Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Size: px
Start display at page:

Download "Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY"

Transcription

1 California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re: Otay Mesa Power Purchase Agreement Transmission Project This memorandum requires Board action. EXECUTIVE SUMMARY This memorandum requests ISO Governing Board approval of the Otay Mesa Power Purchase Agreement Transmission Project (Project). The Project is a combination of new line construction and modifications to existing lines and substations that will result in the creation of two new 230 kv transmission lines in the San Diego area (see Figure 1). One of the new lines would go from Otay Mesa Substation to Sycamore Canyon Substation (37 miles total length - 28 miles of new line construction). The other transmission line would go from Otay Mesa Substation to Old Town Substation (33 miles total length - 24 miles of new line construction). The completion of the Miguel Sycamore Canyon 230 kv transmission line is proposed to be completed by June The completion of the Otay Mesa-Old Town 230 kv transmission line is proposed to be completed by June The Project is needed to reliably deliver power from the Otay Mesa Power Plant to San Diego customers. Without this project, congestion north of Miguel Substation would lead to the need to curtail Otay Mesa output during high load periods when the generation is most needed. The estimated capital cost of the Project is $ 209 million. Since the Project cost exceeds $20 million, ISO Board approval is required. The OMGP is needed to satisfy SDG&E s resource adequacy requirements. In its decision D , the California Public Utility Commission (CPUC) approved, among other items, SDG&E s request to enter into a ten-year power purchase agreement for the output of the Otay Mesa Generation Project, which is presently under development by Calpine Corporation. However, the Commission recognized that the output of Otay Mesa is not fully deliverable, and cannot fully satisfy SDG&E s local reliability needs, without some transmission system upgrades. The proposed Project is the preferred alternative for reliably delivering Otay Mesa generation to San Diego. Normally, the ISO reviews and approves projects before they are presented to the CPUC, however SDG&E has already applied to the CPUC for a Certificate of Public Convenience and Necessity (CPCN) for the proposed project. To date, there has not been a CPUC decision on this matter.

2 Fig. 1. Otay Mesa Power Purchase Agreement Transmission Project Map Existing transmission lines Proposed Project Project s alternative rejected due to higher cost and environmental impact Substation Power Plant AJP 4/25/05-2-

3 BACKGROUND In October of 2002, the CPUC directed SDG&E and the other utilities under their jurisdiction to file longterm procurement plans addressing power capacity needs for the years 2004 through In May of 2003, SDG&E issued a Request for Proposals (RFP) for reliability capacity for the procurement plan. Additional in-system generation was needed to provide for load growth and to reduce Reliability-Must-Run generation costs. In response to this RFP, in August 2003, Calpine submitted a proposal to provide generation capacity and energy from the OMGP. At that time, the Otay Mesa project was already fully permitted by the California Energy Commission (CEC) and Calpine had procured all the major equipment and started construction. In June 2004, after review of all the projects submitted for the RFP, the CPUC issued a decision (D ) to approve new electric resource contracts for five proposals for new resources for San Diego. The Otay Mesa Generation Project was one of the approved proposals. However, the engineering studies indicated that the OMGP would cause significant congestion on the transmission system north of Miguel Substation if additional transmission system upgrades were not implemented. When the CAISO first approved the OMGP in May 2003, the approval letter specified that extensive congestion management would be required and that the full generation output cannot be delivered if the transmission system is not upgraded. After the Power Purchase Agreement for the OMGP was approved by the CPUC, SDG&E performed extensive studies to develop alternative plans for upgrades to allow for the full delivery of Otay Mesa output to San Diego. The proposed Project was determined to be the preferred transmission solution. The CAISO sent a letter of concurrence with the scope of the proposed project in November The Existing Transmission System The electric power needs of San Diego are met by a combination of local generation and imported power. Transmission connections between San Diego and neighboring regions include five 230 kv lines that head north towards Los Angeles, one major 500 kv line that heads east to Arizona (the Southwest Power Link or SWPL), and one 230 kv line that heads south to Mexico. The maximum power that can be reliably imported into San Diego through these facilities is 2850 MW. With the most critical of these transmission facilities out of service (the SWPL), this capability is reduced to 2500 MW. The summer peak load in the San Diego area this year is forecasted to be 4586 MW. The difference between the load in San Diego and the import capability must be supplied by local generation sources. Current local generating resources include the Encina Power Plant, the South Bay Power Plant, and a number of combustion turbine facilities located around the service territory. Both the Encina and South Bay Plants are under Reliability Must Run ( RMR ) contracts with the CAISO because they are necessary to meet the reliability requirements of the area. Otay Mesa Generation Project The OMGP will consist of two combustion turbine generators and one steam turbine generator. The maximum total net generation output will be 615 MW 1. The basic interconnection facilities associated with the OMGP include: 1. Looping the Miguel-Tijuana 230 kv transmission line into the new Otay Mesa 230 kv switchyard. 1 This value is based on the interconnection capacity provided by Calpine. AJP 4/25/05-3-

