1 South Dakota 890 Study September 16, 2011

2 South Dakota 890 Study Presentation of 890 Study results from 2011 Includes WAPA suggested system improvements and timelines Stakeholder Feedback Questions? 2

3 Western South Dakota 3

4 Western South Dakota System Improvements During 2011 Increased size of Rapid City Capacitor Banks Capacitors were increased from MVAR to MVAR April 2011 Installation ti of Rapid City Area UVLS Three stages of UVLS were installed at the Rapid City Substation in May 2011 to shed load if 115 kv voltage remains below 0.88 pu for 3 seconds Installation of Pierre Area UVLS Three stages of UVLS are installed at the Pierre Substation in May 2011 to shed load if 115 kv voltage remains below 0.88 pu for 3 seconds One stage of UVLS is installed at the Irv Simmons Substation in May 2011 to shed load if 115 kv voltage remains below 0.88 pu for 3 seconds Bus Replacement at Midland Substation Replaced limiting buswork and jumpers May 2011 Bus Replacement at Wall Substation Replaced limiting buswork and jumpers May 2011 Bus Replacement at Wicksville Substation Replaced limiting buswork and jumpers May 2011 Raised limiting structures on Philip Wicksville Wall New Underwood 115 kv line Line is at conductor thermal limit of 90 MVA June 2011 Special high temperature temporary jumper ratings developed for Fort Randall 95 MVA Continuous, 124 MVA 2 hour emergency Installation ti of Mission i Capacitors Two 8.5 MVAR capacitors installed at Mission September

5 Western South Dakota Near Term Issues (2011) Oahe Area Deficiencies Prior outage of 230/115 kv Auto-Transformer Prior outage of Unit 1 Prior outage of Oahe Ash Tap Prior outage of Oahe Irv Simmons 115 kv Bus fault Can cause low voltages in the Pierre Area Can overload Oahe Ash Tap or Oahe Irv Simmons lines Corps plans to populate existing Double Breaker/Double Bus 115 and 230 kv bays and install a second 230/115 kv transformer This fixes the 115 kv bus fault and the prior outage issues with the Auto-Transformer and Unit 1 5

6 Western South Dakota Near Term Issues (2011) Oahe Area Deficiencies (cont.) Work at Oahe Substation does not address voltage and thermal issues caused by the prior outage either Pierre Ash Tap or Pierre Irv Simmons An additional transmission line is required into the Pierre load pocket Proposed solution is to abandon Ash tap and tie Ash Street directly to Oahe providing a three separate sources to the Pierre load pocket 6

7 Western South Dakota Near Term Issues (2011) 7

8 Western South Dakota Near Term Issues (2011) Rapid City Area Deficiencies Loss of New Underwood KV1A 230/115 kv Transformer 115 kv Bus fault 230 kv Bus fault Prior outage of New Underwood Rushmore Prior outage of New Underwood Ellsworth or Ellsworth Rapid City Can cause low voltages in the Rapid City Area Rapid City area improvements are planned in four phases 8

9 Western South Dakota Near Term Issues (2011) Phase 1 (In Service before Summer 2012): Add additional UVLS Phase 2 (In Service before Summer 2013): Installation of a parallel 230/115 kv 200 MVA transformer (KV2A) at New Underwood Installation of series bus sectionalizing breakers at New Underwood 115 kv bus between 1462 and 1562 One bus section would contain KV1A and the Rushmore line Second bus section would contain the Ellsworth line and the Wicksville/Wall/Philip line Reconfiguration of New Underwood 230 kv bus Possibly series bus sectionalizing breakers between 582 and 682 Phase 3 (In Service before 2015): Installation of a 230/115 kv 200 MVA transformer at RCDC tie Construction of a 115 kv RCDC-Rapid City line Possibility of constructing 230 double circuit to be determined Potential Removal of UVLS Phase 4 (future): Close 230 kv loop at Rapid City DC tie Replace existing 230/115 kv 100 MVA transformer (KV1A) at New Underwood with a 200 MVA transformer 9

10 Western South Dakota Near Term Issues (2011) Rapid City Area voltage issues 10

11 Western South Dakota Mid Year Issues ( ) Uprate Oahe Philip Tap New Underwood 230 kv line Also identified in Keystone XL Study Currently limited to 240 MVA by CT settings New limit will be 320 MVA CT limit CT change should be completed before new Philip 200 MVA Transformer is installed Uprate Eagle Butte - Oahe 115 kv line CT tap change at Oahe (currently limits to 60 MVA) CT tap change at Eagle Butte (currently limits to 80 MVA) New limit will be 104 MVA jumpers 11

