Purple Line Extension Section 1 Construction Community Meeting January 17, 2019

Size: px
Start display at page:

Download "Purple Line Extension Section 1 Construction Community Meeting January 17, 2019"

Transcription

1 Purple Line Extension Section 1 Construction Community Meeting January 17,

2 Agenda Section 1 MOW 64 Facility Project Construction Updates: Fossils Project-wide Tunneling Wilshire/Western Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega 2

3 Purple Line Extension Project Alignment 3

4 Sections 1, 2 & 3 Status *Subject to change. The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles 2.59 Miles 2.56 Miles New Stations Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega Wilshire/Rodeo Century City/ Constellation Westwood/UCLA Westwood/VA Hospital Pre-Construction Activities Construction Operations

5 Purple Line Extension Section 1 Alignment 5

6 Purple Line Extension Section 1 Schedule *As of January 2019, subject to change 6

7 Purple Line Maintenance Facility Maintenance Facility Located in the Arts District, north of 6 th St Bridge 590 S Santa Fe Av Current Work Started installing exterior steel building panels Installed windows Finishing interior walls Location 64 Site utilities complete 7

8 Purple Line Maintenance Facility Sealant being installed around windows. Working on electrical pathways in storage area. 8

9 Purple Line Maintenance Facility Finish coat applied to the third floor. 9

10 Project-wide Tunneling One of two tunnels, looking into tail of TBM. 10

11 Fossils The treasure trove grows 11

12 Fossils One of the most unsual digs in the country - CBS 12

13 Wilshire/Western Connection Schedule Schedule *As of January 2019, subject to change 13

14 Wilshire/Western Connection Upcoming Work Construction activities between Wilshire Bl/Manhattan Pl and Wilshire Bl/Western Av behind work zone: Excavation Dewatering Instrumentation Work zone will be in place until the end of January 2019 Location of construction on Wilshire Bl at Western Av, instrumentation and dewatering work will intermittently extend onto Manhattan Pl 14

15 Wilshire/Western Connection Excavation Leveling the ground to create the TBM slab 15

16 Wilshire/La Brea Station 16

17 Wilshire/La Brea Station Box Rendering shows length of the Wilshire/La Brea underground station box on Wilshire Bl from Orange Dr to Detroit St 17

18 Wilshire/La Brea Station Schedule *As of January 2019, subject to change 18

19 Wilshire/La Brea Station Station Construction Shoring for future concourse deck. 19

20 Wilshire/La Brea Station Station Construction Construction the interior walls. 20

21 Wilshire/Fairfax Station 21

22 Wilshire/Fairfax Station Box Rendering shows length of the Wilshire/Fairfax underground station box on Wilshire Bl from west of Fairfax Av to just west of Ogden Dr 22

23 Wilshire/Fairfax Station Schedule *As of January 2019, subject to change 23

24 Wilshire/Fairfax Station Excavation Excavation progress. 24

25 Wilshire/Fairfax Station Concrete and Rebar Winter 2019 Concrete and rebar (steel) work anticipated to start in February 2019 Work will require worksite traffic control on the south side of Wilshire Bl from Orange Grove Av to Ogden Dr Night time work: 7pm 6am Ventilation vans now running at full capacity during nighttime hours for safety of workers and to continue excavation More details to be provided in future construction notices and briefings Concrete work shown from the street level at Wilshire/La Brea. Concrete is being pumped underground from the street level. Similar work will be done at the Wilshire/Fairfax. 25

26 Wilshire/Crescent Heights Tunnel Investigation, January 2019 Investigative drilling in advance of tunneling anticipated at Wilshire Bl/Crescent Heights Bl beginning January 2019 Expected traffic control: Non-rush hour weekday lane reductions on Wilshire Bl Typical work hours, 9am 3:30pm Weekend directional closures of Wilshire Bl and/or Crescent Heights Bl Typical work hours 7am 11pm. Approximate work locations at Wilshire/Crescent Heights. Intermittent sidewalk closures with pedestrian detours 26

27 Upcoming Restoration Work Bus Pads and Water Crossings Beginning February 2019, design-builder will restore bus pads and water crossings at the following locations: Wilshire Bl/Bronson Av Wilshire Bl/Lorraine Bl Wilshire Bl/McCadden Pl Wilshire Bl/Citrus Av Wilshire Bl/Cloverdale Av Wilshire Bl/McCarthy Vista Wilshire Bl/San Vicente Bl The following traffic control will be in place: Wilshire Bl in the work area will be reduced to one lane This lane reduction will be begin on Saturday mornings and will be removed on Monday mornings More details will be provided in future construction notices Example of bus pad on Wilshire Bl

28 Wilshire/La Cienega Station 28

29 Wilshire/La Cienega Station Box Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr 29

30 Wilshire/La Cienega Station *As of January 2019, subject to change 30

31 Wilshire/La Cienega Construction Staging Yards Typical Activities/Equipment: Excavation Steel work Deliveries Hauling Typical hours are 7am 11pm; yard use is permitted 24/7 All noise levels must remain in compliance with MOA and FEIR requirements Excavator in the La Cienega shaft 31

32 Wilshire/Gale Intermittent Daily Gale Closure *Pending City of Beverly Hills Approval Gale Dr will be intermittently closed Monday to Friday, 6am to *10pm, and Saturday 7am to 6pm This closure is a public safety measure due to high volumes of ingress/egress from the property Access to N Gale Dr will be maintained from San Vicente Bl Gale Dr from north of Wilshire Bl 32

