Crenshaw/LAX Transit Corridor. Transit Coalition Meeting June 26, 2012

Size: px
Start display at page:

Download "Crenshaw/LAX Transit Corridor. Transit Coalition Meeting June 26, 2012"

Transcription

1 Transit Coalition Meeting June 26, 2012

2 Measure R Projects 8 ½ mile light rail line from Exposition/Crenshaw Blvds. to Metro Green Line s Aviation/LAX station Six stations with two optional stations carried as bid options Serves the cities of LA, Inglewood, Hawthorne and El Segundo as well as portions of unincorporated Los Angeles County Federally assisted contract

3 Regional Transit Network

4 Benefits Provides economic development and employment opportunities. Future potential development opportunities within ½ mile of the station. Riders will be able to make easy connections from the Green Line, Exposition Line, and bus lines to the Crenshaw/LAX Line. Creates new regional transportation connections to downtown Los Angeles, West Los Angeles, Norwalk, El Segundo, and the LAX airport area.

5 Project Overview 8.5 mile Light Rail Line Extends from Exposition at Crenshaw Bl to MGL Stations: 6 Stations: Exposition Bl, Martin Luther King Jr., Slauson Ave, West Bl, La Brea Ave, Century Bl 2 Station Bid Options: Vernon, Hindry Southwestern Yard $1.749 Billion (Board approved LOP) 24,400 Project Trips (2035) Federally assisted contract

6 Base Project Vertical Profile

7 History of Corridor View of the Yellow Car Line 5 operating in the medians on Crenshaw Boulevard and Leimert Avenue in the 1950 s, heading south on Leimert Avenue towards Crenshaw Boulevard

8 Green Line to Century Blvd

9 LAX Existing Conditions

10 Century Station Design Concept

11 Century Boulevard to Manchester

12 Southwestern Yard Maintenance Facility > Metro Board on April 28, 2011, approved the preferred maintenance facility location at Arbor Vitae/Bellanca in City of los Angeles

13 Manchester to Centinela

14 I-405 Freeway Crossing Prior Design Concept Current Design Shifts LRT Structure onto BNSF Freight Alignment in Background

15 La Brea Station

16 Harbor Subdivision

17 Centinela to W 59th

18 Cut and Cover Construction

19 59 th to Mark Luther King Bl

20 Crenshaw Boulevard Park Mesa Segment

21 Slauson Station Design Concept

22 Martin Luther King Station Design Concept

23 Martin Luther King Station Design Concept

24 Martin Luther King Station Design Concept

25 MLK Station Construction Staging

26 Martin Luther King Blvd to Exposition Blvd

27 Exposition Station Current Condition

28 Exposition Station - Construction Zone Evaluating constructability at underground stations and for tunneling.

29 Major Milestones Metro Board Approved the FEIS/FEIR September 2011 Metro Board Approved the Crenshaw/LAX Life of Project Budget October 2011 FTA issued the Record of Decision December 2011 Advance Utility Contract Bids received April 18, 2012 (1 st Metro contract with PLA) Contract Award May 31, 2012 Ground breaking held on June 4, 2012

30 Major Milestones (Continued) Main Design-Build Contract 20 Percent Separate Participation Goals for Design and Construction Project labor Agreement /Careers Policy 40 % Goal to economic disadvantaged communities Request for Proposals for Main Design-Build Contract Released June 22, 2012

31 Major Milestones (Continued) Four of five teams pre-qualified to receive a RFP Crenshaw Transit Partners (Fluor, Balfour Beatty, S.A. Healy) Kiewit Skanska Traylor JV Walsh Shea Corridors Constructors URS Dragados Flatiron D-B Contract award anticipated in early Southwestern Yard Design-Build - Invitation for bid released in early Technically Acceptable, Low Bid Procurement Approach

32 Acquisition Background Design-Build Delivery System Statutory Requirements Public Contract Code (PCC) : Sealed Bid or a Sections Negotiated full trade off best value procurement process

33 Method of Procurement Two Step Negotiated Trade-off Best Value Procurement Process Step One : Request for Qualifications (RFQ) - Statement of Qualifications - Pass/Fail evaluation Step Two : Request for Proposal (RFP) - Technical and Price Proposal Evaluation - Best Value Determination

34 Source Selection Process Major Activities Phase 1 - Review Initial Proposals (incl. ATCs) Definition of ATCs Alternative Technical Concepts - Allows for submittal of innovative ideas by proposers - Should reduce cost or provide other efficiencies - Address one or more elements of the Work - Improve aesthetic and functional design of the stations and structures - Provide schedule milestone and cost savings - Lessen community impacts and traffic interruptions - Results in improved operation, maintenance and serviceability

35 Source Selection Process (Cont.) Phase 2 - Oral Presentations and Determination of Best Value source If Metro does not make an award decision in Phase 2: Phase 3 - Establish Competitive Range Phase 4 - Request BAFO and Determine Contract Award

