Rocky Mountain Power Five Year Study Findings & Kick Off Meeting

Size: px
Start display at page:

Download "Rocky Mountain Power Five Year Study Findings & Kick Off Meeting"

Transcription

1 2000 PACIFICORP PAGE 1 Attachment K Rocky Mountain Power Five Year Study Findings & Kick Off Meeting Thursday, December

2 2000 PACIFICORP PAGE 2 Study Areas for 2016 Findings Reports Southeast, Utah Nicole DeGiulio Vernal, Utah Sachith Abayakoon Kickoff Studies Salt Lake Valley, Utah Nicole DeGiulio Wyoming West, Wyoming Carlton Jones

3 2000 PACIFICORP PAGE 3 Southeast Study Findings AREA PLANNER: NATHAN WILSON Prepared by: Nicole DeGiulio

4 2000 PACIFICORP PAGE 4 System Overview Covers 6,500 square miles Main source is Pinto (via 345 kv Huntington to Four Corners), Abajo & Moab 31 substations, 14 being customer owned Area has 345, 138, and 69 kv lines The study will concentrate on 138 kv and 69 kv lines and associated substations

5 2000 PACIFICORP PAGE 5 Load Growth Base System Loads o o Summer 2016: 90 MW Winter : 82 MW Growth: o Average Summer Percentage 1.8% o Average Winter Percentage 1.6% Projected System Loads o o Summer 2021: 103 MW Winter : 92 MW Distribution capacity: 77 MVA Area Utilization Factor: 35%

6 2000 PACIFICORP PAGE 6 N-0 Conditions Increase Capacity Seven Mile Upgrade, 2017 Seven Mile transformer loads to 106% (0.35 MVA) Solution: Replace existing transformer with a 0.5 MVA Regulators replacement is not required Estimated cost: $120k

7 2000 PACIFICORP PAGE 7 N-0 Conditions Increase Capacity Spanish Valley Upgrade, 2018 Spanish Valley transformer loads to 147% (9.2 MVA) after load is switched to it in 2018 Solution: Replace existing transformer with a 14 MVA. Regulators and fuse will have to be upgraded as well Estimated cost: $1.4m

8 2000 PACIFICORP PAGE 8 N-0 Conditions Improve Voltage Rattlesnake feeder issue, 2020 Rattlesnake has two 25 kv feeders. The RAT22 feeder will experience low voltage in 2020 Solution: Install new kv substation called Disappearing Angel. This will take load off of the feeder with low voltage issues Estimated cost: $1.67m

9 2000 PACIFICORP PAGE 9 N-1 Conditions There were no prominent N-1 conditions

10 2000 PACIFICORP PAGE 10 Total Construction Costs Construction Item 2017 CONSTRUCTION Cost Seven Mile ~ Increase Capacity $120k Spanish Valley ~ Increase Capacity 2018 CONSTRUCTION 2020 CONSTRUCTION Rattlesnake ~ Install Disappearing Angel substation TOTAL COST Subtotal $120k Subtotal Subtotal $1.40m $1.40m $1.67m $1.67m $3.185m

11 Any questions or comments? 2000 PACIFICORP PAGE 11

12 2000 PACIFICORP PAGE 12 Vernal Study Findings AREA PLANNER: NATHAN WILSON Prepared by: Sachith Abayakoon

13 2000 PACIFICORP PAGE 13 Vernal Study Area Town of Hanna in west Town of Vernal in east Bonanza Power Plant (Deseret Gas & Transmission) Approximately 53 miles northwest of Helper, Utah

14 2000 PACIFICORP PAGE 14 System Overview About 1,700 sq miles of territory located in Duchesne & Uintah counties Major communities served are Vernal & Maeser 11 substations, four customer owned Transmission voltages include 345,138, & 69 kv

15 2000 PACIFICORP PAGE 15 Vernal Area Generation Generation from Flaming Gorge contributes to the area Bonanza (owned by Deseret Generation & Transmission) is the only generation within the study area

