1 Meeting Date: April 10, 2018 STAFF REPORT Agency: City of Belmont Staff Contact: Carlos de Melo, Community Development Director, (650) Agenda Title: Agenda Action(s): Caltrain Modernization Program Presentation Recommendation 1) Receive presentation; and 2) Confirm Overhead Contact System (OCS) Electrical Pole Color Selection. Summary The Caltrain Modernization Program (CalMod) includes both electrification and other projects that will upgrade the performance, efficiency, capacity, safety and reliability of Caltrain s service. The electrification project provides the foundation that future CalMod improvements are based on, including full conversion to an electric fleet, platform and station improvements, the extension of service to Downtown San Francisco, and other projects that allow Caltrain to grow and evolve within the Bay Area. The Caltrain right-of-way segment within Belmont is approximately 1.6 miles and the project will include installation of Overhead Contact System (OCS) poles and supportive infrastructure. Tonight s presentation provides an overview of the project, status, and next steps. Staff is also requesting the Council provide feedback on the potential color selection for the OCS poles see Attachment 2 for the currently proposed color choices. Color-matched samples will also be provided at the meeting. Alternative 1. Provide feedback as appropriate to staff. Attachments 1. Caltrain Modernization Program Presentation 2. Overhead Contact System (OCS) Color Samples/Photos Fiscal Impact No Impact/Not Applicable Funding Source Confirmed: Source: Purpose: Public Outreach: Council Statutory/Contractual Requirement Posting of Agenda Staff Council Vision/Priority Other** Citizen Initiated Discretionary Action Other Plan Implementation ** E-Notification of agendas
2 Peninsula Corridor Electrification Update Meeting Belmont City Council April 10, 2018
3 Agenda Caltrain System Overview Project Overview Electric Trains Infrastructure Construction Belmont Activities
4 Caltrain System 32 Stations Gilroy to San Francisco 92 Weekday Trains JBP owns right-of-way from SF to San Jose At-Grade Crossings, viaducts, and bridges Intermodal Connections Bike Commuters
5 Average Daily Ridership Ridership 65,000 60,000 55,000 50,000 45,000 40,000 35,000 30,000 25,000 20,000
6 At Capacity Today Bi-directional commute with riders standing on trains going southbound and northbound
7 Regional Transportation Needs US 101 and Interstate 280 Congested Corridor supports growing economy 75% Caltrain riders commute to work 60% are choice riders
8 Aging Fleet At Retirement Age: 20/29 loco; 73/134 cars
9 Project Description 51 miles Area Project Service San Francisco to San Jose (Tamien Station) Electrification: Overhead Contact System (OCS) Traction Power Facilities Electric Trains (EMUs) 75 percent of fleet Up to 79 mph Service Increase 6 trains / hour / direction More station stops / reduced travel time Restore Atherton & Broadway service Mixed-fleet service (interim period) Continue tenant service ACE, Capital Corridor, Amtrak, Freight
10 Service Benefits Metric Today PCEP Example Baby Bullet Train Retain 5-6 stops 60 minutes 45 minutes Retain SF to SJ 60 minutes Example RWC Station Train stops / peak hour 6 stops 13 stops 3 5 9
11 Key Regional Benefits (2040) Note: 2013 BAC Report, generates $2.5B economic activity and 9,600 jobs
12 Schedule
13 Electric Train
14 Electric Train Input 2016 Capacity Board Decision (bike to seat ratio, onboard bathrooms, upper doors not precluded ) 2017 Design Refinement (exterior design, seats, bike storage, ADA restroom) Over 15,000 comments (online, in-person, surveys, station popups)
15 Electric Train Design
16 Enhancements 2018 Virtual Reality 360 Tour
17 Construction
18 Construction Phasing 51 Miles Corridor 4 Work Segments 3,000 Poles 10 Power Substations Segments 2 & 4 followed by 1 & 3
19 Belmont Field Work Status Status Activity Complete Utility Survey Geotech Investigations Disposal of Soil from Geotech Work Soil Testing Site Surveys Signal Cable Inspections Potholing for Foundations and Signals* Tree Pruning and Removal* Upcoming Work Foundation Installation Pole Installation Wire Installation *Site specific needs may require additional work
20 Belmont Upcoming Work Date Work Activity Expected Duration Summer 2018 Foundation Installation 3-4 months Late 2018 Overhead Wiring Pole and Wire Installation 3-4 months Expected duration indicates first and last day. Number of actual work days will be fewer.
