Project #94. Generation Interconnection System Impact Study Report Revision

Size: px
Start display at page:

Download "Project #94. Generation Interconnection System Impact Study Report Revision"

Transcription

1 Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning

2 Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection Service Results...3 Network Resource Interconnection Service Results...4 Definitions...6 Energy Resource Interconnection Service...6 Network Resource...6 Network Resource Interconnection Service...6 Generator and Interconnection Data...8 Study Parameters...9 Senior Queue Generator Assumptions...9 Steady State Power Flow Analysis...10 Method...10 Results...10 Mitigation...10 Transient Stability Analysis...11 Method...11 Results...11 PV Analysis...13 Method...13 Results...13 Mitigation...13 Fault Duty Analysis...14 Method...14 Results...14 Mitigation...14 Conclusions...15 N-0 Mitigation...15 N-1 Mitigation...15 N-2 Mitigation...15 Next Steps...15 Attachments

3 Executive Summary NorthWestern Energy ( NWE ) has completed the System Impact Study ( SIS ) for Project #94 ( Generation Project ) near Great Falls, MT. NWE studied your project both as a Network Resource Interconnection Service ( NRIS ) and an Energy Resource Interconnection Service ( ERIS ). The SIS is an in-depth analysis that examines the response of the transmission system to a variety of system operating conditions. NWE is responsible for maintaining acceptable system reliability, and must be certain that system reliability is maintained with the addition of the Generation Project. NWE uses tolerance levels outlined by FERC, NERC, and/or WECC. The SIS uses the following types of analyses: Steady-State Power Flow Post Transient Steady-State Power Flow Transient Stability Fault Duty Reactive Margin The results of the SIS confirm that the addition of 128 MW interconnected to NWE s Great Falls 230 kv Switchyard is feasible only with system improvements. The findings included in this study do not assure the Interconnection Customer that the planned Generation Project will be allowed to operate at full capacity under all operating conditions. NWE cannot guarantee that future analysis will not identify additional problems. Energy Resource Interconnection Service Results ERIS allows the Interconnection Customer to connect the Small Generating Facility to the Transmission System and be eligible to deliver the Small Generating Facility s output using the existing firm or nonfirm capacity of the Transmission System on an as available basis. ERIS does not in and of itself convey any right to deliver electricity to any specific customer or Point of Delivery. The ERIS study is designed to answer two questions: I. What is the maximum allowed output to interconnect without additional network upgrades? Answer: The maximum allowed output to interconnect and move power without additional network upgrades is 0 MW. The Generation Project s SIS high level, non-binding cost estimates for ERIS are the same as the costs presented in Table I of the Revised SIS for Project #53 that was provided to Project #94 on 05/13/2008, with the exception of the following additions: an additional $80k in substation upgrades for metering units; an additional $25k in EMS costs. These additional costs bring the total ERIS high level, non-binding cost estimate to $2.46 million (which includes the ERIS cost of $2.35 million for Project #53). II. What are the necessary upgrades to allow for full output of the Generation Project? Answer: The necessary upgrades are described in the NRIS Results section of this report. 3

