Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.

Size: px
Start display at page:

Download "Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project."

Transcription

1 Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project April 23, 2003 Introduction Eurus originally requested an interconnection capacity of 104 MW for their wind farm in north eastern Oregon. However, since extensive local transmission modifications might be required, Eurus also considered a reduced capacity of 41 MW. This report discusses the requirements at each level, Eurus subsequent selection of the 41 MW level, and detailed studies at the lower level. 41 MW Interconnection The wind farm can be interconnected to PacifiCorp s existing 69 kv line from the Walla Walla Central Substation to the Pendleton Substation, in the vicinity (south) of the Freewater Substation, via a radial line. The interconnection point would be 9.21 miles due east from the wind farm step-up transformer. PacifiCorp will require a breaker on the line. For this generation level, PacifiCorp recommends its standard conductor size of 397 ACSR (summer rating of 551 amps), as a minimum. For this generation level, EURUS plans to use a single step-up transformer rated at 30/40/50 MVA, with an impedance of 8% on a 30 MBA base. The high and low windings are both grounded wye. The wind turbines will be MHI 1000A. Alternatively, the wind farm could be connected to PacifiCorp s existing 69 kv Umapine Substation. This interconnection point would require approximately an 11 mile radial connection, due east from the wind farm step-up transformer about 8 miles, then north about 3 mile to Umapine Sub. A breaker will be required on the new radial line, preferable at the interconnection point, provided it can be properly coordinated. The Umapine Substation connects to PacifiCorp s existing 69 kv line from Walla Walla Central Substation to the Pendleton Substation at a tap point about 6.5 miles from Walla Walla Central. The tap point about 2.5 miles from the Umapine Sub. This radial tap is currently 4/0 ACSR and must be reconductored 1

2 to at least 397 ACSR. Again, for this generation level, PacifiCorp recommends its standard conductor size of 397 ACSR, as a minimum, for the new radial connection to Umapine. 104 MW Interconnection PacifiCorp s 69 kv line from Walla Walla s Central Sub to Pendleton is currently operated normally open at Weston, about 7 miles south of Freewater Sub, to avoid overloads in the event of a BPA 230 kv line outage. Future expected changes to the BPA system may allow PacifiCorp to operate this line closed, which PacifiCorp may wish to do. The existing conductor on this entire line (about 40 miles) will not support 104 MW. Therefore, interconnections at Freewater or Umapine will require re-conductoring the entire line. The Central Substation is connected to the Walla Walla Substation via two parallel 69 kv paths. One path is 2.5 miles of 397 ACSR. The other path includes about ¾ mile of 397 ACSR. The segments of 397 ACSR on both these paths will require reconductoring so that each path can carry the generator output to the Walla Walla Substation in the event that one of the paths is not available. Use of a scheme to transfer trip generation in the event of a line outage could avoid this reconductor requirement between Central and Walla Walla. There is an alternative new path that could avoid reconductoring approximately the last two miles of the Pendleton to Central 69 kv line (at the Central end), and the two 69 kv paths (or transfer trip scheme) from Central to Walla Walla. The new path would run from a new tap point, about two miles west of Central on the line from Pendleton to Central, and continue about 1.5 miles north to the Walla Walla Substation. This new path would parallel an existing 230 kv line from Walla Walla to Hurricane. It would effectively bypass the Central Substation. The breaker at the existing line at the Central Substation would be set to operate normally open. Additionally, an interconnection at Umapine will require reconductoring the 2.5 mile Umapine tap line. For this generation level, PacifiCorp recommends its standard conductor size of 1272 ACSR (summer rating of

3 amps), as a minimum, for new construction and for reconductoring. For this generation level, EURUS plans to use two step-up transformers each rated at 30/40/50 MVA, with an impedance of 8% on a 30 MBA base. The high and low windings are both grounded wye. EURUS has suggested a configuration that would require a new interconnection location west of Freewater and South of Umapine, at a point about eight miles east of the wind farm s step-up transformer. The new interconnection point would be connected to both the Umapine Sub and the previously mentioned interconnection point south of the Freewater Sub, and the existing 3.5 mile 69 kv segment from Umapine tap to Freewater (on the existing 69 kv line from Walla Walla Central Sub to Pendleton) would be removed. This alternative would still require reconductoring the remaining segments (31 miles from Pendleton to just below Freewater and 2.5 miles from Umapine Sub to Umapine Tap and 6.5 miles from Umapine Tap to Walla Walla Central, or about 4.5 miles from the Umapine Tap to the new tap point which will connect directly to the Walla Walla Substation). PacifiCorp suggests another alternative to eliminate reconductoring at this generation level a radial connection from the wind farm that bypasses Umapine Sub and connects directly to PacifiCorp s Walla Walla Central Substation. In this configuration, existing single circuit transmission structures from Umapine Sub to Walla Walla Central could be replaced by double circuit structures,if necessary. A 69 kv breaker position would be added at Walla Walla Central Substation. For this generation level, PacifiCorp recommends its standard conductor size of 1272 ACSR, as a minimum, for the new construction. Other Requirements For interconnection, EURUS will be required to design, procure and install sufficient reactive compensation to their 34.5 kv system to maintain unity power factor at the point of interconnection. EURUS transmission agent will be required to provide a detailed model of the wind farm generators and distribution 3