21 Pole Foundation Work DrillTech on track foundation train DrillTech off-track OCS Drill Rig Will take place on and off track
22 Pole Installation On/off-track crane for installation Wide flange & square poles Foundation Rebar Cage Approximately 180 pole spacing
23 Wire Installation Will take place on-track
24 Construction Impacts Daytime & night work from 8pm- 6am Some 24 hour weekend work Crews will utilize acoustical barrier blankets and position lights away from homes Dedicated hotline for construction complaints
25 Public Outreach Subscribe to Weekly Updates Visit calmod.org/construction/ Project and Hotline Construction Outreach Office Community Meetings October 2017 Belmont Meeting Future meeting before pole and wire installation
26 Physical Notices Public Outreach
27 Contact Information Website: calmod.org Phone: Toll Free: Project Office: 2121 S. El Camino Real Suite A San Carlos, CA Monday to Friday, 9am to 5pm
28 PENINSULA CORRIDOR ELECTRIFICATION PROGRAM CITY OF BELMONT Attachment 2 OCS COLOR POLE OPTIONS FOR PASSENGER STATION
29 Belmont Station: Existing Station Furniture, Poles Color and Recommended OCS Pole Color Peninsula Corridor Electrification Program RFP No: 14-PCJPB-P
30 Belmont Station: OCS Pole Color Recommendations Option 1 Option 2 Option Green White Marine Green #23 Whilst every effort has been made to match these colours as closely as possible to US Federal Standard colours, the actual colours printed will depend on the printer and the printing ink used and may be significantly different from that shown on the monitor. In addition, the colours of paints from different suppliers can vary even for US Federal Standard 595C colours and change over time. E-paint.co.uk cannot be held responsible in any way for any variance between these colours and those they are intended to match. Peninsula Corridor Electrification Program RFP No: 14-PCJPB-P
Peninsula Corridor Electrification Update Meeting
Peninsula Corridor Electrification Update Meeting Brisbane City Council September 6, 2018 Agenda Caltrain System Overview Project Overview Electric Multiple Unit (EMU) Design Brisbane Construction Activities
More informationElectric Multiple Unit Procurement Update
Electric Multiple Unit Procurement Update Public Meetings September 2014 Caltrain Today 2 1 Key Facts Diesel commuter rail system SF to SJ area 77 mile corridor, 32 stations 92 trains / weekday Ridership:
More informationCaltrain Modernization EMU Procurement
Caltrain Modernization EMU Procurement Boarding Height CAC Meeting May 20, 2015 Context 2 1 Riders (Boardings) Average Weekday Ridership Since 2004 143% increase 60,000 55,000 50,000 45,000 40,000 35,000
More informationCalMod Local Policy Maker Group (LPMG) Agenda
CalMod Local Policy Maker Group (LPMG) Thursday, September 25, 2014 6:00 PM 7:30 PM SamTrans Offices Bacciocco Auditorium 2 nd Floor 1250 San Carlos Ave., San Carlos Agenda 1. JPB Staff Report 2. Information/Discussion
More informationEMU Procurement Seats/Standees/Bikes/Bathroom
EMU Procurement Seats/Standees/Bikes/Bathroom LPMG May 28, 2015 Purpose Seats / standees / bikes / bathroom balance Develop framework for Draft EMU RFP Feedback on car configuration and range of increased
More informationPeninsula Corridor Electrification Project Cost / Schedule Update
Peninsula Corridor Electrification Project Cost / Schedule Update LPMG Meeting November 20, 2014 Context Caltrain/high-speed rail blended system - Primarily 2 track system - Minimize impacts - Shared system
More informationElectric Multiple Unit Procurement Update
Electric Multiple Unit Procurement Update Board of Directors August 7, 2014 Context* * The proposed project is not yet approved pending environmental clearance. 2 1 Status April 2014 - JPB update on EMU
More informationWhat is the Peninsula Corridor Electrification Project (PCEP)?
