EE 456 Design Project
|
|
- Cathleen Gilbert
- 5 years ago
- Views:
Transcription
1 F-2014 EE 456 Design Project PROJECT REPORT MALUWELMENG, CONNIE SHARP, MEGAN
2 Table of Contents Introduction... 2 Assignment I... 2 Setup... 2 Simulation... 2 Assignment II... 3 Problems... 3 Solution... 3 Assignment III... 3 Adding Load... 3 Resolving System... 4 System Cost... 4 Conclusion... 5 References... 5 Appendix I System Map... 6 Appendix II Impedance... 7 Appendix III Cost Data... 8 Line Costs... 8 Capacitor/Inductor Bank Costs... 8 Appendix IV One-line Diagrams... 9 Assignment I... 9 Assignment II Assignment III Appendix V Assignment I Results Basic Plan Line 5-11 Down... 13
3 Introduction For this project, PSS/E 33 was used as the power flow analysis program. Three assignments were necessary for the project; Assignment I was step-by-step basics of PSS/E 33, Assignment II included the design and modification of a basic transformer system with 161kV and 69kV lines, Assignment III required an additional 40MW load bus to be added as well as an overall load increase of 30% to the existing system. Using PSS/E 33, the per unit bus voltages and real and reactive power were simulated for the given system. Through observation and tracing the power flow, necessary modifications were identified, changed, and finally simulated again. This project was an insightful look at how the concepts shown in EE456 (Power Systems Analysis I) can be applied to realistic transmission systems that require improvements and modifications as the needs for power change. Assignment I Setup The first portion of the project consisted of setting up the Eagle Power System in PSS/E 33. Seventeen buses were represented of which three were generators (including a slack bus). The remaining buses were all load buses. Most of the buses in the system had a base power of 161 kilo-volts. Two buses had a base power of 69 kilo-volts. Since all the generators operated at 161kV, the base power of those two buses was achieved by two step-down transformers in the system. Each transformer had a secondary winding of 1.07 turns, impedance of per unit. Then, realistic transmission lines were added to the model. That is, lines had resistance, reactance, and charging capacities. These parameters were based on the type of conductor used, the length of the line, and the base voltages of the buses being connected. After all of the buses were connected, specifics of each of the buses were added. Load data (real and reactive) were added to all of the load buses. Similarly, maximum and minimum values for both real and reactive power were added to the generator buses. They each could generate a maximum of 430MW of real power and reactive power within the range of -100MVAR to 250MVAR. Simulation With the Eagle Power System all modeled in PSS/E, a simulation was run. The simulation used the Full- Newton Raphson method. Just like hand calculations in which there is no specified start, the system was simulated starting with a flat start. The initial simulation just looked at the results without any changes to the system. The resulting voltages and angles for each bus can be seen in Appendix V. Also found there are the real and reactive power flows, currents, and generator power outputs (real and reactive).
4 With results of the initial simulation observed, a contingency plan was simulated. In this case, it was assumed that the line between buses five and eleven was down for some unknown reason. As was expected, the voltages and real power flows at these two buses changed the most between the two simulations. Bus five had a 1.78kV difference in voltage magnitudes between the two simulations whereas bus eleven had a 1.95kV. Further comparisons showed that bus five was essentially absorbing real power from bus 11. With this connection gone, bus five started to absorb more from bus eight (double the amount in the initial simulation). Because bus eleven did not have to feed bus five any more, it absorbed less from generators one and two in the second scenario. Assignment II Problems Once the basic case was set up and simulated in PSS/E, we found that not all of our bus voltage values fell within the desired 0.96~1.04 per unit range. Bus 4, bus 5, and bus 7 all had voltages slightly below 0.96 per unit. After examining the system map, we realized that these buses were all in the urban areas and determined that adding a 100MVAR capacitor bank to bus 5 may be a solution. In a couple of the contingency cases (both when Line and when Line were simulated as offline), the bus voltages for bus 10 and bus 13 were too low. When capacitor banks were added to improve the power factor, they fixed this issue but caused bus voltages for surrounding buses, such