XXXXXXXXXXXXXX 99 MW WIND PARK GENERATOR INTERCONNECTION FEASIBILITY STUDY. September 2008 Prepared by: EL PASO ELECTRIC COMPANY

Size: px
Start display at page:

Download "XXXXXXXXXXXXXX 99 MW WIND PARK GENERATOR INTERCONNECTION FEASIBILITY STUDY. September 2008 Prepared by: EL PASO ELECTRIC COMPANY"

Transcription

1 XXXXXXXXXXXXXX 99 MW WIND PARK GENERATOR INTERCONNECTION FEASIBILITY STUDY September 2008 Prepared by: EL PASO ELECTRIC COMPANY

2 Foreword This report was prepared for XXXXXXXXXXXXX (XXX) of XXXXXXXX by System Planning at. Any correspondence concerning this document, including technical and commercial questions should be referred to: Dennis Malone Manager System Planning Department P.O. Box 982 El Paso, Texas Phone: (915) Fax: (915) Study Performed by: Joaquin Aguilar Principal Engineer Generator Interconnection i September 2008

3 TABLE OF CONTENTS 1.0 Executive Summary...Page Introduction...Page Performance Criteria...Page Methodology...Page Assumptions...Page Procedure...Page Development and Description of Cases...Page List of Contingencies...Page Q-V Analysis...Page Short-Circuit Analysis...Page Powerflow Analysis Results...Page Sensitivity Studies...Page A PNM to EPE Control Area Firm Schedule at West Mesa of 201 MW...Page B PNM to EPE Control Area Firm Schedule at West Mesa of -50 MW...Page Voltage Analysis Results...Page Q-V Analysis Results...Page Short-Circuit Analysis Results...Page Cost Estimates...Page Energy Resource Interconnection Service...Page Disclaimer...Page Certification...Page 26 Generator Interconnection ii September 2008

4 APPENDICIES Generation Interconnection Scope...Appendix 1 EPE s FERC Form 715 Filing...Appendix 2 List of Contingencies...Appendix 3 Q-V Plots...Appendix 4 XXXXXXXXXXXX Modeling Data...Appendix 5 One-Line Maps...Appendix 6 Discretionary Change to System Scope...Appendix 7 Generator Interconnection iii September 2008

5 1.0 EXECUTIVE SUMMARY XXXXXXXXXXXXXXX (XXX) of XXXXXXXXXXXXXXXsubmitted a request for a generator interconnection to the (EPE) system on January 10, This Generator Interconnection request was for a 99 MW wind generation project located approximately 30 miles northeast from Luna 345 kv Substation and interconnected to El Paso Electric Company s (EPE) Springerville-Luna 345 kv line with an in-service date of March 1, A Scoping Meeting was held on February 12, 2008 with the Interconnection Feasibility Study Agreement being signed on February 12, A Scope (Appendix 1) was developed and signed by the parties on May 1, In September 2008, EPE completed the Generator Interconnection (GIFS) for XXX which determined all impacts to the EPE system and southern New Mexico area and to a lesser degree the Arizona area. A 2011powerflow case was developed for powerflow analysis that included three generation interconnection projects senior to the XXXXXXXXXXXX Project. One of those generation interconnection projects was in the System Impact Study Phase (500 MW) and the others were in the Phase (990 MW and 120 MW). The three generation interconnection projects in the EPE Interconnection queue senior to the XXXXXXXXXXXX Project as well as the XXXXXXXXXXXX Project have been modeled in this study such that the generation from these projects is delivered to all entities (and no specific one) in the Western Electricity Coordinating Council (WECC) system. Consequently, no specific transmission path for energy sales has been defined nor does this study guarantee a transmission path will be available when the generator is constructed. A six mile, 115 kv line is to be built between the generation site (XXXXXXXXXXXX Wind Park) and a new 115/345 kv substation to be located on the Springerville-Luna 345 kv line approximately 30 miles from Luna 345 kv Substation ( the Generator Interconnection ). Generator Interconnection 1 September 2008

6 Powerflow results showed that some overload and voltage criteria violations occur in the southern New Mexico and Arizona systems without the addition of the XXXXXXXXXXXX Project. These overload and voltage criteria violations are expected to be corrected by the appropriate generator interconnector senior in the study queue of the XXXXXXXXXXXX interconnection. The primary powerflow analysis in this study was conducted with 141 MW of Afton generation scheduled at West Mesa and a PNM to EPE control area firm schedule of 60 MW. Under this schedule and with all but three contingency scenarios studied, the addition of the XXXXXXXXXXXX Project aggravates slightly those overload and voltage criteria violations previously attributed to those projects senior to the XXXXXXXXXXXX Project. However, the addition of the XXXXXXXXXXXX Project in the southern New Mexico system is directly responsible for three overload criteria violations. The contingency overload criteria violations occur on two transmission lines belonging to Public Service Company of New Mexico (PNM) and one belonging to Tri-State Generation & Transmission Association, Inc. (Tri-State) and include: Central-Hurley 115 kv Luna-Hurley 115 kv El Butte-SocorroP 115 kv PNM s Central-Hurley 115 kv line and Luna-Hurley 115 kv line both overload under the Luna-Hidalgo 345 kv line contingency and Tri-State s El Butte-SocorroP 115 kv line overloads under the Greenlee-Hidalgo 345 kv line contingency. It is important to note that the overloads noted for the transmission lines in the PNM and Tri-State systems were based on ratings shown for the facilities in the base case. These overloaded lines use the same rating value for emergency as they do for normal. At full XXXXXXXXXXXX generation and under the contingencies described above, the Central-Hurley 115 kv line overloads to 101.6% of its normal/emergency rating (4.7% increase compared against the case with no XXXXXXXXXXXX generation), the Luna-Hurley 115 kv line overloads to 103.5% of its normal/emergency rating (4.8% increase compared against the case with no XXXXXXXXXXXX generation) and the Tri-State s El Butte-SocorroP 115 kv line Generator Interconnection 2 September 2008

