Guideline for Parallel Grid Exit Point Connection 28/10/2010

Size: px
Start display at page:

Download "Guideline for Parallel Grid Exit Point Connection 28/10/2010"

Transcription

1 Guideline for Parallel Grid Exit Point Connection 28/10/2010

2 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE Pupose of the document BACKGROUND TO PARALLEL GXP CONNECTIONS What is a parallel connection? Why do parallel connections occur? Type 1: Parallel Connection near one GXP bus Type 2: Parallel Connection between two GXP s - Network Tie Health and Safety responsibilities How are they of interest to the Grid Owner and System Operator? What does the Electricity Industry Participation Code (the Code ) require? SUPPORTING INFORMATION Switching Device Tie Duration Clearing Multi-phase faults Clearing Earth Faults Substations on a spur with an HV star winding Substations on a spur with an HV delta winding Substations in a mesh with an HV delta winding System Power Angle and Magnitude Reverse Power Flow Fault levels Parallel Paths Assessment Template Code Obligations APPENDIX Relevant Code References - System Operator Relevant Code References - Grid Owner and Distributors Version Date Change 2 12/8/05 Rule added to Appendix 2. Revisions to switching device and tie duration updated with Distributor feedback 3 26/10/05 Revised with Distributor comments 4 28/10/10 Updated for the change from EGRs to the new Code references.

3 Guideline for Parallel Grid Exit Point Connection Page 3 of 11 1 Purpose 1.1 Pupose of the document This document is a technical guideline which highlights the issues to be considered when paralleling Grid Exit Points (GXP s). If not managed appropriately, parallel connection of GXP s can compromise operation of the Grid Owners assets ie:protection systems, and can impact on the ability of the System Operator to maintain a secure Grid While this document it is not to be considered as expert technical advice, it does highlight the key issues that need to be considered at a technical level before a parallel connection is made. This document is to be read in conjunction with the document titled: Process for Assessment of Parallel Grid Exit Point Applications. 2 Background to Parallel GXP Connections 2.1 What is a parallel connection? A parallel connection exists between two points when there is more than one path for electrical power flow between two points. 2.2 Why do parallel connections occur? Distribution networks are connected in parallel with the grid for several reasons, most frequently to enable equipment maintenance without disruption of supply. Parallel connections can also be required, following a contingency in a local network, to facilitate restoration of supply to customers. Distributors can typically make two distinct types of parallel connection: 1. A parallel connection between two radial feeders where both feeders are supplied from the same GXP. 2. A parallel connection between GXP supply buses where the system path between the two buses includes enough impedance to potentially cause voltage differences (angular and/or magnitude) between the two buses. Note: Connection Type 2 has the greatest potential to impact on operation of the power system and grid assets. Assessing the implications of this type of connection is the primary focus of this document Type 1: Parallel Connection near one GXP bus The diagram below shows a parallel connection between two radial feeders (A & B) by bridging the two feeders at Y close to the GXP.

4 Guideline for Parallel Grid Exit Point Connection Page 4 of Type 2: Parallel Connection between two GXP s - Network Tie In this figure, parallel paths are formed when GXP A and GXP B are connected via a local distribution network in addition to the normal grid path. This configuration enables the distributor to change its network configuration e.g. a section of network normally supplied from GXP A can be switched over to receive supply from GXP B. 2.3 Health and Safety responsibilities The Distributors and the Grid Owner are responsible for ensuring the safe operation of their assets, and that assets are sufficiently protected. Before paralleling GXP s the Distributors and the Grid Owner need to assess any risks involved, to ensure they are managed appropriately. The document titled: Process for Assessment of Parallel Grid Exit Point Applications outlines the process that distributors and the Grid Owner can follow to assess these situations where necessary. 2.4 How are they of interest to the Grid Owner and System Operator? Parallel connections can impact on the achievement of the System Operators PPO s, the Grid Owners AOPO s, and the operation of protection systems. The Grid Owner and System Operator, in conjunction with the distributor need to assess the impact of parallel connections to identify, any risks that may be involved, and plan to mitigate these as required. 2.5 What does the Electricity Industry Participation Code (the Code ) require? The Code requirements include: Distributors are obligated to agree the temporary or permanent connection of its assets with the System Operator when those assets become simultaneously connected to the grid at more than one point of connection (Part 8, Schedule 8.3, Technical Code A clause 6). Each asset owner will ensure that it provides protection systems for its assets that are connected to, or form part of, the grid. Each asset owner must also ensure that such protection systems will support the System Operator in planning to comply, and complying, with the principal performance obligations and must be designed, commissioned and maintained, and settings must be applied, to achieve the following performance in a reliable manner (Part 8, Schedule 8.3, Technical Code A clause 4). Refer to the appendix of this document for more Code references