as buses 16 or 17, to jump to a higher voltage (somewhere around per unit.) Solution After adding the 100MVAR capacitor bank mentioned above into our simulation, it was determined that this fixed all of the issues with low bus voltages in the basic case. It also fixed many similar issues in contingency cases for buses in the urban area of the system. However, there was still the issue of the low bus voltages in buses 10 and 13 when Line and Line are simulated as offline. Since adding the two 15MVAR capacitor banks to buses 10 and 13 made bus voltages for buses 16 and 17 too high, we decided to add two 10MVAR inductor banks to 16 and 17 as well. This would allow the power factor to improve at buses 10 and 13 while keeping the bus voltages within range for buses 16 and 17. Both the two 15MVAR capacitor banks and the two 10MVAR inductor banks were switch banks - meaning that they are only live for the simulation when Line and Line are offline. In all other cases, the only bank that is live is the 100MVAR capacitor bank at bus 5. With these inductor and capacitor banks added, we were able to stay in the desired 0.96~1.04 per unit voltage range for all buses in the basic case and within the emergency 0.90~1.05 per unit voltage for all the contingency cases. Assignment III Adding Load Both of the previous portions were baby steps to the actual design project. With the Eagle Power System stable, additional loads were added to the system. Each existing load bus saw a 30% increase in both real and reactive powers. In addition to these changes, a steel mill was added to the grid. Essentially, it was treated as a sixteenth load bus operating at 40MW with a unity power factor.
5 A new bus meant new lines. Because the mill was situated near generator two and bus fourteen, it seemed a cost efficient idea to just connect the steel mill to these two buses. However, it was decided that running the second line to generator one instead of bus 14 would provide a more stable system overall. The line lengths connecting the mill to generators one and two were and miles respectively. This big variance in length led to the decision of connecting to generator two with a Dove conductor (smallest available for a 161kV base voltage). The mill was then connected to generator one with a Drake conductor to account for the longer distance. Resolving System Once all the extra parameters were added to the system, an analysis was done on the system. A basic case was run as well as all the simple contingency plans that had been done for the system before the load change. Based off of these results, it was determined that all the switch capacitor and inductor banks added to the system previously would be live at all times. This change showed that all of the bus voltages for almost all cases (basic and contingencies) fell in the 0.96~1.04 per unit (for the basic) and 0.90~1.05 per unit (for contingencies) ranges desired to keep the system stable. Also, all reactive power flows fell within the limit set with a minimum of -100MVAR and a maximum of 250MVAR. However, there were violations observed when analyzing system results. When Line was simulated to be offline, there was a problem with bus 10 having a voltage just below the lower limit. To fix this issue, a 2.5MVAR capacitor bank was switched on once this line went down to increase the power factor at bus ten for this scenario. The basic case in addition to a few of the contingencies also showed voltage issues in the urban areas of the system despite the 100MVAR capacitor bank added previously. Because of this, another 100MVAR capacitor bank was added to bus five. This seemed to stabilize all remaining issues. System Cost To stabilize the initial system, it was decided that the system needed to include three capacitor banks and two inductor banks. Although only given a quote for capacitor banks, it was assumed that costs for inductor banks would be relatively the same. This brought initial costs to $60,000 for each bank for installations. Then, actual banks were priced at $300 per 100kVAR which brought the total cost of stabilizing the system to $750,000. Once the new loads and bus were added, new costs were added. Costs for connecting the steel mill to the grid were incurred along with costs for re-stabilizing the system. Using the Dove and Drake conductors as mentioned in the rural area the steel mill was located led to a cost of $106,000 and $115,000 per mile for the respective conductors. This resulted in a total line cost of about $4.784 million. Lastly, two more capacitor banks were added to stabilize the modified system. With the same cost basis as used for the original system, the additional 100MVAR and 2.5MVAR banks led to a cost of $427,500.
