BC Hydro System 2016 Annual Progress Report

Size: px
Start display at page:

Download "BC Hydro System 2016 Annual Progress Report"

Transcription

1 March 11, 2016 Philip Augustin, P.E. Chair, Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West, Suite 200 Salt Lake City, UT U.S.A ANNUAL PROGRESS REPORT In accordance with reporting guidelines by the WECC Planning Coordinating Committee (PCC), please find attached BC Hydro s 2016 Annual Progress Report on significant additions and changes to our system. Please call me at (604) if you have any questions. Sincerely, British Columbia Hydro By Guihua Wang Manager Performance Planning, T&D AIM Phone: (604) Fax: (604) Guihua.wang@bchydro.com BC Hydro System 2016 Annual Progress Report Major transmission and generation facilities planned and operated by British Columbia Hydro (BCH) over the next 10-year period from 2015 to 2025 are outlined below. A. Previously Reported Projects with ISD updated: 1. New ILM 500 kv Line (5L83) Service Date: November 2015 This line is to provide incremental transmission transfer capability from the Interior of British Columbia to the load centers in the Lower Mainland. This new 500 kv transmission bchydro.com

2 circuit, 5L83, is approximately 250 km long and run between the Nicola and Meridian substations. 5L83 will be 50% series compensated at new Ruby Creek Capacitor Station near Agassiz. 2. Major Generation Addition(>200 MW) Plant Capacity In Service Status Date Waneta Expansion G MW April 2015 In service Waneta Expansion G MW April 2015 In service Mica G5 500 MW Jan In service Mica G6 500 MW Oct Rev G6 500 MW April 2025 Site C G MW DEC Site C G MW Dec Site C G MW Dec Site C G MW Dec.l 2023 Site C G MW Dec.l 2023 Site C G MW Dec Forrest Kerr IPP (stage I) MW July 2014 In service (FKR/VOL) Forrest Kerr IPP (stage II) (with 66 September In service MCY) Dawson Creek / Chetwynd Area Transmission (DCAT) Project. Scheduled in Service Date: November 2015 The Dawson Creek / Chetwynd Area Transmission Project (DCAT) consists a two 60 km 230kV lines running from a new 230 / 138 kv substation named Sundance Substation (SLS) to Bear Mountain Terminal (BMT) and a new 138 kv line from BMT to Dawson Creek Substation (DAW). This project would provide additional transmission capacity into the Dawson Creek area to support new unconventional gas production loads. 4. Transmission Lines from Site C to Peace Canyon. Scheduled in Service Date: 5L5 - December L6 December 2022 At preliminary planning stage, this project is to build two 500 KV lines from Site C to Peace Canyon, to accommodate site C new generation. 5. Other Transmission Projects (Urban system upgrade in Vancouver area): Fraser Valley West Area Reinforcement (230 kv) Scheduled in Service Date: February

3 Construction of a new substation and new transmission lines New station: Fleetwood Substation Splitting 2L75 from Ingledow to McLellan to 2 lines New lines: 2L75 (8 KM) McLellan to Fleetwood 2L74 (8 KM) Fleetwood to Ingledow West End Substation (230 kv) Scheduled in Service Date: October 2019 The planning study is in progress and the following identified is only one alternative, may subject to changes: New station: West End substation Splitting 2L32 from Horne Payne to Cathedral Square to 2 lines 2L32 (7.5 KM) Horne Payne to Murrin 2L30 (1.2 KM) Murrin to Cathedral Square Reterminate 2L33 from Cathedral Square to West End (by extending 2.4 KM of new underground transmission) Reterminate 2L3 from Horne Pane to West End (by extending 10.5 KM of new underground transmission). As a result, 2L3 becomes a mix of overhead and underground transmission from Walter to West End. Add new underground transmission from Cathedral Square to West End (2 KM) Metro North Area Reinforcement (230 kv) Alternative 3 Scheduled in Service Date: October 2019 The planning study is in progress and the following identified is only one alternative, may subject to changes: 1) Construct a new 21.5 km, 230 kv circuit from Meridian to Horne Payne (2L18). 2) Extend an underground circuit (2L51) from Barnard to Mount Pleasant. 3) Add 203 kv 60 MVAR switchable shunt reactor on dedicated 230 kv line position at Camosun 6. Kitimat Modernization Project Scheduled in Service Date: January 2016 Kitimat Modernization Project consists of rebuilding the Kitimat smelter and adding 35% series compensation on the two Kemano to Kitmat 287 kv transmission lines by building a series capacitor station near Kitmat. Five 287/100/28 kv 219 MVA regulating transformers will be installed. 7. Series Compensation Increase (from 50% to 65%) at KDY and MLS Stations Scheduled in Service Date: April

