BART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010
|
|
- Joshua Freeman
- 5 years ago
- Views:
Transcription
1 BART Silicon Valley Berryessa Extension Project Community Update October 27,
2 Agenda Welcome and Introductions Program and Project Background Project Status Project and Station Details Current and Near Term Activities Q and A 2
3 Enhancing Regional Connectivity BART Silicon Valley 16-mile extension from Fremont/Warm Springs to Santa Clara Diridon Station becomes largest transportation hub in northern California Altamont Commuter Express Capitol Corridor VTA bus and light rail Caltrain Amtrak High Speed Rail 3
4 BART Silicon Valley 16 miles of track work 5 miles of tunnel 3 above-ground stations 3 below-ground stations Maintenance yard Parking facilities 100+ daily trains Over 90,000 weekday riders $6 billion 4
5 Project Support 2000 Measure A (70.3%) Capital Funding 2008 Measure B (66.78%) Operating Funding (Requires federal Full Funding Grant Agreement of $750+million) MTC Regional Support Designated Priority Project by VTA Board $639 million commitment from state 5
6 VTA/BART Partnership Comprehensive Agreement guides implementation and operations of BART Silicon Valley Responsibilities: VTA Funding, Development and Constructing BART- Operations and Maintenance 6
7 BART Warm Springs Extension Ground Breaking August 2009 Award Second Contract Spring 2011 Project Completion Late
8 BART Silicon Valley Program Activities BART Extension will be delivered in stages Silicon Valley Berryessa Extension (SVBX) Silicon Valley Santa Clara Extension (SVSX) Corridor Preparation Warren and Kato Grade Separations Relocating Union Pacific Railroad Track Relocating utilities BART Core Modifications to existing system Vehicle Procurement Funding and Grants Communications and Outreach Real Estate Acquisition and Management Agency Coordination 8
9 Corridor Preparation Alameda County Transportation Authority Mission/Warren Grade Separation City of Fremont Kato Road Grade Separation Santa Clara Valley Water District Lower Berryessa Creek Flood Control Improvements Advance Utility Relocations 9
10 Corridor Preparation New Berryessa Creek Box Culvert Under Abel Street Bridge 10
11 Phase 1: Berryessa Extension 10 miles 2 stations Milpitas Berryessa 40 New Trains Frequent Train Service 2018 Peak Hour Headways Berryessa San Francisco/Daly City 15 minutes Berryessa Richmond 15 minutes Combined, trains every 7.5 minutes 2035 Peak Hour Headways Berryessa San Francisco/Daly City 12 minutes Berryessa Richmond 12 minutes Combined, trains every 6 minutes Operates 4 am Midnight 11
12 Future Connections Berryessa to Fremont- 15 minutes Milpitas to Oakland/City Center - 50 minutes Berryessa to San Francisco/Montgomery Station - 64 minutes Approximate times are based on current BART schedules and estimated train travel times for new extension. 12
13 Berryessa Extension Funding Status Received Federal Environmental Clearance June 2010 Required to get federal funding Requesting $900 million Federal Funding Grant Anticipate securing federal grant in late 2011 Securing federal funding will trigger 2008 Measure B sales tax 13
14 Berryessa Extension Stations Key Features Milpitas Station Street level station Train boarding one level down Parking Garage Kiss and Ride Drop Off Shuttle Drop Off Bus Transit Center Bicycle Storage Room VTA Light Rail connection Berryessa Station Street level station Train boarding one level up Bus Transit Center Parking Garage Shuttle Drop Off Shared Bike and Pedestrian trails Bicycle Storage Room End of Line Station 14
15 Milpitas Station Campus and Landscape Plan 15
16 Milpitas Station View from Montague Expressway 16
17 Milpitas Station View from Montague Light Rail Station Platform 17
18 Berryessa Station Campus and Landscape Plan 18
19 Berryessa Station View from Plaza off Berryessa Station Way 19
