Essential Reliability Services From PV Plants

Size: px
Start display at page:

Download "Essential Reliability Services From PV Plants"

Transcription

1 Essential Reliability Services From PV Plants Mahesh Morjaria, Ph. D. VP, PV Systems Enabling a world powered by reliable, affordable solar electricity.

2 Utility-Scale PV Plants Support Grid Stability & Reliability Utility-Scale PV Plants Provide Grid Friendly Features Required by NERC: Voltage regulation Real power control, ramping, and curtailment Primary frequency regulation Frequency droop response Short circuit duty control Fault ride through Utility-Scale PV Plants Contribute to Grid Stability & Reliability Like Conventional Generation Source: NERC: 2012 Special Assessment Interconnection Requirements for Variable Generation 2

3 PV Plant Schematic Sunlight to DC Power DC Power to AC Power AC Power to Grid DC AC SOLAR ARRAYS COMBINER BOX POWER CONVERSION STATION SWITCHGEAR SUBSTATION POWER GRID 69 to 765kV (AC) DC Typical DC Voltage 1kV or 1.5kV Typical AC Collection Voltage 34.5kV (Alternatives 4.16kV to 27.6kV) 3

4 Plant Control System Enables Grid Friendly Features Sunlight to DC Power DC Power to AC Power AC Power to Grid DC AC 69 to 765kV (AC) SOLAR ARRAYS Patent No. 8,774,974. Real-time photovoltaic power plant control system COMBINER BOX DC Typical DC Voltage 1kV or 1.5kV POWER CONVERSION STATION SWITCHGEAR Typical AC Collection Voltage 34.5kV (Alternatives 4.16kV to 27.6kV) SUBSTATION POWER GRID Checks grid s actual conditions and required set points Sends individual instructions to each inverter based on location, losses, and performance Controls quality of power coming out of the PV plant Closed-loop controls at 100 milliseconds! 4

5 Passage of Clouds at a 290 MW PV Plant ~20 minutes Large Plant Size Attenuates Impact of Cloud Passages on Power Output 5

6 AGUA CALIENTE 290MW AC CONNECTING ON 500 KV TRANSMISSION LINE Palo Verde Nuclear Generating Station Agua Caliente Hassayampa Substation California Arizona Hoodoo Wash Substation North Gila Substation 500kV Palo Verde-Hassayampa Transmission Line 6

7 Power (PU) and Reactive Power (PU) Voltage (PU) and Power Factor TYPICAL PLANT OPERATION (UNITY POWER FACTOR) Normalization Values Active Power: 300MW Reactive Power: 20MVAR Voltage: 530kV Typical Operating Day Power (PU) 110% 105% 0.6 Voltage (PU) 0.3 Power Factor 100% 0.0 Reactive Power (PU) 95% % 4:00 8:00 12:00 16:00 20:00 Time of Day Plant Is Maintained At Constant Power Factor as Required 7

8 MARCH 21 ST 2014 EVENT Agua Caliente Palo Verde Nuclear Generating Station Hassayampa SubstationO Line Taken Out of Service Hoodoo Wash Substation North Gila Substation 500kV Palo Verde-Hassayampa Transmission Line 8

9 Voltage Support from PV Plant Grid Operator Seeks Voltage Support Power (PU) Voltage (PU) Voltage (PU) Voltage (PU) Night Shutdown Power (PU) Voltage Control Started Reactive Power (PU) Maintain Voltage Even Under Changing Power Conditions 9

10 Demonstration of Essential Reliability Services by a 300-MW Solar PV Power Plant

11 Can variable energy resources provide essential reliability services to reliably operate the grid? NERC identified three essential reliability services to reliably integrate higher levels of renewable resources 1. Frequency Control 2. Voltage Control 3. Ramping capability or Flexible Capacity Test results demonstrated utility-scale PV plant has the capability to provide these essential reliability services Advancement in smart controls technology allows these plants to provide services similar to conventional resources VERs (Variable Energy Resources) with the right operating characteristics are necessary to decarbonize the grid Page 11

12 PV Power Plant Description First Solar PV modules 4 MVA PV inverters 8 x 40 MVA blocks 34.5 kv collector system Two 170 MVA transformers 34.5 kv Collection Tie with 230 kv transmission line PMUs collecting data on 230 kv side 170 MVA Transformer 230 kv Transmission 4MVA Inverter 40 MVA Block PMU 12

13 Reactive Power Capability PV Plant vs Synchronous Generator P (MW) October 2017 Reactive power capability of a typical synchronous generator compared to a PV Inverter Proposed CAISO Reactive Capability for Asynchronous Resources Q (MVAR) 13