5 Guideline for Parallel Grid Exit Point Connection Page 5 of 11 3 Supporting information 3.1 Switching Device In all circumstances suitably rated devices that are safe to use are required. Where large power angles, or voltage magnitude differences occur, the switching device must have the capability to make or break the resulting current flow that will occur. Where two grid exit points are being tied at supply bus and feeder voltage levels, if the switching device is not a circuit breaker then the respective asset owners should ensure that the switching device can safely make or break the expected current. This may require that additional parallel connections are made with suitably rated equipment. The parallel connection must include a switching device which is capable of removing any source of back feed should a fault occur in the Distributors or Grid Owners network while the parallel takes place. If the switching device switches phases one at a time then the asset owner should consider the impact this may have on the operation of sensitive earth fault protection equipment. 3.2 Tie Duration The duration of any tie should be kept to a minimum. The tie duration should be less than 10 minutes. This allows sufficient time to manually operate a circuit breaker or disconnector. This also allows sufficient time to confirm equipment loading and protection systems are correct prior to the tie being broken and load transferred between GXP s. For paralleling situations where protection operation may be uncertain or the tying time is longer than 10 minutes, the Distributors and the Grid Owner are to agree any measures that may be necessary to mitigate the risk. This could be achieved by minimising switching times and/or the use of temporary protection settings. The agreed measures are then noted as conditions in the agreement. Where there are sufficient protection systems in place, the switching time may be extended to a maximum of 30 minutes. 3.3 Clearing Multi-phase faults All multiphase faults on the grid owners HV system must be detected and cleared. HV faults are most likely to be detected and cleared by the Distributors protection at a point close to the tying CB, if discrimination/selectivity principles have been applied. The magnitude of the current may not be large, especially if there are intermediate transformers such as 33/11 kv step down and 11/33 step up transformers included in the current path. Such transformers are generally of high impedance so act as good fault current limiters. However, if the fault current is reduced too much, the grid owners feeder protection cannot be expected to operate. Protection installed in line with current practices, should be time graded away from the grid owners point of supply i.e. the protection should work more quickly, the further you move away from the grid owners site.

6 Guideline for Parallel Grid Exit Point Connection Page 6 of 11 It is likely the protection will become more sensitive the further away the move from the grid owners point of supply. The sensitivity should be such, as to detect any reduced fault level due to step up/down transformers in their normal system configuration and during the periods of tying. Assurances should be sought in advance that adequate protection is installed and set. This sort of information should be recorded in the notes for each tying procedure. A fault on the grid owners HV system will draw current from the Distributor s network in addition to some/all of the grid owners transformer energising current and station load. The relevant Distributor infrastructure probably cannot support this type of load. A tripping in the Distributors system would be expected, rather than trippings being observed in the grid owners equipment for other than normal strong infeeds from the grid to the actual fault. 3.4 Clearing Earth Faults Figure 1: Earth Fault Example Substations on a spur with an HV star winding Refer to Figure 1 above. An earth fault incident at fault position 1 will cause the transmission circuit protection at Bus B to operate in minimum time, leaving the transformer back energised from the Distributors network. In any case, action should be taken to open the transformer LV CB in case the transformer Earth Fault protection is not sensitive enough to operate from the weak infeed or the Distributor s protection does not clear the fault. The CB opening will be prompted by the operation of Bus B transmission circuit protection.

7 Guideline for Parallel Grid Exit Point Connection Page 7 of 11 Earth fault current flows between the transformer HV star point and earth at Bus A. The transformers earth fault protection would be expected to detect the fault, but will probably be set to a final time of 3 or 4 seconds. Phase current would be expected to increase in the Distributor s network and a tripping to occur close to the tying CB Substations on a spur with an HV delta winding Refer to Figure 1. An earth fault incident at fault position 2 will be detected at Bus C by the transmission circuit protection and normal tripping will occur at Bus C. The Bus D transformer HV winding is a delta winding without an earth reference. Unless there is an intertrip from Bus C to Bus D or there is residual protection installed on Bus D, the fault will remain. This becomes a safety issue. The grid owner needs to be vigilant in situations like this, so that during the period of the tie, if the Bus C transmission circuit protection is seen to operate, the Bus D transformer LV CB is opened without delay. There is a chance that the back-energisation current requirements of the transformer at Bus D will cause the Distributor protection to operate near the tie, but this cannot be guaranteed Substations in a mesh with an HV delta winding An earth fault incident at fault position 3 is less of a concern. There is another HV source of current infeed for faults. Fault current would be delivered by the healthy circuit to allow the fault to be cleared. There may as a consequence be a tripping of the Distributor s assets but this is a risk the Distributor would have to manage. When the Distributor notifies they are going to tie feeders, ensure the bus has sufficient other circuits to develop fault current, or fall back to the fault position 1 scenario. Note, if Bus E faults and all of the incoming transmission circuits trip, the transformer LV CB will need to be opened manually. The bus fault will continue to be fed via the tie. Bus faults are rarer than transmission circuit faults but need to be considered. 3.5 System Power Angle and Magnitude When assessing the option of paralleling two GXP s, the system power angle and magnitude will need to be considered. If the power system angle is large when tying, large active power flows will occur and a tripping is likely to occur in the Distributors network. This is where protection is most sensitive. Large reactive power flows can occur if the magnitudes of voltages are significantly different. The switching device that will be tying the two GXP s needs to be rated to make or break the expected currents that could flow. While it is unusual for a Distributor to want to tie two geographically distant sites, the electrical route between two points can still be great. Normally, as long as the shortest electrical route is healthy, the power system angle should be satisfactory. The Distributor should be satisfied their internal power system angle is within suitable tolerances. In some configuration cases, when a circuit trips it is highly likely the tie will trip also. This could be due to either a strong reactive current flow or some fault contribution being made.