7 overloads to 102.2% of its normal/emergency rating (4.1% increase compared against the case with no XXXXXXXXXXXX generation). Since these criteria violations are on transmission lines owned by other utilities, this report only identifies the violations and does not provide an indication of the specific facility overloaded (conductor, substation equipment, etc.) or a recommendation for mitigating them. PNM and Tri-State will be informed of these violations and asked to participate in the System Impact Study phase of this project to determine the appropriate mitigation (if required). Other overloaded elements in the southern New Mexico system have also been identified but are attributed to those interconnection projects senior to the XXXXXXXXXXXX project. If any of these interconnection projects should drop out, a re-study at XXX s expense would be required and more Network Upgrades may potentially be attributable to the XXXXXXXXXXXX Project. Fault study results showed that several substation circuit breakers exceeded their capabilities without the XXXXXXXXXXXX Project in service. The XXXXXXXXXXXX Project adds a minimal contribution to the regional fault currents but is not the cause for exceeding the short circuit capabilities of the breakers. For those circuit breakers that exceeded their capabilities, Network Upgrades are expected to be supplied by one of the generation interconnection projects senior to the XXXXXXXXXXXX Project. The powerflow system improvements used in the study case for the 990 MW generation interconnection project included significant VAR support. As such, the XXXXXXXXXXXX Project may benefit from the additional VAR support. Q-V VAR margin study results showed that even with the XXXXXXXXXXXX Project in service there is more than adequate VAR margin on all buses monitored under all lines in service and contingency conditions. If the 990 MW project should drop out, a re-study will be needed to determine if there are any VAR margin deficiencies caused by the XXXXXXXXXXXX Project. Generator Interconnection 3 September 2008

8 The overall study results for this Phase showed that the only EPE system improvements that the XXXXXXXXXXXX Project will be responsible for (other than their generation site, step-up transformers, and transmission line) is the interconnection switching station on the Springerville-Luna 345 kv line and the relocating of the series compensation and line reactors (with breakers) at Luna Substation to the switching station as shown in Section 8.0. This is based on the assumption that the three generation interconnection projects senior to the XXXXXXXXXXXX Project will be implemented and projected system expansions by all utilities in the 2011 powerflow case are implemented as planned. (The overloads on the two PNM lines and the one Tri- State line will need to be addressed with the individual utilities in the System Impact Study if this XXXXXXXXXXXX Project should progress to the next study stage). This study satisfied the request for the Energy Resource Interconnection Service (ERIS) and the Network Resource Interconnection Service. Results of the ERIS can be found in Section 9.0 of this report. EPE agreed through a Discretionary Change to the System Scope (Appendix 7), dated February 12, 2008, that XXX could have their own engineering consultants prepare a good faith cost estimate and construction schedule for interconnecting into the EPE system and any required Network Upgrades. Consequently neither EPE nor its engineering consultant has provided any of this information to be included in this at this time. However, EPE does not warrant the accuracy of the non-epe supplied information. 2.0 INTRODUCTION XXXXXXXXXXXXXXX (XXX) of XXXXXXXXX is proposing to construct 99 MW of wind generation (66 wind turbines at 1.5 MW each) that will interconnect to the southern New Mexico transmission system on EPE s Springerville-Luna 345 kv line. A six mile, 115 kv line is to be built between the generation site (XXXXXXXXXXXX Wind Park) and a new 115/345 kv substation to be located on the Springerville-Luna 345 Generator Interconnection 4 September 2008

9 kv line approximately 30 miles from Luna 345 kv Substation. Proposed in-service date is March 1, As per the requirements of the Federal Energy Regulatory Commission (FERC) Large Generator Interconnection Procedures (LGIP), EPE initiated a Generator Interconnection (GIFS) to study the impact of the interconnection. EPE conducted powerflow, VAR margin and short-circuit analyses. In September 2008, EPE completed the GIFS for XXX which determined all impacts to the EPE system and southern New Mexico area and to a lesser degree the Arizona area. A 2011 powerflow case was developed for powerflow analysis that included three generation interconnection projects senior to the XXXXXXXXXXXX Project. One of those generation interconnection projects was in the System Impact Study Phase (500 MW) and the other two were in the Phase (990 MW and 120 MW). The proposed 345 kv transmission configuration for the 990 MW generation interconnection project is preliminary and will be re-evaluated in the System Impact Study Phase in consultation with PNM if the project continues to the next phase. Also, as previously noted, a re-study of this XXXXXXXXXXXX would need to be conducted if any of the generation interconnection projects senior to the XXXXXXXXXXXX Project decide not to pursue their projects any further. 2.1 PERFORMANCE CRITERIA The reliability criteria standards used by EPE in performing this Study are readily acceptable standards and are listed in Section 4 of EPE s FERC Form 715 (Appendix 2). The powerflow analysis was performed using the GE PSLF program. For precontingency solutions, transformer tap phase-shifting transformer angle movement and static VAR device switching was allowed. For each contingency studied, all regulating equipment (transformer controls and switched shunts) was fixed at pre-contingency positions. All buses, lines, and transformers in the El Paso and surrounding New Mexico control areas with base voltages of 69 kv and above were monitored. Pre-contingency flows on lines and transformers must remain at or below the normal rating of the element, and post-contingency flows on network elements must remain at or Generator Interconnection 5 September 2008

10 below the emergency rating. Flows above 100% of an element s rating are considered violations. The minimum and maximum voltages are specified in EPE s FERC Form 715. Voltages that did not meet criteria in the benchmark cases were considered an exception to the criteria for that specific bus and did not have a penalizing effect when evaluating the XXXXXXXXXXXX generation interconnection. The performance criteria utilized in monitoring the EPE and New Mexico areas are shown below in Table 2-1. Table 2.1: Performance Criteria Area EPEC PNM Tri- State Conditions Normal Contingency Normal ALIS Contingency N-1 Contingency N-2 Normal ALIS Contingency N-1 Contingency N-2 Loading Limits < Normal Rating < Emergency Rating Voltage Voltage (p.u.) Drop Application kV and above Artesia 345 kv Arroyo 345 kv PST source side Alamo, Sierra Blanca and Van Horn 69kV % 60 kv to 115 kv % Artesia 345kV % Arroyo 345kV PST source side Alamo, Sierra Blanca and Van Horn 69kV % Hidalgo, Luna, or other 345 kv buses kv and above* < Normal Rating < Emergency %** 46 kv to 115 kv Rating %** 230 kv and above < Emergency Rating % 46 kv and above* < Normal Rating All buses < Emergency Rating < Emergency Rating %** %** % Tri-State buses served from the PNM System (46 kv to 115 kv) Tri-State buses served from the PNM System (230 kv and above) Tri-State buses served from the Tri- State system % All buses * Taiban Mesa and Guadalupe 345 kv bus voltage must be between 0.95 and 1.1 p.u. under normal and contingency conditions. Generator Interconnection 6 September 2008