What is the Peninsula Corridor Electrification Project (PCEP)? Project Purpose and Need Improve Train Performance Increase Service and Ridership Increase Revenue and Reduce Cost Reduce Environmental Impacts
More informationPeninsula Corridor Electrification Project (PCEP)
Peninsula Corridor Electrification Project (PCEP) Q2 Quarterly Update #13 October 1 December 31, 2017 JPB Board Meeting February 1, 2018 Agenda Item # 8b Electrification - Infrastructure Progression of
More informationKey Findings. February 2009 Caltrain Annual Passenger Counts
Key Findings February 2009 Caltrain Annual Passenger Counts The 2009 annual Caltrain passenger counts, which were conducted starting in late-january and were complete by mid-february, followed the same
More informationPeninsula Corridor Electrification Project (PCEP)
Peninsula Corridor Electrification Project (PCEP) Q4 Quarterly Update #11 April 1 June 30, 2017 JPB Board Meeting August 3, 2017 Agenda Item # 8a Electrification - Infrastructure Design Build Contract
More informationFebruary 2012 Caltrain Annual Passenger Counts Key Findings
February 2012 Caltrain Annual Passenger Counts Key Findings Key Findings February 2012 Caltrain Annual Passenger Counts The 2012 annual Caltrain passenger counts, which were conducted in February 2012,
More informationCalMod Local Policy Maker Group (LPMG) Agenda
CalMod Local Policy Maker Group (LPMG) Thursday, March 27, 2014 6:00 PM 7:30 PM SamTrans Offices Bacciocco Auditorium 2 nd Floor 1250 San Carlos Ave., San Carlos Agenda 1. JPB Staff Report 2. Information/Discussion
More informationSAN FRANCISCO TO SAN JOSE PROJECT SECTION
SAN FRANCISCO TO SAN JOSE PROJECT SECTION Local Policy Maker Group Thursday, February 23, 2017 San Carlos, California INTRODUCTIONS 1 CALIFORNIA HIGH-SPEED RAIL PROGRAM UPDATE Jeff Morales, CEO HIGH-SPEED
More informationMobility Management: Caltrain
Mobility Management: Caltrain Community Relations Committee October 4, 2017 Agenda Item 7 Presentation Outline Operating Statistics Ridership On-time Performance Fleet Reliability Capital Program Review
More informationTable of Contents. Attachment 1 Caltrain Service History Attachment 2 Tables and Graphs Caltrain Annual Passenger Counts 1 of 12 Final
February 2013 Caltrain Annual Passenger Counts Key Finding gs Table of Contents Methodology and Background... 2 Recent Service Changes... 2 Weekday Ridership... 2 Stations... 4 Baby Bullet Stations...
More informationSAN FRANCISCO TO SAN JOSE PROJECT UPDATE
SAN FRANCISCO TO SAN JOSE PROJECT UPDATE San Francisco County Transportation Authority Tuesday, April 25, 2017 Ben Tripousis, Northern California Regional Director HIGH-SPEED RAIL: Connecting California
More informationFebruary 2011 Caltrain Annual Passenger Counts Key Findings
February 2011 Caltrain Annual Passenger Counts Key Findings Key Findings February 2011 Caltrain Annual Passenger Counts The 2011 annual Caltrain passenger counts, which were conducted in February 2011,
More informationCaltrain Late Night Service White Paper
Caltrain Late Night Service White Paper Table of Contents Overview of transit network service & network capacity... 1 Rail Service Overview... 1 Ridership... 2 Existing constraints on extending hours of
More informationCaltrain Business Plan
Caltrain Business Plan FEBRUARY 2019 LPMG February 28, 2019 Caltrain Business Plan Project Update 2 3 What is the Caltrain Business Plan? What Why Addresses the future potential of the railroad over the
More informationTransit in Bay Area Blueprint
Rail~Volution 2010 Click to edit Master title style Transit in Bay Area Blueprint October 21, 2010 0 Bottom Line State-of-Good Repair essential for reliable transit service large funding shortfalls BART
More informationPreliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Millbrae
Preliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Millbrae Dominic Spaethling Regional Program Manager Bethany Williams Public Involvement Manager, HNTB April
More informationSAN FRANCISCO TO SAN JOSE PROJECT SECTION. City of Brisbane Baylands Public Hearing June 7, 2017
SAN FRANCISCO TO SAN JOSE PROJECT SECTION City of Brisbane Baylands Public Hearing June 7, 2017 CALIFORNIA HIGH-SPEED RAIL PROGRAM OVERVIEW 2 HIGH-SPEED RAIL: Connecting California 3 HIGH-SPEED RAIL: It
More informationCaltrain Business Plan. Project Update July 2018 through January 2019
Caltrain Business Plan JANUARY 2019 Project Update July 2018 through January 2019 2 Business Plan Overview Business Plan Overview A Vision for Growth Crafting Scenarios Looking Beyond the Tracks Outreach
More informationCalMod Program EMU Procurement Update. TJPA Board May 14, 2015
CalMod Program EMU Procurement Update TJPA Board May 14, 2015 Key Discussion Items Original Plan Alternative Plan Two Timeframes - 2020 electrified service - Future blended service (with level boarding)
More informationCaltrain Downtown Extension Study Ridership Forecast Summary
Caltrain Downtown Extension Study Ridership Forecast Summary presented to Transbay Joint Powers Authority presented by Cambridge Systematics date: March 12, 2009 Transportation leadership you can trust.
