SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

Size: px
Start display at page:

Download "SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN"

Transcription

1 SPN High Value Project PO Route RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

2 Document History Version Date Details Originator V0.1 20/06/2013 Initial version Chris Winch V0.2 23/06/2013 Updates and clarifications Mark Fitch V0.3 24/06/2013 Further clarifications Mark Fitch V1.0 24/06/2013 Draft for review Tendai Matiringe V1.1 24/06/2013 Minor revisions to options description Chris Winch 1

3 EXECUTIVE SUMMARY The preferred approach is to create a new Grid Supply Point to supply Lewes Grid before the single circuit PO route is dismantled. This requires National Grid to construct and commission a new GSP at Horsted Green, installing two 400/132kV transformers and two 132kV circuit breakers (estimated between 14.7 to 16.3M). Lewes Grid would be connected to this new GSP via two new 132kV underground circuits from Horsted Green to Lewes Grid with outdoor 132kV sealing ends at Lewes Grid and at the new GSP. In addition one new 132kV circuit breaker would be added at Lewes Grid on the existing PLB line from Fishersgate to connect in the additional circuit. This allows the dismantling of towers PO86 to PO16 (a rural section under threat from wayleave termination) that run through the National Park. The estimate total cost of the project is 37.2M ( 31.4M in ED1), the lowest cost of all the estimated options. The main drivers for the preferred approach are: o Avoid the need to asset replace the existing single circuit overhead line between Eastbourne and Lewes (Route PO) o Maintain P2/6 Licence compliance to the Lewes and Newhaven group o Avoid the significant risk to land rights to maintain the existing PO Route as a single circuit and the resulting impact on security of supply if rights are terminated o Avoid the need to negotiate a change to the existing rights to allow the route to be rebuilt as double circuit to support load growth The major benefits of preferred approach: o Removal of an overhead line route from a National Park/ area of outstanding natural beauty a key issue for our stakeholders o Reinforcement supports future load growth in the Lewes/Newhaven demand group o Deferral of reinforcement at the adjacent Bolney and Ninfield GSPs BACKGROUND The Lewes - Eastbourne 132kV single circuit tower line is 22 kilometres in length comprising 86 towers and is routed parallel to the south coast. Condition surveys have confirmed the need to asset replace the overhead line due to deteriorating condition. The route traverses the South Downs National Park and works are subject to intense scrutiny to minimise the visual impact of the rebuilt line or its replacement on Areas of Outstanding Natural Beauty (AONBs) through which it passes. This is coupled with escalating initiatives by lobby groups to protect Special Sites of Scientific Interest (SSSI s). These environmental pressures represented a threat to the security of the route and any replacement. 2

4 Any rebuilding, even partial tower rebuilds in the National Park would require permission from the Local Authorities, the Department of Energy and Climate Change (DECC), National Park Land and the Infrastructure Planning Commission, and it is uncertain if this will be granted. The rebuilding of the line was part of our plans in DPCR5. This was for the line to be rebuilt as a double circuit tower line. At that time the group demand was growing, but somewhat below the limit for group demand supplied by the existing two circuits. The works on the circuit could not go ahead because of a number of existing wayleave terminations affecting the rural section. These include two claims in span PO39-PO40, another two claims in PO39-PO38 and one in section PO37-PO36. There is also a threat of termination in span PO42-PO43 although this claim is presently not being pursued by the landowner on the understanding that UK Power Networks is intending to remove the overhead line in the near future. Action has been taken to maintain the integrity of the route while the solution to the wayleave issues has been progressed. Refurbishment work completed in August 2010 replaced rusting tower members and has prolonged the service life by a period of approximately 10 years to 2021, subject to continuous condition monitoring. Further refurbishment works on the route is being undertaken to main the integrity of the line during DPCR5. Description /2012 /2013 /2014 /2015 PO Route Tower Refurbishment (PO16 to 86) The loss of rights to maintain the PO route is a high risk, with landowners anticipating the dismantlement of the line and wayleaves are unlikely to be renewed. The loss of this route would bring an immediate security of supply issues for the Lewes-Newhaven demand group. While we take action to mitigate this risk we are also considering how we fulfil demand growth into the future for the Lewes and Newhaven demand group. Rebuilding or replacing the route in its current single-circuit form would be ineffective in meeting future growth in demand. Further works would be required to support the Lewes-Newhaven demand group to provide security of supply in the future to maintain compliance with Engineering Recommendation P2/6 with the current transfer capability, this may be in ED2 or beyond. The peak winter group demand is 103MW which is forecast to increase to 107W by 2023 (Table 1 refers). Table 1: Extract from CV102 Substation Primary Voltage Secondary Voltage Substation firm capacity under single circuit outage conditions Assessed contribution towards security supply from DG adjustment "Significant" measurable embedded generation adjustment to maximum demand Max demand (MVA) Substation (kv) (kv) MVA MVA (+) MVA (+/-) 2011/ /23 Lewes Grid Newhaven Grid Total

