Transmission Planning Report

Size: px
Start display at page:

Download "Transmission Planning Report"

Transcription

1 Transmission Planning Report Board of Directors Meeting December 15,

2 Overview Study Team Reports Puget Sound Area Study Team Northern Mid-Columbia Study Team Cross Cascades Study Team Centralia Closure Study Team Wind Integration Study Team Northwest Area Coordinator WECC 10-Year Plan ColumbiaGrid 2011 Biennial Transmission Expansion Plan

3 Puget Sound Area Study Team

4 Northern Mid-Columbia Study Team

5 Cross Cascades Study Team

6 Figure 10: Wind Resources

7 Wind Integration Study Team Held a webinar on 12/8 Two main items Task force to work on increasing dynamic transfer capability limits Completion of the report Relative Northwest Benefits of Local vs. Remote Wind Generation

8 Centralia Closure Study Team Developed a study plan Preliminary summer peak and light load study results to be discussed tomorrow (web conference)

9 Northwest Area Coordinator Activities to date Case development performance metrics (Nov-Dec) Two cases approved and posted on the WECC website Four additional cases under development Procedure improvements Completed PacifiCorp data submittal improvements BPA data submittal improvements under development Updates to already approved cases Will be posted under the System Assessment website CG will post preliminary system assessments of updated WECC planning cases for the January 27 planning meeting 2016 Heavy Summer 2021 Heavy Summer Heavy Winter Scenario with 100% Northwest wind generation Heavy Winter

10 Regional Transmission Expansion Planning Project (RTEP) Ten-year plan on schedule for completion in late 2011

11 Subregional Planning Group Coordination Group (SCG)

12 SCG Activities Coordinate activities between SPG s More formal review of neighboring SPG Plans Assist WECC by populating the Transmission Project Information Portal: Assist WECC with the reliability analysis of the 10-year plan

13 2011 Biennial Plan Review Process Draft Biennial Plan posted November 18 th Discussed at November 4 th and December 2 nd planning meetings Comment period through December 7 th Also contacted those not at the December 2 nd planning meeting 13

14 2011 Biennial Plan Review Process Public Review Draft for Board will be posted before Christmas Board will consider taking action on the Biennial Plan at February 17 th meeting 14

15 2011 Biennial Plan Study areas => Potential Study Teams 1. Olympic Peninsula 2. Spokane Area 3. Okanogan Area 15

16 Sensitivity Studies 2011 Biennial Plan 1. Low Generation in the Puget Sound Area 2. Closure of Centralia Power Plant 3. Further study of voltage stability studies and unsolved outages from the System Assessment 4. Northern Mid-Columbia Area 5. Five year light load case 6. Sammamish-Lakeside-Talbot Hill 230 kv lines 16

