1 Ohio Department of Transportation Construction Update DISTRICT 2 KIRK SLUSHER, P.E., ACTING DEPUTY DIRECTOR 317 East Poe Rd. Bowling Green, Ohio ODOT District Two Monthly Construction Update For Immediate Release Thursday, February 16, 2017 Updates are highlighted in bold and underlined. Lucas/Wood Counties 1. Interstate 75: Widening Wood & Hancock Counties (170-14, , & ): Interstate Restrictions: Through July, single lane restrictions are possible on I-75, between US 20 and CR 99 in Hancock County, for finish work. Project complete: October. All work is weather permitting. 2. Interstate 75: Widening Lucas County (485-14, ): Through September 2018, overnight, 7pm through 6am, single lane restrictions are possible on I-75, from I-475 in Toledo to I-280 for widening and bridge work. Effective tonight 10pm, through Friday, February 17 at 1am, southbound I-75, between Polish Village Overpass and Phillips Avenue, will be reduced to one lane for guardrail repair. Additionally at this time, the ramp from southbound I-75 to Phillips Avenue may be closed. Detour: Detroit Avenue (Exit 203); northbound I-75. Effective Friday, February 17, from midnight until 4am, northbound I-75, between I-475 and Berdan Avenue, may be reduced to one lane for guardrail repair. Additionally at this time, the ramp from eastbound I-475 to northbound I-75 will be closed. Detour: southbound I-75; Detroit Avenue (Exit 203); northbound I-75.

2 The following ramps are restricted/closed: Through July 2018, the ramp from Phillips Avenue to southbound I-75 is closed. Detour: northbound I-75; Stickney Avenue (Exit 207); North Expressway Drive; southbound I- 75. Through July 2018, the ramp from Jeep/Willys Parkway to southbound I-75 is closed. Detour: Detroit Avenue. Through July 2018, the ramp from Jeep/Willys Parkway to northbound I-75 is closed. Detour: Berdan Avenue; Detroit Avenue; Phillips Avenue. Through July 2018, the ramp from southbound I-75 to Jeep/Willys Parkway (Exit 205A) is closed. Detour: Detroit Avenue (Exit 203B). Through September 2018, the interchange ramp from eastbound I-475 to southbound I- 75 is reduced to one lane. Local Streets: Effective Friday, February 17, through Thursday, February 23, daily from 8am until 6pm, northbound Detroit Avenue under I-75 will be closed for bridge work. Detour: Berdan Avenue; Haverhill Drive; Phillips Avenue. Through May, the Polish Village Overpass is closed for bridge work. Detour: North Expressway Drive; Stickney Avenue; South Expressway Drive. Through June, South Expressway Drive is restricted to a single lane between Stickney Avenue and Lagrange Street. Through June, Elm Street and Wersell Avenue at South Expressway Drive, are closed. Through June, Stickney Avenue, is restricted to a single lane between North Expressway Drive and South Expressway Drive. Through August, northbound Detroit Avenue under I-75 will be reduced to one lane for bridge work. Through October, expect lane restrictions on Phillips Avenue at I-75 for bridge work. Through July 2018, lane restrictions are possible on Detroit Avenue at I-75 for bridge work. Through July 2018, expect lane restrictions on Berdan Avenue at I-75 for bridge work.

3 Through July 2018, Willys Parkway from Pioneer Lane to Jeep Parkway is closed. Project complete: September All work is weather permitting. 3. Interstate 75: Rest Area Wood County ( ): Through June, the southbound I-75 rest area is closed for renovations and pavement repair. Project complete: June. All work is weather permitting. 4. Interstate 280: Bridge Repair Lucas County ( ): Through February, single lane restrictions are possible on southbound I-280, between Greenbelt Parkway (Exit 11) and Starr Avenue (Exit 8), for lighting installation. Project complete: February. All work is weather permitting. 5. Interstate 475: ProMedica Parkway Ramp Lucas County: The ramp from ProMedica Parkway to eastbound I-475 is open to access southbound I-75 only. Through September 2018, the ramp from ProMedica Parkway to eastbound I-475 to access northbound I-75 is closed. Detour: southbound I-75; Detroit Avenue (Exit 203B); northbound I-75. All work is weather permitting. 6. Interstate 475: Incident Clean-up and Guardrail Repair Lucas County: Tonight at 9pm, through Friday, February 17 at 6am, the ramp from westbound I-475 to northbound US 23 will be closed for clean-up and guardrail repairs from an earlier incident. Detour: southbound I-475; eastbound SR 2/Airport Highway (Exit 8A); northbound I All work is weather permitting. 7. Interstate Maintenance Work Lucas and Wood Counties: Through December, intermittent overnight lane restrictions are possible on I-75, I-280 and I-475 in Lucas and Wood counties for maintenance work. Project complete: December. All work is weather permitting. 8. U.S. Route 20: Central Avenue Interchange Project Lucas County (210-15): Through September, Central Avenue, between McCord Road and Van Fleet Parkway, may be reduced to one lane for finish work. Through September, lane restrictions are possible on I-475/US 23, between Dorr Street and N. Holland Sylvania Road. Through March, lane restrictions are possible on the ramps from US 20 to northbound I-475 and from southbound I-475 to US 20 for lighting work. Project complete: September. All work is weather permitting. 9. U.S. Route 20: Traffic Signal Upgrades Lucas County (301-16): Through February, daytime intermittent lane restrictions are possible