4 At preliminary planning stage, this project is to increase series compensation level at 5L1, 5L2 & 5L7 at KDY, 5L11,5L12 &5L13 at MLS from 50% to 65%, to accommodate site C new generation. 8. Prince George Terrace Compensation (PGTC) Scheduled in Service Date: October 2018 At preliminary planning stage, this project is to install 65% series compensation at 5L61, 5L62, 5L63 from WSN to SKA substation, to accommodate LNG loads in North Coastal BC region. Add 2 x 130 MVAR shunt capacitor at GLN Vancouver Island Cable Project Scheduled in Service Date: March 2016 Add a new 230 kv cable circuit (2L142) from George Tripp to Horsey and add one 150 MVA 230/138 (T14) transformer at George Tripp. 10. Arnott 230/25 kv transformers capacity upgrade Scheduled in Service Date: October 2017 Replace T11 & T12 with 2 new 150 MVA transformers to supply the load growth in the Tsawwassen/Delta area. 11. Terrace - Kitimat Transmission Project Scheduled in Service Date: July 2020 Previously reported as Minette to Skeena Line Rating Upgrade (2L99). This project would replace the 60km transmission line that runs between Skeena and Minette substations and the 3km transmission line that runs between Minette and Kitimat substations with new lines on a new right of way. 12. Skeena Substation Upgrade Scheduled in Service Date: October Add Skeena T3 (500/287/12.6) transformer due to new Shell Canada LNG2 load. 13. Bob Quinn SVC Addition Scheduled in Service Date: April Add +100/-40 SVC for system reinforcement to accommodate NTL (2L102) new mining loads. 14. Add series compensation on circuit 2L102 Scheduled in Service Date: September

5 Add series compensation on NTL (2L102) near Skeena due to new mine loads 15. Horne Payne Substation Upgrade Scheduled in Service Date: October 2018 Add 2 x 230/25 kv 150 MVA transformers at Horne Payne Sub 16. Peace Region Electric Supply (PRES) Project Alternative 5 Scheduled in Service Date: August 2022 This alternative is to build two 500/230 kv 600 MVA transformers and two 230 kv line positions, and construct a 60 km 230 kv double circuit transmission line from Site C to Shell Ground Birch (SGB). The previously reported alternative 2 (as described in the following) has been replaced: Alternative 2 -- Construct a 2 nd 22.8 KM 230 kv overhead transmission line from GMS to Dokie Terminal. Construct a 64.1 KM 230 kv transmission line from Dokie Wind Terminal to Sundance. Replace GMS T13 & T14 with 2 new 600 MVA 500/230 kv transformers. 17. In Preparation For The Site C Generation Project Scheduled in Service Date: April 2023 Add 250 MVAR switchable shunt capacitor at Williston 500 kv substation Add static var compensator (SVC +250/-150 MVAR) at Williston 18. Sukunka MSC addition Schedule in Service date: August, 2017 Add a 230 kv, 45 MVAR MSC at Sukunka due to load increase. 19. Mount Lehman Substation Upgrade Schedule in Service date: October 2017 Replace existing 230 kv transformers with MVA and add 2 x 10 MVAR 25 kv capacitors. B. Additional Projects (Not Reported Previously): 20. West Kelowna Transmission Project (WKTP) Schedule in Service date: October 2020 This project will provide a second transmission line (138 or 230 kv) to BC Hydro s Westbank Substation (WBK), to build the supply redundancy for city of Kelowna area. 5

6 21. Southern Interior Series Compensation Project (SISC) Scheduled in Service Date: April 2025 The project is to add one 500 kv series capacitor station, on 5L98 transmission line from Nicola to Vaseux Lake. This project is a network reinforcement, tied to REV G6. 6

BC Hydro System 2017 Annual Progress Report

BC Hydro System 2017 Annual Progress Report March 14, 2017 Philip Augustin, P.E. Chair, Technical Studies Subcommittee 503-464-7783 philip.augustin@pgn.com Mr. Enoch Davies WECC Technical Staff 155 North 400 West, Suite 200 Salt Lake City, UT 84103-1114