20 Agency Coordination Efforts BART-VTA Partnership Cities of Fremont, Milpitas, and San José Union Pacific Railroad Caltrans Santa Clara County Roads and Airports Santa Clara Valley Water District, Alameda County Water District, Alameda County Flood Control, Regional Water Quality Control Board and US Army Corps of Engineers Public and Private Utilities 20
21 SVBX Project Schedule ROD 1 Engineering /Real Estate 2 Utility Relocations 3 LTSS (C700) Design Construction 4 Campus, Roadways / Parking Design Construction Rev Ops 5 Testing & Commissioning 21
22 Outreach Public Meetings and Group Presentations Neighborhood and Community-Specific Outreach Project Hotline-(408) Website- Electronic Outreach-GovDelivery, Facebook Newsletters 22
23 Questions & Answers 23
Chapter 7. Transportation Capital Improvement Projects. Chapter 7
Chapter 7 Transportation Capital Improvement Projects Chapter 7 81 Chapter 7 Transportation Capital Improvement Projects Local Transportation Sales Tax Programs For over three decades, Santa Clara County
More informationPeninsula Corridor Electrification Project (PCEP)
Peninsula Corridor Electrification Project (PCEP) Q4 Quarterly Update #11 April 1 June 30, 2017 JPB Board Meeting August 3, 2017 Agenda Item # 8a Electrification - Infrastructure Design Build Contract
More informationHigh Speed Rail Conference
High Speed Rail Conference Denver, October 23, 2012 FAST START PROJECT FOR PENINSULA HIGH-SPEED RAIL Kern Jacobson InfraConsult LLC Objective Evaluate incremental approach to expedite high-speed rail to
More informationSemi-Annual Report June Measure A Program
Semi-Annual Report June 2017 2000 Measure A Program 2000 Measure A Program Semi-Annual Report June 2017 Table of Contents TABLE OF CONTENTS Section Title Page 1 EXECUTIVE SUMMARY AND PROJECT COSTS A.
More information4.1 Land Use. SECTION CONTENTS Land Use Transit Transportation Technology
4 FUTURE CHANGES IN THE CORRIDOR Over the next 30 years, Santa Clara County will grow by roughly 637,000 residents and 303,500 jobs increases of 31 percent and 43 percent, respectively. 1 Changes in land
More informationSpeaker Information Tweet about this presentation #TransitGIS
Making the Case for Transit: the Transit Competitiveness Index Title William E. Walter, GISP Speaker Information Tweet about this presentation #TransitGIS Understanding Conditions in Each Travel Market
More informationSanta Clara-Alum Rock Bus Rapid Transit (BRT) Project. Project Update July 2014
Santa Clara-Alum Rock Bus Rapid Transit (BRT) Project Project Update July 2014 Today Overview of Santa Clara-Alum Rock Bus Rapid Transit and update on Construction Shelter Design Updates Construction Mitigation
More informationSAN FRANCISCO TO SAN JOSE PROJECT UPDATE
SAN FRANCISCO TO SAN JOSE PROJECT UPDATE San Francisco County Transportation Authority Tuesday, April 25, 2017 Ben Tripousis, Northern California Regional Director HIGH-SPEED RAIL: Connecting California
More informationLeadership NC. November 8, 2018
v Leadership NC November 8, 2018 Planning for our region s growth The Triangle is one of the fastestgrowing regions in the nation. More than 2 million people are already part of the equation, and the
More informationSustainable Transportation Award Winner. UC/CSU Sustainability Conference Santa Barbara, 2006
Sustainable Transportation Award Winner UC/CSU Sustainability Conference Santa Barbara, 2006 Translocator (Transit Locator) San Jose State University CSU: Transportation Demand Management Eyedin Zonobi,
More informationCONNECTING AND TRANSFORMING CALIFORNIA
CONNECTING AND TRANSFORMING CALIFORNIA High-Speed Rail Local Policy Maker Group (LPMG) San Carlos, CA January 28, 2016 INTRODUCTIONS 1 STATEWIDE OVERVIEW CONNECTING CALIFORNIA Phase I:» 520 Miles» San
More informationThe Future of Transportation on the Caltrain Corridor
The Future of Transportation on the Caltrain Corridor 11.30.16 1 2 Today What is happening Vision Recommendations What is costs How to pay for it 3 The Caltrain Corridor is home to the world s innovation
