Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study

Size: px
Start display at page:

Download "Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study"

Transcription

1 Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study FROM MICHIGAN AVENUE TO INDUSTRY ROAD BREVARD COUNTY, FLORIDA Financial Project ID No: Federal Aid Project No: N/A ETDM No: BICYCLE, PEDESTRIAN, AND TRAILS ADVISORY COMMITTEE PRESENTATION September 21, 2015

2 Agenda What is a PD&E Study? Background Design Alternatives Conclusion 2

3 What is a PD&E Study? Project Development & Environment (PD&E) Study A process to analyze a transportation project 1. Engineering Identify potential design solutions 2. Environmental Evaluate potential impacts to the natural, social, and physical environments 3. Public Involvement Seek public input 3

4 Study Limits Industry Road E. INDUSTRY RD. N From Michigan Avenue to Industry Road Approximately 1.3 miles in length Michigan Avenue 4

5 Purpose and Need Accommodate future traffic needs based on anticipated population and employment growth Certain roadway segments are nearing capacity Enhance safety and mobility Gaps exist in sidewalks and bicycle lanes 5

6 Existing Roadway Typical Section - From Michigan Ave to 720 feet north of Michigan Ave SB NB 3' 12' 12' 12' 12' 12' 10 ' EXISTING R/W 73' 6' Sidewalk 6

7 Existing Roadway Typical Section - From 720 feet north of Michigan Ave to north of Walmart SB NB 5' Sidewalk 16' - 42' 12' 12' 10' - 12' 10' - 12' 11' - 34' EXISTING R/W VARIES 73' - 120' 5' Sidewalk 7

8 Existing Roadway Typical Section - From north of Walmart to Industry Road ±5' Paved Shoulder EB WB ±5' Paved Shoulder 5' Sidewalk 12' - 22' 0' - 12' 12' - 33' VARIES (129' 164') VARIES (75' 100') EXISTING R/W VARIES 229' - 239' 8

9 Alternatives Considered Build Alternative Widen road to four lanes, two travel lanes in each direction Realign existing curve at Walmart Provide continuous 7-ft bicycle lanes and 6-ft sidewalks on both sides Provide access management 22-foot grass/concrete median will limit left turns along corridor Locate potential pond sites No-Build or Do Nothing Alternative No corridor improvements No continuous sidewalks and designated bicycle lanes No-Build continues as an alternative throughout the PD&E study 9

10 Design Alternatives 10

11 Design Alternatives - From Michigan Avenue to Otterbein Avenue (Segment 1) N Otterbein Avenue Michigan Avenue 11

12 Proposed Roadway Typical Section - From Michigan Avenue to Otterbein Avenue 4-Lane Urban Divided Roadway Typical Section 6' Sidewalk SB NB 6' Sidewalk VARIES 12' Min. 7' 11' 11' 22' 11' 11' 7' VARIES 12' Min. 104 MINIMUM PROPOSED R/W EXISTING R/W VARIES 73' - 120' 12

13 Design Alternatives - From Michigan Ave to Otterbein Ave The proposed roadway typical section can be built along three different alignments: West Center East Each alignment has different right-of-way impacts 13

14 Design Alternatives - From Michigan Ave to Otterbein Ave West Alignment N Will require additional right-of-way from the west side of Clearlake Road only 14

15 Design Alternatives - From Michigan Ave to Otterbein Ave Center Alignment N Will require additional right-of-way from both the west side and east side of Clearlake Road 15

16 Design Alternatives - From Michigan Ave to Otterbein Ave East Alignment N Will require additional right-of-way from the east side of Clearlake Road Some right-of-way will still be needed on the west side of Clearlake Road, north and south of Mantes Drive 16

17 Design Alternatives - From Michigan Ave to Otterbein Ave Right-of-Way Impacts Each alignment has a different right-of-way impact and associated cost Evaluation Criteria Four-Lane Urban Typical Section West Alignment Center Alignment East Alignment Residential Parcels Impacted Business Parcels Impacted Unimproved Parcels Impacted Total Parcels Impacted Relocations # of Residences Relocated # of Businesses Relocated Total Number of Relocations Right-of-Way Cost $6,400,000 $7,876,000 $11,714,500 17

18 Design Alternatives - From Otterbein Avenue to Industry Road (Segment 2) Industry Road E. INDUSTRY RD. N Otterbein Avenue 18

19 Proposed Roadway Typical Section - From Otterbein Avenue to Industry Road 4-Lane Urban Divided Roadway Typical Section 6' Sidewalk SB NB 6' Sidewalk VARIES 12' Min. 7' 11' 11' 22' 11' 11' 7' VARIES 12' Min. 104 MINIMUM PROPOSED R/W EXISTING R/W VARIES 120' - 239' 19

20 Design Alternatives - From Otterbein Avenue to Industry Road Four alternatives developed to realign the existing curve: 45 mph curve 35 mph curve Bulb-Out Roundabout N Existing Curve Each alternative to realign curve has different right-of-way impacts 20

