency conditions Post-Project N-0 Power Flow Analysis Power flow study results for the EPE and PNM areas showed that the addition of the XXXXXX Solar generation to the existing system would not cause any power flow violations under non-contingency system conditions Post-Project N-1 Power Flow Analysis Power flow study results for the EPE and PNM areas showed that the addition the XXXXXX Solar generation to the existing system would not have an adverse impact on the El Paso and New Mexico transmission systems, as shown in 3-2. Project

14 Table N-1 Post-project Power Flow Analysis Results Peak or Off-peak From Bus kv To Bus kv Ckt ID Area Rating (MVA) Contingency Without Project % of Rating With Project % of Rating Delta % of Rating Peak JORNADA 115 ARROYO LE1-JORNADA 115 kv Peak DONA_ANA 115 PICACHO LUNA-MIMBRES 115 kv Off-peak JORNADA 115 ARROYO LE1-JORNADA 115 kv Off-peak JORNADA 115 ARROYO LE1-ARROYO 115 kv Project

15 3.3 Power Flow Analysis Conclusion The analysis showed that the addition of the XXXXXX Solar generation to the system would not have an adverse impact on the EPE or New Mexico transmission systems. For the peak load case, the 9.8 MW load as modeled at the 13.8 kv Patriot Bus keeps the 10 MW of Project generation local to the 13.8 kv distribution system without flowing onto the 115 kv transmission system in the area. Depending upon the protection scheme at the Patriot Substation, this may create a possibility of islanding for loss of the 13.8/115 kv transformer. For the off-peak case, EPE should expect back flow on to the 115 kv system from the Project. Project

16 4.0 STEADY STATE VOLTAGE ANALYSIS Bus voltages within the Study Area were compared under both normal and contingency conditions, with and without the XXXXXX Solar generation in service. The Performance Criterion shown in Table 1 was considered when analyzing bus voltages for violations. The voltage analysis results showed that after the addition of the XXXXXX Solar generation, the Study area transmission network voltages stayed within criteria limits or did not significantly change from the pre-project voltage levels. See Appendix C for detailed results. Project

17 5.0 SHORT CIRCUIT ANALYSIS A short circuit analysis was performed to determine if the addition of the XXXXXX Solar generation to the EPE transmission system would cause any of the existing substation circuit breakers on EPE s transmission system to exceed their interrupting capability ratings. 5.1 Short Circuit Analysis Modeling Pre and post-project cases were developed to perform this analysis showing the impact of the integration of the XXXXXX Solar generation on the circuit breakers in the EPE transmission system. As mentioned in earlier sections, any planned or proposed third party generation listed in EPE s study queue ahead of the Project were also modeled in the two cases. The generator data used in the study is shown in Table 5-1 and the impedance data used for the 1.5 mile distribution line is shown in Table 5-2. This analysis evaluated the impact of the XXXXXX Solar generation by comparing the pre- and post- XXXXXX Solar generation fault current levels. Project

18 Table 5-1 Generator Short Circuit Modeling Data Project Total Output (MW) AA100W 100 DS92S 92 XXXXXX Solar Generation Unit ID Pmax (MW) Interconnection Customer Qmax (MVAR) Qmin (MVAR) Z subtransient (p.u) Rating (MVA) GSU Voltage (kv) Z Subtransient (p.u) P j / j P j G j / j0.085 G j / j G *0.00 +j / j0.133 * - Denotes that subtransient impedance values were not available, so default values found in ASPEN were used. Table 5-2 Distribution Line From Bus To Bus kv Ckt. ID Length (mi.) Line Impedance (p.u) R1 X1 R0 X0 XXXXXX Solar Patriot Project