4 at the intersection of Central Avenue/US 20 and Meijer Drive for finish work. Project complete: February. All work is weather permitting. 10. State Route 2: Anthony Wayne Bridge Painting Project Lucas County (220-16): Through November, SR 2, between Oak Street and Broadway Street, is reduced to one lane in each direction for bridge painting. Through February, Utah Street, under the Anthony Wayne Bridge, is closed for bridge painting. Detour: Greenwood Avenue; Oak Street; Nevada Street. Additional local road closures may be announced. Project complete: November. All work is weather permitting. 11. U.S. Route 20: Culvert Replacements, Resurfacing & Turn Lanes *NEW WORK* Wood County (256-16): Effective Monday, March 20, through Monday, April 3, US 20 east of Glenwood Road will be closed for culvert replacement. Additionally at this time, US 20 east of Tracy Road will be closed for culvert replacement. Detour: SR 420; I-280; SR 795; I-75; US 20. Local access to US 20 available via Ault, Oregon and Tracy Roads. Effective Monday, April 3, through Wednesday, April 5, US 20 at Oregon Road will be closed for culvert replacement. Detour: SR 420; I-280; SR 795; I-75; US 20. Effective Thursday, April 6 through April, Oregon Road at US 20 will be closed for turn lane installation. At this time, US 20 will be open to through traffic. Lane restrictions on US 20, between Lime City Road and Stony Ridge Road, for resurfacing will be announced. The reduction of US 20, between Luckey Road and SR 420, to one lane for bridge repair will be announced. Traffic will be maintained by temporary traffic signal. Project complete: June All work is weather permitting. 12. State Route 18: Railroad Repair *CLOSURE BEGINS TUESDAY* Wood County: Effective Tuesday, February 21, through Wednesday, March 8, SR 18, between Railroad Street and Hamm Street in Bloomdale, will be closed for railroad repair. Detour: SR 613; I-75. All work is weather permitting. 13. State Route 25: Diverging Diamond Interchange Wood County ( ): Through October, overnight from 7pm until 6am, single lane restrictions are possible on I-475, between the I-75/475 interchange and Fort Meigs Road, for diverging diamond interchange work. Additionally, overnight from 9pm until 6am, lane restrictions are possible on SR 25, between Levis Commons Boulevard and Eckel Junction Road, for diverging diamond interchange work. Project complete: October. All work is weather permitting. 14. State Route 795: Traffic Signal Upgrades

5 Wood County (301-16): Through February, daytime intermittent lane restrictions are possible on SR 795 at Glenwood Road, for traffic signal upgrades. Project complete: February. All work is weather permitting. 15. Fort Meigs Road: Widening Wood County (460-16): Effective Monday, February 27, through June, Fort Meigs Road, between Five Point Road and the high school drive in Perrysburg, will be closed for widening. Detour: Five Point Road; SR 25; Roachton Road. Local access maintained. Project complete: July. All work is weather permitting. Ottawa/Sandusky/Seneca Counties 16. State Route 53: Traffic Signal Upgrades Sandusky County (301-16): Through February, shoulder restrictions are possible on SR 53, between US 20 and Sean Street, for finish work. Additional restrictions may be announced. Project Complete: February. All work is weather permitting. Williams/Fulton/Henry Counties 17. U.S. Route 20A: Resurfacing and Signal Upgrades *UPDATE* Fulton County ( ): Through April, intermittent lane restrictions are possible on Airport Highway/US 20A, between the Lucas/Fulton County line and CR 3, for signal work. Project complete: May. All work is weather permitting. 18. State Route 109: Damascus Bridge: Bridge Replacement Henry County (1-15): Through October, motorists should watch for additional truck traffic near SR 109 at the Damascus bridge for bridge work. Work impacting traffic will be announced. Project complete: October. All work is weather permitting. 19. State Route 109: Utility Work *CLOSURE BEGINS TUESDAY* Fulton County: Effective Tuesday, February 21, through Friday, February 24, SR 109 at Providence Street in Delta will be closed for utility work. Detour: US 24; SR 108; US 20A. All work is weather permitting. District Wide 20. Various Routes: Guardrail, Striping & Electrical Maintenance District Wide ( & & ): Through December, intermittent lane restrictions are possible district wide for guardrail, striping and electrical maintenance. Project complete: December. All work is weather permitting.

6 The Ohio Department of Transportation maintains the state's largest man-made asset--the transportation system. ODOT's mission is to provide the safe and easy movement of people and goods from place to place. As a $2.8 billion per year enterprise, ODOT invests the bulk of its resources in system preservation through maintenance, construction and snow and ice operations. The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 11, 2015, and executed by FHWA and ODOT. ### For more information contact: The District Two Public Information Office at (419) or D02.PIO@dot.ohio.gov

ODOT District Two Monthly Construction Update

ODOT District Two Monthly Construction Update Ohio Department of Transportation Construction Update DISTRICT 2 KIRK SLUSHER, P.E., ACTING DEPUTY DIRECTOR 317 East Poe Rd. Bowling Green, Ohio 43402-1330 www.transportation.ohio.gov/dist2 ODOT District

More information

NEWS RELEASE November 8, 2017

NEWS RELEASE November 8, 2017 NEWS RELEASE November 8, 2017 Contact: Marsha Roa Public Information Manager 909.839.7055 mroa@diamondbarca.gov GRAND AVENUE INTERCHANGE AT SR-57 (ORANGE) AND SR-60 (POMONA) MULTIPLE ROADWAY, RAMP AND

More information

I-4 Beyond the Ultimate. Florida Transportation Builders Association January 18, 2019

