Open Session Item. Construction Bid Award Pavement Maintenance & Rehabilitation Program FY 16 Chip Seal Applications, Contract No.

Size: px
Start display at page:

Download "Open Session Item. Construction Bid Award Pavement Maintenance & Rehabilitation Program FY 16 Chip Seal Applications, Contract No."

Transcription

1 Board of County Commissioners of Washington County, Maryland Agenda Report Form Open Session Item SUBJECT: Construction Bid Award Pavement Maintenance & Rehabilitation Program FY 16 Chip Seal Applications, Contract No. MS-PMP PRESENTATION DATE: Tuesday, April 5, 2016 PRESENTATION BY: Scott Hobbs, P.E., Deputy Director Division of Engineering & Construction Management RECOMMENDED MOTION: Move to award the bid for the Pavement Maintenance & Rehabilitation Program FY 16 Chip Seal Applications contract to the lowest responsive, responsible bidder, Hammaker East LTD of Fayetteville, PA for the amount of $1,397, REPORT-IN-BRIEF: The project was advertised in The Herald Mail, on the County s website, and on the State of Maryland s website, e-maryland Marketplace. Two (2) bids were received on Wednesday, March 2, 2016 as listed below and further detailed on the attached Bid Tabulation. Contractor: Total Bid: Hammaker East LTD $1,397, American Paving Fabrics, Inc. $2,497, The bids have been evaluated and the low bid by Hammaker East LTD is in order. The engineer s estimate is $1,752, DISCUSSION: The Pavement Maintenance & Rehabilitation Program for chip seal applications generally described as asphalt preservation and repair. The project involves treatment applications of chip seal bar patch, single chip seal surface treatment, double chip seal surface treatment, scrub seal treatment, and permanent pavement markings. This project will include 54 miles of treatment applications. The proposed contract follows standard State Highway Administration provisions for monthly liquid asphalt price adjustments, as used in prior years. The bid documents provide one hundred twenty (120) consecutive calendar days to complete the work. The Notice to Proceed is anticipated on or about May 2, 2016 with a final completion date of August 30, The bid documents include Liquidated Damages in the amount of $ per calendar day for work beyond the completion date. Motorists may experience some minor delays as a result of lane closures. There are no major road closures associated with this work. Public notices will be made and road work signs posted prior to the start of work. The Road Listing is attached and will be posted on the County s website for reference.

2 2 P age AGENDA REPORT FORM FISCAL IMPACT: This is a budgeted Capital Improvement Plan (CIP) project (RDI024) with an unencumbered balance of $5,399, This budget is also for the Hot Mix Asphalt Applications contract. Total expenses for the chip seal applications are estimated at $1,687,470.01; including $1,397, for proposed bid award, $120, for inspection/testing, $70,000 for 5% construction contingency, and $100,000 for asphalt adjustment costs. CONCURRENCES: ALTERNATIVES: ATTACHMENTS: AUDIO/VISUAL TO BE USED: Director of Engineering and Construction Management This is the most cost effective and practical alternative. Roads are substandard and need repairs to extend service life. Bid Tabulation, Road Listing, Road Maps N/A

3 WASHINGTON COUNTY DIVISION OF ENGINEERING & CONSTRUCTION MANAGEMENT FY-2016 Pavement Maintenance & Rehabilitation Program Chip Seal Applications ROAD FROM TO TREATMENT MILES Green Lane Road Creek Road PA State Line Double Chip Seal 0.76 Tollgate Ridge Road Ford Drive PA State Line Double Chip Seal 2.27 White Oak Ridge Road MD Millstone Road PA State Line Double Chip Seal 2.55 Bain Road Maple Ridge White Oak Ridge Double Chip Seal 0.79 Maple Ridge Road MD Millstone Road Weller Road Double Chip Seal 2.71 Weller Road Hollow Road PA State Line Double Chip Seal 1.74 Slabtown Road Hollow Road River Double Chip Seal 1.42 Orchard Ridge Road Slabtown Road Hollow Road Double Chip Seal 1.67 Bottom Road MD 68 - Clear Spring Road MD 68 - Clear Spring Road Double Chip Seal 3.47 Bakersville Road MD 63 - Spielman Road MD 65 - Sharpsburg Pike Double Chip Seal 3.09 Tommytown Road Bakersville Road Taylors Landing Road Double Chip Seal 1.56 Taylors Landing Road MD 65 - Sharpsburg Pike Woburn Road Double Chip Seal 3.10 Remsburg Road Taylors Landing Road Bowie Road Double Chip Seal 0.50 Harpers Ferry Road East High Street Chestnut Grove Road Double Chip Seal 7.01 Millers Sawmill Road Harpers Ferry Road Canal Road Double Chip Seal 1.72 Washington Monument Road Old National Pike Zittlestown Road Double Chip Seal 0.90 Mill Point Road Old National Pike MD 66 - Mapleville Road Double Chip Seal 1.24 Millers Church Road MD 60 - Leitersburg Pike MD 60 - Leitersburg Pike Double Chip Seal 4.29 Leiters Mill Road MD 60 - Leitersburg Pike PA State Line Double Chip Seal 2.50 Black Angus Road Millers Church Road Strite Road Double Chip Seal 0.42 Ritchie Road MD Raven Rock Road MacAfee Hill Road Double Chip Seal 3.91 Wise Road Ritchie Road Frederick County Line Double Chip Seal 0.30 Larrabee Avenue MD550 - Military Road Brooks Avenue Double Chip Seal 0.17 Brooks Avenue MD550 - Military Road Larrabee Avenue Double Chip Seal 0.09 High Rock Road Pavement Transition High Rock Parking Area Double Chip Seal 1.14 Cave Hill Road Itnyre Road West Water Street Double Chip Seal 0.97 Itnyre Road MD 64 - Jefferson Blvd Cave Hill Road Double Chip Seal 0.44 Olivewood Drive College Road Woodside Drive Double Chip Seal 0.08 Woodside Drive Summerlin Drive Sharpsburg Pike Double Chip Seal 0.73 Summerlin Drive Sharpsburg Pike Woodside Drive Double Chip Seal 0.36 Woodside Court Woodside Drive Cul-de-sac Double Chip Seal 0.10 Driftwood Lane Summerlin Drive Woodside Drive Double Chip Seal 0.12 Fernwood Lane Woodside Drive Woodside Drive Double Chip Seal 0.27 Candlewood Lane Summerlin Drive Fernwood Lane Double Chip Seal 0.16