More information

BC Hydro System 2011 Annual Progress Report

BC Hydro System 2011 Annual Progress Report March 1, 2011 Mr. Kyle R. Kohne, Chairman WECC Technical Studies Subcommittee Bonneville Power Administration P.O. Box 491 MS, TPP-OPP-3 Vancouver, WA 98666 Mr. Kent Bolton WECC Technical Staff 155 North

More information

Pacific Gas and Electric Company s Revised 2015 Annual Progress

Pacific Gas and Electric Company s Revised 2015 Annual Progress March 02, 2015 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Avista PO Box 3727 MSC-16 1411 East Mission Ave Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff 155 North 400 West

More information

Pacific Gas and Electric Company s Revised 2016 Annual Progress

Pacific Gas and Electric Company s Revised 2016 Annual Progress March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric

More information

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions. March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

2013 ANNUAL PROGRESS REPORT

2013 ANNUAL PROGRESS REPORT March 1, 2013 Mr. David Franklin, Chairman WECC Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768-2560 Mr. Enoch Davies WECC Technical Staff 155 North 400 West,

More information

March 7, Subject: Southern California Edison 2011 Annual Progress Report

March 7, Subject: Southern California Edison 2011 Annual Progress Report March 7, 2011 Mr. Kyle Kohne Mr. Kent Bolton Chair, WECC Technical Studies Subcommittee WECC Technical Staff Bonneville Power Administration University of Utah Research Park P.O. Box 61409 615 Arapeen

More information

BC HYDRO T&D SYSTEM OPERATIONS SYSTEM OPERATING ORDER 7T 30. NORTH COAST INTERCONNECTION Supersedes 7T-30 issued 07 June 2018

BC HYDRO T&D SYSTEM OPERATIONS SYSTEM OPERATING ORDER 7T 30. NORTH COAST INTERCONNECTION Supersedes 7T-30 issued 07 June 2018 BC HYDRO T&D SYSTEM OPERATIONS SYSTEM OPERATING ORDER 7T 30 NORTH COAST INTERCONNECTION Supersedes 7T-30 issued 07 June 2018 Review Year: 2022 APPROVED BY: Original signed by Bob Cielen for: Paul Choudhury

More information

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Status of PNM s Completed Transmission Construction Projects 11/30/2017 Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information

More information

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and

More information

welcome to the BC Hydro community open house

welcome to the BC Hydro community open house welcome to the BC Hydro community open house Dawson Creek/ Chetwynd Area Transmission ProjecT Open House welcome Dawson Creek/Chetwynd Area Transmission Project (DCAT) The purpose of this open house is

More information

Pacific Gas and Electric Company s 2013 Annual Progress Report

Pacific Gas and Electric Company s 2013 Annual Progress Report March 14, 2013 Mr. David Franklin Chair, WECC Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake

More information

TERRACE TO KITIMAT TRANSMISSION (TKT)

TERRACE TO KITIMAT TRANSMISSION (TKT) TERRACE TO KITIMAT TRANSMISSION (TKT) January 2014 OVERVIEW The need: Replace transmission lines between Terrace and Kitimat Options being studied by BC Hydro Discussion 2 SITUATION Kitimat area supplied

More information

Transmission Planning Attachment K Public Input Meeting

Transmission Planning Attachment K Public Input Meeting Transmission Planning Attachment K Public Input Meeting FERC 890 6 th Quarter Meeting May 25, 2011 Agenda Mountain Time Topic Presenter 1:00 1:15 Greetings and Introduction Dennis Desmarais 1:15 1:30 Attachment

More information

Facilities Study for Alberta to US Available Transfer Capability

Facilities Study for Alberta to US Available Transfer Capability Facilities Study for Alberta to US Available Transfer Capability Report No: NPP2002-05 June 3, 2002 System Planning & Grid Operations, Transmission Line of Business Engineering Services Executive Summary

More information

BC HYDRO REAL TIME OPERATIONS OPERATIONS SUPPORT SYSTEM OPERATING ORDER 7T-13

BC HYDRO REAL TIME OPERATIONS OPERATIONS SUPPORT SYSTEM OPERATING ORDER 7T-13 BC HYDRO REAL TIME OPERATIONS OPERATIONS SUPPORT SYSTEM OPERATING ORDER 7T-13 G.M. SHRUM / PEACE CANYON 500 kv SYSTEM Supersedes OO 7T-13 dated 07 November 2016 Effective Date: 06 February 2017 Review

More information

British Columbia Transmission Corporatlon ("BCTC") Transmission System Capital Plan F2006 to F2015 Amllcation

