Market Congestion Planning Study (South)- Robustness Analysis. Economic Planning Users Group Meeting August 11 th, 2017

Size: px
Start display at page:

Download "Market Congestion Planning Study (South)- Robustness Analysis. Economic Planning Users Group Meeting August 11 th, 2017"

Transcription

1 Market Congestion Planning Study (South)- Robustness Analysis Economic Planning Users Group Meeting August 11 th, 2017

2 Key Takeaways The benefit calculations were updated due to a flowgate rating correction (all scenarios/futures) Chisholm Road to Sabine 230 kv Three projects in the WOTAB/Western focus area are still considered for potential recommendation to Board of Directors Alternate configurations of the WOTAB Economic Project have been evaluated for economic and reliability impact 1 Economic Planning User Group Meeting, August 11th 2017

3 MTEP17 MCPS Scope & Study Progress Nov - Dec 2016 Jan - May 2017 June - Aug 2017 Flowgate Identification Project Candidate Identification Robustness Testing Review Historical Congestion Transmission Development Robustness Analysis Congestion Analysis Identify Top Congested Flowgates Screening Analysis Present Value (PV) Analysis Establish Project Candidate(s) Reliability Analysis MISO Scoping Level Cost Estimation Best Fit Solution(s) 2 Economic Planning User Group Meeting, August 11th 2017

4 WOTAB Economic Project Alternatives Alternative 1 Alternative 2 Alternative 3 Description of Project Alternative Discussed at the July EPUG New Hartburg Sabine 500 kv transmission line New Sabine 500/230 kv transformer Expand Hartburg and Sabine substations Tap the existing Sabine McFadden and Sabine Nederland 230 kv transmission lines into a new substation New Hartburg New substation 500 kv transmission line New substation 500/230 kv transformer New Hartburg Sabine 230 kv transmission line New Hartburg 500/230 kv transformer Expand Hartburg and Sabine 230 kv substations Meets MEP voltage and cost criteria? Yes Yes No 3 Economic Planning User Group Meeting, August 11th 2017

5 WOTAB Economic Project Alternative 1 Project Description New 500kV line from Hartburg to Sabine Expand existing Sabine and Hartburg substations New 500/230kV 1200 MVA Transformer at Sabine substation Location Texas In-Service Year: 2023 Texas Louisiana MISO Scoping Level Cost Estimate (Million$-2017): 135 Note: This image is for illustrative purposes only and does not represent line routing Map represents the transmission system with voltages 230kV and above, in MISO 4 Economic Planning User Group Meeting, August 11th 2017

6 WOTAB Economic Project Alternative 1 Full outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 (Base) , Partial outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) * Note: MTEP17 Futures and associated weights are included in the appendix 5 Economic Planning User Group Meeting, August 11th 2017

7 WOTAB Economic Project Alternative 2 Project Description New 230kV substation tapping the existing Sabine McFadden and Sabine Nederland 230 kv transmission lines New 500kV line from Hartburg to New Substation New 500/230kV 1200 MVA transformer at the new substation Location Texas Texas Louisiana Note: This image is for illustrative purposes only and does not represent line routing Map represents the transmission system with voltages 230kV and above, in MISO In-Service Year: 2023 MISO Scoping Level Cost Estimate (Million$-2017): Economic Planning User Group Meeting, August 11th 2017

8 WOTAB Economic Project Alternative 2 Full outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 (Base) , Partial outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) * Note: MTEP17 Futures and associated weights are included in the appendix 7 Economic Planning User Group Meeting, August 11th 2017

9 WOTAB Economic Project Alternative 3 Project Description New 230kV line from Hartburg to Sabine New 500/230kV 800 MVA transformer at Hartburg substation Location Texas In-Service Year: 2023 Texas Louisiana MISO Scoping Level Cost Estimate (Million$-2017): 99.4 Note: This image is for illustrative purposes only and does not represent line routing Map represents the transmission system with voltages 230kV and above, in MISO 8 Economic Planning User Group Meeting, August 11th 2017

10 WOTAB Economic Project Alternative 3 Full outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 (Base) , Partial outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) * Note: MTEP17 Futures and associated weights are included in the appendix 9 Economic Planning User Group Meeting, August 11th 2017

