Generation Interconnection Facilities Study For

Size: px
Start display at page:

Download "Generation Interconnection Facilities Study For"

Transcription

1 Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015

2 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications... Page 3 Scope of Work, Cost Estimates and Time to Complete... Page 4 Summary... Page 5 Figure 1 Engineer Single Line Layout... Page 6 Figure 2 Site Location... Page 7 Figure 3 SCE&G owned 46kV Switching Station General Arrangement... Page 8 Figure 4 SCE&G owned 46kV Switching Station Switching Configuration... Page 9 2

3 Generator Interconnection Facilities Study For Project in SC A Generator Interconnection Facilities Study follows the previous Generation Interconnection System Impact Study, and specifies and estimates the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the Generator Interconnection System Impact Study in accordance with Good Utility Practice to physically and electrically connect the Interconnection Facility to the Transmission System. A Generator Interconnection Facilities Study also identifies the electrical switching configuration of the connection equipment, including, without limitation: the transformer, switchgear, meters, and other station equipment; the nature and estimated cost of any Transmission Provider's Interconnection Facilities and Network Upgrades, if necessary, to accomplish the interconnection; and an estimate of the time required to complete the construction and installation of such facilities. General Discussion has requested a Solar Photovoltaic (PV) plant in Hampton County. This solar facility has a total generation capacity of 8.16 MVA, consisting of (12) Schneider Electric Conext Core XC680-NA 680 kva solar inverters. group has requested an in service date of 10/1/2016 and that this generation be interconnected to the existing SCE&G 46 kv transmission system at a site near the. A previous Generator Interconnection System Impact Study was conducted to determine the ability of the SCE&G transmission system to interconnect the Generator to the Transmission System and to address any identified power flow, short circuit and instability issues. In that System Impact Study, facilities were identified that would require modifications in order to provide the requested Generator Interconnection. This Facilities Study identifies the cost and scheduled completion date of those modifications needed to provide the requested Generator Interconnection. Generator Interconnection Specifications The solar generation facility design consists of the following information: MVA: 8.16 MW: 8.16 PF: 80% lead/lag GSU: 46/26.56 kv (Wye-Wye) Speed: N/A 3

4 Scope of Work, Cost Estimates and Time to Complete The Table below includes the scope of work, cost estimate and time to complete for the transmission improvements required to provide the requested Generator Interconnection. Time to Complete includes design, drafting, ordering equipment, issuing drawings for construction, issuing drawings, lead time for equipment and construction. (Note that the installation of some equipment may require planned outages of transmission facilities. The ability to schedule an outage and perform the installation is subject to review and is based on transmission system conditions at the time of installation.) Scope of Work Estimated Cost 1 Complete 2 Time to Make modifications to the SCE&G transmission system to provide a radial Generator Interconnection off of the adjacent to project. (See Figure 1, 2, 3 and 4) - Construct an SCE&G-owned 46 kv switching station including, but not limited to, a 46 kv Circuit Breaker, structures, foundation, switches, PT s, CT s, batteries, revenue quality metering, SCADA, station service, lightning arresters, gravel, fencing and ground grid. - Install a Triple Suspended Pull Off (TSPO) wood pole in the center line of the line adjacent to project. Install two spans of transmission conductor from the TSPO to a structure in the SCE&G-owned 46 kv switching station. This cost assumes the SCE&G-owned 46 kv switching station is adjacent to or within 150 ft of the R/W. The cost does not include R/W procurement due to the unknown location of the station. - Make modifications at the Transmission Substation to accommodate reverse power flow through the transformers. $712, months $65,000 8 months $8, months TOTAL Required for Generator Interconnection $785, months 1. Estimated Costs based on future required In-service date. Costs do not include site cost, site preparation, road access or Right of Way procurement if needed. 2. Time to complete based on normal lead times for structures and major equipment and timing to allow an off-peak outage of the Estill-Estill 46 kv line. Time to Complete does not include time to acquire site, prepare the site and/or acquire Right of Way if needed. 3. The need for this modification exists in higher priority generator interconnection requests and may be completed as part of a generator interconnection that has a higher position in the generator interconnection queue. If the higher position generator interconnection request continues, then this modification may not be required as part of this generator interconnection. 4

5 Summary This Generator Interconnection Facilities Study has identified the cost and scheduled completion dates of the modifications needed to provide the requested Generator Interconnection. The 10 month Time to Complete, as shown above, will commence after all appropriate agreements have been signed. 5