5 The demand group supplied from Lewes 132kV substation is connected by two single circuit overhead line connections one from Eastbourne (Route PO) and one from Southern Cross (Route PLB). Newhaven demand is connected via two 132kV transformer feeders onward connected from Lewes. The Southern Cross to Lewes PLB route, also crosses that National Park, is of single circuit construction and we would be similarly unlikely to gain permissions to make this a double circuit route. The geographical and network configurations are shown in the Figures below. Figure 1: Geographical Configuration Little Horsted Double circuit 400kV OHL PLB ROUTE: Single circuit 132kV OHL PO ROUTE: Single circuit 132kV OHL Mile Oak Arlington South Downs National Park Note: 400kV routes in red, 132kV routes in green and 33kV routes in pink. Indication of National Park boundaries in light blue shading. The exact boundaries are shown below. Figure 2: National Park Boundaries 4

6 Figure 3: Lewes Newhaven network configuration Figure 4: Route PO The options considered seek to remove the risk of the loss of the PO route and to accommodate the future load growth and security of supply requirements for the Lewes- Newhaven demand group.. SUMMARY OF THE ALTERNATIVES CONSIDERED Previously considered option The rebuilding of the line (estimated at 17.1M) was part of our plans in DPCR5. This was for the line to be rebuilt as a double circuit tower line. The works on the circuit could not go ahead because of a number of existing wayleave terminations affecting the rural section. Investigations to utilise insulated cross-arm new technology to lower the line profile but, based on recent experience, renegotiating permissions to rebuild this route it is considered to have a low probability of success. Reinforcement considerations has increased the importance of finding a solution to securing future supplies to this demand group and four options have been considered: Option 1 Do Nothing. Rejected due to deteriorating condition of the overhead line and requirement to reinforce the Lewes / Newhaven group Option 2 Phased replacement of the single circuit tower route PO86 to PO16 with two underground cable circuits from Lewes Grid to tower PXB6 through the following stages: 1. Replace top half of the towers and cable the PO circuit in Polegate in period

7 2. Uprate 9.6km of 33kV cable between Moulsecoomb, Rottingdean and Newhaven in to enable Seaford to be recovered under N-2 conditions 3. Replace 132kV circuit from Mile Oak to Southern Cross in 2028 to increase the N-1 firm capacity of the group 4. Complete the replacement of the route from Lewes Grid to tower PXB6 in period with a double underground cable circuit to maintain N-2 compliance Estimated cost M Access permissions are expected to introduce significant delivery risk due to disruption to landowners. Work on the existing towers is likely to accelerate the terminations on the existing Wayleaves. Option 3 Replace part of the PO single circuit route with a one 132kV underground cable circuit and one spare duct from Lewes to tower PXB6, followed by installation of the second 132kV underground cable circuit along the same route M Replace tower PXB6 with a terminal L4 type tower and install outdoor sealing ends at Lewes Grid To support the N-2 recovery of half of Seaford before commissioning of the two cable circuits, replace 1km of 33kV cable section between Moulsecoomb and Rottingdean Dismantle the towers PO86 to PO16 Option 3 carries similar risks to Option 1. Option 4 - Create a new GSP to supply Lewes Grid before the single circuit PO route is dismantled - is 37.2M National Grid to construct and commission a new GSP at Horsted Green, install two 400/132kV transformers and two 132kV circuit breakers (estimated between 14.7 to 16.3M by National Grid) UK Power Networks to: Install two new 132kV underground circuits from Horsted Green to Lewes Grid Install four outdoor 132kV sealing ends (2 at Lewes Grid & 2 at the new GSP) and one new 132kV circuit breaker at Lewes Grid on PLB line Dismantle towers PO86 to PO16 SUMMARY OF PROPOSED STRATEGY The preferred approach is to create a new Grid Supply Point to supply Lewes Grid before the single circuit PO route is dismantled. This requires National Grid to construct and commission a new 2x240MVA 400/132kV substation in the vicinity of Little Horsted, East Sussex. The substation will: 6

