TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY
|
|
- Douglas Dixon
- 5 years ago
- Views:
Transcription
1 TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck
2 ii EXECUTIVE SUMMARY Tucson Electric Power Company (TEP) performed a system impact study as requested by Toltec Power Partnership for interconnection of a new generation plant with a total capacity of 1,096 MW for phase 1 and an additional 1,096 MW for phase 2. The proposed project s 500-kV substation bus will be interconnected to the Saguaro 500-kV bus by a single 500-kV transmission line. Two 500/345-kV transformer banks will be installed at the project s proposed 500-kV bus and the 345-kV bus will be interconnected to the existing South-Westwing 345-kV line by looping the line. The proposed in-service date for the project is June 1, This study report will focus on the study results of the first phase. Study results for the second phase will be covered in a subsequent study report. The purpose of this System Impact Study (phase one) is to determine the adequacy of Arizona s Extra High Voltage (EHV) Electric system to accommodate all or part of the 1,096 MW requested capacity. The study will focus mainly on the electric transmission systems of APS, SRP and TEP. This study will identify if there are any negative impacts to reliability under various power displacement scenarios. New facilities or upgrades will be recommended to maintain system reliability in accordance with the WSCC and NERC planning standards and criteria. The results of this system impact study will be used as the basis to determine project cost allocation for facility upgrades. The study accuracy and the results for the assessment of the system adequacy are contingent on the accuracy of the technical data provided by the customer as shown in Figure 1 and Appendix B. Any changes to the attached data could void the study results. The study was performed for two system load conditions and various generation scenarios Heavy Summer load forecast scenarios: (a) No Toltec Power Project (b) Power displaced in southern and eastern Arizona (c) Power displaced in central Arizona (d) Power displaced in western Arizona (e) Power displaced in northern Arizona (f) Power displaced throughout Arizona (scaled down) (g) Load increased throughout Desert Southwest (once-in-ten-year heat wave assumption) (h) Power exported to California 2003 Light Autumn load forecast scenarios: (a) No Toltec Power Project (b) Power displaced in southern and eastern Arizona (c) Power displaced in central Arizona (d) Power displaced in western Arizona
3 iii (e) Power displaced in northern Arizona (f) Power displaced throughout Arizona (scaled down) (g) Power exported to California The study includes a steady-state power flow analysis, post-transient voltage analysis, and transient stability analysis. Short-circuit duty analysis will be performed as part of the Facilities Study. CONCLUSIONS Studies identified that the existing facilities are inadequate to provide service to the Toltec Power project without additional system reinforcements. The study did not identify any impacts to the TEP system but did identify a number of impacts throughout the Arizona EHV Transmission System. 1. A total of twenty-three transmission facilities (bus-tie, circuits, series capacitors and transformer banks) were identified to be adversely impacted with the addition of the Toltec Power project under the various scenarios evaluated as summarized below. Transmission Facility Type Impacted Cholla 500/345-kV No.1 Transformer Bank 6 of 7 Scenarios Cholla 500/345-kV No.2 Transformer Bank 6 of 7 Scenarios Cholla 345/230-kV Transformer Bank 6 of 7 Scenarios Four Corner 500/345-kV Transformer Bank 1 of 7 Scenarios Country Club-Glendale 230-kV Transmission Line 3 of 7 Scenarios Glendale-Agua Fria 230-kV Transmission Line 3 of 7 Scenarios Pinnacle Peack (APS) 230-kV Bus-Tie 3 of 7 Scenarios Agua Fira-Westwing 230-kV Transmission Line 5 of 7 Scenarios Cholla-Pinnacle Peak 345-kV Transmission Line 6 of 7 Scenarios Cholla-Preacher Canyon 345-kV Transmission Line 6 of 7 Scenarios Preacher Canyon-Pinnacle Peak 345-kV Transmission Line 6 of 7 Scenarios Cholla-Leupp 230-kV Transmission Line 6 of 7 Scenarios Leupp-Coconino 230-kV Transmission Line 6 of 7 Scenarios Moenkopi-El Dorado 500-kV Series Capacitors 4 of 7 Scenarios Navajo-Crystal 500-kV Series Capacitors 1 of 7 Scenarios Yavapai-Verde North 230-kV Transmission Line 2 of 7 Scenarios Saguaro-Tatmomli 230-kV Transmission Line 6 of 7 Scenarios Santa Rosa-Tatmomli 230-kV Transmission Line 6 of 7 Scenarios Lone Peak-Sunny Slope 230-kV Transmission Line 4 of 7 Scenarios Surprise-Westwing 230-kV Transmission Line 1 of 7 Scenarios Corbell-Kyrene 230-kV Transmission Line 2 of 7 Scenarios Santan-Corbell 230-kV Transmission Line 4 of 7 Scenarios Silver King-Goldfield 230-kV Transmission Line 5 of 7 Scenarios
4 iv 2. Since market dispatch conditions are unknown ahead of scheduling, the 2003 heavy summer set of conditions analyzed provide scenarios for testing the Toltec Power project impacts under conditions that credibly represent potential market conditions for integrating additional market generation. These conditions are snapshots of a simultaneous use limit that does not envelope all possible combinations. Efforts were made to try and capture worst case possibilities that may result. The Toltec Power project may be subject to scheduling limitations not identified in this report to insure it that the transmission path flows stay within thermal and/or operational limits. 3. The Toltec Power project (Phase 1) does not introduce system instability for the selected critical contingencies tested. 4. The Toltec Power project results in adversely impacting post-transient bus voltages under all scenarios studied except power displacement at southern and eastern Arizona. A total of twelve single contingencies with the Toltec Power project were found that result in voltage drops in excess of 5%. Seven of the twelve single contingencies were identified to be pre-existing problems that are aggravated with the addition of the Toltec Power project. The remaining five single contingencies are new criteria violations resulting from the addition of the Toltec Power project and various generation/load scenarios modeled. A Facility Study will be needed to determine the interconnection facilities and system upgrades required to interconnect the Toltec Power project. The study should address the following scope: 1. Short-Circuit duty assessments and review of locations where duty is increased by more than 0.1kA and the duty at that bus exceeds more than 60% nameplate rating to determine need for breaker replacement and cost allocation. 2. Identification of physical upgrades (should be done by each impacted utility) or congestion management solutions to ensure that the system stays within operational and planning limits. Congestion management will only be allowed in lieu of physical upgrades without compensation. 3. The Facility Study should address the scope of the operating procedures ( Two-County Rule ) that may be impacted or needed. Actual operating procedures and studies to support those procedures will not be developed until the Facility Interconnection and Operation Agreement (FIOA) is executed. Any operating procedure change or additional new operating procedure will require TEP and other impacted utilities review and approval. These approvals will be obtained after FIOA execution, and prior to service connection for testing and operation. 4. Determine the interconnection facilities required to interconnect the Toltec Power project including, but not limited to, transmission lines and line extensions, switchyard facilities, circuit breakers, relay protection, and metering.