17 Figure 1: ColumbiaGrid Ten-Year Plan

18 Project Name Sponsor Date Change from Previous Plan Estimated Cost A1 Moscow 230 kv Substation Rebuild and Transformer Replacement Avista 2012 New Project $15 Million B1 Mid-Columbia Area Reinforcement (Vantage-Midway 230kV line upgrade) and 230 kv sectionalizing breakers at Vantage and Midway Substations Bonneville Power 2011 $14 Million B2 Second 230/115 kv transformer at Redmond Substation Bonneville Power 2011 $12 Million B3 Bakeoven Series Capacitors plus other shunt capacitors and line upgrades (COI Upgrade) Bonneville Power $64 Million B4 John Day - McNary 500 kv Line Bonneville Power $247+ Million B8 Lower Valley Reinforcement (SE Idaho) Bonneville Power/others $48 Million B9 Ponderosa 500/230 kv #2 Transformer Addition Bonneville Power 2013 New Project No Cost Yet CH1 Relocation/upgrade of the McKenzie - Wenatchee Tap 115 kv line Chelan $6 Million CO1 Cowlitz PUD conversion from 69 kv to 115 kv (Longview-Cowlitz #2, Longview- Lexington #2, Longview-Lexington-Cardwell) Cowlitz PUD $3 Million D1 Douglas - Rapids 230 kv line and Rapids 230/115 kv Substation Douglas 2013 $16 Million PS5 230/115 kv transformer addition at Sedro Woolley Substation in north Puget Sound area Puget Sound Energy $9.4 Million SN1 Beverly Park 230/115 kv transformer (North Puget Sound) Snohomish PUD $25 Million T1 Cowlitz 230 kv transformer replacement (second bank), line retermination, and bus reliability improvement projects Tacoma Power $7.0 Million T2 Canyon Substation and 230/115 kv transformer (Tacoma area) Tacoma Power 2011 $10.0 Million T3 Southwest Substation 230 kv bus reliability improvement project Tacoma Power 2016 $3.0 Million x1 Rapids - Columbia 230 kv line (Mid-Columbia area) undetermined 2013 $11 Million Total of all ColumbiaGrid projects $1,190 Million Cancelled Projects Sandpiper Substation connecting into the existing Ashe-Marion 500 kv line and the new McNary-John Day 500 kv line Bonneville Power NA cancelled New Lookingglass Substation on the Reston - Dixonville 230 kv line (Roseburg area) PacifiCorp NA cancelled Table 1: ColumbiaGrid Ten-Year Plan (partial list)

19 Projects Recently Energized Sponsor Date Retermination of the lines into Andrew York Substation in the Wenatchee area Chelan County PUD 2010 Wenatchee-McKenzie 115 kv Upgrade in the Wenatchee area Chelan County PUD 2010 Rapids - South Nile 115 kv line in the Wenatchee area Douglas County PUD 2010 Sedro - Horse Ranch 230 kv line in the North Puget Sound area Puget Sound Energy 2010 Olympic Peninsula Reinforcement (Satsop-Shelton 230 kv line) Bonneville 2009 Libby - Troy 115 kv line rebuild in western Montana Bonneville 2009 Rogue SVC (South Oregon Coast) Bonneville 2009 Larson-Stratford 115 kv line in central Washington Grant County PUD 2009 Wine Country 230/115 kv Substation (Yakima area) PacifiCorp 2009 North Seattle 115 kv transmission line upgrade Seattle City Light 2009 Boundary 230/115 kv transformer replacement Seattle City Light/Bonneville 2009 Novelty 230/115 transformer fed from the existing Monroe-Sammamish 230 kv line in the north Seattle area Puget Sound Energy 2008 Covington - Berrydale 230 kv line in the south Puget Sound area Puget Sound Energy 2008 Rocky Reach - Andrew York 230 kv line and Andrew York 230/115 kv Substation north of Wenatchee Chelan County PUD 2008 Columbia - Quincy 115 kv line reconductoring in central Washington Grant County PUD 2008 Benewah - Shawnee 230 kv line in eastern Washington Avista 2008 Dry Creek - North Lewiston 230 kv line reconductoring in central Washington Avista 2008 Carver - McLoughlin 230 kv line in the southeast Portland area Portland General Electric 2008 Tambark Junction - Clearview 115 kv line in the north Puget Sound area Snohomish County PUD 2008 Rocky Ford 230/115 transformer in the Mid - Columbia area Grant County PUD 2008 Sherwood - Murrayhill 230 kv line in the southwest Portland area Portland General Electric 2008 Sedro - Bellingham #3 115 kv Reconductor in the north Puget Sound area Puget Sound Energy 2008 Table 3: Projects Recently Energized

20 2011 Biennial Plan Some longer term projects have moved to the Ten Year Plan Ponderosa 500/230 kv Transformer Moscow 230/115 kv Transformer 20

21 Longer Term Project Areas 1. West of Cascades North and South Upgrades 2. Colstrip Upgrades 3. North King County 230/115 kv Transformation and Capacity Increase 4. Pearl- Sherwood Upgrades 5. Shelton-Fairmount-Port Angeles support 6. North Downtown Seattle 7. Mid-Columbia Area Reinforcement 8. Spokane Area 230 kv Reinforcement 9. Lewiston Reinforcements 10. Chemawa 230/115 kv transformer additions 11. Blue Lake-Gresham 230 kv line 12. Kalama Energy 13. Trojan-Horizon 230 kv line 14. Additional 500/230 kv transformation in South Puget Sound area 21