8 Guideline for Parallel Grid Exit Point Connection Page 8 of Reverse Power Flow The connection of two Grid Exit Points must not defeat metering. There is always a risk of a reverse power flow as a consequence of there being a tripping in the core grid during tying. There is also a possibility of reverse power flow where the Distributor has embedded generation in excess of the load. Another situation would be when one substation back feeds another i.e. power is moved across the tie. If site metering is not programmed to be bi-directional, power delivered to the national grid i.e. from embedded generation, will not be recognised. Back feeds into a Grid fault must be cleared by either having backfeed protection installed or as described above. Normal operation of the Grid auto-reclosing may be prevented, where synchronism check detects an uncleared out of synchronism back feed. The loss of auto reclosing affects Grid system security. 3.7 Fault levels The fault levels at both the Grid exit point and the paralleling point must be considered before paralleling can take place. The following three impacts must be considered: The connected equipment must be able to withstand the possible fault current, and break this current if appropriate. The step and touch potential within the substation must be at safe levels and the earth mat design is one way of achieving this. The change in fault level may cause protection discrimination problems and protection operating times may be affected. It is important when considering the increased fault levels at a grid exit point that the public must be protected from injury at all times. 3.8 Parallel Paths When tying two grid exit points a parallel link will be created. If the impedance of this link is low enough it will share current flow with the grid. Larger than normal current flow through the distributors network may cause the protection in the distribution network to operate. 3.9 Assessment Template The following template provides a method for Distributors to identify situations where GXP s can be tied, and at what voltage. This along with any necessary supporting technical information will form the basis for assessing applications to parallel GXP s which is detailed in the document: Process for Assessment of Parallel Grid Exit Point Applications 3.10 Code Obligations Appendices 4.1 & 4.2 provide a summary of the Code references highlighting the various parties responsibilities for managing parallel GXP situations.

9 Guideline for Parallel Grid Exit Point Connection Page 9 of 11 4 Appendix 4.1 Relevant Code References - System Operator This list is provided as a guide. references Code Part/ Clause Part 7 clause 7.2 (1a) Part 8 clause 8.25 (1) Part 8, Schedule 8.3, Technical Code A clause 6 Part 13 clause (1a) Part 8, Schedule 8.3, Technical Code A clause 3 (1) Requirement It is not a complete list of applicable rule Principal Performance Obligations Avoid Cascade failure Act as a reasonable and prudent system operator with the objective of dispatching assets made available in a manner which avoids the cascade failure of assets resulting in the loss of demand and arising from frequency or voltage excursions or supply and demand imbalances Other asset owner performance obligations and technical standards grid owner configuration performance obligation Each grid owner must ensure that the design and configuration of its assets (including its connections to other persons) and associated protection arrangements are consistent with the technical codes and, in the reasonable opinion of the system operator, with maintaining the system operator s ability to comply with the principal performance obligations. In reaching this opinion, the system operator must have regard to the potential impact of the design or configuration of those assets or associated protection arrangements on its compliance with the principal performance obligations and achievement of the dispatch objective. Connection of local networks in parallel with the grid Each distributor must agree with the System Operator any temporary or permanent connection of its assets when those assets become simultaneously connected to the grid at more than one point of connection. Circumstances when revised bids or offers will be submitted Prior to the beginning of the trading period to which the bid applies a purchaser will immediately submit revised bid quantities to the system operator whenever - Bid quantities expected to change by more than 20 MW or 10%. The ability of a purchaser to purchase the quantity bid for a trading period at a grid exit point is expected by that purchaser to change by more than 20 MW or 10% of the quantity bid by that purchaser 3. Requirements for assets information In accordance with rule 4.4 of section III, the following information is required by the system operator to assist it to plan to comply, and to comply, with its principal performance obligations: 3.1 Exchange of information Sufficient information must be exchanged between the system operator and the asset owner to ensure that both fully understand the implications of any changes to the asset capability statement or of any proposed connection of the relevant assets to the grid or to the local network. This information must be exchanged in accordance with a timetable agreed to by both the system operator and the asset owner. 3.2 For planning studies by the system operator Where reasonably requested by the system operator, the asset owner will provide sufficient information to the system operator to demonstrate the compliance of its assets with the asset owner performance obligations and the technical codes.

10 Guideline for Parallel Grid Exit Point Connection Page 10 of Relevant Code References - Grid Owner and Distributors This list is provided as a guide. It is not a complete list of applicable rule references. Code Part/ Clause Part 8 clause 8.22 Part 8 clause 8.24 Part 8 clause 8.25 (1) Part 8, Schedule 8.3, Technical Code A clause 4 Requirement Asset Owner performance obligations and technical standards concerning voltage - Voltage range AOPO s Each asset owner will ensure its assets are capable of being operated within the specified range of voltages Load shedding obligations to support voltage Grid owners and distributors to shed load in accordance with the technical codes or as the system operator reasonably requires Grid Owner configuration performance obligation Each grid owner must ensure that the design and configuration of its assets (including its connections to other persons) and associated protection arrangements are consistent with the technical codes and in the reasonable opinion of the system operator, with maintaining the system operators ability to comply with the PPOs. In reaching this opinion, the system operator will have regard to the potential impact of the design and configuration of those assets or associated protection arrangements on its compliance with the PPOs and achievement of the dispatch objective 4 Requirements for the grid and a grid interface (1) Each asset owner and grid owner must co-operate with the system operator to ensure that protection systems on both sides of a grid interface, which include main protection systems and back up protection systems, are co-ordinated so that a faulted asset is disconnected by the main protection system first and the other assets are not prematurely disconnected. (2) A proposed grid interface, including the settings of any associated protection system, must be agreed between the relevant asset owner and the system operator before being implemented. (3) Each asset owner must ensure that sufficient circuit breakers are provided for its assets so that each of its assets is able to be disconnected totally from the grid whenever a fault occurs within the asset. (4) Each asset owner must ensure that it provides protection systems for its assets that are connected to, or form part of, the grid. Each asset owner must also ensure that as a minimum requirement (a) such protection systems support the system operator in planning to comply, and complying, with the principal performance obligations and are designed, commissioned and maintained, and settings are applied, to achieve the following performance in a reliable manner: (i) disconnect any faulted asset in minimum practical time (taking into account selectivity margins and industry best design practice) and minimum disruption to the operation of the grid or other assets: (ii) be selective when operating, so that the minimum amount of assets are disconnected: (iii) as far as reasonably practicable, preserve power system stability; and (b) it provides duplicated main protection systems for each of its assets at voltages of 220 kv a.c. or above, other than busbars; and (c) it provides, for each of its 220 kv a.c. busbars (i) a single main protection system and a back up protection

