Gateway South Transmission Project

Size: px
Start display at page:

Download "Gateway South Transmission Project"

Transcription

1 Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4

2 Phase 1 Comprehensive Progress Report Executive Summary Introduction The Gateway South project was announced by PacifiCorp in May 2007 to provide increased transmission capacity between Wyoming, Utah and southern Nevada. PacifiCorp initiated the Western Electricity Coordinating Council (WECC) Regional Planning Project Review process for Gateway South and the related Gateway West projects on June 25, The Gateway South Regional Planning Report was issued on May 28, The purpose of this Phase 1 comprehensive progress report is to demonstrate that sufficient technical studies have been conducted for the Gateway South Transmission Project (GS Project) to define the non-simultaneous planned rating(s) for the project and to describe the project preliminary plan-of-service. The Phase 1 studies that are outlined as part of the Study Plan (see Appendix A) focused on the non-simultaneous rating of the GS project, with some limited interactions with other paths and limited simultaneous analysis with the Gateway Projects. These limited simultaneous path interactions include the following: Gateway South (Aeolus Mona) and West of Aeolus and/or Bridger West transmission paths. Mona South and TOT 2C transmission paths (series paths) TOT 2B and TOT 2C transmission paths (exiting nomogram) Due to the scope and nature of the GS project, the Phase 1 portion of this study plan is intended to establish non-simultaneous ratings for the proposed transmission paths listed in Table 1. Table 1. Proposed Gateway South Transmission Lines Line Description 1 Aeolus Mona 500 kv, double circuit line 2 Mona South 500 kv, single circuit 500 kv line and single circuit 345 kv line 3 Red Butte Crystal 500 kv, single circuit line Transmission Path New New TOT 2C Path Rating Direction N S Bidirectional Bidirectional Due to the simultaneous interactions between the Gateway South and Gateway West projects, additional analysis was performed to evaluate the Gateway West project, east of Bridger (Bridger Aeolus Windstar). Because of this overlap between the two projects, WECC1-V4

3 Page ii of vii portions of this analysis will be included in both the Gateway South and Gateway West comprehensive progress reports. In an effort to assure that the proposed Energy Gateway Project (Gateway West, South and Central) were not dependant on other proposed projects to achieve their proposed ratings, sensitivity studies were performed to evaluate system performance with and with out the other project. Project Plan-of-Service An overview of the Gateway South transmission system modifications are summarized below and are illustrated in Figure 1. (A complete plan-of-service summary for the Project is included in the report Introduction Section I.) The Gateway South plan-ofservice calls for new 500 kv transmission facilities that will link Wyoming with the Utah Wasatch Front and continue to southern Utah/Nevada. Aeolus Mona 500 kv #1 & #2 (400 miles) Mona 500/345 kv #1 and #2 autotransformer (1500 MVA) Mona Sigurd 500 kv #1 (75 miles) Sigurd 500/345 kv #1 autotransformer (1500 MVA) Sigurd Red Butte 500 kv #1 (160 miles) Sigurd Red Butte 345 kv #2 (160 Miles) Red Butte 500/345 kv #1 autotransformer (1500 MVA) Red Butte 345 kv, Static VAr Controller (SVC) for voltage control Red Butte - Crystal 500 kv #1 (95 miles) Crystal 500 kv #1 thru #4 Phase Shifting Transformers (450 MVA, ±50 Degrees) Planned Operating Date The Gateway South schedule currently identifies the following in-service dates for key portions of the transmission project: Red Butte 345 kv SVC October 2011 Sigurd Red Butte 345 kv #2 December 2012 Red Butte Harry Allen (600 MW) Upgrade December 2012 Aeolus Mona 500 kv December 2016 Mona Sigurd Red Butte 500 kv December 2016 Red Butte Crystal 500 kv December 2016 Summary and Conclusions The following conclusions were drawn from the Phase 1 studies: Gateway West Analysis (included due to interactions with Gateway South) 1. TOT 4A Path Studies Based on technical findings of this report, the facilities proposed between Aeolus and Windstar will support increasing the nonsimultaneous TOT 4A path rating from 820 MW to 3435 MW. The limiting outage on this ii

4 Page iii of vii path is the N-1 of the Aeolus Windstar 500 kv line. Interactions between the TOT 4A path and other transmission paths will be evaluated during the Phase 2 (simultaneous) technical study review. To withstand a single circuit 500 kv outage, the Dave Johnston Difficulty Aeolus 230 kv line must be rebuilt to ACSR conductor/phase. Additionally, the Aeolus Windstar 230 kv #1 and #2 line must be constructed with ACSR conductor/phase. Interactions between the TOT 4A path and other transmission paths will be evaluated during the Phase 2 (simultaneous) technical study review. 2. West of Aeolus Path Studies Based on technical findings of this report, the facilities proposed between Jim Bridger and Aeolus will support a path rating of 2050 MW (simultaneous with South of Aeolus rating of 3000 MW). The West of Aeolus path rating is limited by the double line outage (N-2) outage of the Aeolus Bridger 500 kv line and the Aeolus Creston 230 kv or the Creston Bridger 230 kv lines and how much generation at Aeolus and Windstar that can be tripped for a specific system conditions. While the requirement for generator tripping at Jim Bridger (for outages west of Bridger), Aeolus or Windstar has been identified within the report, specific levels of Wyoming generator tripping vs. path flow levels and resource mix/location will need to be addressed in follow-on analysis. If the 230 kv line west of Aeolus (constructed 500 kv, energized 230 kv) was converted to 500 kv operation, transfers on the West of Aeolus path could be increased and generator tripping levels could be greatly reduced. Interactions between the West of Aeolus path and other transmission paths will be evaluated during the Phase 2 (simultaneous) technical study review. Gateway South 1. South of Aeolus (Aeolus Mona) Path Studies Based on technical findings of this report, the facilities proposed between Aeolus and Mona will support a path rating of 3000 MW (simultaneous with West of Aeolus flows of 2050 MW and Bridger West flows of 5200 MW). The Gateway South (South of Aeolus) path rating is limited by the double line outage (N-2) outage of the Aeolus Mona 500 kv #1 and #2 lines and how much generation at Aeolus and Windstar that can be tripped for a specific system condition. While the requirement for generator tripping at Jim Bridger (for outages west of Bridger), Aeolus or Windstar has been identified within the report, specific levels of Wyoming generator tripping vs. path flow levels and resource mix/location will need to be addressed in follow-on analysis. iii

5 Page iv of vii If the 230 kv line west of Aeolus (constructed 500 kv, energized 230 kv) was converted to 500 kv operation, generator tripping levels could be greatly reduced. Interactions between the Gateway South path and other transmission paths will be evaluated during the Phase 2 (simultaneous) technical study review 2. Mona South Path Studies Based on technical findings of this report, the facilities proposed South of Mona Path (Mona Sigurd Red Butte) will support a path rating (simultaneous with the TOT 2B paths) of at least 2400 MW north to south and 790 MW south to north. The Mona South path rating is limited by (1) load levels in southern Utah and (2) rating of the TOT 2C transmission path. Further Interactions between the Mona South path and other transmission paths will be evaluated during the Phase 2 (simultaneous) technical study review. 3. TOT 2C Path Studies Based on technical findings of this report, the facilities proposed to be added to the TOT 2C Path (Red Butte Harry Allen/Crystal) will support a path rating (simultaneous with the TOT 2B paths) of at least 2100 MW north to south and 1700 MW south to north. The TOT 2C path rating is limited by the outage of the Red Butte Crystal 500 kv line, and subsequent (proposed) tripping of a portion of the series capacitor bank at Harry Allen. Further Interactions between the TOT 2C path and other transmission paths will be evaluated during the Phase 2 (simultaneous) technical study review. Voltage Stability Analysis Voltage stability analysis was performed on the Case 1a, 1b and 1c base case for each of the paths noted above. Per the WECC reactive margin requirements, the 5% case showed acceptable reactive margins for the n-1 outages while the 2.5% case showed acceptable reactive margin for the n-2 outages. Sensitivity Studies Sensitivity study technical results have demonstrated that the Energy Gateway Projects can achieve their rating with or without the Great Basin North 500 kv line being constructed. The technical findings of this report demonstrate that sufficient technical studies have been conducted for the Gateway South Transmission Project (GS Project) to define the non-simultaneous planned rating(s) for the project and to describe the project preliminary plan-of-service. iv

