PUBLIC WORKS DEPARTMENT DECEMBER 2017 UPDATE DESIGN & CONSTRUCTION DIVISION
|
|
- Christopher Brown
- 5 years ago
- Views:
Transcription
1 TESTER ROAD WATER MAIN UPGRADE PUBLIC WORKS DEPARTMENT DECEMBER 2017 UPDATE DESIGN & CONSTRUCTION DIVISION The City will be replacing an aging water main under Tester Road this year. The project will begin at the main entrance to the Monroe High School, then head south along Tester Road. The project also includes placing a new water main under SR522, which will be accomplished utilizing boring or directional drilling technology. Estimated Cost: $900,000 (Water CIP Fund) Construction Target: Fall 2017 Colacurcio Brothers, Inc is actively working on the project. Most of the new water main has been installed along Tester Road, as well as the boring, casing and water main under SR522. The contractor will finish the project this month by performing the required connections to the existing water supply network. Timeline Jan.-Apr Design July 2017 August 2017 Sept Dec Advertise to contractors Contract awarded Construction begins Construction complete 1 Page 1 of 16
2 CHAIN LAKE ROAD SHARED PATH EXTENSION The City of Monroe received a federal grant through Puget Sound Regional Council (PSRC) to design and purchase additional right-of-way for extending the shared sidewalk/path north along Chain Lake Road and end at Brown Road. The sidewalk would match to the existing sidewalk in the vicinity of Rainier View Road. Complete funding for construction will need to be secured before the city programs the project's final phase. Estimated Design Cost: $803,250 (design & right-of-way acquisition) $219,723 Street CIP Fund $583,527 FHWA Grant Estimated Construction Cost: $2,800,000* $1,296,975 Street CIP Fund $1,515,692 FHWA Grant *Cost to construct will likely be lower based on current private development activity which will reduce the work necessary for this project. The City solicited for professional design services in November. Several firms responded to solicitation, of which the review panel short-listed three for interviews. Ultimately, the contract award offer was extended to WHPacific, Inc. The City will spend the month of December to negotiate the scope and fee for this contract, after which the Local Agency Consultant Agreement (LACA) will be presented to Council for authorization. Timeline 2018 Design Process No timeline No timeline Right-of-Way Acquisition Design/Right-of-Way Complete Construction begins Construction ends 2 Page 2 of 16
3 SIDEWALK AT-GRADE RAILROAD CROSSINGS FRYELANDS BOULEVARD & 179 TH AVENUE SE In 2015 the City received a $244,500 grant from the Community Development Block Grant (CDBG) program of Snohomish County. The purpose of this project is to provide safe pedestrian pathways across the existing railroad tracks at both the Fryelands Boulevard and 179 th Avenue SE street crossing locations. Estimated Project Cost: $291,500 $47,000 Street CIP Fund $244,500 CDBG Grant Construction Target: November 2017 BNSF has scheduled railroad flagging/spotter crew beginning January 8 th, The City s contractor (RCNW) will begin work on or a couple days before this date. Once started, the contractor will work diligently to complete the job before the end of February Timeline January 2015 Grant Awarded 2016/2017 Design Process May 2017 July 2017 January 2018 Advertise for construction Contract awarded Construction begins February 2018 Construction ends 179 th Avenue SE Fryelands Boulevard 3 Page 3 of 16
4 FAIRFIELD PARK ENTRANCE The existing entrance into Snohomish County s Fairfield Park is difficult to access for vehicles travelling north on Fryelands Boulevard. This project represents a coordinated effort with Snohomish County Parks to realign the entrance to the south and across from 156 th Street SE. The City will construct the new entrance from Fryelands Boulevard to the City Limits, and the County will extend the park s access road to connect to the new location. Construction Target: Late summer 2017 City crews have completed the City s portion of this collaborative project. We are waiting for the County to complete their culvert installation and new driveway before the new entrance is made available to the public. Timeline Spring 2016 May 2016 May 2016 August 2017 Sept Design Design completed Coordination with County Construction begins Construction ends 4 Page 4 of 16
5 SMITH STREET & PARK STREET UTILITY UPGRADES The aging water main will be replaced in Smith Street and a portion of Park Street. Additionally, the sewer main in Smith Street will be upgraded to increase functionality. The project design documents will be prepared in 2017, with actual construction occurring the following year in Estimated Project Cost: $710,000 $355,000 Water CIP Fund $355,000 Sewer CIP Fund Construction Target: Spring/Summer 2018 The design process is underway and will be ongoing throughout the remainder of Timeline 2017 Design process Jan Advertise for construction Feb March 2018 July 2018 Award contract Construction begins Construction ends 5 Page 5 of 16
6 DICKINSON ROAD UTILITIES PROJECT Engineering staff are developing plans to replace the aging water main under Dickinson Road, as well as address stormwater ponding issues at various locations along this road. The design efforts will occur during 2017, followed by actual construction in early summer Estimated Project Cost: $665,000 $425,000 Water CIP Fund $240,000 Storm CIP Fund Construction Target: Summer 2018 The design process is underway and will be ongoing throughout the remainder of Timeline 2017 Design process May 2018 Advertise for construction June 2018 June 2018 Sept Contract award Construction begins Construction ends 6 Page 6 of 16
7 AIRFIELD WATER MAIN UPGRADE PROJECT The City is developing plans to increase the size of the water main adjacent to First Air Field (Monroe airport). The objective is to increase water supply to the Foothills area during peak demand or emergencies. Design will occur during 2017 with actual construction commencing in the spring of Estimated Project Cost: $480,000 Water CIP Fund Construction Target: Summer 2018 Engineering staff are working on the design development, and coordinating with Snohomish County Fairgrounds for potential use of their property to avoid critical areas and existing utilities. The design process will be ongoing throughout Timeline 2017 Design process Feb Advertise for construction Feb March 2018 June 2018 Contract award Construction begins Construction ends 7 Page 7 of 16