5 v CONTENTS Page INTRODUCTION 1 STUDY CONDITIONS AND ASSUMPTIONS 2 A. Planning Criteria 2 B. Congestion Management 3 C. Toltec Power Project Phase One 5 D. Power Flow Study 5 E. Transient Stability Study 9 F. Post Transient Voltage Study 11 G. Short Circuit Duty Study 11 STUDY RESULTS 11 A. Power Flow Study 11 B. Transient Stability Study 20 C. Post Transient Voltage Study 20 CONCLUSIONS 23 TABLES 1-1. Load Forecast 1-2. Pre-Toltec Generation Dispatch 2-1. Power Flow Results, 2003 Heavy Summer Displace Southern and Eastern Arizona 2-2. Power Flow Results, 2003 Heavy Summer Displace Central Arizona 2-3. Power Flow Results, 2003 Heavy Summer Displace Western Arizona 2-4. Power Flow Results, 2003 Heavy Summer Displace Northern Arizona 2-5. Power Flow Results, 2003 Heavy Summer Displace Entire Arizona 2-6. Power Flow Results, 2003 Heavy Summer Increase Desert Southwest load 2-7. Power Flow Results, 2003 Heavy Summer Export Power to California 3. Transient Stability, Summary 4-1. Post Transient Voltage, 2003 Heavy Summer Displace Southern & Eastern Arizona 4-2. Post Transient Voltage, 2003 Heavy Summer Displace Central Arizona 4-3. Post Transient Voltage, 2003 Heavy Summer Displace Western Arizona 4-4. Post Transient Voltage, 2003 Heavy Summer Displace Northern Arizona 4-5. Post Transient Voltage, 2003 Heavy Summer Displace Entire Arizona 4-6. Post Transient Voltage, 2003 Heavy Summer Increase Desert Southwest load 4-7. Post Transient Voltage, 2003 Heavy Summer Export Power to California
6 vi FIGURES 1. Toltec Power Project 2. Proposed Toltec Power Project Interconnection APPENDIX A Load Flow Plots Base Cases with all projects in the queue Single Contingency cases with all projects in the queue Double Contingency cases with all projects in the queue APPENDIX B Stability Machine Models APPENDIX C 2003 Heavy Summer Stability Plots APPENDIX D 2004 Light Autumn Stability Plots
7 TOLTEC POWER PROJECT INTERCONNCETION STUDY SYSTEM IMPACT STUDY January 7, 2002 INTRODUCTION Tucson Electric Power Company (TEP) performed a system impact study as requested by Toltec Power Partnership for interconnection of a new generation plant with a total capacity of 1,096 MW for phase 1 and an additional 1,096 MW for phase 2. The proposed project s 500-kV substation bus will be interconnected to the Saguaro 500-kV bus by a single 500-kV transmission line. Two 500/345-kV transformer banks will be installed at the project s proposed 500-kV bus and the 345-kV bus will be interconnected to the existing South-Westwing 345-kV line by looping the line. The proposed in-service date for the project is June 1, This study report will focus on the study results of the first phase. Study results for the second phase will be covered in a subsequent study report. The purpose of this System Impact Study (phase one) is to determine the adequacy of Arizona s Extra High Voltage (EHV) Electric system to accommodate all or part of the 1,096 MW requested capacity. The study will focus mainly on the electric transmission systems of APS, SRP and TEP. This study will identify if there are any negative impacts to reliability under various power displacement scenarios. New facilities or upgrades will be recommended to maintain system reliability in accordance with the WSCC and NERC planning standards and criteria. The results of this system impact study will be used as the basis to determine project cost allocation for facility upgrades. The study accuracy and the results for the assessment of the system adequacy are contingent on the accuracy of the technical data provided by the customer as shown in Figure 1 and Appendix B. Any changes to the attached data could void the study results. The study was performed for two system load conditions and various generation scenarios Heavy Summer load forecast scenarios: (a) No Toltec Power Project (b) Power displaced in southern and eastern Arizona (c) Power displaced in central Arizona (d) Power displaced in western Arizona (e) Power displaced in northern Arizona (f) Power displaced throughout Arizona (scaled down) (g) Load increased throughout Desert Southwest (once-in-ten-year heat wave assumption) (h) Power exported to California
8 2
9 Light Autumn load forecast scenarios: (a) No Toltec Power Project (b) Power displaced in southern and eastern Arizona (c) Power displaced in central Arizona (d) Power displaced in western Arizona (e) Power displaced in northern Arizona (f) Power displaced throughout Arizona (scaled down) (g) Power exported to California The following sections provide detailed study conditions and assumptions and present the results of Steady-state power flow, Post-transient voltage, and Stability assessments. STUDY CONDITIONS AND ASSUMPTIONS A. Planning Criteria The study was conducted by applying the Western Systems Coordinating Council (WSCC) Reliability Criteria. More specifically, the main criteria applicable to this study are as follows: Load Flow Assessment The following contingencies are considered for transmission or subtransmission lines and 500/345-kV and 500/230-kV transformer banks ( AA-Banks ): Single Transmission Line Contingencies (138-kV and above) Single Transformer Contingencies (500-kV, 345-kV, and 230-kV Banks) Double Transmission Line Contingencies (Common Mode) Single Line and Single Transformer Bank (Common Mode) (Outages of two AA-Banks are beyond the Planning Criteria) Stability Assessment The Transmission System is to remain stable under a three-phase-to-ground fault at the most critical locations, normally cleared, with the loss of one or two transmission lines. The system is also to remain stable under the most critical single-phase-to-ground fault with delayed clearing. Maximum acceptable first swing voltage drops are 25% under single contingencies and 30% under double contingencies. In addition, first swing voltage swings are not to exceed 20% for more than 20 cycles under single contingency and no more than 20% for 40 cycles under double contingency conditions as defined by the WSCC Planning Criteria.
10 4 Post Transient Voltage Assessment The maximum voltage deviations allowed under contingency conditions in the post transient time frame are: 5 percent under N-1 (one generator, one circuit, or one transformer) 10 percent under N-2 (two generators or two circuits) B. Congestion Management Maximum generation (P max = 23,857 MW) within Arizona exceeds the total Arizona area load (P Load = 15,058 MW) prior to the addition of the Toltec Power Project. Generation in excess of the Arizona load will therefore be competing for available export capacity to California, New Mexico, and Nevada. Under heavy summer conditions, the No Toltec modeled base case is assumed to have a total Arizona load of 15,058 MW with a corresponding generation output of 17,981 MW and an export of 2,567 MW. Approximately 4,000 MW of new proposed projects in the Palo Verde area were assumed to be off-line for this assessment as a result of export limitations after reserving capacity for the Toltec Power Project. This was done as a means to properly evaluate impacts attributed solely to the Toltec Power Project. Actual operation of the system will not reserve export capacity for the Toltec Power Project. As a result, the Toltec Power Project will be competing for available capacity to serve the Arizona load displacing generation within Arizona as determined by market conditions. Since these conditions are not known in advance, several scenarios were developed that looked at generation displacements taken in different areas. The following principles were used in determining whether congestion management, remedial action schemes, or facility upgrades are required to mitigate base case, single contingency, or double contingency overloads. Congestion management, as means to mitigate base case overloads, can be used if it is determined that the overloads are minimal (less than 5% of the facility normal rating) and impacted utilities concur with the use of congestion management. Facility upgrades will be required if it is determined that the use of congestion management is impractical (loading exceeds nameplate by more than 5%). Since remedial action schemes (RAS) are not allowed to mitigate single contingency overloads by the Arizona Corporation Commission (ACC), facility upgrades will be required to mitigate single contingency overloads. RAS, in lieu of facility upgrades, will be recommended for double contingencies if the scheme is effective and is not a hazard to reliability. Hazard to reliability is determined to be in excess of a single Palo Verde unit. Facility upgrades will be recommended if RAS is determined to be unworkable or determined to be a hazard to reliability.
