Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board

Size: px
Start display at page:

Download "Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board"

Transcription

1 Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board PJM Staff Whitepaper October 2013

2 EXECUTIVE SUMMARY On December 5, 2012 the PJM Board of Managers approved changes to the Regional Transmission Expansion Plan (RTEP), totaling $1,781.3 million, primarily to resolve identified baseline reliability criteria violations as well as to address reliability criteria violations driven by the proposed interconnection of new generation resources. Since that time PJM has identified additional baseline reliability criteria violations within the planning horizon as part of the 2013 RTEP. Transmission upgrades have been identified to resolve these reliability criteria violations. In addition, the cost and scope of a number of previously approved projects has changed. The total increase to the RTEP to include these baseline project changes is $1,241.1 million. With these changes, the RTEP will include over $24.2 billion of transmission additions and upgrades since the first plan was approved by the Board in The additional baseline upgrades that were reviewed with the PJM Board are summarized in the following paper. PJM 2013 Page 1 of 21 PJM DMS #768430

3 SUMMARY OF UPGRADES 2013 Baseline Transmission Upgrades Changes and Additions One aspect of the development of the Regional Transmission Expansion Planning Process is an evaluation of the baseline system, i.e. the transmission system without any of the generation interconnection requests included in the current planning cycle. This baseline analysis determines the compliance of the existing system with reliability criteria and standards. Transmission upgrades required to maintain a reliable system are identified and reviewed with the Transmission Expansion Advisory Committee (TEAC). The cost of transmission upgrades to mitigate such criteria violations are the responsibility of the PJM transmission owners. For the 2013 Plan, the baseline assessment resulted in the need for transmission upgrades in several transmission zones. A summary of the more significant baseline projects with expected costs greater than $5 million are detailed below. A complete listing of all of the new recommended projects is attached at the end of this white paper. The projects that cost less than $5 million include circuit breaker upgrades or replacements to address short circuit problems, new or upgrades to existing capacitor banks to address voltage violations, terminal equipment upgrades and conductor replacements to increase the ratings of transmission lines to address thermal violations. Mid-Atlantic Region System Upgrades Atlantic Electric Transmission Zone Upgrade the Tackahoe to Mill 69 kv line $9.9 M Install a 50 MVAR shunt reactor at Mickleton 230 kv and relocate the #1 230/69 kv transformer - $7.6 M Install a +150/-100 MVAR SVC at Cedar 230 kv - $23.2 M Rebuild 9.7 miles of the Upper Pittsgrove Landis 138 kv line and upgrade terminal equipment at Landis - $11.2 M BG&E Transmission Zone Install four 115 kv breakers at Chestnut Hill - $6.4 M Install a new 230/115 kv transformer at Raphael Road and build 115 kv line from Rpahael Road to Joppatowne - $35 M Build a new 115 kv underground line between Waugh Chapel and Bestgate - $27.2 M DPL Transmission Zone Build a new 138 kv line from Piney Grove to Wattsville - $16.3 M JCPL Transmission Zone Install a 260 MVAR shunt reactor at West Wharton 230 kv - $8 M PENELEC Transmission Zone Relocate substation controls from the deactivating Shawville generating station to a new substation control building - $6.7 M PJM 2013 Page 2 of 21 PJM DMS #768430