12 Western South Dakota Mid Year Issues ( ) Uprate New Underwood Rapid City 115 kv lines New Underwood Rushmore Rapid City New Underwood Ellsworth Ellsworth Rapid City Currently limited it by 80 MVA CT settings Increase rating to conductor rating Will require a LIDAR study 12

13 Western South Dakota Mid Year Issues ( ) A major rebuild of Fort Randall Substation is planned by the Corps beginning in 2012 Replace buswork and jumpers Install dedicated transformer breakers for both 230/115 kv transformers Targeted completion date of 2015 High temperature jumper ratings have been implemented for limiting iti substation ti conductors until rebuild is complete 95 MVA continuous 124 MVA 2-hour emergency 13

14 Western South Dakota Mid Year Issues ( ) A new Lower Brule substation is planned just outside of Big Bend on the Big Bend Fort Thompson line in 2013 A Lower Brule Witten 230 kv line is also planned A 200 MVA 230/115 kv transformer will be installed at Witten A SPS or Generator dropping scheme will be needed for loss of Lower Brule Fort Thompson UVLS is required at Keystone XL PS 21 near Gregory for the prior outage of the new 230 kv line 14

15 Western South Dakota Out Year Issues ( ) Replacement of Martin 115/34.5 kv transformer Required before 2021 Sizing to be determined at a later date Replacement of Newell 115/69 kv transformer Required before 2021 Sizing to be determined at a later date 15

16 Summary of New Facilities Continue with Oahe improvements (completion 2015) Continue with Fort Randall improvements (completion 2015) Construct Oahe Ash Tap 115 kv line (In service 2012) Uprate Oahe Philip Tap New Underwood 230 kv line (2012) Uprate Oahe Eagle Butte 115 kv line (2012) Study Nebraska Panhandle for system improvements in 2012 Install SPS/Generator Dropping for Lower Brule Witten 230 kv line (2013) 16

17 Action Items Install additional UVLS in the Rapid City Load Pocket (Early 2012) Determine ROW options in the Rapid City area for future 230 kv transmission (2011) Begin study based on available transmission routes Study Lower Brule SPS/Generator dropping (2012) Determine New Underwood 230 kv bus arrangement (double breaker/double bus or series bus sectionalizing breakers) 17

18 Questions? 18

19 Eastern South Dakota 19

20 Eastern South Dakota System Improvements During 2011 Installation of Eagle Area UVLS on 69 kv system NIPCO and MEC installed a load dropping scheme to shed load during critical contingencies i at Eagle substation. ti NIPCO and MEC are studying additional system improvements in the area to reinforce the 69 kv system Replacement of Sioux City 161/69 kv transformer KV3A 74 MVA transformer replaced with 100 MVA transformer Installation of a 20 MVAR reactor at Sully Buttes Required for the outage of Oahe Sully Buttes Increased Huron Redfield Groton 115 kv line rating Increased from 80 MVA to 120 MVA Increased Watertown Brookings #2 line rating Increased from 80 MVA to 120 MVA 20

21 Eastern South Dakota Near Term Issues (2011) Ordway Area issues Ordway substation serves load in the Aberdeen area Loss of Groton Ordway leaves Ordway load hanging radially from Jamestown Can be masked in off-the-shelf powerflow cases by waste heat generation at Ordway and a wind farm at Edgeley East River has added 12 MVAR capacitors on the 69 kv system Were not previously modeled Capacitors and transmission improvements recommended To Jamestown 21

22 Eastern South Dakota Near Term Issues (2011) Add a capacitor at Ordway Not sufficient to keep voltages at an acceptable level as load continues to grow Large capacitors would only be required under prior outage conditions May have to be automatically fast switched with loss of Groton Ordway line 10 MVAR is suggested in combination with transmission improvements Additional 10 MVAR may be required as loads continue to increase Construct Ordway Aberdeen 115 kv line Provides an additional source into the Ordway area Also helps to support the Aberdeen area for loss of Groton Aberdeen 115 kv line 22