14 Real Power (P) Typical Grid Requirement (e.g. ERCOT in Texas) Provide leading and lagging reactive power at Point of Interconnection (POI/POC) for all real power ranges from 10% to 100% Example: Real Power: P n = 300 MW Reactive Power: Q n = ~100 MVAr Apparent Power: S n = ~315 MVA Power Factor pf = 0.95 The PV plant must be capable of either producing or absorbing up to 100 MVAr when real power is from 30 MW to 300 MW Q n Inductive (Q-I) 0.95 pf Line P n P max Reactive Power (Q) 0.95 pf Line S n Corner Point driving design Q n (P n,q n ) Q = S 2 P 2 pf = P S Capacitive (Q-C) Grid POI Requirement 14

15 Demonstrated the Capability to Change System Voltage October 2017 MVAR Set Point Voltage MVAR Output By changing the reactive output of the plant from +100 MVAR to -100 MVAR, the voltage at the POI changed from 242 kv to 227 kv Demonstrated the ability of the plant to produce or absorb reactive power (±100 MVAR) even at nearly zero power output 15

16 Frequency Droop Tests Example of 3% droop test (under-frequency) Droop = P/P rated f/60hz 3% and 5% under and over-frequency tests Frequency Power 20% headroom ±36 mhz dead band Used actual frequency event time series measured in the U.S. Western Interconnection 16

17 Examples of Over-Frequency Droop Tests Example of 5% droop test (over-frequency) Power Frequency Measured droop response 5% Measured droop response 5% Measured droop response 3% Measured droop response 3% 17

18 Measured Reactive Power Capability and Voltages at POI Reactive power tests at high and low power production levels The plant meets the proposed CAISO reactive power requirements The plant is capable of providing +/- 100MVAR of dynamic reactive power response at any point when operating on this P-Q plane 18

19 Active Power Curtailment Test Active Power Set Point Active Power 19

20 POWER (MW) POWER (MW) AGC Participation Tests 300 MW Utility-Scale PV Plant MORNING 230 Available MW Min allowed MW Commanded MW Measured MW MW Headroom Commanded MW Available MW Measured MW Minimum Allowed MW RELATIVE TIME (sec) MIDDAY Avaliable MW Min Allowed MW Commanded MW Measured (MW) 30MW Headroom Commanded MW Available MW Measured MW Minimum Allowed MW RELATIVE TIME (sec) 30MW headroom 4-sec AGC signal provided to Plant Controller Tests were conducted for Sunrise Middle of the day Sunset 20

21 PV Plants Outperform Conventional Resources in Frequency Regulation 100% 90% 80% 70% 60% Regulation accuracy by PV Plant is about 24-30% points better than fast gas turbines 63% 87-93% 50% 40% 40% 30% 20% 10% 0% Steam Turbine Pump Turbine Hydro Combined Cycle Limited Energy Storage Gas Turbine Solar PV (Middle of the Day) Solar PV (Sunset) Solar PV (Sunrise Blue bars taken from the ISO s informational submittal to FERC on the performance of resources providing regulation services between January 1, 2015 and March 31,

22 Summary of Conducted Tests Regulation-up and regulation-down, or AGC tests during sunrise, middle of the day, and sunset Frequency response tests with 3% and 5% droop settings for over- frequency and under- frequency conditions Curtailment and APC tests to verify plant performance to decrease or increase its output while maintaining specific ramp rates Voltage and reactive power control tests Voltage control at near zero active power levels (nighttime control) 22

23 TESTS SUCCESSFULLY CONDUCTED ON 300 MW SOLAR PV PLANT Power Ramping Ramp its real-power output at a specified ramp-rate Provide regulation up/down service Voltage Control Control a specified voltage schedule Operate at a constant power factor Produce a constant level of MVAR Provide controllable reactive support (droop setting) Provide reactive support at night Frequency Provide frequency response for low frequency & high frequency events Control the speed of frequency response Provide fast frequency response to arrest frequency decline Utility-Scale PV Plant Contributes to Grid Stability & Reliability Like Conventional Generation 23

24 Utility-scale PV solar is a flexible resource that can enhance grid reliability Dispatchable PV Plant Solar can provide NERC-identified essential services to reliably integrate higher levels of renewable resources, including: Frequency Control Voltage Control Ramping capability or flexible capacity Automated Generation Control (AGC) regulation accuracy of %points better than fast gas turbines Reduces need for services from conventional generation Goes beyond simple PV energy value Enables additional solar Reduces need for expensive storage CAISO: Grid Friendly Utility-Scale PV Plants are Essential for Large-Scale PV Integration 24

Essential Reliability Services From PV Plants

Essential Reliability Services From PV Plants Essential Reliability Services From PV Plants Mahesh Morjaria, Ph. D. VP, PV Systems Enabling a world powered by reliable, affordable solar electricity. Can variable energy resources provide essential