19 5.2 Short Circuit Analysis Procedure The initial short circuit analysis was performed with all other third-party generation projects ahead of the XXXXXX Solar generation in the study queue in service and XXXXXX Solar generation out of service. This identified the base case fault duties of the circuit breakers. The short circuit analysis was performed again with XXXXXX Solar generation in service on the 2014 ASPEN One Liner case provided by EPE. Three phase, two phase, and single-phase line-to-ground faults were simulated at selected buses in the EPE system with terminal voltages at 69 kv and above. EPE also requested faults on all transformer tertiary buses. ASPEN One Liner and Batch Short Circuit Module were used to perform the short circuit analysis. The short circuit fault analyses were performed with the following settings: Transmission line G+jB ignored. Shunts with positive sequence impedance ignored. Transformer line shunts ignored The pre-fault voltage was calculated using a Flat bus voltage of 1.05 per unit. The difference between the fault current values in the two cases demonstrates the post-project fault contribution of the XXXXXX Solar generation to the pre-project fault current levels in the EPE system. The resulting fault currents in the post-project scenario were compared to the lowest breaker interruption ratings at each of the substations to determine whether or not the XXXXXX Solar project caused any adverse impact. Project

20 5.3 Short Circuit Analysis Results The results of this short circuit study showed that the existing maximum fault currents (without the XXXXXX Solar generation in service) exceeded the breaker interrupting capability at some substations. These are existing criteria violations that EPE is currently addressing, and will not be discussed in this report. The short circuit analysis results for the monitored buses in the immediate EPE Project area (2 busses away) are shown below in Table 5-3 below. Table XXXXXX Solar Generation Short Circuit Summary Results Lowest Pre Post Breaker Bus Fault On: Fault Current Pre X/R Current Rating (ka) (ka) (ka) CROMO 115kV 40 NEWMAN 115kV 50 PATRIOT 13.8kV PATRIOT 115kV XXXXXX SOLAR 13.8kV TBD TBD TBD Post X/R Delta (Amps) 3LG LG LG LG LG LG LG LG LG LG LG LG LG LG LG Short Circuit Analysis Conclusions The results of this short circuit study showed that the post-project fault currents with the XXXXXX Solar generation on-line increases fault levels at the existing Patriot 13.8 kv bus by approximately 1.9 ka, but does not cause fault currents to exceed the breaker interrupting capability of any breakers in the EPE transmission system. Therefore, the project generation does have an adverse impact to the EPE transmission breaker duties. EPE Substation and Protection Engineering verified the minimal breaker ratings at all the sites listed in the table. Project

21 6.0 DISTRIBUTION ANALYSIS Several analyses were performed to determine if the addition of the XXXXXX Solar generation would have any adverse effects on El Paso s distribution system fed out of the Patriot Substation in the immediate Project Area. These analyses included a closer look at the requirements necessary to interconnect and model PV generation under IEEE standards, the impact of changes in sun exposure at the solar farm, and a low level transient stability analysis on the immediate Project Area. 6.1 General Requirements IEEE Standards The Interconnection Request did not specify the model of PV inverters that will be used for this Project. However, in order for the Project to move forward to the Facilities Study phase of the Interconnection process, the PV inverters to be used will need to be specified and adhered to the following IEEE standards and guidelines: IEEE Standard , IEEE Standard for Interconnecting Distributed Resources with Electric Power Systems. UL Standard 1741, Inverters, Converters and Charge Controllers for Use in Independent Power Systems. IEEE Standard , IEEE Recommended Practice for Utility Interface of Photovoltaic (PV) Systems Noise and Harmonics The inverter is certified IEEE 1547, compliant and the Total Harmonic Distortion (THD) is given at less than 3.0%. 6.2 Voltage Flicker Analysis Voltage flicker is defined as a voltage variation sufficient in duration to allow visual observation of a change in electric light intensity of an incandescent light bulb. The IEEE curve showing fluctuations per time period versus borderline of visibility and borderline of irritation is shown below. The suggested operating criteria is that the magnitude of voltage flicker must be limited to less than 3% and that the frequency of flicker fluctuations be less than the border line of irritation boundary. Project