4 PEPCO Transmission Zone Add two 100 MVAR reactors at Dickerson Station H and two 100 MVAR reactors at Brighton 230 kv - $16 M PPL Transmission Zone Add a second 150 MVA 230/69 kv transformer at Springfield - $6.7 M Add a 150 MVAR shunt reactor at Alburtis 500 kv - $9 M Add a 100 MVAR shunt reactor at Elimsport - $6.5 M Rebuild Susquehanna Jenkins 230 kv circuit $109.5 M Rebuild the Siegfried Frackville 230 kv circuit - $84.5 M PSEG Transmission Zone Rebuild 4 miles of overhead line from Edison Meadow Rd Metuchen (Q-1317) - $46 M Install a 50 MVAR shunt reactor at Saddlebrook 230 kv - $9.2 M Install a 50 MVAR shunt reactor at Athenia 230 kv - $8.4 M Install a 50 MVAR shunt reactor at Bergen 230 kv - $8.3 M Install a 50 MVAR shunt reactor at Hudson 230 kv - $7.9 M Install two 50 MVAR shunt reactor at Stanley Terrace 230 kv - $15.7 M Install a 50 MVAR shunt reactor at West Orange 230 kv - $8.7 M Install a 50 MVAR shunt reactor at Aldene 230 kv - $6.9 M Install a 150 MVAR shunt reactor at Camden 230 kv - $8.3 M Install a 150 MVAR shunt reactor at Gloucester 230 kv - $7.8 M Install a 50 MVAR shunt reactor at Clarksville 230 kv - $7.2 M Install a 50 MVAR shunt reactor at Hinchmans 230 kv - $10 M Install a 50 MVAR shunt reactor at Beaverbrook 230 kv - $7 M Install a 50 MVAR shunt reactor at Cox s Corner 230 kv - $7 M Reconfigure the Sewaren 230 kv; Convert the two 138 kv circuits from Sewaren Metuchen to 230 kv circuits including Lafayette and Woodbridge substation; Reconfigure the Metuchen 230 kv station to accommodate the two converted circuits - $101 M Western Region System Upgrades AEP Transmission Zone Reconductor the AEP portion of the Cloverdale Lexington 500 kv line - $40 M Install a 300 MVAR shunt reactor at Dequine 345 kv - $8 M Replace the 150 MVAR shunt reactor at Amos on the Amos to Hanging Rock 765 kv line with a 300 MVAR shunt reactor - $5 M Rebuild the Corner to Degussa 138 kv line - $7.5 M Upgrade the 138 kv line between Harrison and Ross - $40.5 M Rebuild the Pokagon Corey 69 kv line at a double circuit 138 kv line - $65 M Install a new 138/69 kv transformer at George Washington - $7 M Build a new 138/12 kv substation near Nicholsville; Tap the Hydramatic Valley 138 kv circuit (~ structure 415), build a new 138 kv line (~3.75 miles) to this new station; From this station, construct a new 138 kv line (~1.95 miles) to REA s Marcellus station; From REA s Marcellus station construct new 138 kv line (~2.35 miles) to a tap point on Valley Hydramactic 138 kv ckt (~structure 434); Retire sections of the 138 kv line in between structure 415 and 434 (~ 2.65 miles); Retire AEP s Marcellus 34.5/12 kv and Nicholsville 34.5/12 kv stations and also the Marcellus Valley 34.5 kv line - $30 M PJM 2013 Page 3 of 21 PJM DMS #768430

5 Build a new 69 kv line from Hartford to Keeler ; Rebuild the 34.5 kv lines between Keeler - Sister Lakes and Glenwood tap switch to 69 kv (~12 miles); Implement in - out at Keeler and Sister Lakes 34.5kV stations; Retire Glenwood tap switch and construct a new Rothadew station. These new lines will continue to operate at 34.5 kv - $30 M Rebuild the North Delphos to S kv line and upgrade terminal equipment - $22.4 M Build a new 138 kv line from Richlands Station to the intersection of the Hales Branch to Grassy Creek 138 kv line - $28 M APS Transmission Zone Install a 250 MVAR SVC at Squab Hollow 230 kv - $33.5 M Reconfigure the Lake Lynn Lardin 138 kv circuits - $22.9 M Convert the Shingletown 230 kv bus to a six breaker ring bus - $5.5 M Install a 230/138 kv transformer at Squab Hollow and loop the Forest Elko 230 kv line into Squab Hollow and loop the Brookville Elko 138 kv line into Squab Hollow - $16.8 M ATSI Transmission Zone Reconductor the ATSI portion of Howard Brookside 138 kv line - $7.75 M Duquesne Transmission Zone Install a 200 MVAR shunt reactor at Brunot Island 345 kv - $8.65 M Install a 200 MVAR shunt reactor on the future Brunot Island Carson underground 345 kv line - $8.65 M EKPC Transmission Zone Build a new 69 kv line from Mercer County Industrial to Van Arsdell Substation; Construct a new 69 kv switching station ("South Anderson") adjacent to the LGE/KU Bonds Mill substation; Loop the North Springfield - Van Arsdell 69 kv line through South Anderson. Terminate the existing 69 kv to the LGE/KU Bonds Mill substation at South Anderson and establish a second 69 kv from S. Anderson to the LGE/KU Bonds Mill sub; Construct 0.12 miles of 69 kv line from South Anderson to the Powell Taylor distribution substation and serve this substation radially from South Anderson - $6.64 M Southern Region System Upgrades Dominion Transmission Zone Build a new 230 kv line from Dooms to Lexington on existing ROW - $35 M Construct a new 230 kv line from Idylwood to Dulles Toll Road - $32 M PJM 2013 Page 4 of 21 PJM DMS #768430

