Re: Comments on the 12/7/09 Dynamic Transfer Stakeholder Meeting

Size: px
Start display at page:

Download "Re: Comments on the 12/7/09 Dynamic Transfer Stakeholder Meeting"

Transcription

1 Joseph H. Rowley Vice President Project Development 101 Ash Street, HQ14A San Diego, CA Tel: Fax: December 15, 2009 Ms. Anjali Sheffrin Mr. Kyle Hoffman Mr. Clyde Loutan Mr. Jim Price California Independent System Operator 151 Blue Ravine Road Folsom, CA Re: Comments on the 12/7/09 Dynamic Transfer Stakeholder Meeting Sempra Generation appreciates this opportunity to provide follow up comments on the Dynamic Transfer Stakeholder Meeting held by the CAISO on December 7, Threshold Fairness Test Providing non-discriminatory access to transmission is a primary mission of the CAISO, and fulfilling this mission is primary objective of the CAISO Tariff, information systems, and grid operations. With that in mind, any proposed concept for implementing dynamic transfers must be able to pass the following threshold fairness test, which poses the simplest possible scenario: Generator A is directly connected to a bus that is also a CAISO intertie. Lines that are part of the CAISO-controlled grid are connected to the same bus, but the bus itself is in a neighboring balancing authority area. As a result, there are no intervening transmission facilities between Generator A and the CAISO-controlled grid, other than the intertie bus itself. Generator B is connected to a hypothetical, CAISO-controlled bus that is (electrically speaking) an insignificant distance away from the intertie bus. In testing any proposed concept for implementing a dynamic transfer of Generator A into the CAISO balancing authority area, will Generator A have materially the same access (both physically and economically) to transmission as Generator B? If the answer is yes, then certainly there are other criteria that should be considered before adopting the concept being tested. However, if the answer is no, the concept should be rejected without further consideration. Otherwise, Generator A would be incentivized to make an interconnection request to the CAISO that would compel actual construction of the hypothetical second bus. A concept that results in the proliferation of nearby, otherwise unnecessary highvoltage buses is clearly not in the interest of either generators or end users. Sempra Generation is not the same company as the utility, SDG&E or SoCalGas, and the California Public Utilities Commission does not regulate the terms of Sempra Generation s products and services.

2 Dynamic Transfer Stakeholder Comments December 15, 2009 Mesquite Solar The threshold fairness test described above is not merely a construct that is useful for screening proposed concepts for implementation of dynamic transfers. In fact, this scenario is exactly the circumstance presented by the Mesquite Solar project. Mesquite Solar is a 500 MW photovoltaic project that will be directly connected to the Palo Verde Hub. Located in the SRP balancing authority area, the Palo Verde Hub is comprised of the 500 kv Palo Verde bus, the nearby 500 kv Hassayampa bus, and three bus ties. Two CAISO-controlled 500 kv lines are also connected to the Palo Verde Hub, these being Palo Verde-Devers and the Southwest Powerlink. Both of these CAISO-controlled lines pass close by the six square mile Mesquite Solar site owned by Sempra Generation, which is situated in between the two lines a short distance west of the Palo Verde Hub as shown on Figure 1. Interconnection of Mesquite Solar with either Palo Verde-Devers or the Southwest Powerlink would have required construction of a new 500 kv switchyard a short distance from the Palo Verde Hub. Given the close proximity of the Palo Verde Hub, and the fact that the Hassayampa Switchyard was constructed in 2002 expressly for the purpose of providing a point of interconnection for new generators in the vicinity as well as new 500 kv lines, it made no sense for the Mesquite Solar project to request the construction of yet another 500 kv switchyard in the immediate vicinity. Accordingly, on May 14, 2007, Sempra Generation submitted a request for interconnection to the Hassayampa Switchyard (which forms part of the Palo Verde Hub). As stated in the attached letter dated November 9, 2009, Mesquite Solar has received final approval of its interconnection request, as well as authorization to proceed to an interconnection agreement, from the ANPP High Voltage Switchyard Engineering & Operating Committee (often referred to as the Palo Verde E&O Committee). The approval was unanimous and included Southern California Edison, Arizona Public Service, Salt River Project, El Paso Electric, Public Service of New Mexico, Southern California Public Power Authority, and Los Angeles Department of Water and Power. With its interconnection already approved and its final permitting approval anticipated on January 13, the Mesquite Solar project will move forward with procurement and construction as soon as power purchase arrangements are in place. However, in order to sell to California investor-owned utilities, a dynamic transfer of Mesquite Solar to the CAISO balancing authority area is necessary. Participation in PIRP Once a pseudo-tie is implemented, there is no practical difference between a generator situated as is Mesquite Solar and a generator that is located elsewhere within the CAISO balancing authority area. Especially in the post-mrtu environment that now exists, issues such as congestion management and energy balancing must be handled in a consistent manner across the 3,000+ buses, including intertie buses, included in the CAISO s Full Network Model. Likewise, the CAISO-controlled line segments connected to the Palo Verde Hub must be handled in a consistent manner with the multitude of other CAISO-controlled line segments. Accordingly, if PIRP is available to any solar project in the CAISO balancing authority area, it must also be available to Mesquite Solar.

