EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION

Size: px
Start display at page:

Download "EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION"

Transcription

1 EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION El Paso Electric Company System Operations Department System Planning Section August 2006

2 I. INTRODUCTION The interconnection of new generating units into a transmission system will increase the fault current contribution into the system. Therefore, as part of this Study, a short circuit analysis was performed to determine if the additional fault current contribution from the XXX wind generators into the EPE transmission system will cause any of EPE s existing substation circuit breakers to exceed their interruption ratings. II. SHORT CIRCUIT STUDY MODELING The wind generation proposed by XXX is sited approximately 53 miles east of EPE s Amrad 345 kv substation. Data provided by XXX indicates that the wind turbines will be interconnected on the Amrad-Artesia 345 kv transmission line through two 150/200/250 MVA, 34.5/345 kv step-up transformers. Each step-up transformer has a positive sequence impedance of 8.5% and a zero sequence impedance of 9% on a 150 MVA base. The step-up transformer impedances modeled in the short circuit analysis for both step-up transformers were: Z 1 (step-up) = J per unit (150 MVA base) Z 0 (step-up) = J per unit (150 MVA base) Equivalent reactance data for the modeling of the wind machines in EPE s short-circuit data base was difficult to obtain from XXX and their consultants. However, Public Service company of New Mexico (PNM) has experience in modeling wind machines for a short-circuit analysis and they provided assistance in obtaining a short-circuit model for these machines. PNM contacted its GE representative, who in turn provided the shortcircuit modeling for the wind generator. GE stated that an official model for the 1.5 MW turbine has not been developed as of yet. Therefore, they recommended the use of their 1.67 MVA model at a 0.90 power factor to achieve the 1.5 MVA output of each machine. The following equivalent reactance values for the wind machines were supplied by GE and modeled in the EPE short circuit data base: X d = Direct Axis Synchronous Reactance = 0.28 per unit X d = Direct Axis Transient Reactance = 0.28 per unit X d = Direct Axis Subtransient Reactance = 0.28 per unit R = Direct Axis Resistance = 0.01 per unit These reactance values were also based on a 150 MVA base and used to model the wind generator in the short circuit study. The location of the XXX wind machines on the Amrad-Artesia 345 kv line also required the line impedances to be recalculated. Therefore, the Amrad-Artesia line was divided Short Circuit Analysis for XXX s 1 El Paso Electric Company

3 into two sections, the Amrad-XXX 345 kv line and the XXX-Artesia 345 kv line. The line impedance of the Amrad-Artesia line (125.4 miles in length) was proportioned according to the location of the XXX generators (53 miles east of Amrad Substation). Therefore, the Amrad-XXX 345 kv line impedance was modeled as 42.3% (53/125.4) of the total Amrad-Artesia 345 kv line impedance and the XXX-Artesia 345 kv line impedance was modeled as 57.7% (72.4/125.4) of the total Amrad-Artesia 345 kv line impedance. The impedances modeled for each of the XXX 345 kv line segments are shown below: AMRAD-XXX LINE IMPEDANCE XXX-ARTESIA LINE IMPEDANCE Z 1 = j Z 1 = j Z 0 = j Z 0 = j In addition to the new XXX generation, all existing and proposed third party generation ahead of the XXX project in the study queue were modeled in the data base. These generation projects included the following: 570 MW of existing generation (Luna Energy Facility) interconnected at Luna 345 kv Substation and scheduled to WECC. 141 MW of existing generation (Afton) interconnected at Afton 345 kv Substation and scheduled through EPE s Arroyo PST. 60 MW of existing generation interconnected at Tri-State Generation and Transmission Association, Inc. s (Tri-State) Hidalgo 115 kv Substation and scheduled to WECC. 80 MW of existing generation interconnected at Texas-New Mexico Power Company s (TNP) Lordsburg 115 kv Substation and scheduled to WECC. 94 MW of generation (presently being constructed) interconnected at Afton 345 kv Substation and scheduled to WECC. Two cases were developed to perform this analysis, one with and one without the XXX generation. Three phase and single-line-to-ground faults were then simulated at the Amrad and Artesia 345 kv buses in each of the two cases. The difference between the fault current values in the two cases is the additional fault current contribution from the XXX wind generation. Fault currents were monitored at the buses closest to where the XXX generation will be interconnected, since this is where the greatest fault current contribution can be attributed to the XXX project. The buses monitored included the following: Short Circuit Analysis for XXX s 2 El Paso Electric Company