More information

DEMONSTRATION OF ESSENTIAL RELIABILITY SERVICES BY A 300-MW SOLAR PV POWER PLANT

DEMONSTRATION OF ESSENTIAL RELIABILITY SERVICES BY A 300-MW SOLAR PV POWER PLANT DEMONSTRATION OF ESSENTIAL RELIABILITY SERVICES BY A 300-MW SOLAR PV POWER PLANT CONTROL SYSTEM DESIGN FIRST SOLAR PLANT CONTROL SYSTEM ARCHITECTURE Monitor conditions at the POI and compare them with

More information

Advances in Utility- Scale PV Plants: Key Lessons Learned

Advances in Utility- Scale PV Plants: Key Lessons Learned Advances in Utility- Scale PV Plants: Key Lessons Learned Mahesh Morjaria, Ph.D. VP, PV Systems Enabling a world powered by reliable, affordable solar electricity. Key Messages Advances in Utility-Scale

More information

UTILITY-SCALE SOLAR & THE EVOLVING GRID

UTILITY-SCALE SOLAR & THE EVOLVING GRID GRID FLEXIBLE SOLAR UTILITY-SCALE SOLAR & THE EVOLVING GRID As a least-cost new resource, more solar is added to the power grid every day As solar penetration increases, grid operators face new challenges

More information

By Mahesh Morjaria, Dmitriy Anichkov, Vladimir Chadliev and Sachin Soni First Solar, Tempe, Arizona

By Mahesh Morjaria, Dmitriy Anichkov, Vladimir Chadliev and Sachin Soni First Solar, Tempe, Arizona Grid Integration of Large Utility-Scale PV Plants: Key Lessons Learned By Mahesh Morjaria, Dmitriy Anichkov, Vladimir Chadliev and Sachin Soni First Solar, Tempe, Arizona Abstract The increase in competitiveness

More information

Grid-Friendly Utility-Scale PV Plants

Grid-Friendly Utility-Scale PV Plants White Paper Grid-Friendly Utility-Scale PV Plants Mahesh Morjaria & Dmitriy Anichkov, First Solar, Tempe, Arizona, USA 13 August 2013 Table of Contents Introduction.... 3 Power Plant Controller Architecture...

More information

Distributed Energy Resources

Distributed Energy Resources Distributed Energy Resources WECC Data Subcommittee Rich Hydzik, Avista (ERSWG/DER Subgroup Lead) June 29, 2018 Why Are We Concerned About DER? Concern about changing generation fleet Large coal fired

More information

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 1 Reactive Power Compensation for Solar Power Plants Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 2 Objectives Refresh the basics of reactive power from a generator s perspective Regulatory

More information

Operational Opportunities to Minimize Renewables Curtailments

Operational Opportunities to Minimize Renewables Curtailments Operational Opportunities to Minimize Renewables Curtailments Clyde Loutan Principal, Renewable Energy Integration July 24, 2017 2017 CAISO - Public Page 1 Agenda Background Real-time control performance

More information

Essential Reliability Services Engineering the Changing Grid

Essential Reliability Services Engineering the Changing Grid Essential Reliability Services Engineering the Changing Grid Robert W. Cummings Senior Director Engineering and Reliability Initiatives i-pcgrid March 39, 2016 Change is Coming Characteristics and behavior

More information

Ancillary Services & Essential Reliability Services

Ancillary Services & Essential Reliability Services Ancillary Services & Essential Reliability Services EGR 325 April 19, 2018 1 Basic Products & Ancillary Services Energy consumed by load Capacity to ensure reliability Power quality Other services? o (To

More information

Georgia Transmission Corporation Georgia Systems Operations Corporation

Georgia Transmission Corporation Georgia Systems Operations Corporation Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia

More information

A Grid-Friendly Plant

A Grid-Friendly Plant A Grid-Friendly Plant By Mahesh Morjaria, Dmitriy Anichkov, Vladimir Chadliev, and Sachin Soni plant fotosearch, background image licensed by ingram publishing The Role of Utility-Scale Photovoltaic Plants

More information

Advanced Inverter Design

Advanced Inverter Design GE Energy Advanced Inverter Design Matt Perkins, Sales Manager Global solar landscape Annual Solar Installations (GW) $3.85 Module ASP ($/W) $1.70 $1.60 $1.35 $1.25 $1.15 70% Industry dynamics 11 9 11

More information

Utility Scale Solar PV Riley Saito 2011 SunPower Corporation

Utility Scale Solar PV Riley Saito 2011 SunPower Corporation Asia Pacific Clean Energy Summit and Expo Utility Scale Solar PV Riley Saito September 13, 2011 Outline Utility Scale Solar PV Introduction to SunPower SunPower s Utility Experience History of Grid Interconnected