6 Page v of vii FIGURE 1 Gateway South Single-line Gateway West Aeolus 230 kv to Windstar 500 kv to Windstar 230 kv to Creston/Bridger SVC 230 kv MVA 500 kv to Bridger Middle kv Gateway Central 500 kv to Limber Middle miles 3 - Athabaska/TW Mona #1 #2 500 kv MVA Sigurd 500 kv 345 kv 75 miles 3 - Athabaska/TW MVA 345 kv Red Butte #2 160 miles 3 - Athabaska/TW Crystal 500 kv 1500 MVA 345 kv 160 miles 2 Cardinal 954 ACSR 95 miles 3 - Athabaska/TW New 500 kv NPC Bus 500 kv MVA +50 PST 500 kv 345 kv 230 kv v

7 TABLE OF CONTENTS Gateway South Transmission Project Page vi of vii I. Introduction...1 General Project Plan-of-Service Planned Operating Date II. Objectives...4 A. Satisfy Reliability Criteria B. Define Plan-of-Service C. Acquire a Non-Simultaneous Rating III. IV. Approach...6 Conclusions...8 V. Summary of Study Results...11 VI. Discussion of Technical Results...23 VII. Sensitivity Studies...35 VIII. Phase 1 Technical Findings...44 vi

8 Page vii of vii APPENDICES APPENDIX A APPENDIX B APPENDIX C APPENDIX D APPENDIX E APPENDIX F APPENDIX G Study Plan Energy Gateway Project Plan of Service Base Case Summaries Power Flow - tables, flow diagrams Post Transient Outages - tables, flow diagrams Sensitivity Studies - tables, flow diagrams Voltage Stability - reactive margin tables Dynamic Stability Performance Tables Dynamic Stability Plots vii

9 Phase 1 - Comprehensive Progress Report I. Introduction General The Gateway South project was announced by PacifiCorp in May 2007 to provide increased transmission capacity between Wyoming, Utah and southern Nevada. This project is designed to meet the needs of PacifiCorp s network transmission customers by delivering network resource to network loads, supporting retail customer load growth, and improve reliability. PacifiCorp initiated the Western Electricity Coordinating Council (WECC) Regional Planning Project Review process for Gateway South and the related Gateway West projects on June 25, This process was completed on May 28, 2008 with the issuance of the Gateway South Regional Planning Report. The purpose of this Phase 1 comprehensive progress report is to demonstrate that sufficient technical studies have been conducted for the Gateway South Transmission Project (GS Project) to define the non-simultaneous planned rating(s) for the project and to describe the project preliminary plan-of-service. This report summarizes the results of technical studies conducted in concert with Gateway West Transmission Project to evaluate the planned ratings of the Energy Gateway Projects. These technical studies include power flow, transient stability, and post-transient power flow and voltage stability analysis. Appendix A contains the detailed study plan that was followed to complete these studies. Project Plan-of-Service The Gateway South Project proposed plan-of-service system additions/ modifications are summarized below: Aeolus Mona 500 kv #1 & #2 (400 miles, 3- Athabaska/TW ) Mona 500/345 kv #1 and #2 autotransformer (1500 MVA) Mona Sigurd 500 kv #1 (75 miles, 3- Athabaska/TW ) Sigurd 500/345 kv #1 autotransformer (1500 MVA) Sigurd Red Butte 500 kv #1 (160 miles, 3- Athabaska/TW ) Sigurd Red Butte 345 kv #2 (160 Miles, 2-Cardnal 954 ACSR) Red Butte 500/345 kv #1 autotransformer (1500 MVA) Red Butte 345 kv, -100 MVAR/+250 MVAR SVC, plus three MVAR MSC capacitors (nominally, the output should be held to -20 MVAR/+50 MVAR during steady-state conditions) Red Butte - Crystal 500 kv #1 (95 miles, 3-Athabaska/TW ) Crystal 500 kv #1 thru #4 PST (450 MVA, ±50 Degrees) The proposed plan-of-service single-line diagram for the Gateway South Project is illustrated in Figure 2. The complete plan-of-service for the Gateway South Transmission Project is provided in Appendix B. The transmission system changes

10 Page 2 of 51 defined above will support nonsimultaneous path flows up the levels defined in this report. Planned Operating Date The Gateway South schedule currently identifies the following in-service dates for key portions of the transmission project: Red Butte 345 kv SVC October 2011 Sigurd Red Butte 345 kv #2 December 2012 Red Butte Harry Allen (600 MW) Upgrade December 2012 Aeolus Mona 500 kv December 2016 Mona Sigurd Red Butte 500 kv December 2016 Red Butte Crystal 500 kv December 2016

11 Page 3 of 51 FIGURE 2 Gateway South Single-line Gateway West Aeolus 230 kv to Windstar 500 kv to Windstar 230 kv to Creston/Bridger SVC 230 kv MVA 500 kv to Bridger Middle kv Gateway Central 500 kv to Limber Middle miles 3 - Athabaska/TW Mona #1 #2 500 kv MVA Sigurd 500 kv 345 kv 75 miles 3 - Athabaska/TW MVA 345 kv Red Butte #2 160 miles 3 - Athabaska/TW Crystal 500 kv 1500 MVA 345 kv 160 miles 2 Cardinal 954 ACSR 95 miles 3 - Athabaska/TW New 500 kv NPC Bus 500 kv MVA +50 PST 500 kv 345 kv 230 kv

12 II. Objectives Gateway South Transmission Project Page 4 of 51 The objectives of this study are summarized below: A. Satisfy Reliability Criteria The study results will comply with the PacifiCorp, Idaho Power, NV Energy (Nevada Power/Sierra Pacific) and NERC/WECC planning standards. B. Define Plan-of-Service 1. Provide an opportunity for WECC members to review and comment on the Project proposed plan-of-service. 2. Establish a consensus that the plan-of-service supports the project nonsimultaneous rating. C. Acquire a Non-Simultaneous Rating 1. Establish a non-simultaneous rating for the following transmission paths: o Gateway South (Aeolus Mona) o Mona South (Mona Sigurd Red Butte) o TOT 2C (Red Butte Harry Allen 345 kv and Red Butte Crystal 500 kv) Due to the simultaneous interactions between the Gateway South and Gateway West projects, additional analysis was performed to evaluate the Gateway West project, east of Bridger (Bridger Aeolus Windstar). Because of this overlap between the two projects, portions of this analysis will be included in both the Gateway South and Gateway West comprehensive progress reports 2. The sensitivity analysis was performed as a preliminary assessment of interactions between GS and projects that are planned to be developed in the same time frame as GS. Additionally, one other project was analyzed in parallel with GS which could have an impact on the performance of the existing transmission system. This project, Gateway West (GW) will be constructed at least one year before GS. The following projects and uncertainties were evaluated as sensitivity cases: a. A single 500 kv line generic version of a northern Nevada project will be modeled to include either the Ely Energy Center & 500 kv Line, or the Great Basin South 500 kv lines. The Great Basin North 500 kv line (Robinson Summit Cedar Hill 500 kv) was modeled both inservice and out-of-service as a sensitivity. (See Case 1A-S configuration.) b. Southern portion GS: Mona Sigurd Red Butte, bi-directional rating (For this analysis, the southern Utah flows in Case 1c was compared with Case 1a.)