11 5 The following study method was implemented to assess the extent of possible congestion: a). Under Base Case (all transmission facilities in service), without the proposed Toltec Power project, the system was evaluated with all existing interconnected generation and all known generation requests in the area that have a queue position ahead of this project. b). Under Base Case, the total output of the proposed Toltec Power project was added and the system was reevaluated. If the normal loading limits of facilities are exceeded in (a), the overload is identified as an existing overload or an overload caused by a project or number of projects in the queue ahead of the proposed project. If the normal loading limits of facilities are exceeded in (b) but where not identified in (a), the overload is identified as having been caused by the addition of the proposed project. The Toltec Power project and other projects in the queue ahead of this request may be subjected to congestion management, potential upgrade cost sharing and/or participation of any proposed remedial action schemes if the project aggravates or triggers the overload. Additionally, Toltec Power project may have to participate in mitigation of overloads triggered by subsequent projects in the queue, subject to FERC protocols and policies. The results of these studies should be able to identify: a). If there is capacity available to accommodate the proposed project and all projects in the queue without the need for congestion management, remedial action schemes or facility upgrades. b). If overloads exist in the area with all projects in the queue and all facilities in service. c). If congestion exists in the area with all projects in the queue under single element and double element outage conditions assuming no new remedial action schemes in place. d). If remedial action schemes appear to be workable solutions to increasing the amount of generation that can be accommodated prior to a potential double element outage condition.
12 6 C. Toltec Power Partnership Toltec Power Project (Phase One) Figure 1 shows the one-line diagram of the proposed Toltec Power Project. A summary of the total plant output is as follows: Proposed Toltec Power Project Phase One Two 2x1 Combined-Cycle Units 4 Gas Units (G1-G2) 155 MW (each) 2 Steam Unit (ST) 250 MW (each) Auxiliary Load Totals 24 MW Net Phase One Plant Output 1,096 MW The proposed project s 500-kV substation (Toltec) bus will be interconnected to the Saguaro 500-kV bus by a single 500-kV transmission line. Two 500/345-kV transformer banks will be installed at the project s proposed 500-kV bus and the 345-kV bus will be interconnected to the existing South-Westwing 345-kV line by looping the line. Figure 2 illustrates this interconnection. The dynamic data utilized for the Toltec generating units, using the GE PSLF models, as well as customer supporting documentation is shown in Appendix B. D. Power Flow Study To simulate the Arizona Extra High Voltage (EHV) transmission system for analysis, the study used a WSCC 2003 heavy summer and 2004 Light Autumn database modified by APS, WAPA, and TEP to reflect more current information. Heavy summer and light autumn load forecast are shown in Table 1. The following scenarios were considered: 2003 Heavy Summer load forecast scenarios: (a) No Toltec Power Project (b) Power displaced in southern and eastern Arizona (c) Power displaced in central Arizona (d) Power displaced in western Arizona (e) Power displaced in northern Arizona (f) Power displaced throughout Arizona (scaled down) (g) Load increased throughout Desert Southwest (heat wave assumption) (h) Power exported to California 2003 Light Autumn load forecast scenarios: (a) No Toltec Power Project (b) Power displaced in southern and eastern Arizona (c) Power displaced in central Arizona (d) Power displaced in western Arizona
13 7 (e) Power displaced in northern Arizona (f) Power displaced throughout Arizona (scaled down) (g) Power exported to California Load flow studies were conducted under 2003 heavy summer and 2004 light autumn conditions. Further description of the case assumptions follows: 2003 Heavy Summer a) Heavy Summer without the Toltec Power project, Case heavy summer load with 2,305 MW East-of-River (EOR) and 6,171 MW West-of-River (WOR) power flow. Arizona exports were set at 2,567 MW with high central, eastern, northern, and southern Arizona area generation patterns. Approximately 4,000 MW of new proposed projects in the Palo Verde area were assumed to be off-line for this assessment as a result of export limitations after reserving capacity for the Toltec Power Project. b) Heavy Summer with the Toltec Power project displacing southern and eastern Arizona generation, Case 2 Case 1 revised to include the proposed 1,096 MW Toltec Power project. Generation displacement was taken by reducing output at the Apache, Cholla, and Coronado generating facilities. c) Heavy Summer with the Toltec Power project displacing central Arizona generation, Case 3 Case 1 revised to include the proposed 1,096 MW Toltec Power project. Generation displacement was taken by reducing output at the West Phoenix and Desert Basin generating facilities. d) Heavy Summer with the Toltec Power project displacing western Arizona generation, Case 4 Case 1 revised to include the proposed 1,096 MW Toltec Power project. Generation displacement was taken by reducing output at the Arlington and Harquahala generating facilities. e) Heavy Summer with the Toltec Power project displacing northern Arizona generation, Case 5 Case 1 revised to include the proposed 1,096 MW Toltec Power project. Generation displacement was taken by reducing output at the Four Corners and Navajo generating facilities.
14 8 f) Heavy Summer with the Toltec Power project displacing entire Arizona generation, Case 6 Case 1 revised to include the proposed 1,096 MW Toltec Power project. Generation displacement was taken by scaling down output from all Arizona generating facilities. g) Heavy Summer with increasing Desert Southwest load to account for the Toltec Power project, Case 7 Case 1 revised to include the proposed 1,096 MW Toltec Power project. Loads from the Desert Southwest region (Arizona, Nevada, and New Mexico) were scaled-up to balance output from the Toltec Power Project. h) Heavy Summer with the Toltec Power project exporting power to California, Case 8 Case 1 revised to include the proposed 1,096 MW Toltec Power project. Exports to California were increased to balance output from the Toltec Power Project Light Autumn a) Light Autumn without the Toltec Power project, Case Light Autumn load with 2,305 MW East-of-River (EOR) and 6,171 MW West-of-River (WOR) power flow. Arizona exports were set at 2,567 MW with high central, eastern, northern, and southern Arizona area generation patterns. Approximately 4,000 MW of new proposed projects in the Palo Verde area were assumed to be off-line for this assessment as a result of export limitations after reserving capacity for the Toltec Power Project. b) Light Autumn with the Toltec Power project displacing southern and eastern Arizona generation, Case 10 Case 9 revised to include the proposed 1,096 MW Toltec Power project. Generation displacement was taken by reducing output at the Apache, Cholla, and Coronado generating facilities. c) Light Autumn with the Toltec Power project displacing central Arizona generation, Case 11 Case 9 revised to include the proposed 1,096 MW Toltec Power project. Generation displacement was taken by reducing output at the West Phoenix and Desert Basin generating facilities.