More information

ANCILLARY SERVICES WITH VRE (VARIABLE RENEWABLE ENERGY): FOCUS PV

ANCILLARY SERVICES WITH VRE (VARIABLE RENEWABLE ENERGY): FOCUS PV ANCILLARY SERVICES WITH VRE (VARIABLE RENEWABLE ENERGY): FOCUS PV September 2017 1st International Conference on Large-Scale Grid Integration of Renewable Energy in India Andreas Falk, Ancillary services

More information

Q51 Generation Interconnection

Q51 Generation Interconnection Q51 Generation Facilities Study Results APS Contract No. 52395 By Arizona Public Service Company Transmission Planning September 4, 2013 [Version 1.0] Q51 FACILITIES STUDY TABLE OF CONTENTS Contents 1.

More information

SPIDER Modeling Sub-Group DER Modeling, CAISO Experience

SPIDER Modeling Sub-Group DER Modeling, CAISO Experience SPIDER Modeling Sub-Group DER Modeling, CAISO Experience Irina Green, Modeling Sub-Group Chair Regional Transmission Senior Advisor, California ISO NERC SPIDER Work Group Meeting, January 2019 Presentation

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

THE TRES AMIGAS PROJECT

THE TRES AMIGAS PROJECT UNITING THE NATION S ELECTRIC POWER GRID THE TRES AMIGAS PROJECT Project Development, Business Case, and Benefits -ERCOT Presentation Jan 22, 2010 Agenda Project Overview Project Objective Project Description,

More information

Workshop on Grid Integration of Variable Renewable Energy: Part 1

Workshop on Grid Integration of Variable Renewable Energy: Part 1 Workshop on Grid Integration of Variable Renewable Energy: Part 1 System Impact Studies March 13, 2018 Agenda Introduction Methodology Introduction to Generators 2 Introduction All new generators have

More information

RESERVOIR SOLUTIONS. GE Power. Flexible, modular Energy Storage Solutions unlocking value across the electricity network

RESERVOIR SOLUTIONS. GE Power. Flexible, modular Energy Storage Solutions unlocking value across the electricity network GE Power RESERVOIR SOLUTIONS Flexible, modular Energy Storage Solutions unlocking value across the electricity network TRENDS DISRUPTING THE POWER SECTOR FROM GENERATION TO T&D DECARBONIZATION DIGITIZATION

More information

DER101: Distributed Energy Resources basics. May 4, 2017

DER101: Distributed Energy Resources basics. May 4, 2017 DER101: Distributed Energy Resources basics May 4, 2017 Agenda Introduction Definitions Abbreviations Types Why it is important Common Misconceptions DER System Basics References, Codes and Standards Interconnection

More information

PES Cook Islands KEMA Grid Study Final Report

PES Cook Islands KEMA Grid Study Final Report Integrating PV Solar and Wind generation with the TAU electric system Te Aponga Uira O Tumu-Te_Varovaro Contents 1. Executive summary... 2 2. Introduction... 5 2.1 Proposed wind turbine sites... 6 2.2

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Flywheel as High Power Storage Devices for Grid Load Balancing and Stabilization

Flywheel as High Power Storage Devices for Grid Load Balancing and Stabilization Flywheel as High Power Storage Devices for Grid Load Balancing and Stabilization Matt Lazarewicz Vice President and Chief Technical Officer International Renewable Energy Storage Conference Gelsenkirchen,

More information

Session 10 NERC Interconnection Requirements

Session 10 NERC Interconnection Requirements GE Energy Session 10 NERC Interconnection Requirements UVIG Short Course 2014 Portland, Oregon Jason MacDowell NERC Standards Recently Adopted NERC GVSDT* standards MOD (Model Validation): MOD-025: Verification

More information

Accidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies

Accidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies CIGRÉ-EPRI Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS Boston, MA, October 20-22, 2013 http : //www.cigre.org Accidental Islanding of Distribution Systems with Multiple Distributed Generation

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems Farid Katiraei *, Barry Mather **, Ahmadreza Momeni *, Li Yu *, and Gerardo Sanchez * * Quanta Technology, Raleigh,

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

The Power Potential Project A guide to participating

The Power Potential Project A guide to participating The Power Potential Project 0 A guide to participating A technical guide to the services for synchronous and non-synchronous DER participants Page 1 of 17 Table of Contents Our vision... 3 1. Introduction...