22 Figure 9: Northwest to British Columbia

23 Figure 10: Wind Resources

24 Project Name Add Bus section breaker at Columbia 230 kv to split station bus Separate the terminals of the 230 kv lines between Pearl and Sherwood Substations with new breakers to separate circuits Remove jumpers from the circuits between Raver-Covington and Raver-Tacoma 500 kv lines Trip remote ends Pearl-Cushman 115 kv lines along with consequential load to mitigate inadvertent breaker opening Trip remote ends of McNary - Franklin 115 kv line to mitigate inadvertent breaker opening Trip remote ends of the Fairmount - Happy Valley line to mitigate inadvertent breaker opening Trip remote ends of Sherwood-Cascade Tap- Carlton 230 kv line along with consequential load to mitigate inadvertent breaker opening Trip remote ends Redmond - Harney 115 kv lines along with consequential load to mitigate inadvertent breaker opening Potential Mitigation Proposed by: Bonneville Bonneville/Portland General Electric Bonneville Tacoma Bonneville Bonneville Bonneville/Portland General Electric Bonneville Table 5: Transmission Owner Identified Mitigation Projects Substation Max Mvar Owner Calapooya 110 PacifiCorp Dixonville 45 PacifiCorp East Omak 50 Bonneville Flathead 15 Bonneville Green Valley Tap 25 Bonneville Horse Heaven 30 Bonneville Pilot Butte 80 PacifiCorp Ponderosa 110 PacifiCorp Roundup 20 Bonneville Tillamook 35 Bonneville TRS 20 Energy Northwest Table 6: Potential Reactive Mitigation Projects

25 Review Process Public Review Draft of 2011 Biennial Transmission Expansion Plan for Board Review will be posted before Christmas Board to consider taking action on Biennial Plan at February 17 th meeting Comments and questions today? 25

Ten-year Plan. Figure 1 and Table 1. Each of the facilities shown in the plan is described in greater depth in the last appendix of this report.

Ten-year Plan. Figure 1 and Table 1. Each of the facilities shown in the plan is described in greater depth in the last appendix of this report. Ten-year Plan As a result of the analysis completed for the 2009 System Assessment, the follow-up sensitivity studies, analysis completed by the study teams, and individual planning participant studies,

More information

Process Timeline. Area Bubbles. Legend. Problem Area that have been resolved. Recurring Areas from previous System Assessment.

Process Timeline. Area Bubbles. Legend. Problem Area that have been resolved. Recurring Areas from previous System Assessment. Process Timeline Legend Problem Area that have been resolved Recurring Areas from previous System Assessment New Areas Area Bubbles Flows Modeled for One-Year Heavy Winter Peak Conditions Base Case Conditions

More information

Public Review Draft. June 30, System Assessment

Public Review Draft. June 30, System Assessment Public Review Draft June 30, 2009 2009 System Assessment 2 Copies of this report are available from: ColumbiaGrid 8338 NE Alderwood Rd Suite 140 Portland, OR 97220 503.943.4940 www.columbiagrid.org Spring/Summer

More information

PSE Attachment K Puget Sound Area Transmission Meeting

PSE Attachment K Puget Sound Area Transmission Meeting PSE Attachment K Puget Sound Area Transmission Meeting Stephanie Lu Senior Engineer December 15, 2011 Agenda Attachment K Review Economic Studies Process PSE Planning Process and Assumptions PSE Projects

More information

2013 Biennial Transmission Expansion Plan

2013 Biennial Transmission Expansion Plan 2013 Biennial Transmission Expansion Plan Copies of this report are available from: ColumbiaGrid 8338 NE Alderwood Rd Suite 140 Portland, OR 97220 503.943.4940 www.columbiagrid.org February 2013 Photos