22 Figure 6-1 IEEE Flicker Curve Clouds shading the PV panels adversely impact the output of a PV system. As a cloud shadow passes over a PV system the output will decrease due to the reduction in sunlight. The change in PV system output on a distribution circuit may cause a fluctuation of voltage that might be seen by electric customers. This fluctuation would be classified as a voltage flicker. A rapid change in load cannot be compensated by the voltage regulation equipment installed on a distribution system. Most utilities use a typical time delay setting of 60 seconds for substation LTCs and 90 seconds for line voltage regulators. This time delay means that an LTC or voltage regulator will not respond to voltage changes until the voltage has been outside of the bandwidth for a low of 60 or 90 seconds. This helps to control hunting of the multiple devices trying to control the voltage. As a cloud passes over a PV system the output will decrease to a lower value. Given the amount of PV system output reduction due to clouds is not known, the assumption is that it goes to zero and returns to full output once sunlight returns. The voltage at the Patriot 13.8 kv Substation bus is anticipated to be fixed at 1.05 p.u. with and without the Project for peak and off peak load periods. Table 6-1 summarizes the balanced voltage and the calculated voltage flicker magnitude. Project output will exhibit relatively slow variations due to cloud cover shading rather than spike between full on and off. Consequently, the results shown in Table 6-1 represent a worst-case scenario, such as a sudden shutdown of the PV plant. Project

23 Table 6-1 Voltage Flicker at the POI Due to Project Project POI Bus Voltage Case Off Peak Load Peak Load Without Project kv kv With Project* kv kv % Voltage Flicker NOTE: % Voltage Flicker calculated as With Project minus Without Project divided by Without Project times 100. *The Project is set to operate at Unity power factor. Table 6-2 is based on an interpolation of the flicker frequency from the IEEE flicker graph. Cloud movement is slow; therefore the frequency of the voltage fluctuations will be less than the frequency limits shown in Table 6-2. The calculated magnitude of the flicker due to the Project is much less than the 3% limit criterion. The distribution voltage flicker resulting from changes in the Project output is not anticipated to have an adverse effect. Table 6-2 Frequency of Voltage Flicker Due to PV Output Changes % Voltage Flicker Based on GE Flicker Curve Border Line of Visibility Border Line of Irritation < 1/sec < 1/sec < 1/sec < 1/sec NOTE: Fluctuation per time period extrapolated from the IEEE flicker graph 6.3 Transient Stability Analysis EPE requested TRC to take a closer look at the impacts of the Project on their Distribution System in the Project area. In order to ensure the damping effects of the EPE system in the area, a Transient Stability Analysis was completed. The simulations were conducted using the General Electric, Inc. PSLF load flow and dynamic simulation software package, Version 18. Dynamic stability simulations were conducted for peak and off-peak load conditions with the XXXXXX Solar generation units on at full capacity and off. EPE provided the base cases and dynamic file data for this part of the study. The Interconnection Customer did not provide any data for modeling of their facility. As a result, typical modeling data for solar facilities was used as per WECC modeling standards. The XXXXXX Solar generation was modeled as one PV plant with a maximum output of 10 MW. Project

24 Table 6 shows the models used for the studies. Table 6-3 Generator Models Used for Studies Project Turbine Type Notes PSLF Model XXXXXX Solar Unknown Used Typical Type 4 Wind Turbines for model data and parameters as per WECC Standards WT4G, WT4E Transient Stability Study Case Development Two base cases were used to simulate Peak and Off-Peak conditions. The analysis compared the system response to the fault simulations before and after the XXXXXX Solar generation was added. The dynamic study cases are listed in 6-4. Table 6-4 Stability Post-Project Case Scenarios Descriptions Year Heavy Load Case Light Load or Off-Peak Case 2014 Senior Queued Projects in-service Arroyo PST out of service Afton in service Transient Stability Analysis Results Senior Queued Projects in-service Arroyo PST out of service Afton out of service The stability analysis showed that the EPE Patriot distribution system and the EPE transmission system remained stable for all simulated faults before and after the addition of the Project. Simulated fault locations, time durations, and the system response are shown in 6-5. The stability plots for these faults can be found in Appendix D Transient Stability Analysis Conclusion The study area remains stable and well damped for all the contingencies analyzed. The Project addition to the system does not pose any concern to system stability performance. Project