More informationMobility Management: Caltrain
Mobility Management: Caltrain Community Relations Committee October 4, 2017 Agenda Item 7 Presentation Outline Operating Statistics Ridership On-time Performance Fleet Reliability Capital Program Review
More informationElectric Multiple Unit Procurement Update
Electric Multiple Unit Procurement Update Board of Directors August 7, 2014 Context* * The proposed project is not yet approved pending environmental clearance. 2 1 Status April 2014 - JPB update on EMU
More informationPomona Rotary December 19, 2017
Pomona Rotary December 19, 2017 Los Angeles County s population will grow by 5.9% to 10.7 million by 2024 During that same period, the San Gabriel Valley will grow by 7.6% to more than 1.5 million; taking
More informationSAN FRANCISCO TO SAN JOSE PROJECT SECTION
SAN FRANCISCO TO SAN JOSE PROJECT SECTION Local Policy Maker Group Thursday, February 23, 2017 San Carlos, California INTRODUCTIONS 1 CALIFORNIA HIGH-SPEED RAIL PROGRAM UPDATE Jeff Morales, CEO HIGH-SPEED
More informationREGIONAL RAIL RIGHT OF WAY ACTION PLAN TECHNICAL MEMORANDUM #1 RIGHT OF WAY INVENTORY
REGIONAL RAIL RIGHT OF WAY ACTION PLAN TECHNICAL MEMORANDUM #1 RIGHT OF WAY INVENTORY This memorandum provides an update to the description of corridor planning contained in the 2007 MTC Regional Rail
More informationCaltrain Modernization EMU Procurement
Caltrain Modernization EMU Procurement Boarding Height CAC Meeting May 20, 2015 Context 2 1 Riders (Boardings) Average Weekday Ridership Since 2004 143% increase 60,000 55,000 50,000 45,000 40,000 35,000
More informationBUS RAPID TRAN SIT. Institute of Tra nsporta tion Engineers October 17, 2013
Institute of Tra nsporta tion Engineers October 17, 2013 Why is VTA d oing BRT? Building a transit network for today and future Fast, frequent core network Focus improvements in growing corridors Pursuing
More informationState of California Transit and Intercity Passenger Rail Program. Caltrain Grant Application Overview January 2018
State of California Transit and Intercity Passenger Rail Program Caltrain Grant Application Overview January 2018 TIRCP Program Overview The TIRCP provides grants from the Greenhouse Gas Reduction Fund
More informationDevelop ground transportation improvements to make the Airport a multi-modal regional
Project Overview TRANSPORTATION IMPROVEMENTS WHAT ARE THE PROJECT GOALS? Transportation transportation hub. Develop ground transportation improvements to make the Airport a multi-modal regional Land Use
More informationPhysical construction of VTA s BART Silicon Valley Phase I Extension. BART Silicon Valley Update
BART Silicon Valley Update Station Construction Static Testing Dynamic Testing Integration Testing Safety Certification Passenger Service TEST TEST Complete landscaping, station interiors and exteriors
More information3.15 SAFETY AND SECURITY
3.15 SAFETY AND SECURITY Introduction This section describes the environmental setting and potential effects of the alternatives analyzed in this EIR with regard to safety and security in the SantaClara-Alum
More informationSanta Clara Valley Transportation Authority 2013 PROGRESS REPORT
VTA looks to the future and is ready to keep Silicon Valley moving forward. Santa Clara Valley Transportation Authority 2013 PROGRESS REPORT nyone who has run a relay race knows the importance of making
More informationDART Priorities Overview
City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee
More informationSERVICE DESIGN GUIDELINES
VTA TRANSIT SUSTAINABILITY POLICY: APPENDIX A SERVICE DESIGN GUIDELINES Adopted February 2007 COMMUNITYBUS LOCALBUS EXPRESSBUS BUSRAPIDTRANSIT LIGHTRAILTRANSIT STATIONAREAS S A N T A C L A R A Valley Transportation
More informationMilpitas BART Station Transportation Impact Analysis, Hexagon Transportation Consultants, Inc., December 23, 2008.