23 Eastern South Dakota Near Term Issues (2011) Sioux Falls Area Issues Sioux Falls 230/115 kv transformers are near the end of their expected life span Breaker failure of the 230 kv bus sectionalizing breaker results in low voltages on the 115 kv system Loss of one transformer can overload the second transformer in the out year cases Circulating VAR/voltage set point issue between Western s Sioux Falls and with NSP s Split Rock Sioux Falls transformers are 220/115 kv transformers The 115 kv Sioux Falls Lawrence line is operated normally open 23

24 Eastern South Dakota Near Term Issues (2011) High flows between Western and NSP load up the 230/115 kv transformer at Split Rock and the 230/115 kv transformers at Sioux Falls The Sioux Falls Lawrence 115 kv line is operated normally open due to historical post contingent loading concerns Closing the Sioux Falls Lawrence 115 kv line reduces transformer loading while having a minor effect on net powerflow between Western and NSP Power flows on both the 230 and 115 paths reducing 230/115 kv transformer loading at both Sioux Falls and Split Rock Closing the Sioux Falls Lawrence line helps both Western and NSP under prior outage conditions When Sioux Falls Lawrence line is closed transformer sizing requirements are reduced 24

25 Action Items Size Sioux Falls transformers and determine replacement timeline 25

26 Eastern South Dakota Near Term Issues (2011) Sioux Falls Gavins Point Loop Issues Loss of either end of the loop results in low voltages when a large amount of load is served radially Closing the Sioux Falls Lawrence line helps voltages for loss of the Gavins Point end of the loop A capacitor is suggested for N-1 low voltage issues Transmission improvements are suggested to prevent load from being dropped under N conditions 26

27 Eastern South Dakota Near Term Issues (2011) Add 20 MVAR capacitor bank at Spirit Mound or Beresford substation Increases voltages during a single contingency Add Rasmussen EJ Manning 115 kv line Creates a third source into the load pocket to increase reliability under prior outages Requires the addition of a 230/115 kv transformer and a 115 kv yard at Rasmussen Rasmussen Vermillion line is also an option 27

28 Eastern South Dakota Near Term Issues (2011) Replacement of Creston transformers Currently scheduled for 2012 Operating guide has been created to prevent violations until improvements are completed Dedicated transformer breakers will be added when transformers are replaced Existing 56 MVA transformers will be replaced with 150 MVA transformers Dedicated transformer breakers will be installed A 69 kv bus tie breaker will be installed A 69 kv capacitor will be installed 28

29 Eastern South Dakota Near Term Issues (2011) Eagle Substation Issues Breaker failure can de- energize the entire substation and cause low voltages on the 69 kv system NIPCO and MEC have installed a load dropping scheme on the 69 kv system NIPCO and MEC are studying options for additional transmission for the 69 kv system No Bulk Electric System problems for these contingencies Large load pocket on networked 69kV system 29

30 Eastern South Dakota Mid Year Issues ( ) Replacement of Spencer transformers Currently scheduled for 2013 Dedicated transformer breakers will be added when transformers are replaced Capacitor will be added to the 161 kv bus Transformer sizing will be finalized in a supplemental study Large load pocket on networked 69kV system 30

31 Eastern South Dakota Out Year Issues ( ) Replacement of Granite Falls 115/69 kv transformer Required before 2020 Sizing to be determined at a later date 31

32 Summary of New Facilities Ordway 115 kv Capacitor (In service 2012) Beresford/Spirit Mound Capacitor (In service 2012) Continue with Creston improvements (In service 2012) Continue with Spencer improvements, finalize transformer sizing (In service 2013) Construct t Ordway Aberdeen Siebrecht 115 kv line (In service 2013) Add 230/115 kv transformer at Rasmussen and construct Rasmussen EJ Manning (or Vermillion) 115 kv line (In service 2013) Size Sioux Falls transformers and determine timeline for replacement 32

33 2011 South Dakota Additional Sensitivities Aurora New delivery point that relocates City of Aurora load from Brookings to Aurora Roberts County New delivery point on the Summit Forman 115 kv line Summit Transformer Verify sizing of replacement transformer Study combined with Roberts County request Fort Randal/Tyndall Voltage Support Additional voltage support required, especially during Corps bird runs Voltages drop to 0.98 pu system intact t 33

34 Questions? 34

Western Area Power Administration

Western Area Power Administration 2014/15 Integrated System (IS) 890 Local Planning Stakeholder Meeting #2 Western Area Power Administration Upper Great Plains Region Transmission Planning Stakeholder Meeting Wednesday, December 10 th,

More information

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 14, 2005 1 2004-06 EGSI-TX Transmission Western Region Reliability