25 Table Stability Analysis Results for both Peak and Off-Peak Cases 2014 Results # Fault Location Event Description Clearing (cycles) Off Peak Load Project Off Project On Project Off Peak Load 1 XXXXXX 115kV Three Phase fault at XXXXXX 115 kv XXXXXX 115 kv= 6.0, Open bus. XXXXXX-Patriot 115kV Line Stable Stable Stable Stable 2 Patriot 115 kv Three Phase fault at Patriot 115 kv bus. Patriot 115 kv= 6.0 Stable Stable Stable Stable 3 Patriot 13.8 kv Three Phase fault at Patriot 13.8 kv bus. Patriot 13.8 kv= 6.0 Stable Stable Stable Stable Project On Project

26 7.0 COST ESTIMATES Good faith cost estimates have been determined. The cost estimates are in 2013 dollars (no escalation applied) and are based upon typical construction costs in the area for previously performed similar construction. These estimated costs include all applicable labor and overheads associated with the engineering, design, and construction of these new facilities. These estimates did not include the cost for any other Interconnection Customer owned equipment or associated design and engineering except for those located at the POI. The estimated total cost for the required upgrades is $635,000. This breaks down to $635,000 for the EPE Interconnection Cost 4 and $0 for Network Upgrades Cost 5. The Generator Interconnection Cost 6 estimates are not included. 7.1 General Cost Assumptions 1. The cost estimates provided are good faith scoping estimates. 2. Estimates do not include land or permitting. 3. Interconnection Customer to secure POI site and transfer ownership to EPE. 4. Permitting time frames are included. Actual time frames will vary due to local and Federal requirements. 5. Estimates are in 2013 U.S. dollars. 6. Where applicable, the Interconnection Customers are responsible for funding and construction of all transmission facilities from the proposed generator substation to the Points of Interconnection including disconnect switches, use and reset existing relays, and reset relays at remote ends. 7. Interconnection Customer is responsible for Engineering, Procurement, and Construction for all and any FACTs and other transmission and distribution compensation devices at their generation site or along their long interconnecting transmission or distribution lines to just outside the POI sites EPE Interconnection Cost: Cost of facilities paid for by interconnector but owned and operated by EPE from the Change of Ownership Point to the Point of Interconnection. Not subject to transmission credits. Network Upgrades Cost: Cost of facilities from the Point of Interconnection outward, paid for by the interconnector but owned and operated by EPE. Subject to transmission credits. Generator Interconnection Cost: Cost of facilities paid for by interconnector and owned and operated by the interconnector from the generator faculties to the Change of Ownership Point, which is typically at the Point of Interconnection substation first dead-end. Not subject to transmission credits. Project

27 8.0 DISCLAIMER If any of the project data provided by Interconnection Customer and used in this study varies significantly from the actual data after the XXXXXX Solar generation equipment is installed, the results from this study will need to be verified with the actual data at the Project Interconnection Customer's expense. Additionally, any change in the generation in EPE s Interconnection Queue that is senior to the XXXXXX Solar generation may require a re-evaluation of this Study. Project

28 9.0 CONCLUSIONS This XXXXXX Solar Feasibility Study, consisting of a Steady State, Short Circuit, Transient Stability and Voltage Flicker Analysis, for a net 10 MW of generation interconnecting to the EPE transmission and distribution systems has demonstrated that the XXXXXX Solar generation will NOT have an adverse impact on the EPE and Southern New Mexico transmission systems or the EPE distribution system. The estimated cost for integrating the XXXXXX Solar generation onto the EPE and Southern New Mexico transmission systems is $635,000. The good faith estimate of the time frame to Engineer, Procure, and Construct all facilities is 12 months. Project

29 APPENDIX A XXXXXX Solar Feasibility Study Statement of Work Project Appendix A

30 APPENDIX B Power Flow Contingency List Project Appendix B

31 APPENDIX C Stability Plots Project Appendix C

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ART320W 320 MW Wind Powered Project Prepared for: El Paso Electric Company Prepared by: TRC Engineers, LLC 249 Western Avenue Augusta, ME 04330

More information

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report

More information

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION El Paso Electric Company System Operations Department System Planning Section August 2006 I. INTRODUCTION The

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS El Paso Electric Company System Operations Department System Planning

More information

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study System Operations Department System Planning Section March 2002 Table of Contents: 1.0 EXECUTIVE SUMMARY 4 2.0 COST ESTIMATES 8 2.1 Cost

More information

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY Short Circuit Analysis System Operations Department System Planning Section March 2001 I. Introduction XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

More information

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS System Operations Department System Planning Section June 2001 TABLE OF CONTENTS 1.0 Executive Summary...Page

More information

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS El Paso Electric Company System Operations Department System Planning Section September 2001 Short Circuit

More information

Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study

Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study Study Performed by El Paso Electric Company System Planning Section - 1 I.