8 191 ST AVENUE SE EXTENSION The concept of this project originated from concerns regarding increased traffic on Chain Lake Road and the need for a second route for neighborhoods that have Rainier View Road as their only access to Chain Lake Road. In January and February of 2017 there were a series of council meetings to discuss the possibility of extending 191 st Avenue SE south through the US2 Bypass corridor, including four possible alignments that connected at various locations along Chain Lake Road or to Galaxy Way. An Open House was conducted in January 2017 to receive public input on the project. The direction given to staff was to pursue a road alignment that best followed the original 191 st Ave SE roadbed, but include a walking path as part of the roadside elements. Estimated Project Cost: $2,500,000 Streets CIP Construction Target: Unknown WSDOT has given positive response to this project, meaning that the State would be willing to lease their property to the City once they have reviewed and agree to the proposed construction plans. Engineering staff are working with WSDOT to fast-track their lease process ahead of preparing plans and specifications. We anticipate receiving a final draft of the lease agreement some time in December. Potential Timeline 2018 / 2019 Design process 2018 / 2019 Right-of-Way Agreements 2020 / 2021 Construction 8 Page 8 of 16
9 BLUEBERRY LANE / KELSEY STREET INTERSECTION IMPROVEMENTS This intersection has long been known as being problematic and congested at times. Improving the intersection is complicated due to the immediate proximity of Burlington Northern Santa Fe railroad and US2. The flow of traffic is sensitive to the tracks being clear and the US2 signal phasing. In December 2016 and January 2017 a series of council meetings were held to discuss potential design options. Additionally, an Open House was conducted in January 2017 to receive public input on design options. Staff are exploring a design that would create a second, northbound lane along Kelsey Street. This lane would begin at North Street and provide a turn pocket for vehicles wanting to turn onto Blueberry Lane, and also additional queuing capacity for left turns at US2. Estimated Project Cost: $450,000 Street CIP Construction Target: Unknown Engineering staff applied for a grant through the Transportation Improvement Board (TIB) that would assist in funding the design and construction phases of this project. Unfortunately, this project was not selected for award. Staff are evaluating options, including alternate funding sources. Potential Timeline 2018 Design Phase 2019 Construction Phase 9 Page 9 of 16
10 TJERNE PLACE SE STREET IMPROVEMENTS Tjerne Place SE (a.k.a. Oaks Street) is located between Woods Creek Road and Old Owen Road, behind the Monroe Plaza where Albertson s used to be. This private road sees increasing traffic as drivers look to other routes to avoid traffic on US2. The City is interested in converting the road to public right-of-way and making improvements to become similar to other segments of Tjerne Place SE. Additionally, a signalized intersection would be proposed where Tjerne Place SE connects to Old Owen Road. Estimated Project Cost: $6,950,000 Street CIP Fund Construction Target: Unknown Engineering staff applied for a Transportation Improvement Board (TIB) grant that would contribute to funding design, right-of-way acquisition and construction of this project. Unfortunately, this project was not selected for award. Staff are evaluating options, including alternate funding sources. Potential Timeline 2018 Design process 2018 & 2019 Right-of-Way Acquisition 2019/2020 Construction Begins 2020/2021 Project Completion CONCEPTUAL TJERNE PLACE SE STREET IMPROVEMENTS 10 Page 10 of 16
11 2017 STREET PRESERVATION PROGRAM The City has established a Transportation Benefit District (TBD) to help maintain existing streets. Maintenance efforts include practices such as overlaying with new asphalt, adding new aggregate to the road surface (chip sealing), replacing lost binder oils on the surface (fog seal), and filling in cracks with elastomeric material (crack sealing). The City has a program that determines best use of TBD funds to maximize maintenance efforts toward our citywide street system. Additionally, the asphalt overlays will be combined with Snohomish County s annual overlay program for efficiency and competitive pricing opportunities. Other treatments may be coordinated with Snohomish County, other local agencies, or pursued as a capital project using contractor bids to perform the work. For overlays, existing sidewalk ramps adjacent to the project area will be reviewed and reconstructed as necessary to be compliant with current ADA standards. All treatments are anticipated to occur during the dry summer months. The City will contract with Snohomish County forces through our Inter Local Agreement (ILA). The County will perform the fog sealing, chip sealing, and asphalt overlay work in August. All asphalt overlay work has been completed. Small items remain to be completed, including some pavement markings, signage and incidental cleanup work. The remaining work is anticipated to be ongoing throughout December and into January as weather conditions allow. Street Name Where Treatment 155 th St SE 170 th Ave SE to 171 st Ave SE crack seal / other 157 th Pl SE 158 th Pl SE to 179 th Ave SE asphalt overlay 158 th Pl SE SW End to 179 th Ave SE asphalt overlay 160 th St SE 175 th Dr SE to 179 th Ave SE asphalt overlay 170 th St SE 155 th St SE to 154 th St SE crack seal / other 171 st Ave SE 154 th St SE to Wales St SE chip seal 171 st Ave SE Wales St SE to End asphalt overlay 178 th Ave SE Main St to 160 th St SE asphalt overlay 182 nd Ave SE W. Columbia St to 154 th St SE asphalt overlay Arthur Lane W Hill St to W Elizabeth St crack seal / other Chain Lake Rd Rainier View Rd to Brown Rd asphalt overlay Country Crescent roundabout to Woods Cr Rd chip seal Elizabeth St W end to N Kelsey St chip seal Fryelands Blvd Main St to 152 nd St SE (NB lanes) asphalt overlay Old Owen Rd US2 to Oaks St asphalt overlay Sawyer St 171 st Ave SE to east end crack seal / other Woods Creek Rd Oaks St to city limits chip seal S. Madison St Main St to Powell St asphalt overlay 11 Page 11 of 16