21 Design Alternative to Realign Curve - 45 MPH Curve 21

22 Design Alternative to Realign Curve - 45 MPH Curve N 22

23 Design Alternative to Realign Curve - 35 MPH Curve 23

24 Design Alternative to Realign Curve - 35 MPH Curve N 24

25 Design Alternative to Realign Curve - Bulb-Out 25

26 Design Alternative to Realign Curve - Bulb-Out N 26

27 Design Alternative to Realign Curve - Roundabout 27

28 Design Alternative to Realign Curve - Roundabout N 28

29 Design Alternatives - From Otterbein Avenue to Industry Road Right-of-Way Impacts Each alternative to realign the curve has a different right-of-way impact and associated cost Evaluation Criteria Realign Curve 45 mph curve 35 mph curve Roundabout Bulb-Out Residential Parcels Impacted Business Parcels Impacted Unimproved Parcels Impacted Total Parcels Impacted Relocations # of Residences Relocated # of Businesses Relocated Total Number of Relocations Right-of-Way Cost $4,762,500 $2,538,000 $813,000 $3,102,000 29

30 Cost Estimate for Entire Study Limit - Michigan Avenue to Industry Road Realign Curve Evaluation Criteria 45 mph curve 35 mph curve Roundabout Bulb-Out Phase Cost Construction (Entire Study Limits) $10,100,999 $10,260,818 $10,393,540 $10,509,539 Design (Entire Study Limits) $1,800,000 $1,800,000 $1,800,000 $1,800,000 Right-of-Way (Otterbein Ave to Industry Rd) $4,762,500 $2,538,000 $813,000 $3,102,000 Right-of-Way (Ponds) TBD TBD TBD TBD Construction Engineering and Inspections $1,010,100 $1,026,082 $1,039,354 $1,050,954 Mitigation TBD TBD TBD TBD Total Cost * $17,775,439 $15,749,371 $14,068,525 $16,841,565 Four-Lane Urban Typical Section Evaluation Criteria West Alignment Center Alignment East Alignment Right-of-Way Cost (Michigan Ave to Otterbein Ave) $6,400,000 $7,876,000 $11,714,500 * Option chosen to realign curve Option chosen to align the typical section Total Estimated Project Cost Bulb-Out West Alignment $23,241,565 30

31 Conclusion 31

32 Funding Design Funded in 2016 Concurrent PD&E & Design phases New process by FDOT to streamline and accelerate all projects in the pre-construction phases Right-of-Way Purchase Currently not funded Construction Currently not funded 32

33 Next Steps Further refine and evaluate design alternatives Select a recommended design alternative Complete environmental and engineering reports Public Hearing Anticipated in February of 2016 All reports will be available for public review 21 days prior to the Public Hearing Obtain State Environmental Impact Report (SEIR) approval from the FDOT District Five Secretary Anticipated in April of

34 Study Website Documents & Publications: All information presented at public meetings, including the presentation All draft engineering and environmental and reports 34

35 Contact Us! Jazlyn Heywood, P.E. FDOT Project Manager FDOT District Five 719 South Woodland Blvd., M.S. 501 Deland, FL Tel: (386) Aniruddha (Rudy) Gotmare, P.E. Consultant Project Manager Scalar Consulting Group, Inc W. Blue Heron,P.E. Blvd. Suite 119 Riviera Beach, FL Tel: (954)

36 Thank you for attending! BICYCLE, PEDESTRIAN, AND TRAILS ADVISORY COMMITTEE PRESENTATION Clearlake Road PD&E Study 36

Public Information Workshop

Public Information Workshop Public Information Workshop Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 29, 2018 Welcome to the Public Information Workshop for Harborview Road Project Development and Environment (PD&E)

More information

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What

More information

WOODVILLE HIGHWAY (SR 363) PD&E STUDY From Capital Circle Southeast To Paul Russell Road FPID NUMBER: Public Hearing

WOODVILLE HIGHWAY (SR 363) PD&E STUDY From Capital Circle Southeast To Paul Russell Road FPID NUMBER: Public Hearing WOODVILLE HIGHWAY (SR 363) PD&E STUDY From Capital Circle Southeast To Paul Russell Road FPID NUMBER: 424009-3 Public Hearing May 9, 2013 This Public Hearing is being held in accordance with the Federal-aid

More information

Kendall Drive Premium Transit PD&E Study

Kendall Drive Premium Transit PD&E Study Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study From

More information

Traffic Impact Statement (TIS)

Traffic Impact Statement (TIS) Traffic Impact Statement (TIS) Vincentian PUDA Collier County, FL 10/18/2013 Prepared for: Global Properties of Naples Prepared by: Trebilcock Consulting Solutions, PA 2614 Tamiami Trail N, Suite 615 1205

More information

METRO Orange Line BRT American Boulevard Station Options

METRO Orange Line BRT American Boulevard Station Options METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN

More information

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015 SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment

More information

Lacey Gateway Residential Phase 1

Lacey Gateway Residential Phase 1 Lacey Gateway Residential Phase Transportation Impact Study April 23, 203 Prepared for: Gateway 850 LLC 5 Lake Bellevue Drive Suite 02 Bellevue, WA 98005 Prepared by: TENW Transportation Engineering West

More information

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP)

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP) NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP) Project Overview Briefing Packet March 2017 PROJECT OVERVIEW Environmental Impact Statement (EIS) Project divided into 3 Segments Segment 1: Beltway 8

More information

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,

More information

HDR Engineering. HART North / South. Tampa Bay Applications Group Meeting May 14, 2009

HDR Engineering. HART North / South. Tampa Bay Applications Group Meeting May 14, 2009 HDR Engineering HART North / South BRT Corridor PD&E Tampa Bay Applications Group Meeting May 14, 2009 1 Agenda Update on Project Development and Environment (PD&E) Study Project Overview System Branding

More information

West Broadway Reconstruction/LRT Design. March 19, 2015

West Broadway Reconstruction/LRT Design. March 19, 2015 West Broadway Reconstruction/LRT Design March 19, 2015 1 Meeting Agenda 6:05 6:30 PM Brief presentation What we heard Project overview 6:30 8:00 PM Visit Six Topic Areas Road and LRT design elements Pedestrian

More information

EXCEPTION TO STANDARDS REPORT

EXCEPTION TO STANDARDS REPORT EXCEPTION TO STANDARDS REPORT PROJECT DESCRIPTION AND NEED The project is located in Section 6, Township 23 North, Range 9 East and Section 31 Township 24 North, Range 9 East, in the Town of Stockton,

More information

Rolling Road (Route 638) Widening Project

Rolling Road (Route 638) Widening Project Rolling Road (Route 638) Widening Project From: 0.369 Mile North of Fairfax County Parkway (Route 286) To: Old Keene Mill Road (Route 644) State Project No. 0638-029-156, P104, R204, C504; UPC 5559 Public

More information

Business Advisory Committee. July 7, 2015

Business Advisory Committee. July 7, 2015 Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS

More information

Transportation. Background. Transportation Planning Goals. Level of Service Analysis 5-1

Transportation. Background. Transportation Planning Goals. Level of Service Analysis 5-1 Transportation portion of the city s stormwater utility, and state road and fuel taxes. Background The transportation needs of the City of Lacey and its planning areas are met by a growing multimodal network

More information

PUBLIC MEETING. Bear Creek Park Community Center. January 24, :30 pm to 7:30 pm

PUBLIC MEETING. Bear Creek Park Community Center. January 24, :30 pm to 7:30 pm PUBLIC MEETING Bear Creek Park Community Center January 24, 2017 5:30 pm to 7:30 pm PURPOSE OF THE MEETING This is an open House No formal presentation Introduce the project to the public Present existing

More information

Attachment E3 Vibration Technical Memorandum

Attachment E3 Vibration Technical Memorandum Attachment E3 Technical Memorandum 77 South Bedford Street Burlington, MA 01803 T 781.229.0707 F 781.229.7939 E jross@hmmh.com W www.hmmh.com TECHNICAL MEMORANDUM To: Alisa Swank, CH2M HILL Jodi Ketelsen,

More information

TIMBERVINE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO JANUARY Prepared for:

TIMBERVINE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO JANUARY Prepared for: TIMBERVINE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO JANUARY 2014 Prepared for: Hartford Companies 1218 W. Ash Street Suite A Windsor, Co 80550 Prepared by: DELICH ASSOCIATES 2272 Glen Haven Drive

More information

SH 249 IN GRIMES COUNTY. Open House April 3, 2014

SH 249 IN GRIMES COUNTY. Open House April 3, 2014 SH 249 IN GRIMES COUNTY Open House April 3, 2014 Meeting Agenda Purpose of Meeting Today: Review the purpose and need for the SH 249 Grimes County project Review the proposed project and alternatives Discuss

More information

TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA

TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA PREPARED FOR: UNIVERSITY OF PENNSYLVANIA HEALTH SYSTEM 34 CIVIC CENTER BOULEVARD PHILADELPHIA, PA 1987 (61)

More information

US 81 Bypass of Chickasha Environmental Assessment Public Meeting

US 81 Bypass of Chickasha Environmental Assessment Public Meeting US 81 Bypass of Chickasha Environmental Assessment Public Meeting March 14, 2013 Introductions ODOT FHWA SAIC Meeting Purpose Present need for bypass Provide responses to 10/04/11 public meeting comments

More information

DRAFT Subject to modifications

DRAFT Subject to modifications TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M DRAFT To: Council Members AGENDA ITEM 7A From: Date: Subject: Staff September 17, 2010 Council Meeting High Speed Rail Update Introduction The

More information

Project Description: Georgia Department of Transportation Public Information Open House Handout PI#(s): , County: Muscogee

Project Description: Georgia Department of Transportation Public Information Open House Handout PI#(s): , County: Muscogee Why We Are Here: GDOT s Transportation Improvement Act (TIA) Office, the City of Columbus, and the project delivery team are here this evening to display and answer questions concerning the proposed roadway