More information

Lab Validation of PV Solar Inverter Control as STATCOM (PV-STATCOM) Rajiv K. Varma and Ehsan Siavashi

Lab Validation of PV Solar Inverter Control as STATCOM (PV-STATCOM) Rajiv K. Varma and Ehsan Siavashi 1 Lab Validation of PV Solar Inverter Control as STATCOM (PV-STATCOM) Rajiv K. Varma and Ehsan Siavashi The University of Western Ontario London, ON, CANADA rkvarma@uwo.ca Novel Concept Utilization of

More information

The North Carolina solar experience: high penetration of utility-scale DER on the distribution system

The North Carolina solar experience: high penetration of utility-scale DER on the distribution system 1 The North Carolina solar experience: high penetration of utility-scale DER on the distribution system John W. Gajda, P.E. Duke Energy IEEE PES Working Group on Distributed Resources Integration 2 High

More information

The Solar Trifecta: A Path to Smart Utility-Scale Solar. October 2017

The Solar Trifecta: A Path to Smart Utility-Scale Solar. October 2017 The Solar Trifecta: A Path to Smart Utility-Scale Solar October 2017 Copyright 2017 ScottMadden, Inc. All rights reserved. Report _2017 Contents Executive Summary Traditional Utility-Scale Solar: Growing

More information

CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM

CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM 106 CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM 5.1 INTRODUCTION Inherent characteristics of renewable energy resources cause technical issues not encountered with conventional thermal,

More information

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station East Asian Alternative Energy Futures Workshop By the Nonproliferation Policy Education Center

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

Review of U.S. market reforms for renewable integration, flexibility, and storage

Review of U.S. market reforms for renewable integration, flexibility, and storage Review of U.S. market reforms for renewable integration, flexibility, and storage Eric Hsieh Director Office of Energy Finance and Incentives Analysis U.S. Department of Energy 14 July 2017 Transformations

More information

Power Potential Guide to Participating : A technical 0 guide to the services for synchronous and non-synchronous DER participants 04/10/2017

Power Potential Guide to Participating : A technical 0 guide to the services for synchronous and non-synchronous DER participants 04/10/2017 Power Potential Guide to Participating : A technical 0 guide to the services for synchronous and non-synchronous DER participants 04/10/2017 Our Vision of the Future National Grid (NG) and UK Power Networks

More information

Renewable and Distributed Energy Resource Technologies

Renewable and Distributed Energy Resource Technologies OCIECE EACJ5300/ELG7114i - 2013 Winter Term Renewable and Distributed Energy Resource Technologies Chapter 1 Power System Basics Instructor: Xiaoyu Wang, Assistant Professor Department of Electronics,

More information

The Role of Electricity Storage on the Grid each location requires different requirements

The Role of Electricity Storage on the Grid each location requires different requirements Functional Requirements for Energy on the Utility Grid EPRI Renewable Council Meeting Bill Steeley Senior Project Manager Dan Rastler Program Manager April 5-6, 2011 The Role of Electricity on the Grid

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

Grid Integration Costs: Impact of The IRP Capacity Mix on System Operations

Grid Integration Costs: Impact of The IRP Capacity Mix on System Operations Grid Integration Costs: Impact of The IRP Capacity Mix on System Operations Presenter: Bernard Magoro, System Operator, Transmission Division, Eskom SOC Holdings Date: 05 October 2018 Contents 1. Background

More information

Request for Payment Instructions Rule 21 Export Submittal Instructions

Request for Payment Instructions Rule 21 Export Submittal Instructions Grid Interconnection & Contract Development Request for Payment Instructions Rule 21 Export Submittal Instructions Prior to submitting your application and fee or deposit, please complete and submit this

More information

Grid Stability Analysis for High Penetration Solar Photovoltaics

Grid Stability Analysis for High Penetration Solar Photovoltaics Grid Stability Analysis for High Penetration Solar Photovoltaics Ajit Kumar K Asst. Manager Solar Business Unit Larsen & Toubro Construction, Chennai Co Authors Dr. M. P. Selvan Asst. Professor Department

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

Arizona Transmission Challenges

Arizona Transmission Challenges Power Task Force Agenda Number 2. Arizona Transmission Challenges Central Arizona Water Conservation District Power Committee Presentation May 18, 2017 Transmission Planning Efforts NATIONAL Section 368

More information

Technical & Regulatory Standards Development

Technical & Regulatory Standards Development GE Energy Management Technical & Regulatory Standards Development RENEW / ISONE Interconnection of Renewable Generation Jason MacDowell GE Energy Consulting September 30, 2014 Global Renewable Codes &

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

IFC Workshop on Distributed Generation, 13 February 2013, Moscow, Russia

IFC Workshop on Distributed Generation, 13 February 2013, Moscow, Russia Integration of Distributed Energy Resources Into the Electric Grid: Some Issues and Solutions Larry Adams Senior Electrical & Controls Engineer Spirae, Inc. IFC Workshop on Distributed Generation, 13 February

More information

NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress

NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM ATTACHMENT 2 Utility: Duke Energy Progress Designated Utility Contact: Attention: Customer Owned Generation Mail Code ST13A E-Mail Address: Customerownedgeneration@duke-energy.com

More information

Grid code Compliance and Renewable Energy Projects. Mick Barlow, Business Development Director, S&C Electric, United Kingdom

Grid code Compliance and Renewable Energy Projects. Mick Barlow, Business Development Director, S&C Electric, United Kingdom Grid code Compliance and Renewable Energy Projects Mick Barlow, Business Development Director, S&C Electric, United Kingdom Why Grid Codes? Permit the development of and operation of an efficient and economical

More information

Generation Interconnection Facilities Study For

Generation Interconnection Facilities Study For Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...

