Guam Transportation Program Project Updates. Joanne M.S. Brown Director Carl Dominguez Deputy Director February 6, 2012

Size: px
Start display at page:

Download "Guam Transportation Program Project Updates. Joanne M.S. Brown Director Carl Dominguez Deputy Director February 6, 2012"

Transcription

1 Guam Transportation Program Project Updates Joanne M.S. Brown Director Carl Dominguez Deputy Director February 6, 2012

2 Agenda Road Construction Highlights Ongoing Construction Route 17 Rehabilitation and Widening Route 7A Resurfacing & Pavement Rehabilitation Planning & Design Route 1 / Route 8 Intersection Improvements & Agana Bridges Replacement (Design-Build) Tiyan Parkway Guam Transportation Improvement Plan

3 18 projects worth $102 million are under construction, 11 of which will be complete by June 2012 Asphalt base course and friction course pavements that meet all federal requirements are now being produced Working to streamline: Roadway Construction Highlights Contract and Change Order Approval Process Building Permit Approval Process Payment Review and Processing

4

5 Route 17 Resurfacing Scope of Work: reconstruct and widen from Route 4 to Route 4A, including drainage and four foot shoulders Contractor: Sumitomo Mitsui Construction Management: TG Engineers Cost: $5.6 million

6 Route 17 Resurfacing Base Course pavement has been completed on about 90% of the project Utility relocations underway at the hairpin curve Expected completion: June 2012

7 Route 7A Pavement Rehabilitation

8 Route 7A Pavement Rehabilitation Contractor: Sumitomo Mitsui Construction Co. Scope of Work: Pavement Reconstruction Route 4 to Route 8 Major drainage system upgrades Replacement of approaches at Mindoro Bridge from asphalt to concrete New sidewalks, curbs and gutters Return to two-way traffic: May 2012 Expected project completion: October 2012

9

10 Featured Projects Planning-Design Route 1 / Route 8 Intersection Improvements & Agana Bridges Replacement (Design-Build) Tiyan Parkway Transportation Improvement Plan

11 Route 1 / Route 8 Intersection Improvements & Agana Bridges Replacement (Design-Build) Agana Bridge #2 Chalan Santo Papa Juan Pablo Dos Agana Bridge #1 Route 1 (Marine Corps Drive)

12

13 Route 1 / Route 8 Intersection Improvements & Agana Bridges Replacement (Design-Build) Project Information Contractor: CoreTech International Cost: Project Start: October 2011 $16.4 million Jointly funded by FHWA & DOD Completion: December 2013

14 Route 1 / Route 8 Intersection Improvements & Agana Bridges Replacement (Design-Build) Project Timeline Final Design/Permits: October 2011 May 2012 Preliminary Site Work: February April 2012 Rte 1 / Rte 8 & Bridge #1 April 2012 June 2013 Construction (3-phase) Bridge #2 Construction: June 2013 December 2013 *Dates are approximate and subject to change.

15 Route 1 / Route 8 Intersection Improvements & Agana Bridges Replacement (Design-Build) PHASE 1 PHASE 2 PHASE 3 Construction Sequence & Traffic Control Agana Bridge #1

16 Tiyan Parkway Rte10A Rte 1 East Sunset Blvd Rte 8 Rte16 Existing Entrance to Tiyan from Rte 8 Rte10 Existing Road Network

17 Tiyan Parkway Central Avenue & other roads to be Closed Gates on Route 8 to be Closed Existing Traffic Signal GIAA Road Closure Points

18 Tiyan Parkway Alignment Alternate 4

19 Tiyan Parkway Right-of-Way Acquisition Plan DPW owns no right-of-way at Tiyan Phase 1 ROW to be acquired from GIAA using FHWA funds (avoidance of cliff line retaining walls) Phase 1 sale is contingent on assurances that Phase 2 ROW will be re-acquired by the Government DPW is working cooperatively with GIAA, DLM and the Governor s office on the Phase 2 ROW acquisition plan

20 Tiyan Parkway Phase 1 Project Information Designer: Est. ROW Cost: Est. Const. Cost: Duenas Camacho & Associates $5.6 million $9.9 million Design Start: April 2012 Completion: December 2012

21 Tiyan Parkway Project Timeline Phase 1 NEPA Clearance: June 2012 Final Design: April 2012 December 2012 ROW Acquisition: April 2012 September 2012 Bid/Award/Permit: January 2013 August 2013 Construction: September 2013 June 2014 GIAA Road Closures: February 2013 or TBD *Dates are approximate and subject to change.

