Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects
|
|
- Imogen Glenn
- 5 years ago
- Views:
Transcription
1 Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects 1
2 ETI Draft Construction Plan Update 1 Projects Completed in the Fall of 2012 & 2013 to date 1) Cedar Hill to Plantation 138 kv line Upgrade line conductor and Station Equipment Completed Feb ) Leach to Newton Bulk Upgrade terminal Equipment at Newton Bulk Completed Mar ) Plantation to Conroe 138 kv Upgrade Station Equipment Completed Apr ) Hickory Ridge to Eastgate Upgrade terminal Equipment at Eastgate Completed Apr ) Plantation to Conroe 138 kv- Reconductor line Completed Apr ) Eastgate to Dayton Bulk Upgrade Terminal Equipment at Eastgate - Completed Apr ) Bentwater Substation 138 kv Add Capacitor Bank Completed May ) Expand Capacitor Bank at Calvert 69 kv Completed May ) Jasper to Rayburn 138 kv line Upgrade Completed May
3 ETI Draft Construction Plan Projects 1. College Station SS Create Emergency tie point with ERCOT 2013 Spring 2. Deweyville (JNEC) 69 kv Add Capacitor Bank 2013 winter 3. Ponderosa Switching Station Tie lines Longmire to Fish Creek and Conroe to Woodhaven into new Switching Station 2013 Winter 4. Pansy to Lovells Lake Upgrade line to 100C 2013 Winter Lovells Lake to Texaco Hillebrandt Upgrade line to 100C 2013 Winter 6. Lewis Creek Egypt Reconductor 2014 Summer 7. Parkway: New Cap Bank Summer 8. Leach DETEC Install breakers 2014 Fall Toledo Bend Leach Reconductor Fall 10. Jacinto to Splendora 138 kv line Upgrade Summer 11. Alden 138 kv Substation Add Capacitor Bank Summer 12. Magnolia Groveton Add Cap Bank Summer 13) China to Amelia 230 kv Construct New line Summer 14) Grimes to Ponderosa: Construct new 230 kv line Summer 15) Ponderosa to Conroe: Reconductor 138 kv line Summer 16) Porter Forest New 138 kv line and Sub Summer ISD 2014 ISD 2015 ISD 2016 ISD 2017 ISD 2018ISD 3
4 ETI Draft Construction Plan Projects 17. Orange County 230 kv Project: New Chisholm Road 230 kv Substation, new line from Hartburg to Chisholm Road, new kv Auto 2017 Summer 18. Sabine to Port Neches (Line 515): Reconductor line Summer 19. Sabine: Upgrade terminal equipment (Sabine to Big 3 Line) Summer 20. Egypt to Panorama 138 kv- Reconductor Summer 21. Construct new China to Stowell 138 kv line Summer 22. Sabine to Port Neches (Line 516): Reconductor line Summer 23. Raywood Add 2 nd 138/69 kv Auto Summer 24. Kolbs 230 kv Add Cap Bank Summer 25. Gulfway 230 Upgrade VFW park 230 kv line bay Summer 26. Splendora to Apollo Upgrade 138 kv line Summer 27. Panorama Longmire Reconductor Summer 28. Raywood Add 2 nd 69 kv line to Daisetta Summer ISD 2016 ISD 2017 ISD 2018 ISD 2019 ISD 4
5 Deweyville 69 kv: Add Capacitor Bank 11-ETI-003 Scenario: The single contingency loss of 69 kv Line 81 (Echo to Deweyville) causes low voltage at the Deweyville 69 kv substation (JNEC-owned). Proposed Solution: Add a 14.4 MVAR capacitor bank at the Deweyville 69 kv substation. Proposed In-Service Date: Winter
6 Deweyville 69 kv: Add Capacitor Bank 11-ETI-003 Install 14.4 MVAR Cap Bank Proposed In-Service: Winter
7 Ponderosa Switching Substation 12-ETI-004 Scenario: Loss of the Lewis Creek-Longmire 138 kv line 596 results in overload of the Tubular-Dobbin 138 kv line segment in addition to future voltage violations at Navasota, Sota, Dobbin, Tubular, Fish Creek, Spring Branch and Longmire for an N-1, G-1 Scenario. Proposed Solution: Install a 138 kv switching substation (4 breaker ring bus) where the Longmire- Fish Creek 138 kv line parallels the Conroe-Woodhaven 138 kv line. Cut in both lines leaving space for a future 230/138 kv Autotransformer. Proposed In-Service Date: Winter
8 Ponderosa Switching Substation 12-ETI-004 Build New 138kV Switching Substation Proposed In-Service: Winter
9 Pansy to Lovells Lake 69 kv Upgrade Line 13-ETI Scenario: Loss of the Memorial to Mid County 138 kv line 563 overloads 69 kv lines 62 and 63. Proposed Solution: Lidar 69 kv lines 62 and 63 to determine extent of mitigation to bring Pansy to Lovells Lake line rating back to 4/0 ACSR conductor rating of 49 MVA. Proposed In-Service Date: Winter