6 Rebuild the Susquehanna Jenkins 230 kv Line The Susquehanna Jenkins 230 kv, line located in the PP&L transmission zone, is overloaded for several NERC category C3 contingency combinations as well as for the generation deliverability test. A NERC category C3 contingency is a single contingency followed by system adjustments to return all facilities below their normal rating, followed by the loss of a second single contingency. These types of events are often referred to as N-1-1 events. There are several contingency pairs driving the criteria violation on the Susquehanna Jenkins 230 kv. The recommended solution to address the overload is to rebuild the line using a larger conductor. The existing conductor is a 1033 ACSR. The new conductor will be 1590 ACSR. The existing structures will not meet current design standards with the larger conductor and as a result will need to be replaced as part of the scope of this project. The estimated cost for the project is $109.5 million and is expected to be completed by June 1, PJM 2013 Page 5 of 21 PJM DMS #768430

7 Rebuild the Siegfried Frackville 230 kv Line The Siegfried Frackville 230 kv line is overloaded for the loss of the two Montour to Susquehanna 230 kv lines. The Montour Susquehanna 230 kv lines are built on a double circuit tower-line between the two stations. The overload resulting from the loss of the double circuit tower-line is a NERC category C violation. The recommended solution to address the overload is to rebuild the line using a larger conductor. The existing conductor is a 1033 ACSR. The new conductor will be 1590 ACSR. The existing structures will not meet current design standards with the larger conductor and as a result will need to be replaced as part of the scope of this project. The estimated cost for the project is $84.5 million and is expected to be completed by June 1, PJM 2013 Page 6 of 21 PJM DMS #768430

8 Reconfigure the Sewaren Substation The existing Sewaren substation in the PSE&G transmission zone will be reconfigured to address aging infrastructure concerns as well as to address short circuit problems on the 138 kv system. The proposed solution will eliminate the 138 kv bus by converting the two Metuchen to Sewaren 138 kv circuits to 230 kv. In addition to addressing aging infrastructure concerns the project will also address substation vulnerabilities that were hi-lighted during super storm Sandy. The estimated cost of the project is $101 million and is expected to be completed by June 1, PJM 2013 Page 7 of 21 PJM DMS #768430

9 Convert the Pokagon Corey 69 kv line to a Double Circuit 138 kv line The 2013 RTEP identified a number of low voltage and voltage drop violations on several 138 kv busses in the Michigan portion of the AEP transmission zone. The voltage violations are due to the N-1-1 loss of the Corey to Mottsville to East Elkhart 138 kv line followed by the loss of the Bushz to Flowerfield to Valley 138 kv line. The recommended solution to address this NERC category C3 violation is to rebuild the existing Pokagon Corey 69 kv line as a 138 kv double circuit line between Pokagon and Corey. The estimated cost for this upgrade is $65 million and the required in-service date is June 1, PJM 2013 Page 8 of 21 PJM DMS #768430

10 High Voltage in Real-Time Operations The incidence of high voltage alarms during the valley load period have been increasing and are becoming more difficult for operating personnel to manage. The high voltage conditions are being driven by a number of factors including new transmission that has been built to address thermal violations during peak load conditions as well as changes in generation dispatch patterns resulting from the cost of gas resources relative to coal fired resources. System operators have been managing the high voltage conditions by switching off shunt capacitors and adjusting the reactive output of on-line generation. In some cases, these actions have not been sufficient and operators have been forced to switch lightly loaded transmission lines out of service. The map below shows the areas of the system where the high voltage alarms are most common. As part of the 2013 RTEP PJM staff has developed transmission upgrades to address the high voltage conditions. Historical alarm data was reviewed to identify the locations on the system where the problems are most prevalent. Light load power-flow cases were developed based on energy management system snapshots of the system to simulate the conditions seen in real-time operations. Locations were identified where switchable shunt reactive devices could be installed to address the high voltage conditions. The table on the following page summarizes the location, cost and expected in-service date of the shunt reactive devices that are being recommended to address the high voltage conditions. PJM 2013 Page 9 of 21 PJM DMS #768430