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Sub Regional RTEP Committee - Southern. August 19, 2011

Sub Regional RTEP Committee - Southern. August 19, 2011 Sub Regional RTEP Committee - Southern August 19, 2011 2011 RTEP Analysis Summary 2010 2015 Project Updates 2016 Analysis NERC Category A, B NERC Category C (N-1-1 in progress) Load Deliverability Generator

More information

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04 Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch

More information

Sub-Regional RTEP Committee PJM South

Sub-Regional RTEP Committee PJM South Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates

More information

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Status of PNM s Completed Transmission Construction Projects 11/30/2017 Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic August 24, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects from the competitive planning

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC

More information

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010 FINAL FACILITY STUDY 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1 September 10, 2010 I. Introduction This is a revised facility study performed for Transmission Queue Request 2009

More information

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007 High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent

More information

APPENDIX E: Project Need and Description

APPENDIX E: Project Need and Description APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Tyler 60 kv Shunt Capacitor Installation of a 2x10 MVAR capacitor bank at Tyler 60 kv bus Objectives

More information

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC OCTOBER 17, 2018 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

APPENDIX E: Project Need and Description

APPENDIX E: Project Need and Description APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Lakeville 115 kv Bus Upgrade Installation of a sectionalizing breaker to be installed on 115 kv bus section

More information

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving

More information

MTEP13 SPM #2- Central Region. March 25, 2013

MTEP13 SPM #2- Central Region. March 25, 2013 MTEP13 SPM #2- Central Region Ameren Missouri March 25, 2013 Ameren Missouri Project Review Central Region: Ameren Missouri Ameren Missouri has a total of 10 project proposals that are recommended for

More information

Appendix B. Summary of Changes to the Year Assessment

Appendix B. Summary of Changes to the Year Assessment Appendix B Summary of Changes to the 2003 10- Assessment For the below tables, the following color-coding scheme was utilized for indicating what type of change has been made to the 10- Assessment from

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic March 23, 2018 First Review Baseline Reliability and Supplemental Projects 2 AEC Transmission Zone: Supplemental Project 69/12kV Wenonah Substation Retire/Bypass

More information

Sub Regional RTEP Committee - Southern

Sub Regional RTEP Committee - Southern Sub Regional RTEP Committee - Southern March 03, 2011 www.pjm.com 2010 RTEP Analysis Summary Review of ongoing projects Stakeholder request 2015 Analysis Update Review of NOVA Reliability Deficiencies

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic July 26, 2016 Reliability Analysis Update MetEd Transmission Zone N-1 First Energy Planning Criteria (FERC Form 715): The North Boyertown West Boyertown 69 kv is

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects

Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects Entergy Texas, Inc. Transmission 2014 2018 Draft Construction Plan Update 1 Projects 1 2014-2018 ETI Draft Construction Plan Update 1 Projects Completed in the Fall of 2012 & 2013 to date 1) Cedar Hill

More information

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project. Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project April 23, 2003 Introduction Eurus originally requested an interconnection

More information

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PSE&G System Characteristics New Jersey utility characterized by densely populated

More information

Q0044 interconnection at

Q0044 interconnection at Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description

More information

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN Twin Cities Minnesota Zone Meeting Xcel Energy May 11, 2005 Bloomington, MN Overview of Presentation Xcel Energy Projects: Aldrich to St Louis Park 115 kv line Eden Prairie to Edina 115 kv line Eden Prairie

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic November 04, 2013 2013 RTEP Baseline Analysis Update 11/04/2013 AE Transmission Zone Cost Change for B2354 Install second 230/69kV transformer and 230kV circuit

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

North Oregon Coast Area Study. Adam Lint

North Oregon Coast Area Study. Adam Lint North Oregon Coast Area Study Adam Lint PAGE 2 North Oregon Coast System Overview - Clatsop Study Covers: Transmission Switching Stations (Clatsop District): Astoria Lewis and Clark 115 kv Distribution

More information

Pacific Gas and Electric Company s Revised 2016 Annual Progress

Pacific Gas and Electric Company s Revised 2016 Annual Progress March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic December 19, 2017 First Preliminary Review Baseline Reliability and Supplemental Projects 2 The slide was previously presented at 8/31/2017 and is replaced by the