15 9 d) Light Autumn with the Toltec Power project displacing western Arizona generation, Case 12 Case 9 revised to include the proposed 1,096 MW Toltec Power project. Generation displacement was taken by reducing output at the Arlington and Harquahala generating facilities. e) Light Autumn with the Toltec Power project displacing northern Arizona generation, Case 13 Case 9 revised to include the proposed 1,096 MW Toltec Power project. Generation displacement was taken by reducing output at the Four Corners and Navajo generating facilities. f) Light Autumn with the Toltec Power project displacing entire Arizona generation, Case 14 Case 9 revised to include the proposed 1,096 MW Toltec Power project. Generation displacement was taken by scaling down output from all Arizona generating facilities. g) Light Autumn with the Toltec Power project exporting power to California, Case 15 Case 9 revised to include the proposed 1,096 MW Toltec Power project. Exports to California were increased to balance output from the Toltec Power Project HEAVY SUMMER CONDITIONS ARIZONA AREA TOTAL GENERATION, IMPORT, LOAD AND LOSSES (MW) Case 1 Case 2 Case 3 Case 4 Case 5 Case 6 Case 7 Case 8 SCIT 13,001 13,002 13,000 13,002 13,006 13,002 13,001 13,951* EOR 2,305 2,314 2,328 2,344 2,174 2,294 2,454 2,871 WOR 6,171 6,190 6,147 6,135 6,173 6,164 6,150 7,008 Gen 17,981 17,997 17,939 17,947 17,974 17,903 19,016 19,029 Export 2,567 2,568 2,567 2,567 2,567 2,568 2,916 3,567 Load 14,872 14,916 14,802 14,802 14,892 14,802 15,521 14,892 Losses The table above identifies the Arizona area system demand and resources modeled for the 2003 Heavy Summer load forecast conditions. SCIT limitations are set to 13,200 MW as identified by the SCIT nomogram. Since the SCIT value for Case 8 exceeds this limitation, the Toltec Power Project will be competing for available SCIT capacity under
16 10 this generation dispatch scenario. Both East-of-River and West-of-River conditions are within the allowable limit indicating that reductions on the Midway-Vincent or North of Lugo paths can be made to accommodate the Toltec Power Project. Impact identification will be limited to only the Arizona area since(????). Simulations For each of the eight cases, load flow simulations of the bulk power system were conducted for the base case, single contingencies and double contingencies for lines and transformer banks to determine impacts to the Arizona EHV system. A total of 241 single contingencies in the Arizona EHV system were studied with system performance monitored for planning criteria violations on the Arizona 500-kV, 345-kV, 230-kV, and 138-kV systems. In particular, special attention was placed on identifying impacts on the APS, SRP, and TEP transmission facilities. E. Transient Stability Study Stability studies were conducted for the following NERC category B and C contingencies. Category B contingencies simulated are as follows: 1. A four-cycle three-phase fault on the proposed Toltec 500-kV bus followed by loss of the Saguaro-Toltec 500-kV line. 2. A four-cycle three-phase fault on the Saguaro 500-kV bus followed by loss of the Cholla-Saguaro 500-kV line. 3. A four-cycle three-phase fault on the Saguaro 500-kV bus followed by loss of the Saguaro-Tortolita 500-kV line. 4. A four-cycle three-phase fault on the Perkins 500-kV bus followed by loss of the Perkins-Mead 500-kV line. 5. A four-cycle three-phase fault on the Westwing 500-kV bus followed by loss of the Navajo-Westwing 500-kV line. 6. A four-cycle three-phase fault on the Westwing 500-kV bus followed by loss of the Yavapai-Westwing 500-kV line. 7. A four-cycle three-phase fault on the Westwing 500-kV bus followed by loss of the Palo Verde-Westwing No kV line. 8. A four-cycle three-phase fault on the Moenkopi 500-kV bus followed by loss of the Moenkopi-El Dorado 500-kV line.
17 11 9. A four-cycle three-phase fault on the Palo Verde 500-kV bus followed by loss of the Palo Verde-Devers 500-kV line. 10. A four-cycle three-phase fault on the Palo Verde 500-kV bus followed by loss of the Palo Verde-North Gila 500-kV line. 11. A four-cycle three-phase fault on the proposed Toltec 345-kV bus followed by loss of the Westwing-Toltec 345-kV line. 12. A four-cycle three-phase fault on the proposed Toltec 345-kV bus followed by loss of the South-Toltec 345-kV line. 13. A four-cycle three-phase fault on the Liberty 345-kV bus followed by loss of the Liberty-Peacock 345-kV line. 14. A four-cycle three-phase fault on the proposed Toltec 500-kV bus followed by loss of one Toltec 500/345-kV transformer bank. 15. A four-cycle three-phase fault on the Saguaro 500-kV bus followed by loss of one Saguaro 500/115-kV transformer bank. 16. A four-cycle three-phase fault on the proposed Toltec 500-kV bus followed by loss of one 2x1 Toltec combined-cycle unit (548 MW). 17. A four-cycle three-phase fault on the Palo Verde 500-kV bus followed by loss of one Palo Verde generating unit. Category C contingencies simulated are as follows 1. A four-cycle three-phase fault on the Westwing 345-kV bus followed by simultaneous loss of the Westwing-Toltec 345-kV and Westwing-Liberty 230-kV lines. 2. A four-cycle three-phase fault on the Westwing 500-kV bus followed by simultaneous loss of both Palo Verde-Westwing 500-kV lines. 3. A four-cycle three-phase fault on the Westwing 500-kV bus followed by simultaneous loss of the Yavapai-Westwing and Westwing-Navajo 500-kV lines. These twenty contingencies have been identified to be the most critical cases for stability analysis of the proposed Toltec Power project. Switch decks were developed to simulate each complete contingency. Each contingency run contains a one second predisturbance, a four-cycle faulted condition simulated by faulting a bus, flashing series capacitor bank, clearing the line and re-inserting the series capacitor bank. Although
