Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation
|
|
- Reynold McGee
- 5 years ago
- Views:
Transcription
1 Decision D Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016
2 Alberta Utilities Commission Decision D : Alberta Electric System Operator Needs Identification Document Application Application A001 Facility Applications Applications A002 to A005 Proceeding September 7, 2016 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Telephone: Fax: Website:
3 Alberta Utilities Commission Calgary, Alberta Alberta Electric System Operator Needs Identification Document Application Decision D Facility Applications Proceeding Applications A001 to A005 1 Decision summary 1. In this decision, the Alberta Utilities Commission must decide whether to approve applications filed by the Alberta Electric System Operator (AESO) and (ATCO Electric) for transmission development in the Spirit River area. After consideration of the record of the proceeding, and for the reasons outlined in this decision, the Commission finds the AESO s assessment of the need to be correct and finds that approval of the development proposed by ATCO Electric is in the public interest, having regard to the social and economic effects of the project and its effects on the environment. 2 Introduction and background 2. On July 4, 2016, the AESO filed a needs identification document application for approval of the need for transmission development in the Spirit River area (the needs identification document application). The needs identification document application, filed pursuant to Section 34 of the Electric Utilities Act, was registered as Application A Pursuant to Section 35 of the Electric Utilities Act, the AESO directed ATCO Electric to submit facility applications to the Commission to meet the need identified in the needs identification document application. 4. ATCO Electric filed facility applications to meet the need identified by the AESO pursuant to sections 14 and 15 of the Hydro and Electric Energy Act. ATCO Electric proposed to construct the, construct a new transmission line to connect the proposed substation to the existing 144-kilovolt (kv) Transmission Line 7L10, and alter the existing Rycroft 730S Substation (the proposed project). Its applications were filed on July 7, 2016, and were registered as applications A002 to A005 (the facility applications). ATCO Electric is the operator of Transmission Line 7L10 pursuant to Permit and Licence AP and the Rycroft 730S Substation pursuant to Permit and Licence AP The AESO and ATCO Electric requested that the applications be considered jointly pursuant to Section 15.4 of the Hydro and Electric Energy Act. The Commission advised the AESO and ATCO Electric that the applications had been combined and were being considered jointly as Proceeding Permit and Licence AP 84-40, Application , September 21, Permit and Licence AP 86-27, Application , June, 16, Decision D (September 7, 2016) 1
4 6. On July 28, 2016, the Commission issued a notice of applications for Proceeding with a deadline of August 28, 2016, for submissions to express objections, concerns, or support for one or more of the applications. The notice was sent directly to all occupants, residents and landowners within 800 metres of the project, as well as to other stakeholders who were contacted as part of the participant involvement program as identified by ATCO Electric. The notice was also published in the Rycroft Central Peace Signal on August 9, 2016 and on the AUC website. Notification was automatically ed to efiling System users who had chosen to be notified of notices of application issued by the Commission. 7. No submissions were received by the submission deadline of August 28, On July 28, 2016, the Commission issued information requests to ATCO Electric to clarify details of the facility applications. ATCO Electric submitted its responses on August 9, Discussion 3.1 Needs identification document application 9. ATCO Electric, the owner of electric distribution facilities in the Spirit River area, requested system access service from the AESO to meet its distribution reliability criteria and serve industrial load growth in the area. ATCO Electric s request included a rate demand transmission service contract capacity of approximately 21 megawatts to support the load from industrial and oil field customers in the Spirit River district. 10. The AESO indicated that the need could be met by constructing a new 144/25-kV point-of-delivery substation, designated as the, and a new 144-kV circuit, designated as Transmission Line 7LA10, connecting the proposed substation to the existing 144-kV Transmission Line 7L10 in a T-tap configuration. The AESO also proposed a 144-kV circuit breaker to be installed at the existing Rycroft 730S Substation. 11. The AESO considered two alternatives to the proposed project that involved capacity upgrades at the existing Rycroft 730S, Ksituan River 754S and Saddle Hills 865S substations. The AESO ruled out the alternatives because the proposed project would require the least complex transmission development, have lower cost and allow operational flexibility. 12. The connection assessment conducted by the AESO identified the potential for a thermal violation on a section of Transmission Line 7L10 under conditions when all transmission elements are in service following completion of the proposed project. The AESO indicated that ATCO Electric had plans to uprate the section of Transmission Line 7L10 prior to the proposed transmission development, thereby mitigating the potential thermal violation. The AESO also stated that remaining thermal violations would be managed by real-time operational procedures. 13. The AESO directed ATCO Electric to file a facility application with the AUC to meet the need identified and to assist in conducting a participant involvement program that would provide stakeholders with an opportunity to raise any concerns regarding the needs identification document application. 2 Decision D (September 7, 2016)