3 Dynamic Transfer Stakeholder Comments December 15, 2009 Dynamic Transfer of a Portion of a Project Sempra Generation believes that the most straightforward way to implement the dynamic transfer of a portion of a project is to physically segregate and separately meter that portion of the project. As renewable energy projects require long term power purchase agreements in order to be economically viable, and as such agreements normally correspond to specific generation facilities, such segregation and separate metering is generally feasible and is a practical and simple approach to accomplishing the transfer. Once a generator has been dynamically transferred into the CAISO, the short term export of a portion of the generator s output to a neighboring balancing authority area should be handled in the same manner as the export of any other such energy (i.e., energy that originates inside the CAISO balancing authority area but does not flow across CAISO-controlled transmission facilities). For such exports, the Wheeling Access Charge (i.e., the charge based on the revenue requirements of CAISO-controlled transmission facilities) should not apply. Response to Dispatch Instructions from the CAISO By their nature, renewable energy projects, including Sempra Generation s photovoltaic projects, normally produce the maximum output achievable under any given operating conditions. As a result, renewable energy projects are generally not able to respond to dispatch instructions for increased output. While response to a dispatch instruction for reduced output is possible, such an instruction should be given only for the purpose of preserving grid reliability. Restricting downward dispatch instructions is important for both economic and societal reasons. Renewable energy projects generally have zero or near-zero variable costs, so such projects should be the last generators considered when the CAISO selects units for downward dispatch in order to preserve grid reliability. Because such projects create Renewable Energy Credits (RECs) only when energy is generated, power purchasers would not receive RECs for energy that would have been generated if not for downward dispatch instructions. Furthermore, the selection of fossil fuel units for downward dispatch reduces air emissions and conserves non-renewable resources, whereas the selection of renewable energy units for downward dispatch would waste the capacity that has been constructed expressly for the purpose of meeting environmental objectives. Many, if not most renewable energy projects, including Sempra Generation s photovoltaic projects, do not have the ability to ramp down in a continuous, governor-controlled manner. However Sempra Generation s projects will have the ability to provide instantaneous output reductions in multiple controlled steps. Our projects are designed with multiple, medium voltage (e.g., 34.5 kv) collection circuits of up to 30 MW each, and each circuit is provided with a remotely-controllable breaker. Accordingly, output reductions needed to preserve grid reliability can be provided quickly by opening these breakers in succession. Conclusion We offer these comments as practical approaches for quickly resolving key issues involved in dynamic transfers. We look forward to continued participation in the stakeholder process, and an outcome that will support construction and initial operation of Mesquite Solar in While this letter is focused on key issues discussed at the December 7 Stakeholder Meeting, Sempra

4 Dynamic Transfer Stakeholder Comments December 15, 2009 Generation will separately submit a response to certain matters addressed in the CAISO Issue Paper dated November 30, Sincerely, Joseph H. Rowley

5 Figure 1: Palo Verde Hub, Mesquite Solar, and CAISO-Controlled Lines Palo Verde Nuclear Generating Station PVNGS Palo Westwing Westwing Rudd Palo Verde Devers (CAISO) Verde Palo Verde Harquehala Bus Tie #3 Bus Tie #2 Bus Tie #1 Hub Arlington Valley Energy Facility Mesquite Generating Station Mesquite Solar Generation-tie Southwest Powerlink (CAISO) Palo Verde Jojoba