6 6

7 7

8 8

9 9

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007 High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services

More information

Schneider Electric PV Skid. Optimized solar power conversion system tailored to enhance any North American PV power plant

Schneider Electric PV Skid. Optimized solar power conversion system tailored to enhance any North American PV power plant Schneider Electric PV Skid Optimized solar power conversion system tailored to enhance any North American PV power plant 1 PV Skid solution Integrated solution designed for optimal performance in any environment

More information

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010 FINAL FACILITY STUDY 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1 September 10, 2010 I. Introduction This is a revised facility study performed for Transmission Queue Request 2009

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Western Region ATSI Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems Ben Huckaba, P.E. President & Principal Engineer 317-273-9841 benh@alphaeng.us Indiana University Bloomington,

More information

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget Project 1 of 34 Aiken Trans - Aiken Hampton 115 kv Line: Upgrade 1272A Upgrade the 115 kv line between Aiken and Aiken Hampton substations from 336 ACSR to 1272 ACSR. Total line length approximately 3.7

More information

ELECTRIC SERVICE RULES DISTRIBUTED GENERATION Issued Jan 2016

ELECTRIC SERVICE RULES DISTRIBUTED GENERATION Issued Jan 2016 DISTRIBUTED GENERATION CHAPTER 5 500. SCOPE This chapter includes distributed or customer-owned generation connected in parallel and operating with Alliant Energy s electric distribution system. For all

More information

PJM Generation Interconnection Request Queue #A55 Lakewood 230kV Facilities Study Report

PJM Generation Interconnection Request Queue #A55 Lakewood 230kV Facilities Study Report PJM Generation Interconnection Request Queue #A55 Lakewood 230kV Facilities Study Report 155697 September 2001 Table of Contents DESCRIPTION PAGE 1.0 Introduction 3 2.0 Description of Facilities Included

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent

More information

Functional Specification Revision History

Functional Specification Revision History Functional Specification Revision History Revision Description of Revision Author Date B0 For comments Yale Zhou January 26, 2016 B1 Updated as per comments Yale Zhou February 1, 2016 Final issuance Yale

More information

New 115 kv Disconnect Switches at Bloomsburg MTS

New 115 kv Disconnect Switches at Bloomsburg MTS 115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115

More information

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget Project 1 of 28 Blythewood 115 kv Switching Station: Construct 03087A Construct Blythewood Switching Station with four 115 kv line terminals, with plans to expand to 230 kv at a future date. Fold in the

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Sunmine Solar Project. Interconnection System Impact Study

Sunmine Solar Project. Interconnection System Impact Study XXXX Sunmine Solar Project Interconnection System Impact Study Report No: T&S Planning 2013-012 May 2013 Revision 0 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Schedules 1 to 4, Lot B: Extension of the Lessos Substation

Schedules 1 to 4, Lot B: Extension of the Lessos Substation 1.0 LIGHTNING ARRESTORS 1.1 ZNO lightning arrester, 192 kv rated voltage, 10 ka nominal discharge current 2.0 CAPACITIVE VOLTAGE TRANSFORMER ea. 45 2.1 220 kv capacitive voltage transformer 220/ 3 / 0.11/

More information

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation Intentionally left blank F1 Description and Functional Specifications of Proposed

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT INTERCONNECTION FACILITIES STUDY REPORT Interconnection Request No. TI-12-0217 8 MW Hydropower Generating Facility POI on the Dallas Creek to South Canal 115kV Line in SW Colorado FINAL REPORT February

More information

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014 1 BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada IEEE PES Meeting July 2014 General BC Hydro Overview Crown Corporation Serving about 95% of province and 1.9 million customers

More information

Targeted Application of STATCOM Technology in the Distribution Zone

Targeted Application of STATCOM Technology in the Distribution Zone Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric

More information

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation 1. Description In the 2013-2014 Transmission Planning Cycle, the ISO approved the construction

More information

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655) - (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility

More information

Solar Power Switchgear & Energy Storage Renewable Energy Systems

Solar Power Switchgear & Energy Storage Renewable Energy Systems 7 Solar Power Switchgear & Energy Storage Renewable Energy Systems - Solution Brochure www.apt-power.com 433 N. 36 th Street PROVIDING A COMPREHENSIVE Lafayette, IN 47905 www.apt-power.com 433 APPROACH

More information

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202 Transmission and Distribution Substation Projects Operating Company: Entergy Gulf States - Texas Customer: PID # 202 Funding Project Number: F4PPGS0386 Facility Study for PID # 202: Study for 146 MW Revision