11 Alternatives 2 & 3 produce a Benefit-to-Cost ratio greater than 1.25 in all generation siting scenarios Alternati ve # 1 Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) , , , * Note: MTEP17 Futures and associated weights are included in the appendix 10 Economic Planning User Group Meeting, August 11th 2017

12 Alternative 2 (500kV) fully relieves the congestion in Sabine/Port Arthur area and provides higher VLR makewhole payment relief compared to Alternative 3 (230kV) Alternative 2 (500kV) Alternative 3 (230kV) Congestion Relief Inland Orange McLewis Chisholm Sabine 230kV (100% Congestion Relief) Marshall Mossville 138kV (98% Congestion Relief) Inland Orange McLewis Chisholm Sabine 230kV (98% Congestion Relief) Marshall Mossville 138kV (80% Congestion Relief) Voltage & Local Reliability (VLR) Make whole payment (MWP) reduction in WOTAB (Nominal - $) $ Million $ Million $ Million $ Million $ Million $ Million 11 Economic Planning User Group Meeting, August 11th 2017

13 Sam Rayburn to Fork Creek to Doucette 138 kv Network Upgrade Project Description Replace 26 transmission structures on the Sam Rayburn to Fort Creek to Turkey Creek to Doucette 138kV transmission line Rating increases to 137MVA from 112MVA Location Texas In-Service Year: 2020 Texas MISO Planning Level Cost Estimate (Million$-2017): 2.8 Note: This image is for illustrative purposes only and does not represent line routing Map represents the transmission system with voltages 100kV and above, in MISO 12 Economic Planning User Group Meeting, August 11th 2017

14 Sam Rayburn to Fork Creek to Doucette 138 kv Network Upgrade is a robust transmission solution under all scenarios evaluated Full outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 (Base) Partial outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 (Base) * Note: MTEP17 Futures and associated weights are included in the appendix 13 Economic Planning User Group Meeting, August 11th 2017

15 Substation Equipment Upgrade at Carlyss Louisiana Project Description Replace two air break switches (17549 and 17551) at Carlyss 138 kv to a minimum of 1600 A The 138 kv bus and the line bay bus at Carlyss (138 kv autotransformer line bay) will also be upgraded to at least 1600 A Rating on Carlyss 230/138kV transformer increases to 300MVA from 243MVA Location Louisiana In-Service Year: 2020 Note: This image is for illustrative purposes only and does not represent line routing Map represents the transmission system with voltages 100kV and above, in MISO MISO Planning Level Cost Estimate (Million$- 2017): Economic Planning User Group Meeting, August 11th 2017

16 Substation Equipment Upgrade at Carlyss is a robust project under all scenarios evaluated Full outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 (Base) (9.05) Partial outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 (Base) (7.98) (1.92) * Note: MTEP17 Futures and associated weights are included in the appendix 15 Economic Planning User Group Meeting, August 11th 2017

17 Cost Allocation for WOTAB Economic Project Alternative 2

18 Market Efficiency Project (MEP) - Cost Allocation Methodology Based on Attachment FF-6 of MISO Tariff During the 5 year cost allocation transition period, costs of Market Efficiency Projects located solely in MISO South are allocated only to MISO South Overview of Market Efficiency Project Cost Allocation Methodology 20% of the project costs are allocated to each pricing zone based on load ratio share 80% of the project costs are allocated to pricing zones based on the distribution of APC savings to the Local Resource Zones (LRZ) with positive APC savings (see table and map on next slide) If the total future weighted APC saving for an LRZ is negative then the LRZ is not allocated a portion of the 80% 17 Economic Planning User Group Meeting, August 11th 2017

19 APC Benefit Distribution for WOTAB Economic Project Alternative 2 LRZ State Weighted Present Value of APC Benefit ($M) Local Resource Zone Share of APC Benefits 8 8 AR (1.9) 0% 10 9 LA, TX % 10 MS (2.4) 0% 9 18 Economic Planning User Group Meeting, August 11th 2017