11 Guideline for Parallel Grid Exit Point Connection Page 11 of 11 Policy Statement, clause 86 system; or (ii) if the performance of its back up protection system does not meet the requirements of paragraph (a), a duplicated main protection system; and (d) it provides duplicated main protection systems for each of its busbars at voltages above 220 kv a.c; and (e) it designs, tests and maintains its main protection systems at voltages of 220 kv a.c. or above in accordance with the requirements set out in Appendix A; and (f) it provides a circuit breaker failure protection system, that need not be duplicated, for each circuit breaker at voltages of 220 kv a.c. or above. Circuit breaker duplication is not required; and (g) protection system design for a connection of assets to the grid at lower voltages must be similar to existing design practice in adjacent connections of assets to ensure coordination of protection systems 86. Where, pursuant to rule 6 of technical code A of schedule C3 of part C, a distributor requests agreement of the system operator to connection of local networks in parallel with the grid, the system operator will require the distributor to provide the following: Any information reasonably required by the system operator to evaluate the consequences and determine conditions that may apply (and the system operator will list on its website the type of information generally required) Written evidence of the grid owner s agreement to the simultaneous connection of those assets.

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Guidelines for connection of generators:

Guidelines for connection of generators: Guidelines for connection of generators: Greater than 30 kva, and not greater than 10 MW, to the Western Power distribution network January, 2017. EDM 32419002 / DM 13529244 Page 1 of 14 Contents 1 INTRODUCTION...

More information

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS 1. PURPOSE AND SCOPE OF THIS DOCUMENT... 3 2. DEFINITIONS...

More information

PHILIPPINE DISTRIBUTION CODE 2017 EDITION

PHILIPPINE DISTRIBUTION CODE 2017 EDITION PHILIPPINE DISTRIBUTION CODE 2017 EDITION PDC 2017- Background Revised the PDC 2001 Starts of revision in 2010 April 18 and 24, 2012 conducted a series of expository presentation for Visayas and Mindanao

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd Embedded Generation - Technical Access Standards Embedded Generation - 5 MW or Greater ELE SP 0003 Public 1 October 2014 TABLE OF CONTENTS TABLE OF CONTENTS Abbreviations...

More information

Company Directive STANDARD TECHNIQUE: SD4O/1. Standard HV Connection Arrangements

Company Directive STANDARD TECHNIQUE: SD4O/1. Standard HV Connection Arrangements Company Directive STANDARD TECHNIQUE: SD4O/1 Standard HV Connection Arrangements Policy Summary This document specifies the standard arrangements for HV metered connections. NOTE: The current version of

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program. Electric Tariff _2nd Revised Sheet No. 72 Filed with Iowa Utilities Board Cancels _1st Sheet No. _72 Cooperative is a member of Central Iowa Power Cooperative (CIPCO), a generation and transmission cooperative

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

SUBSTATION INTERLOCKING SCHEMES

SUBSTATION INTERLOCKING SCHEMES SUBSTATION INTERLOCKING SCHEMES This document is for internal and contract specific use only. Disclaimer NGG and NGET or their agents, servants or contractors do not accept any liability for any losses

More information

MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017

MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017 MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES Published: 3 August 2017 INCIDENT CLASSIFICATIONS

More information

Compatibility Between Electric Trains and Electrification Systems

Compatibility Between Electric Trains and Electrification Systems Compatibility Between Electric Trains and Electrification Systems Synopsis Process for managing change that affects the compatibility between electric trains and electrification systems Submitted by Signatures

More information

Switchgear and Distribution Systems for Engineers and Technicians

Switchgear and Distribution Systems for Engineers and Technicians Switchgear and Distribution Systems for Engineers and Technicians WHAT YOU WILL LEARN: How to identify typical characteristics of an industrial distribution system Become familiar with the main components

More information

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION Presentation by Engr. O. C. Akamnnonu Chief Executive Officer, Ikeja Electricity Distribution Company AGENDA WORK THROUGH

More information

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012 POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 PREPARED BY: Electricity System Operations Planning and Performance DATE: 5 June 2012 FINAL

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008 NB Power Customer Service and Distribution June 2008 Prepared by: Steven Wilcox Revised by: Steven Wilcox TABLE OF CONTENTS 1.0 Introduction 4 2.0 NB Power Policy on Independent Power Production 4 3.0

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011

POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011 POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO.1 275 KV BUSBAR ON 30 OCTOBER 2011 PREPARED BY: Electricity System Operations Planning and Performance

More information

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011 POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011 PREPARED BY: Electricity System Operations Planning and Performance DATE: 22 March 2012 FINAL

More information

Risk Management of Rail Vehicle Axle Bearings

Risk Management of Rail Vehicle Axle Bearings Railway Group Standard Risk Management of Rail Vehicle Axle Bearings Synopsis This Railway Group Standard mandates that there shall be riskbased processes to minimise and detect failures of rail vehicle