16 2000 PACIFICORP PAGE 16 Load Growth Base System Loads o o Growth Summer 2016: 123 MW Winter : 145 MW o Average Summer Percentage 2.1% o Average Winter Percentage 2.3% Projected System Loads o o Summer 2021: 137 MW Winter : 163 MW Distribution capacity 60 MVA Area Utilization Factor: 71%

17 2000 PACIFICORP PAGE 17 N-0 Conditions There were no prominent N-0 conditions

18 2000 PACIFICORP PAGE 18 N-1 Conditions Improve Voltage Loss of UPALCO Bonanza 138 kv line, 2017 Low voltage in Myton (0.89 pu at 69 kv) Solution: Tap change from tap #1 to tap #2 Estimated cost: N/A

19 2000 PACIFICORP PAGE 19 N-1 Conditions Improve Voltage Loss of WAPA Vernal Ashley 138 kv line, 2017 The 69 kv system will experience low voltage Solution: Install a new two Stage 15 Mvar capacitor bank on Ashley 138 kv and remove one stage of capacitors on Ashley 69 kv Estimated cost: $1.9 M

20 2000 PACIFICORP PAGE 20 Total Construction Costs Construction Item 2017 CONSTRUCTION Cost Ashley ~ Adding 2 stage 15 Mvar each capacitor bank at Ashley 138 kv $1.9 m Subtotal $1.9 m TOTAL COST $1.9 m $18.425m

21 Any questions or comments? 2000 PACIFICORP PAGE 21

22 2000 PACIFICORP PAGE 22 Study Areas for 2016 Kickoff Studies Salt Lake Valley, Utah Nicole DeGiulio Wyoming West, Wyoming Carlton Jones

23 2000 PACIFICORP PAGE 23 Salt Lake Valley Study Service Area Area is located in Salt Lake County Main sources are Terminal, MidValley, 90 th South and Oquirrh. Local Generation is Gadsby and West Valley Generators.

24 2000 PACIFICORP PAGE 24 Salt Lake Valley Study Info Covers 350 square miles in Salt Lake County Serve 1 municipal customer: Murray City 117 substations, 26 are customer owned Transmission voltages are 46, 138 & 345 kv Study will concentrate on the 138 & 46 kv portion of the system

25 Any questions or comments? 2000 PACIFICORP PAGE 25

26 2000 PACIFICORP PAGE 26 Wyoming West Study Service Area Pinedale and industrial load in the north 230 kv feeds 69 kv through Chimney Butte Naughton Plant near Kemmerer 230 kv source from Eastern Wyoming 138 kv system feeds Evanston area

27 2000 PACIFICORP PAGE 27 Wyoming West Study Info Covers 9,000 square miles in Lincoln, Sublette, & Uinta Counties Main source is the 230 kv lines from Monument 36 substations, 17 are customer owned Transmission voltages are 69, 138, and 230 kv Load is approximately 90% industrial Generation at Naughton, Mountain Wind, and Hinshaw (740, 140, and 125 MW)

28 Any questions or comments? 2000 PACIFICORP PAGE 28

Rocky Mountain Power Five Year Study Findings & Kick Off Meeting

Rocky Mountain Power Five Year Study Findings & Kick Off Meeting 2000 PACIFICORP PAGE 1 Attachment K Rocky Mountain Power Five Year Study Findings & Kick Off Meeting Thursday, June 9 th 2016 2000 PACIFICORP PAGE 2 Rocky Mountain Power Area Transmission Planning Manager:

More information

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions. March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating

More information

Q0044 interconnection at

Q0044 interconnection at Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description

More information

Craig Quist Craig Quist

Craig Quist Craig Quist TRANSMISSION PLANNING Craig Quist, Manager Transmission Development & Planning PacifiCorp 1407 West North Temple, Suite 275 Salt Lake City, Utah 84140 801-220-4264 FAX 801-220-2842 craig.quist@pacificorp.com