6 SALT RIVER PROJECT GARY W. HARPER P 0 Box POB009 MANAGER Phoenm, Arizona SYSTEM OPERATIONS (602) Fax (602) gary harper@srpnet com November 9, 2009 Mr. Joseph H. Rowley Vice President Sempra Generation 101 Ash Street, HQ14A San Diego, CA RE: APPROVAL OF TWO INTERCONNECTIONS Dear Mr. Rowley: I am pleased to inform you that the ANPP High Voltage Switchyard Engineering and Operating Committee ("ANPP E&O") has unanimously approved the two pending interconnection requests from Sempra. The ANPP Legal and Negotiating Committee ("ANPP L&N") will work with you to develop appropriate agreements for both the new second 500 kv tie-line between the existing Mesquite Switchyard and the Hassayampa Switchyard and the new photo voltaic ("PV") solar facility that will interconnect into the Mesquite Switchyard. Please contact the ANPP L&N Chair Margaret Rostker at or Marqaret.Rostker(5jsrpnet,com for additional information. On behalf of the ANPP participants we appreciate your interconnection requests and look forward to the two new interconnections in the near future. Sincerely, Gary W. Harper Chair, ANPP ANPP HVS E&O Committee xc: Margaret Rostker, ANPP LSN Committee Chair

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Q51 Generation Interconnection

Q51 Generation Interconnection Q51 Generation Facilities Study Results APS Contract No. 52395 By Arizona Public Service Company Transmission Planning September 4, 2013 [Version 1.0] Q51 FACILITIES STUDY TABLE OF CONTENTS Contents 1.

More information

Four Corners Queue Transmission Interconnection Study

Four Corners Queue Transmission Interconnection Study Four Corners Queue Transmission Interconnection Study Facility Study Results By Arizona Public Service Company Transmission Planning & Interconnection Development March 22, 2016 Version 1 FACILITIES STUDY

More information

March 7, Subject: Southern California Edison 2011 Annual Progress Report

March 7, Subject: Southern California Edison 2011 Annual Progress Report March 7, 2011 Mr. Kyle Kohne Mr. Kent Bolton Chair, WECC Technical Studies Subcommittee WECC Technical Staff Bonneville Power Administration University of Utah Research Park P.O. Box 61409 615 Arapeen

More information

Arizona Energy Consortium Conference

Arizona Energy Consortium Conference SunZia Southwest Transmission Project SunZia and Potential Impacts of Regionalization Arizona Energy Consortium Conference SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 2018 0 SunZia: 500kV Project delivering

More information

Arizona Transmission Challenges

Arizona Transmission Challenges Power Task Force Agenda Number 2. Arizona Transmission Challenges Central Arizona Water Conservation District Power Committee Presentation May 18, 2017 Transmission Planning Efforts NATIONAL Section 368

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of San Diego Gas & Electric Company (U902E) for Authority to Implement Optional Pilot Program to Increase Customer Access to

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market

Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market Beacon Power Corporation Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market Prepared for: New York Business Issues Committee May 21, 2008 Safe Harbor

More information

Docket No. ER June 2018 Informational Report Energy Imbalance Market Transition Period Report Idaho Power Company

Docket No. ER June 2018 Informational Report Energy Imbalance Market Transition Period Report Idaho Power Company California Independent System Operator Corporation August 21, 2018 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Southern California Edison Company (U338E) for Approval of the Results of Its 2013 Local Capacity Requirements Request for

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Exhibit No.: Commissioner: Loretta Lynch Administrative Law Judge: Meg Gottstein Witness: BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Investigation into ) implementation

More information

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report San Diego Gas & Electric, a Sempra Energy Utility SDGE HVDC Phase 1 Project No. 101512 Revision 01 11/29/2018 SDG&E High

More information

for DRECP Alternatives

for DRECP Alternatives Transmission Technical Group Conceptual Transmission Plan for DRECP Alternatives DRECP WebEx Meeting January 9, 2013 Overview Purpose, Participants, and Timeline Generation Assumptions Transmission Assumptions

More information

Essential Reliability Services From PV Plants

Essential Reliability Services From PV Plants Essential Reliability Services From PV Plants Mahesh Morjaria, Ph. D. VP, PV Systems Enabling a world powered by reliable, affordable solar electricity. Utility-Scale PV Plants Support Grid Stability &

More information

October 17, Please contact the undersigned directly with any questions or concerns regarding the foregoing.

