1 Sub Regional RTEP Committee Mid-Atlantic September 24,
2 Reliability Analysis Update 2
3 AE Transmission Zone Generation Deliverability Violation: The Middle 230/69 kv is overloaded for line fault stuck breaker contingency loss of the BL England Middle - Carson and Carson - Dennis 138 kv circuits. Recommended Solution: Replace Middle T3 138/69 kv transformer with 225 MVA nameplate. (B2553) Project ID: P2014_1-12J-U from 2014 RTEP Proposal Window #1 $ 7.5 M Required IS Date: 6/1/2019 3
4 PECO Transmission Zone N-1-1 Violation. The Eddystone to Llanerch 138 kv circuit is overloaded for N-1-1 contingency loss of Plymouth Brynmawr 230 kv and Eddystone to Llanerch 138 kv circuits. Recommended Solution: Replace terminal equipment inside Llanerch substation on the (Eddystone to Llanerch) 138 kv line (B2551). Project ID: P2014_1-5E-U from 2014 RTEP Proposal Window #1 $ 0.1 M Required IS Date: 6/1/2019 4
5 Supplemental 5
6 AE Transmission Zone Supplemental Project : Improves reliability due to age and condition of the circuit. Rebuild 1.86 miles of the Corson-Middle-Lake 69 kv circuit '0720', sections P-Z Lake Tap, including Sections S through V. (S0789) $ 7.83 M 5/31/2015 6
7 AE Transmission Zone Supplemental Project : Improves reliability due to age and condition of the transformer. Replace (9) Single phase 138/69 KV Auto Transformer Units with (3) Three Phase 138/69 KV Auto Transformer at Lewis substation. (S0790) $ M 5/31/2015 7
8 Improves reliability due to age and condition of the circuit. Rebuild miles the Deepwater to Salem 69 kv circuit '0724'. (S0791) $ 5.32 M 12/31/2015 AE Transmission Zone 8
9 Improves reliability due to age and condition of the circuit. Rebuild the Lewis- Ontario #2 69 kv circuit (S0792) $ M 6/1/2016 AE Transmission Zone 9
10 Improves reliability due to age and condition of the circuit. Rebuild approximately 6.4 miles of the Lewis - Higbee 69 kv #1 circuit. (S0793) $ M 6/1/2016 AE Transmission Zone 10
11 AE Transmission Zone Supplemental Project : Improves reliability due to age and condition of the transformer. Replace the existing Sickler T1-230/69kV, autotransformer with a 230/69kV, 335 MVA Transformer. (S0794) $ 7.5 M 5/1/
12 Improves reliability due to age and condition of the circuit. Rebuild 4.14 miles of the Corson-Sea Isle-Swainton 69 kv circuit '0717', sections B & C. (S0795) $ 5.5 M 6/1/2017 AE Transmission Zone 12
13 Improves reliability due to age and condition of the circuit. Rebuild the Corson- Middle #1 138 kv circuit '1412'. (S0796) $ 13.5 M 12/31/2017 AE Transmission Zone 13
14 AE Transmission Zone Supplemental Project : Improves reliability due to age and condition of the circuit. Rebuild the Upper Pittsgrove - Landis 138 kv '1406' 138kv circuit. The rebuild will include parts of the 1404 and 1405 circuits. (S0797) $ M 12/31/
15 Improves reliability due to age and condition of the circuit. Rebuild the Monroe- Lewis 138 kv '1404' Sections B-E. (S0798) $ M 3/31/2020 AE Transmission Zone 15
16 To improves reliability due to the retirement of the of the Deepwater substation. Install 336 MVA 230/138 kv transformer at Churchtown to be connected to the Pittsgrove. (S0799) $ 8.58 M 5/31/2016 AE Transmission Zone 16
17 To improves reliability due to the retirement of the of the Deepwater substation. Install 69/34 kv transformer at Churchtown to feed Valley substation. (S0800) $ 2.7 M 5/31/2016 AE Transmission Zone 17
18 AE Transmission Zone Supplemental Project : To improves reliability due to the retirement of the of the Deepwater substation. Re-terminate Deepwater- Beckett 69 kv line at Churchtown Sub as a result of Deepwater retirement. (S0801) $ 2.57 M 12/31/
19 AE Transmission Zone Supplemental Project : To improves reliability due to the retirement of the of the Deepwater substation. Re-terminate Deepwater- Salem 69 kv line at Churchtown Sub as a result of Deepwater retirement. (S0802) $ 2.57 M 12/31/
20 AE Transmission Zone Supplemental Project : To improves reliability due to the retirement of the of the Deepwater substation. Re-terminate the Deepwater- Woodstown #1 69 kv line at Churchtown Substation as a result of Deepwater retirement. (S0803) $ 1.8 M 5/31/
21 AE Transmission Zone Supplemental Project : To improves reliability due to the retirement of the of the Deepwater substation. Build, and/or rebuild 3.2 miles of 69 kv line to connect the Churchtown - Pennsgrove 69 kv line to Carneys Point. (S0804) $ 2.4 M 5/31/
22 To improves reliability due to the retirement of the of the Deepwater substation. Install 69 kv double ring bus with normally closed bus tie, with 12 (ultimate) terminal positions. (S0805) $ 10.6 M 5/31/2017 AE Transmission Zone 22