More information

Workshop Agenda. Bransford Roundabout. Bedford Intersection/Roundabout. Section 3 Revisions (Left turn lanes) Roadway Section/Curb Type Discussion

Workshop Agenda. Bransford Roundabout. Bedford Intersection/Roundabout. Section 3 Revisions (Left turn lanes) Roadway Section/Curb Type Discussion Workshop Agenda Bransford Roundabout Bedford Intersection/Roundabout Section 3 Revisions (Left turn lanes) Roadway Section/Curb Type Discussion Project Phasing Summary of Recommendation Purpose: Provide

More information

Business Advisory Committee. November 3, 2015

Business Advisory Committee. November 3, 2015 Business Advisory Committee November 3, 2015 1 Today s Topics DEIS Cost Estimate 2 Assumptions Revised Cost Estimate Revised Project Scope Cost Estimate Overview Position Statement Discussion Municipal

More information

YELM HWY AND MERIDIAN RD INTERSECTION IMPROVEMENTS PROJECT CONTEXT

YELM HWY AND MERIDIAN RD INTERSECTION IMPROVEMENTS PROJECT CONTEXT PROJECT CONTEXT 510 Hicks L A C E Y Mullen Rd SE Thurston County Fairgrounds Rd SE Carpenter Long Woodland Elementary Rd SE Marvin Old Paci c H w y 510 Reservation Rd SE Nisqually Indian Community Nis

More information

Harlem Avenue between 63 rd and 65 th

Harlem Avenue between 63 rd and 65 th Harlem Avenue between 63 rd and 65 th Community Advisory Group Meeting #3 December 1, 2017 Bedford Park Public Library 1 Meeting Agenda 1. Welcome/Introductions (3 mins) 2. Project Overview and Re-Cap

More information

Plainfield, Indiana Speed Limit Study

Plainfield, Indiana Speed Limit Study March 21 st, 2017 Prepared on behalf of: Town of Plainfield Building and Engineering Department 206 W. Main Street Plainfield, IN 46168 (317) 839-2561 Prepared by: Thomas S. Vandenberg, PE, PTOE Matthew

More information

Subarea Study. Manning Avenue (CSAH 15) Corridor Management and Safety Improvement Project. Final Version 1. Washington County.

Subarea Study. Manning Avenue (CSAH 15) Corridor Management and Safety Improvement Project. Final Version 1. Washington County. Subarea Study Manning Avenue (CSAH 15) Corridor Management and Safety Improvement Project Final Version 1 Washington County June 12, 214 SRF No. 138141 Table of Contents Introduction... 1 Forecast Methodology

More information

Wentzville Parkway South Phase 2 & 2A

Wentzville Parkway South Phase 2 & 2A Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total

More information

Waco Rapid Transit Corridor (RTC) Feasibility Study

Waco Rapid Transit Corridor (RTC) Feasibility Study Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM

More information

Clifton Corridor Transit Initiative. Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016

Clifton Corridor Transit Initiative. Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016 Clifton Corridor Transit Initiative Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016 Neighborhood Concerns and Requests Provide a general overview and background of the project

More information

I-4 Beyond the Ultimate. Florida Transportation Builders Association January 18, 2019

I-4 Beyond the Ultimate. Florida Transportation Builders Association January 18, 2019 I-4 Beyond the Ultimate Florida Transportation Builders Association January 18, 2019 FDOT District 5 Improving Mobility & Safety in Central Florida FDOT District 5 is: Designing and building a better Interstate

More information

APPENDIX C1 TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS

APPENDIX C1 TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS APPENDIX C1 TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS February 2018 Highway & Bridge Project PIN 6754.12 Route 13 Connector Road Chemung County February 2018 Appendix

More information

Purpose and Need Report

Purpose and Need Report Purpose and Need Report State Highway (SH) 29 From Southwestern Boulevard to SH 95 Williamson County, Texas (CSJ: 0337-02-045) Prepared by Blanton & Associates, Inc. Date: November, 2015 The environmental

More information

City of Pacific Grove

City of Pacific Grove Regional Study Utilizing Caltrans Intersection Evaluation Section 7: City of Pacific Grove s: FIRST STREET AT CENTRAL AVENUE Transportation Agency for Monterey County Prepared by Transportation Agency

More information

Citizens Committee for Facilities

Citizens Committee for Facilities Citizens Committee for Facilities AGENDA Thursday, December 11, 2014 City Council Chambers 305 3 rd Avenue East -Twin Falls, Idaho 11:30 A.M. AGENDA ITEMS Purpose By 1. Discussion and possible action on

More information

2.0 Development Driveways. Movin Out June 2017

2.0 Development Driveways. Movin Out June 2017 Movin Out June 2017 1.0 Introduction The proposed Movin Out development is a mixed use development in the northeast quadrant of the intersection of West Broadway and Fayette Avenue in the City of Madison.