33 Wilshire/La Cienega Excavation Moving excavated material to the removal shaft 33

34 Wilshire/La Cienega Upcoming Work Instrumentation Work & Street Maintenance When: Winter 2019 Instrumentation work on Wilshire Bl and La Cienega Bl Intermittent lane reductions on Wilshire Bl, La Cienega Bl, and side streets during off-peak hours (non-rush hour) Street Maintenance, Dewatering Well Maintenance, and Utility Work on Wilshire Bl Intermittent lane reductions on Wilshire Bl and side streets during off-peak hours (non-rush hour) Example of instrumentation drilling 34

35 Staging Yard Mitigation La Cienega Yard Gale Yard Active ventilation fans and fan lines were wrapped with sound blankets 24 steel frame placed around the ventilation system with sound blankets 14 fences with sound blankets placed around the crane (reduced the noise by 3 dba) Applied an acoustic dampening material to the 895 crane engine enclosure Added a muffling panel on the exhaust door and engine compartment door Relocated slew alarm Added a noise barrier rubber mat to the lower engine panels Acoustic plate under mounted on the crane counterweight Adjusted the crane start up schedule, when possible Started closing the gate, when feasible 35

36 621 S Western Ave #100 Los Angeles, CA (213)

37 805 S. La Brea Ave, Los Angeles, CA (323)

38 Congrats Afghani Kabob House! Small Business Saturday Video Ad on Social Media Over 10K Views Online Afghani Kabob House 8560 Wilshire Blvd Beverly Hills, CA (310)

39 Helping local businesses as we build. Update as of 1/4/19

40 BIF Information and Eligibility > Financial assistance to small mom & pop businesses with 25 or fewer employees directly impacted by Metro Rail construction along three project areas > Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements > Grant amount determined by loss of business revenue related to period of construction disruption > To date, 809 grants have been awarded with a total value of more than $18.9 million along all three projects 40

41 BIF Grant Award Update > Purple Line Extension, Section 1 > BIF Grants Awarded: 181 > BIF Grant Amount Awarded: $4,604, > Number of small businesses awarded: 71 > BIF Business Advisor: Brian Lazo > Pacific Coast Regional Small Business Development Corporation (PCR) > Phone:

42 BIF Grant Award Update > Purple Line Extension, Section 2 > BIF Grants Awarded: 29 > BIF Grant Amount Awarded: $780, > Number of small businesses awarded: 19 > BIF Business Advisor: Darrell Smith > Pacific Coast Regional Small Business Development Corporation (PCR) > Phone:

43 Next Community Meeting Beverly Hills Updates on La Cienega and Rodeo Stations Wednesday, February 6, :30pm 8pm Beverly Hills City Hall Municipal Gallery, 2 nd Floor 455 N Rexford Dr Beverly Hills, CA *On-site parking free after 5pm 43

44 Next Community Meeting Section 1 Section 1: Construction Community Meeting Thursday, April 18, :30pm 7:30pm SAG-AFTRA 5757 Wilshire Bl Los Angeles, CA *On-site parking will be validated 44

45 Halfway There Section 1 Section 1 Halfway There Celebrate 50% Completion of the Project Saturday, May 11, am 3pm Lawn West of the Tar Pits Museum 5801 Wilshire Bl Los Angeles, CA

46 Help Us Keep You Safe Purple Line Extension 24/7 Project Hotline purplelineext@metro.net On Metro Transit See Something, Say Something SAFE (7233) City of Beverly Hills PurpleLine@beverlyhills.org Public Works Customer Service: Construction Safety Awareness Program Glyssa Robles, Community Relations Officer roblesgl@metro.net Phone:

47 Stay in Touch 47

Purple Line Extension Section 1 Construction Community Meeting April 19, 2018

Purple Line Extension Section 1 Construction Community Meeting April 19, 2018 Purple Line Extension Section 1 Construction Community Meeting April 19, 2018 1 Agenda Section 1 MOW 64 Facility Project Construction Updates: Wilshire/Western Wilshire/La Brea Wilshire/Fairfax Wilshire/La

More information

Purple Line Extension Section 1 Construction Community Meeting January 18, 2018

Purple Line Extension Section 1 Construction Community Meeting January 18, 2018 Purple Line Extension Section 1 Construction Community Meeting January 18, 2018 1 Agenda Section 1 2017 Accomplishments TBM Art and Naming Contest MOW 64 Facility Project Construction Updates: Wilshire/Western

More information

Purple Line Extension Updates on La Cienega and Rodeo Stations December 13, 2017

Purple Line Extension Updates on La Cienega and Rodeo Stations December 13, 2017 Purple Line Extension Updates on La Cienega and Rodeo Stations December 13, 2017 1 Agenda Project Overview Section 1 Construction Updates Wilshire/La Cienega Station La Cienega Decking Decking Overview

More information

Purple Line Extension Updates on La Cienega and Rodeo Stations January 10, 2018

Purple Line Extension Updates on La Cienega and Rodeo Stations January 10, 2018 Purple Line Extension Updates on La Cienega and Rodeo Stations January 10, 2018 1 Agenda Project Overview Section 1 Construction Updates 2017 Accomplishments Wilshire/La Cienega Station Decking and Jet

More information

Purple Line Extension, Section 2 Southern California Edison, Phase I

Purple Line Extension, Section 2 Southern California Edison, Phase I Purple Line Extension, Section 2 Southern California Edison, Phase I 1 Agenda Advance Utility Relocation (AUR) Schedule Southern California Edison (SCE) overview Street Impacts Sunday work: 10am-6pm Left

More information

Purple Line Extension, Section 2 Southern California Edison, Phase I June 7, 2017