5 3.2 The facility applications 14. To meet the need identified by the AESO, ATCO Electric proposed to construct the, construct Transmission Line 7LA10 to connect the proposed substation to the existing 144-kV Transmission Line 7L10, and alter the existing Rycroft 730S Substation. 15. The proposed would be located within LSD 1 of Section 15, Township 78, Range 7, west of the Sixth Meridian on private land approximately 8.5 kilometres southwest of Spirt River. 16. Upon completion of the proposed project, the would include the following major equipment: one 144/25-kV, 30/40/50-megavolt-ampere transformer one 144-kV circuit breaker two 240-kV circuit breakers (operated as 144-kV circuit breakers) one 144-kV, 10-megavolt-ampere reactive (MVar) capacitor bank one 144-kV, 15-MVar capacitor bank six 25-kV circuit breakers one telecommunications tower approximately 40 metres tall associated substation equipment 17. ATCO Electric proposed to install two 240-kV circuit breakers on the capacitor banks to avoid performance issues within the proposed. ATCO Electric explained that the existing 144-kV Transmission Line 7L10 operates at 158 kv and could introduce transient voltages during switching that could exceed the rated voltage of 144-kV circuit breakers. ATCO Electric explained that the rationale for the use of the 240-kV circuit breakers was provided to, and accepted by, the AESO. 18. ATCO Electric indicated that the fenced area of the site would be approximately 70 metres by 70 metres. ATCO Electric secured an option to purchase the land from the landowners for the entire proposed substation area and the proposed altered Transmission Line 7L10 right-of-way. ATCO Electric identified the proposed Mowat 2033S Substation site as having favorable level and well-drained ground conditions, good access, sufficient space, good proximity to the customer s future potential development areas and would reduce the length of the transmission line required to connect to the electrical grid. ATCO Electric added that the proposed site would be aligned with municipal planning guidelines and has support of the current landowner. 19. ATCO Electric also proposed to construct one 144-kV single-circuit transmission line approximately 45 metres long, to be designated as 7LA10, that would connect the Mowat 2033S Substation to a tap point along the existing 144-kV Transmission Line 7L10. Transmission Line 7LA10 would be built within the property boundary of the. Decision D (September 7, 2016) 3
6 20. In addition, ATCO Electric proposed to alter approximately 445 metres of existing Transmission Line 7L10 to accommodate the proposed Transmission Line 7LA10. ATCO Electric stated that Transmission Line 7L10 is currently situated within the road allowance of Township Road 782 and does not have an easement. To accommodate the connection of Transmission Line 7LA10, a portion of the existing Transmission Line 7L10 centre line would be shifted north and a new easement would be required. The alteration would include the removal of existing structures and the addition of new structures. 21. ATCO Electric indicated that it selected the route for Transmission Line 7LA10 because it would be located close to two municipal roads which would allow for access. It also stated that the route would reduce the line length and fragmentation of agricultural land as reasonably as possible. 22. ATCO Electric also proposed to alter the Rycroft 730S Substation by replacing the existing 10-metre tall telecommunications tower with an approximately 34-metre tall self-supporting lattice telecommunications tower and the addition of one 144-kV circuit breaker. The Rycroft 730S Substation is located within LSD 16 of Section 9, Township 78, Range 5, west of the Sixth Meridian on approximately 6.14 acres of private land. 23. In response to the AUC s information request about the need for replacing the existing telecommunications tower at the Rycroft 730S Substation, ATCO Electric stated that the AESO functional specification for the Spirit River project included a requirement for ATCO Electric to provide protection-grade communications into Rycroft 730S Substation. ATCO Electric explained that replacing the existing telecommunications tower with the proposed 34-metre telecommunications tower would accommodate the increased height required to upgrade the radio link reliability. ATCO Electric added that no expansion of the Rycroft 730S Substation fenceline would be required. 