8 - Avoid the need to asset replace the existing single circuit overhead line between Eastbourne and Lewes - Route PO - Maintain P2/6 Licence compliance to the Lewes and Newhaven group - Facilitate future reinforcement and re-configuration of the local network - Increase capacity headroom and therefore defer the need for future reinforcement at the adjacent Bolney and Ninfield GSPs A feasibility study undertaken with National Grid confirms the viability of establishing the new GSP adjacent to their existing 400kV double circuit south coast overhead line. The UK Power Network project deliverables are: - New switch house equipped with a two section GIS switchboard - 132kV double circuit cable connection between Little Horsted and Lewes substation - An additional 132kV switch panel at Lewes - Dismantlement of sections of Route PO The estimated cost and phasing of the works are 37.2M ( 31.4M in ED1): Description 2011 / / / / / / / / / /2021 PO Route Replacement Strategy ,176 4,498 5,245 6,366 6,291 5,837 4,821 2,876 MAJOR RISKS, ASSUMPTIONS, ISSUES & DEPENDENCIES Risks o Land purchase and planning permission at Little Horsted o National Grid outage constraints to connect the new super grid transformers o Street service congestion impacting on the open-cut cable route to Lewes 7

Proposed Dounreay - Mybster 275 kv / 132 kv

Proposed Dounreay - Mybster 275 kv / 132 kv Background Scottish Hydro-Electric Transmission Ltd (SHETL) is proposing a new 275 kilovolt (kv) (1 kilovolt = 1000volts) double circuit overhead line (OHL) between the Dounreay sub station and the new

More information

Powering Sydney s Future

Powering Sydney s Future Powering Sydney s Future Frequently Asked Questions December 2017 Project background Q: Why is this project needed? A: Inner Sydney is one of the most critical parts of the NSW electricity network. However,

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

DFO STATEMENT OF NEED REPORT

DFO STATEMENT OF NEED REPORT APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading

More information

The Grid Link Project. Summary of the Report for the Independent Expert Panel

The Grid Link Project. Summary of the Report for the Independent Expert Panel The Grid Link Project Summary of the Report for the Independent Expert Panel Who are EirGrid - and what do we do? EirGrid is responsible for a safe, secure and reliable supply of electricity: now and in

More information

ATTACHMENT - DFO STATEMENT OF NEED

ATTACHMENT - DFO STATEMENT OF NEED ATTACHMENT - DFO STATEMENT OF NEED Table of Contents Executive Summary... 3 1. Description of the Area... 5 1.1 Geographic Study Area... 5 1.2 Current System Configuration... 7 1.3 Distributed Generation...

More information

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test: Salisbury Substation 11kV Feeders DISCLAIMER The purpose of this document is to inform customers, Interested Parties,

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

SUPPLEMENTARY EVIDENCE FROM SCOTTISH AND SOUTHERN ENERGY

SUPPLEMENTARY EVIDENCE FROM SCOTTISH AND SOUTHERN ENERGY SUPPLEMENTARY EVIDENCE FROM SCOTTISH AND SOUTHERN ENERGY Scottish Parliament - Economy, Energy & Tourism Committee National Planning Framework - Evidence Session 14 th January 2009 SHETL Response 1. Key