13 Page 5 of 51 c. TOT 2C: Add a second Red Butte Harry Allen/Crystal line, bidirectional rating d. Different resource mix in Wyoming was evaluated to determine the impact of higher concentrations of wind generation. 3. Provide a Comprehensive Progress Report for submittal to the WECC Planning Coordination Committee (PCC) for entry into Phase 2 of the WECC Path Rating Process for the Gateway South Transmission Project.

14 Page 6 of 51 III. Approach Due to the complexity of the Gateway South Transmission Project, a variety of technical studies were required to establish a non-simultaneous rating for project segments that traversed the Wyoming, Utah, Idaho and southern Nevada transmission systems. Appendix A contains the detailed study plan that was followed to complete these studies. The following technical studies are documented in this Report: A. Gateway West Because of simultaneous interactions between Gateway West and Gateway South, there will be some overlap in technical findings between the two reports. Specific technical analysis included: 1. TOT 4A Path Studies These studies evaluated the impacts of adding two-230 kv lines and one-500 kv line to the TOT 4A path. Interactions between this path and other paths (TOT 4B, etc.) will be addressed during Phase 2 studies. 2. West of Aeolus Path Studies Due to interactions between this path and the South of Aeolus (Aeolus-Mona) transmission path, both paths will be heavily loaded during the analysis. These studies evaluated in interaction of new transmission lines constructed on the West of Aeolus path. Due to the significant transmission system that would be constructed to support transfers west of Aeolus to Bridger, the West of Aeolus path has been defined. This path will include the following transmission lines: o Aeolus Bridger 500 kv, measured at Aeolus o Aeolus Creston 230 kv, measured at Aeolus o Platte Latham (Echo Springs) 230 kv, measured at Platte o Mustang Bridger 230 kv, measured at Mustang o Mustang Wind River 230 kv, measured at Mustang Please refer to the Gateway West Comprehensive Progress Report for the technical analysis that support the non-simultaneous planned rating(s) for the Gateway West Project and a description of the project preliminary plan-ofservice. B. South of Aeolus (Aeolus Mona) Studies These studies evaluated the impacts of adding the two Aeolus Mona 500 kv lines on the transmission system. Due to interactions between this path and the Gateway West paths (West of Aeolus and Bridger West), both paths will be heavily loaded during the analysis. C. Mona South (Mona Sigurd Red Butte) Studies These studies evaluated the impact of adding the Mona Sigurd Red Butte 500 kv lines in parallel with existing 345 kv facilities to form the Mona South path. Due to

15 Page 7 of 51 heavy transfers through southern Utah, a second Sigurd Red Butte 345 kv line has been identified as part of the Gateway South project. D. TOT 2C (Red Butte Harry Allen/Crystal) Studies These studies evaluated the impact of adding the Red Butte Crystal 500 kv line on the TOT 2C path. Interaction between the TOT 2C and 2B (Glen Canyon Sigurd 230 kv and Pinto Four Corners 345 kv) were also evaluated. E. Sensitivity Studies Various sensitivity studies were performed (see Appendix A study plan) to evaluate the impact of the Gateway South under varying system configurations and conditions.

16 IV. Conclusions Gateway South Transmission Project Page 8 of 51 As substantiated by the technical analysis documented in this report, the following conclusions can be drawn: A. Gateway West - TOT 4A Path and West of Aeolus Path Studies 1. TOT 4A Path Studies Based on technical findings of this report, the facilities proposed between Aeolus and Windstar will support increasing the nonsimultaneous TOT 4A path rating from 820 MW to 3435 MW. The limiting outage on this path is the N-1 of the Aeolus Windstar 500 kv line. Interactions between the TOT 4A path and other transmission paths will be evaluated during the Phase 2 (simultaneous) technical study review. To withstand a single circuit 500 kv outage, between Aeolus and Windstar, the Dave Johnston Difficulty Aeolus 230 kv line must be rebuilt to ACSR conductor/phase. Additionally, the Aeolus Windstar 230 kv #1 and #2 line must be constructed with ACSR conductor/phase. Voltage stability analysis was performed on the Case 1a, 1b and 1c base case for the TOT 4A path. Per the WECC reactive margin requirements, the 5% case showed acceptable reactive margins for the n-1 outages while the 2.5% case showed acceptable reactive margin for the n-2 outages. 2. West of Aeolus Path Studies Based on technical findings of this report, the facilities proposed between Jim Bridger and Aeolus will support a path rating of 2050 MW (simultaneous with South of Aeolus rating of 3000 MW). The West of Aeolus path rating is limited by the double line outage (N-2) outage of the Aeolus Bridger 500 kv line and the Aeolus Creston 230 kv or the Creston Bridger 230 kv lines and how much generation at Aeolus and Windstar that can be tripped for a specific system conditions. While the requirement for generator tripping at Jim Bridger (for outages west of Bridger), Aeolus or Windstar has been identified within the report, specific levels of Wyoming generator tripping vs. path flow levels and resource mix/location will need to be addressed in follow-on analysis. If the 230 kv line west of Aeolus (constructed 500 kv, energized 230 kv) was converted to 500 kv operation, transfers on the West of Aeolus path could be increased and generator tripping levels could be greatly reduced. Voltage stability analysis was performed on the Case 1a, 1b and 1c base case for the West of Aeolus path. Per the WECC reactive margin requirements, the 5% case showed acceptable reactive margins for the n-1 outages while the 2.5% case showed acceptable reactive margin for the n-2 outages. Interactions between the West of Aeolus path and other transmission paths will be evaluated during the Phase 2 (simultaneous) technical study review.

17 Page 9 of 51 B. South of Aeolus (Aeolus Mona) Path Studies Based on technical findings of this report, the facilities proposed between Aeolus and Mona will support a path rating of 3000 MW (simultaneous with West of Aeolus flows of 2050 MW and Bridger West flows of 5200 MW). The Gateway South (South of Aeolus) path rating is limited by the double line outage (N-2) outage of the Aeolus Mona 500 kv #1 and #2 lines and how much generation at Aeolus and Windstar that can be tripped for a specific system condition. While the requirement for generator tripping at Jim Bridger (for outages west of Bridger), Aeolus or Windstar has been identified within the report, specific levels of Wyoming generator tripping vs. path flow levels and resource mix/location will need to be addressed in follow-on analysis. If the 230 kv line west of Aeolus (constructed 500 kv, energized 230 kv) was converted to 500 kv operation, generator tripping levels could be greatly reduced. Voltage stability analysis was performed on the Case 1a, 1b and 1c base case for the South of Aeolus path. All reactive margins evaluated met WECC requirements. Interactions between the Gateway South path and other transmission paths will be evaluated during the Phase 2 (simultaneous) technical study review. C. Mona South Path Studies Based on technical findings of this report, the facilities proposed South of Mona Path (Mona Sigurd Red Butte) will support a path rating (simultaneous with the TOT 2B paths) of at least 2400 MW north to south and 790 MW south to north. The Mona South path rating is limited by (1) load levels in southern Utah and (2) rating of the TOT 2C transmission path. Voltage stability analysis was performed on the Case 1a, 1b and 1c base case for the Mona South path. Per the WECC reactive margin requirements, the 5% case showed acceptable reactive margins for the n-1 outages while the 2.5% case showed acceptable reactive margin for the n-2 outages. Further Interactions between the Mona South path and other transmission paths will be evaluated during the Phase 2 (simultaneous) technical study review. D. TOT 2C Path Studies Based on technical findings of this report, the facilities proposed to be added to the TOT 2C Path (Red Butte Harry Allen/Crystal) will support a path rating (simultaneous with the TOT 2B paths) of at least 2100 MW north to south and 1700 MW south to north. The TOT 2C path rating is limited by the outage of the Red Butte Crystal 500 kv line, and subsequent (proposed) tripping of a portion of the series capacitor bank at Harry Allen. Voltage stability analysis was performed on the Case 1a, 1b and 1c base case for the TOT 2C path. Per the WECC reactive margin requirements, the 5% case showed acceptable reactive margins for the n-1 outages while the 2.5% case showed acceptable reactive margin for the n-2 outages.