October 17, Please contact the undersigned directly with any questions or concerns regarding the foregoing. California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 October 17, 2017 Re: California

More information

PREPARED REBUTTAL TESTIMONY OF BETH MUSICH SOUTHERN CALIFORNIA GAS COMPANY AND SAN DIEGO GAS & ELECTRIC COMPANY

PREPARED REBUTTAL TESTIMONY OF BETH MUSICH SOUTHERN CALIFORNIA GAS COMPANY AND SAN DIEGO GAS & ELECTRIC COMPANY Application No: A.14-06-021 Exhibit No.: Witness: Beth Musich Application of Southern California Gas Company (U 904 G) and San Diego Gas & Electric Company (U 902 G) for Low Operational Flow Order and

More information

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS July 15, 2004 TABLE OF CONTENTS Page No. 1. Description of Pasadena s Transmission Lines and Facilities...1 A. Overview:... 1 B.

More information

The Solar Zone at the UA Tech Park Phase II Expansion

The Solar Zone at the UA Tech Park Phase II Expansion The Solar Zone at the UA Tech Park Phase II Expansion Request for Proposals: Solicitation for Advanced Technology Demonstration Projects in the Area of Solar Energy Generation and/or Energy Storage The

More information

MCE SPECIAL MEETING Friday, September 28, :00 A.M. Agenda Page 1 of 2

MCE SPECIAL MEETING Friday, September 28, :00 A.M. Agenda Page 1 of 2 MCE SPECIAL MEETING Friday, September 28, 2018 9:00 A.M. City of Richmond Memorial Auditorium 403 Civic Center Plaza, Richmond, CA Agenda Page 1 of 2 New Board Member Meet and Greet (8:30-9:00) Swearing

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. California Independent System ) ER Operator Corporation ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. California Independent System ) ER Operator Corporation ) ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ER0- -000 ) ) DIRECT TESTIMONY OF DEBORAH A. LE VINE ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION Page

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Reforming the TAC and Retail Transmission Rates. Robert Levin California Public Utilities Commission Energy Division August 29, 2017

Reforming the TAC and Retail Transmission Rates. Robert Levin California Public Utilities Commission Energy Division August 29, 2017 Reforming the TAC and Retail Transmission Rates. Robert Levin California Public Utilities Commission Energy Division August 29, 2017 1 CPUC Staff Rate Design Proposals Restructure the High-Voltage TAC

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION The Nevada Hydro Company, Inc. Docket No. EL18-131-000 SOUTHERN CALIFORNIA EDISON COMPANY'S COMMENTS AND PROTEST TO THE NEVADA HYDRO

More information

Updates. Pat Reiten President and CEO, PacifiCorp Transmission

Updates. Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission and Regional Updates Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission Overview 16,400 circuit-miles of transmission lines 12,685 MW record peak demand

More information

2015 Grid of the Future Symposium

2015 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,

More information

Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014

Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014 Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014 The Clean Coalition recommends that state regulators and utilities account for potential

More information

Utility Solar Business Models

Utility Solar Business Models Utility Solar Business Models February 16, 2009 Julia Hamm SEPA Executive Director Outline About SEPA Historical Utility Solar Engagement Utility Solar Business Models What s a utility solar business model?

More information

HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY BOARD

HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY BOARD SCHEDULED ITEM TO: FROM: HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY BOARD GEORGE F. MORROW, DIRECTOR OF UTILITIES DATE: JANUARY 28, 2013 SUBJECT: APPROVAL OF POWER SALES AGREEMENT ( PSA ) WITH

More information

best to you all Gail Carbiener Page 1 of 5

best to you all Gail Carbiener Page 1 of 5 Please accept this attachment as my up dated response to the B2H DEIS. If this is not acceptable, please let me know. Nice meeting last Monday in Boardman. 300316 best to you all Gail Carbiener 2 Page

More information

February 13, Docket No. ER ; ER Response to Request for Additional Information

February 13, Docket No. ER ; ER Response to Request for Additional Information California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent System

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Salt River Project Agricultural ) Improvement and Sacramento ) Municipal Utility District ) ) Docket No. EL01-37-000 v. ) ) California

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Essential Reliability Services and the ) Evolving Bulk-Power System ) Docket No. RM16-6-000 Primary Frequency Response ) COMMENTS

More information

Frequently Asked Questions New Tagging Requirements

Frequently Asked Questions New Tagging Requirements Frequently Asked Questions New Tagging Requirements Q: Are there new E-tagging requirements related to the new fifteen minute market FERC Order No. 764 fifteen minute scheduling implemented on May 1, 2014?