24. Upon completion of the project, the Rycroft 730S Substation would include the following major equipment: one 144/25-kV, 15/20/25-MVA transformer three 144-kV circuit breakers one 144-kV circuit switcher three 25-kV circuit breakers one telecommunications tower associated substation equipment 25. ATCO Electric notified stakeholders, including landholders, agencies and other potential interested parties located within 800 metres from the proposed and Transmission Line 7LA10. Further, ATCO Electric notified all stakeholders located within 800 metres south, 150 metres north and 200 metres east and west of the existing Rycroft 730S Substation. ATCO Electric explained that the reason for notifying stakeholders at different distances from the Rycroft 730S Substation was because the area surrounding the substation has mixed land use with clear delineated areas for urban use and rural use. 4 Decision D (September 7, 2016)
7 26. ATCO Electric stated that it also conducted personal consultations with all stakeholders directly affected or directly adjacent to the proposed project. ATCO Electric stated that there was one stakeholder undecided and one stakeholder opposed to the proposed project. ATCO Electric stated it is in on-going communications with these stakeholders and would continue to work with them to address their concerns. The Commission did not receive any objections to the proposed project. 27. ATCO Electric stated it notified two First Nations communities due to the locations of the proposed and the Rycroft 730S Substation. ATCO Electric submitted that it did not receive any comments or concerns from any of the First Nations it notified. 28. ATCO Electric submitted an environmental protection plan for the proposed project which described the mitigation measures that would be used to reduce environmental impacts. Further, ATCO Electric stated it would construct and maintain the proposed project adhering to Alberta Environment and Parks R&R/11-03, Environmental Protection Guidelines for Transmission Lines, and in accordance with the terms and conditions of the right-of-way agreements and easements. ATCO Electric indicated that the proposed site would avoid environmentally sensitive areas and reduce the overall impact on adjacent landowners and the surrounding environment. 29. ATCO Electric explained that some equipment at the Rycroft 730S Substation site may contain polychlorinated biphenyls of unknown concentrations, however, the project did not include the removal of suspected polychlorinated biphenyl containing equipment from the substation. ATCO Electric submitted that it would conduct a visual assessment of the substation prior to construction for evidence of releases. Should evidence of staining be observed at the Rycroft 730S Substation, it would perform soil sampling for suspected contaminants and would reference the results against the Alberta Tier 1 Soil and Groundwater Remediation Guidelines. ATCO Electric added that should contaminants be found in concentrations greater than the guidelines, it would engage with Alberta Environment and Parks to discuss requirements around remediation and risk management. 30. ATCO Electric received Historical Resources Act clearance for all locations of the proposed project from Alberta Culture and Tourism. Further, ATCO Electric stated that if historical resources are discovered during construction, activity would be suspended pending notification and direction from Alberta Culture and Tourism. 31. ATCO Electric submitted a noise impact assessment summary form that stated the review was conducted in accordance with Rule 012: Noise Control for the proposed Mowat 2033S Substation. The results of the noise impact assessment summary form indicated that the proposed would not exceed permissible sound levels. ATCO Electric did not complete a noise impact assessment for the proposed alterations to the Rycroft 730S Substation because no additional noise-producing equipment was planned for the substation. 32. The cost of the proposed project was estimated by ATCO Electric to be approximately $18,814,658 (within +20 per cent/-10 per cent accuracy), allocated to the customer. Decision D (September 7, 2016) 5
8 33. Construction of the proposed project would commence in November 2016, with a proposed in-service date of June Findings 34. The Commission is satisfied that the needs identification document application filed by the AESO contains all the information required by the Electric Utilities Act, the Transmission Regulation and Rule 007: Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments. 35. No interested party demonstrated that the AESO s assessment of the need for transmission development in the Spirit River area is technically deficient or that approval of the needs identification document application is not in the public interest. Therefore, in accordance with subsection 38(e) of the Transmission Regulation, the Commission considers the AESO s assessment of the need to be correct, and approves the AESO s needs identification document application. 36. The Commission is also satisfied that ATCO Electric s facility applications comply with the information requirements prescribed in Rule 007 and are consistent with the need identified in the AESO s needs identification document application. 