I-4 Beyond the Ultimate. Florida Transportation Builders Association January 18, 2019 I-4 Beyond the Ultimate Florida Transportation Builders Association January 18, 2019 FDOT District 5 Improving Mobility & Safety in Central Florida FDOT District 5 is: Designing and building a better Interstate

More information

I-820 (East) Project Description. Fort Worth District. Reconstruct Southern I-820/SH 121 Interchange

I-820 (East) Project Description. Fort Worth District. Reconstruct Southern I-820/SH 121 Interchange I-820 (East) Project Description Fort Worth District Reconstruct Southern I-820/SH 121 Interchange I-820 from approximately 2,000 feet north of Pipeline Road/Glenview Drive to approximately 3,200 feet

More information

Traffic Accident Statistics

Traffic Accident Statistics 2000 Missouri State Highway System Traffic Accident Statistics Missouri State Highway System Traffic Accident Statistics Table of Contents Subject Chapter 1: Statewide Traffic Accident Statistics, Introduction

More information

1999 Missouri State Highway System. Missouri Department of Transportation - Transportation Management Systems

1999 Missouri State Highway System. Missouri Department of Transportation - Transportation Management Systems 1999 Missouri State Highway System Traffic Accident Statistics - Transportation Management Systems Missouri State Highway System Traffic Accident Statistics Table of Contents Subject Chapter 1: Statewide

More information

Collision Analysis Safety Tables

Collision Analysis Safety Tables Crash Severity Geography of Geography of Time and Date of Crash Conditions Features Features.. Queries Selected: Town(Hartford), Date(Year:All or //05 to 9/7/06), Severity(All), Route Class(Interstate),

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 2/19/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

OHIO Department of Transportation Project # Franklin County, OH. ISSA Presidents Award Submission Strawser Construction Inc.

OHIO Department of Transportation Project # Franklin County, OH. ISSA Presidents Award Submission Strawser Construction Inc. OHIO Department of Transportation Project #140378 Franklin County, OH ISSA Presidents Award Submission Strawser Construction Inc. Columbus, Ohio Applicant Information Strawser Construction Inc. 1392 Dublin

More information

Automated Photo Enforcement Annual Report 2015

Automated Photo Enforcement Annual Report 2015 Automated Photo Enforcement Annual Report March 8, Financial Services SUSTAINABLE STREETS DIVISION Pursuant to California Vehicle Code section., the San Francisco Municipal Transportation Agency is submitting

More information

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237)

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) W&OD TRAIL BRIDGE OVER LEE HIGHWAY A COMPONENT OF THE I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) October 11, 2018 Bill Cuttler, PE

More information

Asset Recovery & Remarketing Auto Auction Locations

Asset Recovery & Remarketing Auto Auction Locations Asset Recovery & Remarketing Auto Auction Locations Auction Address Phone # Sale Day Sale Type Sale Time Website Auto Dealers Exchange of Indianapolis 8800 Brooksville Rd 317-352-0121 Wednesday Dealer

More information

Expansion Projects Description

Expansion Projects Description Expansion Projects Description The Turnpike expansion program was authorized by the Florida Legislature in 1990 to meet the State s backlog of needed highway facilities. The Legislature set environmental

More information

Delaware County Engineer s Office

Delaware County Engineer s Office Delaware County Engineer s Office JANUARY 2017 County Engineer Responsibility Serve as engineer to the Board of County Commissioners and 18 Boards of Township Trustees for roads, bridges and land surveying

More information

I-405 Sepulveda Pass Improvements Project

I-405 Sepulveda Pass Improvements Project I-405 Sepulveda Pass Improvements Project Community Meeting November 15, 2012 1 Wilshire Segment Overview of Wilshire Segment There are a total of 23 bridges being constructed on this project; almost half

More information

Understanding and Identifying Crashes on Curves for Safety Improvement Potential in Illinois

Understanding and Identifying Crashes on Curves for Safety Improvement Potential in Illinois Understanding and Identifying Crashes on Curves for Safety Improvement Potential in Illinois Priscilla Tobias, P.E. Mouyid Islam, Ph.D. Kim Kolody, P.E. Optional Agenda Image Title Background Workflow

More information

Service Planning Open House

Service Planning Open House Service Planning Open House Presentation to Community RTA Board Room July 17, 2018 575 EYES See Something, Text Something Transit App RTA CLE Mobile Ticketing Bus Stop Consolidation/Safety Improvement

More information

Public Meeting: Metropolitan Washington Airports Authority (MWAA) TNC (Transportation Network Company) Lot on S. Eads Street

Public Meeting: Metropolitan Washington Airports Authority (MWAA) TNC (Transportation Network Company) Lot on S. Eads Street Public Meeting: Metropolitan Washington Airports Authority (MWAA) TNC (Transportation Network Company) Lot on S. Eads Street Department of Environmental Services, Transportation Division Sept. 27, 2018

More information

CDMS - Crash Data Management System. Crash Data Report. Report Memo: RESERVE FOR MAP SCREENSHOT

CDMS - Crash Data Management System. Crash Data Report. Report Memo: RESERVE FOR MAP SCREENSHOT Report Memo: 213-217 RESERVE FOR MAP SCREENSHOT Intersection Summary Top 4 Report 15_2924 15_286 15_7359 15_595 15_22194 15_22158 15_12873 15_17926 15_2279 15_19276 15_1615 15_3128 15_17273 15_26238 15_19328

More information

OHIO Department of Transportation Project # Franklin County, OH. ISSA Presidents Award Submission Strawser Construction Inc.