More informationItem No. 10 Town of Atherton
Item No. 10 Town of Atherton CITY COUNCIL STAFF REPORT REGULAR AGENDA TO: FROM: HONORABLE MAYOR AND CITY COUNCIL GEORGE RODERICKS, CITY MANAGER MICHAEL KASHIWAGI COMMUNITY SERVICES DIRECTOR DATE: DECEMBER
More informationUCLA Lake Arrowhead Conference. October 18, 2010
BART Click to Capacity edit Master Overview title style for UCLA Lake Arrowhead Conference October 18, 2010 0 BART Basics 360,000 daily riders 104 miles 43 stations 1.3 billion annual passenger miles 1
More informationModernization: How Caltrain Will Meet Growing Demand
Modernization: How Caltrain Will Meet Growing Demand BY LEAH HARNACK ON JUN 4, 2018 San Francisco is the most densely populated county in California and serves as the region s largest job center, bringing
More informationCaltrain 2017 Annual Passenger Count Key Findings
Caltrain 2017 Annual Passenger Count Key Findings Table of Contents Methodology and Background... 2 Latest Service Operations Changes (through April 2017)... 2 Annual Count Weather Data... 3 Survey Count
More informationCONNECTING AND TRANSFORMING CALIFORNIA
CONNECTING AND TRANSFORMING CALIFORNIA High-Speed Rail Local Policy Maker Group (LPMG) San Carlos, CA January 28, 2016 INTRODUCTIONS 1 STATEWIDE OVERVIEW CONNECTING CALIFORNIA Phase I:» 520 Miles» San
More informationUCLA Lake Arrowhead Conference. October 18, 2010
BART Click to Capacity edit Master Overview title style for UCLA Lake Arrowhead Conference October 18, 2010 0 BART Basics 360,000 daily riders 104 miles 43 stations 1.3 billion annual passenger miles 1
More informationUCLA Lake Arrowhead Conference. October 18, 2010
BART Click to Capacity edit Master Overview title style for UCLA Lake Arrowhead Conference October 18, 2010 0 BART Basics 360,000 daily riders 104 miles 43 stations 1.3 billion annual passenger miles 1
More informationCalMod Program EMU Procurement Update
CalMod Program EMU Procurement Update Board of Directors May 7, 2015 Agenda Item 7a Key Discussion Items Original Plan Alternative Plan Two Timeframes - 2020 electrified service - Future blended service
More informationBicycle Advisory Committee CORRESPONDENCE. March 17, 2016
Bicycle Advisory Committee CORRESPONDENCE March 17, 2016 From: To: Subject: Date: Attachments: RKS05 Caltrain, Bac (@caltrain.com); cacsecretary (@caltrain.com) Really? Overhead rack and luggage car would
More informationAgenda. Open House Presentation Question and Answer Break Out Groups Report Out & Close
Agenda Open House Presentation Question and Answer Break Out Groups Report Out & Close Preliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Sunnyvale Dominic Spaethling
More informationBART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010
BART Silicon Valley Berryessa Extension Project Community Update October 27, 2010 1 Agenda Welcome and Introductions Program and Project Background Project Status Project and Station Details Current and
More information2019 New Transit Service Plan
Agenda Item 7.2 2019 New Transit Service Plan Draft Proposal VTA Board of Directors January 2019 Background: Next Network Plan and Today s Plan Early 2016 Transit Choices report and the ridership-coverage
More informationPomona Rotary December 19, 2017
Pomona Rotary December 19, 2017 Los Angeles County s population will grow by 5.9% to 10.7 million by 2024 During that same period, the San Gabriel Valley will grow by 7.6% to more than 1.5 million; taking
More informationChicago Milwaukee Intercity Passenger Rail Corridor
Chicago Milwaukee Intercity Passenger Rail Corridor Past, Present, and Future Arun Rao, Passenger Rail Manager Wisconsin Department of Transportation Elliot Ramos, Passenger Rail Engineer Illinois Department