12 GRANTS The City actively pursues other sources of project funding through grants. Grants sources include State and Federal resources and help defray the cost of maintaining and improving the City of Monroe's infrastructure. The following is a summary of grant activity that Public Works has received. Active Grants: Grant Amount Description Sidewalk Railroad Crossing $244,500 Fryelands Blvd & 179 th Ave SE sidewalks Chain Lake Rd Shared Path Extend the concrete sidewalk to Brown Rd. $173,000 Design $488,725 Right-of-Way Acquisition $1,515,692 Construction The following list represents grant application efforts and their respective grants current status: Chain Lake Road Phase 2a: This project would extend the existing wide sidewalk along the west side of Chain Lake Road north to Brown Road (City Limits). The City has received federal grants (PSRC) to fund the construction phase and the design and rightof-way phases. Requested Grant: $2,432,867 (CMAQ/STP) Partially Awarded. Requested Grant: $234,723 (WSDOT Ped/Bike) Not Awarded. US-2 Shared Use Path: Both federal and state grants have been applied for to fund the design phase of a new sidewalk segment along Highway 2, specifically along the north side between Cascade View Drive and 179th Avenue NE (fairgrounds area). Requested Grant: $90,250 (CMAQ/STP) Awarded. Requested Grant: $107,190 (WSDOT Ped/Bike) Not Awarded. Funds not to be obligated (released) until th Street SE/179 th Avenue SE Signal: This location was identified in the Comprehensive Plan as operating at a substandard level of service. As such, the recommended improvement listed in the City s streets Capital Improvement Plan is a signalized intersection. Engineering staff applied for a competitive grant through the Transportation Improvement Board s (TIB) Urban Arterial Program. UPDATE: Requested Grant Amount: $674,100 Not Awarded. 179 th Avenue SE Sidewalk Extension: City staff are looking to extend sidewalk along 179 th Avenue SE, continuing where new sidewalk ended during the 2016 capital improvement efforts. Engineering staff applied for a competitive grant through the Transportation Improvement Board s (TIB) Sidewalk Program. If awarded, new sidewalk would be installed along the west side of 179 th Avenue SE from 157 th Place SE north to 154 th Street SE. UPDATE: Requested Grant Amount: $624,900 Not Awarded 12 Page 12 of 16
13 191 st Avenue SE Extension: The City has a strong interest in extending 191 st Avenue SE southerly through the unopened US2 Bypass corridor. This project which would create a second access point to neighborhoods utilizing Rainier View Road for access. The proposed road alignment would follow along the north boundary of Walmart and connect to the roundabout at Chain Lake Road and Kelsey Street. Staff continue to work with WSDOT to obtain their approval for this potential project. Engineering staff applied for a competitive grant through the Transportation Improvement Board s (TIB) Urban Arterial Program to fund a significant portion of the design and construction costs. UPDATE: Requested Grant Amount: $2,700,000 Not Awarded Oaks Street Improvements: Engineering staff applied for a competitive grant through the Transportation Improvement Board s (TIB) Urban Arterial Program. If awarded, the grant would fund a significant portion of the design, right-of-way acquisition, and construction costs to improve Oaks Street to a roadway similar to Tjerne Place SE, including a signal at the intersection of Oaks Street and Old Owen Road. UPDATE: Requested Grant Amount: $5,949,150 Not Awarded Blueberry Lane / Kelsey Street Intersection Improvements: The City has a strong interest in improving this intersection by creating a third, northbound lane that will allow additional queuing and left turn movements at this intersection. Engineering staff applied for a competitive grant through the Transportation Improvement Board s (TIB) Urban Arterial Program to fund a significant portion of the design and construction costs. If successful, design would be completed in 2018, with construction likely in UPDATE: Requested Grant Amount: $508,130 Not Awarded 2018 Arterial Preservation Program: Historically, this grant has provided approximately $415,000 each year to assist in maintaining our existing roadways. Engineering staff have asked for funds to help defray the cost of overlaying Main Street between 179 th Avenue SE and Kelsey Street. This would include upgrading adjacent sidewalk ramps to current standards. Grant award notifications are anticipated in late November. Requested Grant Amount: $518,000. UPDATE: Grant Amount Awarded: $440,000 Blueberry Lane Stormwater Repairs The City has applied for a Department of Ecology Water Quality grant to help with design and construction costs to replace the existing stormwater infiltration facility located under Blueberry Children s Park. This project will fix localized flooding issues that occur on Blueberry Lane during larger storm events. We anticipate DOE s list of awards to be released in January Requested Grant Amount: $1,203,566 City Match Required: $401, Page 13 of 16
14 Grants Status Project Agency Program Ask Date Recommended Date Awarded Date Encumbered Date Obligated Date Collected As of Closed Woods Creek Road PSRC CMAQ $ 1,718,000 4/23/2014 $ 1,718,000 12/23/2015 $ 1,718,000 12/23/2015 $ 1,718,000 12/16/2014 $ 1,718,000 12/16/2014 $ 1,451, /28/2017 Obligated Pedestrian RR Crossings CDBG Public Facilities/Infrastructure $ 244,500 11/10/2014 $ 244,500 6/1/2015 $ 244,500 6/1/2015 $ 244,500 $ 244,500 $ 6, /19/2016 Awarded US2 Sidewalk Extension PSRC CMAQ $ 90,250 4/26/2016 $ 90,250 12/27/2016 $ 90,250 12/27/2016 Awarded Chain Lake Rd Trail Extension PSRC CMAQ $ 2,432,867 4/22/2016 $ 1,515,692 11/4/2016 $ 1,515,692 12/27/2016 Awarded Chain Lake Rd Trail Extension PSRC CMAQ $ 661,725 4/23/2014 $ 583,527 1/15/2016 $ 583,527 1/15/2016 Encumbered 2017 Asphalt Overlay TIB APP $ 750,000 8/16/2016 $ 417,726 11/21/2016 $ 417,726 3/31/2017 $ 417,726 12/13/2016 $ 417,726 12/13/2016 $ 15, /31/2017 Encumbered Monroe Gateway PSRC RTCC $ 5,575,000 3/29/2013 $ 246,000 10/30/2013 $ 246,000 10/30/2013 $ 126, /30/2015 Denied Monroe Gateway 2nd Attempt PSRC RTCC $ 650,000 3/9/2017 Closed 2016 LED Lighting upgrades TIB Relight Washington $ 11,314 11/10/2016 $ 6,170 11/16/2016 $ 6,170 11/16/2016 $ 6, /19/2016 Obligated Pothole Repairs TIB Emergency Repair Program $ 50,000 5/19/2017 $ 50,000 5/26/2017 $ 50,000 5/26/2017 $ 50,000 6/13/2017 $ 50,000 8/15/2017 Looking 2017 LED Lighting upgrades TIB Relight Washington $ 11,300 Denied 179th Ave Sidewalks TIB SP $ 624,900 8/18/ /17/2017 Denied 191st Ave SE Extension TIB UAP $ 1,657,550 8/18/ /18/2017 Denied Oaks Street Improvements TIB UAP $ 5,949,150 8/18/ /19/2017 Denied 147th St / 179th Ave Signal TIB UAP $ 674,100 8/18/ /20/2017 Denied Blueberry / Kelsey Intersection TIB UAP $ 508,100 8/18/ /21/2017 Awarded Main Street Grind/Overlay TIB APP $ 518,000 8/18/2017 $ 440,000 11/22/2017 Applied Blueberry Lane Stormwater Repair DOE WQ $ 1,203,566 10/16/2017 GRANT SUMMARY TABLE 14 Page 14 of 16