4 Amrad 345 kv Amrad 115 kv Artesia 345 kv Caliente 345 kv Caliente 115 kv The resulting fault currents were then compared to the circuit breaker interruption ratings of the breakers at each of the above mentioned substations. III. RESULTS OF THE SHORT CIRCUIT ANALYSIS The following is a list of existing circuit breakers and their interruption ratings at each of the substations monitored in this study: Breaker Breaker Interruption Substation Voltage Number Rating (Amps) Amrad B 40, B 40, B 40, B 40,000 Amrad B 40, B 40, B 40, B 40,000 Caliente B 40, B 40, B 40, B 40, B 40,000 Caliente B 40, B 40, B 40, B 40, B 40, B 40, B 40, B 40, B 40,000 Artesia 345 4R10 40, R05 40,000 Short Circuit Analysis for XXX s 3 El Paso Electric Company

5 The short circuit analysis was first performed without the XXX generation interconnected into the EPE system, but with all other third party generation projects in. This analysis produced the base case short-circuit values of the existing system. The proposed XXX generation was then modeled into the system and a short-circuit analysis was again performed with the XXX generation installed. The incremental difference between the two cases determined the increase in short-circuit contribution to the existing EPE transmission system due to the proposed XXX generators. If this incremental difference causes any of the existing substation circuit breakers to exceed their maximum interruption ratings, they will have to be replaced. In addition to the buses shown above, faults were simulated at the XXX 345 kv and XXX 34.5 kv buses. This was done to provide XXX with an estimate of the fault current contribution from the wind machines during a contingency of the XXX wind generation. This will give XXX an indication of the size of circuit breakers it will need to protect its 34.5 kv and 345 kv buses. The short circuit (fault) currents with and without the XXX generation at the buses listed above are shown below: Three Phase Line to Ground: Without XXX Gen With XXX Gen Fault Current Fault Current Faulted Bus (Amps) (Amps) Amrad 345 kv Bus 3,507 4,683 Amrad 115 kv Bus 7,000 8,004 Caliente 345 kv Bus 6,599 7,481 Caliente 115 kv Bus 14,760 15,632 Artesia 345 kv Bus 1,507 2,035 XXX 34.5 kv Bus - 42,176 XXX 345 kv Bus - 3,628 Single Phase Line to Ground: Without XXX Gen With XXX Gen Fault Current Fault Current Faulted Bus (Amps) (Amps) Amrad 345 kv Bus 3,082 4,239 Amrad 115 kv Bus 5,976 7,062 Caliente 345 kv Bus 6,328 6,965 Caliente 115 kv Bus 15,842 16,593 Artesia 345 kv Bus 965 1,475 XXX 34.5 kv Bus - 36,988 XXX 345 kv Bus - 3,672 Short Circuit Analysis for XXX s 4 El Paso Electric Company

6 IV. Results and Conclusions This short circuit analysis was performed on the EPE system comparing the maximum fault current on the system at various substations both with and without the proposed XXX generation. The table below shows the results of the short circuit analysis with the proposed XXX generation interconnected into the EPE transmission system. Short Circuit Results With Proposed XXX Generation Maximum Maximum Circuit Breaker Fault Current With Interruption Rating XXX Generation Bus (AMPS) (AMPS) Amrad 345 kv Bus 40,000 4,683 Amrad 115 kv Bus 40,000 8,004 Caliente 345 kv Bus 40,000 7,481 Caliente 115 kv Bus 40, Artesia 345 kv Bus 40,000 2,035 XXX 345 kv Bus - 3,672 XXX 34.5 kv Bus - 42,176 Results of the analysis indicate that the maximum fault currents are well within the maximum circuit breaker ratings at each of the buses analyzed. Therefore, the interconnection of the XXX wind machines into the EPE transmission system as modeled in this analysis will not cause any existing EPE circuit breaker to operate outside its interruption rating limit. The results also indicate that XXX will need to install 50,000 Amp circuit breakers at its 34.5 kv bus to protect its system in the event of a loss of all its wind generation. Short Circuit Analysis for XXX s 5 El Paso Electric Company