6 The grand total for all the modifications for the system was approximately $5.961 million as outlined in Appendix II. Conclusion It was decided after the initial system analysis that if the most cost efficient solution would consist of a few capacitor or inductor banks. Line additions were kept to a minimum just because the additional lines connecting the steel mill to the grid proved to be the bulk of the costs incurred for the system modifications. It also made sense to let the voltage base for the steel mill be 161kV based off of its electrical closeness 161kV buses. To give it a 69kV base voltage would lead to installing transformers at one of the nearby buses or routing a line from the existing transformers on the other side of the grid. Both options would have well exceeded the already high costs incurred by simply adding 161kV lines. Without a set systematic way of resolving violations within the system, it was difficult to create any kind of medication. The realization of tracing the power flow to help determine where each bus was obtaining its power from helped in producing better educated guesses as to what should be done stabilize the system. This design project provided a simple but very insightful glance transmission planning. One cannot simply make a change on the grid without seeing how the rest of the system is affected. Because a grid is interlocked, each bus and/or line affects another one way or another. References Bergen, A.R. and V. Vittal, 1999: Power Systems Analysis (2 nd Edition). Colorado State University, n.d.: Introduction to PSS/E. [Available online at
7 Appendix I System Map 18
8 Appendix II Impedance Line Conductor Type Resistance 1 Reactance 2 Charging Drake Drake Drake Drake Drake Drake Drake Dove Drake Drake Drake Dove Drake Dove Dove Dove Drake Drake Drake Hawk Hawk Hawk Resistance is calculated by using R/mile at 50 C in Appendix A8.1 of Bergen and Vittal s Power Systems Analysis. 2 Reactance in the line was calculated by using X/mile in Appendix A8.1 of Bergen and Vittal s Power Systems Analysis. 3 Charging factor was calculated by using (x a+x d)-mile in which x a was obtained from Appendix A8.1 and x d from A8.3 of Bergen and Vittal s Power Systems Analysis. Also taken into consideration was the base voltages of the buses.
9 Appendix III Cost Data Line Costs Conductor Size Cost Basis (161kV Rural) Line Length Total Cost of Line Dove $106, miles $1,650,420 Drake $115, miles $3,133,750 $4,784,170 Capacitor/Inductor Bank Costs Bus Installation Cost Capacity Cost Basis Bank Size Total Bank Cost 5 $60,000 $300/100kVAR 100,000 kvar $360,000 5 $60,000 $300/100kVAR 100,000 kvar $360, $60,000 $300/100kVAR 2,500 kvar $67, $60,000 $300/100kVAR 15,000 kvar $105, $60,000 $300/100kVAR 15,000 kvar $105,000 16* $60,000 $300/100kVAR 10,000 kvar $90,000 17* $60,000 $300/100kVAR 10,000 kvar $90,000 $1,177,500 *Indicative of inductor banks.
10 Appendix IV One-line Diagrams Assignment I
11 Assignment II
12 Assignment III
13 Appendix V Assignment I Results Basic Plan
14 Line 5-11 Down
Electrical Transmission System Analysis EE 456 project. Team Members Abdulaziz Almarzouqi Hamzah Abeer
Electrical Transmission System Analysis EE 456 project Team Members Abdulaziz Almarzouqi Hamzah Abeer Due December 14, 2012 Changes: 1. 134MW Wind added 2. N-1 Contingency limits changed to.95-1.05 3.
More informationPower System Economics and Market Modeling
Power System Economics and Market Modeling M5: Security Constrained Optimal Power Flow 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com http://www.powerworld.com
More informationProject #148. Generation Interconnection System Impact Study Report
Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection
More informationSIEMENS POWER SYSTEM SIMULATION FOR ENGINEERS (PSS/E) LAB1 INTRODUCTION TO SAVE CASE (*.sav) FILES
SIEMENS POWER SYSTEM SIMULATION FOR ENGINEERS (PSS/E) LAB1 INTRODUCTION TO SAVE CASE (*.sav) FILES Power Systems Simulations Colorado State University The purpose of ECE Power labs is to introduce students
More informationPower System Economics and Market Modeling
Power System Economics and Market Modeling M5: Security Constrained Optimal Power Flow 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com http://www.powerworld.com
More informationFinal Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description
Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing
More informationTargeted Application of STATCOM Technology in the Distribution Zone
Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric
More informationIntroduction to PowerWorld Tutorial Created by the University of Illinois at Urbana-Champaign TCIPG PMU Research Group 1
1 Introduction to PowerWorld Tutorial Created by the University of Illinois at Urbana-Champaign TCIPG PMU Research Group 1 INTRO: In this tutorial, we will modify the following 3-bus system. In this system,
More informationTutorial. Running a Simulation If you opened one of the example files, you can be pretty sure it will run correctly out-of-the-box.