OHIO Department of Transportation Project # Franklin County, OH. ISSA Presidents Award Submission Strawser Construction Inc. OHIO Department of Transportation Project #140378 Franklin County, OH ISSA Presidents Award Submission Strawser Construction Inc. Columbus, Ohio Strawser Construction Project Team Chris Anspaugh Regional

More information

New Jersey Turnpike Authority Interchange 6 to 9 Widening Program

New Jersey Turnpike Authority Interchange 6 to 9 Widening Program New Jersey Turnpike Authority Interchange 6 to 9 Widening Program Tuesday, September 18, 2007 Public Hearings: Time: 5:00 PM - 8:00 PM Wednesday, September 19, 2007 Senior Center 3 Municipal Drive Bordentown,

More information

STATE OF NEW YORK DEPARTMENT OF TRANSPORTATION OFFICE OF ENGINEERING AMENDMENT NO. 4 TO: IN THE LETTING OF FEBRUARY 21, 2013

STATE OF NEW YORK DEPARTMENT OF TRANSPORTATION OFFICE OF ENGINEERING AMENDMENT NO. 4 TO: IN THE LETTING OF FEBRUARY 21, 2013 STATE OF NEW YORK DEPARTMENT OF TRANSPORTATION OFFICE OF ENGINEERING AMENDMENT NO. 4 TO: ALBANY, NEW YORK FEBRUARY 5, 2013 D262162 F. A. PROJECT BRONX COUNTY CPIN X806.63 STATE OF GOOD REPAIR III IN THE

More information

WIM #37 was operational for the entire month of September Volume was computed using all monthly data.

WIM #37 was operational for the entire month of September Volume was computed using all monthly data. SEPTEMBER 2016 WIM Site Location WIM #37 is located on I-94 near Otsego in Wright county. The WIM is located only on the westbound (WB) side of I-94, meaning that all data mentioned in this report pertains

More information

Public Information Packet FY Fargo-Moorhead Metropolitan Transportation Improvement Program (TIP)

Public Information Packet FY Fargo-Moorhead Metropolitan Transportation Improvement Program (TIP) Public Information Packet FY - Fargo-Moorhead Metropolitan Transportation Improvement Program (TIP) Comment Form Annual Element TIP Projects - TIP Projects Year - Metropolitan Transportation Improvement

More information

Wentzville Parkway South Phase 2 & 2A

Wentzville Parkway South Phase 2 & 2A Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total

More information

Guam Transportation Program Project Updates. Joanne M.S. Brown Director Carl Dominguez Deputy Director February 6, 2012

Guam Transportation Program Project Updates. Joanne M.S. Brown Director Carl Dominguez Deputy Director February 6, 2012 Guam Transportation Program Project Updates Joanne M.S. Brown Director Carl Dominguez Deputy Director February 6, 2012 Agenda Road Construction Highlights Ongoing Construction Route 17 Rehabilitation and

More information

ORDINANCE NO. 14,336

ORDINANCE NO. 14,336 ORDINANCE NO. 14,336 AN ORDINANCE to amend the Municipal Code of the City of Des Moines, Iowa, 2000, adopted by Ordinance No. 13,827, passed June 5, 2000, and amended by Ordinance No. 13,972, passed July

More information

Clean Harbors Canada, Inc.

Clean Harbors Canada, Inc. Clean Harbors Canada, Inc. Proposed Lambton Landfill Expansion Environmental Assessment Terms of Reference Transportation Assessment St. Clair Township, Ontario September 2009 itrans Consulting Inc. 260

More information

December 12, Dear Secretary Foxx:

December 12, Dear Secretary Foxx: Chair Pete White City Councilmember Vice-Chair Jay Adams Mustang Mayor Secretary/Treasurer Matt Dukes Midwest City Mayor association of central oklahoma governments Executive Director John G. Johnson December

More information

CITY OF BEVERLY HILLS STAFF REPORT

CITY OF BEVERLY HILLS STAFF REPORT Meeting Date: July 7, 2011 To: From: Subject: CITY OF BEVERLY HILLS STAFF REPORT Honorable Mayor & City Council Pamela Mottice Muller, Director of Emergency Management 405 Closure Attachments: 1. 1-405

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY BOARD OF DIRECTORS. RESOLUTION No

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY BOARD OF DIRECTORS. RESOLUTION No SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY BOARD OF DIRECTORS RESOLUTION No. 170718-088 WHEREAS, The City adopted the Vision Zero Policy in February 2014 which aims to eliminate all traffic fatalities

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.5 DIVISION: Sustainable Streets BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Amending Transportation Code, Division II, Section 601 to add previously

More information

Michigan. Traffic. Profile

Michigan. Traffic. Profile June 2014 Revised 5/11/15 Michigan 2013 Traffic Crash Profile Reporting Criteria Please pay particular attention to the wording when interpreting the three levels of data gathered for this report. Crash

More information

FINAL DRAFT Traffic Operations and Safety Study for the City of Belpre 2008

FINAL DRAFT Traffic Operations and Safety Study for the City of Belpre 2008 FINAL DRAFT Traffic Operations and Safety Study for the City of Belpre 2008 Tracy A. Higgins Randy L. Durst Fred L. Rader WOOD WASHINGTON WIRT INTERSTATE PLANNING COMMISSION An affiliate agency of the

More information

Transportation Improvement Program (TIP) Candidate Project List for Public Review

Transportation Improvement Program (TIP) Candidate Project List for Public Review 2011-2014 Transportation Improvement Program (TIP) Candidate List for Public Review Table 1 Annual Listing Of Federal Aid Obligation For Federal Fiscal Year 2010 North Dakota s Number Transit 410083 Transit

More information

LOADING AND UNLOADING SURVEY NATIONAL SCHOOL BUS. Kansas leads the world in the success of each student.