18 12 series capacitor flash-over will only occur as a result of increase voltage or increased current and is highly dependant on the short-circuit duty current, the simulations assumed the capacitors would flash in order to simulate the worst case scenario. The same Toltec Power project cases used for power flow studies were also used for the stability study. F. Post Transient Study The power flow study voltage results were used as a screen to identify those contingencies that may require additional post transient voltage studies. Contingencies identified in the power flow to have a voltage drop in excess of 5% where the Toltec Power project either triggers or aggravates the voltage drop for single and double contingencies were selected for post-transient simulation. A total of thirteen single contingencies were identified to require a post-transient voltage study performed. G. Short Circuit Duty Study <NEED TO DETERMINE IF THIS ASSESSMENT SHOULD BE INCLUDED IN THE SIS OR PERFORMED AS PART OF THE FACILITIES STUDY> STUDY RESULTS A. Power Flow Study Power flow studies performed for the various scenarios identified a number of transmission facilities that are adversely impacted by the addition of the Toltec Power Project. Tables 2-1 through 2-7 summarize the power flow results. Below is a detailed description of each facility impacted and potential system mitigation that should be addressed by the corresponding Utility owner in the Facilities Study: 1) Cholla 500/345-kV No.1 & No.2 Transformer Banks (APS) Loading levels on the Cholla 500/345-kV No.1 and No.2 transformer banks are well within the 500 MVA nameplate ratings prior to the addition of the Toltec Power project. With the Toltec Power project, loadings exceed the transformer nameplate ratings under two single contingency conditions for all scenarios studied in the Heavy Summer except displacement of power in southern and eastern Arizona. Under all other scenarios, outage of the Coronado-Silver King 500-kV line results in loading the banks up to 116%. Outage of a single Cholla 500/345-kV bank results in loading the remaining Cholla 500/345-kV bank up to 118%. Transformer bank emergency ratings are not shown in the GE data sets. It is recommended to review the transformer banks in order to determine if emergency
19 13 ratings can be applied to mitigate these overloads. A third Cholla 500/345-kV transformer bank will be required to mitigate overloads if it is determined that emergency ratings cannot be applied. 2) Cholla 345/230-kV Transformer Bank (APS) The study identified two existing contingencies that result in overloading the Cholla 345/230-kV transformer bank in excess of the 203 MVA rating prior to the addition of the Toltec Power project. With the addition of the Toltec Power project, the study identified additional contingencies that result in overloading the transformer bank beyond the nameplate rating for all scenarios studied except power displacement in southern and eastern Arizona. Scenario Number of Contingencies Highest Loading No Toltec Scanario 2 112% (227 MVA) Displace Central Arizona 6 118% (240 MVA) Displace Western Arizona % (252 MVA) Displace Northern Arizona 6 119% (242 MVA) Displace Entire Arizona 7 121% (245 MVA) Increase DSW load 8 122% (247 MVA) Export Power to California % (258 MVA) Transformer bank emergency rating is not shown in the GE data sets. It is recommended to review the transformer bank in order to determine if an emergency rating can be applied to mitigate these overloads. A second Cholla 345/230-kV transformer bank will be required to mitigate overloads if it is determined that emergency ratings cannot be applied 3) Four Corners 500/345-kV Transformer Bank Loading on the Four Corners 500/345-kV transformer bank is well within the 840 MVA nameplate ratings prior to the addition of the Toltec Power project. With the Toltec Power project displacing power in Northern Arizona (Navajo and Four Corner), loadings exceed the transformer nameplate rating under base case and one single contingency condition. Base case loading was increased from 551 MVA up to 1026 MVA or 122%. Outage of the Coronado-Silver King 500-kV line resulted in loading the bank up to 1099 MVA or 131%. No adverse impacts were identified under all other scenarios indicating problem is attributed to generation displacement conditions modeled and not solely attributed to the Toltec Power project. Transformer bank emergency ratings are not shown in the GE data sets. It is recommended to review the transformer banks in order to determine if emergency ratings can be applied to mitigate these overloads. A second Four Corners 500/345kV
20 14 transformer bank will be required to mitigate overloads if it is determined that displacement scenario is valid and emergency ratings cannot be applied. 4) Country Club-Glendale 230-kV Transmission Line The study identified two existing contingencies that result in overloading the Country Club-Glendale 230-kV transmission line in excess of the 1433 amp emergency rating prior to the addition of the Toltec Power project. Loading levels were identified to be at 109% and 132% of the 1433 amp emergency rating under outage of the Country Club-Lincoln Street 230-kV and Lincoln Street-West Phoenix 230-kV transmission lines respectively. With the addition of the Toltec Power project and generation displacement in central Arizona, loading on the Country Club-Glendale 230-kV transmission line exceeds the 1000 amp allowable limit by 35% in the base case. The existing contingency overloads identified above were found to be aggravated under power displacement in southern and eastern and central Arizona scenarios as well as in the load increase scenario. In addition, two new single contingency overloads were identified in the central Arizona displacement and load increase scenarios. Line re-conductor may be required as a means to mitigate this overload if it is determined that the displacement scenarios impacting this line are valid. 5) Glendale-Agua Fria 230-kV Transmission Line The study identified four existing contingencies that result in overloading the Glendale-Agua Fria 230-kV transmission line in excess of the 1433 amp emergency rating prior to the addition of the Toltec Power project. With the addition of the Toltec Power project and generation displacement in central Arizona, loading on the Glendale-Agua Fria 230-kV transmission line exceeds the 1150 amp allowable limit by 28% in the base case. Base case loading is also exceeded, by 10%, under the load increase scenario. All four existing contingency overloads identified above were found to be aggravated under power displacement in southern and eastern and central Arizona scenarios as well as in the load increase scenario. Line re-conductor may be required as a means to mitigate this overload if it is determined that the displacement scenarios impacting this line are valid. 6) Pinnacle Peak (APS) 230-kV Bus Tie The study identified nine existing contingencies that result in overloading the Pinnacle Peak APS 230-kV bus-tie in excess of the 1700 amp emergency rating prior to the addition of the Toltec Power project.