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Transmission Planning Attachment K Public Input Meeting

Transmission Planning Attachment K Public Input Meeting Transmission Planning Attachment K Public Input Meeting FERC 890 6 th Quarter Meeting May 25, 2011 Agenda Mountain Time Topic Presenter 1:00 1:15 Greetings and Introduction Dennis Desmarais 1:15 1:30 Attachment

More information

Date: March 15, Mr. Enoch Davies WECC Technical Staff 155 North 400 West, Suite 200 Salt Lake City, Utah

Date: March 15, Mr. Enoch Davies WECC Technical Staff 155 North 400 West, Suite 200 Salt Lake City, Utah TRANSMISSION PLANNING Craig Quist Director of Area/Transmission Planning East PacifiCorp 1407 West North Temple, Suite 275 Salt Lake City, Utah 84116 (801)220-4264 PH (801)220-2842 FAX Date: March 15,

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

North Oregon Coast Area Study. Adam Lint

North Oregon Coast Area Study. Adam Lint North Oregon Coast Area Study Adam Lint PAGE 2 North Oregon Coast System Overview - Clatsop Study Covers: Transmission Switching Stations (Clatsop District): Astoria Lewis and Clark 115 kv Distribution

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

2-MWh Flow Battery Application by PacifiCorp in Utah Mark T. Kuntz VP Marketing & Business Development

2-MWh Flow Battery Application by PacifiCorp in Utah Mark T. Kuntz VP Marketing & Business Development 2-MWh Flow Battery Application by PacifiCorp in Utah Mark T. Kuntz VP Marketing & Business Development mkuntz@vrbpower.com California Energy Commission Staff Workshop: Meeting California s Electricity

More information

Wyoming Energy Projects

Wyoming Energy Projects Wyoming Energy Projects Wyoming Infrastructure Authority Spring Conference March 28-29, 2019 PacifiCorp Overview Two divisions Rocky Mountain Power and Pacific Power 5600 Employees 1.9 million electricity

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

2013 ANNUAL PROGRESS REPORT

2013 ANNUAL PROGRESS REPORT March 1, 2013 Mr. David Franklin, Chairman WECC Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768-2560 Mr. Enoch Davies WECC Technical Staff 155 North 400 West,

More information

Transmission Planning Report

Transmission Planning Report Transmission Planning Report Board of Directors Meeting December 15, 2010 1 Overview Study Team Reports Puget Sound Area Study Team Northern Mid-Columbia Study Team Cross Cascades Study Team Centralia

More information

Customer Charge or Minimum Bill. Total Average Annual Bill (9 Dth) Total Volumetric Rate*

Customer Charge or Minimum Bill. Total Average Annual Bill (9 Dth) Total Volumetric Rate* Residential Gas Rates for Wyoming Regulated Utilities Gas Rates are in effect as of: 11/03/17 Estimates of Seasonal Bills (illustrational purposes only) Customer Charge or Minimum Bill Total Volumetric

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Process Timeline. Area Bubbles. Legend. Problem Area that have been resolved. Recurring Areas from previous System Assessment.

Process Timeline. Area Bubbles. Legend. Problem Area that have been resolved. Recurring Areas from previous System Assessment. Process Timeline Legend Problem Area that have been resolved Recurring Areas from previous System Assessment New Areas Area Bubbles Flows Modeled for One-Year Heavy Winter Peak Conditions Base Case Conditions

More information

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Local Transmission Plan. October 11, 2013 Revised August 25, 2014 Local Transmission Plan October 11, 2013 Revised August 25, 2014 2 Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

Salt Lake County Electrical Plan Task Force October Douglas N. Bennion, P.E. Vice President Rocky Mountain Power

Salt Lake County Electrical Plan Task Force October Douglas N. Bennion, P.E. Vice President Rocky Mountain Power Salt Lake County Electrical Plan Task Force October 2009 Douglas N. Bennion, P.E. Vice President Rocky Mountain Power 1 Rocky Mountain Power s Bright History In 1881, Salt Lake City became the fifth city