British Columbia Transmission Corporatlon (BCTC) Transmission System Capital Plan F2006 to F2015 Amllcation B-2 Marcel Reghelini Director, Regulatory Affairs Phone: 604 699-7331 Fax: 604 699-7537 E-mail: marcei.reghelini@bctc.com May 5,2005 Mr. Robert J. Pellatt Commission Secretary British Columbia Utilities

More information

BC HYDRO REAL TIME OPERATIONS SYSTEM OPERATING ORDER 7T-35. PEACE 138/230 kv NETWORK OPERATION Supersedes 7T-35 issued 15 June 2017

BC HYDRO REAL TIME OPERATIONS SYSTEM OPERATING ORDER 7T-35. PEACE 138/230 kv NETWORK OPERATION Supersedes 7T-35 issued 15 June 2017 BC HYDRO REAL TIME OPERATIONS SYSTEM OPERATING ORDER 7T-35 PEACE 138/230 kv NETWORK OPERATION Supersedes 7T-35 issued 15 June 2017 Review Year: 2021 Original signed by Brett Hallborg for: APPROVED BY:

More information

2018 Annual Progress Report to WECC Pacific Gas and Electric Company

2018 Annual Progress Report to WECC Pacific Gas and Electric Company 2018 Annual Progress Report to WECC Pacific Gas and Electric Company Waiver of Significant Transmission Project Status Table 1 and 2 update the planned transmission and generation projects, respectively,

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

Market Efficiency RTEP Proposal Window

Market Efficiency RTEP Proposal Window Market Efficiency RTEP Proposal Window Market Efficiency RTEP Proposal Window Status Window opened on 8/12/2013 Closed on 9/26/2013 17 individual proposals addressing congestion from Market Efficiency

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic December 19, 2017 First Preliminary Review Baseline Reliability and Supplemental Projects 2 The slide was previously presented at 8/31/2017 and is replaced by the

More information

Ambient PM 10 Monitoring Sechelt, B.C Update

Ambient PM 10 Monitoring Sechelt, B.C Update Ministry of Environment LOWER MAINLAND REGION Ambient PM 10 Monitoring Sechelt, B.C. 2004-2005 Update E N V I R O N M E N T A L Q U A L I T Y Library and Archives Canada Cataloguing in Publication Data

More information

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04 Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch

More information

Water Consumption Statistics Report

Water Consumption Statistics Report Water Consumption Statistics Report Operations and Maintenance Department 29 Edition TABLE OF CONTENTS 29 Water Consumption Statistics Report October 21 SYSTEM AND MUNICIPAL CONSUMPTION 29 GVWD Statistics

More information

Inventory Levels - All Prices. Inventory Levels - By Price Range

Inventory Levels - All Prices. Inventory Levels - By Price Range Inventory Levels - All Prices Idaho Falls Bonneville Total 3-Nov-17 198 128 326 2-Nov-18 155 134 289-11% Inventory Levels - By Price Range 3-Nov-17 2-Nov-18 0-100,000 17 11 100,001-125,000 15 9 125,001-150,000

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

Western Area Power Administration

Western Area Power Administration 2014/15 Integrated System (IS) 890 Local Planning Stakeholder Meeting #2 Western Area Power Administration Upper Great Plains Region Transmission Planning Stakeholder Meeting Wednesday, December 10 th,

More information

Market Efficiency Update

Market Efficiency Update Market Efficiency Update Transmission Expansion Advisory Committee July 13, 2017 Agenda Where we are in the process Interregional Projects Status RPM Projects Status Reevaluation Analysis Status Next Steps

More information

TERRACE TO KITIMAT TRANSMISSION PROJECT OPEN HOUSE 5 P.M. 8 P.M. GDS14-027

TERRACE TO KITIMAT TRANSMISSION PROJECT OPEN HOUSE 5 P.M. 8 P.M. GDS14-027 TERRACE TO KITIMAT TRANSMISSION PROJECT OPEN HOUSE 5 P.M. 8 P.M. WELCOME! Take a look at the storyboards and maps to learn more about the Terrace to Kitimat Transmission Project Why it is needed What options

More information

Sub Regional RTEP Committee - Southern. August 19, 2011

Sub Regional RTEP Committee - Southern. August 19, 2011 Sub Regional RTEP Committee - Southern August 19, 2011 2011 RTEP Analysis Summary 2010 2015 Project Updates 2016 Analysis NERC Category A, B NERC Category C (N-1-1 in progress) Load Deliverability Generator