11 ** For PNM buses in southern New Mexico and Tri-State buses in southern New Mexico served from the PNM system, the allowable N-1 voltage drop is 7%. Generator Interconnection 7 September 2008

12 3.0 METHODOLOGY 3.1 Assumptions The following assumptions are consistent for all study scenarios unless otherwise noted. System improvement good faith estimated costs and construction schedule for the XXXXXXXXXXXX generation interconnection were to be developed by XXX s consultants. EPE does not warrant the accuracy of this information. This study assumes that all system expansion projects as planned by area utilities by the year under analysis are completed and that any system improvements required by the three generator interconnections senior to the XXXXXXXXXXXX project are implemented. This study did not analyze any transmission service from the interconnection point to any specific point on the grid. It determined Network Upgrades necessary to deliver the proposed XXXXXXXXXXXX generation output uniformly into the entire WECC transmission grid. 3.2 Procedure The analyses in this study included Powerflow, Q-V, and Short-Circuit. Detailed discussions for each topic are included in this report. A description of the procedures used to complete the analyses is shown below Development and Description of Cases A heavy summer load 2011 WECC powerflow case was used with the below modifications to establish a benchmark case without the XXXXXXXXXXXX Project. Benchmark Case: The 2011 benchmark case included the following third party generation: MW of generation (Luna Energy Facility) interconnected at the Luna 345 kv bus and scheduled to the WECC grid. Generator Interconnection 8 September 2008

13 MW of generation (Afton CT) interconnected at the Afton 345 kv Substation and scheduled to PNM through the EPE/PNM control area at the West Mesa 345 kv bus MW of generation (Pyramid) interconnected at PNM s Hidalgo 115 kv Substation and scheduled to the WECC grid MW of generation (Lordsburg) interconnected at PNM s Lordsburg 115 kv Substation and scheduled to the WECC grid MW of generation (Afton ST) interconnected at the Afton 345 kv Substation and scheduled to PNM MW of generation interconnected at EPE s Artesia-Amrad 345 kv line MW of generation interconnected to the EPE and PNM systems in southern New Mexico MW of generation interconnected at the Luna 345 kv Substation in southern New Mexico. Generation Interconnection Case: The XXXXXXXXXXXX Generation Interconnection case modeled the benchmark case described above with the proposed XXXXXXXXXXXX generation in service. The XXXXXXXXXXXX generation output was modeled at a total of 99 MW delivered to WECC List of Contingencies The list of contingencies has been included in Appendix 3. Based on engineering judgment, these contingencies were selected because they represent a good cross section of potential contingencies that would stress the EPE system and PNM s southern New Mexico system. Double contingencies were also analyzed but only for informational purposes to identify potential problem areas. Generator Interconnection 9 September 2008

14 3.2.3 QV Analysis Q-V analyses were performed to verify that the WECC criteria for reactive power margin will be met under the worst contingencies on the EPE system. A procedure developed by WECC was used to determine the reactive power margin. As outlined in this procedure, load was increased by 5% and the worst contingency was analyzed to determine the reactive margin on the system. The margin is determined by identifying the critical (weakest) bus on the system during the worst contingency. The critical bus is the most reactive deficient bus. Q-V curves are developed and the minimum point on the curve is defined as the critical point. If the critical point of the Q-V curve is positive, the system is reactive power deficient. If it is negative, then the system has sufficient reactive power margin and meets the WECC criteria. Prior experience has shown that the worst contingencies impacting reactive power margin are the Springerville-Luna, Luna-Diablo, and Greenlee-Hidalgo 345 kv lines and the buses most impacted are the 345 kv buses at Arroyo, Newman, Caliente, Diablo, Luna, and Hidalgo. All these contingencies and more were analyzed for Q-V margin. The Q-V results are shown on page 20 and the plots for these analyses can be seen in Appendix Short-Circuit Analysis Short-circuit analyses were performed with and without the XXXXXXXXXXXX generation interconnected into the EPE control area. These consisted of substation three phase to ground, two phase to ground, phase to ground, and phase to phase faults. Fault simulations were conducted at several 345 kv and 115 kv buses as shown in the short-circuit analysis table on page 21. The objective of these analyses was to determine the incremental fault current contribution from the XXXXXXXXXXXX generation interconnection and determine if the existing substation breakers in the surrounding area will safely accommodate this additional fault current without exceeding their interruption ratings. The Short-Circuit Analysis report can be found on page 20. Generator Interconnection 10 September 2008

15 4.0 POWER FLOW ANALYSIS RESULTS Powerflow study results for the EPE and PNM load areas showed that no overloads exist in the all lines in service scenarios with or without the XXXXXXXXXXXX Project. However, in the Arizona load area several overloaded elements exist under an all lines in service scenario prior to the addition of the XXXXXXXXXXXX Project. These overloads appear to be caused as a result of the planned 990 MW generation interconnection project, the planned 500 MW generation interconnection project or as existing in the 2011 WECC beginning powerflow case. The Arizona area overloads occur without the XXXXXXXXXXXX Project in service and are slightly aggravated when the XXXXXXXXXXXX Project is added in the powerflow case. A summary of these impacts is shown in the table below that compares the benchmark case (no XXXXXXXXXXXX Project) with the case that includes the XXXXXXXXXXXX Project. ARIZONA AREA - ALL LINES IN SERVICE OVERLOADS 2011 BENCHMARK CASE ( NO XXXXXXXXXXXX) 2011 CASE WITH XXXXXXXXXXXX % OF % OF % FROM TO NORMAL FROM TO NORMAL OVERLOADS BUS KV BUS KV RATING BUS KV BUS KV RATING DELTA BLYTHE 161 BUCKBLVD BLYTHE 161 BUCKBLVD LAGUNATP 69 YUCCA W LAGUNATP 69 YUCCA W SHIPROCK 230 SHIPROCK SHIPROCK 230 SHIPROCK If the Arizona area data modeling is more properly represented in the 2011 WECC case and/or the generation interconnection projects senior to the XXXXXXXXXXXX Project provide for system improvements to relieve the overloading with enough capacity to absorb the delta overloads shown in the above table, XXX will not be expected to provide additional system improvements. However, if the Arizona area data updates and/or Generator Interconnection 11 September 2008

