1 Project Status Report for LATS MPO November 17, 2017 Counties covered in Report: Beaufort & Jasper SCDOT anticipates construction to begin on approximately $206,762,556 in transportation projects between Fiscal Year in the Lowcountry Area Transportation Study Metropolitan Planning Organization area. This includes $2,124,700 in Act 98 funded projects. Lowcountry COG Transportation Funding Summary Program Total Mileage Funding Bridge Replacement/Removal (On-System) $13,333,204 Bridge Interstate/NHS $45,976,100 C Program - C Program $2,360,400 Interstate - Reconstruction $47,600,000 Interstate - Preservation $6,396,900 Pavement Improvement & Preservation Resurfacing (Act 98) $2,124,700 Pavements Non-FA Secondary $2,453,700 Pavements Non-Interstate NHS $9,323,965 Pavements Non-NHS Primary $3,222,200 Pavements FA Secondary 6.56 $982,800 Preventative Maintenance & Operations Signals $759,200 Rural System Upgrade - Lowcountry $57,968,887 Safety Funds $1,075,000 Safety Interstate Safety Improvements $12,215,200 Transportation Alternatives Areas >5K & <200K $970,300 TOTALS Miles $206,441,556 Craig Winn, SCDOT Program Manager for the Lowcountry, WinnCL@scdot.org or (803)

2 Beaufort County: SCDOT anticipates construction to begin on approximately $58,992,365 between fiscal year 2017 and This includes $1,103,400 in Act 98 funded projects. Beaufort County Funding Summary Program Total Mileage Funding Bridge - Replacement (On-System) $8,333,678 Bridge Interstate/NHS $35,620,100 Pavement Improvement & Preservation Resurfacing (Act 98) $1,103,400 Pavements Non-FA Secondary $1,324,300 Pavements Non-Interstate NHS System $3,333,200 Pavements Non-NHS Primary $2,213,300 Pavements FA Secondary $879,800 Preventative Maintenance & Operations - Signals $759,200 Rural System Upgrade - Lowcountry $3,968,887 Safety Funds $1,075,000 Transportation Alternatives Areas >5K & <200K $381,500 TOTALS Miles $58,992,365 Bridge Interstate/NHS A. Project ID : US 278 Corridor Improvements (3.700 Total Miles) Scope: Widening of US 278 from 4 to 6 lanes from Buckingham Plantation Drive to Squire Pope Road, including replacement of the EB Mackay Creek Bridge, intersection improvements on Pickney Island and improvements to Jenkins Island. Termini: US 278 E: Moss Creek Drive to Squire Pope Road Anticipated Construction Cost: $ M

3 Bridge - Replacement (On-System): B. Project ID : S-79 Bridge Replacement over Jarvis Creek (1.120 Total Miles) Scope: Replace Bridge over Jarvis Creek, including roadwork along S-79 (Spanish Wells Road) within the Town limits of Hilton Head Island, Beaufort County. Traffic will be maintained during construction. Termini: S-79 S: Humane Way (local) to Thomas Cohen Drive (local) Anticipated Construction Cost: $8,333,678 Schedule: UNDER CONSTRUCTION, As of July 5, 2017, Contract is 67.24% on money and 73.00% complete on time with a completion date of March 23 rd, Pavement Improvement & Preservation Resurfacing (Act 98): Project ID P029769: 2017 Non-Federal Aid ACT 98 Program (4.560 Total Miles) Scope: Non-Federal Aid Resurfacing in Beaufort County Termini: Keans Neck Road (S-38 E): Kinlock Road (S-43) to End State Maintenance Seabrook Road (S-42 E): End State Maintenance to US-21 (Trask Parkway) Prince Street (S-110 E): US-21 (Carteret Street) to Charles Street (S-133) Carolina Avenue (S-623 N): Clarendon Road (S-71) to Jasperstone Circle (S-623) Carolina Avenue (S-697 N): S-623 to Dead End Anticipated Project Cost: $1,103,400 Anticipated Construction Cost: $1,103,400 Schedule: Project awarded September 2016 to The Lane Construction Corporation. Contract completion date set for 10/31/2017. Project Substantially Complete on 10/31/2017. Pavements Non-Interstate NHS: Project ID P030106: 2017 Federal Aid Primary Program (1.230 Total Miles) Scope: 2017 NHS Federal Aid State Program in Beaufort County Termini: US-21 N (Trask Parkway): 0.15 miles W of US-21 BUS. to 0.05 miles S of Salt Creek Road (L-638) US-21 N: Roseida Road (S-265) to 0.29 miles S of Shanklin Road (S-86) Anticipated Project Cost: $703,600 Anticipated Construction Cost: $703,600 Schedule: Project awarded to Preferred Materials, Inc. Contract completion date set for 08/31/2017. Project bundled with P and P Contract is currently 59% Complete.

4 Project ID P030121: 2017 NHS Federal Aid State Program (2.620 Total Miles) Scope: 2017 NHS Federal Aid State Program in Beaufort County Termini: US-21 N (Trask Parkway): Washington Farm Road (S-238) to 0.30 miles SE of US-17 (Charleston Highway) US-278 E: 0.21 miles E of Mackay Creek Bridge to 0.39 miles E of Mackay Creek Bridge US-278 E (William Hilton Parkway): 0.06 miles NW of Blue Heron Point Road (S-772) to 0.05 miles SE of S-772 SC-170 E (Okatie Highway): 0.01 miles N of US-278 (Fording Island Road) to 0.12 miles N of Barrel Landing Road (S-261) Anticipated Project Cost: $1,725,700 Anticipated Construction Cost: $1,725,700 Schedule: Project awarded to Preferred Materials, Inc. Contract completion date set for 08/31/2017. Project bundled with P and P Contract is currently 59% Complete. Project ID P030691: 2017 Federal Aid NHS Preservation Program (3.050 Total Miles) Scope: SCDOT Federal Aid Preservation in Beaufort County Termini: SC-170 E: 0.76 miles E of Barrel Landing Road (S-261) to Walsh Drive W (S-399) SC-170 E: Jasper County Line to 0.37 miles E of Duke Street (S-54) SC-170 E: 0.37 miles E of Duke Street (S-54) to Chechessee River Bridge Joint Anticipated Project Cost: $903,900 Anticipated Construction Cost: $903,900 Schedule: Letting is scheduled for March Pavements Non-NHS Primary Project ID P030583: 2017 Federal Aid Primary Preservation Program (4.160 Total Miles) Scope: SCDOT Federal Aid Preservation in Beaufort County Termini: US-21 N: US 21 Business to McTeer Bridge Joint US-21 N: McTeer Bridge Joint to SC-281 SC-128 E: SC-170 to US 21 Anticipated Project Cost: $1,065,800 Anticipated Construction Cost: $1,065,800 Schedule: Letting is scheduled for March Project ID P031972: 2018 Primary Improvement Program (1.840 Total Miles) Scope: Primary Improvement in Beaufort County Termini: US-21 BUS N: Bridge Joint to Greenlawn Drive (S-296) Anticipated Project Cost: $1,147,500 Anticipated Construction Cost: $1,147,500 Schedule: Project awarded to Preferred Materials, Inc. Contract completion date set for 05/31/2018. Pavements FA Secondary: Project ID P030164: 2017 Federal Aid Secondary Program (3.130 Total Miles) Scope: 2017 NHS Federal Aid State Program in Beaufort County Termini: Meridian Road (S-36 E): US-21 Business to US-21 Brickyard Point Road (S-72 E): Pleasant Point Road (S-258) to Dead End Anticipated Project Cost: $688,800 Anticipated Construction Cost: $688,800 Schedule: Project awarded to Preferred Materials, Inc. Contract completion date set for 08/31/2017. Project is bundled with P and P Contract is currently 59% Complete. Project ID P030697: 2017 Federal Aid Secondary Preservation Program (2.240 Total Miles) Scope: SCDOT Federal Aid Preservation in Beaufort County Termini: Pinckney Colony Boulevard (S-50 E): US 278 to Logan Road (S-82) Anticipated Project Cost: $191,000 Anticipated Construction Cost: $191,000 Schedule: Letting is scheduled for March 2018.