Purple Line Extension, Section 2 Southern California Edison, Phase I June 7, 2017 Purple Line Extension, Section 2 Southern California Edison, Phase I June 7, 2017 Agenda Advance Utility Relocation (AUR) Schedule Southern California Edison (SCE) overview Street Impacts Sunday work:

More information

Purple Line Extension. Rodeo Station AUR MOA October 24, 2017

Purple Line Extension. Rodeo Station AUR MOA October 24, 2017 Purple Line Extension Rodeo Station AUR MOA October 24, 2017 1 Agenda Project Overview Section 2 Pre-Construction Updates Rodeo Drive Station Advance Utility Relocation (AUR) SCE Phase I, underway SCE

More information

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations November 7, 2018

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations November 7, 2018 Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations November 7, 2018 1 Agenda Project Overview Section 1 Construction Updates Wilshire/La Cienega Station Excavation Metro Art Eat Shop

More information

2.4 Build Alternatives

2.4 Build Alternatives Table 2-1. Future Transit Network Changes between No Build and TSM Alternatives Operator Route Group No. Route ID and Description Peak Headway (min) No Build Off-peak Headway (min) Peak Headway (min) TSM

More information

WESTSIDE SUBWAY EXTENSION PROJECT. Construction Traffic Analysis Report

WESTSIDE SUBWAY EXTENSION PROJECT. Construction Traffic Analysis Report PROJECT Construction Traffic Analysis Report August 2011 Table of Contents 1.0 2.0 3.0 4.0 Table of Contents INTRODUCTION... 1-1 1.1 Objectives of the Report... 1-1 1.2 Project Overview... 1-1 1.3 Approach...

More information

Expo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011

Expo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011 Project Status Update Meeting Project Status Update Meeting Holman United Methodist Church January 27, 2011 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor

More information

Westside Subway Extension Final EIS/EIR. January 2011 Community Update Meetings

Westside Subway Extension Final EIS/EIR. January 2011 Community Update Meetings Westside Subway Extension Final EIS/EIR January 2011 Community Update Meetings Purpose of Tonight s Meeting Background information on planning to date Clarify Locally Preferred Alternative (LPA) under

More information

Chapter 2 Alternatives Considered

Chapter 2 Alternatives Considered Beverly Center Area Station Figure 2-54. Santa Monica/San Vicente Station This station would be under San Vicente Boulevard, extending from just south of Gracie Allen Drive to south of Third Street (Figure

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Project Status Update Meeting West End Corridor Segment C Culver City Senior Center May 27, 2010 Phase 1 Project Description 8.6 mile corridor from Downtown Los Angeles

More information

WESTSIDE SUBWAY EXTENSION PROJECT. Updated Off-street Parking Analysis Memorandum

WESTSIDE SUBWAY EXTENSION PROJECT. Updated Off-street Parking Analysis Memorandum WESTSIDE SUBWAY EXTENSION PROJECT Updated Off-street Analysis Memorandum April 2011 Table of Contents 1.0 INTRODUCTION... 1 2.0 DATA SOURCE... 1 3.0 OFF-STREET LAND USE & PARKING ANALYSIS... 2 3.1 Station

More information

Project Scoping Report Appendix B Project Web Site. APPENDIX B Project Web Site

Project Scoping Report Appendix B Project Web Site. APPENDIX B Project Web Site Project Scoping Report Appendix B Project Web Site APPENDIX B Project Web Site WESTSIDE EXTENSION TRANSIT CORRIDOR STUDY February 4, 2008 News and Info of 1 http://metro.net/projects_programs/westside/news_info.htm#topofpage

More information

WESTSIDE SUBWAY EXTENSION. Traffic Analysis Impact Report

WESTSIDE SUBWAY EXTENSION. Traffic Analysis Impact Report Traffic Analysis Impact Report August 2010 Table of Contents Table of Contents 1.0 INTRODUCTION/SUMMARY...1-1 1.1 Existing (Year 2006) Setting... 1-1 1.2 Future (Year 2035) Setting... 1-2 2.0 PROJECT

More information

WESTSIDE SUBWAY EXTENSION. Final Smart Growth Evaluation Report

WESTSIDE SUBWAY EXTENSION. Final Smart Growth Evaluation Report Final Smart Growth Evaluation Report August 2010 Table of Contents Table of Contents 1.0 INTRODUCTION... 1-1 1.1 4Ds... 1-2 1.2 Direct Ridership Model (DRM)... 1-2 2.0 4DS... 2-1 2.1 Inputs... 2-1 2.2

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Laura Cornejo, DEO Regional Planner Regional Operator Metro is LA County s Regional Builder/Funder Rail Bus Service (Metro/Muni/Local)

More information

Crenshaw-Prairie Transit Corridor Study Public Meetings

Crenshaw-Prairie Transit Corridor Study Public Meetings Crenshaw-Prairie Transit Corridor Study Public Meetings Darby Park: Wednesday, February 20, 2008 6:30 8:00 PM US Bank Community Room: Thursday, February 21, 2008 6:30 8:00 PM Nate Holden Performing Arts

More information

Fixing the Line s Canarsie Tunnel. Manhattan CB6 11/5/2018

Fixing the Line s Canarsie Tunnel. Manhattan CB6 11/5/2018 Fixing the Line s Canarsie Tunnel Manhattan CB6 11/5/2018 Interborough Bus Service 80+ buses in the peak hour in the peak direction over the Williamsburg Bridge Projected to carry 17% of riders 1 Bus Priority

More information

WESTSIDE SUBWAY EXTENSION

WESTSIDE SUBWAY EXTENSION Table of Contents Table of Contents 1.0 INTRODUCTION... 1-1 2.0 PROJECT DESCRIPTION... 2-1 2.1 No Build Alternative... 2-1 2.2 TSM Alternative... 2-1 2.3 Build Alternatives... 2-1 2.3.1 Alternative 1 Westwood/UCLA

More information

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles April 2014

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles April 2014 Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles April 2014 Meeting Agenda Phase 2 Construction Update Meeting Meeting Purpose and Format Construction Update Expo Bikeway Update

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate

More information

We re using a giant machine to dig tunnels for trains.