4 Network Resource Interconnection Service Results NRIS allows the Interconnection Customer to be designated as a Network Resource, up to the Large Generating Facility s full output, on the same basis as existing Network Resources interconnected to the Transmission Provider s Transmission System. NRIS does not in and of itself convey reservation of transmission service. Any network customer under the Tariff can utilize its network service under the Tariff to obtain delivery of electricity from the Generation Project in the same manner as it accesses Network Resources. The NRIS SIS Study found that the Generation Project contributes to the flows on various line segments that have been required to be built, upgraded, or reconductored by senior queued projects. Senior queued project mitigation that the Generation Project s SIS determined are affected includes: a new 230 kv line from Great Falls to Three Rivers; reconductoring the 100 kv lines from Harlowton to Judith Gap Tap to Judith Gap; building a new 100 kv line from Harlowton to Broadview; upgrading the 230/100 kv transformer at Judith Gap. The Generation Project also triggers the need for: reconductoring the 100 kv line from East Helena to Continental Lime Tap; reconductoring the 100 kv line from Continental Lime Tap to Townsend; reconductoring the 100 kv line from Broadwater Tap to Crow Creek; reconductoring the 100 kv line from Crow Creek to Eustis; adding a 36 MVAr Dynamic VAR device at Ovando 230 kv Switchyard. A non-binding cost estimate to interconnect your project is summarized in Table I. Table I. High Level, Non-Binding Cost Estimates Mitigation and Substation $M Cost New 230 kv Great Falls to Three Rivers 1 $ kv Harlowton to Judith Gap Tap to Judith Gap Reconductor 2 $ kv Martinsdale to Two Dot to Harlowtwon 3 $ New 100 kv Harlowton to Broadview (Ckt 2) 100 kv 4 $ Upgrade the Judith Gap 230/100 kv Transformer 5 $ kv Continental Lime Tap to Townsend Reconductor 6 $ kv Broadwater Tap to Crow Creek Reconductor 7 $ kv Crow Creek to Eustis 8 $ kv Eustis to Trident 9 $ MVAr Dynamic VAR device at Ovando 230 kv Switchyard 10 $ Substation N/A Relay N/A Communications N/A Metering N/A EMS N/A Total $76.6 4

5 Table Notes: 1. The cost allocation for mitigation are based on NWE s Cost Allocation and Refund Methodology, new line is $106,765,086. The Generation Project s share of the new 230 kv line would be $41,277,208. Projects junior to the Generation Project in the queue that affect the MW flow on the line would have to contribute to the costs of the new line. 2. The cost allocation for mitigation are based on NWE s Cost Allocation and Refund Methodology, reconductoring is $5,151,000. The Generation Project s share of the reconductoring would be $1,872,421. Projects junior to the Generation Project in the queue that affect the MW flow on the lines would have to contribute to the costs of reconductoring the lines. 3. The cost allocation for mitigation are based on NWE s Cost Allocation and Refund Methodology, reconductoring is $7,211,400. The Generation Project s share of the reconductoring would be $1,547,692. Projects junior to the Generation Project in the queue that affect the MW flow on the lines would have to contribute to the costs of reconductoring the lines. 4. The cost allocation for mitigation are based on NWE s Cost Allocation and Refund Methodology, new line is $21,925,000. The Generation Project s share of the new line would be $20,097,917. Projects junior to the Generation Project in the queue that affect the MW flow on the new line would have to contribute to the costs of building the new line. 5. The cost allocation for mitigation are based on NWE s Cost Allocation and Refund Methodology, transformer upgrade is $1,700,000. The Generation Project s share of the upgrade would be $1,590,000. Projects junior to the Generation Project in the queue that affect the MW flow on the transformer would have to contribute to the costs of the transformer. 6. The cost allocation for mitigation are based on NWE s Cost Allocation and Refund Methodology, reconductoring is $303,000. Projects junior to the Generation Project in the queue that affect the MW flow on the line would have to contribute to the costs of the reconductoring. 7. The cost allocation for mitigation are based on NWE s Cost Allocation and Refund Methodology, reconductoring is $602,970. Projects junior to the Generation Project in the queue that affect the MW flow on the line would have to contribute to the costs of the reconductoring. 8. The cost allocation for mitigation are based on NWE s Cost Allocation and Refund Methodology, reconductoring is $2,908,800. Projects junior to the Generation Project in the queue that affect the MW flow on the line would have to contribute to the costs of the reconductoring. 9. The cost allocation for mitigation are based on NWE s Cost Allocation and Refund Methodology, reconductoring is $1,030,200. Projects junior to the Generation Project in the queue that affect the MW flow on the line would have to contribute to the costs of the reconductoring. 10. The cost allocation for mitigation are based on NWE s Cost Allocation and Refund Methodology, Dynamic VAR device is $5,400,000. 5