4 Chapelwood Lane St. James Circle Woodside Drive Double Chip Seal 0.14 Deanewood Lane Summerlin Drive Woodside Drive Double Chip Seal 0.12 Summerlin Court Woodside Drive Cul-de-sac Double Chip Seal 0.04 Sandlewood Court Woodside Drive Cul-de-sac Double Chip Seal 0.07 Heritage Lane Marsh Pike Portsmouth Drive Double Chip Seal 0.06 Portsmouth Drive Heritage Drive Heritage Drive Double Chip Seal 0.61 Johnnycake Lane Portsmouth Drive Dead End Cul-de-sac Double Chip Seal 0.05 Postrider Court Portsmouth Drive Dead End Cul-de-sac Double Chip Seal 0.11 Newport Court Portsmouth Drive Dead End Cul-de-sac Double Chip Seal 0.08 Total 53.82

5

6 WASHINGTON COUNTY, MARYLAND DIVISION of ENGINEERING and CONSTRUCTION MANAGEMENT PAVEMENT MAINTENANCE and REHABILITATION PROGRAM FY-'16 - CHIP SEAL APPLICATIONS CONTRACT NO. PMP BID TABULATION March 2, 2016 at 10:00 am Hammaker East, LTD American Paving Fabrics Inc. Fayetteville, PA Hanover, MD ITEM No. ITEM DESCRIPTION QTY. UNIT UNIT PRICE ITEM TOTAL UNIT PRICE ITEM TOTAL 101 Maintenance Of Traffic 1 LS $ 43, $ 43, $ 79, $ 79, A Single Chip Seal - Emulsion, CRS-2PM 2,500 GAL $ 1.53 $ 3, $ 2.96 $ 7, B Single Chip Seal - No. 10 Aggregate 50 TON $ $ 1, $ $ A Double Chip Seal - Emulsion, CRS-2PM 489,318 GAL $ 1.53 $ 748, $ 2.96 $ 1,448, B Double Chip Seal - No. 8 Aggregate 7,470 TON $ $ 185, $ $ 323, C Double Chip Seal - No. 10 Aggregate 6,322 TON $ $ 162, $ $ 277, A Chip Seal Bar Patch - Emulsion, CRS-2PM 55,656 GAL $ 1.57 $ 87, $ 2.96 $ 164, B Chip Seal Bar Patch - No. 8 Aggregate 1,509 TON $ $ 41, $ $ 48, A Scrub Seal - Emulsion, CRS-2PM 2,500 GAL $ 1.57 $ 3, $ 2.96 $ 7, B Scrub Seal - No. 10 Aggregate 50 TON $ $ 1, $ $ CONTINGENT - Fog Seal - Emulsion, CSS-1H 2,500 GAL $ 1.63 $ 4, $ 3.52 $ 8, Pavement Marking Paint - Lines 730,342 LF $ 0.14 $ 102, $ 0.17 $ 124, Markings - 12" Wide Crosswalk 50 SF $ 8.25 $ $ 4.79 $ No Preheat Heat Applied Permanent Preformed Thermoplastic Pavement Markings - Lines 24" Wide Stop Bars 834 SF $ 9.75 $ 8, $ 4.79 $ 3, CONTINGENT - No Preheat Heat Applied Permanent Preformed Thermoplastic Pavement Markings - Legends, Letters 115 SF $ $ 1, $ $ 1, No Preheat Heat Applied Permanent Preformed Thermoplastic Pavement Markings - Symbols, Railroad Crossing 130 SF $ $ 1, $ 5.78 $ *denotes mathematical error BID TOTALS $ 1,397, $ 2,497, PMP FY16 - Chip Seal Bid Tab Page 1

Open Session Item. Contract Award of (PUR-1367) Bid for Vehicle and Off Road Industrial

Open Session Item. Contract Award of (PUR-1367) Bid for Vehicle and Off Road Industrial Board of County Commissioners of Washington County, Maryland Agenda Report Form Open Session SUBJECT: Equipment. Contract Award of () Bid for Vehicle and Off Road Industrial PRESENTATION DATE: December

More information

PURCHASING DEPARTMENT DIVISION OF BUDGET & FINANCE

PURCHASING DEPARTMENT DIVISION OF BUDGET & FINANCE PURCHASING DEPARTMENT DIVISION OF BUDGET & FINANCE 100 West Washington Street, Room 3200 Hagerstown, MD 21740-4748 P: 240.313.2330 F: 240.313.2331 www.washco-md.net Q-18-655 ADDENDUM NO. 1 REQUEST FOR

More information

CITY OF STEVENS POINT AGENDA

CITY OF STEVENS POINT AGENDA CITY OF STEVENS POINT BOARD OF PUBLIC WORKS MEETING Monday, April 10, 2017 6:10 p.m. (or immediately following previously scheduled meeting) Lincoln Center 1519 Water Street Stevens Point, WI 54481 AGENDA

More information

Staff Report. (925)

Staff Report. (925) 5.g Staff Report Date: September 13, 2016 To: From: Reviewed by: Prepared by: Subject: City Council Valerie J. Barone, City Manager Justin Ezell, Director of Public Works Jeff Rogers Jeff.rogers@cityofconcord.org

More information

COUNCIL COMMUNICATION

COUNCIL COMMUNICATION COUNCIL COMMUNICATION TO: FROM: DEPARTMENT: Mayor and Council Larry Nimmo Public Works DATE: June 19, 2017 SUBJECT: Award Contract for 2017 Chip Seal Program DESCRIPTION: Award Contract for 2017 Chip Seal

More information

City of Grand Forks Staff Report

City of Grand Forks Staff Report City of Grand Forks Staff Report Committee of the Whole December 1, 016 City Council December 19, 016 Agenda Item: Bids for City Project No. 7551 Lift Station No. 17 & 17A Rehabilitation Submitted by:

More information

City of Grand Island Tuesday, March 13, 2018 Council Session

City of Grand Island Tuesday, March 13, 2018 Council Session City of Grand Island Tuesday, March 13, 2018 Council Session Item G-14 #2018-69 - Approving Purchase of a New ½ Ton, Four-Wheel Drive, Extended Cab Pick-up for the Streets Division of the Public Works

More information

Public Works Department

Public Works Department Public Works Department SUBJECT: Consideration of Resolutions authorizing one-year contract extensions for snow/ice removal services during the 2015-2016 winter season with: 1. Tovar Snow Professionals

More information

Wentzville Parkway South Phase 2 & 2A

Wentzville Parkway South Phase 2 & 2A Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total

More information

ARIZONA DEPARTMENT OF TRANSPORTATION INFRASTRUCTURE DELIVERY AND OPERATIONS DIVISION CONTRACTS AND SPECIFICATIONS SECTION TABULATION OF BIDS

ARIZONA DEPARTMENT OF TRANSPORTATION INFRASTRUCTURE DELIVERY AND OPERATIONS DIVISION CONTRACTS AND SPECIFICATIONS SECTION TABULATION OF BIDS ARIZONA DEPARTMENT OF TRANSPORTATION INFRASTRUCTURE DELIVERY AND OPERATIONS DIVISION CONTRACTS AND SPECIFICATIONS SECTION TABULATION OF BIDS CONTRACT # 2016153 TRACS No. Project No. County District Gross

More information

Report Number: COD Resolution: GG

Report Number: COD Resolution: GG Corporate Services Report If this information is required in an alternate accessible format, please contact the Municipal Clerk at 905-623-3379 ext. 2102. Report To: General Government Committee Date of

More information

Open Session Item. Bid Award (PUR-1349) - Grounds Maintenance for Various County

Open Session Item. Bid Award (PUR-1349) - Grounds Maintenance for Various County Board of County Commissioners of Washington County, Maryland Agenda Report Form Open Session SUBJECT: Departments Bid Award () - Grounds Maintenance for Various County PRESENTATION DATE: June 13, 2017

More information

City of Grand Island Tuesday, June 26, 2018 Council Session

City of Grand Island Tuesday, June 26, 2018 Council Session City of Grand Island Tuesday, June 26, 2018 Council Session Item G-21 #2018-188 - Approving Change Order No. 3 for Sanitary Sewer Collection System Rehabilitation Various Locations; Project No. 2017-S-2A

More information

BUTTE COUNTY DEPARTMENT OF PUBLIC WORKS

BUTTE COUNTY DEPARTMENT OF PUBLIC WORKS PROJECT: 2014 Slurry Seal PROJECT LOCATION: Various Roads in the Thermalito and Oroville Areas Retro-Reflective Pavement Markers. ADVERTISED: February 27, 2014 ENGINEER'S ESTIMATE = $213,700.00 BIDS OPENED:

More information

Effingham County Ash Roads Update 2018 Winter Storm Grayson Jan 16, 2018

Effingham County Ash Roads Update 2018 Winter Storm Grayson Jan 16, 2018 Effingham County Ash Roads Update 2018 Winter Storm Grayson Jan 16, 2018 Brief History Ash from Georgia Pacific was applied to dirt roads starting in 2001 Georgia Environmental Protection Division approves

More information

HURON COUNTY ENGINEER S OFFICE

HURON COUNTY ENGINEER S OFFICE HURON COUNTY ENGINEER S OFFICE 2017 ENGINEER S ANNUAL REPORT The Ohio Revised Code requires that each Ohio County Engineer publish an annual report to the commissioners outlining the general condition

More information

Regular Meeting PULASKI COUNTY Mon. August 18, 2003 PUBLIC SERVICE AUTHORITY FOLLOW-UP ITEM. 1. Citizen Comments

Regular Meeting PULASKI COUNTY Mon. August 18, 2003 PUBLIC SERVICE AUTHORITY FOLLOW-UP ITEM. 1. Citizen Comments AGENDA Regular Meeting PULASKI COUNTY Mon. August 18, 2003 PUBLIC SERVICE AUTHORITY 9:00 a.m. FOLLOW-UP ITEM 1. Citizen Comments 2. Reports from the County Administrator & Staff: a. Collection Staff Activity:

More information

Clarksville Street Department. Fiscal Year 2018 Budget Presentation

Clarksville Street Department. Fiscal Year 2018 Budget Presentation Clarksville Street Department Fiscal Year 2018 Budget Presentation Clarksville Street Department FY 2018 Proposed Budget 4.2% 42.0% Salaries/Benefits 53.8% Operating Expenses Capital Outlay Clarksville

More information

CANTON COMMUNITY REQUEST FOR BOARD ACTION

CANTON COMMUNITY REQUEST FOR BOARD ACTION CANTON COMMUNITY REQUEST FOR BOARD ACTION MEETING DATE: April 11, 2017 AGENDA ITEM #G-6 ITEM: Consider Approval of a Budget Amendment & Award of a Contract to J. Ranck Electric Inc. for the Pedestrian

More information

ADDRESS PO BOX MAIN STREET 175 DRIFT ROAD 100 BILBY ROAD

ADDRESS PO BOX MAIN STREET 175 DRIFT ROAD 100 BILBY ROAD RES#2018-146 CONTRACT TERM: JUNE 22,2018-JUNE 21,2019 BID RESULTS CK09MERCER2017-02 ROAD MATERIALS FOR THE COUNTY OF MERCER AND THE MERCER COUNTY COOPERATIVE CONTRACT PURCHASING SYSTEM FOR A PERIOD OF

More information

STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. District(s): 8 30=047 Start Dt: 05/01/17 Comp. Dt:

STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. District(s): 8 30=047 Start Dt: 05/01/17 Comp. Dt: Letting: 17030200 Letting Dt: March 02, 2017 9:30 A.M. State Proj.: 5101-14 Contract ID: Contract Description: Contract Location: Recommendation: 170020 STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION

More information

MGM SPRINGFIELD OFF-SITE MITIGATION - 9/25/17 TO 10/6/17 WORK HOURS: 7:00 AM TO 3:30 PM

MGM SPRINGFIELD OFF-SITE MITIGATION - 9/25/17 TO 10/6/17 WORK HOURS: 7:00 AM TO 3:30 PM 1 A Dwight Street & I-291 Off Ramp 2 B Locust Street & Mill Street No work anticipated 3 B Main Street & East Columbus Avenue No work anticipated 4 C State Street & St. James Avenue No work anticipated

More information

S T A T E O F M I N N E S O T A D E P A R T M E N T O F T R A N S P O R T A T I O N DATE : 02/27/06 PAGE : 1 TABULATION OF BIDS

S T A T E O F M I N N E S O T A D E P A R T M E N T O F T R A N S P O R T A T I O N DATE : 02/27/06 PAGE : 1 TABULATION OF BIDS PAGE : 1 NUMBER OF DAYS: 63 BRIDGE COUNT : 9 CONTRACT DESCRIPTION : BITUMINOUS OVERLAY & BRIDGE APPROACH PANEL REPLACEMENT CONTRACT LOCATION: LOCATED ON TH 90 FROM 0.8 MILE WEST OF THE BLUE EARTH RIVER

More information

OHIO Department of Transportation Project # Franklin County, OH. ISSA Presidents Award Submission Strawser Construction Inc.

OHIO Department of Transportation Project # Franklin County, OH. ISSA Presidents Award Submission Strawser Construction Inc. OHIO Department of Transportation Project #140378 Franklin County, OH ISSA Presidents Award Submission Strawser Construction Inc. Columbus, Ohio Strawser Construction Project Team Chris Anspaugh Regional

More information

CITY of NOVI CITY COUNCIL

CITY of NOVI CITY COUNCIL CITY of NOVI CITY COUNCIL Agenda Item 3 July 9, 2018 ci tyofnovi.org SUBJECT: Approval to award design engineering services to AECOM Great Lakes, Inc., for the Flint Street Realignment and Reconstruction

More information

City of Grand Forks Staff Report

City of Grand Forks Staff Report City of Grand Forks Staff Report Service/Safety Committee May 27, 2014 City Council June 2, 2014 Agenda Item: Consideration of Bids for City Project Nos. 7152 Dist. No. 501; 7153 Dist. No. 317 and 7154

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.4 DIVISION: Sustainable Streets BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Authorizing the Department of Public Works (DPW) to award DPW Contract

More information

ADDENDUM NO. 1. Contractor shall fax back the recognition sheet acknowledging the receipt of this addendum, or include in their proposal.

ADDENDUM NO. 1. Contractor shall fax back the recognition sheet acknowledging the receipt of this addendum, or include in their proposal. ADDENDUM NO. 1 DATE: August 7, 2014 PROJECT: FROM: TO: 2014 MFT Section 14-00000-00-GM, SUPP1 United City of Yorkville Kendall County, IL Engineering Enterprises, Inc. 52 Wheeler Road Sugar Grove, Illinois

More information

OHIO Department of Transportation Project # Franklin County, OH. ISSA Presidents Award Submission Strawser Construction Inc.

OHIO Department of Transportation Project # Franklin County, OH. ISSA Presidents Award Submission Strawser Construction Inc. OHIO Department of Transportation Project #140378 Franklin County, OH ISSA Presidents Award Submission Strawser Construction Inc. Columbus, Ohio Applicant Information Strawser Construction Inc. 1392 Dublin

More information

City of Pacific Grove

City of Pacific Grove Regional Study Utilizing Caltrans Intersection Evaluation Section 7: City of Pacific Grove s: FIRST STREET AT CENTRAL AVENUE Transportation Agency for Monterey County Prepared by Transportation Agency

More information

Wednesday, April 20, 2016

Wednesday, April 20, 2016 Wednesday, April 20, 2016 MARCH 2015-MARCH 2016 REVENUE VARIANCE % CHANGE $8.6 4.3% $1.7 2.7% -$0.8-6.1% $0.3 6.3% $-21.3-53.4% $1.7 73.9% $-0.6 5.0% $-10.4-3.3% $365.0 $315.0 $311.2 $300.8 $265.0 $215.0

More information

REQUEST FOR COUNCIL ACTION. List of Exhibits A. Project Plan Set B. Bolton & Menk Proposal for Engineering / Inspection Services

REQUEST FOR COUNCIL ACTION. List of Exhibits A. Project Plan Set B. Bolton & Menk Proposal for Engineering / Inspection Services Item #08 - CC Agenda - 05/2/2016 [Page 1 of 5] REQUEST FOR COUNCIL ACTION : May 2, 2016 ITEM NO: 8 Department Approval: Administrator Reviewed: Agenda Section: Name Adam Edwards JML Public Works Director/

More information

Recommended Transportation. Capital Improvement Program

Recommended Transportation. Capital Improvement Program Recommended 2018-2022 Transportation Capital Improvement Program 1 Overview 2017 Review 2018-2022 Considerations 2018-2022 Recommended CIP 2 Limited Resources are Directed to the Highest Priority Number

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.3 DIVISION: Sustainable Streets BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Authorizing the Department of Public Works (DPW) to award DPW Contract

More information

Honorable Mayor and Members of the City Council

Honorable Mayor and Members of the City Council 12/1/2015 GS TO: FROM : DATE: SUBJECT: Honorable Mayor and Members of the City Council Thom Coughran, P.E., Interim Public Works and Utilities Director~ b Prepared by: George Alvarez P.E., T.E., City Engineer/

More information

From: Arthur Canafe, P.E. Approved by: /s/ General Manager

From: Arthur Canafe, P.E. Approved by: /s/ General Manager AGENDA ITEM : 3.F.1 MEETING DATE: 05/17/2010 ADMINISTRATIVE REPORT : 2010-64 To: Honorable Public Utilities Board Submitted by: /s/ Robert Streich AGM Engineering and Operations From: Arthur Canafe, P.E.