11 Upgrade ID Description TO Presented by PJM Staff to the Board Reliability Committee In Service Date Cost Estimate ($M) b MVAR shunt reactor at Brunot Island 345 kv DL 6/1/ MVAR shunt reactor on future Brunot Island b Carson 345 kv circuit DL 6/1/ b2229 Install a 300 MVAR reactor at Dequine 345 kv AEP 12/1/ b2230 b2231 b2232 b2233 Replace existing 150 MVAR reactor at Amos 765 kv substation on Amos N. Proctorville - Hanging Rock with 300 MVAR reactor AEP 6/1/ Install 765 kv reactor breaker at Dumont 765 kv substation on the Dumont - Wilton Center line AEP 12/1/ Install 765 kv reactor breaker at Marysville 765 kv substation on the Marysville - Maliszewski line AEP 6/1/ Change transformer tap settings for the Baker 765/345 kv transformer AEP 6/1/ b MVAR reactor at Monocacy 230 kv APS 6/1/ b MVAR shunt reactor at Mickleton 230 kv and relocate Mickleton # kv transformer AEC 6/1/ b /-100 MVAR SVC at Cedar 230 kv AEC 6/1/ b2234 2x130 MVAR reactor at West Wharton 230 kv JCPL 4/1/ b MVAR reactor at Buckingham 230 kv PECO 12/31/ b MVAR shunt reactor at Alburtis 500 kv PPL 6/1/ b MVAR shunt reactor at Elimsport 230 kv PPL 6/1/ b2279 Add two 100 MVAR reactors at Dickerson Station H and two 100 MVAR reactors at Brighton 230 kv substation PEPCO 6/1/ b MVAR reactor at Saddlebrook 230 kv PSEG 6/1/ b MVAR reactor at Athenia 230 kv PSEG 6/1/ b MVAR reactor at Bergen 230 kv PSEG 6/1/ b MVAR reactor at Hudson 230 kv PSEG 6/1/ b2243 Two 50 MVAR reactors at Stanley Tce 230 kv PSEG 6/1/ b MVAR reactor at West Orange 230 kv PSEG 6/1/ b MVAR reactor at Aldene 230 kv PSEG 6/1/ b MVAR reactor at Camden 230 kv PSEG 6/1/ b MVAR reactor at Gloucester 230 kv PSEG 6/1/ b MVAR reactor at Clarksville 230 kv PSEG 6/1/ b MVAR reactor at Hinchmans 230 kv PSEG 6/1/ b MVAR reactor at Beaverbrook 230 kv PSEG 6/1/ b MVAR reactor at Cox's Corner 230 kv PSEG 6/1/ PJM 2013 Page 10 of 21 PJM DMS #768430

12 Changes to Previously Approved Projects Cost and scope of a number of previously approved RTEP baseline projects have been updated. In addition, a number or projects have been cancelled as they are no longer required. The net result to these changes to previously approved baseline projects is a net increase in the RTEP of $19.7 million. Review by the Transmission Expansion Advisory Committee (TEAC) The results of the analyses summarized in this report were reviewed with the TEAC and Subregional RTEP Committees over several meetings throughout The most recent analysis, along with recommended solution, was reviewed at the September 12, 2013 meeting. Written comments were requested to be submitted to PJM communicating any concerns with the recommendation and any alternative transmission solutions for consideration. As of the writing of this report there have been no comments received on the projects presented to the TEAC. Cost Allocation On October 11, 2012 the PJM Transmission Owners, filed proposed tariff revisions to Schedule 12 of the OATT to modify the methods used for the allocation of costs of transmission upgrades approved pursuant to the RTEP. In an Order issued on January 31, 2013, the FERC conditionally accepted and nominally suspended the proposed cost allocation methods for filing, to be effective February 1, 2013 subject to refund and to a future order in PJM s Order 1000 compliance filing. On July 22, 2013, the PJM Transmission Owners submitted their 2 nd Order No compliance filing in response to the March 22, 2013 Order. A FERC order has yet to be issued on this second compliance filing. Similar to the previous method, the new cost allocation methodology for baseline reliability upgrades has a definition of Regional Facilities that includes A.C. facilities operated at 500 kv or above. In addition it also now includes two A.C. circuits between the same two substations operated at 345 kv and above but less than 500 kv (e.g. 345 kv double circuit towerline). Under the new methodology the cost allocation for Regional Facilities would be assigned 50% on a load ratio share basis and 50% on a use based distribution factor methodology. The cost allocation for lower voltage facilities (i.e. 345 kv single circuit and below) would be based entirely on the use based distribution factor methodology. As was the case with the previous cost allocation method, baseline reliability projects that are expected to cost less than $5 million are allocated entirely to the transmission zone that they are located in. The use based distribution factor methodology is similar to the previous violation based distribution factor methodology in that both use power-flow software to calculate the impact of the load of a transmission zone on a facility. However the cost allocation for a baseline reliability upgrade using the new use based distribution factor methodology is based on the contribution of a transmission zone load to the loading on the new transmission facility. Recall the cost allocation for baseline reliability upgrades under the violation based distribution factor was based on the contribution of a transmission zone to the loading on the overloaded facility (i.e. the facility with the violation) and not the new facility being added to address the overload. PJM 2013 Page 11 of 21 PJM DMS #768430

13 Pursuant to FERC order, the allocations for the recommended baseline reliability upgrades will be developed using the new use based allocation methodology. Board Approval The PJM Board approved all of the recommendations to the 2013 RTEP. PJM 2013 Page 12 of 21 PJM DMS #768430