22 Guam Transportation Improvement Plan Guam TIP is a four year financially constrained plan required by federal statute Draft TIP has been developed Primary fund source is approximately $18.4M a year from the Federal Highway Administration GARVEE bond is under consideration to leverage and accelerate FHWA funding No DOD funding in the plan

23 Guam Transportation Improvement Plan Construction Projects (Draft Plan) Project Construction Value Route 17 Phase 2A Drainage Culverts $1,610,000 Route 4 Agfayan Bridge Replacement $3,595,000 Bile & Pigua Bridges Replacement $2,532,000 Route 4 Merizo Bridge Roadway Restoration Traffic Signal System Upgrade - Islandwide $1,208,000 $1,779,000 Traffic Mgt Center - Communications $2,042,000 Route 4 Inarajan North Leg Bridge Repair $2,392,000 Continued Next Slide

24 Guam Transportation Improvement Plan Construction Projects (Draft Plan) Project Construction Value Route 4 Togcha River to Ipan Beach Park $630,000 Route 3A Extension, Jinapsan Access $2,415,000 Rte 1 Bridge Rehab Asan & Aguada Rivers $1,380,000 ADA Compliance $1,510,000 Route 4 Merizo Creek Culvert Replacement $1,725,000 TOTAL $22,818,000

25 Si Yu us Ma ase For more information visit:

Wentzville Parkway South Phase 2 & 2A

Wentzville Parkway South Phase 2 & 2A Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total

More information

BINGHAMTON METROPOLITAN TRANSPORTATION STUDY

BINGHAMTON METROPOLITAN TRANSPORTATION STUDY BINGHAMTON METROPOLITAN TRANSPORTATION STUDY ANNUAL LISTING OF FEDERAL AID PROJECT OBLIGATIONS FEDERAL FISCAL YEAR Federal regulations require an annual listing of transportation projects, including investments

More information

SC Highway 41 Existing Conditions

SC Highway 41 Existing Conditions SC Highway 41 Existing Conditions Existing Typical Cross Section purposes only and does not replace the required NEPA process necessary for alignment The NEPA process is anticipated to begin in the next

More information

SAINT CHARLES COUNTY ROAD BOARD Minutes of March 21, 2018

SAINT CHARLES COUNTY ROAD BOARD Minutes of March 21, 2018 SAINT CHARLES COUNTY ROAD BOARD Minutes of March 21, 2018 The Wednesday, March 21, 2018, meeting of the St. Charles County Road Board was called to order at 4:30 p.m. in Room 542 of the Administration

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

Municipal Road and Bridge Revolving Loan Fund Program Summary Rhode Island Department of Transportation

Municipal Road and Bridge Revolving Loan Fund Program Summary Rhode Island Department of Transportation Municipal Road and Bridge Revolving Loan Fund 2014 Program Summary Rhode Island Department of Transportation The Basics The FY2014 Budget passed by the Rhode Island General Assembly included Article 20,

More information

S.M. Wright Project (I-45, US 175, SH 310) and Road to Work Opportunity Program. Transportation and Trinity River Project Committee May 23, 2016

S.M. Wright Project (I-45, US 175, SH 310) and Road to Work Opportunity Program. Transportation and Trinity River Project Committee May 23, 2016 635 S.M. Wright Project (I-45, US 175, SH 310) and Road to Work Opportunity Program Transportation and Trinity River Project Committee May 23, 2016 Project Scope Increase safety by removing the existing

More information

ODOT District Two Monthly Construction Update

ODOT District Two Monthly Construction Update Ohio Department of Transportation Construction Update DISTRICT 2 KIRK SLUSHER, P.E., ACTING DEPUTY DIRECTOR 317 East Poe Rd. Bowling Green, Ohio 43402-1330 www.transportation.ohio.gov/dist2 ODOT District

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 2/19/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

800 Access Control, R/W Use Permits and Drive Design

800 Access Control, R/W Use Permits and Drive Design Table of Contents 801 Access Control... 8-1 801.1 Access Control Directives... 8-1 801.2 Access Control Policies... 8-1 801.2.1 Interstate Limited Access... 8-1 801.2.2 Limited Access... 8-1 801.2.3 Controlled

More information

Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study

Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study FROM MICHIGAN AVENUE TO INDUSTRY ROAD BREVARD COUNTY, FLORIDA Financial Project ID No: 433605-1-22-01 Federal Aid Project

More information

April 27, FHWA/FTA Approval of an Amendment to the Kansas STIP to include WAMPO s April 14, 2009 TIP Amendment 6

April 27, FHWA/FTA Approval of an Amendment to the Kansas STIP to include WAMPO s April 14, 2009 TIP Amendment 6 U.S. Department of Transportation Federal Transit Administration Federal Highway Administration 901 Locust Street, Suite 404 6111 SW 29 th Street, Suite 100 Kansas City, MO 64106 Topeka, KS 66614-4271

More information

ODOT District Two Monthly Construction Update

ODOT District Two Monthly Construction Update Ohio Department of Transportation Construction Update DISTRICT 2 KIRK SLUSHER, P.E., ACTING DEPUTY DIRECTOR 317 East Poe Rd. Bowling Green, Ohio 43402-1330 www.transportation.ohio.gov/dist2 ODOT District

More information

Public Information Workshop

Public Information Workshop Public Information Workshop Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 29, 2018 Welcome to the Public Information Workshop for Harborview Road Project Development and Environment (PD&E)

More information

CAPITAL FUND 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS

CAPITAL FUND 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS 2019-2023 9510 STREET & SIDEWALK IMPROVEMENTS - 01 STREET AND SIDEWALK MAINTENANCE PROGRAM $1,250,000 $0 $1,250,000

More information

City Hall 539 Phoenix Street South Haven, Michigan Telephone (269) Fax (269)