More information

XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS El Paso Electric Company System Operations Department System Planning Section September 2001 TABLE

More information

300 MW SOLAR PHOTOVOLTAIC PLANT, GENERATOR INTERCONNECTION FEASIBILITY STUDY

300 MW SOLAR PHOTOVOLTAIC PLANT, GENERATOR INTERCONNECTION FEASIBILITY STUDY 300 MW SOLAR PHOTOVOLTAIC PLANT, GENERATOR INTERCONNECTION FEASIBILITY STUDY El Paso Electric Company System Planning August 2006 TABLE OF CONTENTS 1.0 EXECUTIVE SUMMARY...Page 1 2.0 PURPOSE...Page 7 3.0

More information

XXXXXXXXXXXXXX 99 MW WIND PARK GENERATOR INTERCONNECTION FEASIBILITY STUDY. September 2008 Prepared by: EL PASO ELECTRIC COMPANY

XXXXXXXXXXXXXX 99 MW WIND PARK GENERATOR INTERCONNECTION FEASIBILITY STUDY. September 2008 Prepared by: EL PASO ELECTRIC COMPANY XXXXXXXXXXXXXX 99 MW WIND PARK GENERATOR INTERCONNECTION FEASIBILITY STUDY September 2008 Prepared by: EL PASO ELECTRIC COMPANY Foreword This report was prepared for XXXXXXXXXXXXX (XXX) of XXXXXXXX by

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

120 MW SOLAR-THERMAL PLANT GENERATOR INTERCONNECTION FEASIBILITY STUDY. May 2008 Prepared by: EL PASO ELECTRIC COMPANY

120 MW SOLAR-THERMAL PLANT GENERATOR INTERCONNECTION FEASIBILITY STUDY. May 2008 Prepared by: EL PASO ELECTRIC COMPANY . 120 MW SOLAR-THERMAL PLANT GENERATOR INTERCONNECTION May 2008 Prepared by: EL PASO ELECTRIC COMPANY Foreword This report was prepared for XXXXXXXXXXXXXXXXXXX by System Planning at El Paso Electric Company.

More information

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study

ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study Final Report ABB Power Systems Consulting June 27, 2016 LEGAL NOTICE This document, prepared by ABB Inc, is an

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Interconnection System Impact Study Final Report February 19, 2018

Interconnection System Impact Study Final Report February 19, 2018 Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen

More information

Verde Transmission, LLC. Verde Project. System Impact Study Report

Verde Transmission, LLC. Verde Project. System Impact Study Report Verde Transmission, LLC Verde Project System Impact Study Report March 2017 Prepared by: Public Service Company of New Mexico Foreword This report was prepared for Verde Transmission, LLC by the PNM Transmission/

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007 High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning. A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final

More information

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018 March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM-2017-11 May 2018 Prepared by: Public Service Company of New Mexico Foreword This report is prepared

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Small Generator Interconnection Program Interconnection Technical Requirements

Small Generator Interconnection Program Interconnection Technical Requirements General Program Information What is the purpose of the PGE Small Generator Interconnection Program? How do I initiate a distribution interconnection request for my project? The purpose of our Small Generator

More information

Project #94. Generation Interconnection System Impact Study Report Revision

Project #94. Generation Interconnection System Impact Study Report Revision Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

Midway/Monument Area TTC Study

Midway/Monument Area TTC Study Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny

More information

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems Ben Huckaba, P.E. President & Principal Engineer 317-273-9841 benh@alphaeng.us Indiana University Bloomington,

More information

Georgia Transmission Corporation Georgia Systems Operations Corporation

Georgia Transmission Corporation Georgia Systems Operations Corporation Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia

More information

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Interconnection Feasibility Study Report GIP-369-FEAS-R1 Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 1 Reactive Power Compensation for Solar Power Plants Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 2 Objectives Refresh the basics of reactive power from a generator s perspective Regulatory

More information

Generation Interconnection Facilities Study For

Generation Interconnection Facilities Study For Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

Cargill Power Markets LLC Transmission Service Study (OASIS # TSR and )

Cargill Power Markets LLC Transmission Service Study (OASIS # TSR and ) Cargill Power Markets LLC Transmission Service Study (OASIS # TSR 72608299 and 72827161) Prepared by: Electric Power Research Institute (EPRI) Under contract with: Public Service Company of New Mexico

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

Q217 Generator Interconnection Project

Q217 Generator Interconnection Project Q217 Generator Interconnection System Impact Study APS Contract No. 52588 By Arizona Public Service Company Transmission Planning November 25, 2013 Version 2.0 Prepared by Utility System Efficiencies,

More information

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection

More information

PUD ELECTRIC SYSTEM INTERCONNECTION

PUD ELECTRIC SYSTEM INTERCONNECTION APPENDIX A PROCEDURES & REQUIREMENTS for OKANOGAN PUD ELECTRIC SYSTEM INTERCONNECTION Version 4.0 December 2011 Version 4.0 12/28/2011 Page 1 of 15 TABLE OF CONTENTS DEFINITIONS 1.0 Introduction 2.0 Procedures

More information

PES Cook Islands KEMA Grid Study Final Report

PES Cook Islands KEMA Grid Study Final Report Integrating PV Solar and Wind generation with the TAU electric system Te Aponga Uira O Tumu-Te_Varovaro Contents 1. Executive summary... 2 2. Introduction... 5 2.1 Proposed wind turbine sites... 6 2.2

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Clean Line Energy Partners, LLC. Western Spirit Clean Line 345 kv. System Impact Study

Clean Line Energy Partners, LLC. Western Spirit Clean Line 345 kv. System Impact Study Clean Line Energy Partners, LLC Western Spirit Clean Line 345 kv System Impact Study February, 2017 Prepared by: Public Service Company of New Mexico Foreword This report was prepared for the Clean Line

More information

New Mexico Transmission Expansion Concepts For Wind Resources

New Mexico Transmission Expansion Concepts For Wind Resources New Mexico Transmission Expansion Concepts For Wind Resources May 2008 Update Electric Services Transmission Operations FOREWORD This document contains PNM s latest concepts for expanding the transmission

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

Four Corners Queue Transmission Interconnection Study

Four Corners Queue Transmission Interconnection Study Four Corners Queue Transmission Interconnection Study Facility Study Results By Arizona Public Service Company Transmission Planning & Interconnection Development March 22, 2016 Version 1 FACILITIES STUDY

More information

FEASIBILITY STUDY REPORT

FEASIBILITY STUDY REPORT FEASIBILITY STUDY REPORT HL20S PV Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 249 Eastern Avenue Augusta, ME 04330 (207) 621-7000 July 2012 FOREWORD This report was prepared for

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

PV Grid Integration Research in the U.S.

PV Grid Integration Research in the U.S. PV Grid Integration Research in the U.S. Barry Mather Ph.D. NREL- Power Systems Engineering Center HEPIA IEA PVPS Task 14 Utility Workshop Geneva, Switzerland March 31 st, 2014 NREL is a national laboratory

More information

Grid Stability Analysis for High Penetration Solar Photovoltaics

Grid Stability Analysis for High Penetration Solar Photovoltaics Grid Stability Analysis for High Penetration Solar Photovoltaics Ajit Kumar K Asst. Manager Solar Business Unit Larsen & Toubro Construction, Chennai Co Authors Dr. M. P. Selvan Asst. Professor Department

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

Essential Reliability Services From PV Plants

Essential Reliability Services From PV Plants Essential Reliability Services From PV Plants Mahesh Morjaria, Ph. D. VP, PV Systems Enabling a world powered by reliable, affordable solar electricity. Utility-Scale PV Plants Support Grid Stability &