7 V. Certification This Short Circuit Analysis was performed as part of the Generation Interconnection Feasibility Study requested by XXXXXXXXXXXXXXXXXXX (XXX). The step-up transformer data was supplied by XXX. The model for the wind machine was provided by Public Service Company of New Mexico s (PNM) representative from General Electric (GE). GE stated that it presently does not have an official short-circuit model for XXX s proposed 1.5 MVA wind machines. The model they provided was for a 1.67 MVA wind machine at a 0.90 power factor to achieve the 1.5 MVA rating of each of the XXX wind machines. This was the best data available to model the XXX wind turbines into the sort-circuit data base at the time the study was performed. If XXX decides to continue with its proposed interconnection, it will need to provide a more accurate representation of the wind machines in order for EPE to perform a more accurate short-circuit analysis of its transmission system with the XXX generation installed. This Short Circuit Analysis was performed by El Paso Electric Company (EPE). Name: Title: Dennis H. Malone Manager, System Planning Signature: Company: El Paso Electric Company Date: Short Circuit Analysis for XXX s 6 El Paso Electric Company

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS El Paso Electric Company System Operations Department System Planning

More information

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS El Paso Electric Company System Operations Department System Planning Section September 2001 Short Circuit

More information

Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study

Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study Study Performed by El Paso Electric Company System Planning Section - 1 I.

More information

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY Short Circuit Analysis System Operations Department System Planning Section March 2001 I. Introduction XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

More information

El Paso Electric Company

El Paso Electric Company Feasibility Study XXXXXX Solar Generation Prepared for El Paso Electric Company Prepared by TRC Engineers, LLC 249 Eastern Avenues Augusta, ME 04330 (207) 621-7000 Project Number: 202327 May 2013 FOREWORD

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department

More information

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ART320W 320 MW Wind Powered Project Prepared for: El Paso Electric Company Prepared by: TRC Engineers, LLC 249 Western Avenue Augusta, ME 04330

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS System Operations Department System Planning Section June 2001 TABLE OF CONTENTS 1.0 Executive Summary...Page

More information

XXXXXXXXXXXXXX 99 MW WIND PARK GENERATOR INTERCONNECTION FEASIBILITY STUDY. September 2008 Prepared by: EL PASO ELECTRIC COMPANY

XXXXXXXXXXXXXX 99 MW WIND PARK GENERATOR INTERCONNECTION FEASIBILITY STUDY. September 2008 Prepared by: EL PASO ELECTRIC COMPANY XXXXXXXXXXXXXX 99 MW WIND PARK GENERATOR INTERCONNECTION FEASIBILITY STUDY September 2008 Prepared by: EL PASO ELECTRIC COMPANY Foreword This report was prepared for XXXXXXXXXXXXX (XXX) of XXXXXXXX by

More information

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study System Operations Department System Planning Section March 2002 Table of Contents: 1.0 EXECUTIVE SUMMARY 4 2.0 COST ESTIMATES 8 2.1 Cost

More information

120 MW SOLAR-THERMAL PLANT GENERATOR INTERCONNECTION FEASIBILITY STUDY. May 2008 Prepared by: EL PASO ELECTRIC COMPANY

120 MW SOLAR-THERMAL PLANT GENERATOR INTERCONNECTION FEASIBILITY STUDY. May 2008 Prepared by: EL PASO ELECTRIC COMPANY . 120 MW SOLAR-THERMAL PLANT GENERATOR INTERCONNECTION May 2008 Prepared by: EL PASO ELECTRIC COMPANY Foreword This report was prepared for XXXXXXXXXXXXXXXXXXX by System Planning at El Paso Electric Company.

More information

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

300 MW SOLAR PHOTOVOLTAIC PLANT, GENERATOR INTERCONNECTION FEASIBILITY STUDY

300 MW SOLAR PHOTOVOLTAIC PLANT, GENERATOR INTERCONNECTION FEASIBILITY STUDY 300 MW SOLAR PHOTOVOLTAIC PLANT, GENERATOR INTERCONNECTION FEASIBILITY STUDY El Paso Electric Company System Planning August 2006 TABLE OF CONTENTS 1.0 EXECUTIVE SUMMARY...Page 1 2.0 PURPOSE...Page 7 3.0

More information

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the

More information

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report

More information

XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS El Paso Electric Company System Operations Department System Planning Section September 2001 TABLE