15 PUBLIC WORKS DEPARTMENT DECEMBER 2017 UPDATE OPERATIONS & MAINTENANCE The maintenance work that City staff completes on a regular basis includes a diverse variety of programmatic activities. Examples include water main valve and hydrant operations, storm drain cleaning and inspection, right of way vegetation management, and asphalt surface repairs. During these activities O&M staff often note smaller scale capital improvement projects such as replacing a section of obsolescent water main, updating street lighting, refurbishing a failed drainage infiltration system, or improving ADA access ramps at an intersection. These projects are minor enough in scope and budget to make it more cost effective to complete the work with in-house labor due to the lower labor rates and minimal administrative overhead as compared with the more traditional design, bid, build process. : Listed below is an update for the small project and maintenance schedule for Water System Valve Turning and System Flushing Fall/Winter 2017/2018 Annual system maintenance includes turning every valve and operating every hydrant in the water system. This activity is integral to maintain water quality by removing accumulated sediment from the system. Work is 50% complete as of 11/1/17. Sewer Collections System Dead End Main Cleaning Fall/Winter 2017/2018 Dead end sewer mains pose the greatest risk of clogging due to the often lower flow volumes as compared to non-dead end mains. In order to mitigate this risk high pressure water jetting and vacuum clearing of debris is performed biannually. Public Works Shop Facility Expected completion in 2018 The Design Builder (ET Environmental) has completed 75% foundation plan sets and City staff have done a full review. The Design Builders submittal to the City for permitting of the foundation is expected in the first week of December. Construction is expected to start in April of 2018 with completion by December, Page 15 of 16
16 Operational Statistics NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV WWTP Total Flow (millions of gallons) Average Daily flow (Millions of gallons) Peak Daily Flow (millions of gallons) Removal Rate 98% 99% 95% 81% 80% 91% 93% 98% 95% 97% 98% 98% 98% Biosolids produced (wet tons) Private Development (hours) Capital Projects (hours) Street Sweeping (lane miles) Utility Locates Water sold (millions of gallons) (15th to 15th) Page 16 of 16
2016 PSRC REGIONAL & KING COUNTYWIDE EASTSIDE FUNDING AWARDS. Eastside Transportation Partnership September 9, 2016
2016 PSRC REGIONAL & KING COUNTYWIDE EASTSIDE FUNDING AWARDS Eastside Transportation Partnership September 9, 2016 1 2 PSRC 2016 Project Selection Process 2018-2020 Estimated FHWA Funds Available: (Summary)
More informationCITY OF PORT TOWNSEND, WASHINGTON CAPITAL IMPROVEMENT PLAN
Page 1 of 3 CITY OF PORT TOWNSEND, WASHINGTON CAPITAL IMPROVEMENT PLAN The six-year Capital Improvement Plan (CIP) includes capital projects for 2017 2022. This plan includes capital projects that add
More informationSOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015
SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment
More informationTransportation. Background. Transportation Planning Goals. Level of Service Analysis 5-1
Transportation portion of the city s stormwater utility, and state road and fuel taxes. Background The transportation needs of the City of Lacey and its planning areas are met by a growing multimodal network
More informationFREQUENTLY ASKED QUESTIONS
THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on
More informationCITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE
CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE TUESDAY, DECEMBER 5, 2017 1 DISCUSSION TOPICS Update of Infrastructure Action Plan (IAP) o Sidewalk and Roadway projects
More informationCAPITAL FUND 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS
9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS 2019-2023 9510 STREET & SIDEWALK IMPROVEMENTS - 01 STREET AND SIDEWALK MAINTENANCE PROGRAM $1,250,000 $0 $1,250,000
More informationBrigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction
Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction 550 North to 650 North $ 1,750,000 $ 1,582,113 To widen an existing bridge on 1200 West over Box Elder Creek that will
More informationDraft Results and Open House
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi
More informationCity of Grand Forks Staff Report
City of Grand Forks Staff Report Service/Safety Committee December 15, 2015 City Council December 21, 2015 Agenda Item: Amendment No. 1 to Engineering Services Agreement with CPS for City Project No. 7143,
More informationTransportation Committee Revised Project Scope and Cost Estimate. November 23, 2015
Transportation Committee Revised Project Scope and Cost Estimate November 23, 2015 1 Today s Topics Revised Project Scope Revised Cost Estimate Municipal Approval Action 2 3 Revised Project Scope Project
More informationFREQUENTLY ASKED QUESTIONS
THE PROJECT Last updated on 2/19/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on
More informationTransit Project Delivery Status Report. Significant Issues
Item 1 Transit Project Delivery Status Report Significant Issues Presented By K.N. Murthy Executive Director Construction Committee 1 I-405 Sepulveda Pass Closure Construction Committee I-405 Sepulveda
More informationVan Ness Transit Corridor Improvement Project. Engineering, Maintenance and Safety Committee March 25, 2015
Van Ness Transit Corridor Improvement Project Engineering, Maintenance and Safety Committee March 25, 2015 Project Need 16,000 daily passenger boardings within the project corridor Average bus speed 8
More informationAgenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan
Utility Undergrounding Strategies & Laguna Canyon Road Master Plan January 17, 2017 City Council Meeting 2 Agenda Progress since March 2016 Status of undergrounding and road widening between El Toro Rd.