23 AE Transmission Zone Supplemental Project : To improves reliability due to the retirement of the of the Deepwater substation. Re-terminate #2 Deepwater- Woodstown 69 kv line at Churchtown Sub as a result of Deepwater retirement. (S0806) $ 2.57 M 5/31/
24 AE Transmission Zone Supplemental Project : To improves reliability due to the retirement of the of the Deepwater substation. Re-terminate Deepwater- Pennsgrove 69 kv line at Churchtown Sub as a result of Deepwater retirement. (S0807) $ 2.57 M 5/31/
25 To improves reliability due to the retirement of the of the Deepwater substation. Retire the Deepwater 138 kv and 69 kv substation. (S0808) $ 1.7 M 12/31/2018 AE Transmission Zone 25
26 Improves reliability due to age and condition of the circuit. Rebuild the Mill - Marven 69 kv circuit '0749'. (S0809) $ M 12/31/2018 AE Transmission Zone 26
27 Improves reliability due to age and condition of the circuit. Rebuild the Corson - Merion 138 kv circuit '1411'. (S0810) $ M 12/31/2018 AE Transmission Zone 27
28 Improves reliability due to age and condition of the circuit. Rebuild the BL England - Scull - Mill - Lewis 138 kv #1 circuit '1407'. (S0811) $ M 12/31/2020 AE Transmission Zone 28
29 Improves reliability due to age and condition of the circuit. Rebuild the BL England - Scull - Mill - Lewis 138 kv #2 circuit '1408'. (S0812) $ 9.55 M 12/31/2020 AE Transmission Zone 29
30 Improves reliability due to age and condition of the circuit. Rebuild miles of Circuit the Lewis - Motts Farm 69 kv circuit '0702'. (S0813) $ 24.6 M 5/31/2015 AE Transmission Zone 30
31 Improves reliability due to age and condition of the circuit. Rebuild 10.8 miles of the Salem to Woodstown 69 kv circuit '0745'. (S0814) $ 24.6 M 12/31/2015 AE Transmission Zone 31
32 Improves reliability due to age and condition of the circuit. Rebuild 5.15 miles of the Lincoln - Union 138kV circuit '1419' to 2000A with 1590 ACSR. (S0815) $ 7 M 12/31/2016 AE Transmission Zone 32
33 Improves reliability due to age and condition of the circuit. Rebuild 0.23 mile section of the Cumberland - Sherman 138kV circuit to 2000A with 1590 ACSR. (S0816) $ 0.34 M 12/31/2015 AE Transmission Zone 33
34 Improves reliability due to age and condition of the circuit. Rebuild the Wells- Harrington 69 kv circuit '6784'. (S0817) $ 8.79 M 12/31/2015 DPL Transmission Zone 34
35 Improves reliability due to age and condition of the circuit. Rebuild the Salisbury - Worcester 69 kv circuit '6741 '. (S0818) $ M 5/31/2016 DPL Transmission Zone 35
36 Improves reliability due to age and condition of the circuit. Rebuild the North Salisbury - Pemberton 69 kv circuit ' 6701'. (S0820) $ 1.36 M 12/31/2016 DPL Transmission Zone 36
37 Improves reliability due to age and condition of the circuit. Rebuild the Church - Steele 138 kv circuit ' 13701'. (S0821) $ 29.5 M 5/31/2017 DPL Transmission Zone 37
38 Improves reliability due to age and condition of the circuit. Rebuild the Hares Corner - Red Lion 138 kv circuit ' '. (S0822) $ 4.22 M 12/31/2017 DPL Transmission Zone 38
39 Improves reliability due to age and condition of the circuit. Rebuild the Mt. Hermon - Chesapeake 69 kv circuit '6726'. (S0824) $ 1.36 M 12/31/2017 DPL Transmission Zone 39
40 Improves reliability due to age and condition of the circuit. Rebuild 4.58 miles of the Basin Rd - Bear 138 kv circuit '13816'. (S0825) $ 8.48 M 12/31/2018 DPL Transmission Zone 40
41 Improves reliability due to age and condition of the circuit. Rebuild the Hillsboro - Wye Mills 138 kv circuit '13788'. (S0826) $ 9.15 M 12/31/2018 DPL Transmission Zone 41
42 Improves reliability due to age and condition of the circuit. Replace the Kings Creek AT1 138/69 kv autotransformer. (S0827) $ 1.75 M 12/31/2018 DPL Transmission Zone 42
43 DPL Transmission Zone Supplemental Project : During peak loading the Crisfield generation cannot support the load along 6725 when Kings Creek AT1 is taken out of service. All planned outages are limited to a short window during the fall or spring. Emergency outages during peak and moderate load conditions could result in the loss of load for potentially significant durations. Relocate Line going into Kings Creek substation during the construction of the new Kings Creek 69kV bus. (S0828) $ 0.25 M 12/31/
44 DPL Transmission Zone Supplemental Project : During peak loading the Crisfield generation cannot support the load along 6725 when Kings Creek AT1 is taken out of service. All planned outages are limited to a short window during the fall or spring. Emergency outages during peak and moderate load conditions could result in the loss of load for potentially significant durations. A new terminal at Crisfield 69 kv substation for the new Kings Creek - Crisfield 69kV circuit. (S0829) $ 4.14 M 12/31/