We re using a giant machine to dig tunnels for trains. metro.net/crenshaw We re using a giant machine to dig tunnels for trains. crenshaw/lax transit project Tunnel Boring Machine Fun Facts #CrenshawTBM What is a Tunnel Boring Machine (TBM)? A TBM is like

More information

CITY OF BEVERLY HILLS STAFF REPORT

CITY OF BEVERLY HILLS STAFF REPORT Meeting Date: July 7, 2011 To: From: Subject: CITY OF BEVERLY HILLS STAFF REPORT Honorable Mayor & City Council Pamela Mottice Muller, Director of Emergency Management 405 Closure Attachments: 1. 1-405

More information

Community Meetings June 2018

Community Meetings June 2018 Community Meetings June 2018 1 Welcome and Agenda Thank you for joining us! 6:00 pm Open House 6:30 pm Welcome & Presentation 7:00 pm Q&A 7:15 pm Open House Resumes 8:00 pm Meeting Concludes 2 Purpose

More information

Welcome and Agenda. Thank you for joining us! 6:00 pm Open House. 6:30 pm Welcome & Presentation. 7:00 pm Q&A. 7:15 pm Open House Resumes

Welcome and Agenda. Thank you for joining us! 6:00 pm Open House. 6:30 pm Welcome & Presentation. 7:00 pm Q&A. 7:15 pm Open House Resumes 1 Welcome and Agenda Thank you for joining us! 6:00 pm Open House 6:30 pm Welcome & Presentation 7:00 pm Q&A 7:15 pm Open House Resumes 8:00 pm Meeting Concludes 2 Purpose of this Meeting Introduce project

More information

Click to edit Master text styles

Click to edit Master text styles I-405 Sepulveda Pass Improvements Project Quarterly Community Meeting November 17, 2011 1 Wilshire Segment 2 Quarterly Community Meetings 2012 Month Meeting(s) February 16 May 17 Quarterly Quarterly August

More information

Peninsula Corridor Electrification Update Meeting

Peninsula Corridor Electrification Update Meeting Peninsula Corridor Electrification Update Meeting Brisbane City Council September 6, 2018 Agenda Caltrain System Overview Project Overview Electric Multiple Unit (EMU) Design Brisbane Construction Activities

More information

Table of Contents. Visual and Aesthetic Resources Impact Technical Report Table of Contents

Table of Contents. Visual and Aesthetic Resources Impact Technical Report Table of Contents Table of Contents Table of Contents 1.0 INTRODUCTION... 1-1 2.0 PROJECT DESCRIPTION... 2-1 2.1 No Build Alternative... 2-1 2.2 TSM Alternative... 2-1 2.3 Build Alternatives... 2-1 2.3.1 Alternative 1 Westwood/UCLA

More information

WESTSIDE SUBWAY EXTENSION August 23, 2010 Page 4-61

WESTSIDE SUBWAY EXTENSION August 23, 2010 Page 4-61 4.0 Summary of Construction Methods, Techniques, and Equipment * Figure 4-27: Century City Station to Wilshire/Bundy August 23, 2010 Page 4-61 4.0 Summary of Construction Methods, Techniques, and Equipment

More information

I-405 Sepulveda Pass Improvements Project

I-405 Sepulveda Pass Improvements Project I-405 Sepulveda Pass Improvements Project 26, 2012 Click to edit Master title January style Community Advisory Committee 1 Community Meeting Schedule for 2012 26-Jan CAC, Final Meeting Feb 22-Mar Community

More information

Community Open Houses November 29 December 7, 2017

Community Open Houses November 29 December 7, 2017 Community Open Houses November 29 December 7, 2017 1 Community Open House Agenda 6:00 PM Open House 6:30-7:30 PM Presentation and Q&A 7:30-8:00 PM Open House Resumes after the presentation and Q&A Thank

More information

Expo Light Rail Line. Expo Line Project Westside/Central Metro Service Council November 2014

Expo Light Rail Line. Expo Line Project Westside/Central Metro Service Council November 2014 Expo Line Project Westside/Central Metro Service Council November 2014 2 Expo Line Project Description Phase 2 Expo Line from Culver City to Santa Monica: 6.6 mile corridor 7 new Stations 64,000 Daily

More information

East San Fernando Valley Transit Corridor. TAC Briefing December 4, 2013

East San Fernando Valley Transit Corridor. TAC Briefing December 4, 2013 East San Fernando Valley Transit Corridor TAC Briefing December 4, 2013 Overview Measure R Project Long Range Transportation Plan Reserves $170.1 Million 2018 Revenue Operations Date Coordination with

More information

Westside Subway Extension Draft Environmental Impact Statement/ Environmental Impact Report

Westside Subway Extension Draft Environmental Impact Statement/ Environmental Impact Report Los Angeles County Metropolitan Transportation Authority Westside Subway Extension Draft Environmental Impact Statement/ Environmental Impact Report > Executive Summary September 2010 The U.S. Department

More information

Appendix H - Response to Comments. March 2012 Page H

Appendix H - Response to Comments. March 2012 Page H 593-1 Your support for Alternative 3 (Santa Monica Extension) has been noted. On October 28, 2010, the Metro Board of Directors identified Alternative 2 (Westwood/VA Hospital Extension) as the Locally