More information

Major Widening/New Roadway

Major Widening/New Roadway Revised Evaluation s Major Widening/New Roadway This page provides a summary of any revisions made to the draft scores presented at the October th Attributable Funds Committee meeting. The information

More information

I-405 Sepulveda Pass Improvements Project

I-405 Sepulveda Pass Improvements Project I-405 Sepulveda Pass Improvements Project Community Meeting November 15, 2012 1 Wilshire Segment Overview of Wilshire Segment There are a total of 23 bridges being constructed on this project; almost half

More information

Letter of Transmittal

Letter of Transmittal Letter of Transmittal To: Chris Lovell City of Richmond Hill Date: 5/2/6 Job 2582 Re: Richmond Hill-South Bryan County Transportation STudy WE ARE SENDING YOU THE FOLLOWING ITEMS ( attached) ( under separate

More information

CITY OF POWAY MEMORANDUM

CITY OF POWAY MEMORANDUM CITY OF POWAY MEMORANDUM TO: FROM: Traffic Safety Committee Steve Crosby P.E., City Engineer DATE: February 14, 2018 SUBJECT: Espola Road speeding concerns BACKGROUND In 2017, staff received a request

More information

AASHTO Policy on Geometric Design of Highways and Streets

AASHTO Policy on Geometric Design of Highways and Streets AASHTO Policy on Geometric Design of Highways and Streets 2001 Highlights and Major Changes Since the 1994 Edition Jim Mills, P.E. Roadway Design Office 605 Suwannee Street MS-32 Tallahassee, FL 32399-0450

More information

City of Marina. Regional Roundabout Study Utilizing Caltrans Intersection Control Evaluation Section 4: Transportation Agency for Monterey County

City of Marina. Regional Roundabout Study Utilizing Caltrans Intersection Control Evaluation Section 4: Transportation Agency for Monterey County Regional Roundabout Study Utilizing Caltrans Intersection Control Evaluation Section 4: City of Marina Study Intersections: RESERVATION ROAD AT BEACH ROAD RESERVATION ROAD AT DEFOREST ROAD CARDOZA AVENUE

More information

Rocky Mount. Transportation Plan. Transportation Planning Division. Virginia Department of Transportation

Rocky Mount. Transportation Plan. Transportation Planning Division. Virginia Department of Transportation 2020 Transportation Plan Developed by the Transportation Planning Division of the Virginia Department of Transportation in cooperation with the U.S. Department of Transportation, Federal Highway Administration

More information

Traffic Impact Analysis West Street Garden Plots Improvements and DuPage River Park Garden Plots Development Naperville, Illinois

Traffic Impact Analysis West Street Garden Plots Improvements and DuPage River Park Garden Plots Development Naperville, Illinois Traffic Impact Analysis West Street Garden Plots Improvements and DuPage River Park Garden Plots Development Naperville, Illinois Submitted by April 9, 2009 Introduction Kenig, Lindgren, O Hara, Aboona,

More information

Appendix 3 Traffic Technical Memorandum

Appendix 3 Traffic Technical Memorandum Appendix 3 Traffic Technical Memorandum DRAFT TECHNICAL MEMORANDUM Southport Connector Project Traffic Development Comparison of Future Year Model Results Date: September 10, 2015 Project #:11730.030 To:

More information

West Santa Ana Branch Transit Corridor. Informational Briefing Gateway Cities Service Council April 13, 2017

West Santa Ana Branch Transit Corridor. Informational Briefing Gateway Cities Service Council April 13, 2017 West Santa Ana Branch Transit Corridor Informational Briefing Gateway Cities Service Council April 13, 2017 Project Study Area 98 square miles 20 individual cities plus unincorporated LA County 1.2 million

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 2/19/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

To: File From: Adrian Soo, P. Eng. Markham, ON File: Date: August 18, 2015

To: File From: Adrian Soo, P. Eng. Markham, ON File: Date: August 18, 2015 Memo To: From: Adrian Soo, P. Eng. Markham, ON : 165620021 Date: Reference: E.C. Row Expressway, Dominion Boulevard Interchange, Dougall Avenue Interchange, and Howard 1. Review of Interchange Geometry

More information

LACEY CITY COUNCIL MEETING July 09, 2015

LACEY CITY COUNCIL MEETING July 09, 2015 LACEY CITY COUNCIL MEETING July 09, 2015 SUBJECT: 2016-2021 Six-Year Transportation Improvement Plan and Mitigation List RECOMMENDATION: Adopt Resolution approving the proposed 2016-2021 Six- Year Transportation

More information

Dixie Transportation Planning Office

Dixie Transportation Planning Office A project must be given a yes rating on items 1 & 2 in order to be prioritized. Sponsor: St. George City Project: Pioneer Parkway Type: Road Widening and Reconstruction Rev. 9/17/2010 Dixie Transportation