More information

Grid Operations and the Increasing Challenges of Balancing Renewable Energy ALBUQUERQUE QUALITY NETWORK

Grid Operations and the Increasing Challenges of Balancing Renewable Energy ALBUQUERQUE QUALITY NETWORK Grid Operations and the Increasing Challenges of Balancing Renewable Energy JANUARY 18 ALBUQUERQUE QUALITY NETWORK JANUARY 18, 2018 AGENDA Overview and History of PNM Grid Operation Challenges Generation

More information

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy ENERGY STRATEGY FOR YUKON Independent Power Production Policy May 20, 2014 Page 2 of 11 BACKGROUND The Government of Yukon released the Energy Strategy for Yukon in January 2009. The strategy sets out

More information

Re: California Independent System Operator Corporation

Re: California Independent System Operator Corporation California Independent System Operator October 21, 2014 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent

More information

LANCASTER CHOICE ENERGY S BIENNIAL ENERGY STORAGE PROCUREMENT COMPLIANCE REPORT

LANCASTER CHOICE ENERGY S BIENNIAL ENERGY STORAGE PROCUREMENT COMPLIANCE REPORT January 1, 2016 CA Public Utilities Commission Energy Division Attention: Tariff Unit 505 Van Ness Avenue, 4thFloor San Francisco, CA 94102-3298 Advice Letter LCE 001-E RE: LANCASTER CHOICE ENERGY S BIENNIAL

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of San Diego Gas & Electric Company (U902E) for Authority to Implement Optional Pilot Program to Increase Customer Access to

More information

SunZia Southwest Transmission Project

SunZia Southwest Transmission Project SunZia Southwest Transmission Project SunZia Project Update for the 9 th Annual Transmission Summit West October 13, 2017 SUNZIA SOUTHWEST TRANSMISSION PROJECT OCTOBER 13, 2017 0 SouthWestern Power Group

More information

BC Hydro writes in compliance with Exhibit A-4 to provide its Final Submission in respect of the Application (Exhibit B-1).

BC Hydro writes in compliance with Exhibit A-4 to provide its Final Submission in respect of the Application (Exhibit B-1). Ken Duke Solicitor & Counsel Phone: 604-623-3623 Fax: 604-623-3606 bchydroregulatorygroup@bchydro.com April 30, 2014 Sixth Floor 900 Howe Street Vancouver, BC V6Z 2N3 Dear Ms. Hamilton: RE: (BCUC) British

More information

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station East Asian Alternative Energy Futures Workshop By the Nonproliferation Policy Education Center

More information

December 4, Docket: ER Energy Imbalance Market Special Report Transition Period July 2018 for Idaho Power Company

December 4, Docket: ER Energy Imbalance Market Special Report Transition Period July 2018 for Idaho Power Company California Independent System Operator Corporation December 4, 2018 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

The Gambia National Forum on

The Gambia National Forum on The Gambia National Forum on Renewable Energy Regulation Kairaba Hotel, The Gambia January 31 February 1, 2012 Tariff and Price Regulation of Renewables Deborah Erwin Public Service Commission of Wisconsin

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

APS and Regional Transmission Systems Overview

APS and Regional Transmission Systems Overview APS and Regional Transmission Systems Overview Bob Smith Director Energy Delivery Asset Management and Planning Agenda About APS Regional Transmission System Overview APS Transmission System Overview Industry

More information

SunZia Southwest Transmission Project

SunZia Southwest Transmission Project SunZia Southwest Transmission Project SunZia Project Update for the Southern Arizona Economic Development Group September 12, 2017 SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 0 SouthWestern

More information

REGIONAL TRANSMISSION ORGANIZATIONS / INDEPENDENT SYSTEM OPERATORS AND THE ENERGY IMBALANCE MARKET: AN OVERVIEW OF THE PICTURE IN THE WEST

REGIONAL TRANSMISSION ORGANIZATIONS / INDEPENDENT SYSTEM OPERATORS AND THE ENERGY IMBALANCE MARKET: AN OVERVIEW OF THE PICTURE IN THE WEST REGIONAL TRANSMISSION ORGANIZATIONS / INDEPENDENT SYSTEM OPERATORS AND THE ENERGY IMBALANCE MARKET: AN OVERVIEW OF THE PICTURE IN THE WEST MEGAN O REILLY COALITION FOR CLEAN AFFORDABLE ENERGY EPE IRP STAKEHOLDER

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) Southwest Power Pool, Inc. ) Docket No. ER ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) Southwest Power Pool, Inc. ) Docket No. ER ) ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Southwest Power Pool, Inc. ) Docket No. ER13-1748 ) ) MOTION TO INTERVENE AND COMMENTS OF THE ELECTRICITY STORAGE ASSOCIATION

More information

February 10, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

February 10, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation February 10, 2016 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

August 15, Please contact the undersigned directly with any questions or concerns regarding the foregoing.