21 15 With the addition of the Toltec Power project and generation displacement in central Arizona, loading on the Pinnacle Peak 230-kV bus-tie exceeds the 1600 amp allowable limit by 3% in the base case. All nine existing single contingency overloads identified above were found to be aggravated under power displacement at central Arizona and under increased DSW load scenarios. In addition, ten new single contingency overloads were identified under the central Arizona generation displacement scenario. Bus-tie upgrades may be required as a means to mitigate these overloads if it is determined that the displacement scenarios are valid. 7) Agua Fria-Westwing 230-kV Transmission Line The study identified nine existing contingencies that result in overloading the Agua Fria-Westwing 230-kV transmission line in excess of the 1320 amp rating prior to the addition of the Toltec Power project. No emergency loading capability is identified to be available in the GE dataset. With the addition of the Toltec Power project and generation displacement in central Arizona, loading on the Agua Fria-Glendale 230-kV transmission line exceeds the 1230 amp allowable limit by 9% in the base case. Existing single contingency overloads identified above were found to be aggravated under power displacement in southern and eastern and central Arizona scenarios as well as in the DSW load increase scenario. In addition, eleven new single contingency overloads were identified under generation displacement at southern and eastern Arizona. Generation displacement at western Arizona resulted in four new single contingency overloads, displacement in Northern Arizona resulted in five new single contingency overloads and increased DSW load scenario resulted in 7 new single contingency overloads. It is recommended to review the transmission line in order to determine if emergency ratings can be applied to mitigate these overloads. Line re-conductor may be required as a means to mitigate these overloads if it is determined that the displacement scenarios impacting this line are valid and that emergency ratings cannot be applied 8) Cholla-Pinnacle Peak 345-kV Transmission Line The study identified two existing contingencies that result in overloading the Cholla- Pinnacle Peak 345-kV transmission line in excess of the 1310 amp emergency rating prior to the addition of the Toltec Power project. With the addition of the Toltec Power project loading on the Cholla-Pinnacle Peak 345-kV transmission line exceeds the 1004 amp allowable limit in the base case for all scenarios evaluated except power displacement at southern and eastern Arizona. Existing single contingency overloads identified above were found to be aggravated under all scenarios evaluated except power displacement in southern and eastern
22 16 Arizona. In addition, two new single contingency overloads were identified under all scenarios evaluated except generation displacement at southern and eastern Arizona. Line re-conductor may be required as a means to mitigate the new base case overload and single contingency overloads identified if it is determined that the displacement scenarios impacting this line are valid. 9) Cholla-Preacher Canyon 345-kV Transmission Line The study identified existing base case and two single contingency overloads on Cholla-Preacher Canyon 345-kV transmission prior to the addition of the Toltec Power project. With the addition of the Toltec Power project base case loading on the Cholla- Preacher Canyon 345-kV transmission line is increased from 104% up to 116% for all scenarios evaluated except power displacement at southern and eastern Arizona. Existing single contingency overloads identified above were found to be aggravated under all scenarios evaluated except power displacement in southern and eastern Arizona. In addition, a new single contingency overload was identified under all scenarios evaluated except generation displacement at southern and eastern and central Arizona. Line re-conductor may be required as a means to mitigate the increased base case overload and single contingency overloads identified if it is determined that the displacement scenarios impacting this line are valid. 10) Preacher Canyon-Pinnacle Peak 345-kV Transmission Line The study did not identify any overloads on Preacher Canyon-Pinnacle Peak 345-kV transmission line prior to the addition of the Toltec Power project. With the addition of the Toltec Power project loading on the Preacher Canyon- Pinnacle Peak 345-kV transmission line exceeds the 1004 amp allowable limit by up to 8% in the base case for all scenarios evaluated except power displacement at southern and eastern Arizona. In addition, three new single contingencies were identified to load the Preacher Canyon-Pinnacle Peak 345-kV transmission line in excess of the 1310 amp emergency rating. Line re-conductor may be required as a means to mitigate the new base case and single contingency overloads identified if it is determined that the displacement scenarios impacting this line are valid.
23 17 11) Cholla-Leupp 230-kV Transmission Line The study identified one existing contingency that results in overloading the Cholla- Leupp 230-kV transmission line in excess of the 720 amp rating prior to the addition of the Toltec Power project. With the addition of the Toltec Power project, the existing single contingency overload identified above was found to be aggravated under all scenarios evaluated except power displacement in southern and eastern Arizona. In addition, a new single contingency overload was identified under all scenarios evaluated except generation displacement at southern and eastern, central, and northern Arizona as well as the increased DSW load scenario. Line re-conductor may be required as a means to mitigate these two single contingency overloads identified if it is determined that the displacement scenarios impacting this line are valid. 12) Leupp-Coconino 230-kV Transmission Line The study did not identify any overloads on Leupp-Coconino 345-kV transmission line prior to the addition of the Toltec Power project. With the addition of the Toltec Power project, up to two new single contingency overloads were identified under all scenarios evaluated except generation displacement at southern and eastern Arizona. Line re-conductor may be required as a means to mitigate these two new single contingency overloads identified if it is determined that the displacement scenarios impacting this line are valid. 13) Moenkopi-El Dorado 500-kV Transmission Line The study identified one existing contingency that results in overloading the Moenkopi-El Dorado 500-kV transmission line in excess of the 1900 amp rating (by 2%) prior to the addition of the Toltec Power project. With the addition of the Toltec Power project, the existing single contingency overload was identified to be aggravated under generation displacement of central Arizona, increased DSW load, and export to California scenarios. Outage of the Navajo-Crystal 500-kV line results in loading the Moenkopi-El Dorado 500-kV line up to 2459 amps which is in excess of the 1900 amp rating as limited by series capacitors. Upgrades to series capacitor may be required as a means to mitigate the new single contingency overload identified if it is determined that the export scenario impacting this line is valid.
24 18 14) Navajo-Crystal 500-kV Transmission Line The study did not identify any overloads on Navajo-Crystal 500-kV transmission line prior to the addition of the Toltec Power project. With the addition of the Toltec Power project, a new single contingency overload was identified under the export to California scenario. Outage of the Moenkopi-El Dorado 500-kV line results in loading the Navajo-Crystal 500-kV line up to 2382 amps which is in excess of the 2200 amp emergency rating as limited by series capacitors. Upgrades to series capacitor may be required as a means to mitigate the new single contingency overload identified if it is determined that the export scenario impacting this line is valid. 15) Yavapai-Verde North 230-kV Transmission Line The study identified two existing contingencies that results in overloading the Yavapai-Verde N 230-kV transmission line in excess of the 530 amp rating (by 25%) prior to the addition of the Toltec Power project. With the addition of the Toltec Power project, the existing single contingency overloads identified above were found to be aggravated by 1% to 7% under DSW load increase and export to California scenarios. Line re-conductor may be required as a means to mitigate the increased single contingency overload identified if it is determined that the displacement scenarios impacting this line are valid. 16) Saguaro-Tatmomli 230-kV Transmission Line The study identified one existing contingency that results in overloading the Saguaro- Tatmomli 230-kV transmission line in excess of the 720 amp rating (by 25%) prior to the addition of the Toltec Power project. With the addition of the Toltec Power project, the existing single contingency overload identified above was found to be aggravated by 15% to 27% under all scenarios evaluated except power displacement in southern and eastern and central Arizona. Line re-conductor may be required as a means to mitigate the increased single contingency overload identified if it is determined that the displacement scenarios impacting this line are valid.
25 19 17) Santa Rosa-Tatmomli 230-kV Transmission Line The study identified one existing contingency that results in overloading the Santa Rosa-Tatmomli 230-kV transmission line in excess of the 720 amp rating (by 17%) prior to the addition of the Toltec Power project. With the addition of the Toltec Power project, the existing single contingency overload identified above was found to be aggravated by 16% to 28% under all scenarios evaluated except power displacement in southern and eastern and central Arizona. Line re-conductor may be required as a means to mitigate the increased single contingency overload identified if it is determined that the displacement scenarios impacting this line are valid. 18) Lone Peak-Sunnyslope 230-kV Transmission Line The study identified one existing contingency that results in overloading the Lone Peak-Sunnyslope 230-kV transmission line in excess of the 1368 amp emergency rating (by 1%) prior to the addition of the Toltec Power project. With the addition of the Toltec Power project, the existing single contingency overload identified above was found to be aggravated by 1% to 6% under all scenarios evaluated except power displacement in southern and eastern and northern Arizona and under the Arizona generation reduction scenario. Line re-conductor may be required as a means to mitigate the increased single contingency overload identified if it is determined that the displacement scenarios impacting this line are valid. 19) Surprise-Westwing 230-kV Transmission Line The study did not identify any overloads on Surprise-Westwing 345-kV transmission line prior to the addition of the Toltec Power project. With the addition of the Toltec Power project, two new single contingency overloads were identified under the power displacement in central Arizona scenario. Loading is increased from 1755 amps (87% of emergency rating) up to 2037 amps (101% of emergency rating). Line re-conductor may be required as a means to mitigate the new single contingency overload identified if it is determined that the displacement scenario impacting this line are valid.