More information

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Status of PNM s Completed Transmission Construction Projects 11/30/2017 Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

West Station-West Cañon 115 kv Transmission Project

West Station-West Cañon 115 kv Transmission Project West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon

More information

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30)

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30) TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30) Submitted to TOT1A Stakeholders and TOT1A Interconnected Utilities And Western Electricity Coordinating Council June 6, 2013

More information

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No. 17-035-40 Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct

More information

BC Hydro System 2011 Annual Progress Report

BC Hydro System 2011 Annual Progress Report March 1, 2011 Mr. Kyle R. Kohne, Chairman WECC Technical Studies Subcommittee Bonneville Power Administration P.O. Box 491 MS, TPP-OPP-3 Vancouver, WA 98666 Mr. Kent Bolton WECC Technical Staff 155 North

More information

Wyoming Cost of Living Index for the Second Quarter of 2012

Wyoming Cost of Living Index for the Second Quarter of 2012 State of Wyoming Department of Administration and Information Economic Analysis Division 2800 Central Avenue Cheyenne, WY 82002-0060 E-mail: ai-ead-info@wyo.gov http://eadiv.state.wy.us Ph. (307) 777-7504

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

Chapter 7 - Appendix A

Chapter 7 - Appendix A Chapter 7 - Appendix A Transmission and Distribution Supplemental Information Table 7A.1 MTEP Transmission Projects in Missouri 1 Project Approved Project Title Project Description Category Estimated Cost

More information

Western Area Power Administration Rocky Mountain Region (LAPT) Network Integrated Transmission Service. Designated Network Resources

Western Area Power Administration Rocky Mountain Region (LAPT) Network Integrated Transmission Service. Designated Network Resources Customer Name Basin Electric Cheyenne Power and Light City of Fort Morgan & Estimated Maximum Resource MW Point of Receipt Delivering Party & Voltage Antelope Valley 2 Yellowtail Basin Electric 115 kv

More information

747 ACRES LAND FOR SALE

747 ACRES LAND FOR SALE 747 ACRES LAND FOR SALE 3400 NORTH PONY EXPRESS PARKWAY, EAGLE MOUNTAIN, UTAH 84005 Salt Lake Count y Lehi 73 Sar atoga Spring s Eagle Mountain Blvd g Eagle Mountain Eagle Mountain Blvd Pony Express Pkwy

More information

TransWest Express Project

TransWest Express Project TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company

More information

March 7, Subject: Southern California Edison 2011 Annual Progress Report

March 7, Subject: Southern California Edison 2011 Annual Progress Report March 7, 2011 Mr. Kyle Kohne Mr. Kent Bolton Chair, WECC Technical Studies Subcommittee WECC Technical Staff Bonneville Power Administration University of Utah Research Park P.O. Box 61409 615 Arapeen

More information

WYOMING COST OF LIVING FOR THE SECOND QUARTER 2010

WYOMING COST OF LIVING FOR THE SECOND QUARTER 2010 State of Wyoming Department of Administration and Information Economic Analysis Division 2800 Central Avenue Cheyenne, WY 82002-0060 E-mail: ead@wyo.gov http://eadiv.state.wy.us Ph. (307) 777-7504 Fax

More information

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget Project 1 of 28 Blythewood 115 kv Switching Station: Construct 03087A Construct Blythewood Switching Station with four 115 kv line terminals, with plans to expand to 230 kv at a future date. Fold in the

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic December 19, 2017 First Preliminary Review Baseline Reliability and Supplemental Projects 2 The slide was previously presented at 8/31/2017 and is replaced by the

More information

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012 First Energy Generator Deactivation Request - January 2012 Deactivation Study Results and Required Upgrades April 25, 2012 General PJM received a notice on January 26, 2012 from FirstEnergy of its intent

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic August 24, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects from the competitive planning