Tutorial PowerWorld is a great and powerful utility for solving power flows. As you learned in the last few lectures, solving a power system is a little different from circuit analysis. Instead of being
More informationXXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS
XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS El Paso Electric Company System Operations Department System Planning
More informationPOWER FLOW SIMULATION AND ANALYSIS
1.0 Introduction Power flow analysis (also commonly referred to as load flow analysis) is one of the most common studies in power system engineering. We are already aware that the power system is made
More informationABB POWER SYSTEMS CONSULTING
ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February
More informationIslanding of 24-bus IEEE Reliability Test System
Islanding of 24-bus IEEE Reliability Test System Paul Trodden February 14, 211 List of Figures 1 24-bus IEEE RTS, with line (3,24) tripped and buses 3,24 and line (3,9) uncertain....................................
More informationAbstract. Executive Summary. Emily Rogers Jean Wang ORF 467 Final Report-Middlesex County
Emily Rogers Jean Wang ORF 467 Final Report-Middlesex County Abstract The purpose of this investigation is to model the demand for an ataxi system in Middlesex County. Given transportation statistics for
More informationDynamic Control of Grid Assets
Dynamic Control of Grid Assets Panel on Power Electronics in the Smart Grid Prof Deepak Divan Associate Director, Strategic Energy Institute Director, Intelligent Power Infrastructure Consortium School
More informationIslanding of 24-bus IEEE Reliability Test System
Islanding of 24-bus IEEE Reliability Test System Paul Trodden February 17, 211 List of Figures 1 24-bus IEEE RTS, with line (3,24) tripped and buses 3,24 and line (3,9) uncertain....................................
More informationTHE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS
THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive
More informationCHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK
91 CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK CHAPTER CONTENTS: 5.1 INTRODUCTION 5.2 CONDUCTION OF VARIOUS POWER FLOW STUDIES ON THE MODEL 5.3 EXPERIMENTS CONDUCTED FOR VARIOUS POWER FLOW
More informationECE 740. Optimal Power Flow
ECE 740 Optimal Power Flow 1 ED vs OPF Economic Dispatch (ED) ignores the effect the dispatch has on the loading on transmission lines and on bus voltages. OPF couples the ED calculation with power flow
More informationStability Study for the Mt. Olive Hartburg 500 kv Line
Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.
More informationEL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS
EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004
More informationEl PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS
El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the
More informationECEN 667 Power System Stability Lecture 19: Load Models
ECEN 667 Power System Stability Lecture 19: Load Models Prof. Tom Overbye Dept. of Electrical and Computer Engineering Texas A&M University, overbye@tamu.edu 1 Announcements Read Chapter 7 Homework 6 is
More information: ANIMATION OF A POWER SYSTEM USING POWERWORLD SIMULATOR
2006-1767: ANIMATION OF A POWER SYSTEM USING POWERWORLD SIMULATOR Frank Pietryga, University of Pittsburgh-Johnstown FRANK W. PIETRYGA is an Assistant Professor at the University of Pittsburgh at Johnstown.
More informationEL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION
EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION El Paso Electric Company System Operations Department System Planning Section August 2006 I. INTRODUCTION The
More informationAppendix D Black Hills Project Summary
Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain
More informationEnhancement of Power Quality in Transmission Line Using Flexible Ac Transmission System
Enhancement of Power Quality in Transmission Line Using Flexible Ac Transmission System Raju Pandey, A. K. Kori Abstract FACTS devices can be added to power transmission and distribution systems at appropriate
More informationPOWER DISTRIBUTION SYSTEM ANALYSIS OF URBAN ELECTRIFIED RAILWAYS
POWER DISTRIBUTION SYSTEM ANALYSIS OF URBAN ELECTRIFIED RAILWAYS Farhad Shahnia Saeed Tizghadam Seyed Hossein Hosseini farhadshahnia@yahoo.com s_tizghadam@yahoo.com hosseini@tabrizu.ac.ir Electrical and
More informationXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY Short Circuit Analysis System Operations Department System Planning Section March 2001 I. Introduction XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
More informationELG4125: Flexible AC Transmission Systems (FACTS)
ELG4125: Flexible AC Transmission Systems (FACTS) The philosophy of FACTS is to use power electronics for controlling power flow in a transmission network, thus allowing the transmission line to be loaded
More informationA Method for Determining the Generators Share in a Consumer Load
1376 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 15, NO. 4, NOVEMBER 2000 A Method for Determining the Generators Share in a Consumer Load Ferdinand Gubina, Member, IEEE, David Grgič, Member, IEEE, and Ivo
More informationTransWest Express Project
TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company
More informationResearch on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC
Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC Rong Cai, Mats Andersson, Hailian Xie Corporate Research, Power and Control ABB (China) Ltd. Beijing, China rong.cai@cn.abb.com,
More informationFIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION
PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection
More informationEskisehir Light Train- Correcting Capacitive
Case Study-Estram Light Train Eskisehir Light Train- Correcting Capacitive Power Factor Eskisehir, a city in the Anatolia region of Turkey is located in an area inhabited since at least 3500 BCE- the copper
More informationDISTRIBUTED GENERATION FROM SMALL HYDRO PLANTS. A CASE STUDY OF THE IMPACTS ON THE POWER DISTRIBUTION NETWORK.