4.2 TRANSPORTATION 4.2.1 INTRODUCTION This section includes an updated traffic analysis that entirely replaces the transportation section in the SEIR-1. This existing and future transportation conditions
More informationParking & Transportation Services (P&TS) C a r d i n a l a t W o r k W e l c o m e C e n t e r
Parking & Transportation Services (P&TS) C a r d i n a l a t W o r k W e l c o m e C e n t e r Transportation Programs and Services Parking Shuttle & Charters Bicycle Program Sustainable Commuting Sustainability
More informationSAN FRANCISCO TO SAN JOSE PROJECT SECTION. City of Brisbane Baylands Public Hearing June 7, 2017
SAN FRANCISCO TO SAN JOSE PROJECT SECTION City of Brisbane Baylands Public Hearing June 7, 2017 CALIFORNIA HIGH-SPEED RAIL PROGRAM OVERVIEW 2 HIGH-SPEED RAIL: Connecting California 3 HIGH-SPEED RAIL: It
More informationRedefining Mobility Ready or not: Autonomous and connected vehicle planning and policy, now and in the future
Redefining Mobility Ready or not: Autonomous and connected vehicle planning and policy, now and in the future Randy Iwasaki November 30, 2017 WHO WE ARE The Contra Costa Transportation Authority (CCTA)
More informationMobility Corridor Updates. Transit & Active Transportation Projects
Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate
More informationPreliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Millbrae
Preliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Millbrae Dominic Spaethling Regional Program Manager Bethany Williams Public Involvement Manager, HNTB April
More informationPeninsula Corridor Electrification Project (PCEP)
Peninsula Corridor Electrification Project (PCEP) Q2 Quarterly Update #13 October 1 December 31, 2017 JPB Board Meeting February 1, 2018 Agenda Item # 8b Electrification - Infrastructure Progression of
More informationUpdate on Transportation Activities in Fairfax County
Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation Association June 13, 2018 Tom Biesiadny, Director Fairfax County Continuing Project Implementation
More informationWestchester County Department of Public Works and Transportation First and Last Mile Connections TNC Partnership Study
Westchester County Department of Public Works and Transportation First and Last Mile Connections TNC Partnership Study Mobility Advisory Forum December 11, 2018 Naomi Klein, Director of Planning Craig
More informationProposed Program of Interrelated Projects
DALLAS AREA RAPID TRANSIT Proposed Program of Interrelated Projects Federal Transit Administration Capital Investment Program Summer 204 INTRODUCTION The current federal transportation bill, Moving Ahead
More informationRegional Transportation District. Dave Genova Interim General Manager and CEO August 21, 2015
Regional Transportation District Dave Genova Interim General Manager and CEO August 21, 2015 About RTD Created in 1969 Eight-county service area Service area: 2,340 square miles 2.8 million population
More informationEast Bay Bus Rapid Transit Project. Downtown Oakland to San Leandro International Blvd to East 14 th St
East Bay Bus Rapid Transit Project 1 AC Transit at a Glance EAST BAY AREA S LARGEST PUBLIC TRANSIT PROVIDER RIDERSHIP Daily (weekday) 178,851* Annual 54,987,132 Paratransit (daily) 1,994 ** * Includes
More informationRail alignment and benefits (rab) study
Rail alignment and benefits (rab) study previously known as railyard alternatives & i-280 boulevard study June 5, 2018 CONNECTING CALIFORNIA 4,300 lane miles + 115 Airport gates would be needed to create
More informationCEDAR AVENUE TRANSITWAY Implementation Plan Update
CEDAR AVENUE TRANSITWAY Implementation Plan Update EECUTIVE SUMMARY DECEMBER 2015 Executive Summary In 2013, the Twin Cities metropolitan area s first bus rapid transit (BRT) line, the METRO Red Line,
More informationAgenda. Preliminary Station Footprint High Speed Train Station in the City of Millbrae
Agenda Preliminary Station Footprint High Speed Train Station in the City of Millbrae Open House 7:00 7:30 Presentation 7:30 8:00 Community Question/Answer 8:00 9:00 Adjourn 2 Preliminary Station Footprint