18 Page 10 of 51 Further Interactions between the TOT 2C path and other transmission paths will be evaluated during the Phase 2 (simultaneous) technical study review. E. Sensitivity Studies Sensitivity study technical results have demonstrated that the Energy Gateway Projects can achieve their rating with or without the Great Basin North 500 kv line being constructed. The technical findings of this report demonstrate that sufficient technical studies have been conducted for the Gateway South Transmission Project (GS Project) to define the non-simultaneous planned rating(s) for the project and to describe the project preliminary plan-of-service.

19 Page 11 of 51 V. Summary of Study Results A brief summary of the power flow, stability, post-transient, voltage stability and sensitivity studies completed to evaluate the performance of the Gateway Project are presented in this section. Appendix D, E and F contain technical study findings, flow diagrams and performance tables which are discussed in this section and discussed in detail in Section VI and VII. Study assumptions, guidelines, criteria and methodology, and system representations are described in the Study Plan provided in Appendix A. In addition, the plan-of-service for the entire Energy Gateway Project is summarized in Appendix B. A. Gateway West (TOT 4A Path and West of Aeolus Path) Studies After the preliminary Gateway Project plan-of-service was developed, three base cases representing a wide range of resource mix and flow conditions for the 2015 Heavy Summer operating conditions were used to evaluate the Gateway West Project (Bridger Aeolus Windstar) facility additions under a wide range of flows conditions. 1. TOT 4A Path a. Power Flow Analysis Power flow study results for all three base cases indicate: 1) For all base cases conditions, there were no steady-state (N-0) bus voltage or line flow violations within the study area. 2) For all single contingency (N-1) disturbances, there were no bus voltage or line loading violations. 3) line loading violations were evident for this portion of the system in the base cases. b. Stability Analysis Stability study results indicate: 1) All disturbances simulated were stable and system performance was well within the NERC/WECC and PacifiCorp Planning Standards tolerances. 2) The rating of this path is limited during high transfer conditions (Case 1a) by the single line (N-1) outage of the Aeolus Windstar 500 kv line causing the dynamic voltage dip at Difficulty 230 kv dipping by 26.5% to.753 pu (below 20% voltage deviation for 26.5 cycles). Upon replacing the Dave Johnston Difficulty Aeolus 230 kv proposed line conductor ( ACCC) with ACSR conductor and repeating the disturbance, the dynamic voltage dip at Difficulty 230 kv dipping by 22.8% to.792 pu (below 20%

20 Page 12 of 51 voltage deviation for 15 cycles). This performance meets the NERC/WECC transient voltage criteria. Conclusion: The Dave Johnston Difficulty Aeolus 230 kv line must be rebuilt to ACSR conductor/phase. Additionally, the Aeolus Windstar 230 kv #1 and #2 line must be constructed with ACSR conductor/phase. 3) In reviewed the Case 1b (N-1 and N-2) dynamic stability study findings vs. Case 1a, the following results were noted: o It is evident from the voltage swings that reducing thermal generation at Bridger and Windstar while increasing wind generation at Aeolus and on the 230 kv system in Wyoming will reduce the system impacts of the Aeolus - Windstar 500 kv outage. (Change in voltage swing on 230 kv system south of DJ reduced.) c. Post-Transient Analysis Post-transient study results within this portion of the three base cases indicate: 1) For all single contingency (N-1) disturbances, there were no bus voltage or line loading violations. 2) line loading violations were evident for this portion of the system in the base cases. d. Voltage Stability Analysis Voltage stability analysis was performed on the Case 1a, 1b and 1c base case for the TOT 4A path. Appendix F contains all the Tables associated with the reactive margin (Q/V) study results. Per the WECC reactive margin requirements, the 5% case showed acceptable reactive margins for the n-1 outages while the 2.5% case showed acceptable reactive margin for the n-2 outages. Study Conclusion: Based on technical findings of this report, the facilities proposed between Aeolus and Windstar will support increasing the nonsimultaneous TOT 4A path rating from 820 MW to 3435 MW. The limiting outage on this path is the N-1 of the Aeolus Windstar 500 kv line. Interactions between the TOT 4A path and other transmission paths will be evaluated during the Phase 2 (simultaneous) technical study review. 2. West of Aeolus Path a. Power Flow Analysis Power flow study results for all three base cases indicate:

21 Page 13 of 51 1) For all base cases conditions, there were no steady-state (N-0) bus voltage or line flow violations within the study area. 2) For all single contingency (N-1) disturbances, there were no bus voltage or line loading violations. 3) Under heavy transfer conditions west and south of Aeolus (Case 1a and 1b), Jim Bridger generator tripping will be required (see posttransient results) for the double line (N-2) outage of the Jim Bridger Populus 500 kv #1 and #2 lines to alleviate (1) overload conditions on Three Mile Knoll 345 kv series capacitor and (2) overloads on the Hunter #2 345/24 kv GSU transformer. (This overload condition can also be relieved by adjusting the Hunter GWU transformer taps.) 4) Under light transfer conditions (Case 1c) west and south of Aeolus generator tripping will not be required for this double contingency (N- 2) outages. b. Stability Analysis Stability study results indicate: 1) All disturbances simulated were stable and system performance was well within the NERC/WECC and PacifiCorp Planning Standards tolerances. 2) In reviewed the Case 1b (N-1 and N-2) dynamic stability study findings vs. Case 1a, the following results were noted: It is evident from the voltage swings that reducing thermal generation at Bridger and Windstar while increasing wind generation at Aeolus and on the 230 kv system in Wyoming will: o Increased the system impacts of the Aeolus - Bridger 500 kv (N-1 and N-2) disturbances. (Change in voltage swings in southern Wyoming) o Reduce the system impacts of the Bridger - Populus 500 kv (N-1 and N-2) disturbances. (Change in voltage swings at Caribou and other locations significantly reduced.) c. Post-Transient Analysis Post-transient study results within this portion of the three base cases indicate: 1) For all single contingency (N-1) disturbances, there were no bus voltage or line loading violations. 2) For the double line (N-2) outage of the Aeolus Bridger 500 kv line and the Aeolus Creston 230 kv line or the Creston Bridger 230 kv line: o Under light or moderate flow conditions (Case 1a and 1c) on the West of Aeolus Path (<1300 MW), for this N-2