More information

Transmission Planning. WECC 2014 Progress Report. March 14, 2014

Transmission Planning. WECC 2014 Progress Report. March 14, 2014 Transmission Planning WECC 2014 Progress Report March 14, 2014 Report Prepared By: Dennis Stevens -TPP (360) 619-6821 BPA TS TPP 2014-022 Page 1 Table of Contents 1 Introduction... 1 2 Planned Transmission

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

MTEP13 SPM #2- Central Region. March 25, 2013

MTEP13 SPM #2- Central Region. March 25, 2013 MTEP13 SPM #2- Central Region Ameren Missouri March 25, 2013 Ameren Missouri Project Review Central Region: Ameren Missouri Ameren Missouri has a total of 10 project proposals that are recommended for

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

Market Efficiency RTEP Proposal Window

Market Efficiency RTEP Proposal Window Market Efficiency RTEP Proposal Window Market Efficiency RTEP Proposal Window Status Window opened on 8/12/2013 Closed on 9/26/2013 17 individual proposals addressing congestion from Market Efficiency

More information

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget Project 1 of 28 Blythewood 115 kv Switching Station: Construct 03087A Construct Blythewood Switching Station with four 115 kv line terminals, with plans to expand to 230 kv at a future date. Fold in the

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

Transmission Planning Report

Transmission Planning Report Transmission Planning Report Board of Directors Meeting December 15, 2010 1 Overview Study Team Reports Puget Sound Area Study Team Northern Mid-Columbia Study Team Cross Cascades Study Team Centralia

More information

Inventory Levels - All Prices. Inventory Levels - By Price Range

Inventory Levels - All Prices. Inventory Levels - By Price Range Inventory Levels - All Prices Idaho Falls Bonneville Total 3-Mar-17 152 108 260 2-Mar-18 109 78 187-28% Inventory Levels - By Price Range 3-Mar-17 2-Mar-18 0-100,000 41 6 100,001-125,000 19 8 125,001-150,000

More information

Inventory Levels - All Prices. Inventory Levels - By Price Range

Inventory Levels - All Prices. Inventory Levels - By Price Range Inventory Levels - All Prices Idaho Falls Bonneville Total 7-Apr-17 154 111 265 6-Apr-18 113 91 204-23% Inventory Levels - By Price Range 7-Apr-17 6-Apr-18 0-100,000 36 10 100,001-125,000 13 9 125,001-150,000

More information

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study Cromby Units 1 and 2 and Eddystone Units 1 and 2 Deactivation Study Original Posting Date: March 2, 2010 Updated May 10, 2010 Updated June 7, 2010 Updated September 7, 2010 General PJM received notice

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS July 15, 2004 TABLE OF CONTENTS Page No. 1. Description of Pasadena s Transmission Lines and Facilities...1 A. Overview:... 1 B.

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JULY 2015) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget Project 1 of 34 Aiken Trans - Aiken Hampton 115 kv Line: Upgrade 1272A Upgrade the 115 kv line between Aiken and Aiken Hampton substations from 336 ACSR to 1272 ACSR. Total line length approximately 3.7

More information

New 115 kv Disconnect Switches at Bloomsburg MTS

New 115 kv Disconnect Switches at Bloomsburg MTS 115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115

More information

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 1 Reactive Power Compensation for Solar Power Plants Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 2 Objectives Refresh the basics of reactive power from a generator s perspective Regulatory

More information

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014 1 BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada IEEE PES Meeting July 2014 General BC Hydro Overview Crown Corporation Serving about 95% of province and 1.9 million customers

More information

Public Service Company of Colorado Transmission Projects Status. CCPG May 5, 2016

Public Service Company of Colorado Transmission Projects Status. CCPG May 5, 2016 Public Service Company of Colorado Transmission Projects Status CCPG May 5, 2016 1 Transmission Ownership Colorado 2016 Transmission Planning Drivers Load Service / Near-Term (1-5 years) TPL Studies (5

More information

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan XXXXX Kokish River Hydroelectric Project Interconnection Facilities Study and Project Plan March 16, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All

More information

PSCo 10-Year Transmission Plan/20-Year Scenario Assessment

PSCo 10-Year Transmission Plan/20-Year Scenario Assessment PSCo 10-Year Transmission Plan/20-Year Scenario Assessment May 2009 This report contains transmission planning data that may be conceptual in nature and is subject to change. The transmission projects

More information

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th Alex Bettencourt Managing Director National Association Made Up of Entire Industry Utilities Industry Academia / R&D