More informationBROWARD BOULEVARD CORRIDOR TRANSIT STUDY
BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,
More informationCapital Improvement Plan Review
City of Manhattan Beach Public Works Department Fiscal Year 2014/2015 2018/2019 Capital Improvement Plan Review Community Meeting: April 10, 2014 Objectives Creating the Capital Improvement Plan Funding
More informationFALL 2017 ADVERTISING SCHEDULE
INFRASTRUCTURE FALL 2017 ADVERTISING SCHEDULE CONSTRUCTION AND MATERIAL SUPPLY TENDERS Manitoba Infrastructure Contract Services Branch 1630 215 Garry Street Winnipeg, MB R3C 3P3 204 945 3637 The Construction
More informationWentzville Parkway South Phase 2 & 2A
Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total
More informationI-820 (East) Project Description. Fort Worth District. Reconstruct Southern I-820/SH 121 Interchange
I-820 (East) Project Description Fort Worth District Reconstruct Southern I-820/SH 121 Interchange I-820 from approximately 2,000 feet north of Pipeline Road/Glenview Drive to approximately 3,200 feet
More informationACTION TRANSMITTAL No
Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: January 4, 2016 TO: ACTION TRANSMITTAL No. 2016-19 TAC Funding and Programming Committee PREPARED BY: Joe Barbeau, Senior
More informationI-4 Beyond the Ultimate. Florida Transportation Builders Association January 18, 2019
I-4 Beyond the Ultimate Florida Transportation Builders Association January 18, 2019 FDOT District 5 Improving Mobility & Safety in Central Florida FDOT District 5 is: Designing and building a better Interstate
More informationDraft Results and Recommendations
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Recommendations Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System
More informationRTID Travel Demand Modeling: Assumptions and Method of Analysis
RTID Travel Demand Modeling: Assumptions and Method of Analysis Overall Model and Scenario Assumptions The Puget Sound Regional Council s (PSRC) regional travel demand model was used to forecast travel
More informationMobility Management: Caltrain
Mobility Management: Caltrain Community Relations Committee October 4, 2017 Agenda Item 7 Presentation Outline Operating Statistics Ridership On-time Performance Fleet Reliability Capital Program Review
More informationSection III Transportation and Stormwater Projects Receiving Additional Funding Project Detail Sheets Alphabetical Listing by Project Name Five Year
Section III Transportation and Stormwater Projects Receiving Additional Funding Project Detail Sheets Alphabetical Listing by Project Name Five Year Capital Improvement Plan FY2015/2016 through FY2020
More informationMobility Corridor Updates. Transit & Active Transportation Projects
Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate
More informationCommittee Report. Transportation Committee. Business Item No
Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope
More informationBINGHAMTON METROPOLITAN TRANSPORTATION STUDY
BINGHAMTON METROPOLITAN TRANSPORTATION STUDY ANNUAL LISTING OF FEDERAL AID PROJECT OBLIGATIONS FEDERAL FISCAL YEAR Federal regulations require an annual listing of transportation projects, including investments
More informationUS 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017
US 29 Bus Rapid Transit Planning Board Briefing February 16, 2017 Project Goals Improve the quality of transit service Improve mobility opportunities and choices Enhance quality of life Support master
More informationWaco Rapid Transit Corridor (RTC) Feasibility Study
Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM
More informationMobility Program. City of St. Augustine. Mobility Program Update. City Commission Meeting Monday, August 27, Moving People Through History
Mobility Program City of St. Augustine Mobility Program Update City Commission Meeting Monday, August 27, 2018 Moving People Through History Program Update: North Florida Safe Streets Summit 2018 Program
More informationBusiness Advisory Committee. November 3, 2015
Business Advisory Committee November 3, 2015 1 Today s Topics DEIS Cost Estimate 2 Assumptions Revised Cost Estimate Revised Project Scope Cost Estimate Overview Position Statement Discussion Municipal
More informationToo Good to Throw Away Implementation Strategy
Too Good to Throw Away Implementation Strategy Council Briefing by Sanitation Services October 4, 2006 Purpose of Briefing Summarize preparations for Too Good To Throw Away recycling services FY07 Recommend
More informationChicago to St. Louis High-Speed Rail. IDOT District 8 Crossings. July 29, 2015
Chicago to St. Louis High-Speed Rail IDOT District 8 Crossings July 29, 2015 1 History: Chicago-St. Louis Corridor» IDOT has actively developed the Chicago to St. Louis corridor since the mid 1980 s» In
More informationApril 2011 April 2011 Presented by Robert Spaulding & Alan Eirls
April 2011 April 2011 Presented by Robert Spaulding & Alan Eirls A Partnership Between the Coeur d Alene Tribe, FTA, the State of Idaho, the Local MPO, and Kootenai County. Current System The Citylink
More informationCity Hall 539 Phoenix Street South Haven, Michigan Telephone (269) Fax (269)
City of South Haven City Hall 539 Phoenix Street South Haven, Michigan 49090-1499 Telephone (269) 637-0700 Fax (269) 637-5319 Dunkley and Black River Infrastructure Improvements Dunkley - Dyckman Avenue
More informationBusiness Advisory Committee. July 7, 2015
Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS
More informationMobility Program. City of St. Augustine. Mobility Program Update. City Commission Meeting Monday, October 22, Moving People Through History
Mobility Program City of St. Augustine Mobility Program Update City Commission Meeting Monday, October 22, 2018 Moving People Through History Program Update: Activity Management Progress to Date Level/Initiative
More informationSAN RAFAEL CITY COUNCIL AGENDA REPORT
Agenda Item No: 8.b Meeting Date: December 19, 2016 Department: PUBLIC WORKS SAN RAFAEL CITY COUNCIL AGENDA REPORT Prepared by: Bill Guerin, Public Works Director City Manager Approval: File No.: 18.01.79
More informationEssex Junction Train Station Access and Scoping Study Presentation of Transportation Alternatives
Essex Junction Train Station Access and Scoping Study Presentation of Transportation Alternatives Village of Essex Junction Chittenden County Regional Planning Commission RSG, Inc. Scott & Partners Architectural
More informationLAX Specific Plan Amendment Study. CONCEPT DEVELOPMENT Public Meeting Series #5 August 23 & 26, 2006
LAX Specific Plan Amendment Study CONCEPT DEVELOPMENT Public Meeting Series #5 August 23 & 26, 2006 Agenda Background on public planning process Regional planning update LAWA progress on settlement commitments
More informationMETRO Orange Line BRT American Boulevard Station Options
METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN
More informationProject Budget and Schedule Status
Item 44 Program Management Project Budget and Schedule Status Project Schedules* Project 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Expo Phase I Orange Line Extension I-405 Sepulveda
More informationUtility work, road construction substantially done on Fourth Street
November 2010 Fourth Street in downtown is reopen to vehicle traffic between Minnesota and Broadway streets. Utility relocation and road construction are substantially complete there. Utility work, road
More informationWestern ND Meeting. February 19, 2014 Grant Levi, NDDOT Director
Western ND Meeting February 19, 2014 Grant Levi, NDDOT Director 1 Traffic Trends in North Dakota 2 Truck Traffic 2008 3 Truck Traffic 2012 4 Average Daily Traffic 5 ND Vehicle Miles Traveled Statewide
More informationPublic Works Department, Capital Improvement Program Project Tracking
Community Facilities Name CF-01 Eastshore State Park/Powell Street Bioswale Seeking grant funding. TT CF-02 South Bayfront Bridge and Horton Landing Park CF-03 / - 04 Transit Center Updated plans are being
More informationFederal Way Link Extension
Federal Way Link Extension Draft EIS Summary Route & station alternatives and impacts Link Light Rail System Map Lynnwood Mountlake Terrace Lynnwood Link Extension Shoreline 14th Northgate 40 Northgate
More informationHarlem Avenue between 63 rd and 65 th
Harlem Avenue between 63 rd and 65 th Community Advisory Group Meeting #3 December 1, 2017 Bedford Park Public Library 1 Meeting Agenda 1. Welcome/Introductions (3 mins) 2. Project Overview and Re-Cap
More information5. OPPORTUNITIES AND NEXT STEPS
5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours
More informationChallenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007
EAST-WEST CORRIDOR Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007 Presentation Agenda Project Overview / Purpose and Need Highway Component Transit Component
More informationCITY OF BLAINE 435 Martin Street, #3000 BLAINE, WA BUS: FAX:
435 Martin Street, #3000 BLAINE, WA 98230 BUS: 360.332.8311 FAX: 360.332.8330 www.cityofblaine.com September 10, 2018 To: From: Subject: City Council Department Heads Michael Jones, City Manager Jeffrey
More informationMobility Corridor Updates. Transit & Active Transportation Projects
Mobility Corridor Updates Transit & Active Transportation Projects Laura Cornejo, DEO Regional Planner Regional Operator Metro is LA County s Regional Builder/Funder Rail Bus Service (Metro/Muni/Local)
More informationRecommended Transportation. Capital Improvement Program
Recommended 2018-2022 Transportation Capital Improvement Program 1 Overview 2017 Review 2018-2022 Considerations 2018-2022 Recommended CIP 2 Limited Resources are Directed to the Highest Priority Number
More informationState Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009
State Regulatory Affairs and Local Relations Update ATC Customer Meeting November 19, 2009 Project Certification Steve Parker Manager State Regulatory Affairs CA/CPCN Applications (Filed/Ordered/Under
More informationSTH 60 Northern Reliever Route Feasibility Study Report
#233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development
More informationApril 2010 April 2010 Presented by Alan Eirls
April 2010 April 2010 Presented by Alan Eirls A Partnership Between the Coeur d Alene Tribe, the State of Idaho, the KMPO, and Kootenai County. Current System The Citylink system began on the Coeur d Alene
More informationMOTION NO. M Preferred Alternative for the Puyallup Station Access Improvement Project
MOTION NO. M2014 64 Preferred Alternative for the Puyallup Station Access Improvement Project MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 8/14/14 8/28/14 Recommendation
More informationPeninsula Corridor Electrification Project (PCEP)
Peninsula Corridor Electrification Project (PCEP) Q4 Quarterly Update #11 April 1 June 30, 2017 JPB Board Meeting August 3, 2017 Agenda Item # 8a Electrification - Infrastructure Design Build Contract
More informationTable of Contents INTRODUCTION... 3 PROJECT STUDY AREA Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS...