4 2. Converting the Miguel-Otay Mesa section of the Miguel-Tijuana 230 kv line to two bundled 900 kcmil ACSS circuits with separate circuit breakers. 3. Installing two remedial action schemes that will trip Otay Mesa generation for loss of the 230 kv circuits between Otay Mesa and Miguel which share the same tower The California Energy Commission has already permitted the above facilities as part of the plant s basic interconnection plan of service. The cost of these facilities is not included in the cost estimate for the Project that is the subject of this memo. Calpine plans to complete construction of the OMGP by December The anticipated commercial in-service date for the Project is January 2008 when all the transmission upgrades will be completed. The CAISO and SDG&E agree that the plant should not be allowed to come on-line before all the transmission additions are completed. Presently, the construction of the plant is on hold pending the approval of the Project. Description of the Problem and the Transmission Project The scope of facilities associated with the basic interconnection of the OMGP to the grid as described above would connect the OMGP directly to Miguel Substation. However, with the OMGP connected to Miguel Substation, and without any additional transmission upgrades from Miguel into the San Diego load area, there would be significant congestion north of Miguel. The most effective means for eliminating this congestion would be to reduce the output of the OMGP. The likelihood of encountering congestion would increase with increased San Diego area load. As a result, when the OMGP is most needed (summer peak load period), it would likely need to be curtailed to mitigate transmission congestion. To mitigate the transmission constraints north of Miguel the following project was developed: 1. Creation of an Otay Mesa-Sycamore 230 kv line. This will require 28 miles of new overhead line construction from Miguel to Sycamore on existing structures. 2. Creation of a Miguel-Old Town 230 kv line. This will require construction of a 14-mile overhead line section (10 miles of new structures in an existing ROW and 4 miles of existing structures) and two underground sections (7 miles in Downtown San Diego and 3 miles on the Chula Vista Bay front). Each of these new lines will be routed through Miguel Substation but they will not normally be connected to Miguel Substation. However, switching will be available to connect these lines to Miguel, which will be desirable under some operating conditions. To allow this switching, it may be necessary to upgrade several circuit breakers due to the increased short circuit duty at Miguel and Tijuana. In addition to the two 230 kv transmission lines, the Project also includes: Installing new 230 kv circuit breakers and associated equipment at the Old Town and Sycamore Canyon Substations to terminate the new 230 kv lines. Installing two 230 kv circuit breakers and associated equipment at the Miguel Substation to allow for connections of the new lines to this substation when desired. Reconductoring the Sycamore Canyon-Fanita Junction (Carlton Hills Tap) section of the existing Chicarita-Carlton Hills- Los Coches 138 kv transmission line. AJP 4/25/05-4-