More information

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M of Need In-service Cost Alternatives Service Projects in PG&E Service Territory Mare Island - Ignacio 115 kv NERC Category 2010 Reconductor the limiting 19 $19M Connect Highway May 2012 Line re-rates and

More information

Transmission Planning. WECC 2014 Progress Report. March 14, 2014

Transmission Planning. WECC 2014 Progress Report. March 14, 2014 Transmission Planning WECC 2014 Progress Report March 14, 2014 Report Prepared By: Dennis Stevens -TPP (360) 619-6821 BPA TS TPP 2014-022 Page 1 Table of Contents 1 Introduction... 1 2 Planned Transmission

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

2013 ANNUAL PROGRESS REPORT

2013 ANNUAL PROGRESS REPORT Bonneville Power Administration 2013 ANNUAL PROGRESS REPORT Report Prepared By: Dennis Stevens Bonneville Power Administration Transmission Planning TPP/OPP-3 (360) 619-6821 BPA TS TPP 2013-018 Page 1

More information

Business Park North Muskegon County, MI

Business Park North Muskegon County, MI Business Park North Muskegon County, MI OVERVIEW January 1, 2017 CONTACT US Scott Corrin, Economic Development Manager 517-374-2248 scott.corrin@cmsenergy.com Consumers Energy Business Center 800-805-0490

More information

Proposed New Construction for

Proposed New Construction for Tri-State Generation and Transmission Association, Inc. Colorado PUC E-Filings System Proposed New Construction for 2016 2019 Colorado PUC Rule 3206 Application April 28, 2016 TABLE OF CONTENTS A) Projects

More information

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment For NPCC Governmental / Regulatory Affairs Advisory Group May 21 st, 2009 ON IT Executive Summary Engineers from Con

More information

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project. Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project April 23, 2003 Introduction Eurus originally requested an interconnection

More information

ROCKY MOUNTAIN POWER A DIVISION OF PACIFICORP

ROCKY MOUNTAIN POWER A DIVISION OF PACIFICORP ROCKY MOUNTAIN POWER A DIVISION OF PACIFICORP January 29, 2014 201 South Main, Suite 2300 Salt Lake City, Utah 84111 VIA ELECTROl.fiC FILI1VG AND OVERNIGHT DELIVERY Wyoming Public Service Commission 2515

More information

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives Addendum San Juan Major Project Tri-State Generation and Transmission Association Power System Planning December, 2008

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

Targeted Application of STATCOM Technology in the Distribution Zone

Targeted Application of STATCOM Technology in the Distribution Zone Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric

More information

Food and Transportation Drive Inflation for the Second Quarter of 2011

Food and Transportation Drive Inflation for the Second Quarter of 2011 State of Wyoming Department of Administration and Information Economic Analysis Division 2800 Central Avenue Cheyenne, WY 82002-0060 E-mail: ai-ead-info@wyo.gov http://eadiv.state.wy.us Ph. (307) 777-7504

More information

Muskegon Waste Water Treatment Site Muskegon County, MI

Muskegon Waste Water Treatment Site Muskegon County, MI Muskegon Waste Water Treatment Site Muskegon County, MI OVERVIEW January 1, 2017 CONTACT US Scott Corrin, Economic Development Manager 517-374-2248 scott.corrin@cmsenergy.com Consumers Energy Business

More information

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04 Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch

More information

Western Area Power Administration

Western Area Power Administration 2014/15 Integrated System (IS) 890 Local Planning Stakeholder Meeting #2 Western Area Power Administration Upper Great Plains Region Transmission Planning Stakeholder Meeting Wednesday, December 10 th,

More information

City of Ironton WWTP. General Information County: Lawrence Counties Served: Lawrence. Type of System: Public: X Private: Year Established: 1953