City Hall 539 Phoenix Street South Haven, Michigan Telephone (269) Fax (269) City of South Haven City Hall 539 Phoenix Street South Haven, Michigan 49090-1499 Telephone (269) 637-0700 Fax (269) 637-5319 Dunkley and Black River Infrastructure Improvements Dunkley - Dyckman Avenue

More information

St. Johns River State College BID-SJR Addendum Three ADDENDUM THREE DATED JUNE 13, 2016

St. Johns River State College BID-SJR Addendum Three ADDENDUM THREE DATED JUNE 13, 2016 St. Johns River State College BID-SJR-10-2016 Addendum Three ADDENDUM THREE DATED JUNE 13, 2016 TO BID-SJR-10-2016 Bid Specifications/Project Manual (Plans) PARKING LOT REHABILITATION PROJECT FOR: DRAWING

More information

Section III Transportation and Stormwater Projects Receiving Additional Funding Project Detail Sheets Alphabetical Listing by Project Name Five Year

Section III Transportation and Stormwater Projects Receiving Additional Funding Project Detail Sheets Alphabetical Listing by Project Name Five Year Section III Transportation and Stormwater Projects Receiving Additional Funding Project Detail Sheets Alphabetical Listing by Project Name Five Year Capital Improvement Plan FY2015/2016 through FY2020

More information

Rolling Road (Route 638) Widening Project

Rolling Road (Route 638) Widening Project Rolling Road (Route 638) Widening Project From: 0.369 Mile North of Fairfax County Parkway (Route 286) To: Old Keene Mill Road (Route 644) State Project No. 0638-029-156, P104, R204, C504; UPC 5559 Public

More information

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237)

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) W&OD TRAIL BRIDGE OVER LEE HIGHWAY A COMPONENT OF THE I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) October 11, 2018 Bill Cuttler, PE

More information

ITEM 13 - NOTICE May 20, 2009

ITEM 13 - NOTICE May 20, 2009 ITEM 13 - NOTICE May 20, 2009 Notice of Proposed Amendment to the 2009 CLRP and FY 2010-2015 TIP to include the Closure of the I-395 Southbound Exit Ramp to 3rd Street NW, the Reconfiguration of the Southbound

More information

Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction

Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction 550 North to 650 North $ 1,750,000 $ 1,582,113 To widen an existing bridge on 1200 West over Box Elder Creek that will

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate

More information

Tulsa Transportation Management Area. Urbanized Area Surface Transportation Program

Tulsa Transportation Management Area. Urbanized Area Surface Transportation Program Tulsa Transportation Management Area Urbanized Area Surface Transportation Program FFY 2022 Application Information Sponsor Location Description STP Request Other Funds Broken Arrow Elm Place: Kenosha

More information

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014 Arterial Bus Rapid Transit System Policy Oversight Committee April 7, 2014 1 Meeting Agenda Welcome and Introductions A Line - Project Status Shelter and Pylon Development Arterial BRT Branding Update

More information

DRIVEWAY/SIDEWALK PERMIT APPLICATION

DRIVEWAY/SIDEWALK PERMIT APPLICATION JOB INFORMATION CITY OF ALEXANDRIA 704 Broadway Alexandria, MN 56308 Phone: 320-763-6678 Fax: 320-763-3511 DRIVEWAY/SIDEWALK PERMIT APPLICATION Permit Fee: $50.00 Deposit: $300.00 PERMIT NUMBER: ROW DATE:

More information

CITY OF PORT TOWNSEND, WASHINGTON CAPITAL IMPROVEMENT PLAN

CITY OF PORT TOWNSEND, WASHINGTON CAPITAL IMPROVEMENT PLAN Page 1 of 3 CITY OF PORT TOWNSEND, WASHINGTON CAPITAL IMPROVEMENT PLAN The six-year Capital Improvement Plan (CIP) includes capital projects for 2017 2022. This plan includes capital projects that add

More information

Exposition Corridor Transit Project

Exposition Corridor Transit Project Exposition Corridor Transit Project Phase 2 Environmental Planning Community Meeting June 9, 2008 Exposition Corridor Transit Project Phase 2 AGENDA Remaining Grade Crossing Recommendations June 9, 2008

More information

Clarksville Street Department. Fiscal Year 2018 Budget Presentation

Clarksville Street Department. Fiscal Year 2018 Budget Presentation Clarksville Street Department Fiscal Year 2018 Budget Presentation Clarksville Street Department FY 2018 Proposed Budget 4.2% 42.0% Salaries/Benefits 53.8% Operating Expenses Capital Outlay Clarksville

More information

Status Report on Bridges and Roads Repair/Renovations

Status Report on Bridges and Roads Repair/Renovations Basis FOR Analysis Compliance with the Clean Water Act as set forth in a Consent Decree approved by the U.S. District Court of Guam in February 2004 Layon site selected by Government of Guam and approved

More information

January 13, 2012 AACE Annual Meeting, Wickenburg, AZ. I-15 in Arizona. Its Past, Present, and Future