More information

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis Terry Blackwell Page 1 of 5 Education 1977 North Carolina State University BS, Electrical Engineering Power Systems emphasis Professional Qualifications 1977 PE-Professional Engineer Business Experience

More information

El Paso Electric Company

El Paso Electric Company Feasibility Study XXXXXX Solar Generation Prepared for El Paso Electric Company Prepared by TRC Engineers, LLC 249 Eastern Avenues Augusta, ME 04330 (207) 621-7000 Project Number: 202327 May 2013 FOREWORD

More information

Solar Farms: design & construction

Solar Farms: design & construction Solar Farms: design & construction Impacts to utility distribution systems John W. Gajda, P.E. Duke Energy Manager, DER Operations Support Agenda North Carolina s unique situation, which is coming to a

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Modular integrated transportable substation (MITS)

Modular integrated transportable substation (MITS) Technical Data TD027002EN transportable substation (MITS) Contents Description Page Voltage regulation with bypassing........................................................ 2 Mobile MITS application...............................................................

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Essential Reliability Services From PV Plants

Essential Reliability Services From PV Plants Essential Reliability Services From PV Plants Mahesh Morjaria, Ph. D. VP, PV Systems Enabling a world powered by reliable, affordable solar electricity. Utility-Scale PV Plants Support Grid Stability &

More information

Imperial Irrigation District Energy Consumers Advisory Committee Agenda Report

Imperial Irrigation District Energy Consumers Advisory Committee Agenda Report Imperial Irrigation District Energy Consumers Advisory Committee Agenda Report 260 TO: FROM: SUBJECT: ECAC Members Jamie Asbury, deputy energy manager, Business/Regulatory Five (5) Generator Interconnection

More information

Power Purchase and Grid Connection Procedures

Power Purchase and Grid Connection Procedures Building Your Biogas System Workshop and Grid Connection Procedures Aidan Foss. amfoss@ieee.org ANF Energy Solutions DG grid connection specialists No project ownership Current projects Biogas 21 Landfill

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

The Power Potential Project A guide to participating

The Power Potential Project A guide to participating The Power Potential Project 0 A guide to participating A technical guide to the services for synchronous and non-synchronous DER participants Page 1 of 17 Table of Contents Our vision... 3 1. Introduction...

More information

Small Generator Interconnection Program Interconnection Technical Requirements

Small Generator Interconnection Program Interconnection Technical Requirements General Program Information What is the purpose of the PGE Small Generator Interconnection Program? How do I initiate a distribution interconnection request for my project? The purpose of our Small Generator

More information

Interconnection Process for Generation Systems

Interconnection Process for Generation Systems Interconnection Process for Generation Systems I. INTRODUCTION...1 II. GENERAL INFORMATION...2 A. Definitions...2 B. Nodak Electric Cooperative, Inc. Generation Interconnection Contacts...3 C. Engineering

More information

Q0044 interconnection at

Q0044 interconnection at Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

The North Carolina solar experience: high penetration of utility-scale DER on the distribution system

The North Carolina solar experience: high penetration of utility-scale DER on the distribution system 1 The North Carolina solar experience: high penetration of utility-scale DER on the distribution system John W. Gajda, P.E. Duke Energy IEEE PES Working Group on Distributed Resources Integration 2 High

More information

Greater reliability and flexibility for large solar installations. Conext Core XC-NA series central inverters

Greater reliability and flexibility for large solar installations. Conext Core XC-NA series central inverters Greater reliability and flexibility for large solar installations Conext Core XC-NA series central inverters Conext Core XC-NA central inverters Introducing the Conext Core XC-NA outdoor-rated central

More information

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY Short Circuit Analysis System Operations Department System Planning Section March 2001 I. Introduction XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

More information

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS El Paso Electric Company System Operations Department System Planning

More information

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report

More information

PREPARED DIRECT TESTIMONY

PREPARED DIRECT TESTIMONY Application No.: A.0-04- Exhibit No.: SDG&E-4 Witness: William V. Torre In the Matter of San Diego Gas & Electric Company s Application for Authorization to (1) to Participate in the Steam Generator Replacement

More information

Transmission Switching

Transmission Switching General Application Southern States supplies a wide offering of Transmission Switching solutions in response to an increasing need for improved system reliability and reduced installation times. This range