LOADING AND UNLOADING SURVEY NATIONAL SCHOOL BUS. Kansas leads the world in the success of each student. NATIONAL SCHOOL BUS LOADING AND UNLOADING SURVEY Kansas leads the world in the success of each student. January 2018 The Kansas State Department of Education School Bus Safety Unit wishes to thank the

More information

Local Market Update 2012 Year In Review

Local Market Update 2012 Year In Review Northwest Area Home Sales for the Year 2012 Sales of single-family homes reported in Toledo and the surrounding area by the Toledo Board of REALTORS totaled 6,793. This was an increase of 6% compared to

More information

SH 249 PUBLIC MEETING DESIGN CHANGES FROM FM 2920 TO HARDIN STORE ROAD

SH 249 PUBLIC MEETING DESIGN CHANGES FROM FM 2920 TO HARDIN STORE ROAD SH 249 PUBLIC MEETING DESIGN CHANGES FROM FM 2920 TO HARDIN STORE ROAD Lone Star College, Tomball Campus December 8, 2015 Open House 5:30-7:30 pm National Environmental Policy Act The environmental review,

More information

Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia 3rd Street Tunnel at Massachusetts Avenue Exit

Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia 3rd Street Tunnel at Massachusetts Avenue Exit Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia 3rd Street Tunnel at Massachusetts Avenue Exit Study Area and Location District PSA Ward ANC Phase Description

More information

MO 370 Interchange Ramp at Salt River Road - Phase 1

MO 370 Interchange Ramp at Salt River Road - Phase 1 MO 3 Interchange Ramp at Salt River Road - Phase 1 Sponsor St Peters Project No. RB19-000023 Project Type New Road TOTAL FUNDING Total County Sponsor Federal $3,304,748.00 $1,652,298.00 $7,450.00 $945,000.00

More information

BINGHAMTON METROPOLITAN TRANSPORTATION STUDY

BINGHAMTON METROPOLITAN TRANSPORTATION STUDY BINGHAMTON METROPOLITAN TRANSPORTATION STUDY ANNUAL LISTING OF FEDERAL AID PROJECT OBLIGATIONS FEDERAL FISCAL YEAR Federal regulations require an annual listing of transportation projects, including investments

More information

Technical Feasibility Report

Technical Feasibility Report Prepared For: Bow Concord I-93 Improvements Project Bow and Concord, NH Prepared By: 53 Regional Drive Concord, NH 03301 NHDOT Project # 13742 Federal Project #T-A000(018) September 2018 TABLE OF CONTENTS

More information

Rural Planning. Highway Projects - CULLMAN COUNTY

Rural Planning. Highway Projects - CULLMAN COUNTY 4/17/2015 ALABAMA DEPARTMENT OF TRANSPORTATION Page - 1 of 9 Length CR-1742 4.770 Highway s - CULLMAN COUNTY RESURFACE CR-1742 FROM SR-74 (US-278) TO SR-67 RESURFACING 100063223 ST-022-888-011- ( ) CONSTRUCTION

More information

Committee Report. Transportation Committee. Business Item No

Committee Report. Transportation Committee. Business Item No Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope

More information

Janice Fortunato Senior Director Business Partnerships

Janice Fortunato Senior Director Business Partnerships Janice Fortunato Senior Director Business Partnerships What are Megaprojects? They are large-scale projects distinguished by cost, complexity and the potential impact on the community. Collectively, these

More information

Start Time. LOCATION: Scotts Valley Dr QC JOB #: SPECIFIC LOCATION: 0 ft from Tabor St. DIRECTION: EB/WB CITY/STATE: Scotts Valley, CA

Start Time. LOCATION: Scotts Valley Dr QC JOB #: SPECIFIC LOCATION: 0 ft from Tabor St. DIRECTION: EB/WB CITY/STATE: Scotts Valley, CA Tube Counts Type of report: Tube Count - Volume Data LOCATION: Scotts Valley Dr QC JOB #: 245667 SPECIFIC LOCATION: ft from Tabor St DIRECTION: EB/WB CITY/STATE: Scotts Valley, CA DATE: Mar 2 24 - Mar

More information

Request for Design Exception (#1) S.M. Wright Phase IIB

Request for Design Exception (#1) S.M. Wright Phase IIB Request for Design Exception (#1) S.M. Wright Phase IIB County: Dallas CSJ s: 0092-01-059, 0092-14-088 Project Limits: From Pennsylvania Avenue to North of Al Lipscomb Way Date: June 28, 2016 Proposed

More information

Summary of the Alcoa Highway Redevelopment Project

Summary of the Alcoa Highway Redevelopment Project Appendix B Summary of the Alcoa Highway Redevelopment Project By Marcia Finfer, October 2009 The Timberlake community, along with numerous other concerned citizen groups (including the Lakemoor Hills community)

More information

Sepulveda Pass Corridor Systems Planning Study

Sepulveda Pass Corridor Systems Planning Study Los Angeles County Metropolitan Transportation Authority Sepulveda Pass Corridor Systems Planning Study Streets and Freeways Subcommittee January 17, 2013 1 Sepulveda Pass Study Corridor Extends for 30