More information5. Adjourn BOARD OF DIRECTORS 2019
BOARD OF DIRECTORS 2019 SPECIAL MEETING AGENDA PENINSULA CORRIDOR JOINT POWERS BOARD Bacciocco Auditorium, 2 nd Floor 1250 San Carlos Avenue, San Carlos CA 94070 January 10, 2019 Thursday JEANNIE BRUINS,
More informationWaco Rapid Transit Corridor (RTC) Feasibility Study
Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM
More informationState of California Transit and Intercity Passenger Rail Program. Caltrain Grant Application Overview January 2018
State of California Transit and Intercity Passenger Rail Program Caltrain Grant Application Overview January 2018 TIRCP Program Overview The TIRCP provides grants from the Greenhouse Gas Reduction Fund
More informationA Transit Plan for the Future. Draft Network Plan
A Transit Plan for the Future Draft Network Plan Project Overview and Status Completed Market Analysis and Service Evaluation. Developed Plan Framework and Guiding Principles. Developed a draft Five Year
More informationHigh Speed Rail Conference
High Speed Rail Conference Denver, October 23, 2012 FAST START PROJECT FOR PENINSULA HIGH-SPEED RAIL Kern Jacobson InfraConsult LLC Objective Evaluate incremental approach to expedite high-speed rail to
More informationEast Bay Bus Rapid Transit Project. Downtown Oakland to San Leandro International Blvd to East 14 th St
East Bay Bus Rapid Transit Project 1 AC Transit at a Glance EAST BAY AREA S LARGEST PUBLIC TRANSIT PROVIDER RIDERSHIP Daily (weekday) 178,851* Annual 54,987,132 Paratransit (daily) 1,994 ** * Includes
More informationSan Francisco to San Jose Preliminary Alternatives Analysis
San Francisco to San Jose High-Speed Train Project EIR/EIS San Francisco to San Jose Preliminary Alternatives Analysis April 15, 2010 Page 1 Largest Public Transportation Project in U.S. History 800 miles
More informationExecutive Summary October 2013
Executive Summary October 2013 Table of Contents Introduction... 1 Rider Transit and Regional Connectivity... 1 Plan Overview... 2 Network Overview... 2 Outreach... 3 Rider Performance... 4 Findings...
More informationThe Future of Transportation on the Caltrain Corridor
The Future of Transportation on the Caltrain Corridor 11.30.16 1 2 Today What is happening Vision Recommendations What is costs How to pay for it 3 The Caltrain Corridor is home to the world s innovation
More informationCorridor Management Committee. March 7, 2012
Corridor Management Committee March 7, 2012 2 Today s Topics SWLRT Project Office Update Engineering Services Procurement Update Legislative Leadership Tour Annual New Starts Report Update on Proposed
More informationSF-LA (125 mph) 2: : :32. SF-SJ (110 mph)
California High-Speed Rail Program Management Team To: Fr: Re: 3 January 203 Jeff Morales, CEO, California High-Speed Rail Authority Frank Vacca, Chief Program Manager, California High-Speed Rail Authority
More informationDRAFT Evaluation Scores. Transit
DRAFT Evaluation s The criteria for evaluating applications for new funding commitments are used to measure how well they advance the six goals identified for the MTP. Through transportation: Reduce per
More informationClifton Corridor Transit Initiative. Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016
Clifton Corridor Transit Initiative Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016 Neighborhood Concerns and Requests Provide a general overview and background of the project
More informationAPPENDIX E: BIBLIOGRAPHY
Caltrain Electrification Program EA/EIR APPENDIX E: BIBLIOGRAPHY Technical Reports The following technical reports, listed alphabetically by report title, document the studies conducted for this EA/EIR.