37. The Commission finds that the joint participant involvement program undertaken by the AESO and ATCO Electric meets the requirements of Rule The Commission is satisfied that the technical, siting and environmental aspects of the project, as submitted by ATCO Electric, fulfill the requirements of Rule The Commission accepts ATCO Electric s statement that there will be no audible noise sources added to Rycroft 730S Substation. Further, the Commission finds that the noise impact assessment summary form submitted by ATCO Electric with respect to the Mowat 2033S Substation fulfills the requirements of Rule The Commission is satisfied that there are no outstanding technical or environmental concerns associated with the project, nor are there any outstanding public or industry concerns from directly and adversely affected parties before the Commission. 41. Given the considerations discussed above, the Commission finds the project to be in the public interest pursuant to Section 17 of the Alberta Utilities Commission Act. 5 Decision 42. Pursuant to Section 34 of the Electric Utilities Act, the Commission approves the need outlined in Needs Identification Document Application A001 and grants the AESO the approval set out in Appendix 1 Needs Identification Document Approval D September 7, Decision D (September 7, 2016)
9 43. Pursuant to sections 14, 15 and 19 of the Hydro and Electric Energy Act, the Commission approves applications A002 to A005 and grants ATCO Electric the following approvals: Appendix 2 Substation Permit and Licence D September 7, 2016, to construct and operate the Mowat 2033 Substation. Appendix 3 Transmission Line Permit and Licence D September 7, 2016, to alter and operate Transmission Line 7L10. Appendix 4 Transmission Line Permit and Licence D September 7, 2016, to construct and operate Transmission Line 7LA10 Appendix 5 Substation Permit and Licence D September 7, 2016, to alter and operate the Rycroft 730S Substation. 44. The appendices will be distributed separately. Dated on September 7, Alberta Utilities Commission (original signed by) Neil Jamieson Commission Member Decision D (September 7, 2016) 7
Alberta Electric System Operator Saleski Transmission Project Needs Identification Document
Decision 2013-127 Alberta Electric System Operator Saleski Transmission Project Needs Identification Document ATCO Electric Ltd. Saleski 901S Substation and 144-kV Transmission Line 7L142 Facility Application
More informationDecision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82
Decision 21447-D01-2016 August 23, 2016 Decision 21447-D01-2016 Proceeding 21447 Application 21447-A001 August 23, 2016 Published by the: Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary,
More informationDecision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016
Decision 21481-D01-2016 October 18, 2016 Alberta Utilities Commission Decision 21481-D01-2016 Proceeding 21481 Application 21481-A001 October 18, 2016 Published by the: Alberta Utilities Commission Fifth
More informationDecision (Errata) Access Pipeline Inc. Errata to Decision Temporary Generation at Smoky Lake Pump Station.
Decision 2011-424 (Errata) Access Pipeline Inc. Errata to Decision 2011-424 Temporary Generation at Smoky Lake Pump Station January 4, 2012 The Alberta Utilities Commission Decision 2011-424 (Errata):
More informationCurrant Lake Transmission Project
Currant Lake Transmission Project September 2010 Why are you receiving this project information package? New transmission facilities are needed in the Monitor area of southeastern Alberta. ATCO Electric
More informationKettle River Transmission Project
April 2012 Why are you receiving this project information package? New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta Electric System Operator
More informationBrion Energy Corporation
Decision 20907-D01-2015 MacKay River Commercial Project October 29, 2015 Alberta Utilities Commission Decision 20907-D01-2015 MacKay River Commercial Project Proceeding 20907 Application 20907-A001 October
More informationCoalspur Mines (Operations) Ltd.
Decision 22744-D01-2017 Application for an Exemption Under Section 24 of the Hydro and Electric Energy Act October 5, 2017 Alberta Utilities Commission Decision 22744-D01-2017 Application for an Exemption
More informationBohn to Kettle River Transmission Project
April 2012 Why are you receiving this project information package? New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta Electric System Operator
More informationWal-Mart Canada Corp.
Decision 2010-596 New 500-kW Emergency Back-up Generator for Wal-Mart Perishable Foods Distribution Centre Balzac, Alberta December 17, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-596: Wal-Mart Canada
More informationDecision The City of Calgary. 30-kW Solar Power Plant. March 8, 2012
Decision 2012-065 30-kW Solar Power Plant March 8, 2012 The Alberta Utilities Commission Decision 2012-065: 30-kW Solar Power Plant Application No. 1607869 Proceeding ID No. 1563 March 8, 2012 Published
More informationWillingdon Substation Decommission
November 2012 Why are you receiving this project information package? New transmission facilities have been proposed in central east Alberta. As a result, some existing facilities are no longer needed.
More informationDecision Blaze Energy Ltd. Application for an Exemption under Section 24 of the Hydro and Electric Energy Act.