More information

Avista BPA, IPCO, PAC Project identified as long term need. Project Committed under Network Open Season. Plan of Service Determined

Avista BPA, IPCO, PAC Project identified as long term need. Project Committed under Network Open Season. Plan of Service Determined Name Region In Ten Year Plan? by Link to More Detail Stage Commitment Need/Driver & Other A1 Bronx-Cabinet 115 kv Rebuild Northeastern Yes 5, 10 ColGrid SA Rebuild/reconductor Bronx-Cabinet 115 kv Avista

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

2015 System Assessment

2015 System Assessment 2015 System Assessment Copies of this report are available from: ColumbiaGrid 8338 NE Alderwood Rd Suite 140 Portland, OR 97220 503.943.4940 www.columbiagrid.org July 2015 Photos provided by: Bonneville

More information

2013 ANNUAL PROGRESS REPORT

2013 ANNUAL PROGRESS REPORT March 1, 2013 Mr. David Franklin, Chairman WECC Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768-2560 Mr. Enoch Davies WECC Technical Staff 155 North 400 West,

More information

Transmission Planning. WECC 2014 Progress Report. March 14, 2014

Transmission Planning. WECC 2014 Progress Report. March 14, 2014 Transmission Planning WECC 2014 Progress Report March 14, 2014 Report Prepared By: Dennis Stevens -TPP (360) 619-6821 BPA TS TPP 2014-022 Page 1 Table of Contents 1 Introduction... 1 2 Planned Transmission

More information

2013 ANNUAL PROGRESS REPORT

2013 ANNUAL PROGRESS REPORT Bonneville Power Administration 2013 ANNUAL PROGRESS REPORT Report Prepared By: Dennis Stevens Bonneville Power Administration Transmission Planning TPP/OPP-3 (360) 619-6821 BPA TS TPP 2013-018 Page 1

More information

Cross Cascades North Study Team Report

Cross Cascades North Study Team Report Cross Cascades North Study Team Report Acknowledgements ColumbiaGrid Members & Participants Avista Corporation Bonneville Power Administration Chelan County PUD Cowlitz County PUD Douglas County PUD Grant

More information

REDACTED. Eastside Needs Assessment Report Transmission System King County. Redacted Draft. October 2013 Puget Sound Energy

REDACTED. Eastside Needs Assessment Report Transmission System King County. Redacted Draft. October 2013 Puget Sound Energy Eastside Needs Assessment Report Transmission System King County Redacted Draft October 2013 Puget Sound Energy Report prepared by: Thomas J. Gentile, P.E. Quanta Technology Donald J. Morrow, P.E. Quanta

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Direct Testimony of Richard A. Vail

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Direct Testimony of Richard A. Vail Application No. -0- Exhibit PAC/00 Witness: Richard A. Vail BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP Investment in Distribution and Transmission Systems April 0 PAC/00

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006 Final System Impact Study for Sierra Pacific Industries 31 MW Generation Project Mount Vernon, WA November 16, 2006 Puget Sound Energy, Inc. Electric Transmission Department 1 1. Introduction On October

More information

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions. March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating

More information

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project. Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project April 23, 2003 Introduction Eurus originally requested an interconnection

More information

Update to the 2004 Puget Sound Area Study Group ( PSASG ) Report: Assessment of Puget Sound Area / Northern Intertie Curtailment Risk

Update to the 2004 Puget Sound Area Study Group ( PSASG ) Report: Assessment of Puget Sound Area / Northern Intertie Curtailment Risk Update to the 24 Puget Sound Area Study Group ( PSASG ) Report: Assessment of Puget Sound Area / Northern Intertie Curtailment Risk Chair: John Phillips, Puget Sound Energy Jerry Jackson III, Bonneville

More information

System Impact Study for. Puget Sound Energy s Share of Frederickson I Generation Project. Pierce County, WA

System Impact Study for. Puget Sound Energy s Share of Frederickson I Generation Project. Pierce County, WA System Impact Study for Puget Sound Energy s Share of Frederickson I Generation Project Pierce County, WA Puget Sound Energy OASIS Reference No. 33763 February 4, 2004 Puget Sound Energy, Inc. Electric