5 Project Cost The estimated cost of the Project is $209 million, which excludes the plant s basic interconnection costs. DISCUSSION Benefits of the Project The Project would provide the following benefits: 1. Provide for the firm delivery of the OMGP to San Diego; 2. Support future reliability needs due to continued load growth; 3. Prevent the OMGP from increasing transmission congestion north of Miguel; 4. Reduce RMR costs by allowing the displacement of a portion of the RMR generation in the SDG&E service area; 5. Provide higher operational flexibility during scheduled outages; 6. Improve system voltages; 7. Reduce system losses; 8. Avoid the need to trip additional generation and load for the Miguel transmission line corridor outage; 9. Provide grid expansion capability for future load growth (Specifically, the addition of the Otay Mesa-Old Town 230 kv line will provide the ability to reinforce the source of power to the rapidly growing downtown area of San Diego.); and 10. Enable the retirement of a portion of old and relatively inefficient generation in the San Diego area. The studies for the Project and its alternatives indicate that the Project is the preferred alternative for achieving the benefits listed above. In addition, the Project will minimize environmental impacts by utilizing underground construction and by striving to avoid residential areas where practicable. Alternatives to the Project Several alternatives to the Project were studied. The most competitive alternatives are summarized in the following table: Alternatives for the Otay Mesa Power Purchase Transmission Project Alternative Advantages Disadvantages 1. Construct an Otay Mesa- Mission #3 230 kv line instead of the Otay Mesa -Old Town Same as the preferred alternative - Estimated to have a higher cost due to a longer underground section. - Higher transmission losses. - Would require the full dispatch of South Bay generation where the preferred alternative would only require the partial dispatch of South Bay Generation. - May constrain exports from Mexico. AJP 4/25/05-5-

6 Alternatives for the Otay Mesa Power Purchase Transmission Project Alternative Advantages Disadvantages 2. Construct an Otay Mesa - Mission #3 230 kv line instead of the Otay Mesa - Old Town 230 kv line and connect the Tijuana 230 kv line to Miguel instead of Otay Mesa 3. Construct an Otay Mesa - South Bay 230 kv line instead of an Otay Mesa - Old Town 230 kv line, upgrade South Bay Substation from 138 kv to 230 kv, and complete several lower voltage upgrades 4. Construct the Otay Mesa - Sycamore 230 kv line but not the Miguel-Old Town line. Same as the preferred alternative, although, it may reduce potential congestion north of Otay Mesa while increasing potential congestion north of Miguel. Same as the preferred alternative. Lower cost. - Estimated higher cost due to the new Otay Mesa-Miguel line section. - Congestion north of Miguel with high CFE exports. - Higher load tripping requirement for the Miguel corridor outage. - Does not provide for the combined deliverability of both OMGP and South Bay generation. - Estimated to have a higher cost due to the 69 kv and 138 kv upgrades required to provide the combined deliverability of both OMGP and South Bay generation. - Would require a new 230 kv switchyard and 230/138 kv banks at South Bay, which is not currently included in the long-term plan. - Exports from Mexico may be constrained. - Could lead to the need to sectionalize the 69 kv system and reduce system reliability. - Would require excessive generation tripping for a Miguel corridor outage. - Higher losses. - Does not provide for the full delivery of the OMGP. - Would not provide a 230 kv source to downtown to allow for necessary upgrades in that area. - Would cause congestion at South Bay and Miguel. - Excessive generation tripping would be required for the Miguel corridor outage. - Higher losses. The detailed engineering analysis for the Project as well as the ISO s letter detailing its review of this analysis is available upon request. AJP 4/25/05-6-

7 MANAGEMENT RECOMMENDATION Based on a thorough analysis of the alternatives, both ISO Management and SDG&E have concluded that the recommended transmission project is the preferred transmission solution. Therefore, ISO Management recommends the following motion for Board consideration: MOVED, that the Board of Governors, 1. Approves the Otay Mesa Power Purchase Agreement (OMPPA) Transmission Project to allow the full dispatchability and deliverability of the Otay Mesa Generation Project. The OMPPA was determined to be necessary to satisfy San Diego area resource adequacy requirements by the California Public Utilities Commission and the San Diego Gas and Electric Company. 2. Directs San Diego Gas and Electric Company to complete the permitting, design, and construction of the Otay Mesa Power Purchase Agreement Transmission Project. AJP 4/25/05-7-

SDG&E Valley-Rainbow Project

SDG&E Valley-Rainbow Project SDG&E Valley-Rainbow Project Presentation to Grid Reliability/Operations Committee Steven Mavis ISO Grid Planning Department May 24, 2000 1 Background SDG&E s 1999 Expansion Plan for 2000-2004 indicated

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M of Need In-service Cost Alternatives Service Projects in PG&E Service Territory Mare Island - Ignacio 115 kv NERC Category 2010 Reconductor the limiting 19 $19M Connect Highway May 2012 Line re-rates and