5 Pavements Non-FA Secondary: Project ID P032169: 2018 Non-Federal Aid Preservation Program (1.560 Total Miles) Scope: Non-Federal Aid Preservation in Beaufort County Termini: Parker Drive (S-543 N): US-21 to Schork Road (S-787) Anticipated Project Cost: $198,700 Anticipated Construction Cost: $198,700 Schedule: Project bundled with P032210, Bid Rejected. Will be added to a future letting in December Project ID P032292: 2018 Secondary Pavement Improvement Program (3.310 Total Miles) Scope: Non-Federal Aid Resurfacing in Beaufort County Termini: Harrington Street (S-68 E): Local to Bay Street (S-6) Newcastle Street (S-100 E): Prince Street (S-110) to US 21 Business Newcastle Street (S-100 E): Local to Godfrey Street (S-271) Monson Street (S-102 E): Washington Street (S-106) to Bay Street (S-6) Washington Street (S-106 E): Charles Street (S-133) to US 21 Business Center Drive W (S-250 E): Battery Road (S-159) to Center Drive E (S-251) Lagoon Road (S-327 E): Pope Avenue(S-80) to North Forest Beach Drive (S-244) Pine Court S (S-385 E): Pine Court N (S-250) to SC 281 Anticipated Project Cost: $1,125,600 Anticipated Construction Cost: $1,125,600 Schedule: Letting is scheduled for February Preventative Maintenance & Operations - Signals: Project ID P030853: (3) Traffic Signal Upgrades in Beaufort with Mast Arms (3.402 Total Miles) Scope: 3 Traffic Signal Upgrades along US-21 in Beaufort, Mast Arms provided by Beaufort County and installed by SCDOT Termini: US-21 N US-21 Business N SC 170 E Craven Street (S-62 E) Bladen Street (S-483 N) Anticipated Project Cost: $759,200 Anticipated Construction Cost: $759,200 Schedule: Construction Letting scheduled for November 14 th, 2017.

6 Rural System Upgrade Lowcountry: C. Project ID : SC-802 & Holly Hall / Brickyard Intersection (0.787 Total Miles) Scope: Intersection Improvement (Round-a-bout Construction) along SC Route 802 (Sam's Point Road) at S- 112 (Holly Hall Road)/ S-72 (Brickyard Point Road) on Lady's Island, Beaufort County. Termini: SC-802 E: S-791 Doe Road to Cottage Road (local) S-72 W: S-750 Middle Road to SC-802 S-112 E: SC-802 to 0.2 miles E of Intersection Anticipated Construction Cost: $3,968,887 Schedule: UNDER CONSTRUCTION. Traffic is in the final configuration. Landscaping and permanent pavement markings remain to be completed. Safety Funds: D. Project ID P028659: SC 170 Intersection Improvement (1.050 Total Miles) Scope: Intersection of SC Route 170 to include access management strategies that either eliminate or restrict some turning movements from driveways near the intersection, Beaufort County. Termini: US-21 (Parris Island Gateway): SC-170 to Ambrose Run SC 170 E (Robert Smalls Parkway): 500 ft prior to (WK Alston Drive (S-761) to US 21 WK Alston Drive (S-761 N): SC 170 to 800 ft N of SC 170 Anticipated Project Cost: $1,075,000 Anticipated Construction Cost: $900,000 Schedule: Construction Letting scheduled for Summer 2018.

7 Transportation Alternatives Areas >5K & <200K: E. Project ID P030220: Waddell Road/Ribaut Road Sidewalk Improvements (0.473 Total Miles) Scope: Sidewalk Improvements on Waddell Road between Talbird Rd. and Robinson St. and on Old Shell Rd./Ribaut Road between Pinckney Blvd. and the Naval Hospital Entrance in the Town of Port Royal. Termini: US-21 (Ribaut Rd.) N: Pinckney Blvd. to Old Shell Road S-233 N (Waddell Rd.): Talbird Road to Robinson St. L-52 E (Old Shell Rd.): US-21 to Pinckney Blvd. Anticipated Project Cost: $381,500 Anticipated Construction Cost: $291,900 Schedule: Construction Letting scheduled for Winter

8 Jasper County: SCDOT anticipates construction to begin on approximately $147,770,191 between fiscal year 2017 and This includes $1,021,300 in Act 98 funded projects. Jasper County Transportation Funding Summary Program Total Mileage Funding Bridge - Replacement (On-System) $4,999,526 Bridge Interstate/NHS $10,356,000 C Program $2,360,400 Interstate Interstate Reconstruction $47,600,000 Interstate Interstate Preservation $6,396,900 Pavement Improvement & Preservation Resurfacing (Act 98) $1,021,300 Pavements Non-FA Secondary $1,129,400 Pavements Non-Interstate NHS System $5,990,765 Pavements Non-NHS Primary $1,008,900 Pavements FA Secondary $103,000 Rural System Upgrade - Lowcountry $54,000,000 Safety Interstate Safety Improvements $12,215,200 Transportation Alternatives Areas >5K & <200K $588,800 TOTALS miles $147,770,191 Bridge Replacement/Removal (On-System): F. Project ID : US-17 Bridge Removal, Roadway Work (0.800 Total Miles) Scope: Removal of bridge and construction of at-grade crossing at on US-17 at MP 4.82 (S.C.L RAILROAD) Termini: US-17 N: 0.3 miles North of SC-315 intersection to 1.3 miles South of SC-170 intersection Anticipated Construction Cost: $4,999, Schedule: UNDER CONSTRUCTION. Contract is 64.59% on money and % complete on time. Project awarded to Preferred Materials, Inc. Contract completion date set for 08/31/2017. Awaiting the latest schedule from the contractor for an updated completion date. Paving operations are wrapping up. Once all pavement operations are completed the existing bridge will be demolished.