4 system suitable for use with the PTI Power System Stability Program. These additional studies will model if additional reactive support will be required to PacifiCorp s transmission system. Eurus Decision Regarding Wind Farm Size and Interconnection Configuration Subsequent to the above study phase and conclusions, Eurus decided that it would elect to construct a 41 MW wind farm development at this time. Eurus may request to expand the farm to a power level that can be carried by a 795 ACSR conductor (in summer, about 101 MW) at an unknown later date. Additionally, Eurus elected to deliver the power via new 69 kv transmission to an interconnection point just below PacifiCorp s existing Freewater Substation on the Pendleton-Walla Walla Central 69 kv line (about 9 miles). Except for the last mile (approximatley) of this line, Eurus has selected a conductor size of 795 ACSR. The last section will be constructed at 397 ACSR. If Eurus increases the capacity of the wind farm in the future, they may abandon the interconnection point and the last mile of line and redirect the line northward as a radial to the Walla Walla Substation as a new interconnection point, all with 795 ACSR. A short circuit analysis was performed on the 41 MW system and this interconnection configuration, to determine if the interconnection of the wind farm would cause the fault duty on PacifiCorp breakers to exceed the rating of the breakers. The study results showed that no breaker ratings would be exceeded. PacifiCorp will require a breaker to protect the radial interconnection and proposes that it be located at the high side of the Wind Farm s step up transformer. The addition of this breaker creates a three-terminal line and the best coordination with breakers at Walla Walla Central and Pendleton are achieved by placing the breaker at the west end of the radial interconnection. The interconnection point will require a motor-operated three-way switch. Minor protection changes may be required at the Walla Walla Central and Pendleton locations to implement deadline check on reclosing at Walla Walla Central and synch check at 4

5 Pendleton. Eurus will not be implementing reclosing at their 69 kv breaker. Communication can either be a microwave path from the wind farm or a combination of a fiber path to Eurus off-site O&M location and a leased line beyond that point. A microwave path will require the installation of a tower near the Wind Farm. Eurus has recently selected the microwave alternative. SCADA databases at the PacifiCorp control centers must be modified to recognize real time data. PacifiCorp anticipates that Eurus will own the radial interconnection. PacifiCorp will own the switches at the interconnection point. Load Flow and Transient Stability Analysis The load flow and transient stability used detailed models of the Combine Hills Wind Farm distribution system and its MHI 1000A wind turbines. The results are described in Appendix A and its significant conclusions are summarized below. Summary Conclusions 1) Eurus will install a 41 MW Wind Farm which will be interconnected via a radial 69 kv line at a point on the existing Walla Walla Central Pendleton line near the Freewater Substation. Eurus has selected a 795 ACSR conductor for their 10 mile radial line, except for the last mile at the interconnection end. The last mile will use 397 ACSR conductor. 2) The interconnection will require a breaker at the high side of the wind farm step-up transformer, and a motoroperated switch at the interconnection point. Minor protection modifications may be required at PacifiCorp s Walla Walla Central and Pendleton substations to accommodate reclosing. 3) Existing breakers in the vicinity of the Wind Farm will not require upgrading. 4) A communications tower will be required at the Wind Farm if microwave is selected. 5

6 5) Eurus must add sufficient reactive compensation to the Wind Farm to deliver a unity power factor at the point of interconnection. Note, there may be periods (eg, light load) when PacifiCorp will want Eurus to operate its reactive compensation in such a way that reactive power is absorbed at the interconnection point, to minimize high operating voltages on PacifiCorp s system. 6) PacifiCorp will require that Eurus design their system and reactive compensation to avoid voltage changes of 3% or greater o the PacifiCorp system. PacifiCorp has estimated that Eurus 5 MVAR size capacitor banks will exceed PacifiCorp s voltage limit on PacifiCorp s system. Additionally, PacifiCorp has estimated that these same capacitor banks will exceed manufacturer s voltage change limitations on Eurus wind turbines. PacifiCorp will not be responsible for the design of Eurus system to minimize voltage change impacts on the PacifiCorp or Eurus systems. 6