January 13, 2012 AACE Annual Meeting, Wickenburg, AZ. I-15 in Arizona. Its Past, Present, and Future January 13, 2012 AACE Annual Meeting, Wickenburg, AZ I-15 in Arizona. Its Past, Present, and Future Jean A. Nehme, Ph.D., P.E. State Bridge Engineer, ADOT Presentation Overview Location, History, and Photographs

More information

Public Works. Capital Projects FY

Public Works. Capital Projects FY Public Works Capital Projects FY 2015-17 Projects Completed FY 2014 All Done Projects! Residential and Collector Street Paving Lower Westside Arterial Street Rehab: Front, River St South, Soquel Hwy 1

More information

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007 EAST-WEST CORRIDOR Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007 Presentation Agenda Project Overview / Purpose and Need Highway Component Transit Component

More information

5. HORIZON YEAR TRANSPORTATION MASTER PLAN-COST ESTIMATES

5. HORIZON YEAR TRANSPORTATION MASTER PLAN-COST ESTIMATES 5. HORIZON YEAR TRANSPORTATION MASTER PLAN-COST ESTIMATES 5.1 INTRODUCTION This chapter of the TMP presents an opinion of probable cost estimates for the proposed Horizon Year roadway network improvements

More information

I-820 (East) Project Description. Fort Worth District. Reconstruct Southern I-820/SH 121 Interchange

I-820 (East) Project Description. Fort Worth District. Reconstruct Southern I-820/SH 121 Interchange I-820 (East) Project Description Fort Worth District Reconstruct Southern I-820/SH 121 Interchange I-820 from approximately 2,000 feet north of Pipeline Road/Glenview Drive to approximately 3,200 feet

More information

CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE

CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE TUESDAY, DECEMBER 5, 2017 1 DISCUSSION TOPICS Update of Infrastructure Action Plan (IAP) o Sidewalk and Roadway projects

More information

Exhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup

Exhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Exhibit A Sound Transit Board Resolution R2016-07 Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Access Improvement Project. RESOLUTION NO. R2016-07 Selecting

More information

I-4 Beyond the Ultimate. Florida Transportation Builders Association January 18, 2019

I-4 Beyond the Ultimate. Florida Transportation Builders Association January 18, 2019 I-4 Beyond the Ultimate Florida Transportation Builders Association January 18, 2019 FDOT District 5 Improving Mobility & Safety in Central Florida FDOT District 5 is: Designing and building a better Interstate

More information

Expo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011

Expo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011 Project Status Update Meeting Project Status Update Meeting Holman United Methodist Church January 27, 2011 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor

More information

I-405 Sepulveda Pass Improvements Project

I-405 Sepulveda Pass Improvements Project I-405 Sepulveda Pass Improvements Project Community Meeting November 15, 2012 1 Wilshire Segment Overview of Wilshire Segment There are a total of 23 bridges being constructed on this project; almost half

More information

Update on Transportation Activities in Fairfax County

Update on Transportation Activities in Fairfax County Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation Association June 13, 2018 Tom Biesiadny, Director Fairfax County Continuing Project Implementation

More information

Chicago to St. Louis High-Speed Rail. IDOT District 8 Crossings. July 29, 2015

Chicago to St. Louis High-Speed Rail. IDOT District 8 Crossings. July 29, 2015 Chicago to St. Louis High-Speed Rail IDOT District 8 Crossings July 29, 2015 1 History: Chicago-St. Louis Corridor» IDOT has actively developed the Chicago to St. Louis corridor since the mid 1980 s» In

More information

PARKING LOT REHABILITATION PROJECT FOR: SJRSC PALATKA CAMPUS

PARKING LOT REHABILITATION PROJECT FOR: SJRSC PALATKA CAMPUS PARKING LOT REHABILITATION PROJECT FOR: DRAWING INDE SHEET NO. DRAWING TITLE C. COVER SHEET C1. - C1.17 PALATKA CAMPUS C4. CONSTRUCTION DETAILS PROJECT SITE PROJECT SITE C. 8 4 8 16 32 1 inch = 8 ft. C1.16

More information

Aurora Line/I-225 Rail Project Update Public Meeting. June 4, 2014

Aurora Line/I-225 Rail Project Update Public Meeting. June 4, 2014 Aurora Line/I-225 Rail Project Update Public Meeting June 4, 2014 FasTracks and I-225 Rail Line Update Danielle Smith I-225 Rail Line Design/Build Coordination Manager 2 The RTD FasTracks Plan 122 miles

More information

Building our future, together. Steering Committee Presentation for the Comprehensive Plan Update April 23, 2013

Building our future, together. Steering Committee Presentation for the Comprehensive Plan Update April 23, 2013 Building our future, together Steering Committee Presentation for the Comprehensive Plan Update April 23, 2013 Vision In 2030, the City of Tyler will be nationally known for its commitment to community,

More information

EXCEPTION TO STANDARDS REPORT

EXCEPTION TO STANDARDS REPORT EXCEPTION TO STANDARDS REPORT PROJECT DESCRIPTION AND NEED The project is located in Section 6, Township 23 North, Range 9 East and Section 31 Township 24 North, Range 9 East, in the Town of Stockton,