Crosshaven Drive Corridor Study City of Vestavia Hills, Alabama Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA... 3 Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS...
More informationState Avenue Corridor Bus Rapid Transit (BRT)
State Avenue Corridor Bus Rapid Transit (BRT) Moving Forward Incrementally April 2010 State Ave. BRT Update Bus Rapid Transit Overview State Ave. Alternatives Analysis Results What s Coming Up Right Away!
More informationRolling Road (Route 638) Widening Project
Rolling Road (Route 638) Widening Project From: 0.369 Mile North of Fairfax County Parkway (Route 286) To: Old Keene Mill Road (Route 644) State Project No. 0638-029-156, P104, R204, C504; UPC 5559 Public
More informationBOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension
Date of Meeting: July 20, 2017 # 6 BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM SUBJECT: ELECTION DISTRICT: CRITICAL ACTION DATE: STAFF CONTACTS: Design Endorsement for Sterling Boulevard Extension
More informationOperating & Maintenance Cost Results Report
Operating & Maintenance Cost Results Report Prepared for: Hennepin County Regional Railroad Authority Prepared by: Connetics Transportation Group Under Contract To: Kimley-Horn and Associates FINAL June
More informationRecommendation for 2017 PSRC Funding Transportation Policy Board - June 8, 2017
Recommendation for 2017 PSRC Funding Transportation Policy Board - June 8, 2017 Background PSRC s 2017 funding: Rural Town Centers and Corridor program Regional FTA competition May - Board released projects
More informationFlorida s Turnpike Enterprise. Incident Management Program for All Levels & Specialty Towing & Roadside Repair (STARR)
Florida s Turnpike Enterprise Incident Management Program for All Levels & Specialty Towing & Roadside Repair (STARR) Florida s Turnpike System Largest Toll System in Florida 460 Centerline Miles 2 Million
More informationPUBLIC INFRASTRUCTURE PROJECTS
PUBLIC INFRASTRUCTURE PROJECTS FM 664 / OVILLA ROAD WIDENING & IMPROVEMENTS FM 664 / OVILLA ROAD CONNECTS US 287 WITH I-45 (SOURCE: TEXAS DEPARTMENT OF TRANSPORTATION. 2016 FM 664 / OVILLA ROAD WIDENING
More informationWelcome. Green Line in Your Community
Welcome Green Line in Your Community Today's session will provide you with information about Administration's recommendation for connecting the Green Line in the Beltline to Victoria Park and Inglewood/Ramsay
More informationAppendix E Water Supply Modeling
Supply Modeling Modesto Irrigation District Treatment Plant Expansion Project Modeling I. Introduction The Modesto Irrigation District (MID) is situated adjacent to and north of the Tuolumne River. Over
More informationStrategies to keep people and goods moving in and through Seattle
Strategies to keep people and goods moving in and through Seattle SR 99 Closure and the Seattle Squeeze 2018-2024 DON Information Session Department of Transportation Delridge Community Center November
More informationMUNCIPAL WORK PROGRAMS FY 2015/ /20. MPO Transportation Improvement Program 2015/ /20 Page 9-1
MUNCIPAL PROGRAMS BELLEAIR 2000 Curb/Sidewalk 35 2001 Roadway Projects 2,500 = ; = Local Funds 35 MPO Transportation Improvement Program 2015/16 2019/20 Page 9-1 MUNCIPAL PROGRAMS BELLEAIR BEACH 3000 Resurface/curb
More informationSAINT CHARLES COUNTY ROAD BOARD Minutes of March 21, 2018
SAINT CHARLES COUNTY ROAD BOARD Minutes of March 21, 2018 The Wednesday, March 21, 2018, meeting of the St. Charles County Road Board was called to order at 4:30 p.m. in Room 542 of the Administration
More informationTransportation Improvement Program (TIP) Candidate Project List for Public Review
2011-2014 Transportation Improvement Program (TIP) Candidate List for Public Review Table 1 Annual Listing Of Federal Aid Obligation For Federal Fiscal Year 2010 North Dakota s Number Transit 410083 Transit
More informationLACEY CITY COUNCIL MEETING July 09, 2015
LACEY CITY COUNCIL MEETING July 09, 2015 SUBJECT: 2016-2021 Six-Year Transportation Improvement Plan and Mitigation List RECOMMENDATION: Adopt Resolution approving the proposed 2016-2021 Six- Year Transportation
More informationI-405 Sepulveda Pass Improvements Project
I-405 Sepulveda Pass Improvements Project 26, 2012 Click to edit Master title January style Community Advisory Committee 1 Community Meeting Schedule for 2012 26-Jan CAC, Final Meeting Feb 22-Mar Community
More informationsystem performance I-820 East Loop FM 156 TxDOT is working to expand its busiest metropolitan corridors.