7 Appendix A System Impact Study For Combine Hills Wind Project April 23, 2003 Report Prepared by: PacifiCorp Transmission Planning

8 System Impact Study Combine Hills Wind Project TABLE OF CONTENTS I. Project Description 2 II. Study Objectives 2 III. Study Results 2 Existing System Post Combine Hills Generation IV. Voltage Fluctuation from Capacitor Switching 5 V. Stability Studies 5 VI. Recommendations 6 Appendices Diagram #1: Walla Walla Area Diagram 7 Power Flow Summary Tables 8 Power Flow Plots 10 Stability Case Summary Table 14 Stability Plots 15 Revised: ALW 1

9 System Impact Study Combine Hills Wind Project I. PROJECT DESCRIPTION The Combine Hills Wind Power Project (Combine Project) is located approximately 10 miles west of Freewater, Oregon. The project consists of volt, 1 MW wind turbine generators, connected to 34.5 kv distribution system. Each generator is connected to the distribution circuit via a kv transformer. A single, 3-phase, 69 / 34.5 kv, 30/40/50 MVA transformer is used to step up the voltage of the project to 69 kv. A 8.92 mile 69 kv, 795 ACSR "Drake" conductor transmission line connects to a one mile 397 ACSR transmission line which connects the project to the proposed West Freewater 69 kv substation. This study addresses the 41 MW output of the planned wind farm project. II. STUDY OBJECTIVES The study was conducted to discover any voltage or other transmission impacts from the integration of the Combine Project to PacifiCorp's transmission system in the Walla Walla area as network service. In addition, any existing outage limitations were studied. These outage limitations were studied because a case that modeled all of the PacifiCorp and BPA wind farm additions that have been added to the system was not previously available. System impacts targeted for identification in previous studies were examined as a result of the model change. The study investigated transmission system impacts under two different loading conditions: 1) Peak summer load conditions and 2) Spring minimum load conditions. Both existing system and the system with the Combine Hills Wind Project added were studied. The wind farm was modeled in detail to investigate any potential voltage impacts to the wind turbines. Stability studies were only conducted for the peak summer load conditions to determine overall effects on transmission stability due to the addition of the wind farm. III. STUDY RESULTS The N-0 system configurations were studied to determine if any normal loading problems are encountered for peak or minimum load conditions Several N-1 conditions were studied to determine if any system problems exist due to outages. These conditions were evaluated for peak summer load conditions and for light load conditions. The following outages were conducted to determine any deficiencies in system performance: Walla Walla - Vantage 230 kv Line Outage Walla Walla - N. Lewiston 230 kv Line Outage Walla Walla - Enterprise 230 kv Line Outage Walla Walla - Wallula 230 kv Line Outage Walla Walla - Mill Creek and Central 69 kv Line Outage Walla Walla (PAC) - Walla Walla (BPA) 69 kv Line Outage Bowman - Central 69 kv Line Outage Central - Umapine 69 kv Line Outage Walla Walla (BPA) - Pomeroy (BPA) 115 kv Line Outage Joso - Burbank 115 kv Line Outage McNary - Roundup 230 kv Line Outage Wallula - McNary 230 kv Line Outage The Combine Hills Wind Project was modeled to "mid-level" representation as shown on the next page in figure 1. Revised: ALW 2

10 System Impact Study Combine Hills Wind Project Figure 1 The model is a simplified model of the distribution network of the wind farm. Turbines are lumped together at electrical centers to model each major feeder of the wind farm. The equivalent model of the turbine involves modeling the generator as a fixed MW and MVAR device (uncompensated) along with fixed amount of 600 volt capacitors (capacitive compensation) to achieve an overall power factor dependent upon generation of the turbine. The following table provides information on how each turbine was modeled from minimum generation to maximum generation (it is assumed that each turbine has the same output): Achieved Total Each Each Uncomp. Turbine Targeted Comp. Plant Turbine Turbine Turbine Reactive Turbine Comp. Turbine Output Output Output Output Consumption Output Capacitor Output (MW) (kw) (pu) PF (kvar) PF (kvar) PF Heavy summer peak load conditions were modeled using the WECC 2003 HS4AP base case. Light load conditions were modeled using the WECC 2001 LSP1 base case, modeled with minimum expected loads for the Walla Walla area. Existing System (Pre Combine Hills Generation) Revised: ALW 3