More information

PUBLIC WORKS DEPARTMENT DECEMBER 2017 UPDATE DESIGN & CONSTRUCTION DIVISION

PUBLIC WORKS DEPARTMENT DECEMBER 2017 UPDATE DESIGN & CONSTRUCTION DIVISION TESTER ROAD WATER MAIN UPGRADE PUBLIC WORKS DEPARTMENT DECEMBER 2017 UPDATE DESIGN & CONSTRUCTION DIVISION The City will be replacing an aging water main under Tester Road this year. The project will begin

More information

DART Priorities Overview

DART Priorities Overview City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee

More information

CITY OF OAKLAND INTRODUCTION

CITY OF OAKLAND INTRODUCTION CITY OF OAKLAND CITY HALL ONE FRANK OGAWA PLAZA 3RD FLOOR OAKLAND CA 94612 City Administrator s ADA Programs Division (510) 238-4754 TDD: (510) 238-2007 : January 4, To: Mayor s Commission on Persons with

More information

Expo Light Rail Line. Expo Line Project Westside/Central Metro Service Council November 2014

Expo Light Rail Line. Expo Line Project Westside/Central Metro Service Council November 2014 Expo Line Project Westside/Central Metro Service Council November 2014 2 Expo Line Project Description Phase 2 Expo Line from Culver City to Santa Monica: 6.6 mile corridor 7 new Stations 64,000 Daily

More information

MIAMI-DADE TRANSPORTATION PLANNING ORGANIZATION TRANSPORTATION IMPROVEMENT PROGRAM MIAMI-DADE DEPT OF TRANSPORTATION AND PUBLIC WORKS

MIAMI-DADE TRANSPORTATION PLANNING ORGANIZATION TRANSPORTATION IMPROVEMENT PROGRAM MIAMI-DADE DEPT OF TRANSPORTATION AND PUBLIC WORKS TPO Facility/ Name Prior s Detailed Description TA000100 MDT - DADE / MONROE EXPRESS BUS ROUTE COMMUTER TRANS ASSISTANCE C-6 $12,978 $7,385 4180513, 4409141 Operating assistance of Dade/Monroe Express

More information

City of Grand Forks Staff Report

City of Grand Forks Staff Report City of Grand Forks Staff Report Service/Safety Committee December 15, 2015 City Council December 21, 2015 Agenda Item: Amendment No. 1 to Engineering Services Agreement with CPS for City Project No. 7143,

More information

Task Force Meeting January 15, 2009

Task Force Meeting January 15, 2009 Task Force Meeting January 15, 2009 Study Update August 14 th Task Force Meeting Update on Traffic Projections and Financial Feasibility Study presented by Kane County and WSA staff The presentation summarized

More information

US 67 WIDENING PROJECT

US 67 WIDENING PROJECT US 67 WIDENING PROJECT From Belt Line Rd. to I-20 History & Background The US 67 improvements from Belt Line Rd to I-20 were originally part of TxDOT s Southern Gateway project, studied as part of the

More information

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015 SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment

More information

West Broadway Reconstruction/LRT Design. March 19, 2015

West Broadway Reconstruction/LRT Design. March 19, 2015 West Broadway Reconstruction/LRT Design March 19, 2015 1 Meeting Agenda 6:05 6:30 PM Brief presentation What we heard Project overview 6:30 8:00 PM Visit Six Topic Areas Road and LRT design elements Pedestrian

More information

WELCOME PUBLIC OPEN HOUSE FOR US-64 FROM THE SH-18 INTERSECTION EAST 6.5 MILES JANUARY 10TH, 2017 PAWNEE CITY HALL, 5:30 PM

WELCOME PUBLIC OPEN HOUSE FOR US-64 FROM THE SH-18 INTERSECTION EAST 6.5 MILES JANUARY 10TH, 2017 PAWNEE CITY HALL, 5:30 PM WELCOME PUBLIC OPEN HOUSE FOR US-64 FROM THE SH-18 INTERSECTION EAST 6.5 MILES JANUARY 10TH, 2017 PAWNEE CITY HALL, 5:30 PM 1 PURPOSE OF THIS OPEN HOUSE Present information about the proposed improvements

More information

SCHEDULE OF CAPITAL PROJECTS BY FUND

SCHEDULE OF CAPITAL PROJECTS BY FUND CIP Project Funding Summary 5 7 8 9 10 11 Streets & Highways Fund 3,950,541 2,148,259 1,250,000 1,290,000 1,250,000 9,888,800 Prop C Fund 20,936,435 700,000 700,000 700,000 700,000 23,736,435 Measure R

More information

Transportation Improvement Program (TIP) Candidate Project List for Public Review

Transportation Improvement Program (TIP) Candidate Project List for Public Review 2011-2014 Transportation Improvement Program (TIP) Candidate List for Public Review Table 1 Annual Listing Of Federal Aid Obligation For Federal Fiscal Year 2010 North Dakota s Number Transit 410083 Transit

More information

NASHVILLE AREA MPO FY TIP - ADOPTED DECEMBER

NASHVILLE AREA MPO FY TIP - ADOPTED DECEMBER WILLIAMSON/ MAURY NASHVILLE AREA MPO FY -2017 TIP - ADOPTED DECEMBER 11, 2013 SR-247 (Duplex Road) Widening TIP # 2004-051 Road Widening Spring Hill Williamson Length 3.10 Regional Plan ID 1062-170 Air