system performance TxDOT is working to expand its busiest metropolitan corridors. Nine of the state s 100 most congested highways are located in Tarrant County. Six of these highways will be expanded and
More informationNEWCASTLE MIDDLE SCHOOL Traffic Impact Analysis
Gibson Traffic Consultants 2802 Wetmore Avenue Suite 220 Everett, WA 98201 425.339.8266 NEWCASTLE MIDDLE SCHOOL Traffic Impact Analysis Prepared for: Renton School District Jurisdiction: City of Newcastle
More informationHusky Stadium: TMP Modernization Project
Husky Stadium: TMP Modernization Project 1 Husky Stadium: TMP History 2 Husky Stadium TMP History 1986-1987 Husky Stadium adds the north upper deck. City of Seattle and UW agree on a plan (TMP) to mitigate
More informationANDERSON PROPERTY SITE ANALYSIS
ANDERSON PROPERTY SITE ANALYSIS Introduction The Montgomery County Department of Transportation (MCDOT) initiated a feasibility study in the fall of 2012 to evaluate the need for transit service expansion
More informationMEETING DATE: October 9, 2015 ITEM 7. Authorize Expenditure of Funds and Contract Actions to Support Locomotive Lease from BNSF Railway Company
SOUTHERN CALIFORNIA REGIONAL RAIL AUTHORITY TRANSMITTAL DATE: October 2, 2015 MEETING DATE: October 9, 2015 ITEM 7 TO: FROM: SUBJECT: Board of Directors Arthur T. Leahy Authorize Expenditure of Funds and
More informationTRANSPORTATION ENGINEERING SERVICES: Street Project Management
TRANSPORTATION ENGINEERING SERVICES: Street Project Management Mission Statement Street Project Management is a department within the Division of Public Works, Transportation Engineering section. The mission
More informationCity of University Place
City of University Place City Engineering Department Six Year Transportation Improvement Plan Amended November 10, 2008 Resolution No. 604 City of University Place, Washington SIX-YEAR TRANSPORTATION PLAN
More informationHelp shape your community investment in Wake Transit. Fiscal Year 2019 Draft Work Plan Summary
Help shape your community investment in Wake Transit Fiscal Year 2019 Draft Work Plan Summary Wake County, growth and transit The Triangle is one of the fastest-growing regions in the nation. Wake County
More informationArterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014
Arterial Bus Rapid Transit System Policy Oversight Committee April 7, 2014 1 Meeting Agenda Welcome and Introductions A Line - Project Status Shelter and Pylon Development Arterial BRT Branding Update
More information5. HORIZON YEAR TRANSPORTATION MASTER PLAN-COST ESTIMATES
5. HORIZON YEAR TRANSPORTATION MASTER PLAN-COST ESTIMATES 5.1 INTRODUCTION This chapter of the TMP presents an opinion of probable cost estimates for the proposed Horizon Year roadway network improvements
More informationBART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010
BART Silicon Valley Berryessa Extension Project Community Update October 27, 2010 1 Agenda Welcome and Introductions Program and Project Background Project Status Project and Station Details Current and
More informationHighway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary
Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Prepared
More informationCITY OF OAKLAND INTRODUCTION
CITY OF OAKLAND CITY HALL ONE FRANK OGAWA PLAZA 3RD FLOOR OAKLAND CA 94612 City Administrator s ADA Programs Division (510) 238-4754 TDD: (510) 238-2007 : January 4, To: Mayor s Commission on Persons with
More informationTempe Streetcar. March 2, 2016
Tempe Streetcar March 2, 2016 Tempe Profile 40 sq. miles, highest density in state University Town, center of region Imposed growth boundaries (density increase) Mixed use growth/intensifying land use
More informationCity of Palo Alto (ID # 6416) City Council Staff Report
City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building
More informationKendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study
Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What
More informationCity of Grand Forks Staff Report
City of Grand Forks Staff Report Committee of the Whole December 1, 016 City Council December 19, 016 Agenda Item: Bids for City Project No. 7551 Lift Station No. 17 & 17A Rehabilitation Submitted by:
More informationDevelop ground transportation improvements to make the Airport a multi-modal regional
Project Overview TRANSPORTATION IMPROVEMENTS WHAT ARE THE PROJECT GOALS? Transportation transportation hub. Develop ground transportation improvements to make the Airport a multi-modal regional Land Use
More informationPublic Information Workshop
Public Information Workshop Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 29, 2018 Welcome to the Public Information Workshop for Harborview Road Project Development and Environment (PD&E)
More informationCorridor Management Committee. March 7, 2012
Corridor Management Committee March 7, 2012 2 Today s Topics SWLRT Project Office Update Engineering Services Procurement Update Legislative Leadership Tour Annual New Starts Report Update on Proposed
More informationExhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup
Exhibit A Sound Transit Board Resolution R2016-07 Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Access Improvement Project. RESOLUTION NO. R2016-07 Selecting
More informationGreen Line LRT: Beltline Recommendation Frequently Asked Questions
Green Line LRT: Beltline Recommendation Frequently Asked Questions June 2017 Quick Facts Administration has evaluated several alignment options that would connect the Green Line in the Beltline to Victoria
More informationJune WASHINGTON STATE DEPARTMENT OF TRANSPORTATION Alaskan Way Viaduct and Seawall Replacement Program Seattle, Washington
DESIGN DEVIATION NOs. 1 & 2 Horizontal Stopping Sight Distance and Shoulder Width Reduction SR 99 S. Holgate St to S. King St. Viaduct Replacement Stage 2 MP 29.89 TO MP 30.78 XL-3237 PIN-809936D June
More informationLink LRT: Maintenance Bases, Vehicles and Operations for ST2 Expansion
Project Number SYS-LRT Subareas All Primary Mode Impacted Link Facility Type Link Service Version Number 4.0 Date Last Modified 7/24/2008 Project Locator Map Short Project Description Construct new light
More informationCity Council Report. Mayor and City Council
City Council Report To: From: Mayor and City Council City Council Meeting: February 23, 2016 Agenda Item: 3.J Edward King, Director, Big Blue Bus, Transit Services Department Subject: Custodial and Maintenance
More information