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

Attending Meeting (has not voted) Advance Bylaw Ballot

Attending Meeting (has not voted) Advance Bylaw Ballot Not Voted / Meeting (has 1 Arizona Public Service 1 1 Avista Corporation 1 1 Balancing Authority of Northern California 1 1 1 1 BC Hydro 1 1 Black Hills Corporation 1 1 Bonneville Power Administration

More information

North Oregon Coast Area Study. Adam Lint

North Oregon Coast Area Study. Adam Lint North Oregon Coast Area Study Adam Lint PAGE 2 North Oregon Coast System Overview - Clatsop Study Covers: Transmission Switching Stations (Clatsop District): Astoria Lewis and Clark 115 kv Distribution

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Rocky Mountain Power Five Year Study Findings & Kick Off Meeting

Rocky Mountain Power Five Year Study Findings & Kick Off Meeting 2000 PACIFICORP PAGE 1 Attachment K Rocky Mountain Power Five Year Study Findings & Kick Off Meeting Thursday, December 8 2016 2000 PACIFICORP PAGE 2 Study Areas for 2016 Findings Reports Southeast, Utah

More information

Distribution System Efficiency Potential & Conservation Voltage Reduction

Distribution System Efficiency Potential & Conservation Voltage Reduction 1 Distribution System Efficiency Potential & Conservation Voltage Reduction Power Committee April 2009 Northwest Power and Conservation Council Energy & Capacity Savings slide 2 Northwest Power and Conservation

More information

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Status of PNM s Completed Transmission Construction Projects 11/30/2017 Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

Pacific Gas and Electric Company s Revised 2015 Annual Progress

Pacific Gas and Electric Company s Revised 2015 Annual Progress March 02, 2015 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Avista PO Box 3727 MSC-16 1411 East Mission Ave Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff 155 North 400 West

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Transmission Planning Attachment K Public Input Meeting

Transmission Planning Attachment K Public Input Meeting Transmission Planning Attachment K Public Input Meeting FERC 890 6 th Quarter Meeting May 25, 2011 Agenda Mountain Time Topic Presenter 1:00 1:15 Greetings and Introduction Dennis Desmarais 1:15 1:30 Attachment

More information

Chapter 7: Transmission

Chapter 7: Transmission Sixth Northwest Conservation and Electric Power Plan Chapter 7: Transmission Summary of Key Findings... 1 Background... 1 Northwest Transmission Planning... 6 SUMMARY OF KEY FINDINGS For a number of years

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

2018 CG Transient Stability and MOD 33 Updates

2018 CG Transient Stability and MOD 33 Updates 2018 CG Transient Stability and MOD 33 Updates CG Planning Meeting Oct. 4, 2018 1 Transient Stability Study Updates 2 Studied Case Study performed for 2024HS case Two Colstrip units retired, with ATR model

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

APPENDIX E: Project Need and Description

APPENDIX E: Project Need and Description APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Lakeville 115 kv Bus Upgrade Installation of a sectionalizing breaker to be installed on 115 kv bus section

More information

BC Hydro System 2011 Annual Progress Report

BC Hydro System 2011 Annual Progress Report March 1, 2011 Mr. Kyle R. Kohne, Chairman WECC Technical Studies Subcommittee Bonneville Power Administration P.O. Box 491 MS, TPP-OPP-3 Vancouver, WA 98666 Mr. Kent Bolton WECC Technical Staff 155 North

More information

2018 Annual Progress Report to WECC Pacific Gas and Electric Company

2018 Annual Progress Report to WECC Pacific Gas and Electric Company 2018 Annual Progress Report to WECC Pacific Gas and Electric Company Waiver of Significant Transmission Project Status Table 1 and 2 update the planned transmission and generation projects, respectively,

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Local Transmission Plan. October 11, 2013 Revised August 25, 2014 Local Transmission Plan October 11, 2013 Revised August 25, 2014 2 Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