26 20 20) Corbell-Kyrene 230-kV Transmission Line The study identified one existing contingency that results in overloading the Corbell- Kyrene 230-kV transmission line in excess of the 1600 amp rating prior to the addition of the Toltec Power project. No emergency loading capability is identified to be available in the GE dataset. With the addition of the Toltec Power project, the existing single contingency overload identified above was found to be aggravated under power displacement in central Arizona and under the DSW load increase scenarios. It is recommended to review the transmission line in order to determine if emergency ratings can be applied to mitigate these overloads. Line re-conductor may be required as a means to mitigate these overloads if it is determined that the displacement scenarios impacting this line are valid and that emergency ratings cannot be applied. 21) Santan-Corbell 230-kV Transmission Line The study identified one existing contingency that results in overloading the Santan- Corbell 230-kV transmission line in excess of the 1100 amp emergency rating prior to the addition of the Toltec Power project. With the addition of the Toltec Power project, the existing single contingency overload identified above was found to be aggravated under all scenarios evaluated except power displacement in southern and eastern and northern Arizona and under the Arizona generation reduction scenario. Line re-conductor may be required as a means to mitigate the increased single contingency overload identified if it is determined that the displacement scenarios impacting this line are valid. 22) Silver King-Goldfield 230-kV Transmission Line The study identified one existing contingency that results in overloading the Silver King-Goldfield 230-kV transmission line in excess of the 825 amp rating prior to the addition of the Toltec Power project. With the addition of the Toltec Power project, the existing single contingency overload identified above was found to be aggravated under all scenarios evaluated except power displacement in southern and eastern Arizona and under the Arizona generation reduction scenario. Line re-conductor may be required as a means to mitigate the increased single contingency overload identified if it is determined that the displacement scenarios impacting this line are valid.
Reliability Must-Run Analysis th BTA Presentation. Bob Smith Manager Transmission Planning June 6, 2006
Reliability Must-Run Analysis 2006 2015 4 th BTA Presentation Bob Smith Manager Transmission Planning June 6, 2006 Outline of Presentation 2006 RMR Study Process Description of network and constraint SIL/MLSC
More information100 MW Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility
More informationTransWest Express Project
TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company
More informationQ95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.
A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final
More informationSDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report
SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report San Diego Gas & Electric, a Sempra Energy Utility SDGE HVDC Phase 1 Project No. 101512 Revision 01 11/29/2018 SDG&E High
More informationMILLIGAN SOLAR PROJECT
February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission
More informationTransmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona
Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff
More informationCUSTOMER/ TWIN ARROWS PROJECT
A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset
More informationQ92 Asarco Interconnection
A subsidiary of Pinnacle West Capital Corporation Q92 Asarco Interconnection Feasibility Study APS Contract No. 52239 By Arizona Public Service Company Transmission Planning July 29, 2010 Prepared by Utility
More informationElbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI
Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility
More informationInterconnection System Impact Study Report Request # GI
Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010
More informationTHE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS
THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive
More informationTRANSMISSION PLANNING CRITERIA
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing
More informationProject #148. Generation Interconnection System Impact Study Report
Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection
More informationGenerator Interconnection System Impact Study For
Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...
More informationWestern Area Power Administration Sierra Nevada Region
Western Area Power Administration Sierra Nevada Region 2014 Annual Ten-Year Transmission Plan Assessment Report November 20, 2014 For information or questions regarding this Transmission Assessment Report,
More informationSystem Impact Study Report
Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS
More informationTransmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015
No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the
More informationFour Corners 230kV Generator Interconnections Group
A subsidiary of Pinnacle West Capital Corporation Four Corners kv Generator Interconnections Group Feasibility Study APS Contract Nos. - By Arizona Public Service Company Transmission Planning September,
More informationAPPENDIX F: Project Need and Description
APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was
More informationProject #94. Generation Interconnection System Impact Study Report Revision
Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection
More informationAPS and Regional Transmission Systems Overview
APS and Regional Transmission Systems Overview Bob Smith Director Energy Delivery Asset Management and Planning Agenda About APS Regional Transmission System Overview APS Transmission System Overview Industry
More informationConsulting Agreement Study. Completed for Transmission Customer
Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...
More informationGateway South Transmission Project
Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive
More informationPID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation
PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date
More informationService Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #
Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists
More informationWestern Area Power Administration Sierra Nevada Region
Western Area Power Administration Sierra Nevada Region 2013 Annual Ten-Year Transmission Plan Assessment Report December 1, 2013 For information or questions regarding this Transmission Assessment Report,
More informationGenerator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood
Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents
More informationInterconnection Feasibility Study Report GIP-226-FEAS-R3
Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power
More informationDUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY
DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION
More informationFeasibility Study for the Q MW Solar Project
Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC
More informationInterconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS
Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia
More informationQ217 Generator Interconnection Project
Q217 Generator Interconnection System Impact Study APS Contract No. 52588 By Arizona Public Service Company Transmission Planning November 25, 2013 Version 2.0 Prepared by Utility System Efficiencies,
More informationInterconnection Feasibility Study Report GIP-084-FEAS-R2
Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power
More informationOverview of APS U.S.-JORDAN ELECTRIC POWER TRANSMISSION PARTNERSHIP EXECUTIVE EXCHANGE VISIT. Bob Smith
Overview of APS U.S.-JORDAN ELECTRIC POWER TRANSMISSION PARTNERSHIP EXECUTIVE EXCHANGE VISIT Bob Smith Director Energy Delivery Asset Management and Planning Agenda About APS Regional Transmission System
More informationMidway/Monument Area TTC Study
Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny
More informationQ85 Generation Interconnection
A subsidiary of Pinnacle West Capital Corporation Q85 Generation Interconnection Interconnection Facilities Study AMENDED APS Contract No. 52386 By Arizona Public Service Company Transmission Planning
More informationFour Corners Queue Transmission Interconnection Study
Four Corners Queue Transmission Interconnection Study Facility Study Results By Arizona Public Service Company Transmission Planning & Interconnection Development March 22, 2016 Version 1 FACILITIES STUDY
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:
More informationGeneration Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation
Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY
More informationFeasibility Study Report
Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility
More informationInterconnection Feasibility Study Report GIP-222-FEAS-R3
Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.
More informationTransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis
TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis July 25, 2018 Table of Contents 1. Introduction... 5 1.1. Project Description and
More informationFeasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection
Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection
More informationSPS Planning Criteria and Study Methodology
SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability
More informationInterconnection Feasibility Study Report GIP-157-FEAS-R2
Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia
More informationAMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA
AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions
More informationEL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS
EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004
More informationTransmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014
Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder
More informationFalcon-Midway 115 kv Line Uprate Project Report
Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50
More informationEl PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS
El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the
More informationMerger of the generator interconnection processes of Valley Electric and the ISO;
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric
More informationSupplemental Report on the NCTPC Collaborative Transmission Plan
Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for
More informationNorth Gila Generator Interconnection
A subsidiary of Pinnacle West Capital Corporation North Gila Generator Interconnection System Impact Study APS Contract Nos. 52107 By Arizona Public Service Company Transmission Planning October 2, 2009
More informationFeasibility Study Report
Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019
More informationXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS
XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS System Operations Department System Planning Section June 2001 TABLE OF CONTENTS 1.0 Executive Summary...Page
More informationCOLORADO SPRINGS UTILITIES RESPONSE TO Xcel ENERGY INTERCONNECTION SYSTEM IMPACT STUDY REQUEST # GI , RESTUDY 1 (August 6, 2009)
COLORADO SPRINGS UTILITIES RESPONSE TO Xcel ENERGY INTERCONNECTION SYSTEM IMPACT STUDY REQUEST # GI-2007-12, RESTUDY 1 (August 6, 2009) On June 15, 2009 Xcel Energy released a restudy of a System Impact
More informationQ87 Generation Interconnection
A subsidiary of Pinnacle West Capital Corporation Version 1.0 Q87 Generation Interconnection Interconnection Facilities Study APS Contract No. 52365 By Arizona Public Service Company Transmission Planning
More informationTable of Contents. Purpose. Eldorado Intertie and System (Eldorado- Moenkopi) Scheduling at Willow Beach. Operating Procedure
No. 6930 Table of Contents Purpose... 1 1. Limits, Ratings, & Effectiveness Factors... 2 2. Contingency Operations... 2 2.1 Transmission Lines Outages... 2 2.2 APS Terminal Equipment Outages... 2 2.3 SCE
More informationFIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION
PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection
More informationConnection Engineering Study Report for AUC Application: AESO Project # 1674
APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System
More informationAPS/SRP Stakeholder Meeting For Transmission Planning FERC Order 890 SRP Attachment K APS Attachment E
APS/SRP Stakeholder Meeting For Transmission Planning FERC Order 890 SRP Attachment K APS Attachment E SRP Facility Scottsdale, AZ December 18 th, 2014 9:00 11:00 A.M. Agenda 1. Welcome, Introductions,
More informationSYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company
SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report
More informationSYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company
SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This
More informationDFO STATEMENT OF NEED REPORT
APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading
More informationInterconnection Feasibility Study Report GIP-IR373-FEAS-R1
Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia
More informationCity of Palo Alto (ID # 6416) City Council Staff Report
City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building
More informationPJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008
PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral
More informationStability Study for the Mt. Olive Hartburg 500 kv Line
Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.
More informationUpdated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers
Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,
More informationVerde Transmission, LLC. Verde Project. System Impact Study Report
Verde Transmission, LLC Verde Project System Impact Study Report March 2017 Prepared by: Public Service Company of New Mexico Foreword This report was prepared for Verde Transmission, LLC by the PNM Transmission/
More informationPRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES
PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES 1 PRESENTATION OUTLINE Generation System Demand Outlook Existing Generation Resources Transmission System National Interconnected
More informationDunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study
` Dunvegan Hydroelectric Project For Glacier Power Limited Preliminary Interconnection Study Prepared by Pung Toy, P. Eng. and Ata Rehman, P. Eng. September 24, 2004 Table of Contents Table of Contents...
More informationQ51 Generation Interconnection
Q51 Generation Facilities Study Results APS Contract No. 52395 By Arizona Public Service Company Transmission Planning September 4, 2013 [Version 1.0] Q51 FACILITIES STUDY TABLE OF CONTENTS Contents 1.
More informationValley - Rainbow Interconnection Project Feasibility Study Report
Attachment A Valley - Rainbow Interconnection Project Feasibility Study Report A Joint Study Effort of San Diego Gas & Electric (SDG&E) and Southern California Edison (SCE) in Cooperation with the California
More informationEvaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection
Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba
More informationFeasibility Study Report
Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014
More informationArizona Transmission Challenges
Power Task Force Agenda Number 2. Arizona Transmission Challenges Central Arizona Water Conservation District Power Committee Presentation May 18, 2017 Transmission Planning Efforts NATIONAL Section 368
More informationOperational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks
Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and
More informationPJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study
PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional
More informationFeasibility Study for the Q MW Solar Project
Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC
More informationStatus of PNM s Completed Transmission Construction Projects 11/30/2017
Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information
More informationCONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation
CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent
More informationISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements
Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner
More informationGuide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.
Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...
More informationGeorgia Transmission Corporation Georgia Systems Operations Corporation
Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia
More informationaps January 29, 2016 Docket Control Arizona Corporation Commission 1200 West Washington Street Phoenix, Arizona 85007
aps Kerri A. Carnes Manager State Regulation and Compliance Mail Station 9712 PO Box 53999 Phoenix, Arizona 85072-3999 Tel 602-250-3341 Kerri.Carnes@aps.com January 29, 2016 Docket Control Arizona Corporation
More informationThe Long-Range Transmission Plan
The Long-Range Transmission Plan 2015 2025 Matt Koenig Presentation to ESPWG / TPAS October 29 th, 2015 Long-Range Transmission Plan Driver of the Plan is to maintain local reliability 10-year planning
More informationSupplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications
Supplement to 2013-2014 ISO Transmission Plan Harry Allen-Eldorado Project Description and Functional Specifications Description and Functional Specifications of Proposed Economically Driven Harry Allen
More informationTransmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation
Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT
More informationGeneration Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.
Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project April 23, 2003 Introduction Eurus originally requested an interconnection
More informationInterconnection System Impact Study Final Report February 19, 2018
Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen
More informationEmera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC
OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC
More informationATTACHMENT Y STUDY REPORT
Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation
More information2012 LOCAL TRANSMISSION PLAN:
Colorado PUC E-Filings System 2012 LOCAL TRANSMISSION PLAN: TRANSMISSION COORDINATION AND PLANNING COMMITTEE ANNUAL TRANSMISSION ASSESSMENT FOR BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, L.P., D/B/A
More informationDETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT
DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power
More informationTransmission from East to West Transmission Policy Institute The History, Present and Future Of Electric Transmission Planning
Transmission from East to West Transmission Policy Institute 2011 The History, Present and Future Of Electric Transmission Planning OVERVIEW 1. Energy policy overview the intersection of state and federal
More informationRocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH
Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No. 17-035-40 Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct
More informationInterconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado
Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission
More informationTransmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting
Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid
More information