16 system improvements the interconnection projects senior to the XXXXXXXXXXXX Project will be required to make are not enough to correct the overloads caused by the XXXXXXXXXXXX Project, XXX will be responsible for any necessary additional improvements. If this should happen, the issue of overloads in the Arizona system will have to be addressed by XXX directly with the appropriate Arizona entity if the project should move forward to the next study phase. No cost figures for any remedies in the Arizona system have been provided in this study. Powerflow results for contingency scenarios in the New Mexico/EPE areas (see Appendix 3 for list of contingencies) show that in many of the scenarios, overloads existed prior to the addition of the XXXXXXXXXXXX Project. However, as can be seen in the following table, results show that three overloaded transmission lines are identified due to the addition of the XXXXXXXXXXXX project and include: Central-Hurley 115 kv Luna-Hurley 115 kv El Butte-SocorroP 115 kv The numbers in the table shown under the Without XXXXXXXXXXXX and the With XXXXXXXXXXXX columns represent the % of emergency rating for the element shown. The overloads due to the XXXXXXXXXXXX project are highlighted in yellow. It is important to note that the overloads noted for this analysis of the transmission lines in the PNM and Tri-State systems were based on ratings shown for the facilities in the base case. These overloaded lines use the same rating value for emergency as they do for normal. Generator Interconnection 12 September 2008

17 2011 SINGLE CONTINGENCIES From Bus kv To Bus kv Without XXXXXXXXXXXX With XXXXXXXXXXXX Delta Owner Contingency AVILA_T 115 NO_BERN NM B-A- RIOPUERC1345 B-A 115 B-A NM B-A- RIOPUERC1345 B-A 115 ENCHNTED NM B-A- RIOPUERC1345 B-A 115 NO_BERN NM B-A- RIOPUERC1345 BLYTHE 161 BUCKBLVD AZ MANY CENTRAL 69 CENTRAL NM HID-LORSBRG115 CENTRAL 115 HURLEY_# NM LUNA -HID 345 CENTRAL 69 LORDSBRG NM HID-LORSBRG115 CENTRAL 69 SILVER_C NM TURQUOIS 69/115 CHOLLA 345 CHOLLA AZ SPRGR-VAIL 345 GREEN- COPPERVR 345 COPPERVR AZ WINCH345 EAST_TAP 115 EMBUDO NM WM-SANDIA 345 CAB-MIMBRES EL_BUTTE 115 PICACHO NM 115 EL_BUTTE 115 SOCORROP NM GRN-HID345 ENCHNTED 115 CHAYOTE NM B-A- RIOPUERC1345 GREEN-AE 230 GREEN-AE AZ GREEN- WINCH345 LAGUNATP 69 YUCCA W AZ MANY LORDSBRG 69 LORDSBRG NM HID-LORSBRG115 LUNA 115 HURLEY_# NM LUNA -HID 345 LUNA 115 LUNA NM LUNA -HID 345 RIOPUERCO- PANORAMT 115 VERANDAT NM WM1345 PERSON 115 PROSPER NM WM-SANDIA 345 SHIPROCK 230 SHIPROCK AZ MANY Notes: 1. The numbers shown under the Without XXXXXXXXXXXX and the With XXXXXXXXXXXX columns represent the % of emergency rating for the element shown. 2. Owner: NM=New Mexico, AZ=Arizona 3. Impact of adding XXXXXXXXXXXX Project - New Mexico overloaded transmission elements owners & ratings: a. Central-Hurley 115 KV PNM (normal rating = 131 MVA, eme rgency rating = 131 MVA) b. El_Butte-SocorroP 115 KV Tri-State (normal rating = 60 MVA, emergency rating = 60 MVA) c. Luna-Hurley_# 115 KV PNM (normal rating =131 MVA, emergency rating = 131 MVA) Generator Interconnection 13 September 2008

18 The following table identifies potential problems under double contingency conditions and is presented here for informational purposes only. No mitigations to these overloads were studied for this. From Bus kv To Bus kv 2011 DOUBLE CONTINGENCIES Without XXXXXXXXXXXX With XXXXXXXXXXXX Delta Area Contingencies BLK MESA 230 BMA.3WP AZ MANY BLK MESA 230 BMA.3WP AZ MANY BLYTHE 161 BUCKBLVD AZ MANY CENTRAL 115 HURLEY_# NM LUN-HID,LUNA -DIA CENTRAL 115 TURQUOIS NM 2 HIDALGO AUTOS DONA_ANA 115 LAS_CRUC NM LUN-HID,LUNAUTO DONA_ANA 115 PICACHO NM LUN-HID,LUNAUTO EL_BUTTE 115 PICACHO NM LUN-AFT,LUNAUTO EL_BUTTE 115 PICACHO NM LUN-HID,LUNAUTO EL_BUTTE 115 SOCORROP NM HID-GR,HIDAUTO2 HIDALGO 115 TURQUOIS NM 2 HIDALGO AUTOS LAGUNATP 69 YUCCA W AZ MANY LORDSBRG 69 LORDSBRG NM TUR-H,TUR-PD115 LORDSBRG 69 LORDSBRG NM 2 HIDALGO AUTOS LUNA 115 HURLEY_# NM LUN-HID,LUNA -DIA LUNA 115 LUNA NM LUN-HID,LUNA -DIA SHIPROCK 230 SHIPROCK AZ MANY EPE System One-Line Diagrams with all lines in service and with and without the XXXXXXXXXXXX project can be found in Appendix Sensitivity Studies 4.1A PNM to EPE Control Area Firm Schedule at West Mesa of 201 MW - The powerflow studies discussed above were based on a PNM to EPE Control Area Firm Schedule at the West Mesa 345 kv bus of 60 MW and with Afton generation of 141 MW scheduled to PNM through this control area. This scenario is a very likely operating scenario but in the event that the maximum north to south (PNM to EPE) contract firm Generator Interconnection 14 September 2008