20 WOTAB Economic Project Alternative 2: Cost Allocation Pricing Zone Pricing Zone - Abbr. Local Resource Zone (LRZ) Local Resource Zone Distribution of Benefits [1] [2] [3] Pricing Zone Load Ratio Share of Local Resource Zone See Note 1 MISO South Load Ratio Share [5] 20% Postage Stamp Component [6] = 20% * [5] 80% Local Resource Zone Component [7] = 80% * [3] * [4] Total Pricing Zone Cost Allocation (%) [8] = [6] + [7] Entergy Arkansas EATO % % 20.50% 4.10% 0.00% 4.10% Entergy Louisiana ELTO % 63.71% 41.49% 8.30% 50.96% 59.26% Entergy Mississippi EMTO % 81.97% 11.78% 2.36% 0.00% 2.36% Entergy Texas ETTO % 19.24% 12.53% 2.51% 15.39% 17.89% Cleco Power CLEC % 9.37% 6.10% 1.22% 7.49% 8.71% Cooperative Energy SME % 18.03% 2.59% 0.52% 0.00% 0.52% [4] Lafayette City- Parish Consolidated Entergy New Orleans LAFA % 2.12% 1.38% 0.28% 1.70% 1.97% ENTO % 5.57% 3.63% 0.73% 4.46% 5.18% Note 1: Calculated by dividing the load of applicable pricing zone by the total load of applicable Local Resource Zone 19 Economic Planning User Group Meeting, August 11th 2017

21 Appendix

22 MTEP17 Futures and Future Weights for MCPS South study MTEP17 Future Future Weight (%) Existing Fleet (EF) 40 Policy Regulation (PR) 40 Accelerated Alternative Technologies (AAT) 20 Revised future weights based on the discussion at the March 2017 Planning Advisory Committee (PAC) meeting 1 were utilized for MCPS South Study 1 MTEP17 Weighting discussion at the March 15 th, 2017 PAC: m%2002a%20mtep17%20weighting.pdf 21 Economic Planning User Group Meeting, August 11th 2017

23 Load pocket generation siting scenarios were studied for robustness analysis Scenario 1 Base Futures Scenario 2 RRF Generation sited outside South load pocket(s) Scenario 3 RRF Generation sited at Entergy s RFP proposals Transmission Network upgrades identified from MISO DPP SIS Phase 1 Study were included RRF Regional Resource Forecast; DPP Definitive Planning Phase of MISO generation queue; RFP Request for Proposals; SIS System Impact Study 22 Economic Planning User Group Meeting, August 11th 2017

24 Generation Siting Scenario 2 - Siting Changes in the MISO South Load Pockets for the AAT Future Powerbase Name Scenario 1 Scenario 2 RRF MISO CC:001 Little Gypsy 230 kv Wrightsville 500 kv RRF MISO CC:006 Nelson 230/138 kv Lake Catherine 115 kv RRF MISO CC:060 Nine Mile 230 kv Holland Bottoms 500 kv RRF MISO CT:007 Sabine 138 kv Hot Springs 115 kv RRF MISO CT:010 Hartburg 230kV Hinds 230 kv RRF MISO CT:011 Hartburg 230kV Hinds 230 kv RRF MISO CT:016 Nine Mile 115 kv Big Cajun 230 kv Hartburg RRF MISO CT:090 Sabine 230 kv Couch 115 kv 23 Economic Planning User Group Meeting, August 11th 2017

25 Generation Siting Scenario 2 - Siting Changes in the MISO South Load Pockets for the EF Future Powerbase Name Scenario 1 Scenario 2 RRF MISO CC:001 Little Gypsy 230 kv Wrightsville 500 kv RRF MISO CT:007 Sabine 138 kv Baxter Wilson 115 kv RRF MISO CT:023 Sabine 138 kv Baxter Wilson 115 kv RRF MISO CT:048 Nine Mile 230 kv Rodemacher 230 kv RRF MISO CT:053 Sabine 230 kv Gerald Andrus 230 kv RRF MISO CT:058 Nine Mile 230 kv Gerald Andrus 230 kv RRF MISO CT:066 Nelson 138 kv Baxter Wilson 115kV RRF MISO CT:067 Nelson 138 kv Franklin 500 kv RRF MISO CT:090 Sabine 230 kv Rodemacher 230 kv 24 Economic Planning User Group Meeting, August 11th 2017