More information

PREPARED DIRECT TESTIMONY

PREPARED DIRECT TESTIMONY Application No.: A.0-04- Exhibit No.: SDG&E-4 Witness: William V. Torre In the Matter of San Diego Gas & Electric Company s Application for Authorization to (1) to Participate in the Steam Generator Replacement

More information

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station East Asian Alternative Energy Futures Workshop By the Nonproliferation Policy Education Center

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

2016 SDG&E Grid Assessment Results

2016 SDG&E Grid Assessment Results 2016 SDG&E Grid Assessment Results CAISO Stakeholder Meeting September 22, 2016 Matthew Belden Engineer II San Diego Gas & Electric Email: MBelden@semprautilities.com 2016 Study Windows One to Five-Year

More information

2019 & 2023 Final LCR Study Results San Diego-Imperial Valley non-bulk sub-areas

2019 & 2023 Final LCR Study Results San Diego-Imperial Valley non-bulk sub-areas 2019 & 2023 Final LCR Study Results San Diego-Imperial Valley non-bulk sub-areas Luba Kravchuk Senior Regional Transmission Engineer Frank Chen - Regional Transmission Engineer Lead Stakeholder Call May

More information

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA Submission of Indicated New York Transmission Owners For Authority to Construct and Operate Electric Transmission Facilities in Multiple Counties in New York Case 13-M-0457 Edic to New Scotland 345 kv

More information

Updates. Pat Reiten President and CEO, PacifiCorp Transmission

Updates. Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission and Regional Updates Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission Overview 16,400 circuit-miles of transmission lines 12,685 MW record peak demand

More information

Re: Comments on the 12/7/09 Dynamic Transfer Stakeholder Meeting

Re: Comments on the 12/7/09 Dynamic Transfer Stakeholder Meeting Joseph H. Rowley Vice President Project Development 101 Ash Street, HQ14A San Diego, CA 92101-3017 Tel: 619.696.4455 Fax: 619.696.2911 JRowley@SempraGeneration.com December 15, 2009 Ms. Anjali Sheffrin

More information

APPENDIX F: Project Need and Description

APPENDIX F: Project Need and Description APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014

Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014 Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014 The Clean Coalition recommends that state regulators and utilities account for potential

More information

Southern California Edison

Southern California Edison Recent Energy Storage Projects November 8, 2017 Presented by Kern Economic Development Corporation 1 Agenda 1. California Energy Trends and Recent Events 2. SCE s Storage Projects California Energy Trends

More information

SPP OVERVIEW. Mike Ross Senior Vice President, Government Affairs and Public Relations

SPP OVERVIEW. Mike Ross Senior Vice President, Government Affairs and Public Relations SPP OVERVIEW Mike Ross Senior Vice President, Government Affairs and Public Relations 1 Our Mission Helping our members work together to keep the lights on today and in the future. 2 NORTH AMERICAN INDEPENDENT

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY BOARD

HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY BOARD SCHEDULED ITEM TO: FROM: HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY BOARD GEORGE F. MORROW, DIRECTOR OF UTILITIES DATE: JANUARY 28, 2013 SUBJECT: APPROVAL OF POWER SALES AGREEMENT ( PSA ) WITH

More information

Western NY Public Policy Transmission Planning Report

Western NY Public Policy Transmission Planning Report Western NY Public Policy Transmission Planning Report Dawei Fan Supervisor, Public Policy and Interregional Planning Business Issues Committee September 12, 2017 Operating Committee September 15, 2017

More information

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT

More information

2020 & 2024 Draft LCR Study Results SDG&E Non-Bulk System. Frank Chen - Regional Transmission Engineer Lead Stakeholder Meeting March 14, 2019

2020 & 2024 Draft LCR Study Results SDG&E Non-Bulk System. Frank Chen - Regional Transmission Engineer Lead Stakeholder Meeting March 14, 2019 2020 & 2024 Draft LCR Study Results SDG&E Non-Bulk System Frank Chen - Regional Transmission Engineer Lead Stakeholder Meeting March 14, 2019 ARIZONA San Diego Non-Bulk LCR Area CHINO [SCE] SERRANO [SCE]