19 schedule of 201 MW is exercised (no Afton generation), a sensitivity analysis on transmission loading was conducted using contingency set #1. The tables below compares the loading of area in the majority of scenarios, the most stressful case is when the PNM to EPE control area firm schedule at West Mesa is at 60 MW. WITHOUT XXXXXXXXXXXX % of Emergency Rating FROM BUS KV AREA TO BUS KV 60* 201* CONTINGENCY DELTA CENTRAL 69 NM SILVER_C TURQUOIS 69/ EL_BUTTE 115 NM PICACHO CAB-MIMBRES LUNA 115 NM LUNA LUNA -HID BLYTHE 161 AZ BUCKBLVD MANY 0 COPPERVR 345 AZ COPPERVR GREEN-WINCH GREEN-AE 230 AZ GREEN-AE GREEN-WINCH LAGUNATP 69 AZ YUCCA W MANY 0 SHIPROCK 230 AZ SHIPROCK MANY 2.3 WITH XXXXXXXXXXXX % of Emergency Rating FROM BUS KV AREA TO BUS KV 60* 201* CONTINGENCY DELTA CENTRAL 69 NM SILVER_C TURQUOIS 69/ CENTRAL 115 NM HURLEY_# LUNA -HID EL_BUTTE 115 NM PICACHO CAB-HOTSPRGS EL_BUTTE 115 NM PICACHO CAB-MIMBRES EL_BUTTE 115 NM PICACHO HOTSPRG-CUCH EL_BUTTE 115 NM PICACHO LUNA -MIMBRES EL_BUTTE 115 NM SOCORROP GRN-HID LUNA 115 NM LUNA LUNA -HID LUNA 115 NM HURLEY_# LUNA -HID BLYTHE 161 AZ BUCKBLVD MANY 0 COPPERVR 345 AZ COPPERVR GREEN-WINCH GREEN-AE 230 AZ GREEN-AE GREEN-WINCH345-3 LAGUNATP 69 AZ YUCCA W MANY 0 SHIPROCK 230 AZ SHIPROCK MANY 2.2 * PNM to EPE control area firm schedule at West Mesa 345 kv bus Generator Interconnection 15 September 2008

20 4.1B PNM to EPE Control Area Firm Schedule at West Mesa of -50 MW Under the EPE/PNM Settlement Agreement, a 50 MW south to north schedule at West Mesa 345 kv should be accommodated with Afton generation on. Results of this sensitivity analysis showed that this schedule was able to be maintained. Note: The PNM to EPE Control Area Firm Schedule at the West Mesa 345 kv is based on firm contract schedules within the range of -50 to 201 MW. The sensitivity studies above show that some overloads occur within this schedule range. EPE does not allow rescheduling over this control area interchange point as a matter of course for alleviating overloads identified in the above tables. Generator Interconnection 16 September 2008

21 5.0 VOLTAGE ANALYSIS RESULTS Transmission bus voltage profiles were monitored in the EPE, southern New Mexico and Arizona areas for the powerflow cases with and without the XXXXXXXXXXXX Project. Bus voltage comparison tables were created for all lines in service (ALIS) and select worst contingency conditions to evaluate the impact of bus voltages due to the XXXXXXXXXXXX generation interconnection. The reason this was done was because it was noted that in the case without the XXXXXXXXXXXX Project there were some bus voltages (especially in Arizona) that were not meeting voltage criteria. After further review of the Arizona system it was concluded that the low bus voltage profiles in Arizona were primarily due to inadequate system modeling by Arizona utilities in the beginning powerflow case. As can be seen in the tables below, the impact of the XXXXXXXXXXXX generation interconnection is minimal on area voltage profiles. Area bus voltage deltas greater than per unit are shown below. ALL LINES IN SERVICE VOLTAGE COMPARISON WITHOUT XXXXXXXXXXXX WITH XXXXXXXXXXXX PER UNIT PER UNIT BUS KV VOLTAGE AREA BUS KV VOLTAGE DELTA AMISTAD NM AMISTAD WESTMESA NM WESTMESA SILVER_C NM SILVER_C TYRONE NM TYRONE DEMINGTS NM DEMINGTS VANBUREN NM VANBUREN SANDIA NM SANDIA IVANHOE NM IVANHOE CUCHILLO NM CUCHILLO ELBUT_US NM ELBUT_US EL_BUTTE NM EL_BUTTE HOT_SPRG NM HOT_SPRG WESTMESA NM WESTMESA Generator Interconnection 17 September 2008

22 VOLTAGE COMPARISON FROM WORST CONTINGENCY LIST #1 WITHOUT XXXXXXXXXXXX WITH XXXXXXXXXXXX PER UNIT PER UNIT BUS KV VOLTAGE AREA BUS KV VOLTAGE DELTA SILVER_C NM SILVER_C TYRONE NM TYRONE IVANHOE NM IVANHOE CENTRAL NM CENTRAL CENTRAL NM CENTRAL HURLEY_# NM HURLEY_# CHINO NM CHINO Generator Interconnection 18 September 2008

23 6.0 Q-V ANALYSIS RESULTS Q-V analyses were conducted in order to verify that the scenarios modeled in this Study comply with the WECC Voltage Stability Criteria. The analysis provides a way to investigate the potential for voltage collapse during the post-transient period within 3 minutes after the disturbance. Analyses were performed on the benchmark and XXXXXXXXXXXX powerflow cases. A procedure developed by WECC was used to determine the reactive power margin. As outlined in the procedure, load is increased by 5% and the worst contingency is analyzed to determine the reactive margin on the system. The margin is determined by identifying the critical (weakest) bus on the system during the worst contingency. The critical bus is the most reactive deficient bus. Q-V curves are developed and the minimum point on the curve is the critical point. If the minimum point of the Q-V curve is positive, i.e., above the x-axis, the system is reactive power deficient. If it is negative, i.e., below the x-axis, then the system has some reactive power margin and meets the WECC criteria. From experience, it has been established that the worst contingency impacting reactive power margin on the EPE system is an outage of the Luna-Diablo 345 kv line. This single contingency along with single contingencies of the Springerville-VLTap 345 kv, VLTap-Luna 345 kv, Westmesa-Ft. Craig PST 345 kv, Greenlee-Hidalgo 345 kv, Ft. Craig-VLTap 345 kv, Ft. Craig-Arroyo 345 kv, and Newman-Afton 345 kv lines were simulated and analyzed for Q-V margin. The Arroyo, Luna, Caliente, Newman, and Diablo 345 kv buses were monitored for Q-V margins (as shown in the tables below) to verify that EPE reactive power margins are in compliance with the WECC criteria. As can be seen, there is more than enough VAR margin to meet criteria. Resulting plots can be found in Appendix 4. Note that a negative number indicates that there is sufficient reactive power to meet WECC criteria and a positive number indicates that the system is deficient in reactive power and does not meet the criteria. Generator Interconnection 19 September 2008