Pacific Gas and Electric Company s Revised 2016 Annual Progress

Pacific Gas and Electric Company s Revised 2016 Annual Progress March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric

More information

Key to Status Fields in the Project List

Key to Status Fields in the Project List Key to Fields in the Project List Load Growth Interconnection Economic Reliability Concept Proposed Planned Under Construction In Cancelled N/A Backstop Too early TO Update Base case Increasing load served

More information

Oilseeds and Biofuels in Washington State, 2017

Oilseeds and Biofuels in Washington State, 2017 Oilseeds and Biofuels in Washington State, 2017 Mary Beth Lang, Bioenergy Coordinator Bioenergy Goals Reduce dependence on foreign oil Improve environment / public health Support WA agriculture and rural

More information

NorthernLights HVDC Project

NorthernLights HVDC Project WECC COMPREHENSIVE PROGRESS REPORT December 4, 2008 Prepared for TransCanada by Ben Williams TABLE OF CONTENTS EXECUTIVE SUMMARY... III 1.0 BACKGROUND & INTRODUCTION... 1 1.1 BACKGROUND... 1 1.2 INTRODUCTION...

More information

Pacific Gas and Electric Company s 2013 Annual Progress Report

Pacific Gas and Electric Company s 2013 Annual Progress Report March 14, 2013 Mr. David Franklin Chair, WECC Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake

More information

APPENDIX E: Project Need and Description

APPENDIX E: Project Need and Description APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Tyler 60 kv Shunt Capacitor Installation of a 2x10 MVAR capacitor bank at Tyler 60 kv bus Objectives

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04 Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

National Grid s 2017 Local Transmission Plan

National Grid s 2017 Local Transmission Plan National Grid s 2017 Local Transmission Plan Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

More information

Final System Impact Study for. Horizon Wind Wild Horse Wind Plant Generation Project. Kittitas County, WA

Final System Impact Study for. Horizon Wind Wild Horse Wind Plant Generation Project. Kittitas County, WA Final System Impact Study for Horizon Wind Wild Horse Wind Plant Generation Project Kittitas County, WA PSE OASIS Reference Nos. 26381 & 26382 (Wild Horse) September 19, 2005 (Revised from draft SIS dated

More information

BC Hydro System 2016 Annual Progress Report

BC Hydro System 2016 Annual Progress Report March 11, 2016 Philip Augustin, P.E. Chair, Technical Studies Subcommittee 503-464-7783 philip.augustin@pgn.com Mr. Enoch Davies WECC Technical Staff 155 North 400 West, Suite 200 Salt Lake City, UT 84103-1114

More information

Arizona Transmission Challenges

Arizona Transmission Challenges Power Task Force Agenda Number 2. Arizona Transmission Challenges Central Arizona Water Conservation District Power Committee Presentation May 18, 2017 Transmission Planning Efforts NATIONAL Section 368

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2014 Annual Ten-Year Transmission Plan Assessment Report November 20, 2014 For information or questions regarding this Transmission Assessment Report,

More information

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives Addendum San Juan Major Project Tri-State Generation and Transmission Association Power System Planning December, 2008

More information

BC Hydro System 2017 Annual Progress Report

BC Hydro System 2017 Annual Progress Report March 14, 2017 Philip Augustin, P.E. Chair, Technical Studies Subcommittee 503-464-7783 philip.augustin@pgn.com Mr. Enoch Davies WECC Technical Staff 155 North 400 West, Suite 200 Salt Lake City, UT 84103-1114

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC

More information

APPENDIX F: Project Need and Description

APPENDIX F: Project Need and Description APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was

More information

SPP Notification to Construct

SPP Notification to Construct February 19, 2014 SPP Notification to Construct Mr. Mo Awad Westar Energy, Inc. P.O. Box 889 Topeka, KS 66601 RE: Notification to Construct Approved Reliability Network Upgrades Dear Mr. Awad, Pursuant