DISTRIBUTED GENERATION FROM SMALL HYDRO PLANTS. A CASE STUDY OF THE IMPACTS ON THE POWER DISTRIBUTION NETWORK. N. Lettas*, A. Dagoumas*, G. Papagiannis*, P. Dokopoulos*, A. Zafirakis**, S. Fachouridis**,
More informationINTRODUCTION. In today s highly complex and interconnected power systems, mostly made up of thousands of buses and hundreds of generators,
1 INTRODUCTION 1.1 GENERAL INTRODUCTION In today s highly complex and interconnected power systems, mostly made up of thousands of buses and hundreds of generators, there is a great need to improve electric
More informationINSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT
INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT Prof. Chandrashekhar Sakode 1, Vicky R. Khode 2, Harshal R. Malokar 3, Sanket S. Hate 4, Vinay H. Nasre 5, Ashish
More informationChapter 3.1: Electrical System
Part-I: Objective type Questions and Answers Chapter 3.1: Electrical System 1. The heat input required for generating one kilo watt-hour of electrical output is called as. a) Efficiency b) Heat Rate c)
More informationCost Benefit Analysis of Faster Transmission System Protection Systems
Cost Benefit Analysis of Faster Transmission System Protection Systems Presented at the 71st Annual Conference for Protective Engineers Brian Ehsani, Black & Veatch Jason Hulme, Black & Veatch Abstract
More informationCOMPARISON OF DIFFERENT SOFTWARE PACKAGES IN POWER FLOW AND SHORT-CIRCUIT SIMULATION STUDIES. A Project
COMPARISON OF DIFFERENT SOFTWARE PACKAGES IN POWER FLOW AND SHORT-CIRCUIT SIMULATION STUDIES A Project Presented to the faculty of the Department of Electrical and Electronic Engineering California State
More informationA Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design
A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design Presented at the 2018 Transmission and Substation Design and Operation Symposium Revision presented at the
More informationInterconnection System Impact Study Report Request # GI
Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010
More informationA Transient Free Novel Control Technique for Reactive Power Compensation using Thyristor Switched Capacitor
A Transient Free Novel Control Technique for Reactive Power Compensation using Thyristor Switched Capacitor 1 Chaudhari Krunal R, 2 Prof. Rajesh Prasad 1 PG Student, 2 Assistant Professor, Electrical Engineering
More informationUpdated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers
Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,
More informationECE 5671/6671 Lab 5 Squirrel-Cage Induction Generator (SCIG)
ECE 5671/6671 Lab 5 Squirrel-Cage Induction Generator (SCIG) 1. Introduction 1.1 Objectives The objective of this lab is to connect a SCIG generator directly to the grid and measure the power produced
More informationLarge Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project
Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives Addendum San Juan Major Project Tri-State Generation and Transmission Association Power System Planning December, 2008
More informationPower Consump-on Management and Control for Peak Load Reduc-on in Smart Grids Using UPFC
1 Power Consump-on Management and Control for Peak Load Reduc-on in Smart Grids Using UPFC M. R. Aghaebrahimi, M. Tourani, M. Amiri Presented by: Mayssam Amiri University of Birjand Outline 1. Introduction
More informationFeasibility Study for the Q MW Solar Project
Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC
More informationTieline Controls in Microgrid Applications
Tieline Controls in Microgrid Applications M. Adamiak GE Digital Energy, Multilin K.Bahei-Eldin GE Global Research, S.Bose, GE Global Research, J.deBedout GE Global Research, Y.Liu, GE Global Research,