11 System Impact Study Combine Hills Wind Project No problems were identified under light load conditions. Two major N-1 problems were identified for the existing system. The first problem occurs for a 69 kv outage between Central and Freewater during peak conditions. This outage results in unacceptable low voltages in the Freewater area (Freewater 69 kv voltage is pu). This indicates that the existing system cannot support the entire load on the Central - Pendleton 69 kv line from Pendleton only. No problems were identified for this outage under light loading conditions. Because the chance of this outage occurring at peak load is small, it is recommended that the 69 kv line continue to be operated open between Weston and Athena. If an outage between Central and Umapine occurs at peak loads, the entire Umapine load (10.4 MW) must be curtailed and the Weston load (13.5 MW) would be curtailed to 85% (11.5 MW) in order to meet acceptable voltage limitations. The second problem occurs for an outage of the McNary - Roundup 230 kv line during peak conditions. The result is a severe overload of the Hermiston - Pendleton 69 kv line (169%), an overload of the Weston - Athena 69 kv line (113%), and unacceptable low voltages in the Hermiston and Pendleton 69 kv areas (Athena 69 kv voltage is pu). Opening the Hermiston - Pendleton 69 kv line eliminates the overloaded line and prevents low voltages in the Hermiston area. However, the overload on the Central-Pendleton 69 kv line increases to 153%. Opening the Central-Pendleton 69 kv line between Weston and Athena eliminates this line overload. Voltages are still low in the Pendleton 69 kv area, but they are greatly improved (Athena 69 kv voltage is pu). Reactive additions in the Pendleton area should be investigated as they may alleviate the remaining problems. As these low voltages are an existing system problem, the solution is beyond the scope of this study and should be investigated by Network Planning. Post Combine Hills Generation No problems were identified under light load conditions. The first major N-1 problem identified for the existing system was investigated after the addition of the Combine Hills generation. The new generation does not improve the situation, and was therefore not studied in further detail. The Central - Freewater 69 kv line is not able to support the load at Umapine even with the addition of the Combine Hills generation. No system upgrades are required to solve the problem because the Combine Hills generation does not contribute to this system problem. The second pre-existing problem was also tested after the addition of the Combine Hills generation. This problem is also not improved by the addition of the new generation, and was therefore not studied in further detail. It is recommended the Hermiston - Pendleton 69 kv and Weston - Athena 69 kv lines continue to be operated open as needed for the existing system. No system upgrades are required to solve the problem because the Combine Hills generation does not contribute to this system problem. Revised: ALW 4

12 System Impact Study Combine Hills Wind Project IV. VOLTAGE FLUCTUATIONS FOR CAPACITOR SWITCHING The effect of switching the 5 MVAR capacitors at the Combine Hills generation was studied at maximum output (41 MW), 35 MW, 30 MW, 20 MW and 10 MW. The following table summarizes voltage effects at the wind turbines and the nearest load, Weston. It should be noted the voltage change at Weston exceeds PacifiCorp's voltage fluctuation limit of 3.0% for generation output greater than 30 MW. The wind turbines can experience from 5-8% voltage fluctuations for switching of a 5 MVAR bank. This amount of voltage fluctuation may be excessive for the wind turbines. Switching a 3 MVAR bank results in a 2.3% voltage change at Weston and a 6.7% voltage change at the wind turbines at full load. Generator Total Initial MVAR Switching Capacitor Output Turbine Weston W Freewater Turbine Weston W Freewater MW MVAR Flow Flow uncomp comp MVAR Voltage Voltage Voltage MW MVAR MVAR Voltage change Voltage change Voltage change MW MVAR 5 MVAR capacitor switch % % % % % % % % % % % % % % % % % % MVAR capacitor switch % % % % % % MVAR capacitor switch % % % % % % MVAR capacitor switch % % % % % % Note: Hi-lighted numbers indicate PacifiCorp bus voltage changes exceeding PacifiCorp's 3.0% standard V. TRANSIENT STABILITY STUDIES Transient stability studies were investigated to determine the effects for each of five three-phase fault scenarios: Three-phase fault at Walla Walla 230 and a loss of the Walla Walla - Wallula 230 kv line Three-phase fault at Walla Walla 230 and a loss of the Walla Walla - Vantage 230 kv line Three-phase fault at Wallula 230 and a loss of the Wallula - McNary 230 kv line Three-phase fault at Joso 115 and a loss of the Joso - Burbank 115 kv line Three-phase fault at Central 69 and a loss of the Walla Walla - Mill Creek and Central 69 kv line For the existing system, instability and low voltages in the Wallula area ( pu) occur following the three-phase fault at Wallula 230 and a loss of the Wallula - McNary 230 kv line if other wind farms in the area do not trip. An assumption was made that wind farms would trip due to voltage relays following one second of voltage less than 0.90 pu. Based on this assumption, the wind farms were tripped one second after the fault. When wind farms in the area trip, voltages return to acceptable levels and there are no system problems. Revised: ALW 5