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

Implementing a Microgrid Using Standard Utility Control Equipment

Implementing a Microgrid Using Standard Utility Control Equipment Implementing a Microgrid Using Standard Utility Control Equipment Tom Fenimore Duke Energy Andy Gould and Larry Wright Schweitzer Engineering Laboratories, Inc. Copyright Duke Energy and SEL 2016 Overview

More information

LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST

LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST Cleco Power LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST OASIS 71956063 0 Rev Issue Date Description of Revision Table of Contents 1. Purpose...3 2. System Impact Study Conclusions...3 2.1 The Pineville

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

North Oregon Coast Area Study. Adam Lint

North Oregon Coast Area Study. Adam Lint North Oregon Coast Area Study Adam Lint PAGE 2 North Oregon Coast System Overview - Clatsop Study Covers: Transmission Switching Stations (Clatsop District): Astoria Lewis and Clark 115 kv Distribution

More information

CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK

CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK 91 CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK CHAPTER CONTENTS: 5.1 INTRODUCTION 5.2 CONDUCTION OF VARIOUS POWER FLOW STUDIES ON THE MODEL 5.3 EXPERIMENTS CONDUCTED FOR VARIOUS POWER FLOW

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

DEMONSTRATION OF ESSENTIAL RELIABILITY SERVICES BY A 300-MW SOLAR PV POWER PLANT

DEMONSTRATION OF ESSENTIAL RELIABILITY SERVICES BY A 300-MW SOLAR PV POWER PLANT DEMONSTRATION OF ESSENTIAL RELIABILITY SERVICES BY A 300-MW SOLAR PV POWER PLANT CONTROL SYSTEM DESIGN FIRST SOLAR PLANT CONTROL SYSTEM ARCHITECTURE Monitor conditions at the POI and compare them with

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

PV Grid Integration Research in the U.S.

PV Grid Integration Research in the U.S. PV Grid Integration Research in the U.S. Barry Mather Ph.D. NREL- Power Systems Engineering Center HEPIA IEA PVPS Task 14 Utility Workshop Geneva, Switzerland March 31 st, 2014 NREL is a national laboratory

More information

PUD ELECTRIC SYSTEM INTERCONNECTION

PUD ELECTRIC SYSTEM INTERCONNECTION APPENDIX A PROCEDURES & REQUIREMENTS for OKANOGAN PUD ELECTRIC SYSTEM INTERCONNECTION Version 4.0 December 2011 Version 4.0 12/28/2011 Page 1 of 15 TABLE OF CONTENTS DEFINITIONS 1.0 Introduction 2.0 Procedures

More information

Training Course on Design, Installation of MW Scale Solar PV Systems & Commissioning concepts

Training Course on Design, Installation of MW Scale Solar PV Systems & Commissioning concepts Training Course on Design, Installation of MW Scale Solar PV Systems & Commissioning concepts Course Description: This course is designed To provide the participants with basic understanding of Solar Photovoltaic

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION In re: Staff's Second Data Request on OUC' s Review of Electric Utility Hurricane Preparedness and Restoration Actions Docket No. 20170215-EU Filed: January

More information

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS June 18, 2015 E2Tech Presentation AGENDA Energy storage as a grid solution high level Specific CEP project examples The technology

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving

More information

Customer Substation Manual

Customer Substation Manual Customer Substation Manual Table of Contents Section Page 2 of 81 Description 0 Preface 010.00 General 010.10 Information Required for the Review of New Customer Substations 010.20 New Customer Substation

More information

Wind Interconnection and Net-Metering in MA. Tim Roughan - National Grid Joe Feraci - NStar

Wind Interconnection and Net-Metering in MA. Tim Roughan - National Grid Joe Feraci - NStar Wind Interconnection and Net-Metering in MA Tim Roughan - National Grid Joe Feraci - NStar Electric Transmission and Distribution System The Electric Power System (EPS) is designed to safely and reliably

More information

Chapter 6 Generator-Voltage System

Chapter 6 Generator-Voltage System Chapter 6 Generator-Voltage System 6-1. General The generator-voltage system described in this chapter includes the leads and associated equipment between the generator terminals and the low-voltage terminals

More information

Sub-Regional RTEP Committee PJM South

Sub-Regional RTEP Committee PJM South Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

The Role of Electricity Storage on the Grid each location requires different requirements

The Role of Electricity Storage on the Grid each location requires different requirements Functional Requirements for Energy on the Utility Grid EPRI Renewable Council Meeting Bill Steeley Senior Project Manager Dan Rastler Program Manager April 5-6, 2011 The Role of Electricity on the Grid