26 Generation Siting Scenario 2 - Siting Changes in the MISO South Load Pockets for the PR Future Powerbase Name Scenario 1 Scenario 2 RRF MISO CC:001 Little Gypsy 230 kv Franklin 500 kv RRF MISO CC:006 Nelson 230/138 kv Holland Bottoms 500 kv RRF MISO CC:039 Sabine 138 kv Sterlington 500 kv RRF MISO CT:014 Nine Mile 230 kv Bailey 115 kv RRF MISO CT:015 Nine Mile 230 kv McClellan 115 kv RRF MISO CT:016 Nine Mile 115 kv Teche 138 kv RRF MISO CT:023 Sabine 138 kv Teche 138 kv RRF MISO CT:053 Sabine 230 kv Rex Brown 115 kv 25 Economic Planning User Group Meeting, August 11th 2017

27 Generation Siting Scenario 3 Siting changes in MISO South load pockets Siting Location Capacity (MW) In-Service Year AAT EF PR Little Gypsy 230 kv 1, Nelson 230/138 kv 1, Lewis Creek 230/138 kv 1, Michoud 115 kv Generation siting in the load pocket is replaced with Entergy RFP generation in Scenario 3 Total Generation inside the load pocket is similar to Generation Siting Scenario 1 Transmission Network upgrades identified from MISO DPP SIS Phase 1 Study were included RRF Regional Resource Forecast; DPP Definitive Planning Phase of MISO generation queue; RFP Request for Proposals; SIS System Impact Study 26 Economic Planning User Group Meeting, August 11th 2017

28 Make Whole Payment reduction for WOTAB Economic Project Alternative 1 Generation Scenario (Partial Outage) 3 (Partial Outage) Load Pocket EF PR AAT EF PR AAT EF PR AAT WOTAB + Western (1.2) 6.8 WOTAB (0.8) 6.8 WOTAB + Western (0.3) WOTAB (0.4) WOTAB + Western WOTAB WOTAB + Western WOTAB (0.8) 2.2 WOTAB + Western WOTAB Economic Planning User Group Meeting, August 11th 2017

29 Make Whole Payment reduction for WOTAB Economic Project Alternative 2 Generation Scenario (Partial Outage) 3 (Partial Outage) Load Pocket EF PR AAT EF PR AAT EF PR AAT WOTAB + Western WOTAB WOTAB + Western WOTAB (0.1) 1.1 WOTAB + Western WOTAB WOTAB + Western WOTAB WOTAB + Western WOTAB Economic Planning User Group Meeting, August 11th 2017

30 Make Whole Payment reduction for WOTAB Economic Project Alternative 3 Generation Scenario (Partial Outage) 3 (Partial Outage) Load Pocket EF PR AAT EF PR AAT EF PR AAT WOTAB + Western (0.2) WOTAB (0.2) WOTAB + Western (0.7) WOTAB (0.7) WOTAB + Western WOTAB WOTAB + Western WOTAB WOTAB + Western WOTAB Economic Planning User Group Meeting, August 11th 2017

31 Minimum Project Design Criteria Minimum project requirements for the Market Efficiency Projects (MEP) are specified in BPM-029 Some design requirements are solution specific and are determined through additional analysis 30 Economic Planning User Group Meeting, August 11th 2017

32 Minimum Design Criteria Selection for WOTAB Economic Project 500kV Transmission Line Line Rating 3000A (Default Minimum Transmission Circuit Ampere Ratings) Sabine Substation 500/230kV Transformer Impedance: >7% Rating: 1200MVA (3-phase) 230kV Breaker Symmetrical Interruption Rating (ka) 63kA 31 Economic Planning User Group Meeting, August 11th 2017

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

ICT Strategic Transmission Plan (ISTEP) Review and Status Update

ICT Strategic Transmission Plan (ISTEP) Review and Status Update ICT Strategic Transmission Plan (ISTEP) Review and Status Update Entergy Transmission Summit July 29, 2008 Astor Crown Plaza New Orleans, Louisiana Douglas Bowman, PE Lead Engineer, ICT Planning 501-688-1640