22 Page 14 of 51 contingency, there were no bus voltage or line loading violations. o However, under high flow conditions (Case 1b) on the West of Aeolus path (>2050 MW), for this N-2 contingency, 1100 MW of generator tripping will be required at Aeolus to prevent voltage collapse (none converged solution). After generator tripping, the case solved and there were no bus voltage or line loading violations. 3) For the double line (N-2) outage of the Bridger Populus 500 kv #1 and #2 lines: o Under light flow conditions (Case 1c) on the West of Aeolus path (<975 MW) and Bridger West path (<3345 MW), for this N-2 contingency, there were no bus voltage or line loading violations. o Under moderate flow conditions (Case 1a) on the West of Aeolus path (<1300 MW) and high flow condition on Bridger West Path (5200 MW), for this N-2 contingency, generator tripping will be required at Bridger (750 MW) to prevent voltage collapse (none converged solution). After generator tripping, the case solved and there were no bus voltage or line loading violations. o However, under high flow conditions (Case 1b) on the West of Aeolus path (>2050 MW) and maximum flow condition on Bridger West path (5200 MW), for this N-2 contingency, generator tripping will be required at Aeolus (1100 MW) to prevent voltage collapse (none converged solution). After generator tripping, the case solved and there were no bus voltage or line loading violations. e. Voltage Stability Analysis Voltage stability analysis was performed on the Case 1a, 1b and 1c base case for the West of Aeolus path. Appendix F contains all the Tables associated with the reactive margin (Q/V) study results. Per the WECC reactive margin requirements, the 5% case showed acceptable reactive margins for the n-1 outages while the 2.5% case showed acceptable reactive margin for the n-2 outages. Study Conclusion: Based on technical findings of this report, the facilities proposed between Jim Bridger and Aeolus will support a path rating of 2050 MW (simultaneous with South of Aeolus flows of 3000 MW). The West of Aeolus path rating is limited by the double line outage (N-2) outage of the Aeolus Bridger 500 kv line and the Aeolus Creston 230 kv or the Creston Bridger 230 kv lines and how

23 Page 15 of 51 much generation at Aeolus and Windstar that can be tripped for specific system conditions. While the requirement for generator tripping at Jim Bridger (for outages west of Bridger), Aeolus or Windstar has been identified within the report, specific levels of Wyoming generator tripping vs. path flow levels and resource mix/location will need to be addressed in follow-on analysis. If the 230 kv line west of Aeolus (constructed 500 kv, energized 230 kv) was converted to 500 kv operation, transfers on the West of Aeolus path could be increased and generator tripping levels could be greatly reduced. Interactions between the West of Aeolus path and other transmission paths will be evaluated during the Phase 2 (simultaneous) technical study review. B. South of Aeolus (Aeolus - Mona) Path Studies After the preliminary Gateway Project plan-of-service was developed, three base cases representing a wide range of resource mix and flow conditions for the 2015 Heavy Summer operating conditions were used to evaluate the South of Aeolus Path (Aeolus Mona) facility additions under a wide range of flows conditions. 1. Power Analysis Power flow study results for all three base cases indicate: a. For all base cases conditions, there were no steady-state (N-0) bus voltage or line flow violations within the study area. b. For all single contingency (N-1) disturbances, there were no bus voltage or line loading violations. c. Under heavy transfer conditions west and south of Aeolus (Case 1a and 1b), Windstar generator tripping will be required (see post-transient results) for the double line (N-2) outage of the Aeolus Mona 500 kv #1 and #2 lines, to prevent system voltage collapse (none converged solution). Upon tripping generation, there were no bus voltage or line load violations. d. Under light transfer conditions west and south of Aeolus (Case 1c) generator tripping will not be required for this double contingency (N-2) outages. 2. Stability Analysis Stability study results indicate: a. All disturbances simulated were stable and system performance was well within the NERC/WECC and PacifiCorp Planning Standards tolerances. b. For the double line (N-2) outage of the Aeolus Mona 500 kv #1 and #2 lines:

24 Page 16 of 51 o Under light flow conditions (Case 1c) on both the West of Aeolus path (<1300 MW) and the South of Aeolus path (514 MW), for this N-2 contingency, no generator tripping will be required and system performance meets the NERC/WECC transient voltage criteria. o Under moderate flow conditions (Case 1a) on the West of Aeolus path (<1300 MW) and maximum flow conditions on the South of Aeolus path (3000 MW), for this N-2 contingency, generator tripping will be required at Windstar (680 MW) to achieve voltage stability. After generator tripping, the case solved and system performance meets the NERC/WECC transient voltage criteria. o Under high flow conditions (Case 1b) on the West of Aeolus Path (>2050 MW) and maximum flow conditions on the South of Aeolus path (3000 MW), for this N-2 contingency, generator tripping will be required at Aeolus (1100 MW) and Windstar (600 MW) to achieve voltage stability. After generator tripping, the case solved and system performance meets the NERC/WECC transient voltage criteria. c. In reviewed the Case 1b (N-1 and N-2) dynamic stability study findings vs. Case 1a, the following results were noted: o It is evident from the voltage swings that reducing thermal generation at Bridger and Windstar while increasing wind generation at Aeolus and on the 230 kv system in Wyoming will increased the system impacts of the Aeolus - Mona 500 kv (N-1 and N-2) disturbances. (Change in voltage swings in southern Wyoming and the Cache Valley of Northern Utah). o A change in Wyoming generation (type and location) appears to have only minor impacts on Western Interconnection system performance outside of Wyoming. (E.g. Southern Utah/Nevada disturbances, N-2 PV generation, and IPP DC Line bi-pole outage.) 3. Post-Transient Analysis Post-transient study results within this portion of the three base cases indicate: a. For all single contingency (N-1) disturbances, there were no bus voltage or line loading violations. b. For the double line (N-2) outage of the Aeolus Mona 500 kv #1 and #2 lines: o Under light flow conditions (Case 1c) on both the West of Aeolus path (<1300 MW) and the South of Aeolus path (514

25 Page 17 of 51 MW), for this N-2 contingency, there were no bus voltage or line loading violations. o Under moderate flow conditions (Case 1a) on the West of Aeolus path (<1300 MW) and maximum flow conditions on the South of Aeolus path (3000 MW), for this N-2 contingency, generator tripping will be required at Aeolus (1100 MW) to prevent voltage collapse (none converged solution). Additionally, a 100 MVAr shunt capacitor (proposed) will be required at Bonanza 345 kv to meet the WECC post-transient voltage deviation criteria. Following generator tripping the case solved. Upon switching a capacitor at Bonanza, there were no bus voltage or line loading violations. o Under high flow conditions (Case 1b) on the West of Aeolus Path (>2050 MW) and maximum flow conditions on the South of Aeolus path (3000 MW), for this N-2 contingency, generator tripping will be required at Aeolus (1100 MW) and Windstar (600 MW) to prevent voltage collapse (none converged solution). After generator tripping, the case solved and there were no bus voltage or line loading violations. Study Conclusion: Based on technical findings of this report, the facilities proposed between Aeolus and Mona will support a path rating of 3000 MW (simultaneous with flows on West of Aeolus of 2050 MW and Bridger West of 5200 MW). The South of Aeolus (Aeolus - Mona) path rating is limited by the double line outage (N-2) outage of the Aeolus Mona 500 kv #1 and #2 lines and how much generation at Aeolus and Windstar that can be tripped for specific system conditions. While the requirement for generator tripping at Jim Bridger (for outages west of Bridger), Aeolus or Windstar has been identified within the report, specific levels of Wyoming generator tripping vs. path flow levels and resource mix/location will need to be addressed in follow-on analysis. If the 230 kv line west of Aeolus (constructed 500 kv, energized 230 kv) was converted to 500 kv operation, generator tripping levels could be greatly reduced. Interactions between the South of Aeolus path and other transmission paths will be evaluated during the Phase 2 (simultaneous) technical study review.