6 Definitions Energy Resource Interconnection Service Energy Resource Interconnection Service shall mean an interconnection service that allows the interconnection customer to connect its generating facility to the transmission provider's transmission system to be eligible to deliver the facility's electric output using the existing firm or nonfirm capacity of the transmission provider's transmission system on an as available basis. Energy Resource Interconnection Service in and of itself does not convey transmission service. Under Energy Resource Interconnection Service ( ERIS ), the Generation Project will be able to inject power from the facility into and deliver power across NWE s transmission system on an as available basis up to the amount of MW identified in the applicable stability and steady state studies to the extent the upgrades initially required to qualify for ERIS have been constructed. No transmission delivery service from the Generation Project is assured, but the Generation Project may obtain point-to-point transmission service, network integration transmission service, or be used for secondary network transmission service, pursuant to NWE s Tariff, up to the maximum output identified in the stability and steady state studies. In those instances, in order for the Generation Project to obtain the right to deliver or inject energy beyond the facility point of interconnection or to improve its ability to do so, transmission delivery service must be obtained pursuant to the provisions of NWE's Tariff. The Generation Project's ability to inject its output beyond the point of interconnection, therefore, will depend on the existing capacity of NWE's transmission system at such time as a Transmission Service Request ( TSR ) is made that would accommodate such delivery. The provision of firm point-to-point transmission service or network integration transmission service may require the construction of additional network upgrades. Network Resource Network Resource shall mean any designated generating resource owned, purchased, or leased by a network customer under the network integration transmission service tariff. Network Resources do not include any resource, or any portion thereof, that is committed for sale to third parties or otherwise cannot be called upon to meet the network customer's network load on a non-interruptible basis. Network Resource Interconnection Service NRIS shall mean an Interconnection Service that allows the Interconnection Customer to integrate its Large Generating Facility with the Transmission Provider s Transmission System (1) in a manner comparable to that in which the Transmission Provider integrates its generating facilities to serve native load customers; or (2) in an RTO or ISO with market based congestion management, in the same manner as all other Network Resources. Network Resource Interconnection Service in and of itself does not convey transmission service. NRIS allows the Generation Project to be designated by any network customer under the Tariff on NWE's Transmission System as a Network Resource, up to the Generation Project's full output, on the same basis as existing Network Resources interconnected to NWE's transmission system, and to be studied as a Network Resource on the assumption that such a designation will occur. Although NRIS does not convey a reservation of Transmission Service, any network customer under the Tariff can utilize its network service under the Tariff to obtain delivery of energy from the Generation Project in the same manner as it accesses Network Resources. A facility receiving NRIS may also be used to provide ancillary services after technical studies and/or periodic analyses are performed with respect to the Generation Project's 6

7 ability to provide any applicable ancillary services, provided that such studies and analyses have been or would be required in connection with the provision of such ancillary services by any existing Network Resource. However, if the Generation Project s facility has not been designated as a Network Resource by any load, it cannot be required to provide ancillary services except to the extent such requirements extend to all generating facilities that are similarly situated. The provision of network integration transmission service or firm point-to-point transmission service may require additional studies and the construction of additional upgrades. Because such studies and upgrades would be associated with a request for delivery service under the Tariff, cost responsibility for the studies and upgrades would be in accordance with the Federal Energy Regulatory Commission s ( FERC ) policy for pricing transmission delivery services. NRIS does not necessarily provide the Generation Project with the capability to physically deliver the output of its facility to any particular load on NWE's transmission system without incurring congestion costs. In the event of transmission constraints on NWE's transmission system, the Generation Project s facility shall be subject to the applicable congestion management procedures in NWE's transmission system in the same manner as Network Resources. NWE will follow regional and sub regional congestion management procedures as they are developed. Once the Generation Project satisfies the requirements for obtaining NRIS, any future transmission service request for delivery from the Generation Project s facility within NWE's transmission system of any amount of capacity and/or energy, up to the amount initially studied, will not require that any additional studies be performed or that any further upgrades associated with the Generation Project s facility be undertaken, regardless of whether or not the Generation Project s facility is ever designated by a network customer as a Network Resource and regardless of changes in ownership of the facility. However, the reduction or elimination of congestion or redispatch costs may require additional studies and the construction of additional upgrades. This philosophy is described in the FERC Order Nos. 2003, 2003-A, 2003-B and 2003-C, which govern interconnection of large generators to the transmission grid. The pro forma Large Generator Interconnection Procedures ( LGIP ) and Large Generator Interconnection Agreement ( LGIA ) required in those orders describe the philosophy that NWE used in performing the study work for the Generation Project. To the extent the Generation Project enters into an arrangement for long-term transmission service for deliveries from the facility outside of NWE's transmission system, such request may require additional studies and upgrades in order for NWE to grant the request. NorthWestern Energy is not required to provide certain ancillary services to transmission customers serving load outside of NorthWestern s control area. 7