More information

1. Administrative Items... SPP. 2. Stakeholder Web-Presentation... ABB

1. Administrative Items... SPP. 2. Stakeholder Web-Presentation... ABB Southwest Power Pool, Inc. ENTERGY REGIONAL STATE COMMITTEE MINIMIZING BULK POWER COSTS STUDY STAKEHOLDER MEETING Face-to-face & Web-conference Hyatt Regency DFW DFW Airport, TX Room: Maverick AGENDA July

More information

Market Efficiency Planning Study

Market Efficiency Planning Study Market Efficiency Planning Study West SPM June 12, 2013 SPM : Market Efficiency Planning Study Update March 25, 2012 Market Efficiency Planning Study Recap Objective is to execute an annual structured

More information

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 14, 2005 1 2004-06 EGSI-TX Transmission Western Region Reliability

More information

Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects

Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects Entergy Texas, Inc. Transmission 2014 2018 Draft Construction Plan Update 1 Projects 1 2014-2018 ETI Draft Construction Plan Update 1 Projects Completed in the Fall of 2012 & 2013 to date 1) Cedar Hill

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects

Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 13, 2006 1 Approved 2006 2010 ELL-South Transmission

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

MTEP14 South SPM #2. MISO Texas Project Information. April 7, 2014

MTEP14 South SPM #2. MISO Texas Project Information. April 7, 2014 MTEP14 South SPM #2 MISO Texas Project Information April 7, 2014 MISO Southern Region EAST TEXAS ELECTRIC COOPERATIVE 2 East Texas Electric Cooperative (ETEC) No projects submitted for moving to Appendix

More information

SPP OVERVIEW. Mike Ross Senior Vice President, Government Affairs and Public Relations

SPP OVERVIEW. Mike Ross Senior Vice President, Government Affairs and Public Relations SPP OVERVIEW Mike Ross Senior Vice President, Government Affairs and Public Relations 1 Our Mission Helping our members work together to keep the lights on today and in the future. 2 NORTH AMERICAN INDEPENDENT

More information

Transmission Planning using Production Cost Simulation & Power Flow Analysis

Transmission Planning using Production Cost Simulation & Power Flow Analysis ABB Transmission Planning using Production Cost Simulation & Power Flow Analysis Jinxiang Zhu, Ph.D. Senior Principal, ABB Power Consulting ABB Group January 16, 2018 Slide 1 Power System Studies TECHNICAL

More information

CIL/CEL Values and Study Timeline

CIL/CEL Values and Study Timeline 2019-2020 CIL/CEL Values and Study Timeline LOLEWG 9/11/2018 Updated 10/3/2018 1 Purpose and Key Takeaways Purpose Inform stakeholders of Draft 2019-20 Capacity Import and Export Limits. Key Takeaways

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Impacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities

Impacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities Impacts of MISO DPP-2016-February (West, ATC, MI, South) 1. MISO generators studied: Projects on PJM Facilities Net MW size (Summer) Net MW size (Winter) Service DPP Project Type Region Fuel Type POI J432

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

MTEP13 SPM #2- Central Region. March 25, 2013

MTEP13 SPM #2- Central Region. March 25, 2013 MTEP13 SPM #2- Central Region Ameren Missouri March 25, 2013 Ameren Missouri Project Review Central Region: Ameren Missouri Ameren Missouri has a total of 10 project proposals that are recommended for

More information

High Plains Regional Transmission Summit. Timelines for Planning Processes / Policy

High Plains Regional Transmission Summit. Timelines for Planning Processes / Policy High Plains Regional Transmission Summit John Lawhorn Director Regulatory & Economic Studies Midwest ISO November 2, 2009 Timelines for Planning Processes / Policy 1 year 20 year Planning Horizons Queue

More information

The Transmission Lay of the Land

The Transmission Lay of the Land The Transmission Lay of the Land Overview Energy Markets Transmission Planning Beth Soholt John Moore April 21, 2010 Overview Regional Transmission Organizations Organizations of transmission owners, users,