More information

Elected Officials Briefing. North Metro Rail Line Update. February 9, 2017

Elected Officials Briefing. North Metro Rail Line Update. February 9, 2017 Elected Officials Briefing North Metro Rail Line Update February 9, 2017 Dave Genova, RTD General Manager and CEO Openings 2016-2017 Flatiron Flyer, Jan. 3, 2016 University of Colorado A Line, April 22,

More information

Delaware County Engineer s Office

Delaware County Engineer s Office Delaware County Engineer s Office JANUARY 2017 County Engineer Responsibility Serve as engineer to the Board of County Commissioners and 18 Boards of Township Trustees for roads, bridges and land surveying

More information

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018 NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3 April 19, 2018 NHHIP OVERVIEW NHHIP divided into 3 Segments: Segment 1: I-45: Beltway 8 to I-610 (9 mi) 45 Segment 2: I-45: I-610 to I-10 (3

More information

Truck Enforcement and Screening Station (TESS) Status Briefing

Truck Enforcement and Screening Station (TESS) Status Briefing Truck Enforcement and Screening Station (TESS) Status Briefing May 18, 2017 Welcome Introductions Key Personnel Glenn Leon Guerrero, DPW Director Felix Benavente, DPW Deputy Director Joaquin Blaz, DPW

More information

Metro Highway Program

Metro Highway Program Metro Highway Program ACEC November 2018 I-5 North HOV and Truck Lanes 14 miles of HOV lanes in both directions 2 miles of truck climbing lanes at the south end 7 bridge modifications at: Gavin Canyon

More information

system performance I-820 East Loop FM 156 TxDOT is working to expand its busiest metropolitan corridors.

system performance I-820 East Loop FM 156 TxDOT is working to expand its busiest metropolitan corridors. system performance TxDOT is working to expand its busiest metropolitan corridors. Nine of the state s 100 most congested highways are located in Tarrant County. Six of these highways will be expanded and

More information

VIRGINIA RAILWAY EXPRESS MANASSAS PARK STATION PARKING EXPANSION. Public Meeting June 20, 2017

VIRGINIA RAILWAY EXPRESS MANASSAS PARK STATION PARKING EXPANSION. Public Meeting June 20, 2017 MANASSAS PARK STATION PARKING EXPANSION Public Meeting June 20, 2017 1 AGENDA Project Status Schematic Design Circulation Traffic Analysis Proposed Garage Location Next Steps Cost Estimate 2 PROJECT PHASES

More information

Workshop Agenda. Bransford Roundabout. Bedford Intersection/Roundabout. Section 3 Revisions (Left turn lanes) Roadway Section/Curb Type Discussion

Workshop Agenda. Bransford Roundabout. Bedford Intersection/Roundabout. Section 3 Revisions (Left turn lanes) Roadway Section/Curb Type Discussion Workshop Agenda Bransford Roundabout Bedford Intersection/Roundabout Section 3 Revisions (Left turn lanes) Roadway Section/Curb Type Discussion Project Phasing Summary of Recommendation Purpose: Provide

More information

Snelling Bus Rapid Transit. May 13, 2013 Technical Advisory Committee Meeting #1

Snelling Bus Rapid Transit. May 13, 2013 Technical Advisory Committee Meeting #1 Snelling Bus Rapid Transit May 13, 2013 Technical Advisory Committee Meeting #1 1 Today s meeting TAC Introductions Project Overview Arterial BRT Concept Background Snelling Corridor Plan, Funding & Schedule

More information

Project Application. General Information ODOT PID. Primary County (3 char abrv) ODOT District

Project Application. General Information ODOT PID. Primary County (3 char abrv) ODOT District Current Status (Tier 1, Tier 2 or New) Proposed Status (Tier 1 or Tier 2) Project Application General Information ODOT PID ODOT District Primary County (3 char abrv) Facility Name (i.e. route, rail, terminal,

More information

Doran Street and Broadway/Brazil Grade Separation Project

Doran Street and Broadway/Brazil Grade Separation Project Doran Street and Broadway/Brazil Grade Separation Project Public Outreach Meeting October 4, 2017 Agenda Introductions Project Overview Grade Separation Alternative Traffic Report Update Interim Condition

More information

Draft Results and Open House

Draft Results and Open House Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi

More information

Elected Officials Briefing North Metro Rail Line Update. November 10, 2016

Elected Officials Briefing North Metro Rail Line Update. November 10, 2016 Elected Officials Briefing North Metro Rail Line Update November 10, 2016 Dave Genova, RTD General Manager and CEO Five lines opening in 2016 Flatiron Flyer, Jan. 3 University of Colorado A Line, April

More information

SOUTH TEXAS COMMISSION MEETING

SOUTH TEXAS COMMISSION MEETING SOUTH TEXAS COMMISSION MEETING September 26, 2013 Pharr District Commission Meeting Pharr District: Overview The Pharr District plans, designs, builds, operates and maintains the state transportation system

More information

San Rafael Transit Center. Update. Golden Gate Bridge, Highway & Transportation District Transportation Committee of the Board of Directors