More information

Roundabout Feasibility Study SR 44 at Grand Avenue TABLE OF CONTENTS

Roundabout Feasibility Study SR 44 at Grand Avenue TABLE OF CONTENTS Roundabout Feasibility Study SR 44 at Grand Avenue TABLE OF CONTENTS Introduction and Executive Summary... 1 Existing Conditions... 3 Intersection Volume Conditions... 5 Intersection Operations... 9 Safety

More information

Purple Line Extension, Section 2 Southern California Edison, Phase I

Purple Line Extension, Section 2 Southern California Edison, Phase I Purple Line Extension, Section 2 Southern California Edison, Phase I 1 Agenda Advance Utility Relocation (AUR) Schedule Southern California Edison (SCE) overview Street Impacts Sunday work: 10am-6pm Left

More information

Clifton Corridor Transit Initiative. Briefing to Great Lakes Community February 11, 2016

Clifton Corridor Transit Initiative. Briefing to Great Lakes Community February 11, 2016 Clifton Corridor Transit Initiative Briefing to Great Lakes Community February 11, 2016 Neighborhood Concerns and Requests Provide a general overview and background of the project What are the different

More information

Evaluation Considerations and Geometric Nuances of Reduced Conflict U-Turn Intersections (RCUTs)

Evaluation Considerations and Geometric Nuances of Reduced Conflict U-Turn Intersections (RCUTs) Evaluation Considerations and Geometric Nuances of Reduced Conflict U-Turn Intersections (RCUTs) 26 th Annual Transportation Research Conference Saint Paul RiverCentre May 20, 2015 Presentation Outline

More information

Project Working Group Meeting #5

Project Working Group Meeting #5 September 17, 2013 Project Working Group Meeting #5 1 September 17, 2013 www.i-80will.com Meeting Purpose Project update Discuss Range of Alternatives Discuss next steps 2 September 17, 2013 www.i-80will.com

More information

Purple Line Extension, Section 2 Southern California Edison, Phase I June 7, 2017

Purple Line Extension, Section 2 Southern California Edison, Phase I June 7, 2017 Purple Line Extension, Section 2 Southern California Edison, Phase I June 7, 2017 Agenda Advance Utility Relocation (AUR) Schedule Southern California Edison (SCE) overview Street Impacts Sunday work:

More information

TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION

TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION DECEMBER 24 UPDATED

More information

Broward County Intermodal Center And People Mover. AASHTO Value Engineering Conference Presentation. September 1, 2009 San Diego, CA

Broward County Intermodal Center And People Mover. AASHTO Value Engineering Conference Presentation. September 1, 2009 San Diego, CA Project Development & Environment Study Broward County Intermodal Center And People Mover AASHTO Value Engineering Conference Presentation September 1, 2009 San Diego, CA Background P D & E Study Regional

More information

Memorandum. To: Sue Polka, City Engineer, City of Arden Hills. From: Sean Delmore, PE, PTOE. Date: June 21, 2017

Memorandum. To: Sue Polka, City Engineer, City of Arden Hills. From: Sean Delmore, PE, PTOE. Date: June 21, 2017 Memorandum engineering planning environmental construction 701 Xenia Avenue South Suite 300 Minneapolis, MN 55416 Tel: 763-541-4800 Fax: 763-541-1700 To: Sue Polka, City Engineer, City of Arden Hills From:

More information

Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction

Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction 550 North to 650 North $ 1,750,000 $ 1,582,113 To widen an existing bridge on 1200 West over Box Elder Creek that will

More information

2030 Multimodal Transportation Study

2030 Multimodal Transportation Study 2030 Multimodal Transportation Study City of Jacksonville Planning and Development Department Prepared by Ghyabi & Associates April 29,2010 Introduction Presentation Components 1. Study Basis 2. Study

More information

PUBLIC INFRASTRUCTURE PROJECTS

PUBLIC INFRASTRUCTURE PROJECTS PUBLIC INFRASTRUCTURE PROJECTS FM 664 / OVILLA ROAD WIDENING & IMPROVEMENTS FM 664 / OVILLA ROAD CONNECTS US 287 WITH I-45 (SOURCE: TEXAS DEPARTMENT OF TRANSPORTATION. 2016 FM 664 / OVILLA ROAD WIDENING

More information

STH 60 Northern Reliever Route Feasibility Study Report

STH 60 Northern Reliever Route Feasibility Study Report #233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development

More information

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension Date of Meeting: July 20, 2017 # 6 BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM SUBJECT: ELECTION DISTRICT: CRITICAL ACTION DATE: STAFF CONTACTS: Design Endorsement for Sterling Boulevard Extension

More information

BERKELEY DOWNTOWN AREA PLAN PROGRAM ENVIRONMENTAL IMPACT REPORT TRAFFIC IMPACT ANALYSIS

BERKELEY DOWNTOWN AREA PLAN PROGRAM ENVIRONMENTAL IMPACT REPORT TRAFFIC IMPACT ANALYSIS BERKELEY DOWNTOWN AREA PLAN PROGRAM ENVIRONMENTAL IMPACT REPORT TRAFFIC IMPACT ANALYSIS Prepared for: City of Berkeley Prepared by: REVISED JANUARY 9, 2009 Berkeley Downtown Area Plan Program EIR Traffic