More informationOverview of Regional Commuter Rail Webinar: Phoenix, Arizona December 18, 2013
Overview of Regional Commuter Rail Webinar: Phoenix, Arizona December 18, 2013 2013, All Rights Reserved. 1 The Maricopa Association of Governments (MAG) is the designated metropolitan planning organization
More informationSuccessful Passenger Rail in the State of California
Successful Passenger Rail in the State of California Texas Transportation Forum Austin, Texas Eugene K. Skoropowski, Managing Director Capitol Corridor Joint Powers Authority (CCJPA) Oakland, California
More informationNew Haven-Hartford-Springfield Rail Project Gateway to New England. Program Update March 14, 2011 Revised & Updated March 31, 2011
New Haven-Hartford-Springfield Rail Project Gateway to New England Program Update March 14, 2011 Revised & Updated March 31, 2011 1 New Haven-Hartford-Springfield Rail Corridor Glory Days: 1925-1955 22
More informationRail~Volution 2012 R. Gregg Albright
CALIFORNIA HIGH-SPEED RAIL AUTHORITY October 16 th, 2012 Rail~Volution 2012 R. Gregg Albright WHAT IS CALIFORNIA HIGH-SPEED TRAIN PROJECT (CHSTP) and HOW WILL IT BE IMPLEMENTED? 2 CALIFORNIA HIGH SPEED
More informationCAPITOL CORRIDOR SERVICE PERFORMANCE
The Capitol Corridor continues its streak of positive performance results. In April 2016, a total of 129,984 passengers rode Capitol Corridor trains, a 2.1% year over year (YOY) increase, and revenues
More informationPeninsula Corridor Electrification Project Cost / Schedule Update
Peninsula Corridor Electrification Project Cost / Schedule Update LPMG Meeting November 20, 2014 Context Caltrain/high-speed rail blended system - Primarily 2 track system - Minimize impacts - Shared system
More informationNorthern Indiana Commuter Transportation District VENDOR OPEN HOUSE APRIL 17, 2019
Northern Indiana Commuter Transportation District VENDOR OPEN HOUSE APRIL 17, 2019 VENDOR OPEN HOUSE AGENDA Welcome and Introductions Safety Briefing NICTD Website and Plan Room Upcoming Projects Disadvantaged
More informationAgenda. Open House Presentation Question and Answer Break Out Groups Report Out & Close
Agenda Open House Presentation Question and Answer Break Out Groups Report Out & Close Preliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Sunnyvale Dominic Spaethling
More informationElectric Multiple Unit Procurement Update
Electric Multiple Unit Procurement Update Public Meetings September 2014 Caltrain Today 2 1 Key Facts Diesel commuter rail system SF to SJ area 77 mile corridor, 32 stations 92 trains / weekday Ridership:
More information6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION
June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments
More informationMaryland Gets to Work
I-695/Leeds Avenue Interchange Reconstruction Baltimore County Reconstruction of the I-695/Leeds Avenue interchange including replacing the I-695 Inner Loop bridges over Benson Avenue, Amtrak s Northeast
More informationACEforward. BART Connectivity Alternatives Preliminary Forecasts and Costs Altamont Regional Rail Working Group July 13, 2016
ACEforward ACEforward BART Connectivity Alternatives Preliminary Forecasts and Costs Altamont Regional Rail Working Group July 13, 2016 ACEforward Project Goals Tri-Valley BART Connection Union City BART
More informationREPORT CARD FOR CALIFORNIA S INFRASTRUCTURE WHAT YOU SHOULD KNOW ABOUT CALIFORNIA S TRANSIT FACILITIES
TRANSIT GRADE: C- WHAT YOU SHOULD KNOW ABOUT TRANSIT FACILITIES California needs robust, flexible and reliable transit systems to reduce peak congestion on our highways, provide options for citizens who
More informationUNION STATION MASTER PLAN STUDY
UNION STATION MASTER PLAN STUDY The Chicago Department of Transportation has begun a comprehensive study of issues related to Chicago s Union Station, the Union Station Master Plan. Opened in 1925, Union
More informationTransportation Sustainability Program
Transportation Sustainability Program Photo: Sergio Ruiz San Francisco is a popular place to work, live and visit, straining the existing transportation network Roads and transit vehicles nearing capacity