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic November 04, 2013 2013 RTEP Baseline Analysis Update 11/04/2013 AE Transmission Zone Cost Change for B2354 Install second 230/69kV transformer and 230kV circuit

More information

Western Area Power Administration

Western Area Power Administration 2014/15 Integrated System (IS) 890 Local Planning Stakeholder Meeting #2 Western Area Power Administration Upper Great Plains Region Transmission Planning Stakeholder Meeting Wednesday, December 10 th,

More information

Load Modeling for Power System Studies

Load Modeling for Power System Studies Load Modeling for Power System Studies WECC Load Modeling Task Force Dmitry Kosterev Bonneville Power Administration Transmission Planning Timescale of Interest Our primary interest is the fast dynamic

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2013 Annual Ten-Year Transmission Plan Assessment Report December 1, 2013 For information or questions regarding this Transmission Assessment Report,

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee March 6, 2014 1 2014 RTEP Update 2 2014 RTEP Update Initial 2019 Summer base case and corresponding machine list update complete PJM staff has been reviewing and

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

WECC Regional Planning Review. Canada/Pacific Northwest Northern California Transmission Line Project. Technical Analysis Committee Report

WECC Regional Planning Review. Canada/Pacific Northwest Northern California Transmission Line Project. Technical Analysis Committee Report WECC Regional Planning Review Canada/Pacific Northwest Northern California Transmission Line Project Technical Analysis Committee Report November 1, 2007 Table of Content Summary...1 SECTION 1 SECTION

More information

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee February 7, 2013 1 Issues Tracking 2 Issues Tracking Open Issues None New Issues 3 2013 RTEP Scenario Analysis 4 RTEP Scenario Analysis 2012 North Carolina Transmission

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

South Dakota 890 Study

South Dakota 890 Study South Dakota 890 Study September 16, 2011 South Dakota 890 Study Presentation of 890 Study results from 2011 Includes WAPA suggested system improvements and timelines Stakeholder Feedback Questions? 2

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic July 26, 2016 Reliability Analysis Update MetEd Transmission Zone N-1 First Energy Planning Criteria (FERC Form 715): The North Boyertown West Boyertown 69 kv is

More information

3 Existing National Grid

3 Existing National Grid 3 Existing National Grid 3.1 Introduction 3.2 Load and generation 3.1 Introduction This chapter provides an overview of New Zealand s existing National Grid as at 28 February 2012 with respect to load

More information

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M of Need In-service Cost Alternatives Service Projects in PG&E Service Territory Mare Island - Ignacio 115 kv NERC Category 2010 Reconductor the limiting 19 $19M Connect Highway May 2012 Line re-rates and

More information

2012 LOCAL TRANSMISSION PLAN:

2012 LOCAL TRANSMISSION PLAN: Colorado PUC E-Filings System 2012 LOCAL TRANSMISSION PLAN: TRANSMISSION COORDINATION AND PLANNING COMMITTEE ANNUAL TRANSMISSION ASSESSMENT FOR BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, L.P., D/B/A

More information

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No. 17-035-40 Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct

More information

Sub Regional RTEP Committee - Southern. August 19, 2011

Sub Regional RTEP Committee - Southern. August 19, 2011 Sub Regional RTEP Committee - Southern August 19, 2011 2011 RTEP Analysis Summary 2010 2015 Project Updates 2016 Analysis NERC Category A, B NERC Category C (N-1-1 in progress) Load Deliverability Generator

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

UNITED STATES DEPARTMENT OF AGRICULTURE. Compilation of Statistical Material. Pacific Northwest Federal Milk Marketing Order. Federal Order No.