26 Page 18 of Voltage Stability Analysis Voltage stability analysis was performed on the Case 1a, 1b and 1c base case for the South of Aeolus path. Appendix F contains all the Tables associated with the reactive margin (Q/V) study results. Per the WECC reactive margin requirements, the 5% case showed acceptable reactive margins for the n-1 outages while the 2.5% case showed acceptable reactive margin for the n-2 outages. C. Mona South Path Studies After the preliminary Gateway Project plan-of-service was developed, three base cases representing a wide range of resource mix and flow conditions for the 2015 Heavy Summer operating conditions were used to evaluate the Mona South Path (Mona Sigurd Red Butte) facility additions under a wide range of flows conditions. 1. Power Flow Analysis Power flow study results for all three base cases indicate: a. For all base cases conditions, there were no steady-state (N-0) bus voltage or line flow violations within the study area. NOTE: Under maximum TOT 2B path flow conditions in the Case 1a base case, depressed steady-state voltages were noted near the Pinto and Sigurd PST transformers. Voltages were well within the design specification for the substation equipment. b. For all single contingency (N-1) disturbances (evaluated under heavy north to south and south to north flow conditions), there were no bus voltage or line loading violations. c. line loading violations were evident for this portion of the system in the base cases. NOTE: In the Gateway West (West of Aeolus study results above), under heavy transfer conditions west and south of Aeolus, Jim Bridger generator tripping will be required (see post-transient results) for the double line (N-2) outage of the Jim Bridger Populus 500 kv #1 and #2 lines to alleviate (1) overload conditions on Three Mile Knoll 345 kv series capacitor and (2) overloads on the Hunter #2 345/24 kv GSU transformer. (This overload condition can also be relieved by adjusting the Hunter GWU transformer taps.) 2. Dynamic Stability Analysis Stability study results indicate: a. All disturbances simulated were stable and system performance was well within the NERC/WECC and PacifiCorp Planning Standards tolerances.

27 Page 19 of Post-Transient Analysis Post-transient study results within this portion of the three base cases indicate: a. For all single contingency (N-1) disturbances, there were no bus voltage or line loading violations. b. line loading violations were evident for this portion of the system in the base cases. 4. Voltage Stability Analysis Voltage stability analysis was performed on the Case 1a, 1b and 1c base case for the Mona South path. Appendix E contains all the Tables associated with the reactive margin (Q/V) study results. Per the WECC reactive margin requirements, the 5% case showed acceptable reactive margins for the n-1 outages while the 2.5% case showed acceptable reactive margin for the n-2 outages. Study Conclusion: Based on technical findings of this report, the facilities proposed South of Mona Path (Mona Sigurd Red Butte) will support a path rating (simultaneous with the TOT 2B paths) of at least 2400 MW north to south and 790 MW south to north. The Mona South path rating is limited by (1) load levels in southern Utah and (2) rating of the TOT 2C transmission path. Further Interactions between the Mona South path and other transmission paths will be evaluated during the Phase 2 (simultaneous) technical study review. D. TOT 2C Path After the preliminary Gateway Project plan-of-service was developed, three base cases representing a wide range of resource mix and flow conditions for the 2015 Heavy Summer operating conditions were used to evaluate the Mona South Path (Mona Sigurd Red Butte) and the TOT 2C Path (Red Butte Harry Allen/Crystal) facility additions under a wide range of flows conditions. 1. Power Flow Analysis Power flow study results for all three base cases indicate: 1) For all base cases conditions, there were no steady-state (N-0) bus voltage or line flow violations within the study area. 2) For maximum north to south flow conditions on the TOT 2C path (Case 1a and 1b), the (N-1) outage of the Red Butte Crystal 500 kv line will result flows on the Harry Allen 345 kv #1, #2 and #3 phase shifting transformers exceeded the emergency rating. This overload condition can be relieved by bypassing the Red Butte 345 kv series capacitor.

28 Page 20 of 51 NOTE: Additionally, under N-1 outages of the RB-CR 500 kv line in the Case 1a base case, depressed steady-state voltages were noted near the Pinto and Sigurd PST transformers. Voltages were well within the design specification for the substation equipment. 3) For heavy south to north flow conditions on the TOT 2C path (Case 1c), for all single contingency (N-1) disturbances, there were no bus voltage or line loading violations. 4) line loading violations were evident for this portion of the system in the base cases. 2. Dynamic Stability Analysis Stability study results indicate: a. All disturbances simulated were stable and system performance was well within the NERC/WECC and PacifiCorp Planning Standards tolerances. 3. Post-Transient Analysis Post-transient study results within this portion of the three base cases indicate: 1. For maximum north to south flow conditions on the TOT 2C path (Case 1a and 1b), the single line (N-1) outage of the Red Butte Crystal 500 kv line will result flows on the Harry Allen 345 kv #1, #2 and #3 phase shifting transformers exceeded the emergency (104%). This overload condition was relieved by bypassing 50% of the Harry Allen 345 kv series capacitor. At this point in the simulation, flows on the Sigurd 230 kv PST were 99% of the emergency rating, flows on the Pinto PST were 90% of the emergency rating and flows on the HA 345 kv PST were 94% of the emergency rating. 2. For heavy south to north flow conditions on the TOT 2C path (Case 1c), for all single contingency (N-1) disturbances, there were no bus voltage or line loading violations. However, following the single line (N-1) outage of the Red Butte Crystal 500 kv, flows on the Pinto PST were 91% of the emergency rating, flows on the Sigurd 230 kv PST were 92% of the emergency rating, and flows on the HA 345 kv PST were 86% of the emergency rating. 3. There were no double contingency (N-2) bus voltage or line loading violations that were evident for this portion of the system in the base cases.

29 Page 21 of Voltage Stability Analysis Voltage stability analysis was performed on the Case 1a, 1b and 1c base case for the TOT 2C path. Appendix E contains all the Tables associated with the reactive margin (Q/V) study results. Per the WECC reactive margin requirements, the 5% case showed acceptable reactive margins for the n-1 outages while the 2.5% case showed acceptable reactive margin for the n-2 outages. Study Conclusion: Based on technical findings of this report, the facilities proposed to be added to the TOT 2C Path (Red Butte Harry Allen/Crystal) will support a path rating (simultaneous with the TOT 2B paths) of at least 2100 MW north to south and 1700 MW south to north. The TOT 2C path rating is limited by the outage of the Red Butte Crystal 500 kv line, and subsequent (proposed) tripping of a portion of the series capacitor bank at Harry Allen. Further Interactions between the TOT 2C path and other transmission paths will be evaluated during the Phase 2 (simultaneous) technical study review. E. Sensitivity Studies Due to the judicious selection of resources and path flows modeled in the Case 1a, 1b and 1c base cases, the following sensitivities have previously been addressed in the study findings above: 1. Different resource mix in Wyoming to evaluate higher concentrations of wind generation. (For this analysis, Case 1b will be used to evaluate higher concentrations of wind vs. Case 1a.) 2. Southern portion GS: Mona Sigurd Red Butte, bi-directional rating (For this analysis, the southern Utah flows in Case 1c will be compared with Case 1a.) 3. TOT 2C: Add a second Red Butte Harry Allen/Crystal line, bi-directional rating Each of these base cases assumed that the Great Basin North 500 kv line (Robinson Summit Cedar Hill 500 kv) would be in-service prior to the completion of both the Gateway West and Gateway South projects. As the Great Basin North 500 kv line may potentially have an impact on the Energy Gateway Project, sensitivity analysis was performed with the Case 1a base case to ascertain any changes in system performance if the Great Basin North 500 kv line is out-of-service. This sensitivity analysis was also performed to demonstrate that the Energy Gateway Projects can achieve their rating with or without the Great Basin North 500 kv line being constructed. Detailed technical findings of the sensitivity studies are provided in Section VII. A summary of the sensitivity study findings is summarized below:

30 Page 22 of 51 Removal of the Great Basin North 500 kv line (Robin Summit Cedar Hill 500 kv) will: 1. Based on power flow steady-state and contingency analysis results modeled in the study area, no significant difference was seen in study results. 2. From a transient stability perspective: o Voltage dips in key locations following N-2 of the Aeolus Mona 500 kv line (w/generator tripping) will be 4-5% deeper (duration below 20% will increase 19.6 cycles). o Voltage dips in key locations following N-2 of the Bridger -Populus 500 kv line (w/generator tripping) will be 1.5% deeper (duration below 20% will increase 6.2 cycles). o Voltage dips for key locations following N-2 of the Aeolus Windstar 500 kv line will be 1.3% deeper All transient stability simulations modeled met the NERC/WECC dynamic voltage dip criteria. 3. From a post-transient power flow perspective, only minor differences were seen in the study results. Study Conclusion: Sensitivity study technical results have demonstrated that the Energy Gateway Projects can achieve their rating with or without the Great Basin North 500 kv line being constructed.

31 Page 23 of 51 VI. Discussion of Technical Results Technical study results noted below assume system changes noted in Section VIII were implemented in the Energy Gateway configuration. While the analysis covered a large geographical area, technical results will be documented below by specific path or geographical area. Technical results in this section are documented in Appendix D (power flow, flow diagrams, post-transient), F (Dynamic Stability Performance Tables) and E (voltage stability). The tables inserted in subsections below were developed based on a review of the study results in these appendices. During the course of evaluating the three Gateway base cases (1a, 1b, and 1c), concerns surfaced relating to the high voltage that was evident on the line side of series capacitors at Three Mile Knoll 345 kv, Populus 345 kv, Three Peaks 345 kv, Pinto 345 kv and Red Butte 345 kv, during steady state and contingency conditions. As this issue was so prevalent in the various tables developed to summarize the technical study findings, it was decided that rather than repeat the same finding in multiple locations in Sections A, B and C below, it will be addressed at the start of this section. Series Capacitor Over Voltage Concerns Issue: Under steady-state (N-0), single-contingency (N-1) and doublecontingency (N-2) conditions, high bus voltages ( to pu) were noted on the line-side of the series capacitors at Three Mile Knoll 345 kv (existing), Pinto 345 kv (parameters being specified), Three Peaks 345 kv (being procured), Red Butte 345 kv (planned), and Populus 345 kv (being procured). Resolution: B&V has indicated that per Appendix D, the maximum voltage on the line side of the series capacitor would be about 125%. This value was observed on the Bridger Populus 345 kv circuit series capacitors for the loss of both Bridger Populus 500 kv circuits. As per IEEE Std , capacitors may be operated above rated voltage under emergency and infrequent conditions. The magnitude of the over voltages that may be tolerated without loss of life is dependent upon the duration of each over voltage, the number of applications and

32 Page 24 of 51 the temperature of the capacitor. The capacitor short time power-frequency capabilities given in IEEE Std is shown on the previous page, which is only a representative curve. Similar characteristics need to be specified for the new series capacitors, based on this report s finding. PacifiCorp provides the following feedback: Three Mile Knoll 345 kv: The following capability (excerpt from the equipment specification) is provided: The following series capacitor banks, which are in the procurement stage (draft specifications provided) meet this high voltage requirement: o Populus 345 kv: o Three Peaks 345 kv: o Pinto 345 kv: Recommendation: As future series capacitor banks are specified, high voltage concerns need to be addressed. A. Gateway West (TOT 4A Path and West of Aeolus Path) Studies 1. TOT 4A Path After the preliminary Gateway Project plan-of-service was developed, three base cases representing the 2015 Heavy Summer operating conditions were used to evaluate the modified TOT4A transmission path under a wide range of flows conditions. The technical results that are based on analysis performed for this path are summarized below: a. Power Flow Analysis The results of power flow analysis results for this path are summarized below: 1) Steady-State Conditions Case 1a (High Thermal) Case 1b (High Wind) Case 1c (High So. Utah S-N) No steady-state (N-0) bus voltage or line No steady-state (N-0) bus voltage or line No steady-state (N-0) bus voltage or line loading violations were evident for this portion loading violations were evident for this portion loading violations were evident for this portion of the base case. of the base case. of the base case. base case. 2) Contingency Conditions Case 1a (High Thermal) Case 1b (High Wind) Case 1c (High So. Utah S-N) base case.

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No. 17-035-40 Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis

TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis July 25, 2018 Table of Contents 1. Introduction... 5 1.1. Project Description and

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Midway/Monument Area TTC Study

Midway/Monument Area TTC Study Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny

More information

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions. March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Interconnection System Impact Study Final Report February 19, 2018

Interconnection System Impact Study Final Report February 19, 2018 Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning. A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Date: March 15, Mr. Enoch Davies WECC Technical Staff 155 North 400 West, Suite 200 Salt Lake City, Utah

Date: March 15, Mr. Enoch Davies WECC Technical Staff 155 North 400 West, Suite 200 Salt Lake City, Utah TRANSMISSION PLANNING Craig Quist Director of Area/Transmission Planning East PacifiCorp 1407 West North Temple, Suite 275 Salt Lake City, Utah 84116 (801)220-4264 PH (801)220-2842 FAX Date: March 15,

More information

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project. Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project April 23, 2003 Introduction Eurus originally requested an interconnection

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

Craig Quist Craig Quist

Craig Quist Craig Quist TRANSMISSION PLANNING Craig Quist, Manager Transmission Development & Planning PacifiCorp 1407 West North Temple, Suite 275 Salt Lake City, Utah 84140 801-220-4264 FAX 801-220-2842 craig.quist@pacificorp.com

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report San Diego Gas & Electric, a Sempra Energy Utility SDGE HVDC Phase 1 Project No. 101512 Revision 01 11/29/2018 SDG&E High

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

Georgia Transmission Corporation Georgia Systems Operations Corporation

Georgia Transmission Corporation Georgia Systems Operations Corporation Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia

More information

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED DATE: June 28, 2011 STAFF: Brian Janonis Brian Moeck, PRPA Pre-taped staff presentation: none WORK SESSION ITEM FORT COLLINS CITY COUNCIL SUBJECT FOR DISCUSSION Electric Transmission Update. EXECUTIVE

More information

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30)

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30) TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30) Submitted to TOT1A Stakeholders and TOT1A Interconnected Utilities And Western Electricity Coordinating Council June 6, 2013

More information

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives Addendum San Juan Major Project Tri-State Generation and Transmission Association Power System Planning December, 2008

More information

NorthernLights HVDC Project

NorthernLights HVDC Project WECC COMPREHENSIVE PROGRESS REPORT December 4, 2008 Prepared for TransCanada by Ben Williams TABLE OF CONTENTS EXECUTIVE SUMMARY... III 1.0 BACKGROUND & INTRODUCTION... 1 1.1 BACKGROUND... 1 1.2 INTRODUCTION...