More information

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study Cromby Units 1 and 2 and Eddystone Units 1 and 2 Deactivation Study Original Posting Date: March 2, 2010 Updated May 10, 2010 Updated June 7, 2010 Updated September 7, 2010 General PJM received notice

More information

Surry Skiffes Creek Whealton Modeling and Alternatives Analysis Review

Surry Skiffes Creek Whealton Modeling and Alternatives Analysis Review Surry Skiffes Creek Whealton Modeling and Alternatives Analysis Review US Army Corps of Engineers Norfolk District Regulatory Office Received by: RLS Date: Feb 11, 2016 TOPICS Project Purpose, Need, Timeline

More information

PG&E s 2012 Request Window Proposals

PG&E s 2012 Request Window Proposals 1 PG&E s 2012 Request Window Proposals Central Valley Patrick Tan Transmission System Planning PG&E September 27, 2012 Transmission Projects Overview 2 Projects Seeking CAISO Approval Pease 115/60 kv Transformer

More information

Key to Status Fields in the Project List

Key to Status Fields in the Project List Key to Fields in the Project List Load Growth Interconnection Economic Reliability Concept Proposed Planned Under Construction In Cancelled N/A Backstop Too early TO Update Base case Increasing load served

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2014 Annual Ten-Year Transmission Plan Assessment Report November 20, 2014 For information or questions regarding this Transmission Assessment Report,

More information

Pacific Gas and Electric Company s Revised 2015 Annual Progress

Pacific Gas and Electric Company s Revised 2015 Annual Progress March 02, 2015 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Avista PO Box 3727 MSC-16 1411 East Mission Ave Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff 155 North 400 West

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection

More information

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives Addendum San Juan Major Project Tri-State Generation and Transmission Association Power System Planning December, 2008

More information

2018 Annual Progress Report to WECC Pacific Gas and Electric Company

2018 Annual Progress Report to WECC Pacific Gas and Electric Company 2018 Annual Progress Report to WECC Pacific Gas and Electric Company Waiver of Significant Transmission Project Status Table 1 and 2 update the planned transmission and generation projects, respectively,

More information

Pike County Light & Power Company Summer Reliability Outlook

Pike County Light & Power Company Summer Reliability Outlook Pike County Light & Power Company 2013 Summer Reliability Outlook June 28, 2013 System Overview Pike County Light & Power Company ( PCL&P or the Company ) is an electric distribution company ( EDC ) which

More information

New 115 kv Disconnect Switches at Bloomsburg MTS

New 115 kv Disconnect Switches at Bloomsburg MTS 115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Public Service Company of Colorado System Impact Study Load Interconnection Request for a 50 MVA Load Near Collbran

Public Service Company of Colorado System Impact Study Load Interconnection Request for a 50 MVA Load Near Collbran System Impact Study_50 MVA Load Interconnnection Request Near Collbran.doc Public Service Company of Colorado System Impact Study Load Interconnection Request for a 50 MVA Load Near Collbran PSCo Transmission

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia

More information

Diane Lindsey CenterPoint Energy SWEDE 2010

Diane Lindsey CenterPoint Energy SWEDE 2010 Diane Lindsey CenterPoint Energy SWEDE 2010 Agenda Background Pre Hurricane Ike Dredge Evaluation Aftermath of Hurricane Ike in 2008 Temporary West Galveston Mobile Substation Post Hurricane Ike Dredge

More information

BC Hydro System 2011 Annual Progress Report

BC Hydro System 2011 Annual Progress Report March 1, 2011 Mr. Kyle R. Kohne, Chairman WECC Technical Studies Subcommittee Bonneville Power Administration P.O. Box 491 MS, TPP-OPP-3 Vancouver, WA 98666 Mr. Kent Bolton WECC Technical Staff 155 North

More information

Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects

Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 13, 2006 1 Approved 2006 2010 ELL-South Transmission

More information

The Evolution of System Protection Schemes for the Sarawak Power System By Victor Wong Sarawak Energy Berhad Presented at PQSynergy 2012, Sarawak

The Evolution of System Protection Schemes for the Sarawak Power System By Victor Wong Sarawak Energy Berhad Presented at PQSynergy 2012, Sarawak The Evolution of System Protection Schemes for the Sarawak Power System By Victor Wong Sarawak Energy Berhad Presented at PQSynergy 2012, Sarawak Evolution of System Protection Scheme UFLS- Under Frequency

More information

Reliability Analysis Update

Reliability Analysis Update Reliability Analysis Update Transmission Expansion Advisory Committee October 11, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects

More information

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the

More information

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Connection Engineering Study Report for AUC Application: AESO Project # 1674 APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System

More information

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee March 6, 2014 1 2014 RTEP Update 2 2014 RTEP Update Initial 2019 Summer base case and corresponding machine list update complete PJM staff has been reviewing and

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Kettle River Transmission Project

Kettle River Transmission Project April 2012 Why are you receiving this project information package? New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta Electric System Operator

More information

Sub Regional RTEP Committee South

Sub Regional RTEP Committee South Sub Regional RTEP Committee South October 30, 2017 Baseline Reliability and Supplemental Projects First Preliminary Review 2 Dominion: Baseline Violation 115 kv Line #43 Staunton to Harrisonburg End of

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test: Salisbury Substation 11kV Feeders DISCLAIMER The purpose of this document is to inform customers, Interested Parties,

More information

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M of Need In-service Cost Alternatives Service Projects in PG&E Service Territory Mare Island - Ignacio 115 kv NERC Category 2010 Reconductor the limiting 19 $19M Connect Highway May 2012 Line re-rates and

More information

Feasibility Study For MPC01400 Wind-Powered Generation Facility Interconnected at Euclid, ND

Feasibility Study For MPC01400 Wind-Powered Generation Facility Interconnected at Euclid, ND Feasibility Study For MPC01400 Wind-Powered Generation Facility Interconnected at Euclid, ND Prepared by: Aaron Vander Vorst Tim Bartel Minnkota Power Cooperative, Inc. June, 2009 Table of Contents 1 Introduction...

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation 1. Description In the 2013-2014 Transmission Planning Cycle, the ISO approved the construction

More information

ATC Year Assessment Network Project List. MTEP Cost Reason for Change since Previous System Addition

ATC Year Assessment Network Project List. MTEP Cost Reason for Change since Previous System Addition TC 208 0- ssessment Network Project List 2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 Sherman Street SS, DIC - Replace High Side Circuit Switcher 208*** 208 T-D Interconnection Proposed targeted 8 372

More information

SECTION 27 - PAD-MOUNTED TRANSFORMERS TABLE OF CONTENTS

SECTION 27 - PAD-MOUNTED TRANSFORMERS TABLE OF CONTENTS CABLE AND CONDUIT ENTRANCE SINGLE-PHASE PAD-MOUNTED TRANSFORMER INSTALLATION 100 KVA AND LARGER (CONCRETE PADS ONLY) 27.05-01 CABLE AND CONDUIT ENTRANCE SINGLE-PHASE PAD-MOUNTED TRANSFORMER INSTALLATION

More information

2013 ANNUAL PROGRESS REPORT

2013 ANNUAL PROGRESS REPORT Bonneville Power Administration 2013 ANNUAL PROGRESS REPORT Report Prepared By: Dennis Stevens Bonneville Power Administration Transmission Planning TPP/OPP-3 (360) 619-6821 BPA TS TPP 2013-018 Page 1

More information

Manual 3: Transmission Operations Updates Version 52

Manual 3: Transmission Operations Updates Version 52 Manual 3: Transmission Operations Updates Version 52 Liem Hoang Sr. Lead Engineer, Transmission Operations Review Timeline Manual First Reads: November 2 nd SOS Joint November 2 nd SOS-T (Section 5 only)

More information

PJM SRTEP Meeting Questions Pertaining to Proposed Projects & Scopes AEP: Ambler Ridge:

PJM SRTEP Meeting Questions Pertaining to Proposed Projects & Scopes AEP: Ambler Ridge: PJM SRTEP Meeting 2-13-2018 Questions Pertaining to Proposed Projects & Scopes AEP: Ambler Ridge: The problem statement states two 138kV CB s will be installed at Ambler Ridge, however the potential solution

More information

Impacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities

Impacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities Impacts of MISO DPP-2016-February (West, ATC, MI, South) 1. MISO generators studied: Projects on PJM Facilities Net MW size (Summer) Net MW size (Winter) Service DPP Project Type Region Fuel Type POI J432

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Interconnection Feasibility Study Report GIP-369-FEAS-R1 Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power

More information

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study ` Dunvegan Hydroelectric Project For Glacier Power Limited Preliminary Interconnection Study Prepared by Pung Toy, P. Eng. and Ata Rehman, P. Eng. September 24, 2004 Table of Contents Table of Contents...

More information