San Rafael Transit Center. Update. Golden Gate Bridge, Highway & Transportation District Transportation Committee of the Board of Directors Transportation Committee November 17, 2016 Agenda Item No. 5, Update on the San Rafael Transit Center Relocation San Rafael Transit Center Relocation Study Update 11/17/16 Golden Gate Bridge, Highway &

More information

Basic Project Information

Basic Project Information FY 2015-16 PROJECT DESCRIPTION FORM (7B) Submitting Agency: Fairfax County Basic Project Information Project Title: South Van Dorn Street and Franconia Road Interchange 7B Project Type (check one): Roadway

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Laura Cornejo, DEO Regional Planner Regional Operator Metro is LA County s Regional Builder/Funder Rail Bus Service (Metro/Muni/Local)

More information

Western ND Meeting. February 19, 2014 Grant Levi, NDDOT Director

Western ND Meeting. February 19, 2014 Grant Levi, NDDOT Director Western ND Meeting February 19, 2014 Grant Levi, NDDOT Director 1 Traffic Trends in North Dakota 2 Truck Traffic 2008 3 Truck Traffic 2012 4 Average Daily Traffic 5 ND Vehicle Miles Traveled Statewide

More information

CTA Capital Construction Update May 17, 2007

CTA Capital Construction Update May 17, 2007 Block 37 Signals Project Brown Line Howard CTA Capital Construction Update May 17, 2007 1 Capital Construction Update Agenda Howard Station Reconstruction Brown Line Capacity Expansion Project Block 37

More information

BRT Master Cooperative Agreement Exhibit B: Conformance Standards for Oakland Conditions of Approval Numbers I through IX

BRT Master Cooperative Agreement Exhibit B: Conformance Standards for Oakland Conditions of Approval Numbers I through IX BRT Master Cooperative Agreement Exhibit B: for Oakland Conditions of Approval Numbers I through IX August 1, 2013 NOTE: These COA Standards exclude operations and maintenance (O&M) requirements. The O&M

More information

CHANGE LIST for MDOT Traffic and Safety Geometric Design Guides. May 23, 2017: The following update was made to the web site.

CHANGE LIST for MDOT Traffic and Safety Geometric Design Guides. May 23, 2017: The following update was made to the web site. CHANGE LIST for MDOT Traffic and Safety Geometric Design Guides Note: Located at https://mdotjboss.state.mi.us/tssd/tssdhome.htm May 23, 2017: The following update was made to the web site. GEO-650-D Flares

More information

Middle Harbor Project: Draft EIS/EIR LA Chamber of Commerce June 26, 2008, APM Maersk HQ Pier 400

Middle Harbor Project: Draft EIS/EIR LA Chamber of Commerce June 26, 2008, APM Maersk HQ Pier 400 Middle Harbor Project: Draft EIS/EIR LA Chamber of Commerce June 26, 2008, APM Maersk HQ Pier 400 Richard D. Cameron Director of Environmental Planning, Port of Long Beach CEQA/NEPA Process Summary The

More information

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015 Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015 Meeting Agenda Phase 2 Construction Update Meeting Meeting Purpose and Format Construction Update Expo Bikeway

More information

The Corporation of Delta COUNCIL REPORT Regular Meeting. Noise Variance for Construction Works at the Vancouver Landfill

The Corporation of Delta COUNCIL REPORT Regular Meeting. Noise Variance for Construction Works at the Vancouver Landfill The Corporation of Delta COUNCIL REPORT Regular Meeting F.02 To: From: Mayor and Council Engineering Department File No.: 6280-01 Date: December 13,2016 Noise Variance for Construction Works at the Vancouver

More information

INFRASTRUCTURE AND TRANSPORTATION ADVERTISING SCHEDULE 2015/2016 CONSTRUCTION AND MATERIAL SUPPLY TENDERS

INFRASTRUCTURE AND TRANSPORTATION ADVERTISING SCHEDULE 2015/2016 CONSTRUCTION AND MATERIAL SUPPLY TENDERS INFRASTRUCTURE AND TRANSPORTATION ADVERTISING SCHEDULE 2015/2016 CONSTRUCTION AND MATERIAL SUPPLY TENDERS Manitoba Infrastructure and Transportation Contract Services Branch 1630-215 Garry Street Winnipeg,

More information

DES MOINES AIRPORT AUTHORITY BOARD SUMMARY OF REGULAR MEETING Des Moines International Airport Board Room May 13, 2014

DES MOINES AIRPORT AUTHORITY BOARD SUMMARY OF REGULAR MEETING Des Moines International Airport Board Room May 13, 2014 DES MOINES AIRPORT AUTHORITY BOARD SUMMARY OF REGULAR MEETING Des Moines International Airport Board Room May 13, 2014 Call to Order and Roll Call: Present: Erickson, Feldmann, Hansell, and Ward. Absent:

More information

Rural Planning. Highway Projects - CULLMAN COUNTY

Rural Planning. Highway Projects - CULLMAN COUNTY 4/17/2015 ALABAMA DEPARTMENT OF TRANSPORTATION Page - 1 of 9 Length CR-1742 4.770 Highway s - CULLMAN COUNTY RESURFACE CR-1742 FROM SR-74 (US-278) TO SR-67 RESURFACING 100063223 ST-022-888-011- ( ) CONSTRUCTION