8 Generator and Interconnection Data The proposed generator and interconnection data used in the studies was based on the information received from the Interconnection Customer. From the initial application, NWE identified the following project information. Project Name Project #94 Size (Rated) 128 MW total Location 230 kv Great Falls Switchyard Special Resources/Technology 2ea Trent 60 WLE Combustion Turbine Generators Proposed Commercial Operation Date June 10, 2010 Facilities Connection to the 230 kv Great Falls Switchyard using Project #53 s Point-of- Interconnection Assumptions o MW Output = 128 MW o Scheduled Voltage (pu) = 1.0 at the Point of Interconnection o The generator is assumed to have operational characteristics either through internal or external capabilities to operate throughout a power factor range of.95 leading to.95 lagging at the Point of Interconnection 8

9 Study Parameters In analyzing the Generation Project, NWE utilized PSS/E software to conduct the System Impact Study with the proposed Generation Project. These studies connected the Generation Project to NWE s Transmission System in a computer model to simulate the interaction of the Generation Project with other resources and loads. Two WECC base cases adjusted to include the NWE Transmission System detail representing 2010 light autumn and 2012 heavy summer loads were used for this study. Senior Queue Generator Assumptions Project Number Size (MW) Point of Interconnection Wilsall-Shorey Road 230 kv Line Great Falls 230 kv Switchyard Martinsdale Substation ERIS - Martinsdale Substation Billings Steam Plant Switchyard South Cut Bank - Conrad Auto 115 kv line Loweth - Two Dot 100 kv line kv line at Chester Rainbow Switchyard ERIS - Great Falls 230 kv Switchyard Wilsall-Shorey Road 230 kv Line Bradley Creek Substation Bradley Creek - Three Forks S. 100 kv line kv line between Phillipsburg and Anaconda ERIS - 69 kv line between Fairfield and Bole kv line near Sumatra Substation - (70-72 WITHDRAWN) kv line between Cut Bank and Shelby ASMI 161 kv Substation kv line near Bradley Creek Substation kv line near Bradley Creek Substation Millcreek 230 kv Switchyard ERIS kv line between South Cut Bank and Conrad North River Road Near Rainbow Switchyard 82 Efficiency Improv. Near Rainbow Switchyard ERIS - Cut Bank 115 kv Substation between Cut Bank & Shelby Near Livingston City Substation kv line between Loweth and Two Dot at Groveland 9