More informationLeveraging Land Use Changes through Transportation Funding
Leveraging Land Use Changes through Transportation Funding Railvolution 2005 September 10, 2005 James Corless Senior Planner What is the MTC region? 9 7 101 26 San Francisco Bay Area counties Million people;
More informationModernization: How Caltrain Will Meet Growing Demand
Modernization: How Caltrain Will Meet Growing Demand BY LEAH HARNACK ON JUN 4, 2018 San Francisco is the most densely populated county in California and serves as the region s largest job center, bringing
More informationNortheast Corridor Alternatives Analysis. Public Involvement Round 2 Input on Alternatives for Further Study
Northeast Corridor Alternatives Analysis Public Involvement Round 2 Input on Alternatives for Further Study Feb. 7-9, 2012 Agenda Review project background Progress summary Recommended alternatives for
More informationSamTrans Business Plan Update May 2018
SamTrans Business Plan Update May 2018 SamTrans Business Plan Core Principles: 1. Sustain and enhance services for the transit-dependent 2. Expand and innovate mobility services 3. Promote programs that
More informationVan Ness Transit Corridor Improvement Project. Engineering, Maintenance and Safety Committee March 25, 2015
Van Ness Transit Corridor Improvement Project Engineering, Maintenance and Safety Committee March 25, 2015 Project Need 16,000 daily passenger boardings within the project corridor Average bus speed 8
More informationColorado Association of Ski Towns August 26, 2016
Colorado Association of Ski Towns August 26, 2016 1 Presentation RFTA Overview Long Range Forecast Integrated Transportation System Plan Questions Roaring Fork Transportation Authority (RFTA) RFTA Overview
More information2018 American Zero Emission Bus Conference INNOVATIVE CLEAN TRANSIT PROPOSED REGULATION
2018 American Zero Emission Bus Conference INNOVATIVE CLEAN TRANSIT PROPOSED REGULATION L o s A n g e l e s S e p t e m b e r 1 0 th & 11 th 1 General Considerations of Staff Proposal Achieve zero emission
More informationBART s Transbay Core Capacity Project
BART s Transbay Core Capacity Project Duncan Watry, Principal Planner Bay Area Rapid Transit Oakland, CA dwatry@bart.gov Donald Emerson, Principal Consultant WSP Parsons Brinckerhoff San Francisco, CA
More informationSan Francisco Mobility, Access & Pricing Study
San Francisco Mobility, Access & Pricing Study SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY Summer Workshops 2010 Downtown Growth Projections + 24,000 hsg units + 107,000 jobs +184,000 auto trips +88,000
More informationConnected Vehicle and Autonomous Vehicle (CV/AV) Mobility and Technology
Connected Vehicle and Autonomous Vehicle (CV/AV) Mobility and Technology Randy Iwasaki Executive Director Contra Costa Transportation Authority May13, 2016 WHO WE ARE The Contra Costa Transportation Authority
More informationRail alignment and benefits (rab) study
Rail alignment and benefits (rab) study previously known as railyard alternatives & i-280 boulevard study May 22, 2018 CONNECTING CALIFORNIA 4,300 lane miles + 115 Airport gates would be needed to create
More informationTreasure Island Mobility Management Program
Treasure Island Mobility Management Program Preliminary Toll Policy Recommendations For Buildout Year (2030) Draft TIDA CAB June 2, 2015 About the Treasure Island Mobility Management Program 2003 2008
More informationACEforward. Livermore Valley Chamber of Commerce Business Alliance Meeting. September 6, 2017
ACEforward Livermore Valley Chamber of Commerce Business Alliance Meeting September 6, 2017 Current ACE Connectivity Map WESTBOUND TRAINS ACE 1 ACE 3 ACE 5 ACE 7 Stockton 4:20AM 5:35AM 6:40AM 7:05AM Tracy
More informationState Avenue Corridor Bus Rapid Transit (BRT)
State Avenue Corridor Bus Rapid Transit (BRT) Moving Forward Incrementally April 2010 State Ave. BRT Update Bus Rapid Transit Overview State Ave. Alternatives Analysis Results What s Coming Up Right Away!