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code: Generating Facility Level 2 or 3 Interconnection Review (For Generating Facilities with Electric Nameplate Capacities no Larger than 20 MW) Instructions An Interconnection Customer who requests a Utah

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

Verde Transmission, LLC. Verde Project. System Impact Study Report

Verde Transmission, LLC. Verde Project. System Impact Study Report Verde Transmission, LLC Verde Project System Impact Study Report March 2017 Prepared by: Public Service Company of New Mexico Foreword This report was prepared for Verde Transmission, LLC by the PNM Transmission/

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018 March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM-2017-11 May 2018 Prepared by: Public Service Company of New Mexico Foreword This report is prepared

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP

Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP Grid Interconnection & Contract Development Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP Submittal Instructions Prior to submitting your application and

More information

New Mexico Transmission Expansion Concepts For Wind Resources

New Mexico Transmission Expansion Concepts For Wind Resources New Mexico Transmission Expansion Concepts For Wind Resources May 2008 Update Electric Services Transmission Operations FOREWORD This document contains PNM s latest concepts for expanding the transmission

More information

ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study

ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study Final Report ABB Power Systems Consulting June 27, 2016 LEGAL NOTICE This document, prepared by ABB Inc, is an

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Electrical Handbook Fault Calculations Using The Mva Method

Electrical Handbook Fault Calculations Using The Mva Method Electrical Handbook Fault Calculations Using The Mva Method In the power systems analysis field of electrical engineering, a per-unit system is the Calculations are simplified because quantities expressed

More information

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation 1. Description In the 2013-2014 Transmission Planning Cycle, the ISO approved the construction

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Observations from Avista Short Circuit Analysis WECC Short Circuit Workgroup January 2018 Tracy Rolstad

Observations from Avista Short Circuit Analysis WECC Short Circuit Workgroup January 2018 Tracy Rolstad Observations from Avista Short Circuit Analysis WECC Short Circuit Workgroup January 2018 Tracy Rolstad The Driver (TPL-001, R2.3) With apologies to Protection folks this is all about a Planner s perspective.

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Four Corners Queue Transmission Interconnection Study

Four Corners Queue Transmission Interconnection Study Four Corners Queue Transmission Interconnection Study Facility Study Results By Arizona Public Service Company Transmission Planning & Interconnection Development March 22, 2016 Version 1 FACILITIES STUDY

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection

More information

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Status of PNM s Completed Transmission Construction Projects 11/30/2017 Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information

More information

Clean Line Energy Partners, LLC. Western Spirit Clean Line 345 kv. System Impact Study

Clean Line Energy Partners, LLC. Western Spirit Clean Line 345 kv. System Impact Study Clean Line Energy Partners, LLC Western Spirit Clean Line 345 kv System Impact Study February, 2017 Prepared by: Public Service Company of New Mexico Foreword This report was prepared for the Clean Line

More information

SIEMENS POWER SYSTEM SIMULATION FOR ENGINEERS (PSS/E) LAB1 INTRODUCTION TO SAVE CASE (*.sav) FILES

SIEMENS POWER SYSTEM SIMULATION FOR ENGINEERS (PSS/E) LAB1 INTRODUCTION TO SAVE CASE (*.sav) FILES SIEMENS POWER SYSTEM SIMULATION FOR ENGINEERS (PSS/E) LAB1 INTRODUCTION TO SAVE CASE (*.sav) FILES Power Systems Simulations Colorado State University The purpose of ECE Power labs is to introduce students

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress

NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM ATTACHMENT 2 Utility: Duke Energy Progress Designated Utility Contact: Attention: Customer Owned Generation Mail Code ST13A E-Mail Address: Customerownedgeneration@duke-energy.com

More information

PSNH INTERCONNECTION REQUEST

PSNH INTERCONNECTION REQUEST PSNH INTERCONNECTION REQUEST Send the completed Interconnection Request and required attachments to: Public Service of New Hampshire Attn: Michael Motta, Senior Engineer Supplemental Energy Sources P.