More informationExternal Hard Drive: A DFMA Redesign
University of New Mexico External Hard Drive: A DFMA Redesign ME586: Design for Manufacturability Solomon Ezeiruaku 4-23-2013 1 EXECUTIVE SUMMARY The following document serves to illustrate the effects
More informationIntroduction to PowerWorld Simulator: Interface and Common Tools
Introduction to PowerWorld Simulator: Interface and Common Tools I10: Introduction to Contingency Analysis 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com http://www.powerworld.com
More informationCHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM
61 CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 3.1 INTRODUCTION The modeling of the real time system with STATCOM using MiPower simulation software is presented in this
More informationBy: Ibrahim Anwar Ibrahim Ihsan Abd Alfattah Omareya. The supervisor: Dr. Maher Khammash
Investigations of the effects of supplying Jenin s power distribution network by a PV generator with respect to voltage level, power losses, P.F and harmonics By: Ibrahim Anwar Ibrahim Ihsan Abd Alfattah
More informationCIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems
CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems Ben Huckaba, P.E. President & Principal Engineer 317-273-9841 benh@alphaeng.us Indiana University Bloomington,
More informationContingency Analysis
Contingency Analysis Power systems are operated so that overloads do not occur either in real-time or under any statistically likely contingency. This is often called maintaining system security Simulator
More informationTransmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015
No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the
More informationGeorgia Transmission Corporation Georgia Systems Operations Corporation
Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia
More informationWHITE PAPER. Preventing Collisions and Reducing Fleet Costs While Using the Zendrive Dashboard
WHITE PAPER Preventing Collisions and Reducing Fleet Costs While Using the Zendrive Dashboard August 2017 Introduction The term accident, even in a collision sense, often has the connotation of being an
More informationPump ED 101. Power Factor (Part 2) - - Electricity Behaving Better
Pump ED 101 Power Factor (Part 2) - - Electricity Behaving Better Joe Evans, Ph.D http://www.pumped101.com Last month we took a close look at the flow of voltage and current in purely resistive and inductive
More informationAMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA
AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions
More informationDynamic Control of Grid Assets
Dynamic Control of Grid Assets ISGT Panel on Power Electronics in the Smart Grid Prof Deepak Divan Associate Director, Strategic Energy Institute Director, Intelligent Power Infrastructure Consortium School
More informationNYCA LOLE Violations (Methods D and E )
Proposals for Cost Allocation of Regulated Reliability Solutions Associated with NYCA LOLE Violations (Methods D and E ) Presented by Jerry Ancona National Grid For Discussion by NYISO Electric System
More informationEnergy Management for Regenerative Brakes on a DC Feeding System
Energy Management for Regenerative Brakes on a DC Feeding System Yuruki Okada* 1, Takafumi Koseki* 2, Satoru Sone* 3 * 1 The University of Tokyo, okada@koseki.t.u-tokyo.ac.jp * 2 The University of Tokyo,
More informationPOWERWORLD SIMULATOR. University of Texas at Austin By: Mohammad Majidi Feb 2014
POWERWORLD SIMULATOR University of Texas at Austin By: Mohammad Majidi Feb 2014 AGENDA Contingency Analysis OPF SCOPF Examples 2 START CONTINGENCY ANALYSIS Open case B7SCOPF from the Program Files/PowerWorld/Simulator/Sample