13 System Impact Study Combine Hills Wind Project The addition of the Combine Hills generation causes the instability and low voltages to worsen if other wind farms in the area fail to trip. If wind farms in the area trip after one second of voltage less than 0.90 pu, voltages return to acceptable levels. Therefore, the system is not adversely effected by the addition of the Combine Hills generation. Another fault on the existing system causes instability and low voltage (0.58 pu at Burbank 115 kv) if wind farms in the area do not trip following the three-phase fault at the Joso 115 kv bus and a loss of the Joso - Burbank 115 kv line. Based on the assumption that wind farms will trip off line following one second of voltage less than 0.90 pu, the wind farms were tripped one second after the fault. When the wind farms trip, voltages return to acceptable levels and there are no system problems. The system response to this fault and outage is virtually unchanged following the addition of the Combine Hills generation. Therefore, the Combine Hills generation addition does not adversely effect the transmission system. None of the other fault and subsequent line outage scenarios studied resulted in any other system problems. The transient effects of switching a 5 MVAR capacitor at Combine Hills were also investigated. Capacitor switching does not cause system instability. The earlier section, Voltage Fluctuations for Capacitor Switching, summarizes the overall effects on bus voltages found in the transient study. VI. RECOMMENDATIONS Based on the results of this study, the following recommendations are noted: 1) The Weston - Athena 69 kv and Hermiston - Pendleton 69 kv transmission lines should continue to be operated open, as is the current practice. 2) Switching the 5 MVAR capacitors at Combine Hills does not generally result in excessive voltage change for PacifiCorp's load. When the generation output is 35 MW or greater, however, the voltage change at Weston does exceed PacifiCorp's allowable voltage fluctuation maximum of 3.0%. The voltage change seen at the wind turbines is greater and may be excessive for the generators. Investigation with the turbine manufacturer by the wind farm developer should be conducted to determine if the wind turbines can withstand voltage changes greater than 3.0%. To meet PacifiCorp s 3% voltage change requirements due to capacitor switching, a smaller capacitor size (3.0 MVAR or less), or a dynamic VAR device must be added. 3) High speed under voltage tripping is necessary to prevent system instability for close in faults. It is recommended that an under voltage relay on the 69 kv system connection be installed to trip the Combine Hills wind farm following one second of voltage at 0.90 pu or less. Revised: ALW 6

14 To Schultz To Columbia To Pomona 1008 To Hanford 1008 Vantage WALLA WALLA AREA TRANSMISSION SYSTEM DETAIL N. Lewiston To Hatwai To Shawnee 287 To Mattawa To Midway McNary Hatrock Cold Springs To Ross To Coyote 600 Wanapum To Horse Heaven Wallula Cascade Kraft Attalia Nine Mile F2 250 Franklin To Sacajawea Stateline Wind Farm (210 MW) (90 MW) Badger H2F2 Berrian Paterson 250 Burbank 9C Wind Dodd Rd 100 US Gen Joso Umatilla Touchet NO Stateline Nine Mile F1 (25 MW) (25 MW) 83.3 Walla Walla (PAC) Lagoon Hermiston Hinkle Pendleton (PAC) Buckaroo Roundup (25 MW) Vansycle NO 150 Walla Walla (BPA) Bowman Weston (BPA) NO 33.3 Prospect Central Umapine Freewater (PAC) Weston (PAC) Athena Pendleton (BPA) 33.3 Whitman Pilot Rk Mill Crk Waitsburg Freewater (BPA) Mission Dayton Combine Hills W. Freewater Ukiah Milton Dry Gulch Pomeroy (PAC) 20 Clarkston LEGEND 500 kv Lines 345 kv Lines 230 kv Lines 115 kv Lines 69 kv & Below Pomeroy (BPA) Dotted Lines Indicate Others' Ownership WALAWALA.VSD DAJ To LaGrande

15 Case: Existing System Normally Open System Configuration Transmission Overloads Minimum Voltage Volt. Change > 5% Outage RAS Used Line/Xfmr % Rating Location (pu) Location % Chg. Comments Walla Walla - Vantage 230 None Dayton PPL None Waitsburg Walla Walla - N. Lewiston 230 None Dayton PPL None Waitsburg Walla Walla - Enterprise 230 None Dayton PPL None Waitsburg Walla Walla - Wallula 230 None Dayton PPL None Waitsburg Walla Walla - Mill Creek and Central 69 Prospect - Walla Walla Dayton PPL Dayton PPL Waitsburg Waitsburg Mill Creek Mill Creek Pomeroy Pomeroy Prospect Walla Walla (PAC) - Walla Walla (BPA) 69 None None None Bowman - Central 69 Walla Walla - WW Cen T Dayton PPL None Weston P Central - Umapine 69 Athena - Pendleton Umapine Umapine Umapine Tap Umapine Tap Weston P Weston P Athena Athena Ukiah Ukiah Pilot Rock Pilot Rock Pendleton Pendleton Mission T Mission T Pendleton BPA Pendleton BPA Buckaroo Buckaroo Walla Walla (BPA) - Pomeroy 115 None Dayton PPL None Weston - Athena closed Joso - Burbank 115 Walla Walla - Nine Mi T Stateline W Stateline W Waitsburg Joso Tap Joso Tap Nine Mi T Nine Mi T McNary - Roundup 230 None Ukiah Ukiah Athena Athena Pilot Rock Pilot Rock Pendleton Pendleton Mission T Mission T Buckaroo Buckaroo Pendleton BPA Pendleton BPA Roundup Roundup Wallula - McNary 230 McNary - Umatilla Hermiston Hermiston Cold Springs Cold Springs Umatilla Umatilla McNary McNary Dayton PPL Waitsburg Enterprise Pomeroy Stateline W Stateline W