9 Bridge Interstate/NHS G. Project ID P030260: I-95 SB over Bagshaw Swamp (0.750 miles) Scope: Bridge Replacement I-95 over Bagshaw Swamp Termini: I-95 S Anticipated Project Cost: $5,609,500 Anticipated Construction Cost: $4,309,500 Schedule: Letting is Scheduled for January 2022 H. Project ID P030481: I-95 SB over SC 46 (1.500 miles) Scope: Bridge Replacement I-95 over Bagshaw Swamp Termini: I-95 S Anticipated Project Cost: $4,746,500 Anticipated Construction Cost: $3,646,500 Schedule: Letting is Scheduled for January 2022 C Program Project ID P029507: Jasper CTC Resurfacing $216 Million One-Time Funding (8.610 Total Miles) Scope: H.4230 Funds - Resurface S-29, S-32, S-34, S-38, S-59, S-65, S-67, S-73, S-95, S-133, S-148, S- 178, S-298, S-299, S-300, S-301, S-384, AND S-421 Termini: Smith s Crossing (S-29 N): US-17 (Jacob Smart Boulevard) to SC-336 (Tillman Road) Green Street (S-32 E): 0.03 Miles SW of Woodlawn Street (S-57) to 0.04 miles NW of US-17 Purrysburg Road (S-34 E): 0.59 Miles S of L-242 to 0.03 miles N of Structure Millstone Creek Purrysburg Road (S-34 E): Church Road (S-31) to End State Maintenance Logan Street (S-35 N): US-17 to Dead End Wilson Street (S-59 N): SC-336 to Green Street (S-32) Weathersbee Street (S-65 N): 2 nd Avenue (S-74) to Floyd Street (S-66) Perry Street (S-67 N): Adams Street (S-61) to S-74 Wise Street (S-73 N): Smiths Crossing (S-29) to Woodlawn Street (S-57) Martin Street (S-95 N): Boyd Street (S-96) to SC-46 (Main Street) 1 st Street (S-133 N): Garr Lane (S-178) to Dead End Wall Street (S-148 E): Smiths Crossing (S-29) to Dead End Garr Lane (S-178 E): US-17 to Singleton Street (S-384) Columbia Street (S-298 E): SC-46 to Winthrop Street (S-300) Furman Street (S-299 N): Dead End to Dead End Winthrop Street (S-300 E): Columbia Street (S-298) to Dead End Columbia Street (S-301 N): Columbia Street (S-298) to Dead End S-384 E: Charles Street (S-135) to Dead End Frontage Road (S-421 N): R-8650 to SC-46 (Main Street) Frontage Road (S-424 E): 0.03 miles N of L-341 to 0.33 miles NE of L-341 Point South Drive (S-427 N): 0.07 miles NE of Kings Road (Local) to Yemassee Road (S-276) Anticipated Project Cost: $2,360,400 Anticipated Construction Cost: $2,359,400 Schedule: Project awarded to Preferred Materials, Inc. Notice-To-Proceed: 10/20/16. Contract completion date set for 08/31/2017. Contract is currently 57% Complete. Interstate Interstate Reconstruction I. Project ID P027551: I-95 Reconstruction MP 23 to 33 - Jasper County Section ( Total Miles) Scope: Reconstruction of concrete/asphalt pavement along NB/SB lanes of Interstate 95 from MP 23 to MP 33;. Termini: I-95 N: MP 23 to MP 33 I-95 S: slightly North of MP 22 to MP 33 Anticipated Project Cost: $47,600,000 Anticipated Construction Cost: $46,500,000 Schedule: Project is being identified as going back as preventative maintenance.

10 Interstate - Interstate Preservation J. Project ID P029421: I-95 (Near MM 4 to near MM 18) & I-95 (Near MM 18 to near MM 23) (19.0 Total Miles) Scope: Interstate Preservation in Jasper County. This project will be completed in accordance with the Federal Aid Preventative Maintenance MOA. Scope includes FDP, Diamond Grind & Joint Seal, Hot Pour Sealant. Termini: I- 95 N: 0.90 miles N of Okatie Highway (S-34) to 0.07 miles N of Bees Creek Road (S-13) I- 95 S: 0.90 miles N of S-34 to Exit 22 Anticipated Project Cost: $6,396,900 Anticipated Construction Cost: $6,396,900 Schedule: Project awarded to Interstate Improvement, Inc. Notice-To-Proceed: 09/14/16. Contract completion date set for 08/14/2017. Contract is currently set to finish in November. Pavement Improvement & Preservation Resurfacing (Act 98): Project ID P029807: 2017 Non-Federal Aid Act 98 Program (3.210 Total Miles) Scope: Non-Federal Aid Resurfacing in Jasper County Termini: Bellinger Hill Road (S-92 E): 0.14 miles NW of Turnbridge Landing Road to Pavement Joint S-102 E: Pavement Joint to Dead End (NOT WITHIN LATS BOUNDARY) S-424 E: 0.93 miles S of L-341 to 0.03 miles N of L-341 (NOT WITHIN LATS BOUNDARY) Anticipated Project Cost: $1,021,300 Anticipated Construction Cost: $1,021,300 Schedule: Contract awarded September 2016 to The Lane Construction Corporation. Contract completion date set for 10/31/2017. Project Substantially Complete on 10/31/2017. Pavements Non-FA Secondary: Project ID P032210: 2018 Non-Federal Aid Preservation Program (0.427 Total Miles) Scope: Non-Federal Aid Preservation in Jasper County Termini: Second Avenue (S-74 E): Jasper Street (S-63) to Fifth Avenue (S-70) Shirley Street (S-154 E): Dead End to Dead End Anticipated Project Cost: $66,500 Anticipated Construction Cost: $66,500 Schedule: Project bundled with P032169, Bid Rejected. Will be added to a future Construction Letting in December Project ID P032285: 2018 Secondary Pavement Improvement Program (3.830 Total Miles) Scope: Non-Federal Aid Resurfacing in Jasper County Termini: Okatie Highway (S-34 E) SPR: Okatie Highway (S-34) to Dead End Logan Street (S-35 E): Wilson Street (S-59) to US 17 Langford Street (S-44 E): Green Street (S-32) to Dead End Jasper Street (S-63 N): SC 336 to Hagin Drive (S-62) Floyd Street (S-66 E): SC 336 to US st Avenue (S-68 E): 0.2 miles NE of Great Swamp Road (S-116) to Perry Street (S-67) 2 nd Avenue (S-74 E): 0.03 miles SE of Weathersbee Street (S-65) to SC 336 Connection Jaudon Street (S-82 E): Green Street (S-32) to Dead End Red Dam Road (S-94 E): Brickyard Road (S-88) to 0.15 miles N of Red Dam Church Road (S-93) Mango Drive (S-101 N): Mitchellville Road (S-102) to US 17 Bass Lake Drive (S-291 N): Tarboro Road (S-22) to SC 336 Pine Arbor Road (S-304 E): 0.84 miles S of John Smith Road (S-141) to John Smith Road (S-141) Anticipated Project Cost: $1,062,900 Anticipated Construction Cost: $1,062,900 Schedule: Letting is scheduled for February 2018.

11 Pavements Non-Interstate NHS: Project ID P030151: 2017 NHS Federal Aid State Program (7.880 Total Miles) Scope: 2017 NHS Federal Aid Rehabilitation in Jasper County Termini: US-278 E: 0.30 miles E of Medical Center Drive (S-422) to 0.57 miles E of John Smith Road (S-141) US-321 N: 0.10 miles S of SC-336 to 0.22 miles N of S-397 US-321 N: 0.72 miles N of S-397 to US-601 Anticipated Project Cost: $4,235,565 Anticipated Construction Cost: $4,235,565 Schedule: Letting held March 14. Awarded with Justification to Preferred Materials Inc. with a contract completion date set for 10/31/2018. Project ID P030155: 2017 NHS Federal Aid State Program (3.790 Total Miles) Scope: 2017 NHS Federal Aid Program in Jasper County Termini: US-17 N: 3.79 miles SW of SC-315 to SC-315 Anticipated Project Cost: $1,448,000 Anticipated Construction Cost: $1,448,000 Schedule: Letting held March 14. Project awarded to Preferred Materials Inc. with a contract completion date set for 10/31/2018. Project ID P030581: 2017 Federal Aid Primary Preservation Program (1.060 Total Miles) Scope: SCDOT Federal Aid Preservation in Jasper County Termini: SC-170 E: Old Baileys Road (S-18) to Beaufort County Line Anticipated Project Cost: $307,200 Anticipated Construction Cost: $307,200 Schedule: Letting is scheduled for March Pavements Non-NHS Primary: Project ID P032053: 2018 Primary Improvement Program (1.840 Total Miles) Scope: Primary Improvement in Jasper County Termini: US-17 N: Okatie Highway (S-34) to 0.52 miles N of Toomerville Loop (S-383) Anticipated Project Cost: $1,008,900 Anticipated Construction Cost: $1,008,900 Schedule: Project awarded to Preferred Materials Inc. with a contract completion date set for 05/31/2018. Pavements FA Secondary: Project ID P030698: 2017 Federal Aid Secondary Preservation Program (1.190 Total Miles) Scope: SCDOT Federal Aid Preservation in Jasper County Termini: Brickyard Road (S-88 E): John Smith Road (S-141) to US-278 Anticipated Project Cost: $103,000 Anticipated Construction Cost: $103,000 Schedule: Letting is scheduled for March 2018.