10 Steady State Power Flow Analysis The steady-state power flow analysis examines steady state, system normal, operating conditions with no lines out of service (i.e., N-0 Conditions) and with various lines out of service (i.e., N-1 and N-2 conditions). A power flow simulation is completed before and after the addition of the Generation Project to identify any unacceptable thermal overloads and voltage excursions the project may cause. Method NWE simulated an extensive set of 500 kv and non-500 kv N-1 and N-2 outages. Power flow contingencies were simulated for both operating conditions (2010 light autumn and 2012 heavy summer). The local area contingencies were the primary focus, but major transmission line outages around the NWE system were also studied. The list of contingencies is summarized in Attachment A. Results N-0: The addition of the Generation Project to NWE s Transmission System under N-0 conditions (all lines in-service) causes no adverse effects. N-1: The addition of the Generation Project to NWE s Transmission System under N-1 conditions (one line out-of-service) causes no adverse effects. N-2: The addition of the Generation Project to NWE s Transmission System under N-2 conditions (two elements out-of-service) causes thermal overloading on transmission lines in south-of-helena area (see Attachment A for results). Mitigation Assuming all senior queue projects connect to the system, the Generation Project must facilitate mitigation in order to operate at full capacity. The Generation Project contributes to the flows on various line segments that have been required to be built, upgraded, or reconductored by senior queued projects. Senior queued project mitigation that the Generation Project s SIS determined are affected will require the Generation Project be responsible for sharing the costs with senior queued projects. The following list summarizes the required mitigation that are shared costs with senior queued projects: a new 230 kv line from Great Falls to Three Rivers; reconductoring the 100 kv lines from Harlowton to Judith Gap Tap to Judith Gap; building a new 100 kv line from Harlowton to Broadview; upgrading the 230/100 kv transformer at Judith Gap; The following list summarizes the required mitigation triggered by this project: reconductoring the 100 kv line from East Helena to Continental Lime Tap; reconductoring the 100 kv line from Continental Lime Tap to Townsend; reconductoring the 100 kv line from Broadwater Tap to Crow Creek; reconductoring the 100 kv line from Crow Creek to Eustis; adding a 36 MVAr Dynamic VAR device at Ovando 230 kv Switchyard. 10

11 Transient Stability Analysis When a line fault occurs, the protective relaying must respond by opening circuit breakers to remove the affected transmission line from service. This can result in a system disturbance. The credible worst case fault events must be simulated to determine if the transmission system will recover to acceptable steady state operating conditions. Events that were studied include single-phase and three-phase faults causing either single or multiple line outages. The dynamic simulations performed for this project include an assortment of events that are intended to provide a thorough test of the feasibility and impact of the proposed generation facility. The results from the Transient Stability Analysis are designed to reveal: Whether or not regional electric transmission systems remain stable and satisfactory with each event; Whether or not WECC criteria are met for each outage condition; and Identify where problems are located on the Transmission System. The Colstrip generation employs generator tripping for critical outage events on the 500 kv electric transmission system. The generator-tripping scheme is a computer-based relay called the Acceleration Trend Relay (ATR). This device monitors the generator speed and acceleration (real time), and digitally analyzes these quantities to determine when an unstable event is in progress. If an unstable event is in progress, the device determines the amount of generator tripping that is required to protect the electric transmission system from instability and unacceptable low-voltage swings caused by the event. The ATR then proceeds to trip the necessary number of generating units at Colstrip before the event causes instability problems to occur. Method NWE simulated an extensive set of 500 kv and non-500 kv faults. The term fault refers to a shortcircuit between either a single-phase conductor to ground or all three phases. Various local area faults were also simulated to understand the generator performance during those faults. The breakers at this project facility were assumed to clear a fault within 4 cycles. The results are subject to change if the model for the project was changed. The entire set of faults was simulated on the 2010 Light Autumn case. All the senior queue projects and their mitigation were implemented during the simulations. The entire list of simulated events and its results is included in Attachment B. Results Detailed analysis of the simulation results has shown that all simulations meet the WECC and NWE performance criteria with additional system mitigation for transient stability. The Generation Project will have to install a 36 MVAr DVAR (Dynamic VAR) device at Ovando 230 kv switchyard in order to meet WECC and NWE performance for an N-2 outage (simultaneous outage of Garrison-Taft 500 kv lines). Attachment B shows the Generation Project s performance with and without the DVAR device under the N-2 outage. The high level non binding cost estimate of the DVAR device is shown in Table II. 11

12 Table II: Mitigation requirement due to Transient Stability Mitigation Cost($M) 36 MVAr Dynamic VAR device at Ovando 230 kv Switchyard $5.4 Total $5.4 This study implemented all the mitigations required by the senior queue interconnection projects and the mitigations required by this Generation Project due to powerflow studies. If either one of the senior queue project is withdrawn this study might have to be re-visited to understand the effect of this project on the system due to the withdrawal. List of the senior queue projects could be found on our OASIS website. The results of the simulations are listed in Attachment B. 12