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

MILESTONE SUMMARY REPORT Project funding provided by customers of Xcel Energy through a grant from the Renewable Development Fund

MILESTONE SUMMARY REPORT Project funding provided by customers of Xcel Energy through a grant from the Renewable Development Fund Project Title: Sodium Sulfur Battery Energy Storage Contract Number: RD3-1 Milestone Number: 1 Report Date: May 0, 009 Reporting Period: September 007 April 008 Milestone Description: Milestone 1 - Specifications

More information

American Electric Power s Energy Storage Deployments

American Electric Power s Energy Storage Deployments American Electric Power s Energy Storage Deployments 1 2 American Electric Power : Company Profile The Evolution of the Electric Utility System Before Smart Grid: One-way power flow, simple interactions,

More information

SECTION 1 DESCRIPTION OF THE PROPOSED PROJECT

SECTION 1 DESCRIPTION OF THE PROPOSED PROJECT SECTION 1 DESCRIPTION OF THE PROPOSED PROJECT Supplemental Municipal Consultation Filing The Interstate Reliability Project 1. DESCRIPTION OF THE PROPOSED PROJECT The Connecticut Light and Power Company

More information

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY Table of Contents Chapter 1. Purpose and scope. Pg 3 Chapter 2. Application

More information

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th Alex Bettencourt Managing Director National Association Made Up of Entire Industry Utilities Industry Academia / R&D

More information

EPRI Intelligrid / Smart Grid Demonstration Joint Advisory Meeting March 3, 2010

EPRI Intelligrid / Smart Grid Demonstration Joint Advisory Meeting March 3, 2010 EPRI Intelligrid / Smart Grid Demonstration Joint Advisory Meeting March 3, 2010 Community Energy Storage Presentation & Simulation Results Thomas J. Walker Emeka Okafor 1 Energy Storage Applications in

More information

June Substation Refurbishment and Modernization. Prepared by: Substatiort Refu14bislrment and Modernization NP 2012 CBA

June Substation Refurbishment and Modernization. Prepared by: Substatiort Refu14bislrment and Modernization NP 2012 CBA 2.1 2012 Substatiort Refu14bislrment and Modernization NP 2012 CBA 2012 Substation Refurbishment and Modernization June 2011 Prepared by: Peter Feehan, P.Eng. A FORTIS COMPANY 2.1 2012 Substation Refurbishment

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

PES Cook Islands KEMA Grid Study Final Report

PES Cook Islands KEMA Grid Study Final Report Integrating PV Solar and Wind generation with the TAU electric system Te Aponga Uira O Tumu-Te_Varovaro Contents 1. Executive summary... 2 2. Introduction... 5 2.1 Proposed wind turbine sites... 6 2.2

More information

Guideline on Energy Storage

Guideline on Energy Storage Purpose Commonwealth of Massachusetts Executive Office of Energy and Environmental Affairs DEPARTMENT OF ENERGY RESOURCES SOLAR MASSACHUSETTS RENEWABLE TARGET PROGRAM (225 CMR 20.00) GUIDELINE Guideline

More information

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES: TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design

More information

Supply-Side PV Connections

Supply-Side PV Connections Perspectives on PV Supply-Side PV Connections by John Wiles Plan reviewers and inspectors throughout the country are seeing increasing numbers of supply-side connected utility interactive photovoltaic

More information

Umatilla Electric Cooperative Net Metering Rules

Umatilla Electric Cooperative Net Metering Rules Umatilla Electric Cooperative Net Metering Rules Version: July 2017 Umatilla Electric Cooperative NET METERING RULES Rule 0005 Scope and Applicability of Net Metering Facility Rules (1) Rule 0010 through

More information

3.0 Radial Distribution Systems

3.0 Radial Distribution Systems 3.0 Radial Distribution Systems Radial distribution systems (RDS) are the most common design used by electric utilities, and are the least expensive to plan, construct, and maintain. They generally consist

More information

New Jersey State Report

New Jersey State Report New Jersey State Report July 2017 Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast 2. Markets Capacity Market Results Market Analysis 3. Operations Emissions

More information

Building a 21 st Century Electric Grid. February 23, 2018

Building a 21 st Century Electric Grid. February 23, 2018 Building a 21 st Century Electric Grid February 23, 2018 1 DTE strives to provide customers with a 21 st century electric grid that is safe, highly reliable, affordable and accessible 2 Our investment

More information