More information

Countdown to the Closure Extended 53-Hour Closure of I-405 Freeway Between U.S. 101 and I-10 Planned in Mid-July for Mulholland Bridge Demolition

Countdown to the Closure Extended 53-Hour Closure of I-405 Freeway Between U.S. 101 and I-10 Planned in Mid-July for Mulholland Bridge Demolition Countdown to the Closure Extended 3-Hour Closure of I-40 Freeway Between U.S. 0 and I-0 Planned in Mid-July for Mulholland Bridge Demolition Work Los Angeles, Calif. Plan Ahead, Avoid The Area, Or Stay

More information

I-405 Sepulveda Pass Improvements Project

I-405 Sepulveda Pass Improvements Project I-405 Sepulveda Pass Improvements Project Community Meeting November 15, 2012 1 Wilshire Segment Overview of Wilshire Segment There are a total of 23 bridges being constructed on this project; almost half

More information

Mid-Coast Corridor Transit Project

Mid-Coast Corridor Transit Project San Diego Transportation Development Association Mid Coast Construction Update June 11, 2018 Mid-Coast Corridor Transit Project Mid-Coast Project 11-mile extension of Trolley Blue Line New LRT Infrastructure:

More information

West Santa Ana Branch Transit Corridor. Informational Briefing Gateway Cities Service Council April 13, 2017

West Santa Ana Branch Transit Corridor. Informational Briefing Gateway Cities Service Council April 13, 2017 West Santa Ana Branch Transit Corridor Informational Briefing Gateway Cities Service Council April 13, 2017 Project Study Area 98 square miles 20 individual cities plus unincorporated LA County 1.2 million

More information

Pomona Rotary December 19, 2017

Pomona Rotary December 19, 2017 Pomona Rotary December 19, 2017 Los Angeles County s population will grow by 5.9% to 10.7 million by 2024 During that same period, the San Gabriel Valley will grow by 7.6% to more than 1.5 million; taking

More information

Ottawa LRT Stage 2. McKellar Park Information Session

Ottawa LRT Stage 2. McKellar Park Information Session Ottawa LRT Stage 2 McKellar Park Information Session Stage 2 Background Approved unanimously by Ottawa City Council in July 2015 East to Place d Orléans, west to Bayshore and Baseline, and south to Bowesville

More information

Table of Contents. Comparative Benefits and Costs Analysis Table of Contents

Table of Contents. Comparative Benefits and Costs Analysis Table of Contents Table of Contents Table of Contents 1.0 INTRODUCTION...1-1 2.0 PROJECT DESCRIPTION...2-1 2.1 No Build Alternative... 2-1 2.2 TSM Alternative... 2-1 2.3 Build Alternatives... 2-1 2.3.1 Alternative 1 Westwood/UCLA

More information

4.1 Traffic, Circulation, and Parking

4.1 Traffic, Circulation, and Parking 4.1 Traffic, This section describes the existing transportation and parking conditions within and adjacent to the project area. A traffic report describing the potential impacts of the proposed project

More information

Orange Line Bus Rapid Transit (BRT) Improvements San Fernando Valley Service Council April 3, 2019

Orange Line Bus Rapid Transit (BRT) Improvements San Fernando Valley Service Council April 3, 2019 Orange Line Bus Rapid Transit (BRT) Improvements San Fernando Valley Service Council April 3, 2019 1 Measure M Transit Projects in San Fernando Valley 2 1 2 Measure M Transit Projects Schedule Project

More information

Confederation Line Stage 1 and 2. Our Lady of Fatima Church May 10 th, 2018

Confederation Line Stage 1 and 2. Our Lady of Fatima Church May 10 th, 2018 Confederation Line Stage 1 and 2 Our Lady of Fatima Church May 10 th, 2018 Agenda Confederation Line Stage 1 Overview project, consortium, vehicles Confederation Line Stage 2 Overview project, benefits

More information

Dallas CBD Second Light Rail Alignment (D2)

Dallas CBD Second Light Rail Alignment (D2) Dallas CBD Second Light Rail Alignment (D2) Subway Project Refinement Stakeholder Meeting December 7, 2016 Discussion Items Background Schedule Public/Stakeholder Involvement Comments/Questions from Audience

More information

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237)

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) W&OD TRAIL BRIDGE OVER LEE HIGHWAY A COMPONENT OF THE I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) October 11, 2018 Bill Cuttler, PE

More information

Construction Staging Area 4 Avenue Road

Construction Staging Area 4 Avenue Road REPORT FOR ACTION Construction Staging Area 4 Avenue Road Date: September 27, 2017 To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto and East York District

More information

Staff Contact: Carlos de Melo, Community Development Director, (650)

Staff Contact: Carlos de Melo, Community Development Director, (650) Meeting Date: April 10, 2018 STAFF REPORT Agency: City of Belmont Staff Contact: Carlos de Melo, Community Development Director, (650) 595-7440 cdemelo@belmont.gov Agenda Title: Agenda Action(s): Caltrain

More information

BEVERLY HILLS STAFF REPORT

BEVERLY HILLS STAFF REPORT BEVERLY HILLS STAFF REPORT Meeting Date: June 17, 2014 To: From: Honorable Mayor & City Council Aaron Kunz, Deputy Director of Transportation Martha Eros, Transportation Planner Subject: Request by Councilmembers

More information

Corridor Management Committee. March 7, 2012

Corridor Management Committee. March 7, 2012 Corridor Management Committee March 7, 2012 2 Today s Topics SWLRT Project Office Update Engineering Services Procurement Update Legislative Leadership Tour Annual New Starts Report Update on Proposed