More information

Asset Category Batteries LPN

Asset Category Batteries LPN Asset Category Batteries LPN Asset Stewardship Report 2013 Brian Matthews Approved by Richard Wakelen / Barry Hatton Approved date 03.06.2013 / 04.06.2013 Document Management and Governance by Victoria

More information

Generation Connections Industry Workshop 2017

Generation Connections Industry Workshop 2017 Generation Connections Industry Workshop 2017 1 Introduction- Topics to be covered Background: SONI & NIE Networks Generation Connections Guide Renewable Generation Update Phase 1 Review UR Connections

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007 High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

Building a 21 st Century Electric Grid. February 23, 2018

Building a 21 st Century Electric Grid. February 23, 2018 Building a 21 st Century Electric Grid February 23, 2018 1 DTE strives to provide customers with a 21 st century electric grid that is safe, highly reliable, affordable and accessible 2 Our investment

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd 2016-20 Electricity Distribution Price Review Regulatory Proposal Revocation and substitution submission Attachment 7-14 Revised Flemington network development strategy

More information

The Energy Queensland Group Notice of no non-network options

The Energy Queensland Group Notice of no non-network options The Energy Queensland Group Notice of no non-network options 24 September 2018 MCE Mount Crosby East Establish new substation to replace Mount Crosby Substation (SSMTC) Page 1 of 1 DISCLAIMER While care

More information

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document Decision 2013-127 Alberta Electric System Operator Saleski Transmission Project Needs Identification Document ATCO Electric Ltd. Saleski 901S Substation and 144-kV Transmission Line 7L142 Facility Application

More information

Energy from Waste Grid Connections

Energy from Waste Grid Connections Energy from Waste Grid Connections Catherine Cleary Grid Connection Lead TNEI Services catherine.cleary@tnei.co.uk 0161 233 4839 Overview Introduction to the UK Electricity Network Key Grid Connection

More information

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8 Header Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations RT 007-11 Balhannah and Uraidla - Final Draft Page 1 of 8 DISCLAIMER The purpose of this document is to inform customers,

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

Flexible Distributed Generation. FDG-F Burwell (EPN) May 2017

Flexible Distributed Generation. FDG-F Burwell (EPN) May 2017 Flexible Distributed Generation FDG-F Burwell (EPN) May 2017 Principles of Flexible Distributed Generation A Flexible DG connection is a technical and commercial agreement where a generator is allowed

More information

Electricity industry structure and key players

Electricity industry structure and key players Electricity industry structure and key players Growth in capacity, production and consumption, 2006 2017 Expected demand and addition to generation capacity, 2018 2027 Growth in transmission network and

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd (Vic) Ltd 2016-20 Electricity Distribution Price Review Regulatory Proposal Revocation and substitution submission Attachment 7-11 WSP Parsons Brinckerhoff - Independent review of Sunbury development strategy

More information

INCREASING electrical network interconnection is

INCREASING electrical network interconnection is Analysis and Quantification of the Benefits of Interconnected Distribution System Operation Steven M. Blair, Campbell D. Booth, Paul Turner, and Victoria Turnham Abstract In the UK, the Capacity to Customers

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, 2006 SUBJECT: Scarborough Rt Strategic Plan RECOMMENDATIONS It is recommended that the Commission: 1. Endorse

More information

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat Galapagos San Cristobal Wind Project VOLT/VAR Optimization Report Prepared by the General Secretariat May 2015 Foreword The GSEP 2.4 MW Wind Park and its Hybrid control system was commissioned in October

More information

Recharge the Future Interim Findings

Recharge the Future Interim Findings Recharge the Future Interim Findings Jack Lewis Wilkinson, Smart Grid Development Engineer, UK Power Networks Celine Cluzel, Director, Element Energy Tristan Dodson, Senior Consultant, Element Energy 1

More information

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Western Region ATSI Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Powerco CPP Portfolio Overview Document

Powerco CPP Portfolio Overview Document Putaruru-Tirau Cable Powerco CPP Portfolio Overview Document Portfolio Name Expenditure Class Expenditure Category Putaruru-Tirau Cable Capex Growth & Security As at Date 12 June 2017 Expenditure Forecast

More information

Port Hacking cable crossing project Community engagement and feedback summary August 2016

Port Hacking cable crossing project Community engagement and feedback summary August 2016 Port Hacking cable crossing project Community engagement and feedback summary August 2016 For period from April 2016 to 12 August 2016 1 Contents Contents... 2 1 Project background... 3 1.1 Project options...