10 Pansy to Lovells Lake 69 kv Upgrade Line 13-ETI Upgrade line to 49 MVA Proposed In-Service: Winter
11 Lovells Lake to Texaco Hillebrandt 69 kv Upgrade Line 13-ETI Scenario: Loss of the Memorial to Mid County 138 kv line 563 overloads 69 kv lines 62 and 63. Proposed Solution: Lidar 69 kv lines 62 and 63 to determine extent of mitigation to bring Lovells Lake to Texaco Hillebrandt line rating back to 4/0 ACSR conductor rating of 49 MVA. Proposed In-Service Date: Winter
12 Lovells Lake to Texaco Hillebrandt 69 kv Upgrade Line 13-ETI Upgrade line to 49 MVA Proposed In-Service: Winter
13 Install Breakers at Leach 14-ETI-004 Scenario: DETEC will tie the existing radial (to Sixmile) out of Leach to AEP and Millcreek (through DETEC 138 kv subs); establishing a potential 3 terminal line. Proposed Solution: DETEC to install breakers at Leach on the 138 kv lines to Toledo Bend and Newton Bulk. Proposed In-Service Date: Fall
14 Install Breakers at Leach 14-ETI-004 New 138 kv tie to AEP and Millcreek Install breakers on both 138 kv lines Proposed In-Service: Fall
15 Upgrade Toledo - Leach 138 kv line 11-ETI-033 Scenario: With the DETEC tie project implementation in Fall of 2014, the Toledo Leach line 449 overloads with the loss of the Cypress to Hartburg 500 kv. Proposed Solution: Reconductor line with 1272 ACSR and upgrade all substation equipment to achieve a minimum line rating of 287 MVA (1200 amps) Proposed In-Service Date: Fall
16 Toledo Bend to Leach 138 kv Upgrade Line 11-ETI-033 Upgrade line to 287 MVA Proposed In-Service: Fall
17 Upgrade Lewis Creek -Egypt 138 kv line 13-ETI-011 Scenario: Lewis creek to Egypt was recently derated and overloads with the loss of the Lewis creek to Caney Creek 138 kv line 648 coupled with the loss of Frontier. Proposed Solution: Reconductor line with 1272 ACSS and upgrade all substation equipment to achieve a minimum line rating of 468 MVA (1957 amps) Proposed In-Service Date: Summer
18 Upgrade Lewis Creek -Egypt 138 kv line 13-ETI-011 Upgrade line to 468 MVA Proposed In-Service: Summer
19 Parkway 138 kv Bus New 50.2 MVAR Cap Bank 11-ETI-042 Scenario: Loss of the Porter to New Caney 138 kv line causes low voltage on the New Caney 138 kv bus. Proposed Solution: Install a new 50.2 MVAR Cap Bank on the Parkway 138 kv bus when it is energized in summer 2014 Proposed In-Service Date: Summer
20 Parkway 138 kv Bus New 50.2 MVAR Cap Bank 11-ETI-042 New Parkway Sub to replace temp Hickory Ridge sub New 50.2 MVAR Cap Bank Proposed In-Service: Summer
21 Upgrade Jacinto Splendora 138 kv line 11-ETI-039 Scenario: Loss of the China to Porter 230 kv line coupled with the loss of the Lewis Creek Unit 1 causes the Jacinto to Splendora line to overload. Proposed Solution: Reconductor line with 1272 ACSS and upgrade all substation equipment to achieve a minimum line rating of 468 MVA (1957 amps) Proposed In-Service Date: Summer
22 Upgrade Jacinto Splendora 138 kv line 11-ETI-039 Upgrade line to 468 MVA Proposed In-Service: Summer
23 Alden 138 kv substation Add 50.4 MVAR Cap Bank 12-ETI-007 Scenario: Loss of the China to Porter 230 kv line coupled with the loss of the Lewis Creek unit 1 causes low voltage on the Alden 138 kv bus. Proposed Solution: Install a 50.4 MVAR Capacitor bank on the Alden 138 kv bus. Proposed In-Service Date: Summer
24 Alden 138 kv substation Add 50.4 MVAR Cap Bank 12-ETI-007 Install 50.2 MVAR Cap bank Proposed In-Service: Summer
25 Magnolia Groveton Add 25.1 MVAR Cap Bank 13-ETI-006 Scenario: Loss of the Rivtrin to Staley 138 line 411 coupled with the loss of the Sam Rayburn generator causes low voltage at Staley and Magnolia Groveton. Proposed Solution: Install a 25.1 MVAR Capacitor bank on the Magnolia Groveton 138 kv bus. Proposed In-Service Date: Summer
26 Magnolia Groveton Add 25.1 MVAR Cap Bank 13-ETI-006 Install 25.1 MVAR Cap bank Proposed In-Service: Summer