More information

Community Meetings Welcome

Community Meetings Welcome Community Meetings Welcome Thank you for joining us! Community Meetings Agenda 6pm Open House 6:30pm Welcome & Presentation 7pm Q&A 7:15pm Open House Resumes 8pm Meeting Concludes Community Meetings Agenda

More information

NOTICE OF PUBLIC HEARING Los Angeles County Metropolitan Transportation Authority

NOTICE OF PUBLIC HEARING Los Angeles County Metropolitan Transportation Authority NOTICE OF PUBLIC HEARING Los Angeles County Metropolitan Transportation Authority The Los Angeles County Metropolitan Transportation Authority will hold public hearings in February 2011 to receive community

More information

WILSHIRE/RODEO. Westside Subway Extension - DRAFT IMAGES FOR DISCUSSION PURPOSES ONLY. Torti Gallas and Partners, Inc. June SAAG Workshops 2011

WILSHIRE/RODEO. Westside Subway Extension - DRAFT IMAGES FOR DISCUSSION PURPOSES ONLY. Torti Gallas and Partners, Inc. June SAAG Workshops 2011 WILSHIRE/RODEO 1 WILSHIRE/RODEO: BANK OF AMERICA FULL PORTAL (OPTION A) Note for Option A: Beverly Drive: Retains 2 northbound & 2 southbound lanes Loss of 40 Bank of America underground parking spaces

More information

Elected Officials Briefing. North Metro Rail Line Update. February 9, 2017

Elected Officials Briefing. North Metro Rail Line Update. February 9, 2017 Elected Officials Briefing North Metro Rail Line Update February 9, 2017 Dave Genova, RTD General Manager and CEO Openings 2016-2017 Flatiron Flyer, Jan. 3, 2016 University of Colorado A Line, April 22,

More information

Study Area, Related Projects and Travel Markets

Study Area, Related Projects and Travel Markets Study Area, Related Projects and Travel Markets Study area and related projects Travel between Valley and Westside North San Fernando Valley BRT (Alignment TBD) East San Fernando Valley Transit Corridor

More information

Community Meetings. January/February 2019

Community Meetings. January/February 2019 Community Meetings January/February 2019 Purpose of Meeting Present evaluation of Valley- Westside concepts Present initial Westside- LAX concepts Gather community feedback 2 Study Process 3 Overview:

More information

THE WILSHIRE CORRIDOR: RAIL AND ITS ALTERNATIVES. Prepared By: Jacki Murdock Transportation and Environmental Planner

THE WILSHIRE CORRIDOR: RAIL AND ITS ALTERNATIVES. Prepared By: Jacki Murdock Transportation and Environmental Planner THE WILSHIRE CORRIDOR: RAIL AND ITS ALTERNATIVES Prepared By: Jacki Murdock Transportation and Environmental Planner December 13 th, 2012 Overview Characteristics of Wilshire Boulevard Overview of the

More information

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015 Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015 Meeting Agenda Phase 2 Construction Update Meeting Meeting Purpose and Format Construction Update Expo Bikeway

More information

Develop ground transportation improvements to make the Airport a multi-modal regional

Develop ground transportation improvements to make the Airport a multi-modal regional Project Overview TRANSPORTATION IMPROVEMENTS WHAT ARE THE PROJECT GOALS? Transportation transportation hub. Develop ground transportation improvements to make the Airport a multi-modal regional Land Use

More information

Project Scoping Open House Welcome

Project Scoping Open House Welcome Scoping Meeting Project Scoping Open House Welcome Alternatives Analysis (AA) and Draft Environmental Impact Statement/Draft Environmental Impact Report (DEIS/DEIR) Project Purpose Purpose of the Project

More information

I-405 Sepulveda Pass Improvements Project. Community Advisory Committee July 28, 2011

I-405 Sepulveda Pass Improvements Project. Community Advisory Committee July 28, 2011 I-405 Sepulveda Pass Improvements Project Community Advisory Committee July 28, 2011 1 Wilshire Segment 2 Wilshire Segment (National to Waterford) Ramp and Wall Construction at Sepulveda/Wilshire Intersection

More information

CTA Capital Construction Update December 12, 2006

CTA Capital Construction Update December 12, 2006 Red Line/Dan Ryan Blue Line Block 37 Washington Subsurface Station at Block 37 Block 37 Tracks Randolph Red Line Brown Line Howard CTA Capital Construction Update December 12, 2006 1 Capital Construction

More information

Purple Line Light Rail P3 Project

Purple Line Light Rail P3 Project Purple Line Light Rail P3 Project TPB Meeting May 18, 2016 1 Topics General Project Overview The P3 Contract Details on The Successful Proposal 2 Recap of Purple Line P3 Events In November 2013 MTA initiated

More information

Air Quality Memorandum

Air Quality Memorandum ` WESTSIDE SUBWAY EXTENSION PROJECT Air Quality Memorandum December 0 Air Quality Memorandum Table of Contents.0 INTRODUCTION....0 PROJECT DESCRIPTION... 3.0 ENVIRONMENTAL IMPACT/ENVIRONMENTAL CONSEQUENCES...

More information

WAKE TRANSIT PLAN Summer 2018

WAKE TRANSIT PLAN Summer 2018 WAKE TRANSIT PLAN Summer 2018 Planning for growth WAKE COUNTY s population already exceeds ONE MILLION and grows by more than 60 people a day. That s 23,000 people a year or basically another Morrisville.