13 PV Analysis The SIS examined the reactive margin at critical buses on NWE s Transmission System. In addition, the PV and identifies potential voltage collapse issues under maximum operating conditions. This analysis includes the addition of the Generation Project. Voltage security margins were evaluated using PV analysis. For this type of study, the security margin (distance to the voltage collapse) is defined by the amount of additional power transfer that can occur before voltage collapse is reached on a predefined bus. Voltage collapse occurs at the knee point of the PV curve where the voltage drops rapidly with an increase in the transfer power flow. Operation at or near the stability limit is impractical and a satisfactory operation condition must be ensured to prevent voltage collapse. Method The output of the Generation Project was increased to 5% of the nameplate rating. This increased power output was off-set by reducing the generation output at Colstrip. Results The Generation Project is modeled with all co-existing generation projects and their required mitigation. Results indicate with the Generation Project s output increased to 5% above the nameplate rating there is sufficient reactive power compensation to cope with the steady-state requirements for all scenarios and contingencies analyzed. Mitigation No mitigation is required. 13

14 Fault Duty Analysis When a fault occurs on a power line, protective relaying equipment detects the fault current flowing and signals the associated circuit breakers to open. When the circuit breakers open, they must be capable of interrupting the fault current. If the magnitude of the fault current exceeds the interrupt rating of the circuit breakers, the fault may not be cleared, and damage to system equipment and voltage collapse may result. Method To perform a fault duty analysis, busses at or near the point of interconnection of this project are faulted in a PSS/E model to determine the magnitude of fault current anticipated with the Generation Project in service. The results of this analysis determine whether standard circuit breaker fault duty ratings would be exceeded with the addition of the Generation Project. The events that were analyzed are listed below. 1) A three-phase fault at the Generation Project 230 kv bus. 2) A single-phase fault at the Generation Project 230 kv bus. Results The breakers in the area have sufficient interrupting capability to withstand the maximum short-circuit current with the addition of the Generation Project. A breaker interrupt rating of 40,000 amps was assumed. The highest fault current observed was less than 6,000 amps at the Generation Project 230 kv bus. The results for the analysis are included in Attachment C. Mitigation No mitigation required. 14

15 Conclusions The results of this analysis confirm that the addition of 128 MW of generation interconnected to the Great Falls 230 kv Switchyard is only feasible with system improvements. N-0 Mitigation No mitigation is required. N-1 Mitigation No mitigation is required. N-2 Mitigation The Generation Project triggers the need for: reconductoring the 100 kv line from East Helena to Continental Lime Tap; reconductoring the 100 kv line from Continental Lime Tap to Townsend; reconductoring the 100 kv line from Broadwater Tap to Crow Creek; reconductoring the 100 kv line from Crow Creek to Eustis; The Generation Project also triggers the need for the addition of a 36 MVAr Dynamic VAR device at Ovando 230 kv Switchyard for transient stability issues. The total cost for NRIS is $76.6 million including all steady state and transient study findings. The total cost for ERIS is $2.46 million (which includes the ERIS cost of $2.35 million for Project #53). Next Steps NWE will be scheduling a meeting to discuss the findings of the SIS with the Interconnection Customer. If, after the meeting, the Interconnection Customer wishes to continue with the project, the Generation Project must designate either ERIS or NRIS. A Facility Study specific to the project will then be carried out to determine the final details of the interconnection. This study does not constitute a request for transmission service. The study examined the physics of the electrical system and does not imply that you will receive any transmission required to deliver the generation output to load. You must follow the procedures described in the transmission tariff available on ( to request and/or receive transmission service. Attachments Attachment A Power Flow Analysis Results Attachment B Transient Stability Analysis Results Attachment C Fault Duty Analysis Results 15

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

Grid Stability Analysis for High Penetration Solar Photovoltaics

Grid Stability Analysis for High Penetration Solar Photovoltaics Grid Stability Analysis for High Penetration Solar Photovoltaics Ajit Kumar K Asst. Manager Solar Business Unit Larsen & Toubro Construction, Chennai Co Authors Dr. M. P. Selvan Asst. Professor Department