More information

Alternatives for meeting the need for transmission improvement described

Alternatives for meeting the need for transmission improvement described Alternatives for meeting the need for transmission improvement described 240 kv Alternative Looped System Southern Alberta Transmission Reinforcement For more information please contact the AESO at 1.888.866.2959,

More information

Interconnection System Impact Study

Interconnection System Impact Study Interconnection System Impact Study Pennask and Shinnish Creek Wind Project Report No: T&S Planning 2014 072 December 2014 DRAFT British Columbia Hydro and Power Authority British Columbia Hydro and Power

More information

PSE Attachment K Puget Sound Area Transmission Meeting

PSE Attachment K Puget Sound Area Transmission Meeting PSE Attachment K Puget Sound Area Transmission Meeting Stephanie Lu Senior Engineer December 15, 2011 Agenda Attachment K Review Economic Studies Process PSE Planning Process and Assumptions PSE Projects

More information

MUNICIPALITY OF ANCHORAGE MAYOR S ENERGY TASK FORCE. Joe Griffith, President - 1/11/2012

MUNICIPALITY OF ANCHORAGE MAYOR S ENERGY TASK FORCE. Joe Griffith, President - 1/11/2012 MUNICIPALITY OF ANCHORAGE MAYOR S ENERGY TASK FORCE Joe Griffith, President - 1/11/2012 1 ARCTEC MEMBERS Board of Directors Rick Schikora, Chairman Brad Janorschke, Vice Chairman Janet Kincaid, Secretary

More information

BUREAU OF Statistics Yukon Energy Facts

BUREAU OF Statistics Yukon Energy Facts BUREAU OF Statistics Yukon Energy Facts Electricity Generation YUKON ELECTRICAL COMPANY YUKON ENERGY CORPORATION YUKON TOTAL HYDRO THERMAL HYDRO THERMAL WIND HYDRO THERMAL WIND (MW.h) (MW.h) (MW.h) 26

More information

Modeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation. X. XU, M. BISHOP, D. OIKARINEN S&C Electric Company USA

Modeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation. X. XU, M. BISHOP, D. OIKARINEN S&C Electric Company USA , rue d Artois, F-8 PARIS CIGRE US National Committee http : //www.cigre.org Grid of the Future Symposium Modeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation X. XU,

More information

Central Okanagan Monthly Statistics Graphs January 2018

Central Okanagan Monthly Statistics Graphs January 2018 Monthly Statistics Graphs January January Statistics Table of Contents Table of Contents Single Family Monthly Listings by Price Single Family YTD Listings by Price Single Family Monthly Sales by Price

More information

WECC Regional Planning Review. Canada/Pacific Northwest Northern California Transmission Line Project. Technical Analysis Committee Report

WECC Regional Planning Review. Canada/Pacific Northwest Northern California Transmission Line Project. Technical Analysis Committee Report WECC Regional Planning Review Canada/Pacific Northwest Northern California Transmission Line Project Technical Analysis Committee Report November 1, 2007 Table of Content Summary...1 SECTION 1 SECTION

More information

Peace to Kelly Lake Capacitors Project. Stakeholder Communication and Consultation Summary APRIL 2018-AUGUST 2018 SEPTEMBER 2018 BCH18-940

Peace to Kelly Lake Capacitors Project. Stakeholder Communication and Consultation Summary APRIL 2018-AUGUST 2018 SEPTEMBER 2018 BCH18-940 Peace to Kelly Lake Capacitors Project Stakeholder Communication and Consultation Summary APRIL 2018-AUGUST 2018 SEPTEMBER 2018 BCH18-940 Table of contents Table of contents...1 Introduction.2 Overview...3

More information

3 Existing National Grid

3 Existing National Grid 3 Existing National Grid 3.1 Introduction 3.2 Load and generation 3.1 Introduction This chapter provides an overview of New Zealand s existing National Grid as at 28 February 2012 with respect to load

More information

2012 Water Consumption Statistics Report. Water Services Department

2012 Water Consumption Statistics Report. Water Services Department 212 Water Consumption Statistics Report Water Services Department Issued: December 213 TABLE OF CONTENTS 212 Water Consumption Statistics Report December 213 212 GVWD Statistics Book - Notes...3 Annual

More information

Vehicle insurance policies in force

Vehicle insurance policies in force in B.C. and by region Region 2013 2014 2015 2016 2017 Lower Mainland 1,577,000 1,612,000 1,691,000 1,730,000 1,760,000 Vancouver Island 549,000 558,000 578,000 592,000 596,000 Southern Interior 508,000