More information

California Energy Storage Policies. Carla Peterman Commissioner, California Public Utilities Commission December 2016

California Energy Storage Policies. Carla Peterman Commissioner, California Public Utilities Commission December 2016 California Energy Storage Policies Carla Peterman Commissioner, California Public Utilities Commission December 2016 California Storage Law and Policy l California has supported energy storage through

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

Valley - Rainbow Interconnection Project Feasibility Study Report

Valley - Rainbow Interconnection Project Feasibility Study Report Attachment A Valley - Rainbow Interconnection Project Feasibility Study Report A Joint Study Effort of San Diego Gas & Electric (SDG&E) and Southern California Edison (SCE) in Cooperation with the California

More information

for DRECP Alternatives

for DRECP Alternatives Transmission Technical Group Conceptual Transmission Plan for DRECP Alternatives DRECP WebEx Meeting January 9, 2013 Overview Purpose, Participants, and Timeline Generation Assumptions Transmission Assumptions

More information

Overview of ISO New England and the New England Wholesale Power Markets

Overview of ISO New England and the New England Wholesale Power Markets Overview of ISO New England and the New England Wholesale Power Markets Boston Chapter of IEEE PES Technical Meeting June 15, 2010 Stephen J. Rourke Vice President, System Planning About ISO New England

More information

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007 High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services

More information

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool WIRES University Overview of ISO/RTOs Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool 1 OUR MISSION Helping our members work together to keep the lights on

More information

REGIONAL TRANSMISSION ORGANIZATIONS / INDEPENDENT SYSTEM OPERATORS AND THE ENERGY IMBALANCE MARKET: AN OVERVIEW OF THE PICTURE IN THE WEST

REGIONAL TRANSMISSION ORGANIZATIONS / INDEPENDENT SYSTEM OPERATORS AND THE ENERGY IMBALANCE MARKET: AN OVERVIEW OF THE PICTURE IN THE WEST REGIONAL TRANSMISSION ORGANIZATIONS / INDEPENDENT SYSTEM OPERATORS AND THE ENERGY IMBALANCE MARKET: AN OVERVIEW OF THE PICTURE IN THE WEST MEGAN O REILLY COALITION FOR CLEAN AFFORDABLE ENERGY EPE IRP STAKEHOLDER

More information

Pacific Gas and Electric Company TM

Pacific Gas and Electric Company TM Pacific Gas and Electric Company TM Evelyn C. Lee Mailing Address P.O. Box 7442 San Francisco, CA 94120 Street/Courier Address Law Department 77 Beale Street San Francisco, CA 94105 (415) 973-2786 Fax:

More information

The Development of Competitive Renewable Energy Zones in Texas

The Development of Competitive Renewable Energy Zones in Texas The Development of Competitive Renewable Energy Zones in Texas Warren Lasher Manager, System Assessment 4/23/2008 North American Electric Grids The ERCOT Region is one of 3 NERC grid interconnections.

More information

New Jersey State Report

New Jersey State Report New Jersey State Report July 2017 Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast 2. Markets Capacity Market Results Market Analysis 3. Operations Emissions

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JULY 2015) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1 Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide Version 1.1 October 21, 2016 1 Table of Contents: A. Application Processing Pages 3-4 B. Operational Modes Associated

More information

APPENDIX F: 2012 Request Window Submittals

APPENDIX F: 2012 Request Window Submittals APPENDIX F: 2012 Request Window Submittals Table F-1: 2012 Request Window Submittals Project Name Service Submitted by 1 Lockeford-Lodi 230 kv Development City of Lodi, Electric Utility Department 5/31/2017

More information

Overview of Electricity Trade Agreement between Québec and Ontario. May 10, 2017 For Information Purposes Only

Overview of Electricity Trade Agreement between Québec and Ontario. May 10, 2017 For Information Purposes Only Overview of Electricity Trade Agreement between Québec and Ontario May 10, 2017 For Information Purposes Only Purpose To provide an overview of the electricity trade agreement between the Independent Electricity

More information

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013 Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in 2015 Stakeholder Webconference February 28, 2013 Page 2 Merced Irrigation District (Merced) Background Merced Irrigation