More information

Market Efficiency Update

Market Efficiency Update Market Efficiency Update Transmission Expansion Advisory Committee July 13, 2017 Agenda Where we are in the process Interregional Projects Status RPM Projects Status Reevaluation Analysis Status Next Steps

More information

Market Efficiency Update

Market Efficiency Update Market Efficiency Update Transmission Expansion Advisory Committee October 12, 2017 Market Efficiency Proposal Window 2016-2017 Long Term Proposal Window 1A 2 2016-2017 Long Term Proposal Window 1A Addendum

More information

Reliability Analysis Update

Reliability Analysis Update Reliability Analysis Update Transmission Expansion Advisory Committee October 11, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects

More information

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross Briefing for the Kansas Legislature March 6, 2013 Paul Suskie & Mike Ross psuskie@spp.org mross@spp.org 501.614.3200 Presentation overview Who we are What we do How we benefit the consumer Industry dynamics

More information

2015 Grid of the Future Symposium

2015 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee February 7, 2013 1 Issues Tracking 2 Issues Tracking Open Issues None New Issues 3 2013 RTEP Scenario Analysis 4 RTEP Scenario Analysis 2012 North Carolina Transmission

More information

Western NY Public Policy Transmission Planning Report

Western NY Public Policy Transmission Planning Report Western NY Public Policy Transmission Planning Report Dawei Fan Supervisor, Public Policy and Interregional Planning Business Issues Committee September 12, 2017 Operating Committee September 15, 2017

More information

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool WIRES University Overview of ISO/RTOs Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool 1 OUR MISSION Helping our members work together to keep the lights on

More information

Draft Results and Open House

Draft Results and Open House Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi

More information

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Western Region ATSI Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these

More information

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010 FINAL FACILITY STUDY 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1 September 10, 2010 I. Introduction This is a revised facility study performed for Transmission Queue Request 2009

More information

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study ` Dunvegan Hydroelectric Project For Glacier Power Limited Preliminary Interconnection Study Prepared by Pung Toy, P. Eng. and Ata Rehman, P. Eng. September 24, 2004 Table of Contents Table of Contents...

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

System Impact Study PID MW Plant

System Impact Study PID MW Plant System Impact Study PID 257 252 MW Plant Prepared by: Southwest Power Pool Independent Coordinator of Transmission 415 N. McKinley, Suite140 Little Rock, AR 72205 Rev Issue Date Description of Revision

More information

IMM Quarterly Report: Summer 2017

IMM Quarterly Report: Summer 2017 IMM Quarterly Report: Summer 2017 MISO Independent Market Monitor David Patton, Ph.D. Potomac Economics September 19, 2017 Highlights and Findings: Summer 2017 The MISO markets performed competitively

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

Project #94. Generation Interconnection System Impact Study Report Revision

Project #94. Generation Interconnection System Impact Study Report Revision Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

Donna Painter, Executive Consultant February 27, 2013

Donna Painter, Executive Consultant February 27, 2013 Donna Painter, Executive Consultant February 27, 2013 Transmission What is it and How has it Evolved Legislation and Regulatory Impacts What is Next for AMEA and Others Transmission System High voltage

More information

The Long-Range Transmission Plan

The Long-Range Transmission Plan The Long-Range Transmission Plan 2015 2025 Matt Koenig Presentation to ESPWG / TPAS October 29 th, 2015 Long-Range Transmission Plan Driver of the Plan is to maintain local reliability 10-year planning

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

STH 60 Northern Reliever Route Feasibility Study Report

STH 60 Northern Reliever Route Feasibility Study Report #233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development

More information

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS El Paso Electric Company System Operations Department System Planning

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

Updates. Pat Reiten President and CEO, PacifiCorp Transmission

Updates. Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission and Regional Updates Pat Reiten President and CEO, PacifiCorp Transmission PacifiCorp Transmission Overview 16,400 circuit-miles of transmission lines 12,685 MW record peak demand

More information

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT

More information

FACILITIES STUDY TRANSMISSION SERVICE REQUESTS OASIS

FACILITIES STUDY TRANSMISSION SERVICE REQUESTS OASIS TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:EGSI -LA CUSTOMER: NRG FACILITIES STUDY EJO # F4PPGS0411 TRANSMISSION SERVICE REQUESTS OASIS 1521373 Revision: 0 Issue Revised Project Rev Description of Revision