27 China Amelia 230 kv Construct New Line 11-ETI-018 Scenario: Loss of the China Sabine 230 line 496 or the China Amelia 230 kv line 599 coupled with loss of generation at Frontier or Lewis Creek causes the remaining line to overload. Proposed Solution: Construct a new China to Amelia 230 kv line utilizing a different route. Proposed In-Service Date: Summer
28 China Amelia 230 kv Construct New Line 11-ETI-018 Construct New 230 kv line Proposed In-Service: Summer
29 Grimes to Ponderosa to Grimes Construct New 230 kv Line Reconductor Ponderosa to Conroe 138 kv line 13-ETI and 13-ETI Scenario: The single contingency loss of either kv Autotransformer at the Grimes 345 kv substation causes the remaining Autotransformer to overload. The future loss of the Grimes to Bentwater 138 kv line results in the Grimes to Mt. Zion 138 kv line and eventually the Mt. Zion to Huntsville 138 kv line to overload The future loss of the Mt. Zion to Grimes 138 kv line results in the Grimes to Bentwater 138 kv line to overload Proposed Solution: Construct a new 230 kv line between Grimes and Ponderosa. Add a 345/230 autotransformer at Grimes and a 230/138 kv autotransformer at Ponderosa. Reconductor the Ponderosa to Conroe 138 kv line. Proposed In-Service Date: Summer
30 Grimes to Ponderosa to Grimes Construct New 230 kv Line Reconductor Ponderosa to Conroe 138 kv line 13-ETI and 13-ETI Construct new 230 kv line Grimes: Add 345/230 Auto Ponderosa: Add 230/138 Auto 13-ETI Reconductor 138 kv line 13-ETI Ponderosa Proposed In-Service: Summer
31 Construct New Porter to Forest 138 kv Transmission Line 13-ETI-012 Scenario: Texas Asset Planning requires a new Distribution Sub that will be cut into the Conroe to Goslin 138 kv line 820. Proposed Solution: Install a new 138 kv line from Porter to the new Distribution Sub to provide VAR support to the Woodlands area. Proposed In-Service Date: Summer
32 Construct New Porter to Forest 138 kv Transmission Line 13-ETI-012 New 138 kv line New Forest Substation Proposed In-Service: Summer
33 Orange County Project 11-ETI-023 Scenario: The loss of the Cypress to Hartburg 500 kv line 547 coupled with the loss of Sabine 4 overloads the Hartburg 500/230 kv autotransformer and the Hartburg Inland Orange McLewis 230 line 195. Proposed Solution: Construct a new 230 kv substation (Chisholm Road) at the intersection of 230 lines 195 (Hartburg Helbig) and 572 (Georgetown Sabine). Install a new 500/230 kv autotransformer at Hartburg and build a new 230 kv line from Chisholm Road to Hartburg. Proposed In-Service Date: Summer
34 Orange County Project 11-ETI-023 Install new 500/230 kv auto at Hartburg Build new Chisholm Rd. Sub, cutting in lines 195 and 572 Build new 230 kv line from Chisholm to Hartburg Proposed In-Service: Summer
35 Sabine to Port Neches 138 kv 515 Upgrade Line 11-ETI-002 Scenario: Loss of the Sabine to Port Neches 138 kv line 516 coupled with loss of the Sabine 4 generator causes an overload of the Sabine to Port Neches 138 kv line 515. Proposed Solution: Reconductor approximately 7.2 miles of conductor and replace all underrated equipment at Sabine and Port Neches to achieve minimum rating of 1764 amps (422 MVA). Proposed In-Service Date: Summer
36 Sabine to Port Neches 138 kv 515 Upgrade Line 11-ETI-002 Upgrade line 515 to 422 MVA Proposed In-Service: Summer
37 Sabine: Upgrade Terminal Equipment on Big kv line 12-ETI-009 Scenario: Loss of the Cypress to Hartburg 500 kv line 547 causes an overload of the Sabine to Big Three 230 kv line 428. Proposed Solution: Upgrade line bay bus and revise relay settings at Sabine to achieve minimum rating of 1710 amps (685 MVA). Proposed In-Service Date: Summer
38 Sabine: Upgrade Terminal Equipment on Big kv line 12-ETI-009 Upgrade Terminal Eq. on Line 428 to increase rating to 685 MVA Proposed In-Service: Summer
39 Upgrade Egypt to Panorama 138 kv line 13-ETI-013 Scenario: Egypt to Panorama overloads with the loss of the Grimes to Crockett 345 KV line 119 coupled with the loss of Frontier. Proposed Solution: Reconductor line with 1272 ACSS and replace all substation equipment with the exception of the 1200 amp line switch at Panorama to achieve minimum line rating of 287 MVA (1200 amps). Proposed In-Service Date: Summer