14 Appendix RTEP Baseline Upgrade Cost Allocation Single Zone Allocations Presented by PJM Staff to the Board Reliability Committee PJM 2013 Page 13 of 21 PJM DMS #768430

15 Appendix RTEP Baseline Upgrade Cost Allocation continued Presented by PJM Staff to the Board Reliability Committee PJM 2013 Page 14 of 21 PJM DMS #768430

16 Appendix RTEP Baseline Upgrade Cost Allocation continued Presented by PJM Staff to the Board Reliability Committee PJM 2013 Page 15 of 21 PJM DMS #768430

17 Appendix RTEP Baseline Upgrade Cost Allocation continued PJM 2013 Page 16 of 21 PJM DMS #768430

18 Appendix RTEP Baseline Upgrade Cost Allocation continued PJM 2013 Page 17 of 21 PJM DMS #768430

19 Appendix RTEP Baseline Upgrade Cost Allocation continued PJM 2013 Page 18 of 21 PJM DMS #768430

20 Appendix RTEP Baseline Upgrade Cost Allocation continued PJM 2013 Page 19 of 21 PJM DMS #768430

21 Appendix RTEP Baseline Upgrade Cost Allocation continued PJM 2013 Page 20 of 21 PJM DMS #768430

22 Appendix RTEP Baseline Upgrade Cost Allocation continued Multiple Zone Allocations PJM 2013 Page 21 of 21 PJM DMS #768430

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic November 04, 2013 2013 RTEP Baseline Analysis Update 11/04/2013 AE Transmission Zone Cost Change for B2354 Install second 230/69kV transformer and 230kV circuit

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee March 7, 2013 1 Issues Tracking 2 Issues Tracking Open Issues None New Issues 3 Stage 1A ARR Transmission Project Update 4 Stage 1A ARR Transmission Project Byron

More information

2013 PJM BASELINE RELIABILITY ASSESSMENT

2013 PJM BASELINE RELIABILITY ASSESSMENT 2013 PJM BASELINE RELIABILITY ASSESSMENT For the 2014-2028 Period Issued - January 13, 2014 Version 2 Introduction INTRODUCTION... 4 EXECUTIVE SUMMARY... 8 KEY FINDINGS... 13 OBJECTIVE AND SCOPE... 18

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic July 26, 2016 Reliability Analysis Update MetEd Transmission Zone N-1 First Energy Planning Criteria (FERC Form 715): The North Boyertown West Boyertown 69 kv is

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee February 7, 2013 1 Issues Tracking 2 Issues Tracking Open Issues None New Issues 3 2013 RTEP Scenario Analysis 4 RTEP Scenario Analysis 2012 North Carolina Transmission

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic September 24, 2014 1 Reliability Analysis Update 2 AE Transmission Zone Generation Deliverability Violation: The Middle 230/69 kv is overloaded for line fault stuck

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee March 6, 2014 1 2014 RTEP Update 2 2014 RTEP Update Initial 2019 Summer base case and corresponding machine list update complete PJM staff has been reviewing and

More information

New Jersey State Report

New Jersey State Report New Jersey State Report July 2017 Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast 2. Markets Capacity Market Results Market Analysis 3. Operations Emissions

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic August 24, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects from the competitive planning

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic December 19, 2017 First Preliminary Review Baseline Reliability and Supplemental Projects 2 The slide was previously presented at 8/31/2017 and is replaced by the

More information

STATE OF NEW JERSEY BOARD OF PUBLIC UTILITIES

STATE OF NEW JERSEY BOARD OF PUBLIC UTILITIES STATE OF NEW JERSEY BOARD OF PUBLIC UTILITIES IN THE MATTER OF THE PETITION OF : PUBLIC SERVICE ELECTRIC AND GAS COMPANY : PURSUANT TO N.J.S.A. 40:55D-19 FROM A : DECISION OF THE CITY OF NEWARK ZONING

More information

Reliability Analysis Update

Reliability Analysis Update Reliability Analysis Update Transmission Expansion Advisory Committee September 15, 2016 2016 RTEP Window #3 Anticipated Scope and Timeline Anticipated 2016 RTEP Window #3 Anticipated 2016 RTEP Window

More information

Sub Regional RTEP Committee - Southern. August 19, 2011

Sub Regional RTEP Committee - Southern. August 19, 2011 Sub Regional RTEP Committee - Southern August 19, 2011 2011 RTEP Analysis Summary 2010 2015 Project Updates 2016 Analysis NERC Category A, B NERC Category C (N-1-1 in progress) Load Deliverability Generator