More information

U10 Girls - Coach Alec Long

U10 Girls - Coach Alec Long U10 Girls - Coach Alec Long Game Date Day Time Home Team Visiting Team Field 55 03/9/14 Sat 1:45 PM ASC Grey Wolves-Halsey CSSC-Long Oakdale ES 56 03/30/14 Sun 3:30 PM CSSC-Long HSC Freedom-Hughes Clear

More information

County of Los Angeles Department of Public Works BID SUMMARY

County of Los Angeles Department of Public Works BID SUMMARY PROJECT NAME CENTRAL AVENUE, ET AL. PROJECT ID RDC0013675 Engineer's Estimate (1) All American Asphalt (2) Sequel Contractors, Inc. (3) Sully-Miller Contracting Company (4) Palp, Inc. 5,177,177.00 5,292,979.00

More information

v Deborah Flint - Chief ecutive e, ficer

v Deborah Flint - Chief ecutive e, ficer Date 6/30/2017 6/30/2017: 6/26/2017: Approval EY MY By RW AE MT BY...jil 0.'1 1 Los Angeles World Airports REPORT TO THE B A - e OF AIRPORT COMMISSIONERS Meeting Date:, A irdro, /. Approved : aiph -,...

More information

City of Grand Island Tuesday, October 10, 2017 Council Session

City of Grand Island Tuesday, October 10, 2017 Council Session City of Grand Island Tuesday, October 10, 2017 Council Session Item G-12 #2017-276 - Approving Change Order No. 1 for Lift Station No. 20 Upgrade and Force Main Rehabilitation & Lift Station No. 14 Abandonment;

More information

City Council Report. Mayor and City Council

City Council Report. Mayor and City Council City Council Report To: From: Mayor and City Council City Council Meeting: February 23, 2016 Agenda Item: 3.J Edward King, Director, Big Blue Bus, Transit Services Department Subject: Custodial and Maintenance

More information

City of Grand Island Tuesday, October 23, 2012 Council Session

City of Grand Island Tuesday, October 23, 2012 Council Session City of Grand Island Tuesday, October 23, 2012 Council Session Item G5 #2012-308 - Approving Bid Award - Substation Transformer Testing Services Staff Contact: Tim Luchsinger, Jason Eley Grand Island Council

More information

TABLE OF CONTENTS EXECUTIVE SUMMARY...1 INTRODUCTION...3 PROJECTED FUTURE GROWTH...3 ROADWAY IMPROVEMENT PROJECTS...4 POTENTIAL FUNDING SOURCES...

TABLE OF CONTENTS EXECUTIVE SUMMARY...1 INTRODUCTION...3 PROJECTED FUTURE GROWTH...3 ROADWAY IMPROVEMENT PROJECTS...4 POTENTIAL FUNDING SOURCES... Transportation Impact Fee Study September 2014 TABLE OF CONTENTS EXECUTIVE SUMMARY...1 INTRODUCTION...3 PROJECTED FUTURE GROWTH...3 ROADWAY IMPROVEMENT PROJECTS......4 POTENTIAL FUNDING SOURCES...7 PROPOSED

More information

City of Grand Forks Staff Report

City of Grand Forks Staff Report City of Grand Forks Staff Report Service/Safety Committee December 15, 2015 City Council December 21, 2015 Agenda Item: Amendment No. 1 to Engineering Services Agreement with CPS for City Project No. 7143,

More information

Delaware County Engineer s Office

Delaware County Engineer s Office Delaware County Engineer s Office JANUARY 2017 County Engineer Responsibility Serve as engineer to the Board of County Commissioners and 18 Boards of Township Trustees for roads, bridges and land surveying

More information

DATE: June 12,2007 CONSTRUCTION AND MAINTENANCE CONTRACTS AND PURCHASING

DATE: June 12,2007 CONSTRUCTION AND MAINTENANCE CONTRACTS AND PURCHASING -- -.--- --, - -- -,-. Execibve D~rector's Report to the Board of Harbor Commissioners DATE: June 12, REYNOLDS BUICK/PONTIAC/GMC TRUCKS, INC. SUMMARY Award of contracts to Wondries Fleet Group for the

More information

Purpose of Capital Improvement Program

Purpose of Capital Improvement Program 1 Purpose of Capital Improvement Program o To identify capital projects and funding sources. o To strategically plan and prioritize projects within a budget to maximize the efficient use of funds. o Preserve

More information

CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE

CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE TUESDAY, DECEMBER 5, 2017 1 DISCUSSION TOPICS Update of Infrastructure Action Plan (IAP) o Sidewalk and Roadway projects

More information

US 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017

US 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017 US 29 Bus Rapid Transit Planning Board Briefing February 16, 2017 Project Goals Improve the quality of transit service Improve mobility opportunities and choices Enhance quality of life Support master

More information

City of Grand Island Tuesday, February 13, 2018 Council Session

City of Grand Island Tuesday, February 13, 2018 Council Session City of Grand Island Tuesday, February 13, 2018 Council Session Item G-7 #2018-34 - Approving Certificate of Final Completion for the Construction of North Interceptor Phase I; Project No. 2012-S-6 Staff

More information

Otsego County Road Commission

Otsego County Road Commission Otsego County Road Commission William T. Holewinski, Jr., Commissioner Troy W. Huff, Commissioner David C. Matelski, Commissioner Jason T. Melancon, Manager Thomas A. Deans, Engineer Rebecca L. Jerry,

More information

Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001

Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001 Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001 Revised April 5, 2005 Revised January 27, 2006 Prepared by: Steve Collin, Engineer 2.5 Revised by Douglas

More information

City of Grand Island

City of Grand Island City of Grand Island Tuesday, May 25, 2010 Council Session Item G10 #2010-139 - Approving Bid Award for Substation Power Transformers Staff Contact: Gary R. Mader City of Grand Island City Council Council

More information

AGENDA ITEM C3. RECOMMENDATION: Approve Contract No with Lavandera Electrical

AGENDA ITEM C3. RECOMMENDATION: Approve Contract No with Lavandera Electrical AGENDA ITEM C3 DATE: June 1, 2014 TO: FROM: SUBJECT: Matt Jordan, General Manager Charles H. Carden, Chief Operating Officer Section 21 Wellfield Electrical Components - Project No. 07530 Award Construction

More information

CAPITAL FUND 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS

CAPITAL FUND 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS 2019-2023 9510 STREET & SIDEWALK IMPROVEMENTS - 01 STREET AND SIDEWALK MAINTENANCE PROGRAM $1,250,000 $0 $1,250,000