36 Activity Procurement Schedule With Best and Final Offer (BAFO) Date Industry Review Sept. 11 to Jan.12 RFQ Issue Date December 21, 2011 SOQ Due Date March 12, 2012 Approval of Qualified Firms May 17, 2012 RFP Issue Date June 22, 2012 Pre-Proposal Conference July 10, 2012 Proposal Due Date November 6, 2012 Request BAFO January 2013 BAFO Due Date February 2013 Contract Award April 2013

37 Activity Procurement Schedule Without Request for BAFO Date Industry Review September, 2011 RFQ Issue Date December 21, 2011 SOQ Due Date March 12, 2012 Approval of Qualified Firms May 17, 2012 RFP Issue Date June 22, 2012 Pre-Proposal Conference July 10, 2012 Proposal Due Date November 6, 2012 Contract Award February 2013

38 Evaluation Criteria Description Weighing Project Management Approach 35 % Technical Approach 25 % Price Proposal 40 %

39 Station Bid Options Leimert Park (Vernon) Station Carried as bid option for station shell or fully finished station Florence/Hindry Carried as bid option for finished at-grade station Bid options will be evaluated as part of total contract price Staff recommendation on whether option cost fits project budget

40 Optional Vernon (Leimert Park) Station

41 Hindry St Crenshaw/LAX Transit Corridor Optional Florence/Hindry Station

42 Project Information > Please use one of the following to learn more about the project: > Telephone: > > Web site: metro.net/crenshaw

43 Q & A Questions?

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Laura Cornejo, DEO Regional Planner Regional Operator Metro is LA County s Regional Builder/Funder Rail Bus Service (Metro/Muni/Local)

More information

Crenshaw-Prairie Transit Corridor Study Public Meetings

Crenshaw-Prairie Transit Corridor Study Public Meetings Crenshaw-Prairie Transit Corridor Study Public Meetings Darby Park: Wednesday, February 20, 2008 6:30 8:00 PM US Bank Community Room: Thursday, February 21, 2008 6:30 8:00 PM Nate Holden Performing Arts

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate

More information

engineering phase and during the procurement of design build contracts.

engineering phase and during the procurement of design build contracts. CONSIDERATION OF ALTERNATIVES Below-grade trench alignment along Aviation Boulevard, adjacent to LAX south runways. miles. MOS-Century would extend from the Metro Exposition Line to the Aviation/ Century

More information

We re using a giant machine to dig tunnels for trains.

We re using a giant machine to dig tunnels for trains. metro.net/crenshaw We re using a giant machine to dig tunnels for trains. crenshaw/lax transit project Tunnel Boring Machine Fun Facts #CrenshawTBM What is a Tunnel Boring Machine (TBM)? A TBM is like

More information

Metro Green Line to LAX Alternatives Analysis. March 2012

Metro Green Line to LAX Alternatives Analysis. March 2012 Metro Green Line to LAX Alternatives Analysis 1 2 The Crenshaw/LAX Project Foundation for Metro Green Line to LAX 8.5 mile extension Metro Exposition Line (Crenshaw Exposition) to Metro Green Line (Aviation/LAX

More information

Project Scoping Report Appendix B Project Web Site. APPENDIX B Project Web Site

Project Scoping Report Appendix B Project Web Site. APPENDIX B Project Web Site Project Scoping Report Appendix B Project Web Site APPENDIX B Project Web Site WESTSIDE EXTENSION TRANSIT CORRIDOR STUDY February 4, 2008 News and Info of 1 http://metro.net/projects_programs/westside/news_info.htm#topofpage

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item 44 Program Management Project Budget and Schedule Status Project Schedules* Project 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Expo Phase I Orange Line Extension I-405 Sepulveda

More information

RFP No. P3010 New l.i ght Rail Vehicles

RFP No. P3010 New l.i ght Rail Vehicles rr Los Angeles County Metropolitan Transportation Authority RFP No. P3010 New l.i ght Rail Vehicles Source Selection Committee Award Recommendation Light Rail Transit Project Requirements end P30i 0 Delivery

More information

Corridor Management Committee. March 7, 2012

Corridor Management Committee. March 7, 2012 Corridor Management Committee March 7, 2012 2 Today s Topics SWLRT Project Office Update Engineering Services Procurement Update Legislative Leadership Tour Annual New Starts Report Update on Proposed

More information

Purple Line Light Rail P3 Project

Purple Line Light Rail P3 Project Purple Line Light Rail P3 Project TPB Meeting May 18, 2016 1 Topics General Project Overview The P3 Contract Details on The Successful Proposal 2 Recap of Purple Line P3 Events In November 2013 MTA initiated

More information

Transit Project Delivery Status Report. Significant Issues

Transit Project Delivery Status Report. Significant Issues Item 1 Transit Project Delivery Status Report Significant Issues Presented By K.N. Murthy Executive Director Construction Committee 1 I-405 Sepulveda Pass Closure Construction Committee I-405 Sepulveda

More information

LAX Specific Plan Amendment Study. CONCEPT DEVELOPMENT Public Meeting Series #5 August 23 & 26, 2006