45 DPL Transmission Zone Supplemental Project : During peak loading the Crisfield generation cannot support the load along 6725 when Kings Creek AT1 is taken out of service. All planned outages are limited to a short window during the fall or spring. Emergency outages during peak and moderate load conditions could result in the loss of load for potentially significant durations. A new terminal at Kings Creek 69 kv substation for the new Kings Creek - Crisfield 69kV circuit. (S0830) $ 4.69 M 12/31/
46 DPL Transmission Zone Supplemental Project : During peak loading the Crisfield generation cannot support the load along 6725 when Kings Creek AT1 is taken out of service. All planned outages are limited to a short window during the fall or spring. Emergency outages during peak and moderate load conditions could result in the loss of load for potentially significant durations. Rebuild the existing Kings Creek - Crisfield 69kV circuit '6725' and construct a 2nd Kings Creek - Crisfield 69 kv circuit. (S0831) $ M 12/31/
47 Improves reliability due to age and condition of the circuit. Rebuild 7 miles of the Fruitland - N Salisbury 69 kv circuit '6701'. (S0832) $ 8.33 M 12/31/2016 DPL Transmission Zone 47
48 Improves reliability due to age and condition of the circuit. Rebuild 6.16 miles of the Vienna - Nelson 138 kv circuit '13707' (Delaware). (S0833) $ 7.21 M 12/31/2018 DPL Transmission Zone 48
49 Improves reliability due to age and condition of the circuit. Rebuild 7.57 miles of the Vienna - Nelson 138 kv circuit '13707' (Maryland). (S0834) $ 8.9 M 12/31/2018 DPL Transmission Zone 49
50 Improves reliability due to age and condition of the circuit. Rebuild 14.7 miles of the Vienna - N. Salisbury 69 kv circuit '6708'. (S0835) $ 13.8 M 12/31/2018 DPL Transmission Zone 50
51 DPL Transmission Zone Supplemental Project : Improves reliability due to age and condition of the circuit. Resolves N-1-1 condition on non BES facility. Rebuild the Worcester - Ocean City 69kV circuit '6724'. (S0836) $ M 5/31/
52 DPL Transmission Zone Supplemental Project : Improves reliability due to age and condition of the circuit. Resolves N-1-1 condition on non BES facility. Upgrade terminal equipment at Worcester Substation on the Worcester - Ocean City 69 kv. (S0837) $ 0.37 M 5/31/
53 Thermal overload on the underground egress into Hoper Ave substation. Construct 34.5 kv bypass line at Hooper Ave. substation (S0787). $ 0.2 M 6/1/2015 JCPL Transmission Zone 53
54 Load connection. Tap the Tiffany Lennox 115 kv line and provide meter. (S0788) $ 0.7 M 9/19/2014 PenElec Transmission Zone 54
55 Improves reliability due to load growth. Install a new Waterfront 138/13kV Sub. 223 and build four new 138kV circuits from Buzzard Point to supply the station. (S0838) $ 76 M 12/31/2016 PEPCO Transmission Zone 55
56 Improves reliability due to load growth. Install Mt. Vernon 230/13kV Sub and 230kV High-Side- Bus at Takoma Sub. 27. Extend four new 230kV U.G. circuits from the new Takoma HSB to the Mt. Vernon substation on two separate rights-of-way. (S0839) $ 345 M 12/31/2021 PEPCO Transmission Zone 56
57 Improves reliability due to load growth. Install New Harvard 230/13kV Sub and supply the station by tapping two of the extend circuits to serve Mt. Vernon. (S0840) $ 110 M 12/31/2020 PEPCO Transmission Zone 57
58 Improves reliability due to load growth. Install New Harrison 138/13kV Sub, to replace the existing Harrison Sub. 38. Supply the station by cutting in and out of two 138kV circuits between Bethesda Sub. 6 and Van Ness Sub (S0841) $ 73.5 M 12/31/2027 PEPCO Transmission Zone 58
59 The shunt reactors are being added at Alabama Ave Sub. 136 on Feeders and to avoid overvoltage issues on the 230kV and 13.8kV buses at the station. Operating procedures are currently in place to address this problem, but result in the station Firm Capacity being based on the loss of two transformers. With the shunt reactors in place the Firm Capacity will be based on a single transformer outage with a resultant increase in capacity. Install two 100 MVAR Shunt Reactors at Alabama Avenue Sub (S0842) $ 12 M 12/31/2016 PEPCO Transmission Zone 59
60 Improves reliability due to age and condition of the transformer. Replace Palmers Corner Sub. 84 TR #3 with a new 230/69kV 224 MVA transformer. (S0843) $ 2.2 M 1/12/2015 PEPCO Transmission Zone 60
61 Improves reliability due to age and condition of the transformer. Replace Bells Mill Sub. 121 TR #14 with a new 230/69kV 280 MVA transformer. (S0844) $ 3.3 M 1/31/2015 PEPCO Transmission Zone 61