More information

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Georgia Transmission Corporation Georgia Systems Operations Corporation

Georgia Transmission Corporation Georgia Systems Operations Corporation Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia

More information

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

PUD ELECTRIC SYSTEM INTERCONNECTION

PUD ELECTRIC SYSTEM INTERCONNECTION APPENDIX A PROCEDURES & REQUIREMENTS for OKANOGAN PUD ELECTRIC SYSTEM INTERCONNECTION Version 4.0 December 2011 Version 4.0 12/28/2011 Page 1 of 15 TABLE OF CONTENTS DEFINITIONS 1.0 Introduction 2.0 Procedures

More information

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS El Paso Electric Company System Operations Department System Planning

More information

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program. Electric Tariff _2nd Revised Sheet No. 72 Filed with Iowa Utilities Board Cancels _1st Sheet No. _72 Cooperative is a member of Central Iowa Power Cooperative (CIPCO), a generation and transmission cooperative

More information

Interconnection System Impact Study Final Report February 19, 2018

Interconnection System Impact Study Final Report February 19, 2018 Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

2015 Grid of the Future Symposium

2015 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,

More information

Midway/Monument Area TTC Study

Midway/Monument Area TTC Study Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny

More information

Small Generator Interconnection Program Interconnection Technical Requirements

Small Generator Interconnection Program Interconnection Technical Requirements General Program Information What is the purpose of the PGE Small Generator Interconnection Program? How do I initiate a distribution interconnection request for my project? The purpose of our Small Generator

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Interconnection Feasibility Study Report GIP-369-FEAS-R1 Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION Presentation by Engr. O. C. Akamnnonu Chief Executive Officer, Ikeja Electricity Distribution Company AGENDA WORK THROUGH

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS System Operations Department System Planning Section June 2001 TABLE OF CONTENTS 1.0 Executive Summary...Page

More information

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER 1 Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER Lisa Dangelmaier Hawaii Electric Light lisa.dangelmaier@hawaiielectriclight.com Hawai'i Electric Light System Overview

More information

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ART320W 320 MW Wind Powered Project Prepared for: El Paso Electric Company Prepared by: TRC Engineers, LLC 249 Western Avenue Augusta, ME 04330

More information

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning. A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final

More information

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD

More information

Interconnection and Net Metering Service in Ohio

Interconnection and Net Metering Service in Ohio Interconnection and Net Metering Service in Ohio Partnership between National Association of Regulatory Utility Commissioners and The National Commission for Energy State Regulation of Ukraine June 20,

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028. Merchant Transmission Interconnection PJM Impact Study Report For PJM Merchant Transmission Request Queue Position X3-028 Breed 345 kv October/2014 System Impact Study Breed 345 kv Merchant Transmission

More information

El Paso Electric Company

El Paso Electric Company Feasibility Study XXXXXX Solar Generation Prepared for El Paso Electric Company Prepared by TRC Engineers, LLC 249 Eastern Avenues Augusta, ME 04330 (207) 621-7000 Project Number: 202327 May 2013 FOREWORD

More information

Ancillary Services & Essential Reliability Services

Ancillary Services & Essential Reliability Services Ancillary Services & Essential Reliability Services EGR 325 April 19, 2018 1 Basic Products & Ancillary Services Energy consumed by load Capacity to ensure reliability Power quality Other services? o (To

More information

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation Intentionally left blank F1 Description and Functional Specifications of Proposed

More information

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655) - (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility

More information

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS. 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context indicates otherwise, this section and 25.212 of this title (relating to Technical Requirements

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

Overview of State Distributed Generation Interconnection Rules

Overview of State Distributed Generation Interconnection Rules Overview of State Distributed Generation Interconnection Rules Presentation to EPA CHP Webinar Series June 26, 2008 Wayne Shirley Director The Regulatory Assistance Project 50 State Street, Suite 3 Montpelier,

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department

More information

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Adopted Based on State and Tariff Interconnection Rules Applicable to Northern States Power,