12 Rural System Upgrade Lowcountry: K. Project ID : US-17 Widening (4.100 Total Miles) Scope: Widen on US 17 from a 2-lane to a 4 lane divided highway from Georgia state line to SC-315 Termini: US-17 S (Speedway Boulevard): State line to SC-315 (S Okatie Highway) Anticipated Project Cost: $54,000,000 Anticipated Construction Cost: $45,900,000 Schedule: Construction Letting is scheduled for Fall/Winter Safety Interstate Safety Improvements: L. Project ID P029731: Statewide Interstate Safety I95 MP ( Total Miles) Scope: Safety Improvements along I-95 in Jasper County from milepoint to include tree clearing & minor grading within clear zone. Milepoint to to be included in I-95 Reconstruction (See Project ID P027551) Termini: I-95 N I-95 S Anticipated Project Cost: $12,215,200 Anticipated Construction Cost: $12,215,200 Schedule: Project award to Graham County Land Company, LLC with a contract completion date set for 03/11/2018. Transportation Alternatives Areas >5K & <200K: M. Project ID P030219: Hardeeville Sidewalk Improvements (0.660 Total Miles) Scope: Sidewalk improvements on Charles Street from SC46 to Garr Ln, from Charles Street to US 17, 1st Street from Garr Ln to Hare St., and Hare St. from 1st Street to US 17 Termini: S-130 E: US 17 to 1st Street (S-133) S-133 N: Garr Ln. (S-178) to Hare St. (S-130) S-135 N: SC 46 to Garr Ln (S-178) S-178 E: US 17 to Charles St. (S-135) Anticipated Project Cost: $588,800 Anticipated Construction Cost: $439,100 Schedule: Letting is scheduled for February 2020.

13 Locally Administered Projects - LPA (for information only not included in summary) Project ID : Interstate 95 New Interchange (Exit 3) Project (1.501 Total Miles) Scope: Preliminary Engineering for a new interchange on I-95 at mile-marker 3, the 4 lane widening of Purrysburg Road from I-95 to US 17, an East-West connector roadway from Purrysburg Road to US 321 and intersection improvements at US 321 and US 17 on the Northern end and at US 179 and US 17 on the Southern end, Jasper County & City of Hardeeville with assistance from Beaufort County. Status: Consultant is working with USACE to develop Environmental Impact Statement (EIS) & Interchange Justification Report (IJR) for review and approval by SCDOT & FHWA. Anticipated Project Cost: $119,000,000 ($48,000,000 for interchange) Schedule: SIB & Developer funded project Schedule TBD based on funding availability and NEPA approvals. Beaufort / Jasper Projects: Under Construction Project County Cost Let Date Completion Date P US-17 Bridge Removal / At-grade Crossing Jasper $4,999, /13/2016 TBD by Contractor s Schedule P Jarvis Creek Bridge Replacement Beaufort $8,333, /11/ /23/2018 P SC-802 Roundabout Beaufort $3,968, /12/2016 TBD

14 For detailed information for all projects please visit our Programmed Map Viewer at the website below:

SC Highway 41 Existing Conditions

SC Highway 41 Existing Conditions SC Highway 41 Existing Conditions Existing Typical Cross Section purposes only and does not replace the required NEPA process necessary for alignment The NEPA process is anticipated to begin in the next

More information

Transportation. Background. Transportation Planning Goals. Level of Service Analysis 5-1

Transportation. Background. Transportation Planning Goals. Level of Service Analysis 5-1 Transportation portion of the city s stormwater utility, and state road and fuel taxes. Background The transportation needs of the City of Lacey and its planning areas are met by a growing multimodal network

More information

December 12, Dear Secretary Foxx:

December 12, Dear Secretary Foxx: Chair Pete White City Councilmember Vice-Chair Jay Adams Mustang Mayor Secretary/Treasurer Matt Dukes Midwest City Mayor association of central oklahoma governments Executive Director John G. Johnson December

More information

I-4 Beyond the Ultimate. Florida Transportation Builders Association January 18, 2019

I-4 Beyond the Ultimate. Florida Transportation Builders Association January 18, 2019 I-4 Beyond the Ultimate Florida Transportation Builders Association January 18, 2019 FDOT District 5 Improving Mobility & Safety in Central Florida FDOT District 5 is: Designing and building a better Interstate

More information

Transportation Improvement Program (TIP) Candidate Project List for Public Review

Transportation Improvement Program (TIP) Candidate Project List for Public Review 2011-2014 Transportation Improvement Program (TIP) Candidate List for Public Review Table 1 Annual Listing Of Federal Aid Obligation For Federal Fiscal Year 2010 North Dakota s Number Transit 410083 Transit

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

The State of SCDOT. Presented: February 1, 2017 Secretary Christy A. Hall, P.E.

The State of SCDOT. Presented: February 1, 2017 Secretary Christy A. Hall, P.E. The State of SCDOT Presented: February 1, 2017 Secretary Christy A. Hall, P.E. As we enter our Centennial Year, we have much to do together. 2 Looking # Back # over # the # past # 12 # months Y Y Y Y Y

More information

I-820 (East) Project Description. Fort Worth District. Reconstruct Southern I-820/SH 121 Interchange

I-820 (East) Project Description. Fort Worth District. Reconstruct Southern I-820/SH 121 Interchange I-820 (East) Project Description Fort Worth District Reconstruct Southern I-820/SH 121 Interchange I-820 from approximately 2,000 feet north of Pipeline Road/Glenview Drive to approximately 3,200 feet

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 2/19/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

US 70 Corridor Planning for the Future

US 70 Corridor Planning for the Future New Bern/James City Area - Work Session US 70 Corridor Planning for the Future Brinson Elementary School Thursday, January 31, 2008 Agenda Sign-in, in, View Maps, Talk to Project Team Public Q & A Session

More information

Wentzville Parkway South Phase 2 & 2A

Wentzville Parkway South Phase 2 & 2A Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total

More information

Leadership NC. November 8, 2018

Leadership NC. November 8, 2018 v Leadership NC November 8, 2018 Planning for our region s growth The Triangle is one of the fastestgrowing regions in the nation. More than 2 million people are already part of the equation, and the

More information

US 67 WIDENING PROJECT

US 67 WIDENING PROJECT US 67 WIDENING PROJECT From Belt Line Rd. to I-20 History & Background The US 67 improvements from Belt Line Rd to I-20 were originally part of TxDOT s Southern Gateway project, studied as part of the

More information

Guam Transportation Program Project Updates. Joanne M.S. Brown Director Carl Dominguez Deputy Director February 6, 2012