62 Improves reliability by having Hot Standby to add operational flexibility. Install Palmers Corner Sub /69kV 224 MVA TR #1. (S0845) $ 3 M 3/4/2015 PEPCO Transmission Zone 62
63 Improves reliability due to age and condition of the transformer. Replace Norbeck Sub. 158 TR #3 with a new 230/69kV 224 MVA transformer. (S0846) $ 2.7 M 5/1/2015 PEPCO Transmission Zone 63
64 Improves reliability due to age and condition of the transformer. Replace Norbeck Sub. 158 TR #4 with a new 230/69kV 224 MVA transformer. (S0847) $ 2.6 M 6/2/2015 PEPCO Transmission Zone 64
65 Improves reliability due to age and condition of the transformer. Replace Quince Orchard Sub. 118 TR #3 with a new 230/69kV 224 MVA transformer. (S0848) $ 2.7 M 6/15/2015 PEPCO Transmission Zone 65
66 Improves reliability due to age and condition of the transformer. Replace Norbeck Sub. 158 TR #2 with a new 230/69kV 224 MVA transformer. (S0849) $ 2.5 M 11/1/2015 PEPCO Transmission Zone 66
67 Improves reliability due to age and condition of the transformer. Replace Quince Orchard Sub. 118 TR #1 with a new 230/69kV 224 MVA transformer. (S0850) $ 2.7 M 12/15/2015 PEPCO Transmission Zone 67
68 Supplemental Project: Improve reliability due to age and condition of the transformer. Replace Brunswick 230/69 kv transformer (S0758). $ 15 M 12/31/2015 PSE&G Transmission Zone 68
69 PSE&G Transmission Zone Supplemental Project: To improve reliability due to load increase in the Kearny vicinity. In addition it improves reliability and transformer condition at several Class H substations. Install two 230/13 kv transformers at Kearny Substation (S0759). $ 14 M 12/31/
70 PSE&G Transmission Zone Supplemental Project: To improve reliability due to station overload. In addition it improves reliability and transformer condition at several Class H substations. Install two 230/13 kv transformers at Waldwick Substation (S0760). $ 14 M 12/31/
71 Supplemental Project: Improve reliability due to age and condition of the transformer. Replace Brunswick 230/69 kv transformer (S0761). $ 15 M 12/31/2017 PSE&G Transmission Zone 71
72 Supplemental Project: To improve reliability and transformer availability during contingency/failure Purchase one spare 230/ kv dual ratio high side transformer (S0762). $ 7.8 M 12/31/2015 PSE&G Transmission Zone 72
73 Supplemental Project: To improve reliability and transformer availability during failure. Purchase eight 69/4 kv Transformers for future use (S0763). $ 3.6 M 12/31/2017 PSE&G Transmission Zone 73
74 Supplemental Project: To improves reliability by remotely monitoring major assets Install microprocessor relays, transformer equipments, SCADA systems and alarm panels at Lake Nelson T-1, Harts Lane T-1, T-2, T-3, Sand Hills T-1, T-2 and Federal Square T-1, T-2, T-3 (S0851). $ 13.5 M 12/31/2015 PSE&G Transmission Zone 74
75 Questions? 75
76 Revision History Revision History Version 1: Original version posted to the PJM TEAC on 9/23/
Sub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic July 26, 2016 Reliability Analysis Update MetEd Transmission Zone N-1 First Energy Planning Criteria (FERC Form 715): The North Boyertown West Boyertown 69 kv is
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic November 04, 2013 2013 RTEP Baseline Analysis Update 11/04/2013 AE Transmission Zone Cost Change for B2354 Install second 230/69kV transformer and 230kV circuit
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic August 24, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects from the competitive planning
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic December 19, 2017 First Preliminary Review Baseline Reliability and Supplemental Projects 2 The slide was previously presented at 8/31/2017 and is replaced by the
More informationReliability Analysis Update
Reliability Analysis Update Transmission Expansion Advisory Committee October 11, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects
More informationNew Jersey State Report
New Jersey State Report July 2017 Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast 2. Markets Capacity Market Results Market Analysis 3. Operations Emissions
More informationTransmission Expansion Advisory Committee
Transmission Expansion Advisory Committee March 6, 2014 1 2014 RTEP Update 2 2014 RTEP Update Initial 2019 Summer base case and corresponding machine list update complete PJM staff has been reviewing and
More informationTransmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board
Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board PJM Staff Whitepaper October 2013 EXECUTIVE SUMMARY On December 5, 2012 the PJM Board of Managers approved changes to the