Decision 2014-108 Application for an Exemption under Section 24 of the Hydro and Electric Energy Act April 17, 2014 The Alberta Utilities Commission Decision 2014-108: Application for an Exemption under
More informationconversation SHAPE the May 2015 The AUC
SHAPE the conversation May 2015 Thickwood Hills Transmission PROJECT The Thickwood Hills Transmission Project is needed to connect planned critical transmission infrastructure, that will reinforce the
More informationGrizzly Bear Creek Wind Power Plant Connection Needs Identification Document
APPENDIX C AESO PIP Grizzly Bear Creek Wind Power Plant Connection Needs Identification Document 1.0 Participant Involvement Program (PIP) From December 2015 to May 2016, the AESO conducted a Participant
More informationAPPENDIX C - AESO PIP SUMMARY
APPENDIX C - AESO PIP SUMMARY Whitla Wind Facility Connection PIP Summary 1.0 Participant Involvement Program (PIP) 1.1 PIP Design The AESO s Participant Involvement Program (PIP) is designed to notify
More informationSOUTHWEST CALGARY RING ROAD (SWCRR)
PROJECT OVERVIEW Alberta Transportation has started planning for the construction of the SW portion of the road that will complete the Calgary Ring Road. The completion of the SWCRR requires the relocation
More informationRE: Application for Alteration of Vermilion Substation 710S 144 kv Equipment Addition, 72 kv Equipment Removal, and Fence Expansion
October 12, 2011 Don Popowich, Director, Facilities Alberta Utilities Commission Fifth Avenue Place, 4th floor, 425-1 Street SW Calgary, Alberta, T2P 3L8 Dear Sir: RE: Application for Alteration of Vermilion
More informationAPPENDIX C PARTICIPANT INVOLVEMENT PROGRAM (PIP)
APPENDIX C PARTICIPANT INVOLVEMENT PROGRAM (PIP) Stirling Wind Project Connection PIP Summary 1.0 Participant Involvement Program (PIP) 1.1 PIP Design The AESO s Participant Involvement Program (PIP) is
More informationReactive Power Requirements and Financial Compensation. Addendum to Draft Final Proposal
Reactive Power Requirements and Financial Compensation July 21, 2016 Table of Contents 1. Introduction... 3 2. Changes to Proposal... 4 3. Plan for Stakeholder Engagement... 4 4.... 4 6. Next Steps...
More informationElectric system improvements near you
Electric system improvements near you Red Deer Area Transmission Development Stage 1 substation upgrades April 2011 Volume 1 Did you know? The average four-person family in Alberta today has 20 instant-on
More informationIncluded in this Stakeholder Information Package:
Who can you contact for more information? Yellowhead Area Transmission Reinforcement: TERA Environmental Consultants Dave Sare Phone: 403-538-5734 Email: dsare@teraenv.com Drayton Valley Area AltaLink
More informationDFO STATEMENT OF NEED REPORT
APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading
More informationDirect Energy Regulated Services
Decision 23986-D01-2018 Application for True-Up of the 2017 and 2018 Interim Rates for the Default Rate Tariff and the Regulated Rate Tariff December 4, 2018 Alberta Utilities Commission Decision 23986-D01-2018
More informationENMAX Power Corporation
Decision 23157-D01-2018 Downtown Calgary Transmission Reinforcement Project November 9, 2018 Alberta Utilities Commission Decision 23157-D01-2018 Downtown Calgary Transmission Reinforcement Project Proceeding
More informationUniversity of Alberta
Decision 2012-355 Electric Distribution System December 21, 2012 The Alberta Utilities Commission Decision 2012-355: Electric Distribution System Application No. 1608052 Proceeding ID No. 1668 December
More informationDecision D Finlay Group. Complaint Regarding FortisAlberta Inc. Distribution Line Rebuild Project. February 3, 2016
Decision 20799-D01-2016 Complaint Regarding FortisAlberta Inc. Distribution Line Rebuild Project February 3, 2016 Alberta Utilities Commission Decision 20799-D01-2016 Proceeding 20799 Application 20799-A001
More informationWainwright 51S Substation Connection Enhancement Needs Identification Document
APPENDIX C AESO PIP Wainwright 51S Substation Connection Enhancement Needs Identification Document 1.0 Participant Involvement Program (PIP) From October 2015 to July 2016 the AESO conducted a Participant
More informationDunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study
` Dunvegan Hydroelectric Project For Glacier Power Limited Preliminary Interconnection Study Prepared by Pung Toy, P. Eng. and Ata Rehman, P. Eng. September 24, 2004 Table of Contents Table of Contents...
More informationWOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017
WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 TODAY WE LL TALK ABOUT Our challenges and how we re meeting them Why we re building this project Our planning process and considerations
More informationFOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT
FOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT Proposed 138kV Transmission Line Photo courtesy of The City of Calgary Project Overview The demand for power is increasing as Calgary continues
More informationFOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT
FOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT Proposed 138kV Transmission Line Photo courtesy of The City of Calgary Project Overview The demand for power is increasing as Calgary continues
More informationDecision on Merced Irrigation District Transition Agreement
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation
More informationAlberta Energy and Utilities Board. Application to Construct and Operate Transmission Facilities
Alberta Energy and Utilities Board Application to Construct and Operate Transmission Facilities Albian Sands Energy Inc. August 17, 2007 APPLICATION Shell Canada Limited (Shell), as operator, on behalf
More informationPenn West Petroleum Ltd. Well Blowout W5M August 17, 2010
Penn West Petroleum Ltd. Well Blowout 14-20-065-10W5M August 17, 2010 ERCB Investigation Report August 24, 2011 ENERGY RESOURCES CONSERVATION BOARD ERCB Investigation Report: Penn West Petroleum Ltd.,
More informationDawes Substation Project
Dawes Substation Project Why are you receiving this project information package? March 2013 New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta
More informationPowering Sydney s Future
Powering Sydney s Future Frequently Asked Questions December 2017 Project background Q: Why is this project needed? A: Inner Sydney is one of the most critical parts of the NSW electricity network. However,
More informationJoint Operating Procedures for First Nations Consultation on Energy Resource Activities
Joint Operating Procedures for First Nations Consultation on Energy Resource Activities October 31, 2018 Contents Revision History... iv Definitions of Key Terms... v 1 Background... 1 2 Roles and Responsibilities...
More informationINTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY
INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY Table of Contents Chapter 1. Purpose and scope. Pg 3 Chapter 2. Application
More informationMerger of the generator interconnection processes of Valley Electric and the ISO;
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric
More informationwelcome to the BC Hydro community open house
welcome to the BC Hydro community open house Dawson Creek/ Chetwynd Area Transmission ProjecT Open House welcome Dawson Creek/Chetwynd Area Transmission Project (DCAT) The purpose of this open house is
More informationSPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN
SPN High Value Project PO Route RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN Document History Version Date Details Originator V0.1 20/06/2013 Initial version Chris Winch V0.2
More informationSouthern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1
Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide Version 1.1 October 21, 2016 1 Table of Contents: A. Application Processing Pages 3-4 B. Operational Modes Associated
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:
More information100 MW Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility
More informationPublic Information Centre
Junction Street Wastewater Pumping Station & Forcemain Schedule B Municipal Class Environmental Assessment Study Public Information Centre June 28, 2017. 6:00 to 8:00 pm. The Burlington Performing Arts
More informationJCP&L Verbatim Response to Middletown Township s Questions
JCP&L Verbatim Response to Middletown Township s Questions Township officials sent 13 questions about the proposed Monmouth County Reliability Project to JCP&L on June 10 th. JCP&L provided direct responses
More informationUmatilla Electric Cooperative Net Metering Rules
Umatilla Electric Cooperative Net Metering Rules Version: July 2017 Umatilla Electric Cooperative NET METERING RULES Rule 0005 Scope and Applicability of Net Metering Facility Rules (1) Rule 0010 through
More informationCONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation
CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent
More informationNew 115 kv Disconnect Switches at Bloomsburg MTS
115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115
More informationFebruary 13, Docket No. ER ; ER Response to Request for Additional Information
California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent System
More informationMILLIGAN SOLAR PROJECT
February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission
More informationSTATE IMPLEMENTATION PLAN CREDIT FOR EMISSION REDUCTIONS GENERATED THROUGH INCENTIVE PROGRAMS (Adopted June 20, 2013)
RULE 9610 STATE IMPLEMENTATION PLAN CREDIT FOR EMISSION REDUCTIONS GENERATED THROUGH INCENTIVE PROGRAMS (Adopted June 20, 2013) 1.0 Purpose The purpose of this rule is to provide an administrative mechanism
More informationAPPENDIX F: Project Need and Description
APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was
More informationProject Title: Lowertown Ballpark (CHS Field) Solar Arrays Contract Number: EP4-34 Milestone Number: 1 Report Date: June 21, 2016
DEPARTMENT OF PARKS AND RECREATION DESIGN AND CONSTRUCTION CITY OF SAINT PAUL Mayor Christopher B. Coleman 400 City Hall Annex 25 West 4 th Street Saint Paul, Minnesota 55102 www.stpaul.gov/parks Telephone:
More information15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
More informationWestern NY Public Policy Transmission Planning Report
Western NY Public Policy Transmission Planning Report Dawei Fan Supervisor, Public Policy and Interregional Planning Business Issues Committee September 12, 2017 Operating Committee September 15, 2017
More informationThis page is intentionally left blank.
This page is intentionally left blank. Bipole III Southern Ground Electrode Line Route Selection Introduction Manitoba Hydro has recently selected a route for the southern ground electrode line (Map 1).