Guam Transportation Program Project Updates. Joanne M.S. Brown Director Carl Dominguez Deputy Director February 6, 2012 Guam Transportation Program Project Updates Joanne M.S. Brown Director Carl Dominguez Deputy Director February 6, 2012 Agenda Road Construction Highlights Ongoing Construction Route 17 Rehabilitation and

More information

ALTERNATIVE PROJECT DELIVERY

ALTERNATIVE PROJECT DELIVERY ALTERNATIVE PROJECT DELIVERY Varuna Singh SH 288 IN HARRIS COUNTY SH 288 in Harris County SEGMENT 1: 8 New Tolled Direct Connectors at SH 288 and Beltway 8 Existing traffic uses frontage roads today to

More information

BINGHAMTON METROPOLITAN TRANSPORTATION STUDY

BINGHAMTON METROPOLITAN TRANSPORTATION STUDY BINGHAMTON METROPOLITAN TRANSPORTATION STUDY ANNUAL LISTING OF FEDERAL AID PROJECT OBLIGATIONS FEDERAL FISCAL YEAR Federal regulations require an annual listing of transportation projects, including investments

More information

2016 PSRC REGIONAL & KING COUNTYWIDE EASTSIDE FUNDING AWARDS. Eastside Transportation Partnership September 9, 2016

2016 PSRC REGIONAL & KING COUNTYWIDE EASTSIDE FUNDING AWARDS. Eastside Transportation Partnership September 9, 2016 2016 PSRC REGIONAL & KING COUNTYWIDE EASTSIDE FUNDING AWARDS Eastside Transportation Partnership September 9, 2016 1 2 PSRC 2016 Project Selection Process 2018-2020 Estimated FHWA Funds Available: (Summary)

More information

Public Information Packet FY Fargo-Moorhead Metropolitan Transportation Improvement Program (TIP)

Public Information Packet FY Fargo-Moorhead Metropolitan Transportation Improvement Program (TIP) Public Information Packet FY - Fargo-Moorhead Metropolitan Transportation Improvement Program (TIP) Comment Form Annual Element TIP Projects - TIP Projects Year - Metropolitan Transportation Improvement

More information

CAPITAL FUND 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS

CAPITAL FUND 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS 2019-2023 9510 STREET & SIDEWALK IMPROVEMENTS - 01 STREET AND SIDEWALK MAINTENANCE PROGRAM $1,250,000 $0 $1,250,000

More information

Chapter 7: Corridor Visions

Chapter 7: Corridor Visions Chapter 7: Corridor Visions (see also Appendix 7 for Details) January 24, 2008 NOTE: This document has been prepared using Federal funding from the United States Department of Transportation. The United

More information

Public Information Workshop

Public Information Workshop Public Information Workshop Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 29, 2018 Welcome to the Public Information Workshop for Harborview Road Project Development and Environment (PD&E)

More information

City of Grand Forks Staff Report

City of Grand Forks Staff Report City of Grand Forks Staff Report Service/Safety Committee December 15, 2015 City Council December 21, 2015 Agenda Item: Amendment No. 1 to Engineering Services Agreement with CPS for City Project No. 7143,

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate

More information

CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE

CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE TUESDAY, DECEMBER 5, 2017 1 DISCUSSION TOPICS Update of Infrastructure Action Plan (IAP) o Sidewalk and Roadway projects

More information

Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction

Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction 550 North to 650 North $ 1,750,000 $ 1,582,113 To widen an existing bridge on 1200 West over Box Elder Creek that will

More information

Proposed Project I 35 Improvements from SH 195 to I 10

Proposed Project I 35 Improvements from SH 195 to I 10 I 35 ROADWAY Proposed Project I 35 Improvements from SH 195 to I 10 The existing I 35 facility from State Highway 195 (SH 195) north of Georgetown to Interstate 10 (I 10) in San Antonio varies from four

More information

S.M. Wright Project (I-45, US 175, SH 310) and Road to Work Opportunity Program. Transportation and Trinity River Project Committee May 23, 2016

S.M. Wright Project (I-45, US 175, SH 310) and Road to Work Opportunity Program. Transportation and Trinity River Project Committee May 23, 2016 635 S.M. Wright Project (I-45, US 175, SH 310) and Road to Work Opportunity Program Transportation and Trinity River Project Committee May 23, 2016 Project Scope Increase safety by removing the existing

More information

MUNCIPAL WORK PROGRAMS FY 2015/ /20. MPO Transportation Improvement Program 2015/ /20 Page 9-1

MUNCIPAL WORK PROGRAMS FY 2015/ /20. MPO Transportation Improvement Program 2015/ /20 Page 9-1 MUNCIPAL PROGRAMS BELLEAIR 2000 Curb/Sidewalk 35 2001 Roadway Projects 2,500 = ; = Local Funds 35 MPO Transportation Improvement Program 2015/16 2019/20 Page 9-1 MUNCIPAL PROGRAMS BELLEAIR BEACH 3000 Resurface/curb

More information

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015 SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment

More information

Metro Highway Program

Metro Highway Program Metro Highway Program ACEC November 2018 I-5 North HOV and Truck Lanes 14 miles of HOV lanes in both directions 2 miles of truck climbing lanes at the south end 7 bridge modifications at: Gavin Canyon

More information

Purpose and Need Report

Purpose and Need Report Purpose and Need Report State Highway (SH) 29 From Southwestern Boulevard to SH 95 Williamson County, Texas (CSJ: 0337-02-045) Prepared by Blanton & Associates, Inc. Date: November, 2015 The environmental

More information

Delaware County Engineer s Office

Delaware County Engineer s Office Delaware County Engineer s Office JANUARY 2017 County Engineer Responsibility Serve as engineer to the Board of County Commissioners and 18 Boards of Township Trustees for roads, bridges and land surveying

More information

Corridor Sketch Summary

Corridor Sketch Summary Corridor Sketch Summary SR 241: I-82 Jct (Sunnyside) to SR 24 Jct Corridor Highway No. 241 Mileposts: 7.53 to 25.21 Length: 17.65 miles Corridor Description The seventeen and one-half mile corridor begins

More information

system performance I-820 East Loop FM 156 TxDOT is working to expand its busiest metropolitan corridors.

system performance I-820 East Loop FM 156 TxDOT is working to expand its busiest metropolitan corridors. system performance TxDOT is working to expand its busiest metropolitan corridors. Nine of the state s 100 most congested highways are located in Tarrant County. Six of these highways will be expanded and

More information

2018 Transportation Improvement Program (TIP) Bridge Section Summary of Proposed Changes July 24, 2018

2018 Transportation Improvement Program (TIP) Bridge Section Summary of Proposed Changes July 24, 2018 Transportation Improvement Program (TIP) Bridge Section Summary of Proposed Changes July 24, FFY Section 2A State Prioritized Reliability s Bridge Program/On-System (NHS) Increase the Cost of Holyoke (600936)

More information

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,

More information

Letter of Transmittal

Letter of Transmittal Letter of Transmittal To: Chris Lovell City of Richmond Hill Date: 5/2/6 Job 2582 Re: Richmond Hill-South Bryan County Transportation STudy WE ARE SENDING YOU THE FOLLOWING ITEMS ( attached) ( under separate

More information

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018 NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3 April 19, 2018 NHHIP OVERVIEW NHHIP divided into 3 Segments: Segment 1: I-45: Beltway 8 to I-610 (9 mi) 45 Segment 2: I-45: I-610 to I-10 (3