More information

CTA Capital Construction Update December 12, 2006

CTA Capital Construction Update December 12, 2006 Red Line/Dan Ryan Blue Line Block 37 Washington Subsurface Station at Block 37 Block 37 Tracks Randolph Red Line Brown Line Howard CTA Capital Construction Update December 12, 2006 1 Capital Construction

More information

Prince William County Department of Transportation 4th Quarter Joint Mobility Report January 8, 2019

Prince William County Department of Transportation 4th Quarter Joint Mobility Report January 8, 2019 Prince William County Department of Transportation 4th Quarter Joint Mobility Report January 8, 2019 Projects Completed in 2018 Traffic Signal and Telegraph and Horner Dumfries Road Dual Left Projects

More information

Ottawa LRT Stage 2. McKellar Park Information Session

Ottawa LRT Stage 2. McKellar Park Information Session Ottawa LRT Stage 2 McKellar Park Information Session Stage 2 Background Approved unanimously by Ottawa City Council in July 2015 East to Place d Orléans, west to Bayshore and Baseline, and south to Bowesville

More information

SH 249 IN GRIMES COUNTY. Open House April 3, 2014

SH 249 IN GRIMES COUNTY. Open House April 3, 2014 SH 249 IN GRIMES COUNTY Open House April 3, 2014 Meeting Agenda Purpose of Meeting Today: Review the purpose and need for the SH 249 Grimes County project Review the proposed project and alternatives Discuss

More information

Transit Project Delivery Status Report. Significant Issues

Transit Project Delivery Status Report. Significant Issues Item 1 Transit Project Delivery Status Report Significant Issues Presented By K.N. Murthy Executive Director Construction Committee 1 I-405 Sepulveda Pass Closure Construction Committee I-405 Sepulveda

More information

CITY COUNCIL STUDY SESSION UPDATE ON SMART. January 19, 2017 CITY OF SAN RAFAEL

CITY COUNCIL STUDY SESSION UPDATE ON SMART. January 19, 2017 CITY OF SAN RAFAEL CITY COUNCIL STUDY SESSION UPDATE ON SMART January 19, 2017 CITY OF SAN RAFAEL SONOMA MARIN AREA RAIL TRANSIT UPDATE OUTLINE BACKGROUND INITIAL OPERATION SYSTEM (IOS1) CIVIC CENTER AREA LARKSPUR EXTENSION

More information

Interstate Drive Extension

Interstate Drive Extension Interstate Drive Extension Sponsor County Highway Project No. RB19-000004 Project Type New Road TOTAL FUNDING Total County Sponsor Federal $2,700,000.00 $2,150,000.00 Project Description This project continues

More information

LEADING GATEWAY FOR U.S.-ASIA TRADE

LEADING GATEWAY FOR U.S.-ASIA TRADE PORT OF LONG BEACH LEADING GATEWAY FOR U.S.-ASIA TRADE 4 STATE TIDELANDS TRUST PROMOTE TRADE, BUILD PORT 6 PORT OF LOS ANGELES PORT OF LONG BEACH WORLD S 9 TH BUSIEST PORT COMPLEX *BASED ON 2017 CONTAINER

More information

IH 35 FEASIBILITY STUDY

IH 35 FEASIBILITY STUDY IH 35 FEASIBILITY STUDY COOKE COUNTY, TEXAS February 1, 2007 Prepared by: Carter & Burgess, Inc. For: The Wichita Falls District of the Texas Department of Transportation INDEX I. INTRODUCTION. 3 II. PURPOSE

More information

December 12, Dear Secretary Foxx:

December 12, Dear Secretary Foxx: Chair Pete White City Councilmember Vice-Chair Jay Adams Mustang Mayor Secretary/Treasurer Matt Dukes Midwest City Mayor association of central oklahoma governments Executive Director John G. Johnson December

More information

ALTERNATIVE PROJECT DELIVERY

ALTERNATIVE PROJECT DELIVERY ALTERNATIVE PROJECT DELIVERY Varuna Singh SH 288 IN HARRIS COUNTY SH 288 in Harris County SEGMENT 1: 8 New Tolled Direct Connectors at SH 288 and Beltway 8 Existing traffic uses frontage roads today to

More information

City of Beverly Hills North Santa Monica Blvd Reconstruction. Traffic & Parking Commission June 04, 2015

City of Beverly Hills North Santa Monica Blvd Reconstruction. Traffic & Parking Commission June 04, 2015 City of Beverly Hills North Santa Monica Blvd Reconstruction Traffic & Parking Commission June 04, 2015 1 Overview of June 4 TPC Overview of Possible Traffic Mitigation Measures Toolbox During Construction

More information

HDR Engineering. HART North / South. Tampa Bay Applications Group Meeting May 14, 2009

HDR Engineering. HART North / South. Tampa Bay Applications Group Meeting May 14, 2009 HDR Engineering HART North / South BRT Corridor PD&E Tampa Bay Applications Group Meeting May 14, 2009 1 Agenda Update on Project Development and Environment (PD&E) Study Project Overview System Branding

More information