More informationTRANSMISSION LOSS MINIMIZATION USING ADVANCED UNIFIED POWER FLOW CONTROLLER (UPFC)
TRANSMISSION LOSS MINIMIZATION USING ADVANCED UNIFIED POWER FLOW CONTROLLER (UPFC) Nazneen Choudhari Department of Electrical Engineering, Solapur University, Solapur Nida N Shaikh Department of Electrical
More informationHamdy S. K. El-Goharey, Walid A. Omran, Adel T. M. Taha
1 Military Technical College Kobry El-Kobbah, Cairo, Egypt 10 th International Conference on Electrical Engineering I. ICEENG 2016 Voltage Stability Investigation of the Egyptian Grid With High Penetration
More informationA SIMPLE CONTROL TECHNIQUE FOR UNIFIED POWER FLOW CONTROLLER (UPFC)
Volume 116 No. 21 2017, 469-477 ISSN: 1311-8080 (printed version); ISSN: 1314-3395 (on-line version) url: http://www.ijpam.eu ijpam.eu A SIMPLE CONTROL TECHNIQUE FOR UNIFIED POWER FLOW CONTROLLER (UPFC)
More informationNETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources
NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources Marija Ilic milic@netssinc.com and Jeffrey Lang jeffrey.lang@netssinc.com Principal NETSS Consultants
More informationSteady-State Power System Security Analysis with PowerWorld Simulator
Steady-State Power System Security Analysis with PowerWorld Simulator S3: Techniques for Conditioning Hard-to-Solve Cases 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com
More informationEvaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection
Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba
More informationSimulated Switching Transients in the External Grid of Walney Offshore Wind Farm
Downloaded from orbit.dtu.dk on: Apr 07, 2019 Simulated Switching Transients in the External Grid of Walney Offshore Wind Farm Arana Aristi, Iván; Johnsen, D. T.; Soerensen, T.; Holbøll, Joachim Published
More informationMOTORS, VOLTAGE, EFFICIENCY AND WIRING. A Deeper Understanding
MOTORS, VOLTAGE, EFFICIENCY AND WIRING A Deeper Understanding An understanding of motors, voltage, efficiency, wiring, and how these concepts fit together cohesively is important for several reasons. Greater
More informationComputer Aided Transient Stability Analysis
Journal of Computer Science 3 (3): 149-153, 2007 ISSN 1549-3636 2007 Science Publications Corresponding Author: Computer Aided Transient Stability Analysis Nihad M. Al-Rawi, Afaneen Anwar and Ahmed Muhsin
More informationEEEE 524/624: Fall 2017 Advances in Power Systems
EEEE 524/624: Fall 2017 Advances in Power Systems Lecture 6: Economic Dispatch with Network Constraints Prof. Luis Herrera Electrical and Microelectronic Engineering Rochester Institute of Technology Topics
More informationWorking Principle of Power Saver as per Manufacture:
Analysis the Truth behind Household Power Savers Introduction: A House hold power saving devices has recently received a lot of attention from both consumers and manufacturers. It is generally used in
More informationImpact of Islanding and Resynchroniza?on on Distribu?on Systems
1 Impact of Islanding and Resynchroniza?on on Distribu?on Systems Authors: Dr. Vijay Sood Damanjot Singh Kush Duggal 2 Contents Introduction System Description Rural Radial Distribution System Urban Meshed
More informationFeasibility Study Report
Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014
More informationThe Power Potential Project A guide to participating
The Power Potential Project 0 A guide to participating A technical guide to the services for synchronous and non-synchronous DER participants Page 1 of 17 Table of Contents Our vision... 3 1. Introduction...