More informationMICRO-GENERATION NOTICE SUBMISSION GUIDELINE
www.auc.ab.ca MICRO-GENERATION NOTICE SUBMISSION GUIDELINE (Version 2.0) September 20, 2017 Table of Contents 1. Introduction... 2 2. Purpose... 2 3. Differences between micro-generation and distributed
More informationSheridan 2085S Substation. Needs Identification Document
APPENDIX C AESO PIP Sheridan 2085S Substation Needs Identification Document 1.0 Participant Involvement Program (PIP) From May 2016 to October 2016, the AESO conducted a Participant Involvement Program
More informationFunctional Specification Revision History
Functional Specification Revision History Revision Description of Revision Author Date B0 For comments Yale Zhou January 26, 2016 B1 Updated as per comments Yale Zhou February 1, 2016 Final issuance Yale
More information15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
More informationExplaining AER Setbacks
Explaining AER Setbacks This EnerFAQs explains setbacks in the energy industry, how they are determined, and how they may affect Albertans and their communities. What is a setback? A setback is the absolute
More informationThe Grid Link Project. Summary of the Report for the Independent Expert Panel
The Grid Link Project Summary of the Report for the Independent Expert Panel Who are EirGrid - and what do we do? EirGrid is responsible for a safe, secure and reliable supply of electricity: now and in
More informationHEARING STATEMENT - PALMERSTON NORTH CITY COUNCIL PLAN CHANGE 15A - RURAL ZONE (GENERAL ISSUES)
11111 TRANSPOWER Keeping Ihe energy flowing Sarah Shand Phone: 04 590 7434 Email: sarah.shand@transool.ler.co.nz Transpower House 96 The Terrace PO Box 1021 Wellington 6140 New Zealand p 6444957000 F 6444957]00
More informationSale of land at Old Quarry site, Westmount Gardens to Jersey Electricity plc for creation of electricity substation
Sale of land at Old Quarry site, Westmount Gardens to Jersey Electricity plc for creation of electricity substation For consideration by the Parish Assembly on 27 November 2013 at 7.00pm PARISH OF ST HELIER
More informationBLUMENORT TRANSMISSION PROJECT
APPLICATION TO THE ALBERTA UTILITIES COMMISSION BLUMENORT TRANSMISSION PROJECT March 2014 10035-105 Street P.O. Box 2426 Station Main Edmonton, Alberta T5J 2V6 INDEX OF ATTACHMENTS 1 THROUGH 13 ATTACHMENT
More informationAppendix D Black Hills Project Summary
Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain
More informationWELCOME. New Septage Waste Haulage Receiving Station Municipal Class Environmental Assessment (Class EA)
WELCOME New Septage Waste Haulage Receiving Station Municipal Class Environmental Assessment (Class EA) Public Information Centre (PIC) No. 1 Thursday November 9 th, 2017 6:00pm-8:00pm Please SIGN IN to
More informationHydroGenerations PROGRAM HANDBOOK
HydroGenerations PROGRAM HANDBOOK TABLE OF CONTENTS Please ensure you are reading the most recent version of this handbook by visiting the NV Energy website, www.nvenergy.com/hydro. Contents HydroGenerations
More informationA member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.
Electric Tariff _2nd Revised Sheet No. 72 Filed with Iowa Utilities Board Cancels _1st Sheet No. _72 Cooperative is a member of Central Iowa Power Cooperative (CIPCO), a generation and transmission cooperative
More informationAmbient PM 10 Monitoring Sechelt, B.C Update
Ministry of Environment LOWER MAINLAND REGION Ambient PM 10 Monitoring Sechelt, B.C. 2004-2005 Update E N V I R O N M E N T A L Q U A L I T Y Library and Archives Canada Cataloguing in Publication Data
More informationCOMMERCIAL SCHEME Approval No
COMMERCIAL SCHEME Approval No. 12806 MADE at the City of Calgary, in the Province of Alberta, on ALBERTA ENERGY REGULATOR IN THE MATTER of a commercial scheme of Imperial Oil Resources Ventures Limited
More informationGenerating unit functional document submission form
Generating unit functional document submission form The below form must be completed and returned to generator.reports@aeso.ca. Supporting information to assist generating unit owners to complete this
More informationAPPENDIX E: ELECTRIC AND MAGNETIC FIELDS MANAGEMENT PLAN
APPENDIX E: Final EIS/EIR E-1 FINAL ENVIRONMENTAL IMPACT STATEMENT/ENVIRONMENTAL IMPACT REPORT APPENDIX E: THIS PAGE INTENTIONALLY LEFT BLANK E-2 May 2011 LOS ANGELES DEPARTMENT OF WATER AND POWER Barren
More informationEast Avenue and Queen City Substation Improvement Project
East Avenue & Queen City Substation Improvement Project VIA FIRST CLASS MAIL August 29, 2017 Judith C. Whitney, Clerk Vermont Public Utility Commission 112 State Street, 4 th Floor Montpelier, VT 05620-2701
More informationDUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY
DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION
More informationProposed Dounreay - Mybster 275 kv / 132 kv
Background Scottish Hydro-Electric Transmission Ltd (SHETL) is proposing a new 275 kilovolt (kv) (1 kilovolt = 1000volts) double circuit overhead line (OHL) between the Dounreay sub station and the new