24 2011 Heavy Summer Load Case Q-V Margin (MVAR) Springerville-VLTap 345 kv Line Outage Greenlee-Hidalgo 345 kv Line Outage Without With Without With XXXX XXXX XXXX XXXX Bus XXXX XXXX Bus XXXX XXXX Arroyo 345 kv Arroyo 345 kv Luna 345 kv Luna 345 kv Caliente 345 kv Caliente 345 kv Newman 345 kv Newman 345 kv Diablo 345 kv Diablo 345 kv Luna-Diablo 345 kv Line Outage Ft. Craig-VLTap 345 kv Line Outage Without With Without With XXXX XXXX XXXX XXXX Bus XXXX XXXX Bus XXXX XXXX Arroyo 345 kv Arroyo 345 kv Luna 345 kv Luna 345 kv Caliente 345 kv Caliente 345 kv Newman 345 kv Newman 345 kv Diablo 345 kv Diablo 345 kv VLTap-Luna 345 kv Line Outage without XXXXXXXXXXXX VLTap-SLPOI kv Line Outage with XXXXXXXXXXXX Ft. Craig-Arroyo 345 kv Line Outage Without With Without With XXXX XXXX XXXX XXXX Bus XXXX XXXX Bus XXXX XXXX Arroyo 345 kv Arroyo 345 kv Luna 345 kv Luna 345 kv Caliente 345 kv Caliente 345 kv Newman 345 kv Newman 345 kv Diablo 345 kv Diablo 345 kv Westmesa-Ft. Cr aig PST 345 kv Line Outage Newman-Afton 345 kv Line Outage Without With Without With XXXX XXXX XXXX XXXX Bus XXXX XXXX Bus XXXX XXXX Arroyo 345 kv Arroyo 345 kv Luna 345 kv Luna 345 kv Caliente 345 kv Caliente 345 kv Newman 345 kv Newman 345 kv Diablo 345 kv Diablo 345 kv Generator Interconnection 20 September 2008

25 7.0 SHORT-CIRCUIT RESULTS Short-circuit (fault) analyses were performed with and without the XXXXXXXXXXXX generation interconnected into the EPE system. The objective of this analysis was to determine the incremental fault current contribution from the XXXXXXXXXXXX generation interconnection and determine if the existing substation circuit breakers can safely accommodate this additional fault current without exceeding their interruption ratings. Study results are shown in the tables below and show that in the benchmark case that already certain circuit breaker short-circuit capabilities are exceeded and are further aggravated when the XXXXXXXXXXXX Project is added to the system. Consequently, XXX will not be assigned circuit breaker upgrade responsibilities but are expected to be resolved by one of the generation interconnection projects that are senior to the XXXXXXXXXXXX Project in the study queue. The powerflow and short-circuit modeling data supplied by XXX and used in the modeling of the XXXXXXXXXXXX Project are shown in Appendix 5. The short-circuit data was enhanced with GE shortcircuit data from a previous study using similar wind generators. Generator Interconnection 21 September 2008

26 Fault Current (Amps) Fault Current (Amps) Fault Current (Amps) Without XXXX With XXXX Increase Due to XXXX Generation XXXX Generation XXXXXXXXXXXX Generation Substation Amps (1) 3Ø-g 2Ø-g 1Ø-g L-L 3Ø-g 2Ø-g 1Ø-g L-L 3Ø-g 2Ø-g 1Ø-g L-L Amrad 345 kv 40, Amrad 115 kv 40, Caliente 345 kv 40, Caliente 115 kv 40, Afton 345 kv 50, Arroyo 345 kv 25, Arroyo 115 kv 22, Diablo 345 kv 40, Diablo 115 kv 32, LEF 345 kv 40, Luna 345 kv 40, Luna 115 kv 20, Newman 345 kv 40, Newman 115 kv 40, Ascarate 115 kv 19, Ft. Craig 345 kv (2) VLTap 345 kv (2) Z345 kv (2) SLPOI 345 kv (2) n/a n/a n/a n/a n/a n/a n/a n/a SLPOI 115 kv (2) n/a n/a n/a n/a n/a n/a n/a n/a SL 115 kv (2) n/a n/a n/a n/a n/a n/a n/a n/a Lunasol 345 kv (2) B-A 345 kv 40, Springerville 345 kv 40, Westmesa 345 kv 40, Picante 345 kv (2) Picante 115 kv (2) Rio Grande 115 kv 20, Rio Grande 69 kv 25, (1) Lowest rating in amperes of any breaker at substation bus (2) To be engineered Generator Interconnection 22 September 2008

27 8.0 COST ESTIMATES Through a Discretionary Change to the System Facility Study Scope (Appendix 7), EPE agreed to allow XXX to have their consultants prepare a good faith cost estimate and construction schedule for interconnecting into the EPE system and for any required Network Upgrades. Consequently no cost or timing information in this has been provided by EPE or its cost estimate consultant. Additionally, EPE does not warrant any cost information developed by XXX or its consultant. The diagram below shows the point of interconnection on the Springerville-Luna 345 kv line of the XXXXXXXXXXXX generation. To Springerville Substation thru VL-Tap Substation Series capacitors, reactors & their breakers relocated from Luna XXXXXXXXXXXX Wind Farm 99 MW Total Generation 345/115 kv 200/224 MVA 6 miles 115/34.5 kv SLPOI 345 kv Substation 200/224 MVA 30 miles to Luna Substation A list of cost estimates to be addressed by XXX s consultants should include at least the following: 1. Sixty-six wind generators (1.5 MW each) and associated wind generation park facilities. 2. A 115/34.5 kv, 200/224 MVA step-up transformer (as per original.epc file submitted by XXX). The latest information from XXX is that the new MVA size will be 100/133/ Six miles of 954 ACSR, 115 kv transmission line. Generator Interconnection 23 September 2008