More information

RIIO-T2 Energy Scenarios

RIIO-T2 Energy Scenarios RIIO-T2 Load 20 th September 2018 RIIO-T2 Energy Scenarios 1 RIIO-T2 Energy Scenarios RIIO-T2 Context Jim Sutherland RIIO-T2 Project Director 2 The RIIO Framework Ofgem s framework for setting price controls

More information

2015 Grid of the Future Symposium

2015 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82 Decision 21447-D01-2016 August 23, 2016 Decision 21447-D01-2016 Proceeding 21447 Application 21447-A001 August 23, 2016 Published by the: Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary,

More information

EMERGING REQUIREMENTS

EMERGING REQUIREMENTS EB-00-0 Exhibit D Schedule Page of EMERGING REQUIREMENTS 0 EQUIPMENT STANDARDIZATION THESL plans, designs and constructs distribution system assets in accordance with approved standards. The standards

More information

NETWORK DEVELOPMENT ACHIEVING. Assessing the need for network development. Non-regulated customer connections POWERLINK ANNUAL REPORT 2011/12

NETWORK DEVELOPMENT ACHIEVING. Assessing the need for network development. Non-regulated customer connections POWERLINK ANNUAL REPORT 2011/12 POWERLINK 25 NETWORK DEVELOPMENT ACHIEVING completed four major regulated (prescribed) transmission network development projects to replace transmission equipment reaching the end of its useful life completed

More information

Chirmorie Wind Farm Grid Connection

Chirmorie Wind Farm Grid Connection Chirmorie Wind Farm Grid Connection Welcome Welcome to this public exhibition regarding our proposals to construct a new 132 kilovolt (kv) overhead line (OHL) supported by wood poles to connect the proposed

More information

Powerco CPP Portfolio Overview Document

Powerco CPP Portfolio Overview Document Powerco CPP Portfolio Overview Document Portfolio Name Palmerston North CBD Reinforcement Expenditure Class Capex Expenditure Category Growth & Security As at Date 12 June 2017 Expenditure Forecast 1,2

More information

Modernising the Great Western railway

Modernising the Great Western railway Report by the Comptroller and Auditor General Department for Transport and Network Rail Modernising the Great Western railway HC 781 SESSION 2016-17 9 NOVEMBER 2016 4 Key facts Modernising the Great Western

More information

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND

More information

Sale of land at Old Quarry site, Westmount Gardens to Jersey Electricity plc for creation of electricity substation

Sale of land at Old Quarry site, Westmount Gardens to Jersey Electricity plc for creation of electricity substation Sale of land at Old Quarry site, Westmount Gardens to Jersey Electricity plc for creation of electricity substation For consideration by the Parish Assembly on 27 November 2013 at 7.00pm PARISH OF ST HELIER

More information

SONI LTD TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT

SONI LTD TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT SONI LTD TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT 14 TH MARCH 2008 TABLE OF CONTENTS Page 1 Introduction...1 2 Charging Methodology Objectives...3 3 Connection Charging Methodology...4 4

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Bohn to Kettle River Transmission Project

Bohn to Kettle River Transmission Project April 2012 Why are you receiving this project information package? New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta Electric System Operator

More information

THE PROTEAN AND POC-MAST DESIGN

THE PROTEAN AND POC-MAST DESIGN THE PROTEAN AND POC-MAST DESIGN Contents 1. The changing landscape of generation for power transmission and distribution. 2. The Holford rules and recommendations for OHL routing and design. 3. The current

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Smart EV Managed Charging

Smart EV Managed Charging Smart EV Managed Charging Temporary management of the low voltage network Bob Hopkins, SSEN Daniel Hollingworth, EA Technology SSEN overview Scottish and Southern Electricity Networks owns: two electricity

More information

Reinforcement to the North Shropshire Electricity Distribution System. Updated Strategic Options Report. November 2017

Reinforcement to the North Shropshire Electricity Distribution System. Updated Strategic Options Report. November 2017 Reinforcement to the North Shropshire Electricity Distribution System Updated Strategic Options Report November 2017 Contents 1 Introduction... 2 2 The Need for the Reinforcement of the 132kV Network...