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Laura Cornejo, DEO Regional Planner Regional Operator Metro is LA County s Regional Builder/Funder Rail Bus Service (Metro/Muni/Local)

More information

Committee Report. Transportation Committee. Business Item No

Committee Report. Transportation Committee. Business Item No Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope

More information

Highways: Interstate. Highways: State Highways. Highways: Local Roads. Highways: Off State Hwy Sys/Off Fed Sys. Maintenance: Interstate

Highways: Interstate. Highways: State Highways. Highways: Local Roads. Highways: Off State Hwy Sys/Off Fed Sys. Maintenance: Interstate FLORIDA DEPARTMENT OF TRANSPORTATION 5 - YEAR TRANSPORTATION PLAN ($ IN THOUSANDS) TENTATIVE FY 2019-2023 (10/01/2017 20:15:01) BAKER COUNTY Highways: Interstate 4386501 I-10 BAKER CO SPRAYFIELD EB REST

More information

Rural Planning. Highway Projects - CULLMAN COUNTY

Rural Planning. Highway Projects - CULLMAN COUNTY 4/17/2015 ALABAMA DEPARTMENT OF TRANSPORTATION Page - 1 of 9 Length CR-1742 4.770 Highway s - CULLMAN COUNTY RESURFACE CR-1742 FROM SR-74 (US-278) TO SR-67 RESURFACING 100063223 ST-022-888-011- ( ) CONSTRUCTION

More information

APPENDIX A Interstate 26 Widening Traffic Analysis Report

APPENDIX A Interstate 26 Widening Traffic Analysis Report Interstate 26 Widening MM 85-MM101, Newberry, Lexington, Richland Counties, SC Environmental Assessment APPENDIX A Interstate 26 Widening Traffic Analysis Report Interstate 26 Widening Traffic Analysis

More information

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014 Arterial Bus Rapid Transit System Policy Oversight Committee April 7, 2014 1 Meeting Agenda Welcome and Introductions A Line - Project Status Shelter and Pylon Development Arterial BRT Branding Update

More information

SAINT CHARLES COUNTY ROAD BOARD Minutes of March 21, 2018

SAINT CHARLES COUNTY ROAD BOARD Minutes of March 21, 2018 SAINT CHARLES COUNTY ROAD BOARD Minutes of March 21, 2018 The Wednesday, March 21, 2018, meeting of the St. Charles County Road Board was called to order at 4:30 p.m. in Room 542 of the Administration

More information

STH 60 Northern Reliever Route Feasibility Study Report

STH 60 Northern Reliever Route Feasibility Study Report #233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development

More information

Summary of the Alcoa Highway Redevelopment Project

Summary of the Alcoa Highway Redevelopment Project Appendix B Summary of the Alcoa Highway Redevelopment Project By Marcia Finfer, October 2009 The Timberlake community, along with numerous other concerned citizen groups (including the Lakemoor Hills community)

More information

Energy Technical Memorandum

Energy Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter

More information

MPO Staff Report Technical Advisory Committee: July 12, 2017

MPO Staff Report Technical Advisory Committee: July 12, 2017 MPO Staff Report Technical Advisory Committee: July 12, 2017 RECOMMENDED ACTION: 2 nd TAC Meeting with Kimley-Horn/WSB in Updating the Street/Highway Element of 2045 Metropolitan Transportation Plan. Matter

More information

Project Working Group Meeting #5

Project Working Group Meeting #5 September 17, 2013 Project Working Group Meeting #5 1 September 17, 2013 www.i-80will.com Meeting Purpose Project update Discuss Range of Alternatives Discuss next steps 2 September 17, 2013 www.i-80will.com

More information

Lacey Gateway Residential Phase 1

Lacey Gateway Residential Phase 1 Lacey Gateway Residential Phase Transportation Impact Study April 23, 203 Prepared for: Gateway 850 LLC 5 Lake Bellevue Drive Suite 02 Bellevue, WA 98005 Prepared by: TENW Transportation Engineering West

More information

Open Session Item. Construction Bid Award Pavement Maintenance & Rehabilitation Program FY 16 Chip Seal Applications, Contract No.

Open Session Item. Construction Bid Award Pavement Maintenance & Rehabilitation Program FY 16 Chip Seal Applications, Contract No. Board of County Commissioners of Washington County, Maryland Agenda Report Form Open Session Item SUBJECT: Construction Bid Award Pavement Maintenance & Rehabilitation Program FY 16 Chip Seal Applications,

More information

Project Description: Georgia Department of Transportation Public Information Open House Handout PI#(s): , County: Muscogee

Project Description: Georgia Department of Transportation Public Information Open House Handout PI#(s): , County: Muscogee Why We Are Here: GDOT s Transportation Improvement Act (TIA) Office, the City of Columbus, and the project delivery team are here this evening to display and answer questions concerning the proposed roadway

More information

Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study

Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study FROM MICHIGAN AVENUE TO INDUSTRY ROAD BREVARD COUNTY, FLORIDA Financial Project ID No: 433605-1-22-01 Federal Aid Project

More information

2040 Metropolitan Transportation Plan -- Table XVII-1

2040 Metropolitan Transportation Plan -- Table XVII-1 C:\7. \Projects\ 2040MTP Project List_Nov16-16.xlsx ID # NAME LIMITS DESCRIPTION COST () AGENCY PROJECT TYPE* 2017 1 B Dr S and Capital Ave SW B Dr S from 3.5 Mile Rd eastward to M-66 (1.7 mi); Capital

More information

Richmond Area MPO Regional Priority Transportation Projects

Richmond Area MPO Regional Priority Transportation Projects Regional Priority Transportation Projects September 27, 2007 HANOVER GOOCHLAND ASHLAND POWHATAN RICHMOND HENRICO NEW KENT CHESTERFIELD CHARLES CITY 9211 Forest Hill Avenue, Suite 200 Richmond, Virginia

More information

Rocky Mount. Transportation Plan. Transportation Planning Division. Virginia Department of Transportation

Rocky Mount. Transportation Plan. Transportation Planning Division. Virginia Department of Transportation 2020 Transportation Plan Developed by the Transportation Planning Division of the Virginia Department of Transportation in cooperation with the U.S. Department of Transportation, Federal Highway Administration

More information

NASHVILLE AREA MPO FY TIP - ADOPTED DECEMBER

NASHVILLE AREA MPO FY TIP - ADOPTED DECEMBER WILLIAMSON/ MAURY NASHVILLE AREA MPO FY -2017 TIP - ADOPTED DECEMBER 11, 2013 SR-247 (Duplex Road) Widening TIP # 2004-051 Road Widening Spring Hill Williamson Length 3.10 Regional Plan ID 1062-170 Air

More information

EXCEPTION TO STANDARDS REPORT

EXCEPTION TO STANDARDS REPORT EXCEPTION TO STANDARDS REPORT PROJECT DESCRIPTION AND NEED The project is located in Section 6, Township 23 North, Range 9 East and Section 31 Township 24 North, Range 9 East, in the Town of Stockton,

More information

ITEM 13 - NOTICE May 20, 2009

ITEM 13 - NOTICE May 20, 2009 ITEM 13 - NOTICE May 20, 2009 Notice of Proposed Amendment to the 2009 CLRP and FY 2010-2015 TIP to include the Closure of the I-395 Southbound Exit Ramp to 3rd Street NW, the Reconfiguration of the Southbound