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS N. TRANSPORTATION AND TRAFFIC

IV. ENVIRONMENTAL IMPACT ANALYSIS N. TRANSPORTATION AND TRAFFIC IV. ENVIRONMENTAL IMPACT ANALYSIS N. TRANSPORTATION AND TRAFFIC The following section summarizes the information provided in the traffic report entitled Traffic Impact Analysis for a Proposed Residential

More information

M79. Between Upper East Side and Upper West Side via 79 Street. Local Crosstown Service. Bus Timetable. Effective June 29, New York City Transit

M79. Between Upper East Side and Upper West Side via 79 Street. Local Crosstown Service. Bus Timetable. Effective June 29, New York City Transit Bus Timetable Effective June 29, 2014 New York City Transit M79 Local Crosstown Service a Between Upper East Side and Upper West Side via 79 Street If you think your bus operator deserves an Apple Award

More information

I-26 Fixed Guideway Alternatives Analysis

I-26 Fixed Guideway Alternatives Analysis I-26 Fixed Guideway Alternatives Analysis Public Meetings: North Charleston, January 25, 2016 Charleston: January 26, 2016 Summerville: January 28, 2016 Agenda I. Project Update II. III. IV. Screen Two

More information

Elected Officials Briefing North Metro Rail Line Update. November 10, 2016

Elected Officials Briefing North Metro Rail Line Update. November 10, 2016 Elected Officials Briefing North Metro Rail Line Update November 10, 2016 Dave Genova, RTD General Manager and CEO Five lines opening in 2016 Flatiron Flyer, Jan. 3 University of Colorado A Line, April

More information

TRANSPORTATION STUDY FOR THE 8899 BEVERLY BOULEVARD PROJECT

TRANSPORTATION STUDY FOR THE 8899 BEVERLY BOULEVARD PROJECT DRAFT TRANSPORTATION STUDY FOR THE 8899 BEVERLY BOULEVARD PROJECT WEST HOLLYWOOD, CALIFORNIA NOVEMBER 2013 PREPARED FOR BEVERLY BOULEVARD ASSOCIATION PREPARED BY DRAFT TRANSPORTATION STUDY FOR THE 8899

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS M. TRANSPORTATION AND TRAFFIC

IV. ENVIRONMENTAL IMPACT ANALYSIS M. TRANSPORTATION AND TRAFFIC IV. ENVIRONMENTAL IMPACT ANALYSIS M. TRANSPORTATION AND TRAFFIC INTRODUCTION This section of the (Draft EIR) addresses the subject of traffic and transportation with respect to the proposed (Project or

More information

McNICOLL BUS GARAGE. Public Open House June 12, 2017 Mary Ward Catholic School

McNICOLL BUS GARAGE. Public Open House June 12, 2017 Mary Ward Catholic School McNICOLL BUS GARAGE Public Open House June 12, 2017 Mary Ward Catholic School THE NEED FOR A NEW BUS GARAGE riders Increased ridership means buses Need for new buses garage And a new bus facility Garages

More information

Expo Light Rail Line. Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015

Expo Light Rail Line. Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015 Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015 Meeting Purpose and Format Meeting Purpose and Format The purpose of tonight s meeting is to: Provide a final update

More information

Maryland Gets to Work

Maryland Gets to Work I-695/Leeds Avenue Interchange Reconstruction Baltimore County Reconstruction of the I-695/Leeds Avenue interchange including replacing the I-695 Inner Loop bridges over Benson Avenue, Amtrak s Northeast

More information

CITY COUNCIL STUDY SESSION UPDATE ON SMART. January 19, 2017 CITY OF SAN RAFAEL

CITY COUNCIL STUDY SESSION UPDATE ON SMART. January 19, 2017 CITY OF SAN RAFAEL CITY COUNCIL STUDY SESSION UPDATE ON SMART January 19, 2017 CITY OF SAN RAFAEL SONOMA MARIN AREA RAIL TRANSIT UPDATE OUTLINE BACKGROUND INITIAL OPERATION SYSTEM (IOS1) CIVIC CENTER AREA LARKSPUR EXTENSION

More information

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily 5.8 TRAFFIC, ACCESS, AND CIRCULATION This section describes existing traffic conditions in the project area; summarizes applicable regulations; and analyzes the potential traffic, access, and circulation

More information

CRRMA BOARD PRESENTATION

CRRMA BOARD PRESENTATION CRRMA BOARD PRESENTATION El Paso Streetcar Construction Status Report Gilbert Gardner August 9, 2017 El Paso Streetcar Infrastructure Construction Status Report AGENDA Progress Summary SBE Progress Construction

More information

Project Status Update January 2017

Project Status Update January 2017 Project Status Update January 2017 1 What is the Purple Line? A new 16 mile east-west light rail line Operates mostly on the surface with 21 stations Connects New Carrollton in Prince George s County and

More information

BART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010

BART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010 BART Silicon Valley Berryessa Extension Project Community Update October 27, 2010 1 Agenda Welcome and Introductions Program and Project Background Project Status Project and Station Details Current and

More information

Doran Street and Broadway/Brazil Grade Separation Project

Doran Street and Broadway/Brazil Grade Separation Project Doran Street and Broadway/Brazil Grade Separation Project Public Outreach Meeting October 4, 2017 Agenda Introductions Project Overview Grade Separation Alternative Traffic Report Update Interim Condition

More information

East San Fernando Valley Transit Corridor. Community Meetings April/May, 2012

East San Fernando Valley Transit Corridor. Community Meetings April/May, 2012 East San Fernando Valley Transit Corridor Community Meetings April/May, 2012 Meeting Format Sign-In/Open-House 6:00 P.M. to 6:30 P.M. Welcome/Presentation 6:30 P.M. to 7 P.M. Open-House 7:00 P.M. to 8:00

More information

Metra seeks your feedback!