More information

EL PASO ELECTRIC COMPANY SYSTEM EXPANSION PLAN

EL PASO ELECTRIC COMPANY SYSTEM EXPANSION PLAN EL PASO ELECTRIC COMPANY SYSTEM EXPANSION PLAN 2019-2028 Produced by System Planning 2018 GENERAL EL PASO ELECTRIC COMPANY 2019-2028 SYSTEM EXPANSION PLAN Executive Summary El Paso Electric Company s

More information

FEASIBILITY STUDY REPORT

FEASIBILITY STUDY REPORT FEASIBILITY STUDY REPORT HL20S PV Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 249 Eastern Avenue Augusta, ME 04330 (207) 621-7000 July 2012 FOREWORD This report was prepared for

More information

Project #94. Generation Interconnection System Impact Study Report Revision

Project #94. Generation Interconnection System Impact Study Report Revision Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection

More information

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less)

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less) Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less) Interconnection Customer Contact Information Name Alternative Contact Information (if different

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

Interconnection System Impact Study Final Report February 19, 2018

Interconnection System Impact Study Final Report February 19, 2018 Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen

More information

Simulation and Visualization of Power Grid Operations with High Renewable Penetration

Simulation and Visualization of Power Grid Operations with High Renewable Penetration Simulation and Visualization of Power Grid Operations with High Renewable Penetration Thomas J Overbye Fox Family Professor of Elect. & Comp. Eng. University of Illinois at Urbana-Champaign overbye@illinois.edu

More information

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655) - (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility

More information

CUSTOMER / ACCOUNT INFORMATION Electric Utility Customer Information (As shown on utility bill)

CUSTOMER / ACCOUNT INFORMATION Electric Utility Customer Information (As shown on utility bill) GENERATOR INTERCONNECTION APPLICATION Category 2 (Combined) For All Projects with Aggregate Generator Output of More Than 20 kw but Less Than or Equal to 150 kw Also Serves as Application for Category

More information

COMPARISON OF DIFFERENT SOFTWARE PACKAGES IN POWER FLOW AND SHORT-CIRCUIT SIMULATION STUDIES. A Project

COMPARISON OF DIFFERENT SOFTWARE PACKAGES IN POWER FLOW AND SHORT-CIRCUIT SIMULATION STUDIES. A Project COMPARISON OF DIFFERENT SOFTWARE PACKAGES IN POWER FLOW AND SHORT-CIRCUIT SIMULATION STUDIES A Project Presented to the faculty of the Department of Electrical and Electronic Engineering California State

More information

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems Ben Huckaba, P.E. President & Principal Engineer 317-273-9841 benh@alphaeng.us Indiana University Bloomington,

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Western Region ATSI Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

GENERATING FACILITY INTERCONNECTION APPLICATION. Part 1 Introduction and Overview

GENERATING FACILITY INTERCONNECTION APPLICATION. Part 1 Introduction and Overview Part 1 Introduction and Overview A. Applicability: This Generating Facility Interconnection Application (Application) is used to request the interconnection of a Generating Facility to Southern California

More information

IEEE T&D FACTS Panel Session Part II (08TD0140) Wednesday, April 23, 2008

IEEE T&D FACTS Panel Session Part II (08TD0140) Wednesday, April 23, 2008 IEEE T&D FACTS Panel Session Part II (08TD0140) Wednesday, April 23, 2008 Improving Power System Dynamic Performance in Laredo, TX Prepared by Paul Hassink (AEP) Paul Marken (GE) Rob O Keefe (AEP) Gerardo

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

Request for Payment Instructions Rule 21 Export Submittal Instructions

Request for Payment Instructions Rule 21 Export Submittal Instructions Grid Interconnection & Contract Development Request for Payment Instructions Rule 21 Export Submittal Instructions Prior to submitting your application and fee or deposit, please complete and submit this

More information

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kva to 10 MVA or less)

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kva to 10 MVA or less) Section 466.APPENIX C Levels 2 to 4 Application Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kva to 10 MVA or less) Interconnection Customer Contact Information

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

An Alternative to Reduce Medium-Voltage Transient Recovery Voltage Peaks

An Alternative to Reduce Medium-Voltage Transient Recovery Voltage Peaks An Alternative to Reduce Medium-Voltage Transient Recovery Voltage Peaks D. M. Nobre W. L. A. Neves B. A. de Souza Departamento de Engenharia Elétrica - UFPB Av. Aprígio Veloso, 882 Bodocongó 58.109-970,

More information

Review paper on Fault analysis and its Limiting Techniques.