More information

Maryland Gets to Work

Maryland Gets to Work I-695/Leeds Avenue Interchange Reconstruction Baltimore County Reconstruction of the I-695/Leeds Avenue interchange including replacing the I-695 Inner Loop bridges over Benson Avenue, Amtrak s Northeast

More information

Northeast Pavement Preservation Partnership Burlington, Vermont. Rhode Island DOT

Northeast Pavement Preservation Partnership Burlington, Vermont. Rhode Island DOT Northeast Pavement Preservation Partnership Burlington, Vermont Rhode Island DOT April 8, 2014 SHRP2 R26 (Preservation of High-Traffic Volume Roadways) and MAP-21 Impacts to RIDOT Pavement Management David

More information

Utility work, road construction substantially done on Fourth Street

Utility work, road construction substantially done on Fourth Street November 2010 Fourth Street in downtown is reopen to vehicle traffic between Minnesota and Broadway streets. Utility relocation and road construction are substantially complete there. Utility work, road

More information

Wednesday, April 20, 2016

Wednesday, April 20, 2016 Wednesday, April 20, 2016 MARCH 2015-MARCH 2016 REVENUE VARIANCE % CHANGE $8.6 4.3% $1.7 2.7% -$0.8-6.1% $0.3 6.3% $-21.3-53.4% $1.7 73.9% $-0.6 5.0% $-10.4-3.3% $365.0 $315.0 $311.2 $300.8 $265.0 $215.0

More information

Tulsa Transportation Management Area. Urbanized Area Surface Transportation Program

Tulsa Transportation Management Area. Urbanized Area Surface Transportation Program Tulsa Transportation Management Area Urbanized Area Surface Transportation Program FFY 2022 Application Information Sponsor Location Description STP Request Other Funds Broken Arrow Elm Place: Kenosha

More information

TABLE OF CONTENTS EXECUTIVE SUMMARY...1 INTRODUCTION...3 PROJECTED FUTURE GROWTH...3 ROADWAY IMPROVEMENT PROJECTS...4 POTENTIAL FUNDING SOURCES...

TABLE OF CONTENTS EXECUTIVE SUMMARY...1 INTRODUCTION...3 PROJECTED FUTURE GROWTH...3 ROADWAY IMPROVEMENT PROJECTS...4 POTENTIAL FUNDING SOURCES... Transportation Impact Fee Study September 2014 TABLE OF CONTENTS EXECUTIVE SUMMARY...1 INTRODUCTION...3 PROJECTED FUTURE GROWTH...3 ROADWAY IMPROVEMENT PROJECTS......4 POTENTIAL FUNDING SOURCES...7 PROPOSED

More information

City of Grand Forks Staff Report

City of Grand Forks Staff Report City of Grand Forks Staff Report Committee of the Whole December 1, 016 City Council December 19, 016 Agenda Item: Bids for City Project No. 7551 Lift Station No. 17 & 17A Rehabilitation Submitted by:

More information

Plan Check Policies and Guidelines

Plan Check Policies and Guidelines VIII. TRAFFIC SIGNING AND STRIPING PLANS A. INTRODUCTION Traffic signing and striping plans are required for all General Plan Roads and any roadway that is 56-foot wide curb-to-curb (78 R/W) or wider.

More information

LACEY CITY COUNCIL MEETING July 09, 2015

LACEY CITY COUNCIL MEETING July 09, 2015 LACEY CITY COUNCIL MEETING July 09, 2015 SUBJECT: 2016-2021 Six-Year Transportation Improvement Plan and Mitigation List RECOMMENDATION: Adopt Resolution approving the proposed 2016-2021 Six- Year Transportation

More information

PUBLIC INFRASTRUCTURE PROJECTS

PUBLIC INFRASTRUCTURE PROJECTS PUBLIC INFRASTRUCTURE PROJECTS FM 664 / OVILLA ROAD WIDENING & IMPROVEMENTS FM 664 / OVILLA ROAD CONNECTS US 287 WITH I-45 (SOURCE: TEXAS DEPARTMENT OF TRANSPORTATION. 2016 FM 664 / OVILLA ROAD WIDENING

More information

PUBLIC WORKS DEPARTMENT DECEMBER 2017 UPDATE DESIGN & CONSTRUCTION DIVISION

PUBLIC WORKS DEPARTMENT DECEMBER 2017 UPDATE DESIGN & CONSTRUCTION DIVISION TESTER ROAD WATER MAIN UPGRADE PUBLIC WORKS DEPARTMENT DECEMBER 2017 UPDATE DESIGN & CONSTRUCTION DIVISION The City will be replacing an aging water main under Tester Road this year. The project will begin

More information

Plan Check Policies and Guidelines

Plan Check Policies and Guidelines Plan Check Policies and Guidelines VII. A. INTRODUCTION Traffic signing and striping plans are required for all General Plan Roads and any roadway that is 56-foot wide curb-to-curb (78 R/W) or wider. Transportation

More information

Interstate 85 Widening Phase III Interchange Modification Report Exit 106 E. Cherokee Street. Cherokee County, SC

Interstate 85 Widening Phase III Interchange Modification Report Exit 106 E. Cherokee Street. Cherokee County, SC Interstate 85 Widening Phase III Interchange Modification Report Exit 16 E. Cherokee Street Cherokee County, SC Prepared for: South Carolina Department of Transportation Prepared by: Stantec Consulting

More information

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE DOYLE DRIVE DOYLE DRIVE. Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE DOYLE DRIVE DOYLE DRIVE. Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009 DOYLE DRIVE Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009 Presentation Overview Introduction Project Acceleration Construction Contracts Construction Activities Lane and Road

More information

Characterization of Combined Use of County Road Segment

Characterization of Combined Use of County Road Segment Department of Public Works Inyo County, California Characterization of Combined Use of County Road Segment Segment Name: _Lone Pine No. 1_ Purpose: Which of the following does the combined-use segment

More information

June WASHINGTON STATE DEPARTMENT OF TRANSPORTATION Alaskan Way Viaduct and Seawall Replacement Program Seattle, Washington

June WASHINGTON STATE DEPARTMENT OF TRANSPORTATION Alaskan Way Viaduct and Seawall Replacement Program Seattle, Washington DESIGN DEVIATION NOs. 1 & 2 Horizontal Stopping Sight Distance and Shoulder Width Reduction SR 99 S. Holgate St to S. King St. Viaduct Replacement Stage 2 MP 29.89 TO MP 30.78 XL-3237 PIN-809936D June

More information

Western ND Meeting. February 19, 2014 Grant Levi, NDDOT Director

Western ND Meeting. February 19, 2014 Grant Levi, NDDOT Director Western ND Meeting February 19, 2014 Grant Levi, NDDOT Director 1 Traffic Trends in North Dakota 2 Truck Traffic 2008 3 Truck Traffic 2012 4 Average Daily Traffic 5 ND Vehicle Miles Traveled Statewide

More information

Information Postings

Information Postings For Details, Contact:. Information Postings Matt Hammond mhammond@scana.com Phone (803) 217-2175 Date of Subject of Posting Posting 08/24/2016 In order to provide the necessary infrastructure to carry

More information

Interstate 85 Widening Traffic Analysis Report

Interstate 85 Widening Traffic Analysis Report I-85 Widening Project MM80 MM96 Spartanburg and Cherokee Counties Submitted to: South Carolina Department of Transportation Prepared By: STV Incorporated 140 Stoneridge Drive, Suite 450 Columbia, SC 29210

More information

Appendix F. Local Project Costs

Appendix F. Local Project Costs Appendix F Local Project Costs Appendix F contains several project lists to help demonstrate how fiscal constraint was established and provide additional information on highway and transit program costs.