40 Upgrade Egypt to Panorama 138 kv line 13-ETI-013 Upgrade line to 287 MVA Proposed In-Service: Summer
41 China to Stowell: Construct New 138 kv Line 11-ETI-037 Scenario: Loss of the Mid County to Memorial 138 kv line 563 causes an overload of the 69 kv lines 62 and 63 between South Beaumont, Pansy and Winshire. Proposed Solution: Construct a new 138 kv line between China and Stowell with a minimum rating of 1110 amps (265 MVA) Proposed In-Service Date: Summer
42 China to Stowell: Construct New 138 kv Line 11-ETI-037 Construct a new 230 line (minimum 265 MVA) Proposed In-Service: Summer
43 Sabine to Port Neches 138 kv 516 Upgrade Line 11-ETI-038 Scenario: Loss of the Sabine to Port Neches 138 kv line 515 causes an overload of the Sabine to Port Neches 138 kv line 516. Proposed Solution: Reconductor approximately 7.2 miles of conductor and replace all underrated equipment at Sabine, Linde and Port Neches to achieve minimum rating of 1764 amps (422 MVA). Proposed In-Service Date: Summer
44 Sabine to Port Neches 138 kv 516 Upgrade Line 11-ETI-038 Upgrade line 516 to 422 MVA Proposed In-Service: Summer
45 Raywood Area Improvements Add 2 nd kv Auto at Raywood 14-ETI Scenario: 69 kv lines 57 and 56 overload with the loss of the Raywood 138/69 kv auto Proposed Solution: Install a second 138/69 kv auto matching the size (112 MVA) and impedance of the existing auto. Proposed In-Service Date: Summer
46 Raywood Area Improvements Add 2 nd kv Auto at Raywood 14-ETI Install 2 nd 138/69 kv auto Proposed In-Service: Summer
47 Kolbs 230 kv Capacitor Bank 12-ETI-006 Scenario: The Port Arthur 230 kv loop (Port Arthur Kolbs Hanks - Gulfway VFW Park) experiences low voltage with the loss of the Port Acres Bulk source coupled with the loss of Sabine Generator 4. Proposed Solution: Install a new 72 MVAR Cap Bank on the Kolbs 230 kv bus. Proposed In-Service Date: Summer
48 Kolbs 230 kv Capacitor Bank 12-ETI-006 Install 72 MVAR Cap Bank on Kolbs 230 kv bus Proposed In-Service: Summer
49 Gulfway 230 kv Substation Upgrade VFW Park Line Bay Equipment 12-ETI-017 Scenario: A breaker failure on 230 kv Breaker at Sabine causes the Gulfway to VFW Park 230 line 197 to overload. Proposed Solution: Replace the 1272 ACSR line bay riser at Gulfway 230 kv substation on the VFW Park line bay to achieve a minimum rating of 1720 amps (685 MVA). Proposed In-Service Date: Summer
50 Gulfway 230 kv Substation Upgrade VFW Park Line Bay Equipment 12-ETI-017 Replace line bay riser to obtain 685 MVA line rating Proposed In-Service: Summer
51 Splendora to Apollo 138 kv Upgrade Line 11-ETI-026 Scenario: Loss of the Porter - China 230 line 822 causes an overload of the Splendora to Apollo 138 kv line 571. Proposed Solution: Reconductor approximately 2.67 miles of conductor and upgrade bus and line bay risers at Apollo and Splendora to achieve minimum rating of 1957 amps (468 MVA). Proposed In-Service Date: Summer
52 Splendora to Apollo 138 kv Upgrade Line 11-ETI-026 Upgrade line to 468 MVA Proposed In-Service: Summer
53 Upgrade Panorama to Longmire 138 kv line 13-ETI-014 Scenario: Panorama to Longmire overloads with the loss of the Grimes to Crockett 345 KV line 119 coupled with the loss of Frontier. Proposed Solution: Reconductor line with 1272 ACSS and replace all substation equipment with the exception of the 1200 amp Breaker at Longmire to achieve minimum line rating of 287 MVA (1200 amps). Proposed In-Service Date: Summer
54 Upgrade Panorama to Longmire 138 kv line 13-ETI-014 Upgrade line to 287 MVA Proposed In-Service: Summer
55 Raywood Area Improvements Add 2 nd 69 kv Line from Raywood to Daisetta 14-ETI Scenario: 69 kv lines 55 and 56 overload with the loss of the Raywood-Daisetta 69 kv line 57. Also, Raywood Daisetta 69 kv overloads with the loss of Amelia Sour Lake. Proposed Solution: Extend 69 kv line 440 from the tap point to South Liberty to the Daisetta Substation (2.2 miles). Line rating will be limited by existing 795 AA (775 amps). Proposed In-Service Date: Summer