More information

Central Okanagan Monthly Statistics Graphs February 2019

Central Okanagan Monthly Statistics Graphs February 2019 Monthly Statistics Graphs February February Statistics Table of Contents Table of Contents Single Family Monthly Listings by Price Single Family YTD Listings by Price Single Family Monthly Sales by Price

More information

Offshore Wind: Grid Connection & Technology Options. Dietmar Retzmann Focus on. CO 2 Reduction Green Energy Megacities Security of Supply

Offshore Wind: Grid Connection & Technology Options. Dietmar Retzmann Focus on. CO 2 Reduction Green Energy Megacities Security of Supply Offshore Wind: Grid Connection & Technology Options Dietmar Retzmann 1 10-2011 E T PS S/Re Focus on CO 2 Reduction Green Energy Megacities Security of Supply 2 10-2011 E T PS S/Re 1 EWEA s 2030 Offshore

More information

James Graham, P.E. Standards Coordinator Transformers Committee

James Graham, P.E. Standards Coordinator Transformers Committee James Graham, P.E. Standards Coordinator Transformers Committee Standards approved PARs approved Ballot Status PARs Status Standards Status NEW Standards approved PC57.13.7 REVISIONS approved - Standard

More information

Sub-Regional RTEP Committee PJM South

Sub-Regional RTEP Committee PJM South Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates

More information

Interconnection Feasibility Study

Interconnection Feasibility Study Interconnection Feasibility Study Mount Mabel Wind Energy Project Report No: T&S Planning 2015-054 December 2015 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2015.

More information

CALENDAR OF FILING DEADLINES AND SEC HOLIDAYS

CALENDAR OF FILING DEADLINES AND SEC HOLIDAYS 2018 CALENDAR OF FILING S AND SEC HOLIDAYS USA: 305-396-1415 CAN: 778-819-6838 6800 SW 40th St #213 Miami, FL 33155, USA www.pubcoreporting.com 101 1500 Howe Street, Vancouver, BC, V6Z 2N1, Canada info@pubcoreporting.com

More information

Suicide Deaths in BC

Suicide Deaths in BC Suicide Deaths in BC 2006-2016 This report summarizes all deaths classified as suicide between January 1, 2006 and December 31, 2016. This includes cases that have been completed and those still under

More information

PET(S) FIRST & LAST NAME: January 2019

PET(S) FIRST & LAST NAME: January 2019 January 2019 1 2 3 4 5 New Year's Day 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 SPECIAL TE We will not have Doggie available during these dates: *3/29-4/7, 4/19-4/21, 5/24-5/27,

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016 Decision 21481-D01-2016 October 18, 2016 Alberta Utilities Commission Decision 21481-D01-2016 Proceeding 21481 Application 21481-A001 October 18, 2016 Published by the: Alberta Utilities Commission Fifth

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Algebra II Pacing Guide

Algebra II Pacing Guide Unit 13: Exploring a Business Venture (10 days) 8 May 13 - May 24 n/a MISD Pacing Guide Date Range Unit 01: Introduction to Functions in 15 Aug. 21 - Sept. 11 Sept. 12 Unit 02: Absolute Value Functions,,

More information

2013 ANNUAL PROGRESS REPORT

2013 ANNUAL PROGRESS REPORT Bonneville Power Administration 2013 ANNUAL PROGRESS REPORT Report Prepared By: Dennis Stevens Bonneville Power Administration Transmission Planning TPP/OPP-3 (360) 619-6821 BPA TS TPP 2013-018 Page 1

More information

April 10, Dear Customer:

April 10, Dear Customer: Dear Customer: April 10, Attached is the monthly water supply outlook and projected operations for Yellowtail Dam and Powerplant. If you have any questions or concerns, please feel free to call me at 406-247-7334

More information

June 30, Re: British Columbia Transmission Corporation ( BCTC ) Transmission System Capital Plan F2006 to F2015

June 30, Re: British Columbia Transmission Corporation ( BCTC ) Transmission System Capital Plan F2006 to F2015 B-9 Marcel Reghelini Director, Regulatory Affairs Phone: 604 699-7331 Fax: 604 699-7537 E-mail: marcel.reghelini@bctc.com June 30, 2005 Mr. Robert J. Pellatt Commission Secretary British Columbia Utilities

More information

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector HVDC Innovative Technology for Smart Grids and Super Grids CEO Power Transmission Solutions, Siemens Energy Sector BritNed: Pre-launch Press Event Maasvlakte, March 31, 2011 Siemens AG 2011 Energy Sector

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

Building Collaboration Between East African Nations via Transmission Interconnectors

Building Collaboration Between East African Nations via Transmission Interconnectors Building Collaboration Between East African Nations via Transmission Interconnectors Eng. Christian M.A. Msyani Ag. DEPUTY MANAGING DIRECTOR TRANSMISSION - TANESCO CONTENTS 1. TANESCO - Existing Power

More information

Process Timeline. Area Bubbles. Legend. Problem Area that have been resolved. Recurring Areas from previous System Assessment.