More information

Guidance for Low Voltage Electrical Installations

Guidance for Low Voltage Electrical Installations Guidance for Low Voltage Electrical Synopsis This document provides information in support of GI/RT7007 Low Voltage Electrical. Signatures removed from electronic version Submitted by Anne E Blakeney Standards

More information

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent

More information

SECONDARY FUEL TESTING ARRANGEMENTS

SECONDARY FUEL TESTING ARRANGEMENTS SECONDARY FUEL TESTING ARRANGEMENTS SUMMARY DOCUMENT JULY 2010 Note: 1. This summary document has been produced by EirGrid for information only. Parties should base any decision or actions on the legally

More information

Key DRAFT OPERATING CODE 2 LEGAL TEXT

Key DRAFT OPERATING CODE 2 LEGAL TEXT Key DRAFT OPERATING CODE 2 LEGAL TEXT 1) Blue Text From Grid Code 2) Black Text Changes / Additional words 3) Orange/ Brown text From RfG 4) Purple From HVDC Code 5) Green From DCC (not used in this document)

More information

Implementation procedure for certification and continued airworthiness of Beriev Be-200E and Be-200ES-E

Implementation procedure for certification and continued airworthiness of Beriev Be-200E and Be-200ES-E 1. Scope 1.1 The general process is described in the implementation procedure for design approvals of aircraft, engine and propeller from CIS and in the implementation procedure for design approvals of

More information

GUIDELINES FOR GRID INTERCONNECTION OF SMALL POWER PROJECTS IN TANZANIA

GUIDELINES FOR GRID INTERCONNECTION OF SMALL POWER PROJECTS IN TANZANIA GUIDELINES FOR GRID INTERCONNECTION OF SMALL POWER PROJECTS IN TANZANIA PART B: TECHNICAL GUIDELINES DRAFT MARCH 2011 ENERGY AND WATER UTILITIES REGULATORY AGENCY CONTENTS OF PART B Glossary, Definitions

More information

Addressing ambiguity in how electricity industry legislation applies to secondary networks

Addressing ambiguity in how electricity industry legislation applies to secondary networks In Confidence Office of the Minister of Energy and Resources Chair, Cabinet Business Committee Addressing ambiguity in how electricity industry legislation applies to secondary networks Proposal 1 This

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY Table of Contents Chapter 1. Purpose and scope. Pg 3 Chapter 2. Application

More information

Standards, Procedures and Policies for Grid Connection

Standards, Procedures and Policies for Grid Connection Standards, Procedures and Policies for Grid Connection CONTENTS 1 INTRODUCTION 1 2 EMBEDDED GENERATION 1 2.1.1 OUTLINE OF EMBEDDED GENERATION 1 2.1.2 CHANGES IN EMBEDDED GENERATION 1 2.1.3 ASPECTS OF EMBEDDED

More information

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012 POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012 PREPARED BY: System Performance and Commercial DATE: 7 March 2013 FINAL Disclaimer Purpose This

More information

Advice Pertaining to ERC Resolution No.16 and the Role of Hybrid Generation Advice with respect to specific questions from PIPPA

Advice Pertaining to ERC Resolution No.16 and the Role of Hybrid Generation Advice with respect to specific questions from PIPPA Advice Pertaining to ERC Resolution No.16 and the Role of Hybrid Generation Advice with respect to specific questions from PIPPA George Horvath george.horvath@aecom.com Month Day, Year Part A Introduction

More information

Modular Standardized Electrical and Control Solutions for Fast Track Projects

Modular Standardized Electrical and Control Solutions for Fast Track Projects Modular Standardized Electrical and Control Solutions for Supporting fast track projects ABB is the leading supplier of electrical and control equipment for power plants. The company offers a comprehensive

More information

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010 POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010 PREPARED BY: Electricity System Operations Planning and Performance FINAL Disclaimer (a) Purpose - This report

More information

Export limits for Embedded Generators up to 200 kva connected at Low Voltage

Export limits for Embedded Generators up to 200 kva connected at Low Voltage Export limits for Embedded Generators up to 200 kva connected at Low Voltage Standard Operating Procedure Document number: SOP 33-06 Issue number: 5 Status: FINAL Approver: J Bridge Date of approval: 3

More information

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources Marija Ilic milic@netssinc.com and Jeffrey Lang jeffrey.lang@netssinc.com Principal NETSS Consultants

More information

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance National Grid UK Electricity Transmission plc NATIONAL SAFETY INSTRUCTION and HIGH VOLTAGE METAL CLAD SWITCHGEAR WITH SPOUTS Copyright National Grid plc 2014, all rights reserved. No part of this publication

More information

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System This document is intended to be a general overview of PG&E s current technical

More information

Low Voltage Power Supplies in Electrified Areas

Low Voltage Power Supplies in Electrified Areas Low Voltage Power Supplies in Electrified Areas Synopsis This document mandates requirements for control of return and stray currents and the management of earthing for low voltage power supplies in electrified

More information

Louisville Gas and Electric Company

Louisville Gas and Electric Company P.S.C. Electric No. 11, Original Sheet No. 57 APPLICABLE In all territory served. AVAILABILITY OF SERVICE Available to any customer-generator who owns and operates a generating facility located on Customer

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Functional Specification Revision History

Functional Specification Revision History Functional Specification Revision History Revision Description of Revision Author Date B0 For comments Yale Zhou January 26, 2016 B1 Updated as per comments Yale Zhou February 1, 2016 Final issuance Yale

More information

Large Embedded Generation User Guide A

Large Embedded Generation User Guide A Large Embedded Generation User Guide A For Generating Systems AS4777 compliant and up to 200kW January 2013 SA Power Networks www.sapowernetworks.com.au Table of Contents 1. Introduction... 3 1.1 Embedded