More informationFalcon-Midway 115 kv Line Uprate Project Report
Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50
More informationComputation of Sensitive Node for IEEE- 14 Bus system Subjected to Load Variation
Computation of Sensitive Node for IEEE- 4 Bus system Subjected to Load Variation P.R. Sharma, Rajesh Kr.Ahuja 2, Shakti Vashisth 3, Vaibhav Hudda 4, 2, 3 Department of Electrical Engineering, YMCAUST,
More informationElectrical grid stability with high wind energy penetration
ECOWAS Regional Workshop on WIND ENERGY Praia, Cape Verde. November 4 5, 2013 Electrical grid stability with high wind energy penetration Fernando CASTELLANO HERNÁNDEZ Head of Wind Energy Section Renewable
More informationSimulation and Analysis of 220kV Substation
Simulation and Analysis of 220kV Substation Yogesh Patel 1, Dixit Tandel 2, Dharti Katti 3 PG Student [Power Systems], Dept. of EE, C. G. Patel Institute of Technology, Bardoli, Gujarat, India 1 PG Student
More informationThe Effect Of Distributed Generation On Voltage Profile and Electrical Power Losses Muhammad Waqas 1, Zmarrak Wali Khan 2
International Journal of Engineering Works Kambohwell Publisher Enterprises Vol., Issue 1, PP. 99-103, Dec. 015 www.kwpublisher.com The Effect Of Distributed Generation On Voltage Profile and Electrical
More informationPower Quality Improvement Using Statcom in Ieee 30 Bus System
Advance in Electronic and Electric Engineering. ISSN 2231-1297, Volume 3, Number 6 (2013), pp. 727-732 Research India Publications http://www.ripublication.com/aeee.htm Power Quality Improvement Using
More informationOperational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks
Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and
More informationImplementation of Distributed Generation
Implementation of Distributed Generation Focusing on Rooftop Solar Installations and Associated Technologies JOSEPH GEDDIS, ELETRICAL ENGINEER Residential rooftop solar generation installations have been
More informationAUTOMATIC CAPACITOR BANK WITH CONTACTOR OPERATIONS
AUTOMATIC CAPACITOR BANK WITH CONTACTOR OPERATIONS INSTRUCTION MANUAL (M98125401-03 / 03A) (c) CIRCUTOR S.A. ------Automatic capacitor bank with contactor operations ----- Page 2 TABLE OF CONTENTS 1. Introduction.
More informationGeneration Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation
Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY
More informationAC : CLASSROOM STUDIES IN POWER FLOW AND TRANSMISSION LINES BY MEANS OF PSCAD/EMTDC
AC 2007-321: CLASSROOM STUDIES IN POWER FLOW AND TRANSMISSION LINES BY MEANS OF PSCAD/EMTDC Fanourios Chalkiadakis, California State Polytechnic University-Pomona FANOURIOS (FANIS) CHALKIADAKIS received
More informationReactive Power Compensation using 12 MVA Capacitor Bank in 132/33 KV Distribution Substation
Reactive Power Compensation using 12 MVA Capacitor Bank in 132/33 KV Distribution Substation Yogesh U Sabale 1, Vishal U Mundavare 2, Pravin g Pisote 3, Mr. Vishal K Vaidya 4 1, 2, 3, 4 Electrical Engineering
More informationDETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT
DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power
More informationJournal of American Science 2015;11(11) Integration of wind Power Plant on Electrical grid based on PSS/E
Integration of wind Power Plant on Electrical grid based on PSS/E S. Othman ; H. M. Mahmud 2 S. A. Kotb 3 and S. Sallam 2 Faculty of Engineering, Al-Azhar University, Cairo, Egypt. 2 Egyptian Electricity
More informationPaper ID: EE19 SIMULATION OF REAL AND REACTIVE POWER FLOW ASSESSMENT WITH FACTS CONNECTED TO A SINGLE TRANSMISSION LINE
SIMULATION OF REAL AND REACTIVE POWER FLOW ASSESSMENT WITH FACTS CONNECTED TO A SINGLE TRANSMISSION LINE Prof. Mrs. Shrunkhala G. Khadilkar Department of Electrical Engineering Gokhale Education Society.
More informationGeneration Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.
Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project April 23, 2003 Introduction Eurus originally requested an interconnection
More informationSimulation of Voltage Stability Analysis in Induction Machine
International Journal of Electronic and Electrical Engineering. ISSN 0974-2174 Volume 6, Number 1 (2013), pp. 1-12 International Research Publication House http://www.irphouse.com Simulation of Voltage
More informationFeasibility Study Report
Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility
More informationVariable frequency transformer for asynchronous power transfer
Variable frequency transformer for asynchronous power transfer by Einar Larsen, Richard Piwko and Donald McLaren, GE Energy A new power transmission technology has been developed. The variable frequency
More informationElectric Power Research Institute, USA 2 ABB, USA
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Congestion Reduction Benefits of New Power Flow Control Technologies used for Electricity
More informationCase No. 5 Sequential Motor Dynamic Acceleration Simulation ETAP TS V&V Case Number TCS-TS-181
ETAP Transient Stability Validation Cases and Comparison Results Case No. 5 Sequential Motor Dynamic Acceleration Simulation ETAP TS V&V Case Number TCS-TS-181 Comparison with PTI PSS/E Simulation Results
More information