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

SunZia Southwest Transmission Project

SunZia Southwest Transmission Project SunZia Southwest Transmission Project SunZia Project Update for the 9 th Annual Transmission Summit West October 13, 2017 SUNZIA SOUTHWEST TRANSMISSION PROJECT OCTOBER 13, 2017 0 SouthWestern Power Group

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of San Diego Gas & Electric Company (U902E) for Authority to Implement Optional Pilot Program to Increase Customer Access to

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Exhibit No.: Commissioner: Loretta Lynch Administrative Law Judge: Meg Gottstein Witness: BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Investigation into ) implementation

More information

California Independent System Operator. Memorandum

California Independent System Operator. Memorandum California Independent System Operator Memorandum To: ISO Board of Governors From: Armie Perez, Vice President of Planning and Infrastructure Development Date: Re: Decision on Tehachapi Project This memorandum

More information

SunZia Southwest Transmission Project

SunZia Southwest Transmission Project SunZia Southwest Transmission Project SunZia Project Update for the Southern Arizona Economic Development Group September 12, 2017 SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 0 SouthWestern

More information

Tehachapi Renewable Transmission Project. Chino Hills Proposed Alternative. for Segment 8A of the. Chino Hills - September 11, 2007

Tehachapi Renewable Transmission Project. Chino Hills Proposed Alternative. for Segment 8A of the. Chino Hills - September 11, 2007 Chino Hills Proposed Alternative for Segment 8A of the Tehachapi Renewable Transmission Project Chino Hills - September 11, 2007 1 Objective Start the dialogue on the attributes of the Chino Hills Proposed

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Southern California Edison Company (U338E) for Approval of the Results of Its 2013 Local Capacity Requirements Request for

More information

City of Grand Island

City of Grand Island City of Grand Island Tuesday, May 25, 2010 Council Session Item G10 #2010-139 - Approving Bid Award for Substation Power Transformers Staff Contact: Gary R. Mader City of Grand Island City Council Council

More information

Arizona Transmission Challenges

Arizona Transmission Challenges Power Task Force Agenda Number 2. Arizona Transmission Challenges Central Arizona Water Conservation District Power Committee Presentation May 18, 2017 Transmission Planning Efforts NATIONAL Section 368

More information

Welcome. Please Sign In

Welcome. Please Sign In Welcome South Bay Bus Rapid Transit (BRT) Draft Environmental Impact Report (DEIR) Public Meeting Please Sign In Please comment in any of the following manners: 1. Submit a comment form 2. Provide verbal

More information

Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources

Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources Outline Tri-State Background Tri-State Generation Mix Power Delivery Wholesale Electricity Markets

More information

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross Briefing for the Kansas Legislature March 6, 2013 Paul Suskie & Mike Ross psuskie@spp.org mross@spp.org 501.614.3200 Presentation overview Who we are What we do How we benefit the consumer Industry dynamics

More information

August 15, Please contact the undersigned directly with any questions or concerns regarding the foregoing.

August 15, Please contact the undersigned directly with any questions or concerns regarding the foregoing. California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 August 15, 2017 Re: California

More information

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

Decision on the ISO Transmission Plan

Decision on the ISO Transmission Plan Decision on the 2013-2014 ISO Transmission Plan Neil Millar Executive Director, Infrastructure Development Board of Governors Meeting General Session March 19-20, 2014 Approving the plan means approving

More information

2015 Grid of the Future Symposium

2015 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,

More information

Docket No EI Date: May 22, 2014

Docket No EI Date: May 22, 2014 Docket No. 140032-EI Big Bend Units 1 through 4 are pulverized coal steam units that currently use distillate oil 2 for start-ups and for flame stabilization. The Company seeks to use natural gas in place

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Seabrook Substation Reliability Improvement Project

Seabrook Substation Reliability Improvement Project New England Division Seabrook Substation Reliability Improvement Project 1. Project Summary Description Seabrook Substation is critical to ISO-New England as a Pool Transmission Facility, to grid availability

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN SPN High Value Project PO Route RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN Document History Version Date Details Originator V0.1 20/06/2013 Initial version Chris Winch V0.2