More information

Kent County Traffic Crash Data & Year Trends. Reporting Criteria

Kent County Traffic Crash Data & Year Trends. Reporting Criteria May 2015 Revised 3/16/2016 2014 Reporting Criteria Please pay particular attention to the wording when interpreting the three levels of data gathered for this report. Crash The Crash Level analyzes data

More information

Figure 1 Map of intersection of SR 44 (Ravenna Rd) and Butternut Rd

Figure 1 Map of intersection of SR 44 (Ravenna Rd) and Butternut Rd Abbreviated Study District: 12 County: Geauga Route: SR 44 Section: 1.58 GEA 44 1.58 213 HSP # 47 (Rural Intersection) Prepared April 23, 215 By Bryan Emery Existing Conditions This study contains the

More information

Van Buren County Traffic Crash Data & Year Trends. Reporting Criteria

Van Buren County Traffic Crash Data & Year Trends. Reporting Criteria May 2015 Revised 3/16/2016 2014 Reporting Criteria Please pay particular attention to the wording when interpreting the three levels of data gathered for this report. Crash The Crash Level analyzes data

More information

SH 249 IN GRIMES COUNTY. Open House April 3, 2014

SH 249 IN GRIMES COUNTY. Open House April 3, 2014 SH 249 IN GRIMES COUNTY Open House April 3, 2014 Meeting Agenda Purpose of Meeting Today: Review the purpose and need for the SH 249 Grimes County project Review the proposed project and alternatives Discuss

More information

Lucas County Engineers Office Keith G. Earley, P.E., P.S., Lucas County Engineer

Lucas County Engineers Office Keith G. Earley, P.E., P.S., Lucas County Engineer Lucas County Engineers Office Keith G. Earley, P.E., P.S., Lucas County Engineer Whiteford Road - Sylvania Ave. to Summerfield Rd. Yondota Rd. & Seaman Rd. - Culvert # 1445/1446 Brint Road - Lathrop Rd.

More information

THE CALIFORNIA STATE UNIVERSITY Commercial Paper Equipment Financing (CPEF) Fiscal Year Financing Schedules *

THE CALIFORNIA STATE UNIVERSITY Commercial Paper Equipment Financing (CPEF) Fiscal Year Financing Schedules * Updated 4-10-09 Fiscal Year 2009-10 Financing Schedules * Round of CPEF Call Response CP Issuance Funding Thirteenth March 10, 2009 June 3, 2009 June 4, 2009 Fourteenth June 9, 2009 September 1, 2009 September

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY BOARD OF DIRECTORS. RESOLUTION No

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY BOARD OF DIRECTORS. RESOLUTION No SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY BOARD OF DIRECTORS RESOLUTION No. 16-036 WHEREAS, The San Francisco Municipal Transportation Agency has received a request, or identified a need for traffic

More information

30-Day Look Ahead Summary August 2011

30-Day Look Ahead Summary August 2011 Wilshire Segment 30-Day Look Ahead Summary August 2011 DWP and SCE Utility Relocation Sepulveda reduced to one lane in each direction, Constitution to Ohio, 9pm to 6am Westbound Wilshire reduced to one

More information

Michigan. Traffic. Profile

Michigan. Traffic. Profile June 2014 Revised 5/11/15 Michigan 2013 Traffic Crash Profile Reporting Criteria Please pay particular attention to the wording when interpreting the three levels of data gathered for this report. Crash

More information

Pedestrians Road Safety

Pedestrians Road Safety Pedestrians Road Safety Overview Over the period 1996-2009, 5,323 people have been killed on Irish road. Out of this 22% (1162) were pedestrians. Additional 3863 pedestrians were seriously injured in the

More information

Michigan State Police (MSP) Post 21 - Metro North

Michigan State Police (MSP) Post 21 - Metro North June 2018 Revised 8/3/2018 2017 Reporting Criteria Please pay particular attention to the wording when interpreting the three levels of data gathered for this report. Crash The Crash Level analyzes data

More information

Appendix J Traffic Impact Study

Appendix J Traffic Impact Study MRI May 2012 Appendix J Traffic Impact Study Level 2 Traffic Assessment Limited Impact Review Appendix J [This page was left blank intentionally.] www.sgm-inc.com Figure 1. Site Driveway and Trail Crossing

More information

Michigan State Police (MSP) Post 21 - Metro North

Michigan State Police (MSP) Post 21 - Metro North October 2017 2016 Reporting Criteria Please pay particular attention to the wording when interpreting the three levels of data gathered for this report. Crash The Crash Level analyzes data related to crash

More information

Traffic Safety Network Huron Valley

Traffic Safety Network Huron Valley June 2018 Revised 8/3/2018 2017 Reporting Criteria Please pay particular attention to the wording when interpreting the three levels of data gathered for this report. Crash The Crash Level analyzes data

More information

.MAINTENANCE. Strategic Initiative Four:

.MAINTENANCE. Strategic Initiative Four: The accompanying fact sheets explain specific components of the department s effort to prioritize maintenance activities. This information provides the basis of ODOT s 2001 Strategic Initiative Four: Re-Defining

More information

Pole Mounted Speed Display Pilot Program Study. January, 2016

Pole Mounted Speed Display Pilot Program Study. January, 2016 Pole Mounted Speed Display Pilot Program Study January, 2016 The Prince William County Department of Transportation (PWC DOT) began researching the use of pole mounted speed displays (PMSDs) during the

More information

WIM #48 is located on CSAH 5 near Storden in Cottonwood county.