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

NATIONAL GRID ELECTRICITY TRANSMISSION plc THE CONNECTION & USE OF SYSTEM CODE TABLE OF CONTENTS

NATIONAL GRID ELECTRICITY TRANSMISSION plc THE CONNECTION & USE OF SYSTEM CODE TABLE OF CONTENTS NATIONAL GRID ELECTRICITY TRANSMISSION plc INTRODUCTION THE CONNECTION & USE OF SYSTEM CODE TABLE OF CONTENTS SECTION 1 - APPLICABILITY OF SECTIONS AND RELATED AGREEMENTS STRUCTURE 1.1 Introduction 1.2

More information

GC0023 Protection Fault Clearance Time & Back-Up Protection

GC0023 Protection Fault Clearance Time & Back-Up Protection Stage 03: Report to Grid Code GC0023 Protection Fault Clearance Time & Back-Up Protection What stage is this document at? 01 02 03 Workgroup Report Industry Consultation Report to the This proposal seeks

More information

CHAPTER 4 PROTECTION REQUIREMENTS

CHAPTER 4 PROTECTION REQUIREMENTS CHAPTER 4 PROTECTION REQUIREMENTS CHAPTER 4 PROTECTION REQUIREMENTS 4.1 General Means of protection for automatic disconnection against phase and earth faults shall be provided on the customer main switch.

More information

Specification for 1500V DC Traction Supply WOS 01.E

Specification for 1500V DC Traction Supply WOS 01.E Discipline Engineering Standard Category Rolling Stock Specification for 1500V DC Traction Supply WOS 01.E Applicability ARTC Network wide New South Wales Western Jurisdiction Victoria Primary Source (RIC

More information

Thank you for the detailed information regarding the Refurbishment Project at Marchwood MTS. This project will facilitate equipment maintainability.

Thank you for the detailed information regarding the Refurbishment Project at Marchwood MTS. This project will facilitate equipment maintainability. November 30, 2007 Mr. Ed Donkersteeg Hydro Ottawa Ltd. 1970 Merivale Road Nepean Ontario K2G 6Y9 Dear Mr. Donkersteeg, Marchwood MTS Refurbishment Project Notification of Conditional Approval of Connection

More information

An advisory circular may also include technical information that is relevant to the rule standards or requirements.

An advisory circular may also include technical information that is relevant to the rule standards or requirements. Revision 0 Electrical Load Analysis 2 August 2016 General Civil Aviation Authority advisory circulars contain guidance and information about standards, practices, and procedures that the Director has found

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

Research Brief. Impact of higher 25kV fault currents. T873 - October Background. Aims

Research Brief. Impact of higher 25kV fault currents. T873 - October Background. Aims Research Brief Impact of higher 25kV fault currents Background Increasing the maximum fault levels at traction feeder stations has the potential to reduce the costs of electrification schemes. The potential

More information

Distribution Code Part 4: Distributed Generation Requirements

Distribution Code Part 4: Distributed Generation Requirements Distribution Code Part 4: Distributed Generation Requirements Counties Power Limited Telephone 0800 100 202 14 Glasgow Road Fax (09) 237-0320 Private Bag 4 PUKEKOHE 2340 1.0 Introduction This document

More information

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION Work Order No: File Reference: 16/2/1 This application form for the connection of small scale embedded generation is for small

More information

ATTACHMENT - DFO STATEMENT OF NEED

ATTACHMENT - DFO STATEMENT OF NEED ATTACHMENT - DFO STATEMENT OF NEED Table of Contents Executive Summary... 3 1. Description of the Area... 5 1.1 Geographic Study Area... 5 1.2 Current System Configuration... 7 1.3 Distributed Generation...

More information

Equipotential Bonding of Rail Vehicles to Running Rail Potential

Equipotential Bonding of Rail Vehicles to Running Rail Potential Railway Group Standard Equipotential Bonding of Rail Vehicles to Running Rail Potential Synopsis This standard mandates the requirements for equipotenial bonding of rail vehicles to comply with the Electricity

More information

SA Power Networks Commissioning Witnessing Checklist

SA Power Networks Commissioning Witnessing Checklist SA Power Networks Commissioning Witnessing Checklist CUSTOMER NAME: SOLAR PV APPROVED CAPACITY: BATTERY APPROVED CAPACITY: kw (AC) kw (AC) OPERATING PHILOSOPHY: MAXIMUM EXPORT: Non-Export/Export kw (AC)

More information

AGREEMENT TECHNICAL CO-OPERATION BETWEEN ISO AND CEN. (Vienna Agreement)

AGREEMENT TECHNICAL CO-OPERATION BETWEEN ISO AND CEN. (Vienna Agreement) AGREEMENT ON TECHNICAL CO-OPERATION BETWEEN ISO AND CEN (Vienna Agreement) ISO CEN INTERNATIONAL ORGANIZATION FOR STANDARDIZATION (ISO) EUROPEAN COMMITTEE FOR STANDARDIZATION (CEN) AGREEMENT ON TECHNICAL

More information

Connecting your business diesel generation

Connecting your business diesel generation Connecting your business diesel generation March 2018 For connections more than 10kW 2 Contents Introduction to large distributed generation systems 3 Congestion management and safety 6 Application form

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Adopted Based on State and Tariff Interconnection Rules Applicable to Northern States Power,