More information

SERTP rd Quarter Meeting

SERTP rd Quarter Meeting 2015 SERTP SERTP 2015 3 rd Quarter Meeting 2nd RPSG Meeting September 24 th, 2015 APC Headquarters Birmingham, AL 2015 SERTP Process Information The SERTP process is a transmission planning process. Please

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Generation Deactivation Notification Update

Generation Deactivation Notification Update Generation Deactivation Notification Update Transmission Expansion Advisory Committee November 8, 2018 Generation Deactivations for 2018 2 Generation Deactivation ATSI Transmission Zones Bruce Mansfield

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Proposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1

Proposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1 Proposed FY 2019-2023 Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1 The Capital Improvement Program is: A fiscally constrained, 5-year program of capital projects An implementation

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Market Efficiency Update

Market Efficiency Update Market Efficiency Update Transmission Expansion Advisory Committee August 10, 2017 Where we are - Market Efficiency Timeline 2 2016-2017 Window Market Efficiency Base Case Mid-Cycle Update Base case to

More information

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016 New Transmission Line April 1, 2016 The enclosed information is proprietary to PSE&G and is provided solely for your use. It should not be copied, reproduced, or shared with others without PSE&G s prior

More information

SPP Reliability Coordinator TLR 5 Analysis Report for the ICT Reliability Area

SPP Reliability Coordinator TLR 5 Analysis Report for the ICT Reliability Area SPP Reliability Coordinator TLR 5 Analysis Report for the ICT Reliability Area MAINTAINED BY SPP Reliability Coordinator PUBLISHED: 10/11/2010 LATEST REVISION: 10/12/2010 Copyright 2010 by Southwest Power

More information

New Jersey State Report

New Jersey State Report New Jersey State Report July 2017 Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast 2. Markets Capacity Market Results Market Analysis 3. Operations Emissions

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

TEXAS ECONOMIC STUDY REPORT ICTES INFORMATIONAL ONLY

TEXAS ECONOMIC STUDY REPORT ICTES INFORMATIONAL ONLY TEXAS ECONOMIC STUDY REPORT ICTES-2011-001 INFORMATIONAL ONLY Prepared for: Entergy Service, Inc. (SPO) American Electric Power Service Corporation (AEPSC) GDS Associates, Inc. (GDS), as agent of East

More information

LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST

LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST Cleco Power LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST OASIS 71956063 0 Rev Issue Date Description of Revision Table of Contents 1. Purpose...3 2. System Impact Study Conclusions...3 2.1 The Pineville

More information

APPENDIX F: Project Need and Description

APPENDIX F: Project Need and Description APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was

More information

Draft Results and Recommendations

Draft Results and Recommendations Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Recommendations Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System

More information

Business Park North Muskegon County, MI

Business Park North Muskegon County, MI Business Park North Muskegon County, MI OVERVIEW January 1, 2017 CONTACT US Scott Corrin, Economic Development Manager 517-374-2248 scott.corrin@cmsenergy.com Consumers Energy Business Center 800-805-0490

More information

The Energy Queensland Group Notice of no non-network options

The Energy Queensland Group Notice of no non-network options The Energy Queensland Group Notice of no non-network options 24 September 2018 MCE Mount Crosby East Establish new substation to replace Mount Crosby Substation (SSMTC) Page 1 of 1 DISCLAIMER While care

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC

More information

The Development of Competitive Renewable Energy Zones in Texas

The Development of Competitive Renewable Energy Zones in Texas The Development of Competitive Renewable Energy Zones in Texas Warren Lasher Manager, System Assessment 4/23/2008 North American Electric Grids The ERCOT Region is one of 3 NERC grid interconnections.