More information

The Energy Queensland Group Notice of no non-network options

The Energy Queensland Group Notice of no non-network options The Energy Queensland Group Notice of no non-network options 24 September 2018 MCE Mount Crosby East Establish new substation to replace Mount Crosby Substation (SSMTC) Page 1 of 1 DISCLAIMER While care

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study XXXX Knob Hill Wind Farm Project Report No. August 2010 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All rights reserved.. DISCLAIMER OF WARRANTY, LIMITATION

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2014 Annual Ten-Year Transmission Plan Assessment Report November 20, 2014 For information or questions regarding this Transmission Assessment Report,

More information

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

Interconnection Process for Generation Systems

Interconnection Process for Generation Systems Interconnection Process for Generation Systems I. INTRODUCTION...1 II. GENERAL INFORMATION...2 A. Definitions...2 B. Nodak Electric Cooperative, Inc. Generation Interconnection Contacts...3 C. Engineering

More information

Interconnection System Impact Study

Interconnection System Impact Study Interconnection System Impact Study Pennask and Shinnish Creek Wind Project Report No: T&S Planning 2014 072 December 2014 DRAFT British Columbia Hydro and Power Authority British Columbia Hydro and Power

More information

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management Southern Company Interconnection Process Dexter Lewis Research Engineer Research and Technology Management Southern Company Outline Southern Company GPC Solar Interconnection Process Application requirements

More information

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Adopted Based on State and Tariff Interconnection Rules Applicable to Northern States Power,

More information

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and

More information

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 1 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 2 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC

More information

Interconnection Feasibility Study Report Request # GI

Interconnection Feasibility Study Report Request # GI A. Executive Summary Interconnection Feasibility Study Report Request # GI-2011-04 587 MW Combined Cycle 2x1 Generators Cherokee Station, Denver, Colorado Public Service Company of Colorado Transmission

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

Southwest Power Pool Network Integration Transmission Service Application

Southwest Power Pool Network Integration Transmission Service Application Revised 09/17/2014 REVISION-2, 12/11/2014 Southwest Power Pool Network Integration Transmission Service Application Date: 14-Oct-14 Purpose of Application: (Check boxes as applicable) Initial NITS Application

More information

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED DATE: June 28, 2011 STAFF: Brian Janonis Brian Moeck, PRPA Pre-taped staff presentation: none WORK SESSION ITEM FORT COLLINS CITY COUNCIL SUBJECT FOR DISCUSSION Electric Transmission Update. EXECUTIVE

More information

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba

More information

Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006

Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006 Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006 As per the Manitoba Hydro Open Access Interconnection Tariff, the Transmission Owner has contracted TransGrid Solutions

More information

The Long-Range Transmission Plan

The Long-Range Transmission Plan The Long-Range Transmission Plan 2015 2025 Matt Koenig Presentation to ESPWG / TPAS October 29 th, 2015 Long-Range Transmission Plan Driver of the Plan is to maintain local reliability 10-year planning

More information

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat Galapagos San Cristobal Wind Project VOLT/VAR Optimization Report Prepared by the General Secretariat May 2015 Foreword The GSEP 2.4 MW Wind Park and its Hybrid control system was commissioned in October

More information

The Rollover Request customer accepts a reservation term for the rollover at least as long as that offered by any competing customer.

The Rollover Request customer accepts a reservation term for the rollover at least as long as that offered by any competing customer. XX.X xx.xx ROLLOVER RIGHTS FOR LONG TERM FIRM SERVICE Overview Pursuant to Section 2.2 of the Tariff, long term firm transmission service customers (Network Integration Transmission Service ( NITS ) customers

More information

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM 1 1 The Latest in the MIT Future of Studies Recognizing the growing importance of energy issues and MIT s role as an honest broker, MIT faculty have undertaken a series of in-depth multidisciplinary studies.

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC

More information

Q217 Generator Interconnection Project

Q217 Generator Interconnection Project Q217 Generator Interconnection System Impact Study APS Contract No. 52588 By Arizona Public Service Company Transmission Planning November 25, 2013 Version 2.0 Prepared by Utility System Efficiencies,

More information