56 Raywood Area Improvements Add 2 nd 69 kv Line from Raywood to Daisetta 14-ETI Install 2 nd 69 kv line from tap to Daisetta Proposed In-Service: Summer
57 Draft Construction Plan Update 1 Horizon Projects ETI 1) Carroll St Neches 138 kv Line 457 Reconductor Summer 2) Carroll St Neches 138 kv Line 528 Reconductor Summer 3) Upgrade Apollo to Porter 138 kv Summer 4) Eastgate Add 37.7 MVAR Cap Bank Summer 5) Jacinto Cleveland Upgrade line bay risers at both subs Summer 6) Ponderosa Fish Creek 138 kv - Reconductor Line Summer 7) Amelia Helbig 230 kv Reconductor Line Summer 8) Cut Cleveland into 138 kv line 871 (Jacinto Splendora) Summer 9) Winshire 69 kv Add Cap Bank Summer 10) Dobbins 138 kv Add Cap Bank Summer 11) Add 2 nd Cypress 500/138 kv Auto Summer 12) Helbig Chisholm Road 230 kv Reconductor Summer 13) WRRIP PH 3 Final: Construct new Cypress to Jacinto 230 kv line with series compensation Summer
Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects
Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 14, 2005 1 2004-06 EGSI-TX Transmission Western Region Reliability
More informationMTEP14 South SPM #2. MISO Texas Project Information. April 7, 2014
MTEP14 South SPM #2 MISO Texas Project Information April 7, 2014 MISO Southern Region EAST TEXAS ELECTRIC COOPERATIVE 2 East Texas Electric Cooperative (ETEC) No projects submitted for moving to Appendix
More informationTEXAS ECONOMIC STUDY REPORT ICTES INFORMATIONAL ONLY
TEXAS ECONOMIC STUDY REPORT ICTES-2011-001 INFORMATIONAL ONLY Prepared for: Entergy Service, Inc. (SPO) American Electric Power Service Corporation (AEPSC) GDS Associates, Inc. (GDS), as agent of East
More information1. Administrative Items... SPP. 2. Stakeholder Web-Presentation... ABB
Southwest Power Pool, Inc. ENTERGY REGIONAL STATE COMMITTEE MINIMIZING BULK POWER COSTS STUDY STAKEHOLDER MEETING Face-to-face & Web-conference Hyatt Regency DFW DFW Airport, TX Room: Maverick AGENDA July
More informationEntergy Draft Construction Plan Update 1
Entergy 2014-2018 Draft Construction Plan Update 1 Construction Plan Projects Relating To: Regulatory Transmission Service Economic Enhanced Transmission Reliability Customer Driven Generation Interconnection
More informationEntergy Final Construction Plan
Introduction Entergy 2013-2017 Final Construction Plan Project Driver Project Description Cost Allocation Guideline Project Category Block load addition Projects needed to accommodate the addition of block
More informationFACILITIES STUDY ICTT TRANSMISSION SERVICE FACILITIES STUDY OASIS
TRANSMISSION LINE & SUBSTATION PROJECTS COMPANY: ENTERGY SERVICES, INC. CUSTOMER: EAST TEXAS ELECTRIC COOPERATIVE (ETEC) FACILITIES STUDY EJO NO. F4PPTX0068 ICTT-2011-003 TRANSMISSION SERVICE FACILITIES
More informationMonthly Construction Plan Project Status Report Report Date: 1/16/2014
Monthly Construction Plan Report Report Date: 1/16/2014 EAI EMI ELL ENOI EGSL ETI EGSL/ELL ELL/ENOI ALL General Major Updates Added fifteen transmission reliability projects (SPOF and Under rated breakers).
More informationStability Study for the Mt. Olive Hartburg 500 kv Line
Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.
More informationMarket Congestion Planning Study (South)- Robustness Analysis. Economic Planning Users Group Meeting August 11 th, 2017
Market Congestion Planning Study (South)- Robustness Analysis Economic Planning Users Group Meeting August 11 th, 2017 Key Takeaways The benefit calculations were updated due to a flowgate rating correction
More informationTransmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation
Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT
More informationSouthwest Power Pool, Inc. Entergy ENTERGY SPP RTO REGIONAL PLANNING PROCESS MEETING May 24, 2012 NET CONFERENCE AGENDA 10:00 AM 12:00 PM
Southwest Power Pool, Inc. Entergy ENTERGY SPP RTO REGIONAL PLANNING PROCESS MEETING May 24, 2012 NET CONFERENCE AGENDA 10:00 AM 12:00 PM 1. Administrative A. Introductions... All B. SPP Antitrust Guidelines...