More information

Net Metering Interconnection Requirements

Net Metering Interconnection Requirements Net Metering Interconnection Requirements Customer Generation Capacity Not Exceeding 100 kw Date: 2017-07-01 Version: 1 Revision History Date Rev. Description July 1, 2017 1 Initial Release Newfoundland

More information

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Adopted Based on State and Tariff Interconnection Rules Applicable to Northern States Power,

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

GC108: EU Code: Emergency & Restoration: Black start testing requirement

GC108: EU Code: Emergency & Restoration: Black start testing requirement Stage 01: Modification Proposal Grid Code GC108: EU Code: Emergency & Restoration: Black start testing requirement Purpose of Modification: This modification seeks to align the GB Grid Code with the European

More information

MEDIUM VOLTAGE PRODUCTS. Fault Current Limiters I S. -limiter and FC-Protector The worldʼs fastest switching devices

MEDIUM VOLTAGE PRODUCTS. Fault Current Limiters I S. -limiter and FC-Protector The worldʼs fastest switching devices MEDIUM VOLTAGE PRODUCTS The worldʼs fastest switching devices 2 FAULT CURRENT LIMITERS THE WORLDʼ S FASTETST SWITCHING DEVICES The worldʼs fastest switching devices ABBʼs fault current limiters disconnect

More information

POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS 21 MARCH 2013

POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS 21 MARCH 2013 POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS MARCH 03 PREPARED Y: Systems Capability DATE: 7 June 03 FINAL Disclaimer Purpose This

More information

EDS SUBSTATION LVAC SUPPLIES

EDS SUBSTATION LVAC SUPPLIES Document Number: EDS 08-1112 Network(s): Summary: EPN, LPN, SPN ENGINEERING DESIGN STANDARD EDS 08-1112 SUBSTATION LVAC SUPPLIES The standard details the requirements and options for the provision of LVAC

More information

Net Metering Interconnection Requirements. Customer Generation Capacity Not Exceeding 100 kw. Date: Version: 1

Net Metering Interconnection Requirements. Customer Generation Capacity Not Exceeding 100 kw. Date: Version: 1 Net Metering Interconnection Requirements Customer Generation Capacity Not Exceeding 100 kw Date: 2017-07-01 Version: 1 Revision History Date Rev. Description July 01, 2017 1 Initial release Newfoundland

More information

Proposed New ISO Rules Section Version 2.0 Generating Unit Technical Requirements ( New ISO Rules Section Version 2.

Proposed New ISO Rules Section Version 2.0 Generating Unit Technical Requirements ( New ISO Rules Section Version 2. Stakeholder Comment and Rationale Form AESO AUTHORITATIVE DOCUMENT PROCESS Stakeholder Consultation Draft 2012-11-29 Proposed New ISO Rules Section 502.5 Version 2.0 Generating Unit Technical Requirements

More information

Service and Rehabilitation Electrical Power Systems

Service and Rehabilitation Electrical Power Systems Service and Rehabilitation Electrical Power Systems From water to wire 3 ANDRITZ HYDRO Electrical Power System Modernization and rehabilitation International technology group ANDRITZ is a globally leading

More information

Controlling the Speed of Tilting Trains Through Curves

Controlling the Speed of Tilting Trains Through Curves Controlling the Speed of Tilting Trains Through Curves Synopsis This document mandates the means by which Tilting Trains may be operated at higher speeds than nontilting trains around curves. Signatures

More information

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map EH2741 Communication and Control in Electric Power Systems Lecture 3 Lars Nordström larsn@ics.kth.se 1 Course map 2 1 Outline 1. Repeating Power System Control 2. Power System Topologies Transmission Grids

More information

The University of New South Wales. School of Electrical Engineering and Telecommunications. Industrial and Commercial Power Systems Topic 6

The University of New South Wales. School of Electrical Engineering and Telecommunications. Industrial and Commercial Power Systems Topic 6 The University of New South Wales School of Electrical Engineering and Telecommunications Industrial and Commercial Power Systems Topic 6 PROTECTIONS 1 FUNCTION OF ELECTRICAL PROTECTION SYSTEMS Problems:

More information

Understanding BS 1363 Amendment No.4

Understanding BS 1363 Amendment No.4 Intertek Hilton House, Corporation Street, Rugby, Warwickshire, CV21 2DN UK info.uk@intertek.com 01788 578435 www.intertek.com Introduction A new Amendment applying to several parts of the BS 1363 standard

More information

Small Generator Interconnection Program Interconnection Technical Requirements

Small Generator Interconnection Program Interconnection Technical Requirements General Program Information What is the purpose of the PGE Small Generator Interconnection Program? How do I initiate a distribution interconnection request for my project? The purpose of our Small Generator

More information

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS. 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context indicates otherwise, this section and 25.212 of this title (relating to Technical Requirements

More information

POWER SYSTEM OPERATING INCIDENT REPORT MULTIPLE CONTINGENCY EVENT IN NORTH WEST TASMANIA ON 6 APRIL 2012

POWER SYSTEM OPERATING INCIDENT REPORT MULTIPLE CONTINGENCY EVENT IN NORTH WEST TASMANIA ON 6 APRIL 2012 POWER SYSTEM OPERATING INCIDENT REPORT MULTIPLE CONTINGENCY EVENT IN NORT WEST TASMANIA ON 6 APRIL 2012 PREPARED BY: Systems Capability DATE: 28 September 2012 FINAL IN NORT WEST TASMANIA ON 6 APRIL 2012