More information

CTA Blue Line Study Area

CTA Blue Line Study Area CTA Blue Line Study Area HISTORY OF THE CTA BLUE LINE / I-290 SYSTEM Blue Line / I-290 infrastructure is 55 years old First integrated transit / highway facility in the U.S. PROJECT STUDY AREA EXISTING

More information

INTERSECTION CONTROL EVALUATION

INTERSECTION CONTROL EVALUATION INTERSECTION CONTROL EVALUATION Trunk Highway 22 and CSAH 21 (E Hill Street/Shanaska Creek Road) Kasota, Le Sueur County, Minnesota November 2018 Trunk Highway 22 and Le Sueur CSAH 21 (E Hill Street/Shanaska

More information

5. HORIZON YEAR TRANSPORTATION MASTER PLAN-COST ESTIMATES

5. HORIZON YEAR TRANSPORTATION MASTER PLAN-COST ESTIMATES 5. HORIZON YEAR TRANSPORTATION MASTER PLAN-COST ESTIMATES 5.1 INTRODUCTION This chapter of the TMP presents an opinion of probable cost estimates for the proposed Horizon Year roadway network improvements

More information

Federal Way Link Extension

Federal Way Link Extension Federal Way Link Extension Draft EIS Summary Route & station alternatives and impacts Link Light Rail System Map Lynnwood Mountlake Terrace Lynnwood Link Extension Shoreline 14th Northgate 40 Northgate

More information

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1 Executive Summary Introduction The Eastside Transit Corridor Phase 2 Project is a vital public transit infrastructure investment that would provide a transit connection to the existing Metro Gold Line

More information

Highway 23 New London Access & Safety Assessment. Public Open House #2 October 3, :00 to 7:00 PM

Highway 23 New London Access & Safety Assessment. Public Open House #2 October 3, :00 to 7:00 PM Public Open House #2 October 3, 2017 5:00 to 7:00 PM Highway 9 OVERVIEW OF ASSESSMENT Assessment Limits Highway 23 from County Road 40 to North Shore Dr Purpose: Identify opportunities to reduce serious

More information

Transportation Improvement Program (TIP) Candidate Project List for Public Review

Transportation Improvement Program (TIP) Candidate Project List for Public Review 2011-2014 Transportation Improvement Program (TIP) Candidate List for Public Review Table 1 Annual Listing Of Federal Aid Obligation For Federal Fiscal Year 2010 North Dakota s Number Transit 410083 Transit

More information

Open House. Highway212. Meetings. Corridor Access Management, Safety & Phasing Plan. 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition

Open House. Highway212. Meetings. Corridor Access Management, Safety & Phasing Plan. 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition Welcome Meetings 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition 6:30 to 8:00 p.m. - Open House Why is Highway 212 Project Important? Important Arterial Route Local Support Highway 212

More information

Reston Transportation Strategy July 9, 2018

Reston Transportation Strategy July 9, 2018 Reston Transportation Strategy July 9, 2018 Background: On February 11, 2014, the Board of Supervisors adopted the Reston Phase I Comprehensive Plan Amendment for the core areas of Reston between Sunset

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate

More information

Harlem Avenue between 63 rd and 65 th

Harlem Avenue between 63 rd and 65 th Harlem Avenue between 63 rd and 65 th Public Meeting #2 March 13, 2018 Summit Park District Welcome to the second Public Meeting for the preliminary engineering and environmental studies of Illinois 43

More information

Committee Report. Transportation Committee. Business Item No

Committee Report. Transportation Committee. Business Item No Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope

More information

East Link Extension. September 16, Bel-Red Conclusion to Final Design Open House Public Involvement Summary

East Link Extension. September 16, Bel-Red Conclusion to Final Design Open House Public Involvement Summary East Link Extension September 16, 2014 Bel-Red Conclusion to Final Design Open House Public Involvement Summary Table of contents 1 Background 2 Overview 2 Notification 3 Open House Overview 4 Comment

More information

STATE LOOP 195 PUBLIC MEETING. Footer Text

STATE LOOP 195 PUBLIC MEETING. Footer Text STATE LOOP 195 PUBLIC MEETING STATE LOOP 195 From FM 755 to 1 mile west of Loma Blanca Rd Public Meeting Agenda Welcome & Introductions Octavio Saenz TxDOT Public Information Officer Technical Overview

More information

ACTION TRANSMITTAL No

ACTION TRANSMITTAL No Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: January 4, 2016 TO: ACTION TRANSMITTAL No. 2016-19 TAC Funding and Programming Committee PREPARED BY: Joe Barbeau, Senior

More information

Community Advisory Committee. October 5, 2015

Community Advisory Committee. October 5, 2015 Community Advisory Committee October 5, 2015 1 Today s Topics Hennepin County Community Works Update Project Ridership Estimates Technical Issue #4:Golden Valley Rd and Plymouth Ave Stations Technical