16 Case: Combine Hills Normally Open System Configuration Transmission Overloads Minimum Voltage Volt. Change > 5% Outage RAS Used Line/Xfmr % Rating Location (pu) Location % Chg. Comments Walla Walla - Vantage 230 None Dayton PPL None Waitsburg Walla Walla - N. Lewiston 230 None Dayton PPL None Waitsburg Walla Walla - Enterprise 230 None Dayton PPL None Waitsburg Walla Walla - Wallula 230 Dayton PPL None Waitsburg Walla Walla - Mill Creek and Central 69 Prospect - Walla Walla Dayton PPL Dayton PPL Waitsburg Waitsburg Mill Creek Mill Creek Pomeroy Pomeroy Prospect Walla Walla (PAC) - Walla Walla (BPA) 69 None None None Bowman - Central 69 Walla Walla - WW Cen T Dayton PPL None Weston P Central - Umapine 69 Athena - Pendleton CH CH Umapine Umapine Umapine Tap Umapine Tap W Freewater W Freewater Weston P Weston P Athena Athena Ukiah Ukiah Pilot Rock Pilot Rock Pendleton Pendleton Mission T Mission T Pendleton BPA Pendleton BPA Buckaroo Buckaroo Walla Walla (BPA) - Pomeroy 115 None Dayton PPL None Weston - Athena closed, no true solution Joso - Burbank 115 Walla Walla - Nine Mi T Stateline W Stateline W Waitsburg Joso Tap Joso Tap Nine Mi T Nine Mi T Nine Mi F Nine Mi F McNary - Roundup 230 None Ukiah Ukiah Athena Athena Pilot Rock Pilot Rock Pendleton Pendleton Mission T Mission T Buckaroo Buckaroo Pendleton BPA Pendleton BPA Roundup Roundup Wallula - McNary 230 McNary - Umatilla Hermiston Hermiston Cold Springs Cold Springs Umatilla Umatilla McNary McNary Dayton PPL Waitsburg Enterprise Pomeroy CH CH Stateline W Stateline W

17

18

19

20

21 Existing System Fault Location Trip Line Gen Trip Voltages < 0.9 Comments 3 phase Wallula 230 Wallula - McNary 230 none at 8.0 seconds, Stateline 2 units unstable Wallula 0.7 pu, Weston 0.8 pu 3 phase Wallula 230 Wallula - McNary 230 Stateline at 2.0 seconds, acceptable voltages after tripping 2.0 seconds Stateline pu 3 phase Joso 115 Joso - Burbank 115 at 6.0 seconds, Stateline 1 units unstable Joso 0.58 pu Weston 0.86 pu Load at Joso seconds due to undervoltage 3 phase Joso 115 Joso - Burbank 115 Stateline at 2.0 seconds, acceptable voltages after tripping 2.0 seconds Joso 0.70 pu Combine Hills Gen Added Fault Location Trip Line Gen Trip Voltages < 0.9 Comments 3 phase Wallula 230 Wallula - McNary 230 none at 8.0 seconds, Stateline 2 units unstable Combine Hills 0.38 pu Weston 0.61 pu Wallula 0.68 pu 3 phase Walla Walla 2Walla Walla - Wallula 230 none none none 3 phase Joso 115 Joso - Burbank 115 at 6.0 seconds, Stateline 1 units unstable Joso 0.58 pu Combine Hills 0.87 pu Weston 089 pu 3 phase Walla Walla 2Walla Walla - Vantage 230 none none 3 phase Wallula 230 Wallula - McNary 230 Stateline 2.0 seconds at 2.0 seconds, Joso 0.70 pu 3 phase Joso 115 Joso - Burbank 115 Stateline 2.0 seconds at 2.0 seconds, Wallula 0.80 pu 3 phase Central 69 Walla Walla - Mill Creek - Central 69 none none no fault 5 MVAR Capacitor Switching at none none Combine Hills 34.5