Metra seeks your feedback! Metra seeks your feedback! New Ticket - Day Pass Discounts - Off-Peak Times Zone fixes Tell us what you think: www.surveymonkey.com/r/metrafares or by e-mail metrafarestudy@metrarr.com. Attend a public

More information

Crenshaw/LAX Transit Corridor. Transit Coalition Meeting June 26, 2012

Crenshaw/LAX Transit Corridor. Transit Coalition Meeting June 26, 2012 Transit Coalition Meeting June 26, 2012 Measure R Projects 8 ½ mile light rail line from Exposition/Crenshaw Blvds. to Metro Green Line s Aviation/LAX station Six stations with two optional stations carried

More information

CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE

CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE TUESDAY, DECEMBER 5, 2017 1 DISCUSSION TOPICS Update of Infrastructure Action Plan (IAP) o Sidewalk and Roadway projects

More information

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE DOYLE DRIVE DOYLE DRIVE. Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE DOYLE DRIVE DOYLE DRIVE. Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009 DOYLE DRIVE Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009 Presentation Overview Introduction Project Acceleration Construction Contracts Construction Activities Lane and Road

More information

engineering phase and during the procurement of design build contracts.

engineering phase and during the procurement of design build contracts. CONSIDERATION OF ALTERNATIVES Below-grade trench alignment along Aviation Boulevard, adjacent to LAX south runways. miles. MOS-Century would extend from the Metro Exposition Line to the Aviation/ Century

More information

PAPER FOR AREMA 2006 ANNUAL CONFERENCE LOS ANGELES UNION STATION RUN-THROUGH TRACKS UNION STATION TERMINAL IMPROVEMENTS. Paul Mak, PE, SE HDR Inc

PAPER FOR AREMA 2006 ANNUAL CONFERENCE LOS ANGELES UNION STATION RUN-THROUGH TRACKS UNION STATION TERMINAL IMPROVEMENTS. Paul Mak, PE, SE HDR Inc PAPER FOR AREMA 2006 ANNUAL CONFERENCE LOS ANGELES UNION STATION RUN-THROUGH TRACKS UNION STATION TERMINAL IMPROVEMENTS Paul Mak, PE, SE HDR Inc 801 S. Grand Ave. Suite 500, Los Angeles, CA 90017. Tel

More information

CONFEDERATION LINE EAST SEGMENT

CONFEDERATION LINE EAST SEGMENT The O-Train Confederation Line project is the first stage in Ottawa s future light rail network. The 12.5 kilometre electric rail system will replace existing diesel powered buses, providing rapid transit

More information

Rail~Volution 2005 Hal Ryan Johnson, AICP, Bus Rapid Transit Project Manager Utah Transit Authority September 7, 2005

Rail~Volution 2005 Hal Ryan Johnson, AICP, Bus Rapid Transit Project Manager Utah Transit Authority September 7, 2005 Rail~Volution 2005 Hal Ryan Johnson, AICP, Bus Rapid Transit Project Manager Utah Transit Authority September 7, 2005 Public Transit District Utah Transit Authority Linear Geographic Area - 130 miles by

More information

MEMORANDUM CITY OF BEVERLY HILLS

MEMORANDUM CITY OF BEVERLY HILLS MEMORANDUM CITY OF BEVERLY HILLS TO: FROM: City Council and Traffic and Parking Commission Liaison Committee Chad Lynn, Assistant Public Works Director Genevieve Row, Parking Services Manager Judi Tamasi,

More information

Welcome to Inside FasTracks - - your monthly update about FasTracks news, progress and people

Welcome to Inside FasTracks - - your monthly update about FasTracks news, progress and people December 2014 Welcome to Inside FasTracks - - your monthly update about FasTracks news, progress and people FasTracks News I hear the train a- comin RTD s first electric commuter rail cars arrive in Denver

More information

West Broadway Reconstruction/LRT Design. March 19, 2015

West Broadway Reconstruction/LRT Design. March 19, 2015 West Broadway Reconstruction/LRT Design March 19, 2015 1 Meeting Agenda 6:05 6:30 PM Brief presentation What we heard Project overview 6:30 8:00 PM Visit Six Topic Areas Road and LRT design elements Pedestrian

More information

IMPROVEMENT CONCEPTS

IMPROVEMENT CONCEPTS IMPROVEMENT CONCEPTS for the South Novato Transit Hub Study Prepared by: January 11, 2010 DKS Associates With Wilbur Smith Associates IMPROVEMENT CONCEPTS Chapter 1: Introduction 1. INTRODUCTION The strategic

More information

30-Day Look Ahead Summary August 2011

30-Day Look Ahead Summary August 2011 Wilshire Segment 30-Day Look Ahead Summary August 2011 DWP and SCE Utility Relocation Sepulveda reduced to one lane in each direction, Constitution to Ohio, 9pm to 6am Westbound Wilshire reduced to one

More information

PAG Environmental Planning Advisory Committee Sun Link Streetcar Update May 1, 2015

PAG Environmental Planning Advisory Committee Sun Link Streetcar Update May 1, 2015 PAG Environmental Planning Advisory Committee Sun Link Streetcar Update May 1, 2015 Project Facts 4-mile route, 23 stops 8 made in USA modern streetcars All electric and green Voter-approved project Connects

More information

November 6, Agenda

November 6, Agenda Ohio Canal Interceptor Tunnel OCIT-2 Site OCITConstruction Update Public Meeting November 6, 2014 2:00 pm November 6, 2014 Agenda OCIT Project Overview Purpose Noise Basics Noise Mitigation Measures Vibration

More information