More informationTransmission Expansion Advisory Committee
Transmission Expansion Advisory Committee February 7, 2013 1 Issues Tracking 2 Issues Tracking Open Issues None New Issues 3 2013 RTEP Scenario Analysis 4 RTEP Scenario Analysis 2012 North Carolina Transmission
More informationPJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G
PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PSE&G System Characteristics New Jersey utility characterized by densely populated
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic March 23, 2018 First Review Baseline Reliability and Supplemental Projects 2 AEC Transmission Zone: Supplemental Project 69/12kV Wenonah Substation Retire/Bypass
More informationSub Regional RTEP Committee - Southern. August 19, 2011
Sub Regional RTEP Committee - Southern August 19, 2011 2011 RTEP Analysis Summary 2010 2015 Project Updates 2016 Analysis NERC Category A, B NERC Category C (N-1-1 in progress) Load Deliverability Generator
More informationReliability Analysis Update
Reliability Analysis Update Transmission Expansion Advisory Committee September 15, 2016 2016 RTEP Window #3 Anticipated Scope and Timeline Anticipated 2016 RTEP Window #3 Anticipated 2016 RTEP Window
More informationSubregional RTEP Committee Mid-Atlantic Area. September 9, 2008
Subregional RTEP Committee Mid-Atlantic Area September 9, 2008 PJM 2008 PJM 2008 JCPL N-2 Baseline Upgrades JCPL N-2 Baseline Upgrades - Werner Raritan River 115 kv line / loss of Smithburg-Englishtown
More informationSub Regional RTEP Committee South
Sub Regional RTEP Committee South October 30, 2017 Baseline Reliability and Supplemental Projects First Preliminary Review 2 Dominion: Baseline Violation 115 kv Line #43 Staunton to Harrisonburg End of
More informationTransmission Expansion Advisory Committee. Reliability Analysis Update
Transmission Expansion Advisory Committee Reliability Analysis Update October 8, 2015 Reliability Analysis Update ComEd Transmission Zone Operational Performance Reduce the complexity of the existing Powerton
More informationReliability Analysis Update
Reliability Analysis Update Transmission Expansion Advisory Committee February 8, 2018 2018 RTEP Analysis Update 2 PSE&G Transmission Zone Transmission Service Update 3 Linden VFT Previous agreements:
More informationSub-Regional RTEP Committee PJM South
Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic May 25, 2018 First Review Baseline Reliability and Supplemental Projects 2 Aging Infrastructure The 20.7 mile Five Forks Windy Edge 110511/110512 115kV Circuit
More informationPJM Regional Transmission Expansion Planning (RTEP) Process
PJM Regional Transmission Expansion Planning (RTEP) Process IPSAC May 18, 2018 PJM Planning Links Planning Committee (PC) http:///committees-and-groups/committees/pc.aspx Transmission Expansion Advisory
More informationPJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study
PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional
More informationFIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION
PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection
More informationSub Regional RTEP Committee South
Sub Regional RTEP Committee South December 18, 2017 Baseline Reliability and Supplemental Projects Second Review 2 Date Project Last Presented: 10/30/2017 SRRTEP Problem Statement: DOM End of Life Criteria
More informationSystem Impact Study Report
Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS
More informationTEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY
TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF
More informationIllinois State Report
July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:
More informationFeasibility Study Report
Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014
More informationCromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study
Cromby Units 1 and 2 and Eddystone Units 1 and 2 Deactivation Study Original Posting Date: March 2, 2010 Updated May 10, 2010 Updated June 7, 2010 Updated September 7, 2010 General PJM received notice
More informationGeneration Deactivation Notification Update
Generation Deactivation Notification Update Transmission Expansion Advisory Committee November 8, 2018 Generation Deactivations for 2018 2 Generation Deactivation ATSI Transmission Zones Bruce Mansfield
More information4.7: New Jersey RTEP Overview
State RTEP Overview Section PJM DE DC IL IN KY MD MI NJ NC OH PA TN VA WV.7: New Jersey RTEP Overview MAP.26: PJM Service Area in New Jersey PJM operates the electric transmission system for the delivery
More informationMarket Efficiency RTEP Proposal Window