More informationGreen Line opens June 14
Winter 2014 Green Line opens June 14 To-do list for METRO Green Line s grand opening Yours: Study safety tips at www.centralcorridor.org/safety Learn about planned Metro Transit bus service changes on
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Project Status Update Meeting West End Corridor Segment C Culver City Senior Center May 27, 2010 Phase 1 Project Description 8.6 mile corridor from Downtown Los Angeles
More informationMidtown Corridor Alternatives Analysis. Policy Advisory Committee Meeting February 12, 2014
Midtown Corridor Alternatives Analysis Policy Advisory Committee Meeting February 12, 2014 Today s Agenda Introductions Outreach efforts and survey results Other updates since last meeting Evaluation results
More informationVTA Board of Directors: We are forwarding you the following: Comments regarding 2016 Peninsula Corridor SEIR. Member of the Public. Thank you.
From: Board.Secretary Sent: Friday, July 22, 2016 5:07 PM To: VTA Board of Directors Subject: VTA Correspondence: Comments Regarding 2016 Peninsula Corridor SEIR VTA Board of Directors: We are forwarding
More informationRail alignment and benefits (rab) study
Rail alignment and benefits (rab) study previously known as railyard alternatives & i-280 boulevard study June 5, 2018 CONNECTING CALIFORNIA 4,300 lane miles + 115 Airport gates would be needed to create
More informationNOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT (EIR)
BOARD OF DIRECTORS 203 Ken Yeager, Chair Tom Nolan, Vice Chair José Cisneros Malia Cohen Jerry Deal Ash Kalra Arthur L. Lloyd Adrienne Tissier Perry Woodward Michael J. Scanlon Executive Director NOTICE
More informationBalancing the Transportation Needs of a Growing City
Balancing the Transportation Needs of a Growing City FY 2019 and FY 2020 Capital Budget SFMTA Board Meeting Ed Reiskin, Director of Transportation April 3, 2018 1 FY 2019-23 Capital Improvement Program
More informationCREATING CONNECTIONS IN THE CITY OF WATERLOO
CREATING CONNECTIONS IN THE CITY OF WATERLOO GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX METROLINX PRESENTATION TO
More informationMETRO Light Rail Update
American Society of Highway Engineers METRO Light Rail Update Brian Buchanan Director, Design and Construction October 13, 2009 1 High Capacity Transit System 2 20-Mile Light Rail Line 3 Operations Operations
More informationRTD Commuter Rail System APTA Rail Conference June 23, 2015
RTD Commuter Rail System APTA Rail Conference June 23, 2015 RTD Eagle & North Metro Commuter Rail System Today s Presentation Eagle Design, Construction, Systems Commuter Rail Vehicles and CRMF/OCC EC
More informationUtility work, road construction substantially done on Fourth Street
November 2010 Fourth Street in downtown is reopen to vehicle traffic between Minnesota and Broadway streets. Utility relocation and road construction are substantially complete there. Utility work, road
More informationElected Officials Briefing North Metro Rail Line Update. November 10, 2016
Elected Officials Briefing North Metro Rail Line Update November 10, 2016 Dave Genova, RTD General Manager and CEO Five lines opening in 2016 Flatiron Flyer, Jan. 3 University of Colorado A Line, April
More informationThe Capital Grid Project:
The Capital Grid Project: Building Tomorrow s Energy Grid Today Lamond- Riggs Citizens Association October 2, 2017 Agenda Welcome How Safe, Clean, and Affordable Energy is Delivered Our Current System
More informationRail alignment and benefits (rab) study
Rail alignment and benefits (rab) study previously known as railyard alternatives & i-280 boulevard study May 22, 2018 CONNECTING CALIFORNIA 4,300 lane miles + 115 Airport gates would be needed to create
More informationExpo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011
Project Status Update Meeting Project Status Update Meeting Holman United Methodist Church January 27, 2011 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor
More informationExecutive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1
Executive Summary Introduction The Eastside Transit Corridor Phase 2 Project is a vital public transit infrastructure investment that would provide a transit connection to the existing Metro Gold Line