More information

El Paso Electric Company

El Paso Electric Company Feasibility Study XXXXXX Solar Generation Prepared for El Paso Electric Company Prepared by TRC Engineers, LLC 249 Eastern Avenues Augusta, ME 04330 (207) 621-7000 Project Number: 202327 May 2013 FOREWORD

More information

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code: Generating Facility Level 2 or 3 Interconnection Review (For Generating Facilities with Electric Nameplate Capacities no Larger than 20 MW) Instructions An Interconnection Customer who requests a Utah

More information

RPS TL-UL System. Solutions for the North American Solar Market

RPS TL-UL System. Solutions for the North American Solar Market RPS TL-UL System Solutions for the North American Solar Market 2015/2016 Power, control and green solutions 3 RPS TL-UL System Photovoltaics is now offering the ULcertified RPS TL inverter series. Leveraging

More information

Experiences with Wind Power Plants with Low SCR

Experiences with Wind Power Plants with Low SCR 1 Experiences with Wind Power Plants with Low SCR Lessons learned from the analysis, design and connection of wind power plants to weak electrical grids IEEE PES General Meeting Denver CO, 26 March 2015

More information

MEPPI Power Systems Engineering Division (PSED)

MEPPI Power Systems Engineering Division (PSED) Loss of Synchronous Generation Impacts and Mitigation MEPPI Power Systems Engineering Division (PSED) for EE500E Energy & Environment Seminar, University of WA, October 5, 2017 Agenda 1. An Active Industry

More information

Experience with Model Validation of PV Power Plants. Abraham Ellis, Ryan Elliott, Ray Byrne Sandia National Laboratories

Experience with Model Validation of PV Power Plants. Abraham Ellis, Ryan Elliott, Ray Byrne Sandia National Laboratories 1 Experience with Model Validation of PV Power Plants Abraham Ellis, Ryan Elliott, Ray Byrne Sandia National Laboratories 2 Outline Overview: PV Plants and WECC/REMTF Models Status of WECC/REMTF generic

More information

Renewable Grid Integration Research in the U.S.

Renewable Grid Integration Research in the U.S. Renewable Grid Integration Research in the U.S. Barry Mather Ph.D. NREL- Distributed Energy Systems Integration Group UNSW IEA PVPS Task 14 Workshop Sydney, AU November 26 th, 2013 NREL is a national laboratory

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

C PER. Center for Advanced Power Engineering Research C PER

C PER. Center for Advanced Power Engineering Research C PER Center for Advanced Power Engineering Research C PER 2017 Summer Research Planning Workshop Energy Storage Technologies and Application Roadmap Presented By: Johan Enslin Zucker Family Graduate Education

More information

Clark W Gellings, P.E. Fellow National Conference of State Legislators Energy Supply Task Force August 18, 2014

Clark W Gellings, P.E. Fellow National Conference of State Legislators Energy Supply Task Force August 18, 2014 Clark W Gellings, P.E. Fellow National Conference of State Legislators Energy Supply Task Force August 18, 2014 2014 Electric Power Research Institute, Inc. All rights reserved. Electric Power Research

More information

PSNH INTERCONNECTION REQUEST

PSNH INTERCONNECTION REQUEST PSNH INTERCONNECTION REQUEST Send the completed Interconnection Request and required attachments to: Public Service of New Hampshire Attn: Michael Motta, Senior Engineer Supplemental Energy Sources P.