UNITED STATES DEPARTMENT OF AGRICULTURE. Compilation of Statistical Material. Pacific Northwest Federal Milk Marketing Order. Federal Order No. UNITED STATES DEPARTMENT OF AGRICULTURE 1930-220th St. SE, Ste. 102 AGRICULTURAL MARKETING SERVICE 10050 N 25th Ave., Ste. 302 Bothell, WA 98021-8471 DAIRY PROGRAMS Phoenix, AZ 85021-1664 Phone: (425)

More information

best to you all Gail Carbiener Page 1 of 5

best to you all Gail Carbiener Page 1 of 5 Please accept this attachment as my up dated response to the B2H DEIS. If this is not acceptable, please let me know. Nice meeting last Monday in Boardman. 300316 best to you all Gail Carbiener 2 Page

More information

Market Efficiency RTEP Proposal Window

Market Efficiency RTEP Proposal Window Market Efficiency RTEP Proposal Window Market Efficiency RTEP Proposal Window Status Window opened on 8/12/2013 Closed on 9/26/2013 17 individual proposals addressing congestion from Market Efficiency

More information

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN Twin Cities Minnesota Zone Meeting Xcel Energy May 11, 2005 Bloomington, MN Overview of Presentation Xcel Energy Projects: Aldrich to St Louis Park 115 kv line Eden Prairie to Edina 115 kv line Eden Prairie

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

Craig Quist Craig Quist

Craig Quist Craig Quist TRANSMISSION PLANNING Craig Quist, Manager Transmission Development & Planning PacifiCorp 1407 West North Temple, Suite 275 Salt Lake City, Utah 84140 801-220-4264 FAX 801-220-2842 craig.quist@pacificorp.com

More information

SERTP rd Quarter Meeting

SERTP rd Quarter Meeting 2014 SERTP SERTP 2014 3 rd Quarter Meeting 2 nd RPSG Meeting September 30 th, 2014 APC Headquarters Birmingham, AL 2014 SERTP Process Information The SERTP process is a transmission planning process. Please

More information

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC OCTOBER 17, 2018 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Pacific Northwest/Canada To Northern California Transmission Feasibility Study

Pacific Northwest/Canada To Northern California Transmission Feasibility Study Pacific Nthwest/Canada To Nthern Califnia Transmission Feasibility Study Technical Analysis Committee Presentation By Ben Mris, PG&E 1 December 12, 2006 Topics Study Objectives Alternatives Considered

More information

SPP Notification to Construct

SPP Notification to Construct February 19, 2014 SPP Notification to Construct Mr. John Fulton Southwestern Public Service Company P.O. Box 1261 Amarillo, TX 79105 RE: Notification to Construct Approved Reliability Network Upgrades

More information

West Station-West Cañon 115 kv Transmission Project

West Station-West Cañon 115 kv Transmission Project West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon

More information

National Grid s 2018 Local Transmission Plan

National Grid s 2018 Local Transmission Plan National Grid s 2018 Local Transmission Plan Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

More information

Q0044 interconnection at

Q0044 interconnection at Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description

More information

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit Sound Transit Long-Range Plan Update Issue Paper S.1: Tacoma Link Integration with Central Link Prepared for: Sound Transit Prepared by: Quade & Douglas, Inc. FINAL March 2005 Foreword This issue paper

More information

Sub-Regional RTEP Committee PJM South

Sub-Regional RTEP Committee PJM South Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates

More information

2015 CPS2 Bounds (Effective June 15, 2015)

2015 CPS2 Bounds (Effective June 15, 2015) Bias/ Eastern Interconnection 621,697 6,303.01 1.01 100.00 FRCC 50,282 503.65 1.00 7.99 City of Homestead HST 97 1.00 1.03 0.02 7.47 City of Tallahassee TAL 543 5.43 1.00 0.09 17.40 Duke Energy of Florida

More information

Designated Network Loads and Resources Load Served by Company Owned Resources

Designated Network Loads and Resources Load Served by Company Owned Resources Designated Network Loads and Resources Load Served by Company Owned Resources Entity Location Network Load Network Resources NWMT Point of Receipt (POR) for Off System Resources Resource Owner Desig. MW

More information

SERTP rd Quarter Meeting

SERTP rd Quarter Meeting 2015 SERTP SERTP 2015 3 rd Quarter Meeting 2nd RPSG Meeting September 24 th, 2015 APC Headquarters Birmingham, AL 2015 SERTP Process Information The SERTP process is a transmission planning process. Please

More information