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS System Operations Department System Planning Section June 2001 TABLE OF CONTENTS 1.0 Executive Summary...Page

More information

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Connection Engineering Study Report for AUC Application: AESO Project # 1674 APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia

More information

Targeted Application of STATCOM Technology in the Distribution Zone

Targeted Application of STATCOM Technology in the Distribution Zone Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric

More information

APPENDIX F: Project Need and Description

APPENDIX F: Project Need and Description APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was

More information

Rocky Mountain Power Five Year Study Findings & Kick Off Meeting

Rocky Mountain Power Five Year Study Findings & Kick Off Meeting 2000 PACIFICORP PAGE 1 Attachment K Rocky Mountain Power Five Year Study Findings & Kick Off Meeting Thursday, December 8 2016 2000 PACIFICORP PAGE 2 Study Areas for 2016 Findings Reports Southeast, Utah

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

SMUD 2014 Ten-Year Transmission Assessment Plan. Final. December 18, 2014

SMUD 2014 Ten-Year Transmission Assessment Plan. Final. December 18, 2014 SMUD 2014 Ten-Year Transmission Assessment Plan Final December 18, 2014 I CONTENTS Executive Summary... III 1 Introduction... 2 1.1 Reliability Criteria and Guidelines... 2 1.2 Load Forecast... 2 1.3 Demand

More information

2012 LOCAL TRANSMISSION PLAN:

2012 LOCAL TRANSMISSION PLAN: Colorado PUC E-Filings System 2012 LOCAL TRANSMISSION PLAN: TRANSMISSION COORDINATION AND PLANNING COMMITTEE ANNUAL TRANSMISSION ASSESSMENT FOR BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, L.P., D/B/A

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2014 Annual Ten-Year Transmission Plan Assessment Report November 20, 2014 For information or questions regarding this Transmission Assessment Report,

More information

Q217 Generator Interconnection Project

Q217 Generator Interconnection Project Q217 Generator Interconnection System Impact Study APS Contract No. 52588 By Arizona Public Service Company Transmission Planning November 25, 2013 Version 2.0 Prepared by Utility System Efficiencies,

More information

4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority

4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority ,.,.;i')!i,:;;',;~~~. 'ffrff mm I Government of India ~ ~.I Ministry of Power 4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority III ~~~~~~I"1",~~1 ;J' :. r System Planning & Project Appraisal Division

More information

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 1 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 2 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC

More information

2013 ANNUAL PROGRESS REPORT

2013 ANNUAL PROGRESS REPORT March 1, 2013 Mr. David Franklin, Chairman WECC Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768-2560 Mr. Enoch Davies WECC Technical Staff 155 North 400 West,

More information

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS July 15, 2004 TABLE OF CONTENTS Page No. 1. Description of Pasadena s Transmission Lines and Facilities...1 A. Overview:... 1 B.

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

Facilities Study for Alberta to US Available Transfer Capability

Facilities Study for Alberta to US Available Transfer Capability Facilities Study for Alberta to US Available Transfer Capability Report No: NPP2002-05 June 3, 2002 System Planning & Grid Operations, Transmission Line of Business Engineering Services Executive Summary

More information

Project #94. Generation Interconnection System Impact Study Report Revision

Project #94. Generation Interconnection System Impact Study Report Revision Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection

More information

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study Vince Leung May 1, 2014 Reviewed by: Chris Pink (edited July 8, 2014) Table of Contents Page Background... 4 Objectives... 5 Study

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta

More information

PES Cook Islands KEMA Grid Study Final Report

PES Cook Islands KEMA Grid Study Final Report Integrating PV Solar and Wind generation with the TAU electric system Te Aponga Uira O Tumu-Te_Varovaro Contents 1. Executive summary... 2 2. Introduction... 5 2.1 Proposed wind turbine sites... 6 2.2

More information

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study System Operations Department System Planning Section March 2002 Table of Contents: 1.0 EXECUTIVE SUMMARY 4 2.0 COST ESTIMATES 8 2.1 Cost

More information

ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study

ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study Final Report ABB Power Systems Consulting June 27, 2016 LEGAL NOTICE This document, prepared by ABB Inc, is an

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

QP 311 Kingdom Community Wind Project Interconnection Feasibility Study. July, 2010 FINAL REPORT. Prepared by:

QP 311 Kingdom Community Wind Project Interconnection Feasibility Study. July, 2010 FINAL REPORT. Prepared by: FINAL REPORT QP 311 Kingdom Community Wind Project Interconnection Feasibility Study July, 2010 Prepared by: i For ISO New England and Vermont Electric Power Company Table of Contents Executive Summary...

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2013 Annual Ten-Year Transmission Plan Assessment Report December 1, 2013 For information or questions regarding this Transmission Assessment Report,

More information

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and

More information

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications Supplement to 2013-2014 ISO Transmission Plan Harry Allen-Eldorado Project Description and Functional Specifications Description and Functional Specifications of Proposed Economically Driven Harry Allen

More information

Verde Transmission, LLC. Verde Project. System Impact Study Report

Verde Transmission, LLC. Verde Project. System Impact Study Report Verde Transmission, LLC Verde Project System Impact Study Report March 2017 Prepared by: Public Service Company of New Mexico Foreword This report was prepared for Verde Transmission, LLC by the PNM Transmission/

More information

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Interconnection Feasibility Study Report GIP-369-FEAS-R1 Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power

More information

A Case Study on Aggregate Load Modeling in Transient Stability Studies

A Case Study on Aggregate Load Modeling in Transient Stability Studies A Case Study on Aggregate Load Modeling in Transient Stability Studies Presented by: Daniel Feltes Siemens PTI Coauthors: Carlos Grande-Moran, Bernardo Fernandes, James Feltes, Ming Wu and Robert Wells

More information

Wyoming Energy Projects

Wyoming Energy Projects Wyoming Energy Projects Wyoming Infrastructure Authority Spring Conference March 28-29, 2019 PacifiCorp Overview Two divisions Rocky Mountain Power and Pacific Power 5600 Employees 1.9 million electricity

More information

PUD ELECTRIC SYSTEM INTERCONNECTION

PUD ELECTRIC SYSTEM INTERCONNECTION APPENDIX A PROCEDURES & REQUIREMENTS for OKANOGAN PUD ELECTRIC SYSTEM INTERCONNECTION Version 4.0 December 2011 Version 4.0 12/28/2011 Page 1 of 15 TABLE OF CONTENTS DEFINITIONS 1.0 Introduction 2.0 Procedures

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

The Long-Range Transmission Plan

The Long-Range Transmission Plan The Long-Range Transmission Plan 2015 2025 Matt Koenig Presentation to ESPWG / TPAS October 29 th, 2015 Long-Range Transmission Plan Driver of the Plan is to maintain local reliability 10-year planning

More information

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Status of PNM s Completed Transmission Construction Projects 11/30/2017 Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

New 115 kv Disconnect Switches at Bloomsburg MTS

New 115 kv Disconnect Switches at Bloomsburg MTS 115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115

More information

TransCanyon Cross-Tie Transmission Project

TransCanyon Cross-Tie Transmission Project TransCanyon Cross-Tie Transmission Project Cross-Tie Phase I Progress Report Supplemental Simultaneous Analysis Final Report Revision 1.1 August 2017 Table of Contents 2 Page Executive Summary -------------------------------------------------------------------------------------------

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information