More information

The bid from Modern Chevrolet was the lowest responsive, responsible bidder with a bid of $37, Attachments: Proposal/bid tab sheet RFP

The bid from Modern Chevrolet was the lowest responsive, responsible bidder with a bid of $37, Attachments: Proposal/bid tab sheet RFP MEMORANDUM TO: FROM: SUBJECT: Board of County Commissioners Martha Lide, Interim County Manager Award of Cab and Chassis for Library Book Vehicle DATE: August 1, 2013 It is recommended that the Board award

More information

Ohio Department of Transportation Official Bid Tabulation James G. Beasley, P.E., P.S., Director

Ohio Department of Transportation Official Bid Tabulation James G. Beasley, P.E., P.S., Director Ohio Department of Transportation Official Bid Tabulation James G. Beasley, P.E., P.S., Director Project No. 080598 PID 21272 CUY-SR-237-4.93 - PART I (FRONT STREET); CUY-237-4.55 - P Federal Type: RAILROAD

More information

Our Focus: Your Future 2008 FLEET REPLACEMENT PLAN AWARD OF TENDERS FOR THE PURCHASE OF REPLACEMENT VEHICLES

Our Focus: Your Future 2008 FLEET REPLACEMENT PLAN AWARD OF TENDERS FOR THE PURCHASE OF REPLACEMENT VEHICLES Town of Fort Erie Infrastructure Services Our Focus: Your Future Prepared for Council-in-Committee Report No. IS-08-08 Agenda Date March 3, 2008 File No. 2401-02 Subject 2008 FLEET REPLACEMENT PLAN AWARD

More information

SAN RAFAEL CITY COUNCIL AGENDA REPORT

SAN RAFAEL CITY COUNCIL AGENDA REPORT Agenda Item No: 8.b Meeting Date: December 19, 2016 Department: PUBLIC WORKS SAN RAFAEL CITY COUNCIL AGENDA REPORT Prepared by: Bill Guerin, Public Works Director City Manager Approval: File No.: 18.01.79

More information

BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY. Consent Workshop [ ]

BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY. Consent Workshop [ ] - _j POSTPONED FROM THE JANUARY 14 BCC MEETING Agenda Item #5,::.. I BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY Meeting Date: February 4, 2014 [ ] [ ] Department: Submitted By: Engineering & Public

More information

Riverside County Transportation Department Summary of Bids

Riverside County Transportation Department Summary of Bids 1 COUNTY'S ESTIMATE R-JS General Construction Riverside, CA 92509 ITEM NO. ITEM CODE CONTRACT ITEM UNITS QUANTITY UNIT PRICE ENG ESTIMATE BID UNIT PRICE BID ESTIMATE 1 066102 DUST ABATEMENT LS 1 3,000.00

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.5 SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY DIVISION: Capital Programs & Construction BRIEF DESCRIPTION: Awarding San Francisco Municipal Transportation Agency

More information

DOCUMENTATION WORKBOOK FY 2017

DOCUMENTATION WORKBOOK FY 2017 DOCUMENTATION WORKBOOK SPECIFIC TASK TRAINING PROGRAM Conducted by the ILLINOIS CENTER FOR TRANSPORTATION (ICT) AND IDOT BUREAU OF CONSTRUCTION FY 2017 WORKBOOK TABLE OF CONTENTS Workbook Page 1... Maximum

More information

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015 Transportation Committee Revised Project Scope and Cost Estimate November 23, 2015 1 Today s Topics Revised Project Scope Revised Cost Estimate Municipal Approval Action 2 3 Revised Project Scope Project

More information

4.0 TIER 2 ALTERNATIVES

4.0 TIER 2 ALTERNATIVES 4.0 TIER 2 ALTERNATIVES The Tier 2 Alternatives represent the highest performing Tier 1 Alternatives. The purpose of the Tier 2 Screening was to identify the LPA utilizing a more robust list of evaluation

More information

DES MOINES AIRPORT AUTHORITY BOARD SUMMARY OF REGULAR MEETING Des Moines International Airport Board Room May 13, 2014

DES MOINES AIRPORT AUTHORITY BOARD SUMMARY OF REGULAR MEETING Des Moines International Airport Board Room May 13, 2014 DES MOINES AIRPORT AUTHORITY BOARD SUMMARY OF REGULAR MEETING Des Moines International Airport Board Room May 13, 2014 Call to Order and Roll Call: Present: Erickson, Feldmann, Hansell, and Ward. Absent:

More information

Business Advisory Committee. November 3, 2015

Business Advisory Committee. November 3, 2015 Business Advisory Committee November 3, 2015 1 Today s Topics DEIS Cost Estimate 2 Assumptions Revised Cost Estimate Revised Project Scope Cost Estimate Overview Position Statement Discussion Municipal

More information

EXISTING PAVEMENT EVALUATION Howell Ferry Road Duluth, Gwinnett County, Georgia. WILLMER ENGINEERING INC. Willmer Project No

EXISTING PAVEMENT EVALUATION Howell Ferry Road Duluth, Gwinnett County, Georgia. WILLMER ENGINEERING INC. Willmer Project No EXISTING PAVEMENT EVALUATION WILLMER ENGINEERING INC. Prepared For Clark Patterson Lee Suwanee, Georgia Prepared By WILLMER ENGINEERING INC. 3772 Pleasantdale Road Suite 165 Atlanta, Georgia 30340-4270

More information

traversing them. Speed dips may be installed in lieu of speed humps where the 85 th percentile speed on a street is at least 36 mph.

traversing them. Speed dips may be installed in lieu of speed humps where the 85 th percentile speed on a street is at least 36 mph. County of San Mateo Department of Public Works Residential Speed Control Device Program PURPOSE The purpose of the Residential Speed Control Devices 1 Program is to provide a consistent, fair and cost-effective

More information

TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA

TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA PREPARED FOR: UNIVERSITY OF PENNSYLVANIA HEALTH SYSTEM 34 CIVIC CENTER BOULEVARD PHILADELPHIA, PA 1987 (61)