More information

Interconnection Feasibility Study Report Request # GI

Interconnection Feasibility Study Report Request # GI A. Executive Summary Interconnection Feasibility Study Report Request # GI-2011-04 587 MW Combined Cycle 2x1 Generators Cherokee Station, Denver, Colorado Public Service Company of Colorado Transmission

More information

QP 311 Kingdom Community Wind Project Interconnection Feasibility Study. July, 2010 FINAL REPORT. Prepared by:

QP 311 Kingdom Community Wind Project Interconnection Feasibility Study. July, 2010 FINAL REPORT. Prepared by: FINAL REPORT QP 311 Kingdom Community Wind Project Interconnection Feasibility Study July, 2010 Prepared by: i For ISO New England and Vermont Electric Power Company Table of Contents Executive Summary...

More information

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code: Generating Facility Level 2 or 3 Interconnection Review (For Generating Facilities with Electric Nameplate Capacities no Larger than 20 MW) Instructions An Interconnection Customer who requests a Utah

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management Southern Company Interconnection Process Dexter Lewis Research Engineer Research and Technology Management Southern Company Outline Southern Company GPC Solar Interconnection Process Application requirements

More information

Interconnection Feasibility Study Report GIP-046-FEAS-R2

Interconnection Feasibility Study Report GIP-046-FEAS-R2 Interconnection Feasibility Study Report GIP-046-FEAS-R2 Generator Interconnection Request #46 32 MW Wind Generating Facility Colchester (L-6513), NS August 17, 2007 Control Centre Operations Nova Scotia

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP

Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP Grid Interconnection & Contract Development Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP Submittal Instructions Prior to submitting your application and

More information

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems Farid Katiraei *, Barry Mather **, Ahmadreza Momeni *, Li Yu *, and Gerardo Sanchez * * Quanta Technology, Raleigh,

More information

EL PASO ELECTRIC COMPANY SYSTEM EXPANSION PLAN

EL PASO ELECTRIC COMPANY SYSTEM EXPANSION PLAN EL PASO ELECTRIC COMPANY SYSTEM EXPANSION PLAN 2019-2028 Produced by System Planning 2018 GENERAL EL PASO ELECTRIC COMPANY 2019-2028 SYSTEM EXPANSION PLAN Executive Summary El Paso Electric Company s

More information

Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011

Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011 Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011 Jim Calore Public Service Electric & Gas Co. Overview This

More information

Q92 Asarco Interconnection

Q92 Asarco Interconnection A subsidiary of Pinnacle West Capital Corporation Q92 Asarco Interconnection Feasibility Study APS Contract No. 52239 By Arizona Public Service Company Transmission Planning July 29, 2010 Prepared by Utility

More information

Accidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies

Accidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies CIGRÉ-EPRI Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS Boston, MA, October 20-22, 2013 http : //www.cigre.org Accidental Islanding of Distribution Systems with Multiple Distributed Generation

More information

Interconnection Feasibility Study

Interconnection Feasibility Study Interconnection Feasibility Study Mount Mabel Wind Energy Project Report No: T&S Planning 2015-054 December 2015 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2015.

More information

PV System Impact Guide

PV System Impact Guide PV System Impact Guide NRECA - PV System Impact Guide Foreword This Photovoltaic (PV) System Impact Guide is part of a series of National Rural Electric Cooperative Association (NRECA) guides including

More information

NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress

NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM ATTACHMENT 2 Utility: Duke Energy Progress Designated Utility Contact: Attention: Customer Owned Generation Mail Code ST13A E-Mail Address: Customerownedgeneration@duke-energy.com

More information

Distributed Energy Resources

Distributed Energy Resources Distributed Energy Resources WECC Data Subcommittee Rich Hydzik, Avista (ERSWG/DER Subgroup Lead) June 29, 2018 Why Are We Concerned About DER? Concern about changing generation fleet Large coal fired

More information

Session 10 NERC Interconnection Requirements

Session 10 NERC Interconnection Requirements GE Energy Session 10 NERC Interconnection Requirements UVIG Short Course 2014 Portland, Oregon Jason MacDowell NERC Standards Recently Adopted NERC GVSDT* standards MOD (Model Validation): MOD-025: Verification

More information