WIM #48 is located on CSAH 5 near Storden in Cottonwood county. WIM Site Location WIM #48 is located on CSAH 5 near Storden in Cottonwood county. System Operation WIM #48 was operational for the entire month of August 2017. Volume was computed using all monthly data.

More information

To: File From: Adrian Soo, P. Eng. Markham, ON File: Date: August 18, 2015

To: File From: Adrian Soo, P. Eng. Markham, ON File: Date: August 18, 2015 Memo To: From: Adrian Soo, P. Eng. Markham, ON : 165620021 Date: Reference: E.C. Row Expressway, Dominion Boulevard Interchange, Dougall Avenue Interchange, and Howard 1. Review of Interchange Geometry

More information

THE CORNERSTONE APARTMENTS TRAFFIC IMPACT STUDY R&M PROJECT NO

THE CORNERSTONE APARTMENTS TRAFFIC IMPACT STUDY R&M PROJECT NO THE CORNERSTONE APARTMENTS SITUATED AT N/E/C OF STAUDERMAN AVENUE AND FOREST AVENUE VILLAGE OF LYNBROOK NASSAU COUNTY, NEW YORK TRAFFIC IMPACT STUDY R&M PROJECT NO. 2018-089 September 2018 50 Elm Street,

More information

Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS...

Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS... Crosshaven Drive Corridor Study City of Vestavia Hills, Alabama Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA... 3 Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS...

More information

Michigan State Police (MSP) Traffic Safety Network Traverse Bay Area

Michigan State Police (MSP) Traffic Safety Network Traverse Bay Area June 2016 Revised 2/15/2017 2015 Reporting Criteria Please pay particular attention to the wording when interpreting the three levels of data gathered for this report. Crash The Crash Level analyzes data

More information

Water Consumption Statistics Report

Water Consumption Statistics Report Water Consumption Statistics Report Operations and Maintenance Department 29 Edition TABLE OF CONTENTS 29 Water Consumption Statistics Report October 21 SYSTEM AND MUNICIPAL CONSUMPTION 29 GVWD Statistics

More information

Traffic Engineering Study

Traffic Engineering Study Traffic Engineering Study Bellaire Boulevard Prepared For: International Management District Technical Services, Inc. Texas Registered Engineering Firm F-3580 November 2009 Executive Summary has been requested

More information

PROJECT: Wilkinson Road Corridor Improvement Traffic Management Planning Project SUBJECT: Traffic Analysis

PROJECT: Wilkinson Road Corridor Improvement Traffic Management Planning Project SUBJECT: Traffic Analysis TECHNICAL MEMORANDUM DATE: September 10, 2014 PROJECT 5861.03 NO: PROJECT: Wilkinson Road Corridor Improvement Traffic Management Planning Project SUBJECT: Traffic Analysis TO: Steve Holroyd - District

More information

2016 Community Report De Baca County

2016 Community Report De Baca County 6 De Baca County Produced for the New Mexico Department of Transportation, Traffic Safety Division, Traffic Records Bureau, Under Contract 58 by the University of New Mexico, Geospatial and Population

More information

Alberta Speeding Convictions and Collisions Involving Unsafe Speed

Alberta Speeding Convictions and Collisions Involving Unsafe Speed Alberta Speeding Convictions and Collisions Involving Unsafe Speed 2004-2008 Overview This document was prepared under the Alberta Traffic Safety Plan, Strategic Research Plan for 2008-2010, with the objective

More information

2015 Community Report Doña Ana County

2015 Community Report Doña Ana County 25 Doña Ana County Produced for the New Mexico Department of Transportation, Traffic Safety Division, Traffic Records Bureau, Under Contract 58 by the University of New Mexico, Geospatial and Population

More information

PERFORMANCE ACTIVITY 603 SIGNS

PERFORMANCE ACTIVITY 603 SIGNS PERFORMANCE ACTIVITY 603 SIGNS WORK DESCRIPTION 3 WORK DESCRIPTION 4 WORK DESCRIPTION 6 New Install Maintenance / Replace Temporary 603 SIGNS ACTIVITY DESCRIPTION Install new signs and maintain and replace

More information

IMPROVEMENT CONCEPTS

IMPROVEMENT CONCEPTS IMPROVEMENT CONCEPTS for the South Novato Transit Hub Study Prepared by: January 11, 2010 DKS Associates With Wilbur Smith Associates IMPROVEMENT CONCEPTS Chapter 1: Introduction 1. INTRODUCTION The strategic

More information

Calendar Binder Printable Pack. 38 FREE Printable

Calendar Binder Printable Pack. 38 FREE Printable Calendar Binder Printable Pack 38 FREE Printable Pages @MotherhoodOnADime.com If you would like to find out how we utilize our calendar binder and these printable pages, please visit my post at MotherhoodOnADime.com.