More information

Generation Deactivation Notification Update

Generation Deactivation Notification Update Generation Deactivation Notification Update Transmission Expansion Advisory Committee November 8, 2018 Generation Deactivations for 2018 2 Generation Deactivation ATSI Transmission Zones Bruce Mansfield

More information

Market Efficiency Update

Market Efficiency Update Market Efficiency Update Transmission Expansion Advisory Committee July 13, 2017 Agenda Where we are in the process Interregional Projects Status RPM Projects Status Reevaluation Analysis Status Next Steps

More information

PJM Regional Transmission Expansion Planning (RTEP) Process

PJM Regional Transmission Expansion Planning (RTEP) Process PJM Regional Transmission Expansion Planning (RTEP) Process IPSAC May 18, 2018 PJM Planning Links Planning Committee (PC) http:///committees-and-groups/committees/pc.aspx Transmission Expansion Advisory

More information

Transmission Expansion Advisory Committee. Reliability Analysis Update

Transmission Expansion Advisory Committee. Reliability Analysis Update Transmission Expansion Advisory Committee Reliability Analysis Update October 8, 2015 Reliability Analysis Update ComEd Transmission Zone Operational Performance Reduce the complexity of the existing Powerton

More information

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016 New Transmission Line April 1, 2016 The enclosed information is proprietary to PSE&G and is provided solely for your use. It should not be copied, reproduced, or shared with others without PSE&G s prior

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

Transmission Expansion Advisory Committee Meeting. April 23, 2008

Transmission Expansion Advisory Committee Meeting. April 23, 2008 Transmission Expansion Advisory Committee Meeting April 23, 2008 PJM 2008 Agenda JCSP Update RTEP reliability baseline update Review initial baseline generator deliverability testing results Review initial

More information

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study Cromby Units 1 and 2 and Eddystone Units 1 and 2 Deactivation Study Original Posting Date: March 2, 2010 Updated May 10, 2010 Updated June 7, 2010 Updated September 7, 2010 General PJM received notice

More information

Reliability Analysis Update

Reliability Analysis Update Reliability Analysis Update Transmission Expansion Advisory Committee October 11, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects

More information

Transmission Expansion Advisory Committee Meeting 2014 Market Efficiency Analysis

Transmission Expansion Advisory Committee Meeting 2014 Market Efficiency Analysis Transmission Expansion Advisory Committee Meeting 2014 Market Efficiency Analysis September 02, 2014 Objectives To review simulated congestion results for all Market Efficiency study years To provide an

More information

Designated Entity Pre-Qualification Materials. Exelon Corporation

Designated Entity Pre-Qualification Materials. Exelon Corporation Designated Entity Pre-Qualification Materials By Exelon Corporation On behalf of its affiliates Baltimore Gas and Electric Company, Commonwealth Edison Company, PECO Energy Company and Exelon Transmission

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic March 23, 2018 First Review Baseline Reliability and Supplemental Projects 2 AEC Transmission Zone: Supplemental Project 69/12kV Wenonah Substation Retire/Bypass

More information

Manual 3: Transmission Operations Updates Version 52

Manual 3: Transmission Operations Updates Version 52 Manual 3: Transmission Operations Updates Version 52 Liem Hoang Sr. Lead Engineer, Transmission Operations Review Timeline Manual First Reads: November 2 nd SOS Joint November 2 nd SOS-T (Section 5 only)

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

Reliability Analysis Update

Reliability Analysis Update Reliability Analysis Update Transmission Expansion Advisory Committee February 8, 2018 2018 RTEP Analysis Update 2 PSE&G Transmission Zone Transmission Service Update 3 Linden VFT Previous agreements:

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012 First Energy Generator Deactivation Request - January 2012 Deactivation Study Results and Required Upgrades April 25, 2012 General PJM received a notice on January 26, 2012 from FirstEnergy of its intent

More information

2017 Indiana State Infrastructure Report (January 1, 2017 December 31, 2017)

2017 Indiana State Infrastructure Report (January 1, 2017 December 31, 2017) 2017 Indiana State Infrastructure Report (January 1, 2017 December 31, 2017) May 2018 This report reflects information for the portion of Indiana within the PJM service territory. Table of Contents 1.

More information

Sub-Regional RTEP Committee PJM South

Sub-Regional RTEP Committee PJM South Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates

More information

Manual 3: Transmission Operations Updates Version 52

Manual 3: Transmission Operations Updates Version 52 Manual 3: Transmission Operations Updates Version 52 Yuri Smolanitsky Sr. Engineer, Transmission Operations Review Timeline Manual First Reads: October 4 th SOS Joint November 2 nd SOS-T (Section 5 only)

More information

Generation Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position Y Linden 138 kv & 230 kv

Generation Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position Y Linden 138 kv & 230 kv Generation Interconnection Feasibility Study Report For PJM Generation Interconnection Request Queue Position Y3-051 Linden 138 kv & 230 kv September / 2013 PJM Interconnection 2013. All rights reserved.