More information

Umatilla Electric Cooperative Net Metering Rules

Umatilla Electric Cooperative Net Metering Rules Umatilla Electric Cooperative Net Metering Rules Version: July 2017 Umatilla Electric Cooperative NET METERING RULES Rule 0005 Scope and Applicability of Net Metering Facility Rules (1) Rule 0010 through

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

Simulation and Visualization of Power Grid Operations with High Renewable Penetration

Simulation and Visualization of Power Grid Operations with High Renewable Penetration Simulation and Visualization of Power Grid Operations with High Renewable Penetration Thomas J Overbye Fox Family Professor of Elect. & Comp. Eng. University of Illinois at Urbana-Champaign overbye@illinois.edu

More information

Reforming the TAC and Retail Transmission Rates. Robert Levin California Public Utilities Commission Energy Division August 29, 2017

Reforming the TAC and Retail Transmission Rates. Robert Levin California Public Utilities Commission Energy Division August 29, 2017 Reforming the TAC and Retail Transmission Rates. Robert Levin California Public Utilities Commission Energy Division August 29, 2017 1 CPUC Staff Rate Design Proposals Restructure the High-Voltage TAC

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202 Transmission and Distribution Substation Projects Operating Company: Entergy Gulf States - Texas Customer: PID # 202 Funding Project Number: F4PPGS0386 Facility Study for PID # 202: Study for 146 MW Revision

More information

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications Supplement to 2013-2014 ISO Transmission Plan Harry Allen-Eldorado Project Description and Functional Specifications Description and Functional Specifications of Proposed Economically Driven Harry Allen

More information

West Station-West Cañon 115 kv Transmission Project

West Station-West Cañon 115 kv Transmission Project West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016 Decision 21481-D01-2016 October 18, 2016 Alberta Utilities Commission Decision 21481-D01-2016 Proceeding 21481 Application 21481-A001 October 18, 2016 Published by the: Alberta Utilities Commission Fifth

More information

Review of U.S. market reforms for renewable integration, flexibility, and storage

Review of U.S. market reforms for renewable integration, flexibility, and storage Review of U.S. market reforms for renewable integration, flexibility, and storage Eric Hsieh Director Office of Energy Finance and Incentives Analysis U.S. Department of Energy 14 July 2017 Transformations

More information

APPENDIX E: ELECTRIC AND MAGNETIC FIELDS MANAGEMENT PLAN

APPENDIX E: ELECTRIC AND MAGNETIC FIELDS MANAGEMENT PLAN APPENDIX E: Final EIS/EIR E-1 FINAL ENVIRONMENTAL IMPACT STATEMENT/ENVIRONMENTAL IMPACT REPORT APPENDIX E: THIS PAGE INTENTIONALLY LEFT BLANK E-2 May 2011 LOS ANGELES DEPARTMENT OF WATER AND POWER Barren

More information

TransNet Dollars Keep San Diego Moving

TransNet Dollars Keep San Diego Moving TransNet Dollars Keep San Diego Moving In 1987, San Diego region voters approved the TransNet program a half-cent sales tax to fund a variety of important transportation projects throughout the region.

More information

2016 Load & Capacity Data Report

2016 Load & Capacity Data Report Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC

More information

Four Corners Queue Transmission Interconnection Study

Four Corners Queue Transmission Interconnection Study Four Corners Queue Transmission Interconnection Study Facility Study Results By Arizona Public Service Company Transmission Planning & Interconnection Development March 22, 2016 Version 1 FACILITIES STUDY

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

PREPARED REBUTTAL TESTIMONY OF BETH MUSICH SOUTHERN CALIFORNIA GAS COMPANY AND SAN DIEGO GAS & ELECTRIC COMPANY

PREPARED REBUTTAL TESTIMONY OF BETH MUSICH SOUTHERN CALIFORNIA GAS COMPANY AND SAN DIEGO GAS & ELECTRIC COMPANY Application No: A.14-06-021 Exhibit No.: Witness: Beth Musich Application of Southern California Gas Company (U 904 G) and San Diego Gas & Electric Company (U 902 G) for Low Operational Flow Order and