28 4. A 345/115 kv, 200/224 MVA interconnection transformer (as per original.epc file submitted by XXX). The latest information from XXX is that the new MVA size will be 100/133/ SLPOI 345 kv Substation with three 345 kv breakers and associated facilities. 6. Relocation of the series capacitors and reactors (with breakers) from the Luna end of the Springerville-Luna 345 kv line to SLPOI Substation as shown above. Additional Network Upgrades needed on third party systems include: 1. Determine Tri-State s El Butte-SocorroP 115 kv line (4/0 ACSR conductor, miles, rated 60 MVA normal & emergency) facility limitation. Any appropriate mitigation will be developed in the System Impact Study after consultation with Tri- State. 2. Determine PNM s Central-Hurley 115 kv line (477 ACSR conductor, 6.6 miles, rated 131 MVA normal & 131 MVA emergency) facility limitation. Any appropriate mitigation will be developed in the System Impact Study after consultation with PNM. 3. Determine PNM s Luna-Hurley 115 kv line (477 ACSR conductor, 36.4 miles, rated 131 MVA normal & emergency) facility limitation. Any appropriate mitigation will be developed in the System Impact Study after consultation with PNM. More detailed mitigation for the conductor overloads shown in this study on neighboring utilities (if required) as well as more specific facility requirements and specifications will be developed as a component of the System Impact Study if the study should continue to the next phase. Generator Interconnection 24 September 2008

29 9.0 ENERGY RESOURCE INTERCONNECTION SERVICE As requested by XXX and as per part of EPE s Open Access Transmission Tariff, this includes an analysis of the Energy Resource Interconnection Service. This service is meant to identify the maximum allowable output of the interconnecting XXXXXXXXXXXX generation that would require no additional Network Upgrades under all lines in service (ALIS) and single contingency conditions. This analysis was conducted by increasing the XXXXXXXXXXXX generation output until transmission element overloads start to occur under ALIS and contingency conditions. Results showed that overloads start to occur when the XXXXXXXXXXXX generation is at 49 MW. As previously mentioned, some transmission elements in the powerflow database are rated the same value for both the normal and emergency rating. These results were based on analysis of the powerflow case when loads were at peak value. In the System Impact Study, the powerflow case will be analyzed at peak load as well as some lower load level and may change the results due to the change in counter flows at lower load levels. Note: If those generation interconnection projects senior to XXXXXXXXXXXX in the EPE study queue should change or drop out, a restudy of the XXXXXXXXXXXX interconnection would be required and may change these results. Generator Interconnection 25 September 2008

30 10.0 DISCLAIMER This study assumes that transmission service has not been obtained by XXX to deliver its XXXXXXXXXXXX generation output. Therefore, this Study modeled the XXXXXXXXXXXX power output as being distributed evenly across the entire WECC electrical grid. Whenever XXX determines where it will deliver its generation output to, XXX will have to purchase the required transmission service from the appropriate entity and a Transmission Service Study will be performed to determine the impacts of the XXXXXXXXXXXX transmission path on the EPE and surrounding transmission systems. This study makes no warranties as to the existence or availability of any transmission service XXX will need in order to deliver its XXXXXXXXXXXXXXX generation output. Also, the transfer capacities of certain transmission lines and paths within the southern New Mexico transmission system are limited by contracts between the New Mexico transmission owners and any use of the transfer capacities above the contractual limits will require approval by the contractual parties and renegotiation of the applicable contract(s). If any of the project data used in this study and provided by XXX varies significantly from the actual data once the XXXXXXXXXXXX equipment is installed, the results from this study will need to be verified with the actual data at the Project developer's expense. Additionally, any change in the generation in EPE s Interconnection Queue that is senior to the XXXXXXXXXXXX Project will require a re-evaluation of this Study. Generator Interconnection 26 September 2008

31 11.0 CERTIFICATION (EPE) performed a Generation Interconnection Feasibility Study (GIFS) for XXXXXXXXXXXXX (XXX) pursuant to XXX s letter requesting to interconnect its XXXXXXXXXXXX wind powered generating plant to EPE s Springerville-Luna 345 kv line. The Study determined the impacts to the EPE and surrounding transmission systems due to the interconnection planned for March 1, This recommends Network Upgrades required for mitigating potential impacts due to the addition of the XXXXXXXXXXXX generation. Cost estimates and construction schedules at the generation site and for the transmission interconnection were not provided in this Phase as requested by XXX. XXX s engineering consultants were to provide those items. The powerflow and short-circuit data used to model the XXXXXXXXXXXX generation was supplied by XXX and enhanced with GE short-circuit data from a previous study using similar wind generators. EPE performed power flow, Q-V reactive margin, and short-circuit analyses in this study. Name: Dennis H. Malone Title: Manager, System Planning Signature: Date: Investigating Engineer: Joaquin Aguilar Generator Interconnection 27 September 2008

120 MW SOLAR-THERMAL PLANT GENERATOR INTERCONNECTION FEASIBILITY STUDY. May 2008 Prepared by: EL PASO ELECTRIC COMPANY

120 MW SOLAR-THERMAL PLANT GENERATOR INTERCONNECTION FEASIBILITY STUDY. May 2008 Prepared by: EL PASO ELECTRIC COMPANY . 120 MW SOLAR-THERMAL PLANT GENERATOR INTERCONNECTION May 2008 Prepared by: EL PASO ELECTRIC COMPANY Foreword This report was prepared for XXXXXXXXXXXXXXXXXXX by System Planning at El Paso Electric Company.

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department

More information

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS System Operations Department System Planning Section June 2001 TABLE OF CONTENTS 1.0 Executive Summary...Page

More information

300 MW SOLAR PHOTOVOLTAIC PLANT, GENERATOR INTERCONNECTION FEASIBILITY STUDY

300 MW SOLAR PHOTOVOLTAIC PLANT, GENERATOR INTERCONNECTION FEASIBILITY STUDY 300 MW SOLAR PHOTOVOLTAIC PLANT, GENERATOR INTERCONNECTION FEASIBILITY STUDY El Paso Electric Company System Planning August 2006 TABLE OF CONTENTS 1.0 EXECUTIVE SUMMARY...Page 1 2.0 PURPOSE...Page 7 3.0

More information

XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS El Paso Electric Company System Operations Department System Planning Section September 2001 TABLE

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ART320W 320 MW Wind Powered Project Prepared for: El Paso Electric Company Prepared by: TRC Engineers, LLC 249 Western Avenue Augusta, ME 04330

More information

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION El Paso Electric Company System Operations Department System Planning Section August 2006 I. INTRODUCTION The

More information

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study System Operations Department System Planning Section March 2002 Table of Contents: 1.0 EXECUTIVE SUMMARY 4 2.0 COST ESTIMATES 8 2.1 Cost

More information

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS El Paso Electric Company System Operations Department System Planning

More information

El Paso Electric Company

El Paso Electric Company Feasibility Study XXXXXX Solar Generation Prepared for El Paso Electric Company Prepared by TRC Engineers, LLC 249 Eastern Avenues Augusta, ME 04330 (207) 621-7000 Project Number: 202327 May 2013 FOREWORD

More information

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS El Paso Electric Company System Operations Department System Planning Section September 2001 Short Circuit

More information

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the

More information

Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study

Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study Study Performed by El Paso Electric Company System Planning Section - 1 I.