More information

Emerald Reactive Support Alternative Solution Expressions of interest

Emerald Reactive Support Alternative Solution Expressions of interest Emerald Reactive Support Alternative Solution Expressions of interest Publishing Date 21/02/2017 Closing Date 21/03/2017 1. Executive Summary Ergon Energy Corporation Limited (EECL) is seeking expressions

More information

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 TODAY WE LL TALK ABOUT Our challenges and how we re meeting them Why we re building this project Our planning process and considerations

More information

City Power Johannesburg: Response to Potential Load Shedding. Presented by : Stuart Webb General Manager : PCM October 2014

City Power Johannesburg: Response to Potential Load Shedding. Presented by : Stuart Webb General Manager : PCM October 2014 City Power Johannesburg: Response to Potential Load Shedding Presented by : Stuart Webb General Manager : PCM October 2014 Topics to be discussed Background Challenges Options Available Summary 2 Background

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016 Decision 21481-D01-2016 October 18, 2016 Alberta Utilities Commission Decision 21481-D01-2016 Proceeding 21481 Application 21481-A001 October 18, 2016 Published by the: Alberta Utilities Commission Fifth

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA Submission of Indicated New York Transmission Owners For Authority to Construct and Operate Electric Transmission Facilities in Multiple Counties in New York Case 13-M-0457 Edic to New Scotland 345 kv

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

The Isle of Gigha Flow Battery Project

The Isle of Gigha Flow Battery Project The Isle of Gigha Flow Battery Project S D Wilson and J N Baker, EA Technology J Samuel, Renewable Energy Dynamics Technology. Presentation to All-Energy 2014, Aberdeen, Thursday 22 nd May 2014. Content

More information

Renewable Generation Electrical Infrastructure and Grid Connection Services Provided by Power Systems Project and Consultancy Services (PCS) Ltd

Renewable Generation Electrical Infrastructure and Grid Connection Services Provided by Power Systems Project and Consultancy Services (PCS) Ltd Renewable Generation Electrical Infrastructure and Grid Connection Services Provided by Power Systems Project and Consultancy Services (PCS) Ltd Power Systems Project and Consultancy Services (PCS) Ltd

More information

Building the Business Case for Energy Storage

Building the Business Case for Energy Storage Building the Business Case for Energy Storage A viable and economical alternative power supply solution Unrestricted Siemens AG 2015 All Rights Reserved. March 2015 Siemens.en/siestorage Seconds Minutes

More information

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION Presentation by Engr. O. C. Akamnnonu Chief Executive Officer, Ikeja Electricity Distribution Company AGENDA WORK THROUGH

More information

Kettle River Transmission Project

Kettle River Transmission Project April 2012 Why are you receiving this project information package? New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta Electric System Operator

More information

CHAPTER 8 - GAS AND ELECTRICITY TRANSMISSION COMPARATIVE CASE STUDY

CHAPTER 8 - GAS AND ELECTRICITY TRANSMISSION COMPARATIVE CASE STUDY CHAPTER 8 - AS AND ELECTRICITY TRANSMISSION COMPARATIVE CASE STUDY Summary This chapter presents a cost analysis of building gas and electricity transmission infrastructure to support a 1,000 MW combined-cycle

More information

RENEWABLES INTEGRATION STATUS REPORT

RENEWABLES INTEGRATION STATUS REPORT RENEWABLES INTEGRATION STATUS REPORT NORTHERN IRELAND ELECTRICITY Ltd SYSTEM OPERATOR FOR NORTHERN IRELAND Ltd. June 2015 1. INTRODUCTION The electricity network in Northern Ireland (NI) is facing an unprecedented

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Local Transmission Plan. October 11, 2013 Revised August 25, 2014 Local Transmission Plan October 11, 2013 Revised August 25, 2014 2 Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated

More information

TERRACE TO KITIMAT TRANSMISSION (TKT)