More informationTRANSMISSION PLANNING CRITERIA
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing
More informationTEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY
TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF
More informationInactive Well Compliance Program (IWCP)
Inactive Well Compliance Program (IWCP) Year Two Final Report In addition to Bulletin 2014-19, Alberta Energy Regulator (AER) July 2017 The Alberta Energy Regulator s (AER) Inactive Well Compliance Program
More information120/25-kV Gracefield Substation and 120-kV Lines
Note: kv is the abbreviation for kilovolt, which is equal to 1,000 volts. 120/25-kV Substation and 120-kV Lines INFORMATION ON THE SOLUTION SELECTED November 2015 To meet growing demand for electricity,
More informationWELLINGTON, NEW ZEALAND. PURSUANT to sections 152, 155(a) and (e) and 158(a)(i) of the Land Transport Act 1998
WELLINGTON, NEW ZEALAND PURSUANT to sections 152, 155(a) and (e) and 158(a)(i) of the Land Transport Act 1998 I, Gerry Brownlee, Minister of Transport, HEREBY make the following ordinary Rule: Land Transport
More informationRenewable Generation Electrical Infrastructure and Grid Connection Services Provided by Power Systems Project and Consultancy Services (PCS) Ltd
Renewable Generation Electrical Infrastructure and Grid Connection Services Provided by Power Systems Project and Consultancy Services (PCS) Ltd Power Systems Project and Consultancy Services (PCS) Ltd
More informationCity of Palo Alto (ID # 6416) City Council Staff Report
City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building
More informationK2 Wind Community Liaison Committee Meeting #2 Wednesday, May 28, 2014
K2 Wind Community Liaison Committee Meeting #2 Wednesday, May 28, 2014 K2 Wind Background The K2 Wind Power Project is a 270 megawatt (MW) wind project being developed in the Township of Ashfield-Colborne-Wawanosh
More informationGeorgia Transmission Corporation Georgia Systems Operations Corporation
Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia
More informationSOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015
SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment
More informationGuideline for Parallel Grid Exit Point Connection 28/10/2010
Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND
More informationProposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013
Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in 2015 Stakeholder Webconference February 28, 2013 Page 2 Merced Irrigation District (Merced) Background Merced Irrigation
More information/ Planning and Zoning Staff Report Lonestar Land, LLC. - Rezone, RZ
/ Planning and Zoning Staff Report Lonestar Land, LLC. - Rezone, RZ2018-0019 Hearing Date: October 18, 2018 Development Services Department Applicant: Lonestar Land, LLC. Representative: Lance Warnick
More informationHIGHWAY 28 FUNCTIONAL DESIGN
HIGHWAY 28 FUNCTIONAL DESIGN PUBLIC OPEN HOUSE #1 WEDNESDAY, MARCH 12, 2014 Stantec Presenters: Brad Vander Heyden, Project Engineer Neal Cormack, Project Manager Dave Parker, Project Engineer Beth Thola,
More informationCUSTOMER/ TWIN ARROWS PROJECT
A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset
More informationSTATE OF NEW HAMPSHIRE Inter-Department Communication
STATE OF NEW HAMPSHIRE Inter-Department Communication DATE: February 11, 2010 AT (OFFICE): NHPUC FROM: Torn Frantz Director, Electric Division SUBJECT: DE 09-277: Petition by Public Service Company of
More informationTHE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS
THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive
More informationTransmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014
Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder
More informationChirmorie Wind Farm Grid Connection
Chirmorie Wind Farm Grid Connection Welcome Welcome to this public exhibition regarding our proposals to construct a new 132 kilovolt (kv) overhead line (OHL) supported by wood poles to connect the proposed
More informationDRAFT April 9, STATE IMPLEMENTATION PLAN CREDIT FOR EMISSION REDUCTIONS GENERATED THROUGH INCENTIVE PROGRAMS (Adopted [adoption date])
RULE 9610 STATE IMPLEMENTATION PLAN CREDIT FOR EMISSION REDUCTIONS GENERATED THROUGH INCENTIVE PROGRAMS (Adopted [adoption date]) 1.0 Purpose The purpose of this rule is to provide an administrative mechanism
More informationAutomated and Electric Vehicles Bill
Automated and Electric Vehicles Bill SECOND MARSHALLED LIST OF AMENDMENTS TO BE MOVED IN COMMITTEE OF THE WHOLE HOUSE Amendment No. [Amendments marked * are new or have been altered] Clause 8 37 Page 5,
More informationNew Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities
New Ulm Public Utilities Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities INDEX Document Review and History... 2 Definitions... 3 Overview... 3 Application
More information