August 15, Please contact the undersigned directly with any questions or concerns regarding the foregoing. California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 August 15, 2017 Re: California

More information

Overview of ISO New England and the New England Wholesale Power Markets

Overview of ISO New England and the New England Wholesale Power Markets Overview of ISO New England and the New England Wholesale Power Markets Boston Chapter of IEEE PES Technical Meeting June 15, 2010 Stephen J. Rourke Vice President, System Planning About ISO New England

More information

3.0 Radial Distribution Systems

3.0 Radial Distribution Systems 3.0 Radial Distribution Systems Radial distribution systems (RDS) are the most common design used by electric utilities, and are the least expensive to plan, construct, and maintain. They generally consist

More information

January 18, Docket: ER Energy Imbalance Market Special Report Transition Period September 2018 for Idaho Power Company

January 18, Docket: ER Energy Imbalance Market Special Report Transition Period September 2018 for Idaho Power Company California Independent System Operator Corporation January 18, 2019 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

Solar-Wind Specific Request for Proposals

Solar-Wind Specific Request for Proposals Program Description Solar-Wind Specific Request for Proposals Power Production from Green Resources in North Carolina 04/19/2006 NC GreenPower (NCGP) is a statewide program designed to improve the quality

More information

California Independent System Operator. Memorandum

California Independent System Operator. Memorandum California Independent System Operator Memorandum To: ISO Board of Governors From: Armie Perez, Vice President of Planning and Infrastructure Development Date: Re: Decision on Tehachapi Project This memorandum

More information

January 18, Docket: ER Energy Imbalance Market Special Report Transition Period August 2018 for Idaho Power Company

January 18, Docket: ER Energy Imbalance Market Special Report Transition Period August 2018 for Idaho Power Company California Independent System Operator Corporation January 18, 2019 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

APPENDIX F: Project Need and Description

APPENDIX F: Project Need and Description APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was

More information

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily 5.8 TRAFFIC, ACCESS, AND CIRCULATION This section describes existing traffic conditions in the project area; summarizes applicable regulations; and analyzes the potential traffic, access, and circulation

More information

WestConnect Regional Planning Update

WestConnect Regional Planning Update WestConnect Regional Planning Update WRP Energy Committee May 4, 2015 Webinar Outline WestConnect Overview Membership, Structure & Footprint Planning process and regulatory status Order 890 Update (2014)

More information

SCE Smart Grid. Creating a Cleaner, Smarter Energy Future. Metering, Billing / MDM America Conference. San Diego. March 9, 2010

SCE Smart Grid. Creating a Cleaner, Smarter Energy Future. Metering, Billing / MDM America Conference. San Diego. March 9, 2010 SCE Smart Grid Creating a Cleaner, Smarter Energy Future Metering, Billing / MDM America Conference San Diego March 9, 2010 SOUTHERN CALIFORNIA EDISON Southern California Edison An Edison International

More information

FERC NOPR on Integrating Renewable Energy Resources into the Transmission Grid

FERC NOPR on Integrating Renewable Energy Resources into the Transmission Grid FERC NOPR on Integrating Renewable Energy Resources into the Transmission Grid Presented by: February 17, 2011 Floyd L. Norton, IV (202) 739-5620 fnorton@morganlewis.com Joseph C. Hall (202) 739-5236 jchall@morganlewis.com

More information

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool WIRES University Overview of ISO/RTOs Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool 1 OUR MISSION Helping our members work together to keep the lights on

More information

To: Honorable Public Utilities Board Submitted by: /s/ Rebecca Irwin AGM-Customer Resources. From: Kelly Birdwell Brezovec Approved by: /s/

To: Honorable Public Utilities Board Submitted by: /s/ Rebecca Irwin AGM-Customer Resources. From: Kelly Birdwell Brezovec Approved by: /s/ AGENDA ITEM NO.: 5.A.1 MEETING DATE: 10/16/2017 ADMINISTRATIVE REPORT NO.: 2018-15 To: Honorable Public Utilities Board Submitted by: /s/ Rebecca Irwin AGM-Customer Resources From: Kelly Birdwell Brezovec

More information

Eric Johnson, Director, External Affairs, ISO New England

Eric Johnson, Director, External Affairs, ISO New England To: From: NECPUC and NESCOE Eric Johnson, Director, External Affairs, ISO New England Date: January 22, 2016 Subject: How Energy Storage Can Participate in New England s Wholesale Electricity Markets Interest