More informationClifton Corridor Transit Initiative. Briefing to Great Lakes Community February 11, 2016
Clifton Corridor Transit Initiative Briefing to Great Lakes Community February 11, 2016 Neighborhood Concerns and Requests Provide a general overview and background of the project What are the different
More informationSOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015
SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment
More informationRail~Volution 2012 R. Gregg Albright
CALIFORNIA HIGH-SPEED RAIL AUTHORITY October 16 th, 2012 Rail~Volution 2012 R. Gregg Albright WHAT IS CALIFORNIA HIGH-SPEED TRAIN PROJECT (CHSTP) and HOW WILL IT BE IMPLEMENTED? 2 CALIFORNIA HIGH SPEED
More informationBART s Transbay Core Capacity Project
BART s Transbay Core Capacity Project Duncan Watry, Principal Planner Bay Area Rapid Transit Oakland, CA dwatry@bart.gov Donald Emerson, Principal Consultant WSP Parsons Brinckerhoff San Francisco, CA
More informationSean P. McBride, Executive Director Kalamazoo Metro Transit. Presentation to Michigan Transportation Planning Association July 13, 2016
Sean P. McBride, Executive Director Kalamazoo Metro Transit Presentation to Michigan Transportation Planning Association July 13, 2016 Metro Transit in Kalamazoo County Square Miles = 132 Urbanized Population:
More informationPEACHTREE CORRIDOR PARTNERSHIP. Current Status & Next Steps
PEACHTREE CORRIDOR PARTNERSHIP Current Status & Next Steps PEACHTREE CORRIDOR PARTNERSHIP Why Peachtree? Why Now? I. THE CONTEXT High Level View of Phasing Discussion Potential Ridership Segment 3 Ease
More informationWest Broadway Reconstruction/LRT Design. March 19, 2015
West Broadway Reconstruction/LRT Design March 19, 2015 1 Meeting Agenda 6:05 6:30 PM Brief presentation What we heard Project overview 6:30 8:00 PM Visit Six Topic Areas Road and LRT design elements Pedestrian
More informationREPORT CARD FOR CALIFORNIA S INFRASTRUCTURE WHAT YOU SHOULD KNOW ABOUT CALIFORNIA S TRANSIT FACILITIES
TRANSIT GRADE: C- WHAT YOU SHOULD KNOW ABOUT TRANSIT FACILITIES California needs robust, flexible and reliable transit systems to reduce peak congestion on our highways, provide options for citizens who
More informationCaltrain / California HSR Blended Operations Analysis Supplemental Analysis Requested by Stakeholders. Service Plan / Operations Considerations Study
Caltrain / California HSR Blended Operations Analysis Supplemental Analysis Requested by Stakeholders Service Plan / Operations Considerations Study Prepared for: Peninsula Corridor Joint Powers Board
More information5. OPPORTUNITIES AND NEXT STEPS
5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours
More informationSan Francisco Transportation Plan
San Francisco Transportation Plan Overview and Findings to Date November 13, 2012 www.sfcta.org/movesmartsf twitter.com/sanfranciscota www.facebook.com/movesmartsf Purpose of the SFTP San Francisco s long-range
More informationMINUTES OF SEPTEMBER 18, P. Bendix, J. Berk, B. Jenkins, A. Levin, A. Sweet, C. Tucker, K. Gardiner
CITIZENS ADVISORY COMMITTEE (CAC) PENINSULA CORRIDOR JOINT POWERS BOARD (JPB) SAN MATEO COUNTY TRANSIT DISTRICT ADMINISTRATIVE BUILDING Bacciocco Auditorium, 2 nd Floor 1250 San Carlos Avenue, San Carlos
More informationFREQUENTLY ASKED QUESTIONS
FREQUENTLY ASKED QUESTIONS 2018 What is the More MARTA Atlanta program? The More MARTA Atlanta program is a collaborative partnership between MARTA and the City of Atlanta to develop and implement a program
More informationCentral City Line Locally Preferred Alternative (LPA) Amendment Public Hearing. July 24, 2014
Central City Line Locally Preferred Alternative (LPA) Amendment Public Hearing July 24, 2014 Project Description The Central City Line is a High Performance Transit project that will extend from Browne
More information2.0 INTRODUCTION. Around the Bay Rail Study LS Transit Systems, Inc. in association with DKS & Nelson\Nygaard
2.0 INTRODUCTION Passenger rail service has continually expanded in California for the past twentyyears. The State s growing network of commuter, intercity and inter-state trains now forms the second largest
More informationRELEASED UNDER THE OFFICIAL INFORMATION ACT 1982