More information

i-pcgrid Workshop 2017

i-pcgrid Workshop 2017 i-pcgrid Workshop 2017 Potential Impacts of Flexible Ramping Need on Transmission Planning March 2017 Chifong Thomas Director, Transmission Planning and Strategy Smart Wires Inc. USA Flexible Capacity

More information

Re: Comments on the 12/7/09 Dynamic Transfer Stakeholder Meeting

Re: Comments on the 12/7/09 Dynamic Transfer Stakeholder Meeting Joseph H. Rowley Vice President Project Development 101 Ash Street, HQ14A San Diego, CA 92101-3017 Tel: 619.696.4455 Fax: 619.696.2911 JRowley@SempraGeneration.com December 15, 2009 Ms. Anjali Sheffrin

More information

Dynamic Reactive Power Control for Wind Power Plants

Dynamic Reactive Power Control for Wind Power Plants Dynamic Reactive Power Control for Wind Power Plants Ernst Camm, Charles Edwards, Ken Mattern, Stephen Williams S&C Electric Company, 6601 N. Ridge Blvd, Chicago IL 60626 USA ecamm@sandc.com, cedwards@sandc.om,

More information

Connection of Power Generating Modules to DNO Distribution Networks in accordance with EREC G99

Connection of Power Generating Modules to DNO Distribution Networks in accordance with EREC G99 Connection of Power Generating Modules to DNO Distribution Networks in accordance with EREC G99 Version 2, January 2019 www.energynetworks.org 2 Introduction Connection of Power Generating Modules to DNO

More information

Guideline on Energy Storage

Guideline on Energy Storage Purpose Commonwealth of Massachusetts Executive Office of Energy and Environmental Affairs DEPARTMENT OF ENERGY RESOURCES SOLAR MASSACHUSETTS RENEWABLE TARGET PROGRAM (225 CMR 20.00) GUIDELINE Guideline

More information

Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances

Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances 29 Juli 2014 Page 1 Characteristics of the Project Parameter Detail

More information

Minnesota Dept. of Commerce, Division of Energy Resources. Distributed Generation Workshop Interconnection Standards

Minnesota Dept. of Commerce, Division of Energy Resources. Distributed Generation Workshop Interconnection Standards Minnesota Dept. of Commerce, Division of Energy Resources Distributed Generation Workshop Interconnection Standards Presented by Michael Sheehan, P.E. October 11, 2011 Germans Solar Projected Cost Reductions

More information

Q85 Generation Interconnection

Q85 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q85 Generation Interconnection Interconnection Facilities Study AMENDED APS Contract No. 52386 By Arizona Public Service Company Transmission Planning

More information

Advancements in Energy Storage: Utility-Scale Technologies and Demonstration Projects

Advancements in Energy Storage: Utility-Scale Technologies and Demonstration Projects Advancements in Energy Storage: Utility-Scale Technologies and Demonstration Projects ASERTTI Webinar August 20, 2012 Barbara Tyran Director, Washington & State Relations The Electric Power Research Institute

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

An Introduction to Completing a NERC PRC Study

An Introduction to Completing a NERC PRC Study An Introduction to Completing a NERC PRC-019-2 Study For Synchronous and Distributed Generation Sources PRESENTED BY: MATTHEW MANLEY TEXAS A&M PROTECTIVE RELAYING CONFERENCE MARCH 26-29, 2018 Presentation

More information

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation Intentionally left blank F1 Description and Functional Specifications of Proposed

More information

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report

More information

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems Ben Huckaba, P.E. President & Principal Engineer 317-273-9841 benh@alphaeng.us Indiana University Bloomington,

More information

Renewable Energy & Storage Best Practice at TPL and Issues Faced. Murray Sheerin Power Generation Manager, Tonga Power Limited.

Renewable Energy & Storage Best Practice at TPL and Issues Faced. Murray Sheerin Power Generation Manager, Tonga Power Limited. Renewable Energy & Storage Best Practice at TPL and Issues Faced. Murray Sheerin Power Generation Manager, Tonga Power Limited. Tonga Power Limited Tonga Power Limited (TPL) is a 100% state owned enterprise

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

TECHNICAL STRATEGIC CHOICE: POWER ELECTRONIC SYSTEMS AND APPLICATIONS

TECHNICAL STRATEGIC CHOICE: POWER ELECTRONIC SYSTEMS AND APPLICATIONS POWER ELECTRONIC SYSTEMS AND APPLICATIONS FAULT DETECTION & MITIGATION GPS-BASED SMART RECLOSER DC CIRCUIT PROTECTION IMBALANCES IN 3- PHASE FEEDERS COMPENSATION TECHNIQUES SUB-SYNCHRONOUS RESONANCE MITIGATION

More information

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013 Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in 2015 Stakeholder Webconference February 28, 2013 Page 2 Merced Irrigation District (Merced) Background Merced Irrigation

More information

High speed, closed loop frequency control using PMU measurements for power grids

High speed, closed loop frequency control using PMU measurements for power grids PXiSE Energy Solutions, LLC High speed, closed loop frequency control using PMU measurements for power grids By: Chuck Wells and Raymond de Callafon Date: September 27, 2017 PXiSE Energy Solutions, LLC

More information

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM 1 1 The Latest in the MIT Future of Studies Recognizing the growing importance of energy issues and MIT s role as an honest broker, MIT faculty have undertaken a series of in-depth multidisciplinary studies.