Review paper on Fault analysis and its Limiting Techniques. Review paper on Fault analysis and its Limiting Techniques. Milap Akbari 1, Hemal Chavda 2, Jay Chitroda 3, Neha Kothadiya 4 Guided by: - Mr.Gaurang Patel 5 ( 1234 Parul Institute of Engineering &Technology,

More information

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007 High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services

More information

Q0044 interconnection at

Q0044 interconnection at Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

UNIVERSITY OF SWAZILAND MAIN EXAMINATION, DECEMBER 2014

UNIVERSITY OF SWAZILAND MAIN EXAMINATION, DECEMBER 2014 UNIVERSITY OF SWAZILAND MAIN EXAMINATION, DECEMBER 2014 FACULTY OF SCIENCE AND ENGINEERING DEPARTMENT OF ELECTRICAL AND ELECTRONIC ENGINEERING TITLE OF PAPER: POWER SYSTEM ANALYSIS AND OPERATION COURSE

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

Texas A&M Microgrid and Electrical System Study. Cushing Memorial Library & Archives

Texas A&M Microgrid and Electrical System Study. Cushing Memorial Library & Archives Texas A&M Microgrid and Electrical System Study Cushing Memorial Library & Archives Introduction of Texas A&M Microgrid Study Purpose Why are we studying the TAMU electrical system? Process How do we want

More information

New Mexico Transmission System Overview TRANSMISSION SYSTEM OVERVIEW NETWORK OPERATING COMMITTEE

New Mexico Transmission System Overview TRANSMISSION SYSTEM OVERVIEW NETWORK OPERATING COMMITTEE New Mexico Transmission System Overview TRANSMISSION SYSTEM OVERVIEW NETWORK OPERATING COMMITTEE November 8, 2006 1 PNM Transmission System Uses Retail-PNM native load customers represent about 60% to

More information

APPLICATION ELECTRICITY SERVICES. APPLICATION FOR THE CONNECTION OF SMALL SCALE EMBEDDED GENERATION Page 1

APPLICATION ELECTRICITY SERVICES. APPLICATION FOR THE CONNECTION OF SMALL SCALE EMBEDDED GENERATION Page 1 APPENDIX 2B APPLICATION ELECTRICITY SERVICES APPLICATION FOR THE CONNECTION OF SMALL SCALE EMBEDDED GENERATION Page 1 This application form for the connection of small scale embedded generation is for

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

EE 456 Design Project

EE 456 Design Project F-2014 EE 456 Design Project PROJECT REPORT MALUWELMENG, CONNIE SHARP, MEGAN Table of Contents Introduction... 2 Assignment I... 2 Setup... 2 Simulation... 2 Assignment II... 3 Problems... 3 Solution...

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

2015 Grid of the Future Symposium

2015 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,

More information

Cargill Power Markets LLC Transmission Service Study (OASIS # TSR and )

Cargill Power Markets LLC Transmission Service Study (OASIS # TSR and ) Cargill Power Markets LLC Transmission Service Study (OASIS # TSR 72608299 and 72827161) Prepared by: Electric Power Research Institute (EPRI) Under contract with: Public Service Company of New Mexico

More information

PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)

PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transmission Capability (TTC) & Available Transmission Capability (ATC) On The Open Access Same-Time Information System (OASIS)

More information

Performance Analysis of Transient Stability on a Power System Network

Performance Analysis of Transient Stability on a Power System Network Performance Analysis of Transient Stability on a Power System Network Ramesh B Epili 1, Dr.K.Vadirajacharya 2 Department of Electrical Engineering Dr. Babasaheb Ambedkar Technological University, Lonere

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

Interconnection Feasibility Study

Interconnection Feasibility Study Interconnection Feasibility Study Mount Mabel Wind Energy Project Report No: T&S Planning 2015-054 December 2015 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2015.

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

Designing and Maintaining a Pollution-Resilient Electric Power System. Managing Pollution Issues

Designing and Maintaining a Pollution-Resilient Electric Power System. Managing Pollution Issues Designing and Maintaining a Pollution-Resilient Electric Power System Tom McDermott IEEE/PES T&D Conference April 21-24, 2008 Chicago, IL Managing Pollution Issues Define the metrics, and measure them

More information

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less)

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less) Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less) Interconnection Customer Contact Information Name: Address: Alternative Contact Information

More information

GENERATOR INTERCONNECTION APPLICATION

GENERATOR INTERCONNECTION APPLICATION GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 150 KW BUT LESS THAN OR EQUAL TO 550 KW Also Serves as Application for Category 3 Net Metering (Note:

More information