Process Timeline. Area Bubbles. Legend. Problem Area that have been resolved. Recurring Areas from previous System Assessment. Process Timeline Legend Problem Area that have been resolved Recurring Areas from previous System Assessment New Areas Area Bubbles Flows Modeled for One-Year Heavy Winter Peak Conditions Base Case Conditions

More information

2012 Integrated Resource Plan. Appendix. Portfolio Results

2012 Integrated Resource Plan. Appendix. Portfolio Results Appendix 6A Portfolio Results Table of Contents 1 Introduction... 1 2 Layout of the Portfolio Output Sheets... 1 3 Natural Gas-Fired Generation... 7 3.1 Modelling Assumptions... 7 3.2 Portfolio Output

More information

Smarter Network Storage UK first multi-purpose application of grid scale storage. Dr. Panos Papadopoulos, PhD, CEng

Smarter Network Storage UK first multi-purpose application of grid scale storage. Dr. Panos Papadopoulos, PhD, CEng Smarter Network Storage UK first multi-purpose application of grid scale storage Dr. Panos Papadopoulos, PhD, CEng UK Power Networks GENERATION TRANSMISSION DISTRIBUTION SUPPLY INDUSTRIAL COMMERCIAL RESIDENTIAL

More information

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document Decision 2013-127 Alberta Electric System Operator Saleski Transmission Project Needs Identification Document ATCO Electric Ltd. Saleski 901S Substation and 144-kV Transmission Line 7L142 Facility Application

More information

New Mexico Transmission Expansion Concepts For Wind Resources

New Mexico Transmission Expansion Concepts For Wind Resources New Mexico Transmission Expansion Concepts For Wind Resources May 2008 Update Electric Services Transmission Operations FOREWORD This document contains PNM s latest concepts for expanding the transmission

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82 Decision 21447-D01-2016 August 23, 2016 Decision 21447-D01-2016 Proceeding 21447 Application 21447-A001 August 23, 2016 Published by the: Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary,

More information

Designated Entity Pre-Qualification Materials. Exelon Corporation

Designated Entity Pre-Qualification Materials. Exelon Corporation Designated Entity Pre-Qualification Materials By Exelon Corporation On behalf of its affiliates Baltimore Gas and Electric Company, Commonwealth Edison Company, PECO Energy Company and Exelon Transmission

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010 FINAL FACILITY STUDY 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1 September 10, 2010 I. Introduction This is a revised facility study performed for Transmission Queue Request 2009

More information

Relative Power Factor Correction costs

Relative Power Factor Correction costs SSG REF: S026 Friday 19 th October 2007 TO: John Gleadow Senior Adviser Transmission Electricity Commission FROM: David Hume Ranil de Silva System Studies Group NZ Ltd Relative Power Factor Correction

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

7th Grade Social Studies Pacing Guide Units of Instruction MISD Pacing Guide Days Date Range Test Date

7th Grade Social Studies Pacing Guide Units of Instruction MISD Pacing Guide Days Date Range Test Date 7th Grade Social Studies MISD Pacing Guide Date Range Test Date Unit 01: Thinking Like a Historian (5 days for the entire unit) 5 Aug 27-31 Unit 02: Natural Texas and Its People 1200s-1800s (5 days for

More information

Dynamic Scheduling NI A F S NI S. Where:

Dynamic Scheduling NI A F S NI S. Where: Dynamic Scheduling FERC Order 888 defines dynamic scheduling: which is the electronic transfer of the time-varying electricity consumption corresponding to a load or the time-varying generation associated

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

METRO CNG Program Phase I Update. Customer Service Committee April 2014

METRO CNG Program Phase I Update. Customer Service Committee April 2014 METRO CNG Program Phase I Update Customer Service Committee April 2014 METRO CNG Program Background Bus purchase Short term solutions Long term plans Bus purchase options 2 METRO CNG Program April 2011

More information