City of Ironton WWTP. General Information County: Lawrence Counties Served: Lawrence. Type of System: Public: X Private: Year Established: 1953 City of Ironton WWTP General Information County: Lawrence Counties Served: Lawrence Type of System: Public: X Private: Year Established: 1953 Year of Upgrades: 1987 EPA District: Southeast Treatment Plant

More information

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget Project 1 of 34 Aiken Trans - Aiken Hampton 115 kv Line: Upgrade 1272A Upgrade the 115 kv line between Aiken and Aiken Hampton substations from 336 ACSR to 1272 ACSR. Total line length approximately 3.7

More information

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving

More information

MEETING AGENDA. Western Area Power Administration Rocky Mountain Region. Transmission Planning Stakeholder Meeting

MEETING AGENDA. Western Area Power Administration Rocky Mountain Region. Transmission Planning Stakeholder Meeting MEETING AGENDA Western Area Power Administration Rocky Mountain Region Transmission Planning Stakeholder Meeting Western s RMR Regional Office 5555 East Crossroads Boulevard, Loveland, CO 80538 June 23,

More information

New 115 kv Disconnect Switches at Bloomsburg MTS

New 115 kv Disconnect Switches at Bloomsburg MTS 115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

PG&E s 2012 Request Window Proposals

PG&E s 2012 Request Window Proposals 1 PG&E s 2012 Request Window Proposals Central Valley Patrick Tan Transmission System Planning PG&E September 27, 2012 Transmission Projects Overview 2 Projects Seeking CAISO Approval Pease 115/60 kv Transformer

More information

South Dakota 890 Study

South Dakota 890 Study South Dakota 890 Study September 16, 2011 South Dakota 890 Study Presentation of 890 Study results from 2011 Includes WAPA suggested system improvements and timelines Stakeholder Feedback Questions? 2

More information

Public Service Company of Colorado System Impact Study Load Interconnection Request for a 50 MVA Load Near Collbran

Public Service Company of Colorado System Impact Study Load Interconnection Request for a 50 MVA Load Near Collbran System Impact Study_50 MVA Load Interconnnection Request Near Collbran.doc Public Service Company of Colorado System Impact Study Load Interconnection Request for a 50 MVA Load Near Collbran PSCo Transmission

More information

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006 Final System Impact Study for Sierra Pacific Industries 31 MW Generation Project Mount Vernon, WA November 16, 2006 Puget Sound Energy, Inc. Electric Transmission Department 1 1. Introduction On October

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic November 04, 2013 2013 RTEP Baseline Analysis Update 11/04/2013 AE Transmission Zone Cost Change for B2354 Install second 230/69kV transformer and 230kV circuit

More information

Wyoming electricity use is growing

Wyoming electricity use is growing Wyoming electricity use is growing 12,000 $40 gigawatt-hours 11,000 10,000 9,000 8,000 7,000 6,000 5,000 $38 $36 $34 $32 $30 $28 $26 $24 $22 gross state product (economic growth) ($ billions) 4,000 2004

More information

Appendix B. Summary of Changes to the Year Assessment

Appendix B. Summary of Changes to the Year Assessment Appendix B Summary of Changes to the 2003 10- Assessment For the below tables, the following color-coding scheme was utilized for indicating what type of change has been made to the 10- Assessment from

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Gillette Lost the Most Residents in 2017

Gillette Lost the Most Residents in 2017 FOR IMMEDIATE RELEASE Thursday, May 24, 2018 Contact: Dr. Wenlin Liu, Chief Economist Gillette Lost the Most Residents in 2017 CHEYENNE Cities that lost the most residents in Wyoming between July 1, 2016

More information

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 14, 2005 1 2004-06 EGSI-TX Transmission Western Region Reliability

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation 1. Description In the 2013-2014 Transmission Planning Cycle, the ISO approved the construction

More information

APPENDIX E: Project Need and Description

APPENDIX E: Project Need and Description APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Lakeville 115 kv Bus Upgrade Installation of a sectionalizing breaker to be installed on 115 kv bus section