Market Efficiency RTEP Proposal Window Market Efficiency RTEP Proposal Window Status Window opened on 8/12/2013 Closed on 9/26/2013 17 individual proposals addressing congestion from Market Efficiency
More informationReliability Analysis Update
Reliability Analysis Update Transmission Expansion Advisory Committee April 5, 2018 2018 RTEP Analysis Update 2 2018 Proposed schedule 2 nd -3 rd week of April Preliminary case available May-June Post
More informationSub Regional RTEP Committee Western Region ATSI
Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these
More informationReliability Analysis Update
Reliability Analysis Update Transmission Expansion Advisory Committee January 11, 2018 2017 RTEP Analysis Update 2 Generation Deliverability (Summer) (GD-S798 and GD- S815): Problem Statement: The Edge
More informationSub Regional RTEP Committee - Southern
Sub Regional RTEP Committee - Southern March 03, 2011 www.pjm.com 2010 RTEP Analysis Summary Review of ongoing projects Stakeholder request 2015 Analysis Update Review of NOVA Reliability Deficiencies
More informationSouth Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget
Project 1 of 34 Aiken Trans - Aiken Hampton 115 kv Line: Upgrade 1272A Upgrade the 115 kv line between Aiken and Aiken Hampton substations from 336 ACSR to 1272 ACSR. Total line length approximately 3.7
More informationSouth Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget
Project 1 of 28 Blythewood 115 kv Switching Station: Construct 03087A Construct Blythewood Switching Station with four 115 kv line terminals, with plans to expand to 230 kv at a future date. Fold in the
More informationReliability Analysis Update
Reliability Analysis Update Transmission Expansion Advisory Committee December 15, 2016 Clean Power Plan (CPP) Reliability Studies CPP Planning Background Provide a representative overview of the types
More informationEntergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects
Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 14, 2005 1 2004-06 EGSI-TX Transmission Western Region Reliability
More informationSub Regional RTEP Committee Mid-Atlantic First Energy MAAC Solution Meeting
Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC Solution Meeting November 28, 2018 JCP&L Transmission Zone Need Number: JCPL-2018-001 Process Stage: Solution Meeting Need Presented: 9/21/2018
More informationTransmission Expansion Advisory Committee Meeting. April 23, 2008
Transmission Expansion Advisory Committee Meeting April 23, 2008 PJM 2008 Agenda JCSP Update RTEP reliability baseline update Review initial baseline generator deliverability testing results Review initial
More informationMarket Efficiency RTEP Proposal Window
Market Efficiency RTEP Proposal Window Market Efficiency RTEP Proposal Window Status Window opened on 8/12/2013 Closed on 9/26/2013 17 individual proposals addressing congestion from Market Efficiency
More informationPID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation
PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date
More informationNorth Oregon Coast Area Study. Adam Lint
North Oregon Coast Area Study Adam Lint PAGE 2 North Oregon Coast System Overview - Clatsop Study Covers: Transmission Switching Stations (Clatsop District): Astoria Lewis and Clark 115 kv Distribution
More informationTransmission Expansion Advisory Committee
Transmission Expansion Advisory Committee January 9, 2014 1 2014 RTEP Assumptions (Continued from December 2013 TEAC) 2 RTEP - 2019 Model Status Case currently out to TO s for second review Case distributed
More informationTransmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation
Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT
More informationFalcon-Midway 115 kv Line Uprate Project Report
Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50
More informationPJM SRTEP Meeting Questions Pertaining to Proposed Projects & Scopes AEP: Ambler Ridge:
PJM SRTEP Meeting 2-13-2018 Questions Pertaining to Proposed Projects & Scopes AEP: Ambler Ridge: The problem statement states two 138kV CB s will be installed at Ambler Ridge, however the potential solution
More informationMarket Efficiency Update
Market Efficiency Update Transmission Expansion Advisory Committee December 13, 2018 2018/19 Long Term Window 2 2018/19 Long Term Window Problem Statement and Eligible Congestion Drivers posted on the
More informationATTACHMENT - DFO STATEMENT OF NEED
ATTACHMENT - DFO STATEMENT OF NEED Table of Contents Executive Summary... 3 1. Description of the Area... 5 1.1 Geographic Study Area... 5 1.2 Current System Configuration... 7 1.3 Distributed Generation...