More informationEast. Dalton Utilities. GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission
Southeastern Region Transmission Planning East Dalton Utilities GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission Southeastern Region Transmission
More informationChapter 7 - Appendix A
Chapter 7 - Appendix A Transmission and Distribution Supplemental Information Table 7A.1 MTEP Transmission Projects in Missouri 1 Project Approved Project Title Project Description Category Estimated Cost
More informationEntergy Final Construction Plan
Introduction Entergy 2012-2016 Final Construction Plan Project Driver Project Description Cost Allocation Guideline Project Category Block load addition Projects needed to accommodate the addition of block
More informationGeneration Deactivation Notification Update
Generation Deactivation Notification Update Transmission Expansion Advisory Committee November 8, 2018 Generation Deactivations for 2018 2 Generation Deactivation ATSI Transmission Zones Bruce Mansfield
More informationEntergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects
Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 13, 2006 1 Approved 2006 2010 ELL-South Transmission
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic November 04, 2013 2013 RTEP Baseline Analysis Update 11/04/2013 AE Transmission Zone Cost Change for B2354 Install second 230/69kV transformer and 230kV circuit
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic July 26, 2016 Reliability Analysis Update MetEd Transmission Zone N-1 First Energy Planning Criteria (FERC Form 715): The North Boyertown West Boyertown 69 kv is
More informationFalcon-Midway 115 kv Line Uprate Project Report
Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50
More informationNorth Oregon Coast Area Study. Adam Lint
North Oregon Coast Area Study Adam Lint PAGE 2 North Oregon Coast System Overview - Clatsop Study Covers: Transmission Switching Stations (Clatsop District): Astoria Lewis and Clark 115 kv Distribution
More informationTwin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN
Twin Cities Minnesota Zone Meeting Xcel Energy May 11, 2005 Bloomington, MN Overview of Presentation Xcel Energy Projects: Aldrich to St Louis Park 115 kv line Eden Prairie to Edina 115 kv line Eden Prairie
More informationSouth Dakota 890 Study
South Dakota 890 Study September 16, 2011 South Dakota 890 Study Presentation of 890 Study results from 2011 Includes WAPA suggested system improvements and timelines Stakeholder Feedback Questions? 2
More informationFirst Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012
First Energy Generator Deactivation Request - January 2012 Deactivation Study Results and Required Upgrades April 25, 2012 General PJM received a notice on January 26, 2012 from FirstEnergy of its intent
More informationPacific Gas and Electric Company s Revised 2016 Annual Progress
March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric
More informationMTEP13 SPM #2- Central Region. March 25, 2013
MTEP13 SPM #2- Central Region Ameren Missouri March 25, 2013 Ameren Missouri Project Review Central Region: Ameren Missouri Ameren Missouri has a total of 10 project proposals that are recommended for
More informationInterconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado
Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission
More informationPID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation
PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date
More informationImpacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities
Impacts of MISO DPP-2016-February (West, ATC, MI, South) 1. MISO generators studied: Projects on PJM Facilities Net MW size (Summer) Net MW size (Winter) Service DPP Project Type Region Fuel Type POI J432
More information2018 Annual Progress Report to WECC Pacific Gas and Electric Company
2018 Annual Progress Report to WECC Pacific Gas and Electric Company Waiver of Significant Transmission Project Status Table 1 and 2 update the planned transmission and generation projects, respectively,
More informationAppendix D Black Hills Project Summary
Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain
More informationWestern Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04
Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch
More informationATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M
of Need In-service Cost Alternatives Service Projects in PG&E Service Territory Mare Island - Ignacio 115 kv NERC Category 2010 Reconductor the limiting 19 $19M Connect Highway May 2012 Line re-rates and
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic September 24, 2014 1 Reliability Analysis Update 2 AE Transmission Zone Generation Deliverability Violation: The Middle 230/69 kv is overloaded for line fault stuck
More informationPacific Gas and Electric Company s Revised 2015 Annual Progress
March 02, 2015 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Avista PO Box 3727 MSC-16 1411 East Mission Ave Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff 155 North 400 West
More informationEast. Dalton Utilities. GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission
Southeastern Region Transmission Planning East Dalton Utilities GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission Southeastern Region Transmission
More informationTransmission Expansion Advisory Committee
Transmission Expansion Advisory Committee March 6, 2014 1 2014 RTEP Update 2 2014 RTEP Update Initial 2019 Summer base case and corresponding machine list update complete PJM staff has been reviewing and
More informationAPPENDIX E: Project Need and Description
APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Lakeville 115 kv Bus Upgrade Installation of a sectionalizing breaker to be installed on 115 kv bus section
More informationTransmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015
No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the
More informationSub-Regional RTEP Committee PJM South
Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates
More informationSub Regional RTEP Committee - Southern. August 19, 2011
Sub Regional RTEP Committee - Southern August 19, 2011 2011 RTEP Analysis Summary 2010 2015 Project Updates 2016 Analysis NERC Category A, B NERC Category C (N-1-1 in progress) Load Deliverability Generator
More informationBlack Hills Project Summary
2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission
More informationSystem Impact Study Report
Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS
More informationGeneration Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.
Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project April 23, 2003 Introduction Eurus originally requested an interconnection
More informationTransmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting
Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic August 24, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects from the competitive planning
More informationMILLIGAN SOLAR PROJECT
February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission
More informationStatus of PNM s Completed Transmission Construction Projects 11/30/2017
Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information
More informationSouth Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget
Project 1 of 34 Aiken Trans - Aiken Hampton 115 kv Line: Upgrade 1272A Upgrade the 115 kv line between Aiken and Aiken Hampton substations from 336 ACSR to 1272 ACSR. Total line length approximately 3.7
More informationMarket Efficiency RTEP Proposal Window
Market Efficiency RTEP Proposal Window Market Efficiency RTEP Proposal Window Status Window opened on 8/12/2013 Closed on 9/26/2013 17 individual proposals addressing congestion from Market Efficiency
More informationFeasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation
Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT
More informationWheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation
Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation 1. Description In the 2013-2014 Transmission Planning Cycle, the ISO approved the construction
More informationFeasibility Study Report
Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019
More informationCUSTOMER/ TWIN ARROWS PROJECT
A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset
More information100 MW Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility
More informationTransmission Planning using Production Cost Simulation & Power Flow Analysis
ABB Transmission Planning using Production Cost Simulation & Power Flow Analysis Jinxiang Zhu, Ph.D. Senior Principal, ABB Power Consulting ABB Group January 16, 2018 Slide 1 Power System Studies TECHNICAL
More informationATC Year Assessment Network Project List. MTEP Cost Reason for Change since Previous System Addition
TC 208 0- ssessment Network Project List 2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 Sherman Street SS, DIC - Replace High Side Circuit Switcher 208*** 208 T-D Interconnection Proposed targeted 8 372
More informationQ0044 interconnection at
Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description
More informationOuter Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)
Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving
More informationAPPENDIX E: Project Need and Description
APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Tyler 60 kv Shunt Capacitor Installation of a 2x10 MVAR capacitor bank at Tyler 60 kv bus Objectives
More informationSouth Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget
Project 1 of 28 Blythewood 115 kv Switching Station: Construct 03087A Construct Blythewood Switching Station with four 115 kv line terminals, with plans to expand to 230 kv at a future date. Fold in the
More informationATC Year Asessment Network Project List. Zone 2 switching initiative ASAP*** Operating flexibility Proposed -- --
ATC 20 10-Year Asessment Project List Project ACEC Dellwood Substation: Install line breakers to sectionalize Y- 146 20*** 20 1 T-D interconnection Planned A 7741 Zone 2 switching initiative ASAP*** 20
More informationInterconnection Feasibility Study Report Request # GI
A. Executive Summary Interconnection Feasibility Study Report Request # GI-2011-04 587 MW Combined Cycle 2x1 Generators Cherokee Station, Denver, Colorado Public Service Company of Colorado Transmission
More informationPG&E s 2012 Request Window Proposals
1 PG&E s 2012 Request Window Proposals Central Valley Patrick Tan Transmission System Planning PG&E September 27, 2012 Transmission Projects Overview 2 Projects Seeking CAISO Approval Pease 115/60 kv Transformer
More informationWestern Area Power Administration
2014/15 Integrated System (IS) 890 Local Planning Stakeholder Meeting #2 Western Area Power Administration Upper Great Plains Region Transmission Planning Stakeholder Meeting Wednesday, December 10 th,
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic December 19, 2017 First Preliminary Review Baseline Reliability and Supplemental Projects 2 The slide was previously presented at 8/31/2017 and is replaced by the
More informationPJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008
PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral
More informationEast. Georgia Integrated Transmission System (ITS) GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA)
East Georgia Integrated Transmission System (ITS) Dalton Utilities GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission Expansion Item E-1 Daniel
More informationMarket Efficiency RTEP Proposal Window
Market Efficiency RTEP Proposal Window Market Efficiency RTEP Proposal Window Status Window opened on 8/12/2013 Closed on 9/26/2013 17 individual proposals addressing congestion from Market Efficiency
More informationAppendix B. Summary of Changes to the Year Assessment
Appendix B Summary of Changes to the 2003 10- Assessment For the below tables, the following color-coding scheme was utilized for indicating what type of change has been made to the 10- Assessment from
More informationFeasibility Study Report
Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014
More informationFeasibility Study Report
Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility
More informationNational Grid s 2017 Local Transmission Plan
National Grid s 2017 Local Transmission Plan Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.