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

38

39

40

41

42

43

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

North Oregon Coast Area Study. Adam Lint

North Oregon Coast Area Study. Adam Lint North Oregon Coast Area Study Adam Lint PAGE 2 North Oregon Coast System Overview - Clatsop Study Covers: Transmission Switching Stations (Clatsop District): Astoria Lewis and Clark 115 kv Distribution

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

Q0044 interconnection at

Q0044 interconnection at Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

West Station-West Cañon 115 kv Transmission Project

West Station-West Cañon 115 kv Transmission Project West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon

More information

Project #94. Generation Interconnection System Impact Study Report Revision

Project #94. Generation Interconnection System Impact Study Report Revision Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT

More information

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design Presented at the 2018 Transmission and Substation Design and Operation Symposium Revision presented at the

More information

Interconnection System Impact Study Final Report February 19, 2018

Interconnection System Impact Study Final Report February 19, 2018 Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC

More information

Generation Interconnection Facilities Study For

Generation Interconnection Facilities Study For Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...

More information

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION El Paso Electric Company System Operations Department System Planning Section August 2006 I. INTRODUCTION The

More information

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 1 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1 Page 2 of 76 NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC

More information

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems Ben Huckaba, P.E. President & Principal Engineer 317-273-9841 benh@alphaeng.us Indiana University Bloomington,

More information

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives Addendum San Juan Major Project Tri-State Generation and Transmission Association Power System Planning December, 2008

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic July 26, 2016 Reliability Analysis Update MetEd Transmission Zone N-1 First Energy Planning Criteria (FERC Form 715): The North Boyertown West Boyertown 69 kv is

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic November 04, 2013 2013 RTEP Baseline Analysis Update 11/04/2013 AE Transmission Zone Cost Change for B2354 Install second 230/69kV transformer and 230kV circuit

More information

Cost Benefit Analysis of Faster Transmission System Protection Systems

Cost Benefit Analysis of Faster Transmission System Protection Systems Cost Benefit Analysis of Faster Transmission System Protection Systems Presented at the 71st Annual Conference for Protective Engineers Brian Ehsani, Black & Veatch Jason Hulme, Black & Veatch Abstract

More information

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study XXXX Knob Hill Wind Farm Project Report No. August 2010 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All rights reserved.. DISCLAIMER OF WARRANTY, LIMITATION

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC OCTOBER 17, 2018 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia

More information

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No. 17-035-40 Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation 1. Description In the 2013-2014 Transmission Planning Cycle, the ISO approved the construction

More information

APPENDIX E: Project Need and Description

APPENDIX E: Project Need and Description APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Tyler 60 kv Shunt Capacitor Installation of a 2x10 MVAR capacitor bank at Tyler 60 kv bus Objectives

More information

APPENDIX F: Project Need and Description

APPENDIX F: Project Need and Description APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and

More information

Targeted Application of STATCOM Technology in the Distribution Zone

Targeted Application of STATCOM Technology in the Distribution Zone Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric

More information

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power

More information

XXXX. Kokish River Hydroelectric Project. Interconnection System Impact Study

XXXX. Kokish River Hydroelectric Project. Interconnection System Impact Study XXXX Kokish River Hydroelectric Project Report No. August 2010 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All rights reserved.. DISCLAIMER OF WARRANTY,

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30)

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30) TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30) Submitted to TOT1A Stakeholders and TOT1A Interconnected Utilities And Western Electricity Coordinating Council June 6, 2013

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

Facilities Study for Alberta to US Available Transfer Capability

Facilities Study for Alberta to US Available Transfer Capability Facilities Study for Alberta to US Available Transfer Capability Report No: NPP2002-05 June 3, 2002 System Planning & Grid Operations, Transmission Line of Business Engineering Services Executive Summary

More information

South Dakota 890 Study

South Dakota 890 Study South Dakota 890 Study September 16, 2011 South Dakota 890 Study Presentation of 890 Study results from 2011 Includes WAPA suggested system improvements and timelines Stakeholder Feedback Questions? 2

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Direct Testimony of Richard A. Vail

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Direct Testimony of Richard A. Vail Application No. -0- Exhibit PAC/00 Witness: Richard A. Vail BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP Investment in Distribution and Transmission Systems April 0 PAC/00

More information

PES Cook Islands KEMA Grid Study Final Report

PES Cook Islands KEMA Grid Study Final Report Integrating PV Solar and Wind generation with the TAU electric system Te Aponga Uira O Tumu-Te_Varovaro Contents 1. Executive summary... 2 2. Introduction... 5 2.1 Proposed wind turbine sites... 6 2.2