More informationDFO STATEMENT OF NEED REPORT
APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading
More informationTRANSMISSION PLANNING CRITERIA
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing
More informationInterconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado
Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission
More informationNew Services Queue Network Upgrades
New Services Queue Network s September 2009 TEAC AEC Queue Number T84 Project Name Corson 138kV MWC MWE Fuel Type 70 350 Wind T146 England 69.2 346 Wind U1-056 U1-066 Lewis 138kV Carlls Corner 69kV 45.5
More informationPJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008
PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral
More informationEntergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects
Entergy Texas, Inc. Transmission 2014 2018 Draft Construction Plan Update 1 Projects 1 2014-2018 ETI Draft Construction Plan Update 1 Projects Completed in the Fall of 2012 & 2013 to date 1) Cedar Hill
More informationTransmission Expansion Advisory Committee
Transmission Expansion Advisory Committee March 7, 2013 1 Issues Tracking 2 Issues Tracking Open Issues None New Issues 3 Stage 1A ARR Transmission Project Update 4 Stage 1A ARR Transmission Project Byron
More informationCase Study- DG Uses at Conectiv Future Challenges & Opportunities
Case Study- DG Uses at Conectiv Future Challenges & Opportunities Joe Lo Porto Steve Steffel US DOE Mid-Atlantic Distributed Energy Resource Workshop- February 21, 2002 1 Case Study- DG Uses at Conectiv
More informationRogers Road to Clubhouse 230kV New Transmission Line April 1, 2016
New Transmission Line April 1, 2016 The enclosed information is proprietary to PSE&G and is provided solely for your use. It should not be copied, reproduced, or shared with others without PSE&G s prior
More informationProposed New Construction for
Tri-State Generation and Transmission Association, Inc. Colorado PUC E-Filings System Proposed New Construction for 2016 2019 Colorado PUC Rule 3206 Application April 28, 2016 TABLE OF CONTENTS A) Projects
More informationMTEP13 SPM #2- Central Region. March 25, 2013
MTEP13 SPM #2- Central Region Ameren Missouri March 25, 2013 Ameren Missouri Project Review Central Region: Ameren Missouri Ameren Missouri has a total of 10 project proposals that are recommended for
More informationFirst Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012
First Energy Generator Deactivation Request - January 2012 Deactivation Study Results and Required Upgrades April 25, 2012 General PJM received a notice on January 26, 2012 from FirstEnergy of its intent
More informationSTATE OF NEW JERSEY Board of Public Utilities 44 South Clinton Avenue, 9 th Floor P.O. Box 350 Trenton, New Jersey
STATE OF NEW JERSEY Board of Public Utilities 44 South Clinton Avenue, 9 th Floor P.O. Box 350 Trenton, New Jersey 08625-0530 IN THE MATTER OF THE PETITION OF ATLANTIC CITY ELECTRIC COMPANY FOR A DETERMINATION
More informationFeasibility Study Report
Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019
More information100 MW Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility
More informationWheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation
Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation 1. Description In the 2013-2014 Transmission Planning Cycle, the ISO approved the construction
More informationTwin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN
Twin Cities Minnesota Zone Meeting Xcel Energy May 11, 2005 Bloomington, MN Overview of Presentation Xcel Energy Projects: Aldrich to St Louis Park 115 kv line Eden Prairie to Edina 115 kv line Eden Prairie
More informationFeasibility Study Report
Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility
More informationSouth Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget
Project 1 of 24 Queensboro 115 kv Switching Station: Construct 0062A,B,C,D Build 4-terminal 115 kv switching station at Queensboro substation. Terminate the existing Queensboro St. Andrews, Church Creek
More informationSub Regional RTEP Committee PJM West
Sub Regional RTEP Committee PJM West July 27, 2018 First Review Baseline Reliability and Supplemental Projects 2 AEP Transmission Zone: Baseline B2798 Cancellation Cancel B2798 B2798 was presented in 5/31/2017
More informationThe Energy Queensland Group Notice of no non-network options
The Energy Queensland Group Notice of no non-network options 24 September 2018 MCE Mount Crosby East Establish new substation to replace Mount Crosby Substation (SSMTC) Page 1 of 1 DISCLAIMER While care
More informationLocal Transmission Plan. October 11, 2013 Revised August 25, 2014
Local Transmission Plan October 11, 2013 Revised August 25, 2014 2 Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated
More informationMarket Efficiency Update
Market Efficiency Update Transmission Expansion Advisory Committee October 12, 2017 Market Efficiency Proposal Window 2016-2017 Long Term Proposal Window 1A 2 2016-2017 Long Term Proposal Window 1A Addendum
More informationTransmission Expansion Advisory Committee Meeting 2014 Market Efficiency Analysis
Transmission Expansion Advisory Committee Meeting 2014 Market Efficiency Analysis September 02, 2014 Objectives To review simulated congestion results for all Market Efficiency study years To provide an
More informationElbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI
Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility
More informationATC Year Asessment Network Project List. Zone 2 switching initiative ASAP*** Operating flexibility Proposed -- --
ATC 20 10-Year Asessment Project List Project ACEC Dellwood Substation: Install line breakers to sectionalize Y- 146 20*** 20 1 T-D interconnection Planned A 7741 Zone 2 switching initiative ASAP*** 20
More informationMerchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.