TERRACE TO KITIMAT TRANSMISSION (TKT) TERRACE TO KITIMAT TRANSMISSION (TKT) January 2014 OVERVIEW The need: Replace transmission lines between Terrace and Kitimat Options being studied by BC Hydro Discussion 2 SITUATION Kitimat area supplied

More information

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT

More information

New Mexico Transmission Expansion Concepts For Wind Resources

New Mexico Transmission Expansion Concepts For Wind Resources New Mexico Transmission Expansion Concepts For Wind Resources May 2008 Update Electric Services Transmission Operations FOREWORD This document contains PNM s latest concepts for expanding the transmission

More information

Document 21 Asset Category Batteries LPN

Document 21 Asset Category Batteries LPN Document 21 Asset Category Batteries LPN Asset Stewardship Report 2014 Brian Matthews UK Power Networks (Operations) Limited. Registered in England and Wales. Registered No. 3870728. Registered Office:

More information

welcome to the BC Hydro community open house

welcome to the BC Hydro community open house welcome to the BC Hydro community open house Dawson Creek/ Chetwynd Area Transmission ProjecT Open House welcome Dawson Creek/Chetwynd Area Transmission Project (DCAT) The purpose of this open house is

More information

The Grid West project - Summary of the report for the Independent Expert Panel

The Grid West project - Summary of the report for the Independent Expert Panel The Grid West project - Summary of the report for the Independent Expert Panel 1. Glossary Glossary AC AC is a type of electrical current, in which the direction of the flow of electrons switches back

More information

INTERCONNECTION BETWEEN IRELAND AND ENGLAND / WALES TECHNICAL INVESTIGATION INTO CONNECTION OF EAST WEST INTERCONNECTOR TO IRISH TRANSMISSION SYSTEM

INTERCONNECTION BETWEEN IRELAND AND ENGLAND / WALES TECHNICAL INVESTIGATION INTO CONNECTION OF EAST WEST INTERCONNECTOR TO IRISH TRANSMISSION SYSTEM INTERCONNECTION BETWEEN IRELAND AND ENGLAND / WALES TECHNICAL INVESTIGATION INTO CONNECTION OF EAST WEST INTERCONNECTOR TO IRISH TRANSMISSION SYSTEM EIRGRID AUGUST 2007 EXPLANATORY NOTE FOR PUBLISHED DOCUMENT

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee March 6, 2014 1 2014 RTEP Update 2 2014 RTEP Update Initial 2019 Summer base case and corresponding machine list update complete PJM staff has been reviewing and

More information

Building Collaboration Between East African Nations via Transmission Interconnectors

Building Collaboration Between East African Nations via Transmission Interconnectors Building Collaboration Between East African Nations via Transmission Interconnectors Eng. Christian M.A. Msyani Ag. DEPUTY MANAGING DIRECTOR TRANSMISSION - TANESCO CONTENTS 1. TANESCO - Existing Power

More information

Currant Lake Transmission Project

Currant Lake Transmission Project Currant Lake Transmission Project September 2010 Why are you receiving this project information package? New transmission facilities are needed in the Monitor area of southeastern Alberta. ATCO Electric

More information

Willingdon Substation Decommission

Willingdon Substation Decommission November 2012 Why are you receiving this project information package? New transmission facilities have been proposed in central east Alberta. As a result, some existing facilities are no longer needed.

More information

P.O BOX 429, NUKU ALOFA, Tel: (676) Fax: (676)

P.O BOX 429, NUKU ALOFA, Tel: (676) Fax: (676) P.O BOX 429, NUKU ALOFA, Tel: (676) 27-390 Fax: (676) 23-047 Email: jvanbrink@tongapower.to 22 October 2012 Lord Dalgety Electricity Commission Tu atakilangi Nuku alofa Dear Lord Dalgety Compliance Reporting

More information

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016 New Transmission Line April 1, 2016 The enclosed information is proprietary to PSE&G and is provided solely for your use. It should not be copied, reproduced, or shared with others without PSE&G s prior