More informationTHE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS
THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive
More informationMTEP14 West SPM #2. ATC, DPC, XEL Project Review. April 2, 2014
MTEP14 West SPM #2 ATC, DPC, XEL Project Review April 2, 2014 MISO West Region AMERICAN TRANSMISSION COMPANY, LLC 2 Project Count ATC A in MTEP14 Project Summary 30 Projects by type 25 20 15 10 5 Other
More information2013 ANNUAL PROGRESS REPORT
March 1, 2013 Mr. David Franklin, Chairman WECC Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768-2560 Mr. Enoch Davies WECC Technical Staff 155 North 400 West,
More informationSoutheastern Region Transmission Planning. 10 Year Transmission Expansion Plan
10 Year Transmission Expansion Plan Disclaimer The projects described in this presentation represent the current ten (10) year expansion plan. The expansion plan is periodically reviewed and may be revised
More informationFIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION
PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection
More informationATTACHMENT Y STUDY REPORT
Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation
More informationAPPENDIX F: 2012 Request Window Submittals
APPENDIX F: 2012 Request Window Submittals Table F-1: 2012 Request Window Submittals Project Name Service Submitted by 1 Lockeford-Lodi 230 kv Development City of Lodi, Electric Utility Department 5/31/2017
More information2016 SPP Transmission Expansion Plan Project List Kansas Projects
WR Zonal Reliability $9,308,090 Build 6.7 mile Clay Center Switching Station to TC Riley 115 kv line 6/1/2018 10/1/2012 115 6.7 Install a 2000 Amp bus system, GOAB switches, metering and WR Zonal Reliability
More informationEL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS
EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004
More informationLocal Transmission Plan. October 11, 2013 Revised August 25, 2014
Local Transmission Plan October 11, 2013 Revised August 25, 2014 2 Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated
More informationThe Energy Queensland Group Notice of no non-network options
The Energy Queensland Group Notice of no non-network options 24 September 2018 MCE Mount Crosby East Establish new substation to replace Mount Crosby Substation (SSMTC) Page 1 of 1 DISCLAIMER While care
More informationUpdated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers
Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,
More informationTransmission Expansion Advisory Committee
Transmission Expansion Advisory Committee February 7, 2013 1 Issues Tracking 2 Issues Tracking Open Issues None New Issues 3 2013 RTEP Scenario Analysis 4 RTEP Scenario Analysis 2012 North Carolina Transmission
More informationAttached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.
March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating
More informationNational Grid s 2018 Local Transmission Plan
National Grid s 2018 Local Transmission Plan Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.
More informationSub Regional RTEP Committee South
Sub Regional RTEP Committee South December 18, 2017 Baseline Reliability and Supplemental Projects Second Review 2 Date Project Last Presented: 10/30/2017 SRRTEP Problem Statement: DOM End of Life Criteria
More informationSPP Notification to Construct
February 19, 2014 SPP Notification to Construct Mr. Mo Awad Westar Energy, Inc. P.O. Box 889 Topeka, KS 66601 RE: Notification to Construct Approved Reliability Network Upgrades Dear Mr. Awad, Pursuant
More informationGateway South Transmission Project
Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive
More informationMarch 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1
Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System
More informationPJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study
PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional
More informationKey to Status Fields in the Project List KEY
Key to Fields in the List KEY Description is under consideration as possible solution to a Concept need, but little or no analysis is available National Grid has internally detemined that the project is
More informationInterconnection Feasibility Study Report GIP-157-FEAS-R2
Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia
More informationNew 115 kv Disconnect Switches at Bloomsburg MTS
115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115
More informationTransmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202
Transmission and Distribution Substation Projects Operating Company: Entergy Gulf States - Texas Customer: PID # 202 Funding Project Number: F4PPGS0386 Facility Study for PID # 202: Study for 146 MW Revision
More informationSouth Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget
Project 1 of 24 Queensboro 115 kv Switching Station: Construct 0062A,B,C,D Build 4-terminal 115 kv switching station at Queensboro substation. Terminate the existing Queensboro St. Andrews, Church Creek
More informationMid-Year Population Estimates for H-GAC Region Cities 1 Source: U.S. Census Bureau Released: May 2018
Mid-Year Population Estimates for H-GAC Region Cities 1 Region 7,064,712 6,969,489 6,833,956 6,665,117 6,497,288 6,350,627 6,225,081 6,114,513 5,991,217 5,840,526 5,704,344 5,587,630 5,398,017 5,295,983
More informationTRANSMISSION PLANNING CRITERIA
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing
More information