More information

2015 Community Report Chaparral

2015 Community Report Chaparral 5 Chaparral Produced for the New Mexico Department of Transportation, Traffic Safety Division, Traffic Records Bureau, Under Contract 58 by the University of New Mexico, Geospatial and Population Studies,

More information

TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA

TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA PREPARED FOR: UNIVERSITY OF PENNSYLVANIA HEALTH SYSTEM 34 CIVIC CENTER BOULEVARD PHILADELPHIA, PA 1987 (61)

More information

January 13, 2012 AACE Annual Meeting, Wickenburg, AZ. I-15 in Arizona. Its Past, Present, and Future

January 13, 2012 AACE Annual Meeting, Wickenburg, AZ. I-15 in Arizona. Its Past, Present, and Future January 13, 2012 AACE Annual Meeting, Wickenburg, AZ I-15 in Arizona. Its Past, Present, and Future Jean A. Nehme, Ph.D., P.E. State Bridge Engineer, ADOT Presentation Overview Location, History, and Photographs

More information

PET(S) FIRST & LAST NAME: January 2019

PET(S) FIRST & LAST NAME: January 2019 January 2019 1 2 3 4 5 New Year's Day 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 SPECIAL TE We will not have Doggie available during these dates: *3/29-4/7, 4/19-4/21, 5/24-5/27,

More information

2015 Community Report Los Lunas

2015 Community Report Los Lunas 25 Los Lunas Produced for the New Mexico Department of Transportation, Traffic Safety Division, Traffic Records Bureau, Under Contract 58 by the University of New Mexico, Geospatial and Population Studies,

More information

2014 Community Report Los Lunas

2014 Community Report Los Lunas 4 Los Lunas Produced for the New Mexico Department of Transportation, Traffic Safety Division, Traffic Records Bureau, Under Contract 58 by the University of New Mexico, Geospatial and Population Studies,

More information

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015 SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment

More information

MONTHLY RIDERSHIP AND PERFORMANCE REPORT. August 2018 Monthly Performance Report

MONTHLY RIDERSHIP AND PERFORMANCE REPORT. August 2018 Monthly Performance Report MONTHLY RIDERSHIP AND PERFORMANCE REPORT August 2018 Monthly Performance Report Ridership AUGUST, 2018 MONTHLY PERFORMANCE REPORT Ridership for the month of August decreased 2.6% when compared to August

More information

TTI TRAFFIC SAFETY CONFERENCE. John A. Barton, P.E.

TTI TRAFFIC SAFETY CONFERENCE. John A. Barton, P.E. TTI TRAFFIC SAFETY CONFERENCE John A. Barton, P.E. Introduction TxDOT Mission Work with others to provide safe and reliable transportation solutions for Texas. 2 Mission Zero Is a Journey toward: Zero

More information

MEMORANDUM. Figure 1. Roundabout Interchange under Alternative D

MEMORANDUM. Figure 1. Roundabout Interchange under Alternative D MEMORANDUM Date: To: Liz Diamond, Dokken Engineering From: Subject: Dave Stanek, Fehr & Peers Western Placerville Interchanges 2045 Analysis RS08-2639 Fehr & Peers has completed a transportation analysis

More information

Construction Staging Area 4 Avenue Road

Construction Staging Area 4 Avenue Road REPORT FOR ACTION Construction Staging Area 4 Avenue Road Date: September 27, 2017 To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto and East York District

More information

Metro Highway Program

Metro Highway Program Metro Highway Program ACEC November 2018 I-5 North HOV and Truck Lanes 14 miles of HOV lanes in both directions 2 miles of truck climbing lanes at the south end 7 bridge modifications at: Gavin Canyon

More information

Chapter 7. Transportation Capital Improvement Projects. Chapter 7

Chapter 7. Transportation Capital Improvement Projects. Chapter 7 Chapter 7 Transportation Capital Improvement Projects Chapter 7 81 Chapter 7 Transportation Capital Improvement Projects Local Transportation Sales Tax Programs For over three decades, Santa Clara County

More information

INTERCHANGE OPERTIONS STUDY Interstate 77 / Wallings Road Interchange

INTERCHANGE OPERTIONS STUDY Interstate 77 / Wallings Road Interchange INTERCHANGE OPERTIONS STUDY Interstate 77 / Wallings Road Interchange City of Broadview Heights, Cuyahoga County, Ohio Prepared For: City of Broadview Heights Department of Engineering 9543 Broadview Road

More information

2016 Community Report Los Alamos County

2016 Community Report Los Alamos County 6 Los Alamos County Produced for the New Mexico Department of Transportation, Traffic Safety Division, Traffic Records Bureau, Under Contract 58 by the University of New Mexico, Geospatial and Population

More information

2012 Water Consumption Statistics Report. Water Services Department

2012 Water Consumption Statistics Report. Water Services Department 212 Water Consumption Statistics Report Water Services Department Issued: December 213 TABLE OF CONTENTS 212 Water Consumption Statistics Report December 213 212 GVWD Statistics Book - Notes...3 Annual

More information

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE DOYLE DRIVE DOYLE DRIVE. Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE DOYLE DRIVE DOYLE DRIVE. Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009 DOYLE DRIVE Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009 Presentation Overview Introduction Project Acceleration Construction Contracts Construction Activities Lane and Road

More information

January Florida City State Farmers Market. Opened April 1,

January Florida City State Farmers Market. Opened April 1, DECEMBER 2015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 January 2016 FEBRUARY 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

More information

2015 Community Report White Rock

2015 Community Report White Rock 5 White Rock Produced for the New Mexico Department of Transportation, Traffic Safety Division, Traffic Records Bureau, Under Contract 58 by the University of New Mexico, Geospatial and Population Studies,

More information

WIM #31 US 2, MP 8.0 EAST GRAND FORKS, MN JANUARY 2015 MONTHLY REPORT

WIM #31 US 2, MP 8.0 EAST GRAND FORKS, MN JANUARY 2015 MONTHLY REPORT WIM #31 US 2, MP 8.0 EAST GRAND FORKS, MN JANUARY 2015 MONTHLY REPORT WIM #31 EAST GRAND FORKS MONTHLY REPORT - JANUARY 2015 WIM Site Location WIM #31 is located on US 2 at mile post 8.0, southeast of

More information