More information

GUIDELINES FOR OPERATING, METERING AND PROTECTIVE RELAYING FOR. NET METERED SYSTEMS UP TO 50 kw AND BELOW 750 VOLTS

GUIDELINES FOR OPERATING, METERING AND PROTECTIVE RELAYING FOR. NET METERED SYSTEMS UP TO 50 kw AND BELOW 750 VOLTS GUIDELINES FOR OPERATING, METERING AND PROTECTIVE RELAYING FOR NET METERED SYSTEMS UP TO 50 kw AND BELOW 750 VOLTS 1. INTRODUCTION... 3 1.1 POLICY ON CUSTOMER GENERATION.... 3 1.2 GENERATION SOURCES AND

More information

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION Summary Abhay Kumar Mata Prasad R C Maheshwari Asea Brown Boveri Ltd. 4th Floor, 71 Nehru Place, New Delhi

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

Electric Networks/Ina Lehto Updated Original 12/2011

Electric Networks/Ina Lehto Updated Original 12/2011 1 TECHNICAL APPENDIX 2 TO THE GUIDELINES CONNECTING AN ELECTRICITY GENERATION INSTALLATION TO THE DISTRIBUTION NETWORK CONNECTING AN INSTALLATION WITH A NOMINAL RATED CAPACITY OF OVER 100 These instructions

More information

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)*

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)* Australian Capital Territory Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)* Disallowable instrument DI2016 189 made under the Utilities Technical Regulation

More information

MICHIGAN ELECTRIC UTILITY

MICHIGAN ELECTRIC UTILITY MICHIGAN ELECTRIC UTILITY Generator Interconnection Requirements Category 4 Projects with Aggregate Generator Output Greater Than 550 kw or More, but Less Than or Equal to 2 MW August 3, 2009 Page 1 Introduction

More information

TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 NOVEMBER 2015

TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 NOVEMBER 2015 TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 AN AEMO POWER SYSTEM OPERATING INCIDENT REPORT FOR THE NATIONAL ELECTRICITY MARKET Published: August 2016 IMPORTANT

More information

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems Ben Huckaba, P.E. President & Principal Engineer 317-273-9841 benh@alphaeng.us Indiana University Bloomington,

More information

Substation LV AC Supplies. Document Number: 1-11-FR-04

Substation LV AC Supplies. Document Number: 1-11-FR-04 Substation LV AC Supplies Document Number: 1-11-FR-04 VERSION 1.0 June 2018 This functional requirements document is in line with the organisation's 1-11-ACS-04 LV AC Supplies Asset Class Strategy Intellectual

More information

CLP POWER HONG KONG LIMITED. SUPPLY RULES March 2001

CLP POWER HONG KONG LIMITED. SUPPLY RULES March 2001 CLP POWER HONG KONG LIMITED SUPPLY March 2001 ADVISORY SERVICE Advice concerning matters relating to the supply of electricity may be obtained free of charge from the Company. OTHER COMPANY PUBLICATIONS

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Design Considerations to Enhance Safety and Reliability for Service Entrance Switchboards

Design Considerations to Enhance Safety and Reliability for Service Entrance Switchboards Design Considerations to Enhance Safety and Reliability for Service Entrance Switchboards Robert P. Hansen, P.E., PhD GE Specification Engineer Introduction Switchboards are a widely used type of equipment

More information

School bus safety behaviours and responsibilities

School bus safety behaviours and responsibilities 4 School bus safety behaviours and responsibilities New Zealand has a very good school transport safety record. To maintain this record and minimise risks and hazards, everyone using school buses should

More information

TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT

TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT 14 TH MARCH 2008 TABLE OF CONTENTS Page 1 Introduction... 2 2 Charging Methodology Objectives... 4 3 Connection Charging Methodology... 5 4 Connection

More information

Overview Overvoltage protection

Overview Overvoltage protection A P P L I C AT I O N N OT E 1.0 Overview Overvoltage protection The APPLICATION NOTES (AN) are intended to be used in conjunction with the APPLICATION GUIDELINES Overvoltage protection Metal-oxide surge

More information

BSCP31 Trading Unit Application for West Burton A&B Power Stations

BSCP31 Trading Unit Application for West Burton A&B Power Stations Attachment 1 BSCP31 Trading Unit Application for West Burton A&B Power Stations Full description of nominated BM Unit(s) (in conjunction with form BSCP31/4.5) West Burton A Power Station comprises: Plant

More information

GC108: EU Code: Emergency & Restoration: Black start testing requirement

GC108: EU Code: Emergency & Restoration: Black start testing requirement Stage 01: Modification Proposal Grid Code GC108: EU Code: Emergency & Restoration: Black start testing requirement Purpose of Modification: This modification seeks to align the GB Grid Code with the European

More information

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM Page 1 of 19 Table of Contents 1.0 SCOPE...4 2.0 PURPOSE...4 3.0 LIMITATIONS...5 4.0 GENERAL INTERCONNECTION

More information

PROPOSAL FOR STORAGE CONNECTION REQUIREMENTS

PROPOSAL FOR STORAGE CONNECTION REQUIREMENTS PROPOSAL FOR STORAGE CONNECTION REQUIREMENTS Public consultation 15 March 23 April 2018 Contents 1 Introduction and background... 2 2 Definitions and applicability... 2 3 SPM categories types... 3 4 SPM

More information

Rapid Response. Lineside Signal Spacing. Railway Group Standard GK/RT0034 Issue Three Date September 1998

Rapid Response. Lineside Signal Spacing. Railway Group Standard GK/RT0034 Issue Three Date September 1998 Rapid Response Railway Group Standard Lineside Signal Spacing Synopsis This Standard specifies the minimum distance that must be provided between the first signal displaying a cautionary aspect and the

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information