Subject MINISTERIAL BRIEFING NOTE Rapid Transit in Auckland Date 1 November 2017 Briefing number BRI-1133 Contact(s) for telephone discussion (if required) Name Position Direct line Cell phone 1 st contact
More informationFINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit
Sound Transit Long-Range Plan Update Issue Paper S.1: Tacoma Link Integration with Central Link Prepared for: Sound Transit Prepared by: Quade & Douglas, Inc. FINAL March 2005 Foreword This issue paper
More informationNew Haven Hartford Springfield Rail
New Haven Hartford Springfield Rail Opportunities for Economic Growth NHHS Rail Conference, October 25, 2011 NHHSrail.com Tom Maziarz, CT DOT, Bureau of Policy & Planning Thomas.Maziarz@ct.gov New Haven
More informationBroward County Intermodal Center And People Mover. AASHTO Value Engineering Conference Presentation. September 1, 2009 San Diego, CA
Project Development & Environment Study Broward County Intermodal Center And People Mover AASHTO Value Engineering Conference Presentation September 1, 2009 San Diego, CA Background P D & E Study Regional
More informationRestoration of Historic Streetcar Services in Downtown Los Angeles
Restoration of Historic Streetcar Services in Downtown Los Angeles Early Scoping Meeting for Alternatives Analysis (AA) May 17, 2011 Introduction Key players Local lead agency: Metro Federal lead agency:
More informationBackground Information about the Metrobus 29 Lines Study
Background Information about the Metrobus 29 Lines Study Questions Overview of Existing Service Q. Why is the study being conducted? A. The 29 Lines provide an important connection between Annandale and
More informationDenver Metro Association of Realtors
Denver Metro Association of Realtors North Metro Rail Line October 2, 2014 1 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new Park-n-Rides;
More informationProposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1
Proposed FY 2019-2023 Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1 The Capital Improvement Program is: A fiscally constrained, 5-year program of capital projects An implementation
More informationMore than $9 Million coming to Central Valley for transportation
More than $9 Million coming to Central Valley for transportation From free bus service to electric buses Part of overall $97 Million awarded to public transportation projects A total of 152 local public
More informationPurple Line Extension Section 1 Construction Community Meeting January 17, 2019
Purple Line Extension Section 1 Construction Community Meeting January 17, 2019 1 Agenda Section 1 MOW 64 Facility Project Construction Updates: Fossils Project-wide Tunneling Wilshire/Western Wilshire/La
More informationQuarterly Update Meeting
Quarterly Update Meeting December 6, 2011 www.dcstreetcar.com / hotline: (855)413-2954 Agenda I. Welcome II. System Overview III. Project Update IV. Upcoming Meetings V. Stay Connected Provided by DC Streetcar
More informationAugust 6 th, Board of Directors. Kent Riffey Tony Daniels. Chief Engineer Program Director. Project Implementation & Phasing Workshop
Exhibit A Board of Directors Project Implementation & Phasing Workshop August 6 th, 2009 Kent Riffey Tony Daniels Chief Engineer Program Director Today s Workshop Objectives Discussion of Bringing Phase
More informationNortheast Corridor Alternatives Analysis. Public Involvement Round 2 Input on Alternatives for Further Study
Northeast Corridor Alternatives Analysis Public Involvement Round 2 Input on Alternatives for Further Study Feb. 7-9, 2012 Agenda Review project background Progress summary Recommended alternatives for
More informationAPPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY]
APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY] Jackson/Teton Integrated Transportation Plan 2015 Appendix I. Fixed-Guideway Transit Feasibility Jackson/Teton County Integrated Transportation Plan v2
More informationDoran Street and Broadway/Brazil Grade Separation Project
Doran Street and Broadway/Brazil Grade Separation Project Public Outreach Meeting October 4, 2017 Agenda Introductions Project Overview Grade Separation Alternative Traffic Report Update Interim Condition