More information

OVERVIEW OF UNDERGROUND POWER CABLES AT HIGH/EXTRA HIGH VOLTAGE LEVELS

OVERVIEW OF UNDERGROUND POWER CABLES AT HIGH/EXTRA HIGH VOLTAGE LEVELS OVERVIEW OF UNDERGROUND POWER CABLES AT HIGH/EXTRA HIGH VOLTAGE LEVELS 2006 WWW.EUROPACABLE.COM Introduction to Europacable Europacable is The Association of European Cable Manufacturers including ABB,

More information

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden Conference-1 Latest Technologies in T & D, Renewable Energy Integration, Smart Grid, Energy Efficiency, Communication Next Generation of UHVDC System R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC

More information

SPP Notification to Construct

SPP Notification to Construct February 19, 2014 SPP Notification to Construct Mr. John Fulton Southwestern Public Service Company P.O. Box 1261 Amarillo, TX 79105 RE: Notification to Construct Approved Reliability Network Upgrades

More information

The Highways Agency is working to improve the M3 between junctions 2 to 4a.

The Highways Agency is working to improve the M3 between junctions 2 to 4a. Welcome The Highways Agency is working to improve the M3 between junctions 2 to 4a. The M3 Junctions 2 to 4a is part of a major strategic road network connecting people, communities and businesses, carrying

More information

Planning Studies for Connection of 500 MW Photovoltaic Power Plant to Oman Grid at Ibri

Planning Studies for Connection of 500 MW Photovoltaic Power Plant to Oman Grid at Ibri Helwan University From the SelectedWorks of Omar H. Abdalla November 11, 2018 Planning Studies for Connection of 500 MW Photovoltaic Power Plant to Oman Grid at Ibri Hisham A. Al-Riyami Adil Al-Busaidi

More information

Smarter Network Storage: Introduction to grid-scale storage and applications, the DNO perspective

Smarter Network Storage: Introduction to grid-scale storage and applications, the DNO perspective Smarter Network Storage: Introduction to grid-scale storage and applications, the DNO perspective 2 Storage: the DNO perspective Context to the storage boom Smarter Network Storage: What have we achieved?

More information

EDS SUBSTATION LVAC SUPPLIES

EDS SUBSTATION LVAC SUPPLIES Document Number: EDS 08-1112 Network(s): Summary: EPN, LPN, SPN ENGINEERING DESIGN STANDARD EDS 08-1112 SUBSTATION LVAC SUPPLIES The standard details the requirements and options for the provision of LVAC

More information

Approved by This document is the property of Network Rail... Date: It shall not be reproduced in whole Phil Collins Head of Asset Management (E&P)

Approved by This document is the property of Network Rail... Date: It shall not be reproduced in whole Phil Collins Head of Asset Management (E&P) Report (updated) Estimate of AC losses: Electricity Supply Tariff Area Analysis CP5 proposal Network Rail January 2013 Document Author... Date: Kevin Middleton National Enhancements Project Engineer (E&P)

More information

Approved by This document is the property of Network Rail... Date: It shall not be reproduced in whole Phil Collins Head of Asset Management (E&P)

Approved by This document is the property of Network Rail... Date: It shall not be reproduced in whole Phil Collins Head of Asset Management (E&P) Report Estimate of AC losses Electricity Supply Tariff Area Analysis Document Author... Date: Kevin Middleton National Enhancements Project Engineer (E&P) Checked... Date: Simon Polley Principal Policy

More information

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS 1. PURPOSE AND SCOPE OF THIS DOCUMENT... 3 2. DEFINITIONS...

More information

Vantage to Pomona Heights Transmission Project Frequently asked questions

Vantage to Pomona Heights Transmission Project Frequently asked questions Vantage to Pomona Heights Transmission Project Frequently asked questions These are some frequently asked questions regarding the proposed Vantage to Pomona Heights transmission line project. General What

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Post Opening Project Evaluation. M6 Toll

Post Opening Project Evaluation. M6 Toll M6 Toll Five Post Years Opening After Study: Project Summary Evaluation Report Post Opening Project Evaluation M6 Toll Five Years After Study Summary Report October 2009 Document History JOB NUMBER: 5081587/905

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information