More informationCommunity Outreach Meetings
Community Outreach Meetings BCT At A Glance 410 square miles service area More than 41.5 million annual trips 327 fixed-route buses 44 bus routes 78 Community Buses in 19 Municipalities BCT At A Glance
More informationStaff Contact: Carlos de Melo, Community Development Director, (650)
Meeting Date: April 10, 2018 STAFF REPORT Agency: City of Belmont Staff Contact: Carlos de Melo, Community Development Director, (650) 595-7440 cdemelo@belmont.gov Agenda Title: Agenda Action(s): Caltrain
More informationAGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, :30 P.M. 1) APPROVAL OF AGENDA 1 min.
AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, 2016 5:30 P.M. CALL TO ORDER 1) APPROVAL OF AGENDA 1 min. 2) INTRODUCTIONS 5 min. A. Welcome City of Yelm Councilmember Molly Carmody B. Welcome
More informationUCLA Lake Arrowhead Conference. October 18, 2010
BART Click to Capacity edit Master Overview title style for UCLA Lake Arrowhead Conference October 18, 2010 0 BART Basics 360,000 daily riders 104 miles 43 stations 1.3 billion annual passenger miles 1
More informationSEPULVEDA PASS CORRIDOR
SEPULVEDA PASS CORRIDOR PUBLIC PRIVATE PARTNERSHIP DELIVERY PRE-DEVELOPMENT AGREEMENT PDA Sepulveda Pass Mobility Issues Most congested highway segment in the U.S. 295,000 vehicles per day (2010) 430,000
More informationSustainability SFMTA Path to Platinum
Sustainability SFMTA Path to Platinum Ed Reiskin San Francisco Municipal Transportation Agency, Director of Transportation San Francisco, CA Timothy Papandreou Deputy Director Strategic Planning & Policy
More informationRail~Volution 2005 Hal Ryan Johnson, AICP, Bus Rapid Transit Project Manager Utah Transit Authority September 7, 2005
Rail~Volution 2005 Hal Ryan Johnson, AICP, Bus Rapid Transit Project Manager Utah Transit Authority September 7, 2005 Public Transit District Utah Transit Authority Linear Geographic Area - 130 miles by
More informationGreen Line opens June 14
Winter 2014 Green Line opens June 14 To-do list for METRO Green Line s grand opening Yours: Study safety tips at www.centralcorridor.org/safety Learn about planned Metro Transit bus service changes on
More informationEUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT
EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT (BRIEF) Table of Contents EUGENE-SPRINGFIELD, OREGON (USA)... 1 COUNTY CONTEXT AND SYSTEM DESCRIPTION... 1 SYSTEM OVERVIEW... 1 PLANNING
More informationTransit in Bay Area Blueprint
Rail~Volution 2010 Click to edit Master title style Transit in Bay Area Blueprint October 21, 2010 0 Bottom Line State-of-Good Repair essential for reliable transit service large funding shortfalls BART
More informationSuccessful Strategies. for Managing the Complex ebart Extension
Successful Strategies for Managing the Complex ebart Extension 1 Maurice Ric Rattray, PE Group Manager, Capital Program BART 1 Andy Kleiber, PE Principal Construction Manager MNS Engineers, Inc. 0 1 Introduction
More informationCaltrain Business Plan
Caltrain Business Plan FEBRUARY 2019 LPMG February 28, 2019 Caltrain Business Plan Project Update 2 3 What is the Caltrain Business Plan? What Why Addresses the future potential of the railroad over the
More informationTreasure Island Toll Policy, Affordability and Transit Pass Programs. TIMMA Board Meeting December 11, 2018
Treasure Island Toll Policy, Affordability and Transit Pass Programs TIMMA Board Meeting December 11, 2018 Avoiding Island Gridlock 2 Island Mobility Goals Incentivize transit, walking, and biking Discourage
More informationBusiness Advisory Committee. July 7, 2015
Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS
More informationtrains to/from Roseville), and the replacement and upgrade of the Passenger Information Display System.