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PSE&G System Characteristics New Jersey utility characterized by densely populated

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Market Efficiency Update

Market Efficiency Update Market Efficiency Update Transmission Expansion Advisory Committee October 12, 2017 Market Efficiency Proposal Window 2016-2017 Long Term Proposal Window 1A 2 2016-2017 Long Term Proposal Window 1A Addendum

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee January 9, 2014 1 2014 RTEP Assumptions (Continued from December 2013 TEAC) 2 RTEP - 2019 Model Status Case currently out to TO s for second review Case distributed

More information

Reliability Analysis Update

Reliability Analysis Update Reliability Analysis Update Transmission Expansion Advisory Committee December 15, 2016 Clean Power Plan (CPP) Reliability Studies CPP Planning Background Provide a representative overview of the types

More information

4.7: New Jersey RTEP Overview

4.7: New Jersey RTEP Overview State RTEP Overview Section PJM DE DC IL IN KY MD MI NJ NC OH PA TN VA WV.7: New Jersey RTEP Overview MAP.26: PJM Service Area in New Jersey PJM operates the electric transmission system for the delivery

More information

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Local Transmission Plan. October 11, 2013 Revised August 25, 2014 Local Transmission Plan October 11, 2013 Revised August 25, 2014 2 Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated

More information

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Western Region ATSI Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these

More information

SERTP rd Quarter Meeting

SERTP rd Quarter Meeting 2015 SERTP SERTP 2015 3 rd Quarter Meeting 2nd RPSG Meeting September 24 th, 2015 APC Headquarters Birmingham, AL 2015 SERTP Process Information The SERTP process is a transmission planning process. Please

More information

Market Efficiency RTEP Proposal Window

Market Efficiency RTEP Proposal Window Market Efficiency RTEP Proposal Window Market Efficiency RTEP Proposal Window Status Window opened on 8/12/2013 Closed on 9/26/2013 17 individual proposals addressing congestion from Market Efficiency

More information

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection

More information

Market Efficiency RTEP Proposal Window

Market Efficiency RTEP Proposal Window Market Efficiency RTEP Proposal Window Market Efficiency RTEP Proposal Window Status Window opened on 8/12/2013 Closed on 9/26/2013 17 individual proposals addressing congestion from Market Efficiency

More information

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Status of PNM s Completed Transmission Construction Projects 11/30/2017 Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information

More information

Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board

Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board PJM Staff Whitepaper October 2017 EXECUTIVE SUMMARY On July 25, 2017 the PJM Board of Managers approved changes to the

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

Market Efficiency Update

Market Efficiency Update Market Efficiency Update Transmission Expansion Advisory Committee December 13, 2018 2018/19 Long Term Window 2 2018/19 Long Term Window Problem Statement and Eligible Congestion Drivers posted on the

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016 New Transmission Line November 15, 2016 The enclosed information is proprietary to PSE&G and is provided solely for your use. It should not be copied, reproduced, or shared with others without PSE&G s

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

Energy Policy Implications: PJM Planning

Energy Policy Implications: PJM Planning Energy Policy Implications: PJM Planning Chicago, Illinois November 14, 2012 Steven R. Herling Vice President, Planning PJM Interconnection PJM as Part of the Eastern Interconnection 26% of generation

More information

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028. Merchant Transmission Interconnection PJM Impact Study Report For PJM Merchant Transmission Request Queue Position X3-028 Breed 345 kv October/2014 System Impact Study Breed 345 kv Merchant Transmission

More information

PJM SRTEP Meeting Questions Pertaining to Proposed Projects & Scopes AEP: Ambler Ridge:

PJM SRTEP Meeting Questions Pertaining to Proposed Projects & Scopes AEP: Ambler Ridge: PJM SRTEP Meeting 2-13-2018 Questions Pertaining to Proposed Projects & Scopes AEP: Ambler Ridge: The problem statement states two 138kV CB s will be installed at Ambler Ridge, however the potential solution

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Reliability Analysis Update

Reliability Analysis Update Reliability Analysis Update Transmission Expansion Advisory Committee January 11, 2018 2017 RTEP Analysis Update 2 Generation Deliverability (Summer) (GD-S798 and GD- S815): Problem Statement: The Edge

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic May 25, 2018 First Review Baseline Reliability and Supplemental Projects 2 Aging Infrastructure The 20.7 mile Five Forks Windy Edge 110511/110512 115kV Circuit