Merchant Transmission Interconnection PJM Impact Study Report For PJM Merchant Transmission Request Queue Position X3-028 Breed 345 kv October/2014 System Impact Study Breed 345 kv Merchant Transmission
More informationGenerator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood
Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents
More informationSurry Skiffes Creek Whealton Modeling and Alternatives Analysis Review
Surry Skiffes Creek Whealton Modeling and Alternatives Analysis Review US Army Corps of Engineers Norfolk District Regulatory Office Received by: RLS Date: Feb 11, 2016 TOPICS Project Purpose, Need, Timeline
More informationAppendix D Black Hills Project Summary
Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain
More informationChapter 7 - Appendix A
Chapter 7 - Appendix A Transmission and Distribution Supplemental Information Table 7A.1 MTEP Transmission Projects in Missouri 1 Project Approved Project Title Project Description Category Estimated Cost
More informationTransmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona
Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff
More informationEL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS
EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004
More informationWestern Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04
Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch
More informationMILLIGAN SOLAR PROJECT
February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission
More informationMarket Efficiency Update
Market Efficiency Update Transmission Expansion Advisory Committee July 13, 2017 Agenda Where we are in the process Interregional Projects Status RPM Projects Status Reevaluation Analysis Status Next Steps
More informationMaddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016
New Transmission Line November 15, 2016 The enclosed information is proprietary to PSE&G and is provided solely for your use. It should not be copied, reproduced, or shared with others without PSE&G s
More informationStability Study for the Mt. Olive Hartburg 500 kv Line
Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.
More information2017 Indiana State Infrastructure Report (January 1, 2017 December 31, 2017)
2017 Indiana State Infrastructure Report (January 1, 2017 December 31, 2017) May 2018 This report reflects information for the portion of Indiana within the PJM service territory. Table of Contents 1.
More informationOuter Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)
Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving
More informationThe Capital Grid Project:
The Capital Grid Project: Building Tomorrow s Energy Grid Today Lamond- Riggs Citizens Association October 2, 2017 Agenda Welcome How Safe, Clean, and Affordable Energy is Delivered Our Current System
More informationNational Grid s 2017 Local Transmission Plan
National Grid s 2017 Local Transmission Plan Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.
More informationNational Grid s 2018 Local Transmission Plan
National Grid s 2018 Local Transmission Plan Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.
More informationSub Regional RTEP Committee - Western. October 21, 2009
Sub Regional RTEP Committee - Western October 21, 2009 Dayton Transmission Zone N-1-1 Thermal Violation Sidney - Shelby 138 kv line for the loss of Darby 138/69 kv transformer and Urbana 138/69 kv transformer
More informationEXCEPTIONS TO RELIABILITY RULES Revision 11 February 9, 2018
1 NYPA Run Back of EXCEPTIONS RELIABILITY RULES Revision 11 February 9, 2018 Post Contingency Flow on Marcy-New Scotland The post-contingency flow on the Marcy-New Scotland 18 line is allowed to exceed
More informationBlack Hills Project Summary
2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission
More informationPacific Gas and Electric Company s Revised 2015 Annual Progress
March 02, 2015 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Avista PO Box 3727 MSC-16 1411 East Mission Ave Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff 155 North 400 West
More informationMarch 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1
Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System
More informationTHE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS
THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive
More informationGeneration Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.
Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project April 23, 2003 Introduction Eurus originally requested an interconnection
More information