Service Performance Overview The Capitol Corridor set a record for monthly ridership and revenues in. A total of 141,520 passengers rode Capitol Corridor trains during the month, representing a remarkable
More informationSAN RAFAEL CITY COUNCIL AGENDA REPORT
Agenda Item No: 8.b Meeting Date: December 19, 2016 Department: PUBLIC WORKS SAN RAFAEL CITY COUNCIL AGENDA REPORT Prepared by: Bill Guerin, Public Works Director City Manager Approval: File No.: 18.01.79
More informationBasic Project Information
FY 2015-16 PROJECT DESCRIPTION FORM (7B) Submitting Agency: Fairfax County Basic Project Information Project Title: South Van Dorn Street and Franconia Road Interchange 7B Project Type (check one): Roadway
More informationEMU Procurement Seats/Standees/Bikes/Bathroom
EMU Procurement Seats/Standees/Bikes/Bathroom LPMG May 28, 2015 Purpose Seats / standees / bikes / bathroom balance Develop framework for Draft EMU RFP Feedback on car configuration and range of increased
More informationEast San Fernando Valley Transit Corridor. Information Session, October 10, 2017
East San Fernando Valley Transit Corridor Information Session, October 10, 2017 1 Welcome and Meeting Purpose Introductions Metro Transit Corridors Planning Metro Real Estate Metro Community Relations
More informationFuture of VTA Light Rail
Future of VTA Light Rail SPUR Presentation 11/12/2014 Light Rail System: Guadalupe & Almaden Guadalupe Opening: 1987-1991 19.6 miles 29 stations Almaden Opening: 1991 1.1 miles 2 stations Light Rail System:
More information2019 New Transit Service Plan
Agenda Item 7.2 2019 New Transit Service Plan Draft Proposal VTA Board of Directors January 2019 Background: Next Network Plan and Today s Plan Early 2016 Transit Choices report and the ridership-coverage
More informationUpdate of the Midwest Regional Rail Initiative. Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI
Update of the Midwest Regional Rail Initiative Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI Key Presentation Take-Aways Status of Midwest Regional Rail Initiative
More informationMARTA s blueprint for the future. COFFEE AND CONVERSATION Kyle Keahey, More MARTA Atlanta Dec. 5, 2018
MARTA s blueprint for the future COFFEE AND CONVERSATION Kyle Keahey, More MARTA Atlanta Dec. 5, 2018 TODAY S AGENDA About MARTA Economic development/local impact More MARTA Atlanta program Program summary/timeline
More informationSan Rafael Transit Center. Update. Golden Gate Bridge, Highway & Transportation District Transportation Committee of the Board of Directors
Transportation Committee November 17, 2016 Agenda Item No. 5, Update on the San Rafael Transit Center Relocation San Rafael Transit Center Relocation Study Update 11/17/16 Golden Gate Bridge, Highway &
More informationDraft Results and Recommendations
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Recommendations Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System
More informationWest Broadway Reconstruction/LRT Design. March 19, 2015
West Broadway Reconstruction/LRT Design March 19, 2015 1 Meeting Agenda 6:05 6:30 PM Brief presentation What we heard Project overview 6:30 8:00 PM Visit Six Topic Areas Road and LRT design elements Pedestrian
More informationThursday, August 15, 2013 MINUTES
\ TRANSIT PLANNING & OPERATIONS COMMITTEE Thursday, August 15, 2013 MINUTES CALL TO ORDER The Regular Meeting of the Transit Planning and Operations (TP&O) Committee was called to order at 4:08 p.m. by
More informationMOTION NO. M Preferred Alternative for the Puyallup Station Access Improvement Project
MOTION NO. M2014 64 Preferred Alternative for the Puyallup Station Access Improvement Project MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 8/14/14 8/28/14 Recommendation
More informationUnified Corridor Investment Study DRAFT Step 2 Scenario Analysis Report
Unified Corridor Investment Study DRAFT Step 2 Scenario Analysis Report REVISIONS 1. Table 39: New Public Investments for Operation and Maintenance Costs 2. Appendix A-10: Passenger Rail Service - Operations
More informationCentral City Line Locally Preferred Alternative (LPA) Amendment Public Hearing. July 24, 2014
Central City Line Locally Preferred Alternative (LPA) Amendment Public Hearing July 24, 2014 Project Description The Central City Line is a High Performance Transit project that will extend from Browne
More information