More information

Pacific Gas and Electric Company s Revised 2016 Annual Progress

Pacific Gas and Electric Company s Revised 2016 Annual Progress March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric

More information

Energy from Waste Grid Connections

Energy from Waste Grid Connections Energy from Waste Grid Connections Catherine Cleary Grid Connection Lead TNEI Services catherine.cleary@tnei.co.uk 0161 233 4839 Overview Introduction to the UK Electricity Network Key Grid Connection

More information

APPENDIX E: Project Need and Description

APPENDIX E: Project Need and Description APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Tyler 60 kv Shunt Capacitor Installation of a 2x10 MVAR capacitor bank at Tyler 60 kv bus Objectives

More information

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent

More information

Four Corners Queue Transmission Interconnection Study

Four Corners Queue Transmission Interconnection Study Four Corners Queue Transmission Interconnection Study Facility Study Results By Arizona Public Service Company Transmission Planning & Interconnection Development March 22, 2016 Version 1 FACILITIES STUDY

More information

Unrestricted. Air Core Reactor Applications Current Limiting Reactors

Unrestricted. Air Core Reactor Applications Current Limiting Reactors Unrestricted Air Core Reactor Applications Current Limiting Reactors Faults on Electrical System - Basic Concepts Three major concerns arise from this scenario: 1- The mechanical stresses on the transformer

More information

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study Cromby Units 1 and 2 and Eddystone Units 1 and 2 Deactivation Study Original Posting Date: March 2, 2010 Updated May 10, 2010 Updated June 7, 2010 Updated September 7, 2010 General PJM received notice

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Sub-Regional RTEP Committee PJM South

Sub-Regional RTEP Committee PJM South Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates

More information

Southeastern Region Transmission Planning. 10 Year Transmission Expansion Plan

Southeastern Region Transmission Planning. 10 Year Transmission Expansion Plan 10 Year Transmission Expansion Plan Disclaimer The projects described in this presentation represent the current ten (10) year expansion plan. The expansion plan is periodically reviewed and may be revised

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

Local Transmission Plan

Local Transmission Plan 2012 2013 Local Transmission Plan Idaho Power Delivery Planning Final Report December 2013 2013 Idaho Power Idaho Power Company TABLE OF CONTENTS Table of Contents... i List of Tables... ii List of Figures...

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

PSCo 10-Year Transmission Plan/20-Year Scenario Assessment

PSCo 10-Year Transmission Plan/20-Year Scenario Assessment PSCo 10-Year Transmission Plan/20-Year Scenario Assessment May 2009 This report contains transmission planning data that may be conceptual in nature and is subject to change. The transmission projects

More information

TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis

TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis July 25, 2018 Table of Contents 1. Introduction... 5 1.1. Project Description and

More information

Ten-year Plan. Figure 1 and Table 1. Each of the facilities shown in the plan is described in greater depth in the last appendix of this report.

Ten-year Plan. Figure 1 and Table 1. Each of the facilities shown in the plan is described in greater depth in the last appendix of this report. Ten-year Plan As a result of the analysis completed for the 2009 System Assessment, the follow-up sensitivity studies, analysis completed by the study teams, and individual planning participant studies,

More information

Dynamic Reactive Power Control for Wind Power Plants

Dynamic Reactive Power Control for Wind Power Plants Dynamic Reactive Power Control for Wind Power Plants Ernst Camm, Charles Edwards, Ken Mattern, Stephen Williams S&C Electric Company, 6601 N. Ridge Blvd, Chicago IL 60626 USA ecamm@sandc.com, cedwards@sandc.om,

More information

Food Prices Propel Inflation for the Fourth Quarter of 2011

Food Prices Propel Inflation for the Fourth Quarter of 2011 State of Wyoming Department of Administration and Information Economic Analysis Division 2800 Central Avenue Cheyenne, WY 82002-0060 E-mail: ai-ead-info@wyo.gov http://eadiv.state.wy.us Ph. (307) 777-7504

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information