More information

ODOT District Two Monthly Construction Update

ODOT District Two Monthly Construction Update Ohio Department of Transportation Construction Update DISTRICT 2 KIRK SLUSHER, P.E., ACTING DEPUTY DIRECTOR 317 East Poe Rd. Bowling Green, Ohio 43402-1330 www.transportation.ohio.gov/dist2 ODOT District

More information

Kentucky Highway District 6

Kentucky Highway District 6 Kentucky Highway District 6 ROAD AND BRIDGE CONDITIONS, TRAFFIC SAFETY, TRAVEL TRENDS, AND NEEDS MARCH 2018 PREPARED BY WWW.TRIPNET.ORG Founded in 1971, TRIP of Washington, DC, is a nonprofit organization

More information

Chapter 9 Recommended Locally Preferred Alternative and Alternatives for Evaluation in Draft SEIS/SEIR

Chapter 9 Recommended Locally Preferred Alternative and Alternatives for Evaluation in Draft SEIS/SEIR Chapter 9 Recommended Locally Preferred Alternative and Alternatives for Evaluation in Draft SEIS/SEIR 9.0 RECOMMENDED LOCALLY PREFERRED ALTERNATIVE AND ALTERNATIVES FOR EVALUATION IN DRAFT SEIS/SEIR

More information

Richmond Area MPO Regional Priority Transportation Projects

Richmond Area MPO Regional Priority Transportation Projects Regional Priority Transportation Projects October 12, 2006 Town of Ashland Counties of Charles City Chesterfield Goochland Hanover Henrico New Kent Powhatan City of Richmond Richmond Regional Planning

More information

Prince William County Department of Transportation 1st Quarter Joint Mobility Report March 13, 2018

Prince William County Department of Transportation 1st Quarter Joint Mobility Report March 13, 2018 Prince William County Department of Transportation 1st Quarter Joint Mobility Report March 13, 2018 Burwell Road (Rural Rustic) Plans were submitted to VDOT and PWC for review and comment on December 11,

More information

Kentucky Highway District 1

Kentucky Highway District 1 Kentucky Highway District 1 ROAD AND BRIDGE CONDITIONS, TRAFFIC SAFETY, TRAVEL TRENDS, AND NEEDS FEBRUARY 2018 PREPARED BY WWW.TRIPNET.ORG Founded in 1971, TRIP of Washington, DC, is a nonprofit organization

More information

Middle Georgia Transportation Executive Committee. September 27, 2017

Middle Georgia Transportation Executive Committee. September 27, 2017 Middle Georgia Transportation Executive Committee September 27, 2017 Project Discussions MACON BIBB, CRAWFORD, MONROE Project List Development Process to Date Cities, Counties and MPOs submitted projects

More information

Open House. Highway212. Meetings. Corridor Access Management, Safety & Phasing Plan. 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition

Open House. Highway212. Meetings. Corridor Access Management, Safety & Phasing Plan. 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition Welcome Meetings 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition 6:30 to 8:00 p.m. - Open House Why is Highway 212 Project Important? Important Arterial Route Local Support Highway 212

More information

INDIANA DEPARTMENT OF TRANSPORTATION PAGE 1 NOTICE TO HIGHWAY CONTRACTORS

INDIANA DEPARTMENT OF TRANSPORTATION PAGE 1 NOTICE TO HIGHWAY CONTRACTORS INDIANA DEPARTMENT OF TRANSPORTATION PAGE 1 NOTICE TO HIGHWAY CONTRACTORS DATE OF LETTING: March 04, 2015 TIME OF LETTING: 10:00 AM EASTERN STD DESIGN BUILD CONTRACTS Sealed proposals for certain highway

More information

PALM BEACH COUNTY FIVE YEAR ROAD PROGRAM - EXHIBIT A

PALM BEACH COUNTY FIVE YEAR ROAD PROGRAM - EXHIBIT A Page 1 of 5 PALM BEACH COUNTY FIVE YEAR ROAD PROGRAM - EXHIBIT A FY 2017 TOTAL BUDGETED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED Local Option Gas Taxes Total 49,679,000 49,679,000 49,679,000

More information

Anderson Area Transportation Study ANATS Transportation Improvement Plan FY

Anderson Area Transportation Study ANATS Transportation Improvement Plan FY Anderson Area Transportation Study ANATS Transportation Improvement Plan FY 2017-2022 www.cityofandersonsc.com Table of Contents Introduction 1 Process 2 Products 3 Funding 4 Certification 6 Financial

More information

Light Emitting Diode (LED) Induction

Light Emitting Diode (LED) Induction February 8 8, 2011 DOE awarded the City $491,000 EECBG in 2009 In December 2010, Council authorized reallocating $85,000 from the Financial Incentive Program to the Streetlight Conversion Program $382,000

More information

US 10 Corridor Performance

US 10 Corridor Performance Corridor Context The corridor runs northwest 18 miles from I-35W to the edge of Anoka County. The corridor connects the cities of Ramsey, Anoka,, Mounds View, and Blaine. Current Corridor Characteristics

More information

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237)

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) W&OD TRAIL BRIDGE OVER LEE HIGHWAY A COMPONENT OF THE I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) October 11, 2018 Bill Cuttler, PE

More information

NEWCASTLE MIDDLE SCHOOL Traffic Impact Analysis

NEWCASTLE MIDDLE SCHOOL Traffic Impact Analysis Gibson Traffic Consultants 2802 Wetmore Avenue Suite 220 Everett, WA 98201 425.339.8266 NEWCASTLE MIDDLE SCHOOL Traffic Impact Analysis Prepared for: Renton School District Jurisdiction: City of Newcastle

More information

Harlem Avenue between 63 rd and 65 th

Harlem Avenue between 63 rd and 65 th Harlem Avenue between 63 rd and 65 th Public Meeting #2 March 13, 2018 Summit Park District Welcome to the second Public Meeting for the preliminary engineering and environmental studies of Illinois 43

More information

ODOT District Two Monthly Construction Update

ODOT District Two Monthly Construction Update Ohio Department of Transportation Construction Update DISTRICT 2 KIRK SLUSHER, P.E., ACTING DEPUTY DIRECTOR 317 East Poe Rd. Bowling Green, Ohio 43402-1330 www.transportation.ohio.gov/dist2 ODOT District

More information

CY 2013 and CY 2014 NOVA District Advertisement Schedule Design-Bid-Build

CY 2013 and CY 2014 NOVA District Advertisement Schedule Design-Bid-Build 1 2013 Planned s System Route UPC Category Locality Project Description 395 98836 Bridge Arlington Clean/Re-Paint 7 Bridges I-395 Corridor Arlington/Alexandria 4/9/2013 $ 3.45 HOT Lanes Bicycle/Pedestrian

More information

Workshop Agenda. Bransford Roundabout. Bedford Intersection/Roundabout. Section 3 Revisions (Left turn lanes) Roadway Section/Curb Type Discussion

Workshop Agenda. Bransford Roundabout. Bedford Intersection/Roundabout. Section 3 Revisions (Left turn lanes) Roadway Section/Curb Type Discussion Workshop Agenda Bransford Roundabout Bedford Intersection/Roundabout Section 3 Revisions (Left turn lanes) Roadway Section/Curb Type Discussion Project Phasing Summary of Recommendation Purpose: Provide

More information

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What

More information