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

Market Efficiency Update

Market Efficiency Update Market Efficiency Update Transmission Expansion Advisory Committee August 10, 2017 Where we are - Market Efficiency Timeline 2 2016-2017 Window Market Efficiency Base Case Mid-Cycle Update Base case to

More information

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC OCTOBER 17, 2018 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC

More information

Pennsylvania State Report

Pennsylvania State Report July 2016 Pennsylvania State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

2018 PJM BASELINE RELIABILITY ASSESSMENT

2018 PJM BASELINE RELIABILITY ASSESSMENT 2018 PJM BASELINE RELIABILITY ASSESSMENT For the 2018-2033 Period Issued - January 30, 2019 Version 1 Introduction Introduction...3 Executive Summary... 7 Key Findings...12 Objective and Scope...15 Analysis

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

Local Transmission Plan. Rev. 1: April 2018

Local Transmission Plan. Rev. 1: April 2018 Local Transmission Plan Rev. 1: April 2018 1 Central Hudson s Service Territory Own & Operate approximately 610 miles of 69 kv, 115 kv & 345 kv transmission lines and three 345 kv substations 2 Central

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions. March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating

More information

2013 ANNUAL PROGRESS REPORT

2013 ANNUAL PROGRESS REPORT March 1, 2013 Mr. David Franklin, Chairman WECC Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768-2560 Mr. Enoch Davies WECC Technical Staff 155 North 400 West,

More information

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 14, 2005 1 2004-06 EGSI-TX Transmission Western Region Reliability

More information

New Services Queue Network Upgrades

New Services Queue Network Upgrades New Services Queue Network s September 2009 TEAC AEC Queue Number T84 Project Name Corson 138kV MWC MWE Fuel Type 70 350 Wind T146 England 69.2 346 Wind U1-056 U1-066 Lewis 138kV Carlls Corner 69kV 45.5

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

SPP Notification to Construct

SPP Notification to Construct February 19, 2014 SPP Notification to Construct Mr. Mo Awad Westar Energy, Inc. P.O. Box 889 Topeka, KS 66601 RE: Notification to Construct Approved Reliability Network Upgrades Dear Mr. Awad, Pursuant

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT

More information

Appendix B. Summary of Changes to the Year Assessment

Appendix B. Summary of Changes to the Year Assessment Appendix B Summary of Changes to the 2003 10- Assessment For the below tables, the following color-coding scheme was utilized for indicating what type of change has been made to the 10- Assessment from

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Sub Regional RTEP Committee - Southern

Sub Regional RTEP Committee - Southern Sub Regional RTEP Committee - Southern March 03, 2011 www.pjm.com 2010 RTEP Analysis Summary Review of ongoing projects Stakeholder request 2015 Analysis Update Review of NOVA Reliability Deficiencies

More information

Impacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities

Impacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities Impacts of MISO DPP-2016-February (West, ATC, MI, South) 1. MISO generators studied: Projects on PJM Facilities Net MW size (Summer) Net MW size (Winter) Service DPP Project Type Region Fuel Type POI J432

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

EXCEPTIONS TO RELIABILITY RULES Revision 11 February 9, 2018

EXCEPTIONS TO RELIABILITY RULES Revision 11 February 9, 2018 1 NYPA Run Back of EXCEPTIONS RELIABILITY RULES Revision 11 February 9, 2018 Post Contingency Flow on Marcy-New Scotland The post-contingency flow on the Marcy-New Scotland 18 line is allowed to exceed

More information

Subregional RTEP Committee Mid-Atlantic Area. September 9, 2008

Subregional RTEP Committee Mid-Atlantic Area. September 9, 2008 Subregional RTEP Committee Mid-Atlantic Area September 9, 2008 PJM 2008 PJM 2008 JCPL N-2 Baseline Upgrades JCPL N-2 Baseline Upgrades - Werner Raritan River 115 kv line / loss of Smithburg-Englishtown

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

APPENDIX F: Project Need and Description

APPENDIX F: Project Need and Description APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC

More information

Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects

Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects Entergy Texas, Inc. Transmission 2014 2018 Draft Construction Plan Update 1 Projects 1 2014-2018 ETI Draft Construction Plan Update 1 Projects Completed in the Fall of 2012 & 2013 to date 1) Cedar Hill

More information

SERTP rd Quarter Meeting

SERTP rd Quarter Meeting 2014 SERTP SERTP 2014 3 rd Quarter Meeting 2 nd RPSG Meeting September 30 th, 2014 APC Headquarters Birmingham, AL 2014 SERTP Process Information The SERTP process is a transmission planning process. Please