More information

INTRODUCTION. June 15, Mark D. Marini, Secretary Massachusetts Department of Public Utilities One South Station Boston, MA 02110

INTRODUCTION. June 15, Mark D. Marini, Secretary Massachusetts Department of Public Utilities One South Station Boston, MA 02110 June 15, 2016 Mark D. Marini, Secretary Massachusetts Department of Public Utilities One South Station Boston, MA 02110 Re: D.P.U. 16-64 Investigation of the Department of Public Utilities, on its own

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JULY 2015) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

Decision on the ISO Transmission Plan

Decision on the ISO Transmission Plan Decision on the 2013-2014 ISO Transmission Plan Neil Millar Executive Director, Infrastructure Development Board of Governors Meeting General Session March 19-20, 2014 Approving the plan means approving

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Generation Interconnection Facilities Study For

Generation Interconnection Facilities Study For Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...

More information

To: Honorable Public Utilities Board Submitted by: /s/ Barry Leska AGM Energy Resource Planning. From: Alan Hanger Approved by: /s/

To: Honorable Public Utilities Board Submitted by: /s/ Barry Leska AGM Energy Resource Planning. From: Alan Hanger Approved by: /s/ AGENDA ITEM NO.: 4.J.1 To: Honorable Public Utilities Board Submitted by: /s/ Barry Leska AGM Energy Resource Planning From: Alan Hanger Approved by: /s/ Senior Energy Resource Analyst Glenn O. Steiger

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking on the Commission s own motion to improve distribution level interconnection rules and regulations for certain

More information

Operational Opportunities to Minimize Renewables Curtailments

Operational Opportunities to Minimize Renewables Curtailments Operational Opportunities to Minimize Renewables Curtailments Clyde Loutan Principal, Renewable Energy Integration July 24, 2017 2017 CAISO - Public Page 1 Agenda Background Real-time control performance

More information

Guideline on Energy Storage

Guideline on Energy Storage Purpose Commonwealth of Massachusetts Executive Office of Energy and Environmental Affairs DEPARTMENT OF ENERGY RESOURCES SOLAR MASSACHUSETTS RENEWABLE TARGET PROGRAM (225 CMR 20.00) GUIDELINE Guideline

More information

Table of Contents. Purpose. Eldorado Intertie and System (Eldorado- Moenkopi) Scheduling at Willow Beach. Operating Procedure

Table of Contents. Purpose. Eldorado Intertie and System (Eldorado- Moenkopi) Scheduling at Willow Beach. Operating Procedure No. 6930 Table of Contents Purpose... 1 1. Limits, Ratings, & Effectiveness Factors... 2 2. Contingency Operations... 2 2.1 Transmission Lines Outages... 2 2.2 APS Terminal Equipment Outages... 2 2.3 SCE

More information

Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications

Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications 1. Who is a self-generation or Net Metering Member? This is a Member who has installed grid-connected renewable generation, such

More information

Q137 Generation Interconnection

Q137 Generation Interconnection Q137 Generation Interconnection Interconnection Facilities Study Results APS Contract No. 52675 By Arizona Public Service Company Transmission Planning July 28, 2014 Q137 FACILITIES STUDY - TECHNICAL REVIEW

More information

Welcome to the November 22, 2005 DRCC Webinar. Guidelines and Instructions

Welcome to the November 22, 2005 DRCC Webinar. Guidelines and Instructions Welcome to the November 22, 2005 DRCC Webinar Guidelines and Instructions If you have not already done so, please dial in to the number provided for the audio. You will initially be in a waiting room.

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

Southern California Edison

Southern California Edison Recent Energy Storage Projects November 8, 2017 Presented by Kern Economic Development Corporation 1 Agenda 1. California Energy Trends and Recent Events 2. SCE s Storage Projects California Energy Trends

More information

Los Angeles. June 17, The Honorable City Council c/o Office of the City Clerk Room 395, City Hall Mail Stop 160

Los Angeles. June 17, The Honorable City Council c/o Office of the City Clerk Room 395, City Hall Mail Stop 160 Los Angeles LA w Department of Water & Power ERIC GARCETTI Mayor Commission MEL LEVINE, President WILLIAM W. FUNDERBURK JR., Vice President JILL BANKS BARAD MICHAEL F. FLEMING CHRISTINA E. NOONAN BARBARA