More information

Transmission Planning Report

Transmission Planning Report Transmission Planning Report Board of Directors Meeting December 15, 2010 1 Overview Study Team Reports Puget Sound Area Study Team Northern Mid-Columbia Study Team Cross Cascades Study Team Centralia

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

Transmission Planning. WECC 2014 Progress Report. March 14, 2014

Transmission Planning. WECC 2014 Progress Report. March 14, 2014 Transmission Planning WECC 2014 Progress Report March 14, 2014 Report Prepared By: Dennis Stevens -TPP (360) 619-6821 BPA TS TPP 2014-022 Page 1 Table of Contents 1 Introduction... 1 2 Planned Transmission

More information

New 115 kv Disconnect Switches at Bloomsburg MTS

New 115 kv Disconnect Switches at Bloomsburg MTS 115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Interconnection System Impact Study

Interconnection System Impact Study Interconnection System Impact Study Pennask and Shinnish Creek Wind Project Report No: T&S Planning 2014 072 December 2014 DRAFT British Columbia Hydro and Power Authority British Columbia Hydro and Power

More information

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection

More information

MTEP13 SPM #2- Central Region. March 25, 2013

MTEP13 SPM #2- Central Region. March 25, 2013 MTEP13 SPM #2- Central Region Ameren Missouri March 25, 2013 Ameren Missouri Project Review Central Region: Ameren Missouri Ameren Missouri has a total of 10 project proposals that are recommended for

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent

More information

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions. March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating

More information

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028. Merchant Transmission Interconnection PJM Impact Study Report For PJM Merchant Transmission Request Queue Position X3-028 Breed 345 kv October/2014 System Impact Study Breed 345 kv Merchant Transmission

More information

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection

More information

Ten-year Plan. Figure 1 and Table 1. Each of the facilities shown in the plan is described in greater depth in the last appendix of this report.

Ten-year Plan. Figure 1 and Table 1. Each of the facilities shown in the plan is described in greater depth in the last appendix of this report. Ten-year Plan As a result of the analysis completed for the 2009 System Assessment, the follow-up sensitivity studies, analysis completed by the study teams, and individual planning participant studies,

More information

EE 456 Design Project

EE 456 Design Project F-2014 EE 456 Design Project PROJECT REPORT MALUWELMENG, CONNIE SHARP, MEGAN Table of Contents Introduction... 2 Assignment I... 2 Setup... 2 Simulation... 2 Assignment II... 3 Problems... 3 Solution...

More information

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation Intentionally left blank F1 Description and Functional Specifications of Proposed

More information

Pacific Gas and Electric Company s Revised 2015 Annual Progress

Pacific Gas and Electric Company s Revised 2015 Annual Progress March 02, 2015 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Avista PO Box 3727 MSC-16 1411 East Mission Ave Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff 155 North 400 West

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2014 Annual Ten-Year Transmission Plan Assessment Report November 20, 2014 For information or questions regarding this Transmission Assessment Report,

More information

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN Twin Cities Minnesota Zone Meeting Xcel Energy May 11, 2005 Bloomington, MN Overview of Presentation Xcel Energy Projects: Aldrich to St Louis Park 115 kv line Eden Prairie to Edina 115 kv line Eden Prairie

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

Midway/Monument Area TTC Study

Midway/Monument Area TTC Study Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny

More information

DYNAMIC LOAD FLOW STUDIES OF DISTRIBUTION FEEDS IN THE SAN JOAQUIN VALLEY REGION

DYNAMIC LOAD FLOW STUDIES OF DISTRIBUTION FEEDS IN THE SAN JOAQUIN VALLEY REGION DYNAMIC LOAD FLOW STUDIES OF DISTRIBUTION FEEDS IN THE SAN JOAQUIN VALLEY REGION INTERIM REPORT AS OF JULY 21, 2016 PRESENTED JULY 21, 2016 1 TABLE OF CONTENTS Section Introduction Advanced Inverter Approach

More information

DISTRIBUTED GENERATION FROM SMALL HYDRO PLANTS. A CASE STUDY OF THE IMPACTS ON THE POWER DISTRIBUTION NETWORK.

DISTRIBUTED GENERATION FROM SMALL HYDRO PLANTS. A CASE STUDY OF THE IMPACTS ON THE POWER DISTRIBUTION NETWORK. DISTRIBUTED GENERATION FROM SMALL HYDRO PLANTS. A CASE STUDY OF THE IMPACTS ON THE POWER DISTRIBUTION NETWORK. N. Lettas*, A. Dagoumas*, G. Papagiannis*, P. Dokopoulos*, A. Zafirakis**, S. Fachouridis**,

More information