More information

Energy Storage Interconnection Initiative

Energy Storage Interconnection Initiative Energy Storage Interconnection Initiative Stakeholder Call November 25, 2014 Agenda Time Agenda Item Speaker 10:00-10:10 Introduction, Stakeholder Process Tom Cuccia 10:10-10:30 Applying the GIDAP to energy

More information

Challenges With Underground High Voltage Transmission SCE Tehachapi Renewable Transmission Project First 500 kv Underground T/L in North America

Challenges With Underground High Voltage Transmission SCE Tehachapi Renewable Transmission Project First 500 kv Underground T/L in North America Challenges With Underground High Voltage Transmission SCE Tehachapi Renewable Transmission Project First 500 kv Underground T/L in North America Noe Bargas, PE Supervising Senior Civil Engineer Southern

More information

LANCASTER CHOICE ENERGY S BIENNIAL ENERGY STORAGE PROCUREMENT COMPLIANCE REPORT

LANCASTER CHOICE ENERGY S BIENNIAL ENERGY STORAGE PROCUREMENT COMPLIANCE REPORT January 1, 2016 CA Public Utilities Commission Energy Division Attention: Tariff Unit 505 Van Ness Avenue, 4thFloor San Francisco, CA 94102-3298 Advice Letter LCE 001-E RE: LANCASTER CHOICE ENERGY S BIENNIAL

More information

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES: TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design

More information

Michigan Renewable Energy Case Study

Michigan Renewable Energy Case Study Michigan Renewable Energy Case Study NARUC ENERGY REGULATORY PARTNERSHIP WITH GEORGIAN NATIONAL ENERGY AND WATER SUPPLY REGULATORY COMMISSION TBILISI, GEORGIA JANUARY 27-31, 2014 GREG R. WHITE, COMMISSIONER

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

Agricultural Internal Combustion (IC) Engine Conversion Incentive Program Questions and Answers

Agricultural Internal Combustion (IC) Engine Conversion Incentive Program Questions and Answers CALIFORNIA FARM BUREAU FEDERATION Agricultural Internal Combustion (IC) Engine Conversion Incentive Program Questions and Answers Q1. Who is eligible to sign up for an AG-ICE program? A. In order to be

More information

SCE Smart Grid. Creating a Cleaner, Smarter Energy Future. Metering, Billing / MDM America Conference. San Diego. March 9, 2010

SCE Smart Grid. Creating a Cleaner, Smarter Energy Future. Metering, Billing / MDM America Conference. San Diego. March 9, 2010 SCE Smart Grid Creating a Cleaner, Smarter Energy Future Metering, Billing / MDM America Conference San Diego March 9, 2010 SOUTHERN CALIFORNIA EDISON Southern California Edison An Edison International

More information

Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market

Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market Beacon Power Corporation Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market Prepared for: New York Business Issues Committee May 21, 2008 Safe Harbor

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

Impact of Distributed Energy Resources on Transmission System Reliability

Impact of Distributed Energy Resources on Transmission System Reliability S E P T E M B E R 1 3, 2 0 1 8 W E B I N A R Impact of Distributed Energy Resources on Transmission System Reliability National Council on Electricity Policy (NCEP) Alan McBride D I R E C T O R, T R A

More information

October 1, Docket: ER Energy Imbalance Market Special Report Transition Period June 2018 for Powerex Corp.

October 1, Docket: ER Energy Imbalance Market Special Report Transition Period June 2018 for Powerex Corp. California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 October 1, 2018 Re: California

More information

LADWP Energy Storage Update. Board of Water and Power Commissioners August 15, 2017

LADWP Energy Storage Update. Board of Water and Power Commissioners August 15, 2017 LADWP Energy Storage Update Board of Water and Power Commissioners August 15, 2017 Energy Storage Overview Energy Storage (ES) is the capture and re-dispatch of already produced energy using various technologies.

More information

Reactive Power Requirements and Financial Compensation. Addendum to Draft Final Proposal

Reactive Power Requirements and Financial Compensation. Addendum to Draft Final Proposal Reactive Power Requirements and Financial Compensation July 21, 2016 Table of Contents 1. Introduction... 3 2. Changes to Proposal... 4 3. Plan for Stakeholder Engagement... 4 4.... 4 6. Next Steps...

More information