More information

Yukon s Independent Power Production Policy

Yukon s Independent Power Production Policy Yukon s Independent Power Production Policy Updated October 2018 BACKGROUND The Government of Yukon (YG) released the Energy Strategy for Yukon in January 2009. The strategy sets out YG s energy priorities,

More information

Feed-In Tariffs Presentation to the Nevada Production and Use of Energy Committee

Feed-In Tariffs Presentation to the Nevada Production and Use of Energy Committee Feed-In Tariffs Presentation to the Nevada Production and Use of Energy Committee November 3, 2009 Sara Birmingham Director of Western Policy The Solar Alliance -1- Who We Are An Alliance of PV manufacturers,

More information

The Value of Energy Storage. Dr. Ralph Romero Steven Rupp

The Value of Energy Storage. Dr. Ralph Romero Steven Rupp The Value of Energy Storage Dr. Ralph Romero Steven Rupp Solving the World s Complex Challenges in These Markets Energy Water Telecommunications Indonesia Hong Kong SAR California, USA Security Management

More information

Considerations for Municipal Solar Projects. Ben Frevert Larsen Engineers November 16, 2016

Considerations for Municipal Solar Projects. Ben Frevert Larsen Engineers November 16, 2016 Considerations for Municipal Solar Projects Ben Frevert Larsen Engineers November 16, 2016 Topic Areas Benefits of going green / solar Actions local governments can take Programs and incentives Implementation

More information

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1 Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide Version 1.1 October 21, 2016 1 Table of Contents: A. Application Processing Pages 3-4 B. Operational Modes Associated

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JULY 2014) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

California Energy Storage Policies. Carla Peterman Commissioner, California Public Utilities Commission December 2016

California Energy Storage Policies. Carla Peterman Commissioner, California Public Utilities Commission December 2016 California Energy Storage Policies Carla Peterman Commissioner, California Public Utilities Commission December 2016 California Storage Law and Policy l California has supported energy storage through

More information

Department of Market Quality and Renewable Integration November 2016

Department of Market Quality and Renewable Integration November 2016 Energy Imbalance Market March 23 June 3, 216 Available Balancing Capacity Report November 1, 216 California ISO Department of Market Quality and Renewable Integration California ISO i TABLE OF CONTENTS

More information

Overview of APS U.S.-JORDAN ELECTRIC POWER TRANSMISSION PARTNERSHIP EXECUTIVE EXCHANGE VISIT. Bob Smith

Overview of APS U.S.-JORDAN ELECTRIC POWER TRANSMISSION PARTNERSHIP EXECUTIVE EXCHANGE VISIT. Bob Smith Overview of APS U.S.-JORDAN ELECTRIC POWER TRANSMISSION PARTNERSHIP EXECUTIVE EXCHANGE VISIT Bob Smith Director Energy Delivery Asset Management and Planning Agenda About APS Regional Transmission System

More information

Flexible Ramping Product Technical Workshop

Flexible Ramping Product Technical Workshop Flexible Ramping Product Technical Workshop September 18, 2012 Lin Xu, Ph.D. Senior Market Development Engineer Don Tretheway Senior Market Design and Policy Specialist Agenda Time Topic Presenter 10:00

More information

September 9, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E., Room 1A Washington, DC 20426

September 9, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E., Room 1A Washington, DC 20426 Mark D. Patrizio Attorney at Law 77 Beale Street, B30A San Francisco, CA 94105 Mailing Address P.O. Box 7442 San Francisco, CA 94120 (415) 973.6344 Fax: (415) 973.5520 E-Mail: MDP5@pge.com September 9,

More information

Reactive Power Requirements and Financial Compensation. Addendum to Draft Final Proposal

Reactive Power Requirements and Financial Compensation. Addendum to Draft Final Proposal Reactive Power Requirements and Financial Compensation July 21, 2016 Table of Contents 1. Introduction... 3 2. Changes to Proposal... 4 3. Plan for Stakeholder Engagement... 4 4.... 4 6. Next Steps...

More information

Demand Charges to Deal With Net Energy Metering: Key Considerations

Demand Charges to Deal With Net Energy Metering: Key Considerations Demand Charges to Deal With Net Energy Metering: Key Considerations Amparo Nieto Vice President Presented at EUCI Residential Demand Charges Symposium Calgary, Canada December 1, 2015 Key Rate Design Principles

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ISO New England Inc. ) Docket No. ER12-1643-001 Order No. 755 Compliance Filing ) ) MOTION TO ACCEPT COMMENTS FILED OUT OF TIME

More information