More information

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION El Paso Electric Company System Operations Department System Planning Section August 2006 I. INTRODUCTION The

More information

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia

More information

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic August 24, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects from the competitive planning

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

Western NY Public Policy Transmission Report

Western NY Public Policy Transmission Report Western NY Public Policy Transmission Report Dawei Fan Supervisor, Public Policy and Interregional Planning ESPWG/TPAS July 20, 2017, KCC Agenda Public Policy Transmission Planning Process Western NY Public

More information

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report ORANGE COUNTY TRANSPORTATION AUTHORITY Agreement to Purchase Compressed Natural Gas Articulated Staff Report November 8, 2012 To: From: Subject: Transit Committee Will Kempton, Chief Executive Officer

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

PSE Attachment K Puget Sound Area Transmission Meeting

PSE Attachment K Puget Sound Area Transmission Meeting PSE Attachment K Puget Sound Area Transmission Meeting Stephanie Lu Senior Engineer December 15, 2011 Agenda Attachment K Review Economic Studies Process PSE Planning Process and Assumptions PSE Projects

More information

Reliability Analysis Update

Reliability Analysis Update Reliability Analysis Update Transmission Expansion Advisory Committee February 8, 2018 2018 RTEP Analysis Update 2 PSE&G Transmission Zone Transmission Service Update 3 Linden VFT Previous agreements:

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

Muskegon Waste Water Treatment Site Muskegon County, MI

Muskegon Waste Water Treatment Site Muskegon County, MI Muskegon Waste Water Treatment Site Muskegon County, MI OVERVIEW January 1, 2017 CONTACT US Scott Corrin, Economic Development Manager 517-374-2248 scott.corrin@cmsenergy.com Consumers Energy Business

More information

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202 Transmission and Distribution Substation Projects Operating Company: Entergy Gulf States - Texas Customer: PID # 202 Funding Project Number: F4PPGS0386 Facility Study for PID # 202: Study for 146 MW Revision

More information

Sub Regional RTEP Committee - Southern. August 19, 2011

Sub Regional RTEP Committee - Southern. August 19, 2011 Sub Regional RTEP Committee - Southern August 19, 2011 2011 RTEP Analysis Summary 2010 2015 Project Updates 2016 Analysis NERC Category A, B NERC Category C (N-1-1 in progress) Load Deliverability Generator

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Waco Rapid Transit Corridor (RTC) Feasibility Study

Waco Rapid Transit Corridor (RTC) Feasibility Study Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM

More information

SERTP rd Quarter Meeting

SERTP rd Quarter Meeting 2014 SERTP SERTP 2014 3 rd Quarter Meeting 2 nd RPSG Meeting September 30 th, 2014 APC Headquarters Birmingham, AL 2014 SERTP Process Information The SERTP process is a transmission planning process. Please

More information

VIRGINIA RAILWAY EXPRESS MANASSAS PARK STATION PARKING EXPANSION. Site Evaluation & Recommendation. October 18, 2016

VIRGINIA RAILWAY EXPRESS MANASSAS PARK STATION PARKING EXPANSION. Site Evaluation & Recommendation. October 18, 2016 MANASSAS PARK STATION PARKING EXPANSION Site Evaluation & Recommendation October 18, 2016 1 INFORMATION ITEM Project Overview Parking Demand Site Evaluation VRE Recommended Preferred Alternative Next Steps

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

Interconnection and Net Metering Service in Ohio

Interconnection and Net Metering Service in Ohio Interconnection and Net Metering Service in Ohio Partnership between National Association of Regulatory Utility Commissioners and The National Commission for Energy State Regulation of Ukraine June 20,

More information

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving

More information

Donna S. Painter Record of Litigation Experience

Donna S. Painter Record of Litigation Experience Page 1 ER13-1605-000 NV Energy Operating Companies Las Vegas Power Transmission cost of service and 2013-14 Company LLC revenue requirements, postage stamp and zonal rates United States District Court,

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

The North Carolina solar experience: high penetration of utility-scale DER on the distribution system

The North Carolina solar experience: high penetration of utility-scale DER on the distribution system 1 The North Carolina solar experience: high penetration of utility-scale DER on the distribution system John W. Gajda, P.E. Duke Energy IEEE PES Working Group on Distributed Resources Integration 2 High

More information

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY Short Circuit Analysis System Operations Department System Planning Section March 2001 I. Introduction XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information