More information

CITY OF WINDCREST ROADWAY CAPITAL IMPROVEMENT PROGRAM STATUS REPORT JULY 2014

CITY OF WINDCREST ROADWAY CAPITAL IMPROVEMENT PROGRAM STATUS REPORT JULY 2014 CITY OF WINDCREST ROADWAY CAPITAL IMPROVEMENT PROGRAM STATUS REPORT JULY 2014 IN THE SPOTLIGHT Roadway Improvement Projects - Package #2 Construction Package #2 is the second of four groupings of similar

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.5 DIVISION: Transit Services BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Requesting authorization for the SFMTA, through the Director of Transportation,

More information

Alpine Highway to North County Boulevard Connector Study

Alpine Highway to North County Boulevard Connector Study Alpine Highway to North County Boulevard Connector Study prepared by Avenue Consultants March 16, 2017 North County Boulevard Connector Study March 16, 2017 Table of Contents 1 Summary of Findings... 1

More information

Elkhart River Greenway Trail

Elkhart River Greenway Trail EXTENDED ROUTE Elkhart River Greenway Trail For more information on this trail, see page 34 of the Elkhart County 2017 Trail Guide. Start at the Elkhart River Greenway Trailhead in Studebaker Park and

More information

2017 Jefferson County Outreach Jefferson County Maintenance. Matthew Burkett ~ Jefferson County Maintenance Manager

2017 Jefferson County Outreach Jefferson County Maintenance. Matthew Burkett ~ Jefferson County Maintenance Manager Outreach 2017 2017 Jefferson County Outreach Jefferson County Maintenance Matthew Burkett ~ Jefferson County Maintenance Manager MATERIAL 2016-2017 Jefferson County Outreach Winter Maintenance Information

More information

AGENDA REPORT. Craig Crowder, Fleet Manager %-

AGENDA REPORT. Craig Crowder, Fleet Manager %- AGENDA REPORT Meeting Date: April 5, 2016 Item Number: D 22 To: Honorable Mayor & City Council From: Chad Lynn, Assistant Director of Public Works Service s1 Craig Crowder, Fleet Manager %- Subject: APPROVAL

More information

City of Grand Island Tuesday, January 22, 2013 Council Session

City of Grand Island Tuesday, January 22, 2013 Council Session City of Grand Island Tuesday, January 22, 2013 Council Session Item G10 #2013-24 - Approving Bid Award for Two (2) Storm Water Pumps for the Solid Waste Division Staff Contact: Terry Brown, Interim Public

More information

HMA Thin Lifts for Pavement Preservation in Tennessee

HMA Thin Lifts for Pavement Preservation in Tennessee HMA Thin Lifts for Pavement Preservation in Tennessee The Tennessee Program 5,109 Interstate Lane Miles 26,244 State Route LM 31,353 Total* MARK WOODS, P.E. TDOT DIV. OF MATERIALS AND TESTS * As of 2008

More information

Board of Directors authorization is required for all goods and services contracts obligating TriMet to pay in excess of $500,000.

Board of Directors authorization is required for all goods and services contracts obligating TriMet to pay in excess of $500,000. Date: April 11, 2012 To: From: Board of Directors Neil McFarlane Subject: RESOLUTION 12-04-30 OF THE TRI-COUNTY METROPOLITAN TRANSPORTATION DISTRICT OF OREGON (TRIMET) AUTHORIZING A CONTRACT WITH SIEMENS

More information

STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. Start Dt: 05/08/17 Comp. Dt:

STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. Start Dt: 05/08/17 Comp. Dt: Letting: 17012700 Letting Dt: January 27, 2017 9:30 A.M. State Proj.: 4308-34 Contract ID: Contract Description: Contract Location: Recommendation: 170004 STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION

More information

Highways: State Highways. Highways: Local Roads. Highways: Off State Hwy Sys/Off Fed Sys. Transportation Planning: Non-System Specific

Highways: State Highways. Highways: Local Roads. Highways: Off State Hwy Sys/Off Fed Sys. Transportation Planning: Non-System Specific FLORIDA DEPARTMENT OF TRANSPORTATION 5 - YEAR TRANSPORTATION PLAN ($ IN THOUSANDS) TENTATIVE FY 2019-2023 (10/01/2017 20:15:01) LEVY COUNTY Highways: State Highways 4135251 D2-LEVY COUNTY TRAFFIC SIGNAL

More information

SPECIFICATIONS AND DOCUMENTS FOR PURCHASE OF ROAD MATERIALS AND RENTAL OF CERTAIN PIECES OF CONSTRUCTION EQUIPMENT

SPECIFICATIONS AND DOCUMENTS FOR PURCHASE OF ROAD MATERIALS AND RENTAL OF CERTAIN PIECES OF CONSTRUCTION EQUIPMENT SPECIFICATIONS AND DOCUMENTS FOR PURCHASE OF ROAD MATERIALS AND RENTAL OF CERTAIN PIECES OF CONSTRUCTION EQUIPMENT (Gravel, Crushed Rock, Sand, Road Oils, Recycled Aggregate, Bituminous Milling, Sealcoating,

More information

City of Freeport Water & Sewer Capital Improvement Program FY2019-FY2024

City of Freeport Water & Sewer Capital Improvement Program FY2019-FY2024 City of Freeport Water & Sewer Capital Improvement Program FY2019-FY2024 Current Issues $210 million in depreciated water & sewer assets are in need of replacement Many items: Production Wells, Treatment

More information

Municipal Road and Bridge Revolving Loan Fund Program Summary Rhode Island Department of Transportation

Municipal Road and Bridge Revolving Loan Fund Program Summary Rhode Island Department of Transportation Municipal Road and Bridge Revolving Loan Fund 2014 Program Summary Rhode Island Department of Transportation The Basics The FY2014 Budget passed by the Rhode Island General Assembly included Article 20,

More information

I.D.O.T. Update Version -

I.D.O.T. Update Version - I.D.O.T. Update - 2007 Version - RUBBLIZATION Rubblization with HMA Overlay Rehabilitation method for deteriorated concrete pavements Alternative to extensive patching or reconstruction Pavement in effect