More information

FY Regional Surface Transportation Program (RSTP) Allocations *

FY Regional Surface Transportation Program (RSTP) Allocations * FY 2015-2020 Regional Surface Transportation Program (RSTP) Allocations * Cost Previous Actual Other Source Total Allocation Jurisdiction/Project Description UPC Estimate Funding Allocation * Projected

More information

Speed measurements were taken at the following three locations on October 13 and 14, 2016 (See Location Map in Exhibit 1):

Speed measurements were taken at the following three locations on October 13 and 14, 2016 (See Location Map in Exhibit 1): 2709 McGraw Drive Bloomington, Illinois 61704 p 309.663.8435 f 309.663.1571 www.f-w.com www.greennavigation.com November 4, 2016 Mr. Kevin Kothe, PE City Engineer City of Bloomington Public Works Department

More information

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237)

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) W&OD TRAIL BRIDGE OVER LEE HIGHWAY A COMPONENT OF THE I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) October 11, 2018 Bill Cuttler, PE

More information

The Design-Builder shall meet local road criteria provided by the local governing agencies.

The Design-Builder shall meet local road criteria provided by the local governing agencies. 11 ROADWAYS 11.1 General The -Builder shall conduct all Work necessary to meet the requirements of roadways. Roadway classifications include mainline, acceleration lanes, deceleration lanes, auxiliary

More information

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007 EAST-WEST CORRIDOR Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007 Presentation Agenda Project Overview / Purpose and Need Highway Component Transit Component

More information

Traffic Impact Analysis. Yelm East Gateway Planned Action

Traffic Impact Analysis. Yelm East Gateway Planned Action Traffic Impact Analysis Planned Action Yelm, Washington November 2014 Traffic Impact Analysis Project Information Project: Prepared for: Evergreen Pacific Fund, LLC Steve Guidinger 2724 Alki Avenue SW,

More information

Appendix C-5: Proposed Refinements Rail Operations and Maintenance Facility (ROMF) Traffic Impact Analysis. Durham-Orange Light Rail Transit Project

Appendix C-5: Proposed Refinements Rail Operations and Maintenance Facility (ROMF) Traffic Impact Analysis. Durham-Orange Light Rail Transit Project Appendix C-5: Proposed Refinements Rail Operations and Maintenance Facility (ROMF) Traffic Impact Analysis Durham-Orange Light Rail Transit Project July 25, 218 ROMF Transportation Impact Analysis Version

More information

August 2, 2010 Public Meeting

August 2, 2010 Public Meeting Public Meeting LYMMO Expansion Alternatives Analysis Study Purpose of study is to provide a fresh look at potential LYMMO expansion, following Federal Transit Administration (FTA) Alternatives Analysis

More information

CITY OF PORT TOWNSEND, WASHINGTON CAPITAL IMPROVEMENT PLAN

CITY OF PORT TOWNSEND, WASHINGTON CAPITAL IMPROVEMENT PLAN Page 1 of 3 CITY OF PORT TOWNSEND, WASHINGTON CAPITAL IMPROVEMENT PLAN The six-year Capital Improvement Plan (CIP) includes capital projects for 2017 2022. This plan includes capital projects that add

More information

APPENDIX B Traffic Analysis

APPENDIX B Traffic Analysis APPENDIX B Traffic Analysis Rim of the World Unified School District Reconfiguration Prepared for: Rim of the World School District 27315 North Bay Road, Blue Jay, CA 92317 Prepared by: 400 Oceangate,

More information

Attachment F Transportation Technical Memorandum

Attachment F Transportation Technical Memorandum Attachment F Transportation Technical Memorandum Sounder Yard and Shops Facility Project Transportation Technical Memorandum March 25, 216 Prepared for: Sound Transit Prepared by: Parsons Brinckerhoff

More information

Restoration of Historic Streetcar Services in Downtown Los Angeles

Restoration of Historic Streetcar Services in Downtown Los Angeles Restoration of Historic Streetcar Services in Downtown Los Angeles Early Scoping Meeting for Alternatives Analysis (AA) May 17, 2011 Introduction Key players Local lead agency: Metro Federal lead agency:

More information

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018 NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3 April 19, 2018 NHHIP OVERVIEW NHHIP divided into 3 Segments: Segment 1: I-45: Beltway 8 to I-610 (9 mi) 45 Segment 2: I-45: I-610 to I-10 (3

More information

TRAFFIC IMPACT ANALYSIS FOR. McDONALD S RESTAURANT IN CARMICAEL Sacramento County, CA. Prepared For:

TRAFFIC IMPACT ANALYSIS FOR. McDONALD S RESTAURANT IN CARMICAEL Sacramento County, CA. Prepared For: TRAFFIC IMPACT ANALYSIS FOR McDONALD S RESTAURANT IN CARMICAEL Sacramento County, CA Prepared For: McDonald s USA, LLC Pacific Sierra Region 2999 Oak Road, Suite 900 Walnut Creek, CA 94597 Prepared By:

More information