More information

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY Short Circuit Analysis System Operations Department System Planning Section March 2001 I. Introduction XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report

More information

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company

SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY. El Paso Electric Company SYSTEM IMPACT STUDY REPORT LA450S GENERATION STUDY Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD

More information

New Mexico Transmission Expansion Concepts For Wind Resources

New Mexico Transmission Expansion Concepts For Wind Resources New Mexico Transmission Expansion Concepts For Wind Resources May 2008 Update Electric Services Transmission Operations FOREWORD This document contains PNM s latest concepts for expanding the transmission

More information

Verde Transmission, LLC. Verde Project. System Impact Study Report

Verde Transmission, LLC. Verde Project. System Impact Study Report Verde Transmission, LLC Verde Project System Impact Study Report March 2017 Prepared by: Public Service Company of New Mexico Foreword This report was prepared for Verde Transmission, LLC by the PNM Transmission/

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018 March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM-2017-11 May 2018 Prepared by: Public Service Company of New Mexico Foreword This report is prepared

More information

ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study

ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study Final Report ABB Power Systems Consulting June 27, 2016 LEGAL NOTICE This document, prepared by ABB Inc, is an

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Cargill Power Markets LLC Transmission Service Study (OASIS # TSR and )

Cargill Power Markets LLC Transmission Service Study (OASIS # TSR and ) Cargill Power Markets LLC Transmission Service Study (OASIS # TSR 72608299 and 72827161) Prepared by: Electric Power Research Institute (EPRI) Under contract with: Public Service Company of New Mexico

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Clean Line Energy Partners, LLC. Western Spirit Clean Line 345 kv. System Impact Study

Clean Line Energy Partners, LLC. Western Spirit Clean Line 345 kv. System Impact Study Clean Line Energy Partners, LLC Western Spirit Clean Line 345 kv System Impact Study February, 2017 Prepared by: Public Service Company of New Mexico Foreword This report was prepared for the Clean Line

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Status of PNM s Completed Transmission Construction Projects 11/30/2017 Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

PUD ELECTRIC SYSTEM INTERCONNECTION

PUD ELECTRIC SYSTEM INTERCONNECTION APPENDIX A PROCEDURES & REQUIREMENTS for OKANOGAN PUD ELECTRIC SYSTEM INTERCONNECTION Version 4.0 December 2011 Version 4.0 12/28/2011 Page 1 of 15 TABLE OF CONTENTS DEFINITIONS 1.0 Introduction 2.0 Procedures

More information

Project #94. Generation Interconnection System Impact Study Report Revision

Project #94. Generation Interconnection System Impact Study Report Revision Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

EL PASO ELECTRIC COMPANY SYSTEM EXPANSION PLAN

EL PASO ELECTRIC COMPANY SYSTEM EXPANSION PLAN EL PASO ELECTRIC COMPANY SYSTEM EXPANSION PLAN 2019-2028 Produced by System Planning 2018 GENERAL EL PASO ELECTRIC COMPANY 2019-2028 SYSTEM EXPANSION PLAN Executive Summary El Paso Electric Company s

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007 High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services

More information

Midway/Monument Area TTC Study

Midway/Monument Area TTC Study Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning. A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

Interconnection System Impact Study Final Report February 19, 2018

Interconnection System Impact Study Final Report February 19, 2018 Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)

PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) Determination and Posting Of Total Transmission Capability (TTC) & Available Transmission Capability (ATC) On The Open Access Same-Time Information System (OASIS)

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Four Corners Queue Transmission Interconnection Study

Four Corners Queue Transmission Interconnection Study Four Corners Queue Transmission Interconnection Study Facility Study Results By Arizona Public Service Company Transmission Planning & Interconnection Development March 22, 2016 Version 1 FACILITIES STUDY

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

Georgia Transmission Corporation Georgia Systems Operations Corporation

Georgia Transmission Corporation Georgia Systems Operations Corporation Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives Addendum San Juan Major Project Tri-State Generation and Transmission Association Power System Planning December, 2008

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

FEASIBILITY STUDY REPORT

FEASIBILITY STUDY REPORT FEASIBILITY STUDY REPORT HL20S PV Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 249 Eastern Avenue Augusta, ME 04330 (207) 621-7000 July 2012 FOREWORD This report was prepared for

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006

Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006 Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006 As per the Manitoba Hydro Open Access Interconnection Tariff, the Transmission Owner has contracted TransGrid Solutions

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

2012 LOCAL TRANSMISSION PLAN:

2012 LOCAL TRANSMISSION PLAN: Colorado PUC E-Filings System 2012 LOCAL TRANSMISSION PLAN: TRANSMISSION COORDINATION AND PLANNING COMMITTEE ANNUAL TRANSMISSION ASSESSMENT FOR BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, L.P., D/B/A

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30)

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30) TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30) Submitted to TOT1A Stakeholders and TOT1A Interconnected Utilities And Western Electricity Coordinating Council June 6, 2013

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 1 Reactive Power Compensation for Solar Power Plants Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 2 Objectives Refresh the basics of reactive power from a generator s perspective Regulatory

More information

Hamdy S. K. El-Goharey, Walid A. Omran, Adel T. M. Taha

Hamdy S. K. El-Goharey, Walid A. Omran, Adel T. M. Taha 1 Military Technical College Kobry El-Kobbah, Cairo, Egypt 10 th International Conference on Electrical Engineering I. ICEENG 2016 Voltage Stability Investigation of the Egyptian Grid With High Penetration

More information

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and

More information

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Connection Engineering Study Report for AUC Application: AESO Project # 1674 APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources

Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources Outline Tri-State Background Tri-State Generation Mix Power Delivery Wholesale Electricity Markets

More information

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS. 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context indicates otherwise, this section and 25.212 of this title (relating to Technical Requirements

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta

More information