More information

CITY OF ELK GROVE CITY COUNCIL STAFF REPORT

CITY OF ELK GROVE CITY COUNCIL STAFF REPORT CITY OF ELK GROVE CITY COUNCIL STAFF REPORT AGENDA ITEM NO. 10.2 AGENDA TITLE: Receive Update on Citywide Light Emitting Diode (LED) Streetlight Conversion and Provide Guidance on Next Steps MEETING DATE:

More information

Date: 04/20/2018 City Project No.: Addendum No.: 4. The following changes shall be made to the project plans and specifications:

Date: 04/20/2018 City Project No.: Addendum No.: 4. The following changes shall be made to the project plans and specifications: DEVELOPMENT SERVICES PHONE: (209) 668-5520 ENGINEERING DIVISION FAX: (209) 668-5563 156 S. BROADWAY, SUITE 150 TDD: (800) 735-2929 TURLOCK, CA 95380 engineering@turlock.ca.us Date: 04/20/2018 City Project

More information

STREET IMPROVEMENTS PROPOSAL BID ITEMS

STREET IMPROVEMENTS PROPOSAL BID ITEMS STREET IMPROVEMENTS 1 Excavation 3,525 CY $ $ 2 A.C. Planing (2" to 4" Depth) 20,586 SY $ $ 3 Furnish & Install Asphalt Concrete 4,270 TON $ $ 4 Furnish & Install Aggregate Base 2,955 TON $ $ 5 Remove

More information

Richmond Area MPO Regional Priority Transportation Projects

Richmond Area MPO Regional Priority Transportation Projects Regional Priority Transportation Projects September 27, 2007 HANOVER GOOCHLAND ASHLAND POWHATAN RICHMOND HENRICO NEW KENT CHESTERFIELD CHARLES CITY 9211 Forest Hill Avenue, Suite 200 Richmond, Virginia

More information

Workshop Agenda. Bransford Roundabout. Bedford Intersection/Roundabout. Section 3 Revisions (Left turn lanes) Roadway Section/Curb Type Discussion

Workshop Agenda. Bransford Roundabout. Bedford Intersection/Roundabout. Section 3 Revisions (Left turn lanes) Roadway Section/Curb Type Discussion Workshop Agenda Bransford Roundabout Bedford Intersection/Roundabout Section 3 Revisions (Left turn lanes) Roadway Section/Curb Type Discussion Project Phasing Summary of Recommendation Purpose: Provide

More information

West Broadway Reconstruction/LRT Design. March 19, 2015

West Broadway Reconstruction/LRT Design. March 19, 2015 West Broadway Reconstruction/LRT Design March 19, 2015 1 Meeting Agenda 6:05 6:30 PM Brief presentation What we heard Project overview 6:30 8:00 PM Visit Six Topic Areas Road and LRT design elements Pedestrian

More information

Contract Awards December 22, Composite Report

Contract Awards December 22, Composite Report STAFF REPORT ACTION REQUIRED Contract Awards December 22, 2010 - Composite Report Date: December 16, 2010 To: From: Bid Committee Director, Purchasing and Materials Management Reference Various Calls SUMMARY

More information

STREET LIGHTING AND ELECTRICAL SYSTEM UNDERGROUNDING. Underground Vault

STREET LIGHTING AND ELECTRICAL SYSTEM UNDERGROUNDING. Underground Vault CIP_215 Title Pages 217:Layout 1 8/16/16 4:2 PM Page 7 STREET LIGHTING AND ELECTRICAL SYSTEM UNDERGROUNDING Underground Vault A D O P T E D C A P I T A L I M P R O V E M E N T P R O G R A M B U D G E T

More information

CITY OF STEVENS POINT AGENDA

CITY OF STEVENS POINT AGENDA CITY OF STEVENS POINT BOARD OF PUBLIC WORKS MEETING Monday, September 11, 2017 6:00 p.m. (or immediately following previously scheduled meeting) Lincoln Center 1519 Water Street Stevens Point, WI 54481

More information

The Director, Purchasing and Materials Management recommends that the Bid Award Panel grant authority to award the following contract:

The Director, Purchasing and Materials Management recommends that the Bid Award Panel grant authority to award the following contract: Award of Request for Quotation No. 6102-16-3100 for the provision of overflow preventative maintenance and repair services to vehicles of various classes for various City of Toronto Divisions Date: February

More information

POSTPONED UNTIL JULY 25, 2013 BID RESULTS AB FESTIVAL GROUNDS PLAZA PROJECT JULY 11, 2013

POSTPONED UNTIL JULY 25, 2013 BID RESULTS AB FESTIVAL GROUNDS PLAZA PROJECT JULY 11, 2013 POSTPONED UNTIL JULY 25, 2013 BID RESULTS AB2013-23 FESTIVAL GROUNDS PLAZA PROJECT JULY 11, 2013 Work will commence within Ten (10) Calendar Days after receipt of written "Notice to Proceed" and be substantially

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate

More information

NCDOT Facilities Management & Division of Motor Vehicles Summary of Requests for Proposals for Leasing Options for new DMV Headquarters Site

NCDOT Facilities Management & Division of Motor Vehicles Summary of Requests for Proposals for Leasing Options for new DMV Headquarters Site NCDOT Facilities Management & Division of Motor Vehicles Summary of Requests for Proposals for Leasing Options for new DMV Headquarters Site Report Compiled by: NCDOT Facilities Management Unit Director:

More information

City of San Juan Capistrano Agenda Report

City of San Juan Capistrano Agenda Report 12/16/214 82 City of San Juan Capistrano Agenda Report TO: FROM: DATE: SUBJECT: Karen P. Brust, City Manag4(?1-- Keith Van Der Maaten, P.E., Public Works and Utilities Directo Prepared by: George Alvarez,

More information

15 Year Road Improvement / Maintenance Plan 2017 through 2031 Elko County Infrastructure Tax Allocation Amended Version Number Two

15 Year Road Improvement / Maintenance Plan 2017 through 2031 Elko County Infrastructure Tax Allocation Amended Version Number Two 15 Year Road Improvement / Maintenance Plan 2017 through 2031 Elko County Infrastructure Tax Allocation Amended Version Number Two Estimated Annual Resources - $2,000,000 Elko County $ 1,500,000 75.00%

More information