More information

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management Southern Company Interconnection Process Dexter Lewis Research Engineer Research and Technology Management Southern Company Outline Southern Company GPC Solar Interconnection Process Application requirements

More information

Primary Frequency Response. Summary of Stakeholder Comments Appendix

Primary Frequency Response. Summary of Stakeholder Comments Appendix Primary Frequency Response Summary of Stakeholder Comments Appendix October 20, 2015 1. Introduction The Frequency Response initiative s goal is to propose an option that will reduce the risk of the ISO

More information

Proposed New ISO Rules Section Version 2.0 Generating Unit Technical Requirements ( New ISO Rules Section Version 2.

Proposed New ISO Rules Section Version 2.0 Generating Unit Technical Requirements ( New ISO Rules Section Version 2. Stakeholder Comment and Rationale Form AESO AUTHORITATIVE DOCUMENT PROCESS Stakeholder Consultation Draft 2012-11-29 Proposed New ISO Rules Section 502.5 Version 2.0 Generating Unit Technical Requirements

More information

DG Standard Updates. IEEE 1547, UL 1741 SA, and Rule 21 CHASE SUN GII/PG&E 3/28/18

DG Standard Updates. IEEE 1547, UL 1741 SA, and Rule 21 CHASE SUN GII/PG&E 3/28/18 DG Standard Updates IEEE 1547, UL 1741 SA, and Rule 21 CHASE SUN GII/PG&E 3/28/18 DER Interconnection Standards Chronology Arab Oil Embargo 1973 Gas Rationing. Oil went from $3/barrel (gas at $ 0.35/gal)

More information

GE Energy. Variable Frequency Transformers Grid Inter-tie

GE Energy. Variable Frequency Transformers Grid Inter-tie GE Energy Variable Frequency Transformers Grid Inter-tie Variable Frequency Transformers GE Energy revolutionizes the world of transmission solutions with its new Variable Frequency Transformer (VFT).

More information

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba

More information

IEEE SESSION COMPUTER AIDED SMART POWER GRID

IEEE SESSION COMPUTER AIDED SMART POWER GRID IEEE SESSION COMPUTER AIDED SMART POWER GRID GEN_1 t.giras@ieee.org GEN_2 LOAD_1 LOAD_2 1 HIGH SMART GRID LEVEL LOW SMART POWER GRID TECHNOLOGY HISTORY MIT NETWORK ANALYZER 1940 ANALOG DISPATCH ACE SCADA

More information

Electrical Power Electric power electrical electric power Electric power electric electric

Electrical Power Electric power electrical electric power Electric power electric electric Power Calculations Electrical Power Electric power is the rate at which electrical energy is transferred by an electric circuit. The SI unit of power is the watt, one joule per second. Electric power is

More information

Targeted Application of STATCOM Technology in the Distribution Zone

Targeted Application of STATCOM Technology in the Distribution Zone Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Q87 Generation Interconnection

Q87 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Version 1.0 Q87 Generation Interconnection Interconnection Facilities Study APS Contract No. 52365 By Arizona Public Service Company Transmission Planning

More information

Tieline Controls in Microgrid Applications

Tieline Controls in Microgrid Applications Tieline Controls in Microgrid Applications M. Adamiak GE Digital Energy, Multilin K.Bahei-Eldin GE Global Research, S.Bose, GE Global Research, J.deBedout GE Global Research, Y.Liu, GE Global Research,

More information

Variable frequency transformer for asynchronous power transfer

Variable frequency transformer for asynchronous power transfer Variable frequency transformer for asynchronous power transfer by Einar Larsen, Richard Piwko and Donald McLaren, GE Energy A new power transmission technology has been developed. The variable frequency

More information

DRAFT. Guidelines on Power quality & safety issues in usage of roof-top solar pv system CENTRAL ELECTRICITY AUTHORITY

DRAFT. Guidelines on Power quality & safety issues in usage of roof-top solar pv system CENTRAL ELECTRICITY AUTHORITY DRAFT Guidelines on Power quality & safety issues in usage of roof-top solar pv system CENTRAL ELECTRICITY AUTHORITY 2018 1. INTRODUCTION Solar energy has become the most popular renewable energy source

More information

ROLE FOR ADJUSTABLE SPEED PUMPED STORAGE IN THE GRID OF THE FUTURE Peter Donalek

ROLE FOR ADJUSTABLE SPEED PUMPED STORAGE IN THE GRID OF THE FUTURE Peter Donalek CIGRE US National Committee Cleveland, OHIO October 23, 2017 2017 Grid of the Future Symposium ROLE FOR ADJUSTABLE SPEED PUMPED STORAGE IN THE GRID OF THE FUTURE Peter Donalek PRESENTATION Adjustable speed

More information