LAX Specific Plan Amendment Study. CONCEPT DEVELOPMENT Public Meeting Series #5 August 23 & 26, 2006 LAX Specific Plan Amendment Study CONCEPT DEVELOPMENT Public Meeting Series #5 August 23 & 26, 2006 Agenda Background on public planning process Regional planning update LAWA progress on settlement commitments

More information

I-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results. Public Meeting. Wulf Grote, Director Project Development Rick Pilgrim, Project Manager

I-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results. Public Meeting. Wulf Grote, Director Project Development Rick Pilgrim, Project Manager I-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results Public Meeting Wulf Grote, Director Project Development Rick Pilgrim, Project Manager March 4 & 5, 2008 Today s Agenda Overview of Alternatives

More information

Program. presented by: September 22, 2010

Program. presented by: September 22, 2010 Minnesota s s High Speed Passenger Rail Program presented by: Minnesota Department of Transportation September 22, 2010 Presentation Overview State Rail Plan National High Speed Rail Initiatives Passenger

More information

FasTracks News. RTD s Eagle P3 Transit Project Nears Halfway Mark to Opening Day EP3 will add three commuter rail lines to metro area in 2016

FasTracks News. RTD s Eagle P3 Transit Project Nears Halfway Mark to Opening Day EP3 will add three commuter rail lines to metro area in 2016 July 29, 2013 Welcome to Inside RTD FasTracks a monthly e- update to keep you informed about the progress of the Regional Transportation District's FasTracks program. FasTracks News RTD s Eagle P3 Transit

More information

ACTION: ESTABLISH LIFE-OF-PROJECT BUDGET FOR UP TO 100 NEW COMPO BUSES

ACTION: ESTABLISH LIFE-OF-PROJECT BUDGET FOR UP TO 100 NEW COMPO BUSES QD Metro Los Angeles County Metropolitan Transportation Authority One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro.net oplo OPERATIONS COMMITTEE June 16, 2011 SUBJECT: PURCHASE REPLACEMENT

More information

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1 Executive Summary Introduction The Eastside Transit Corridor Phase 2 Project is a vital public transit infrastructure investment that would provide a transit connection to the existing Metro Gold Line

More information

SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE JULY 17, 2014 PURCHASE OF HYBRID SEDANS APPROVE CONTRACT AWARD ACTION: RECOMMENDATION

SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE JULY 17, 2014 PURCHASE OF HYBRID SEDANS APPROVE CONTRACT AWARD ACTION: RECOMMENDATION One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE JULY 17, 2014 SUBJECT: ACTION: PURCHASE OF HYBRID SEDANS APPROVE CONTRACT AWARD

More information

Board of Directors authorization is required for all goods and services contracts obligating TriMet to pay in excess of $500,000.

Board of Directors authorization is required for all goods and services contracts obligating TriMet to pay in excess of $500,000. Date: April 11, 2012 To: From: Board of Directors Neil McFarlane Subject: RESOLUTION 12-04-30 OF THE TRI-COUNTY METROPOLITAN TRANSPORTATION DISTRICT OF OREGON (TRIMET) AUTHORIZING A CONTRACT WITH SIEMENS

More information

APPROVE VANPOOL VEHICLE SUPPLIER BENCH CONTRACTS

APPROVE VANPOOL VEHICLE SUPPLIER BENCH CONTRACTS One Gateway Plaza Lo s Angeles, CA 90012-2952 2 13.9 2 2.200 0 Tel metro. net 55 REGULAR BOARD MEETING May 23,2013 SUBJECT: ACTION: METRO VANPOOL PROGRAM APPROVE VANPOOL VEHICLE SUPPLIER BENCH CONTRACTS

More information

Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis

Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis Transit Coalition September 26, 2012 2 Study Area Pacific Electric Rightof-Way/West Santa Ana Branch (PEROW/ WSAB) extends

More information

DART Priorities Overview

DART Priorities Overview City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee

More information

One Gateway Plaza Metropolitan Transportation Authority Los Angeles, CA EXECUTE CONTRACT MODIFICATIONS FOR BUS INSPECTION SERVICES

One Gateway Plaza Metropolitan Transportation Authority Los Angeles, CA EXECUTE CONTRACT MODIFICATIONS FOR BUS INSPECTION SERVICES @ Metro Los Angeles County One Gateway Plaza Metropolitan Transportation Authority Los Angeles, CA 90012-2952 I I I REGULAR BOARD MEETING JUNE 28,2012 SUBJECT: BUS INSPECTION SERVICES ACTION: EXECUTE CONTRACT

More information

SUBJECT: CONTRACT C080S, HOIST REPLACEMENT AT BUS MAINTENANCE DIVISIONS 3, 5, 9, 10, AND 18, PETERSON HYDRAULICS AND ROTARY LIFT, A JOINT VENTURE

SUBJECT: CONTRACT C080S, HOIST REPLACEMENT AT BUS MAINTENANCE DIVISIONS 3, 5, 9, 10, AND 18, PETERSON HYDRAULICS AND ROTARY LIFT, A JOINT VENTURE æ Metro Metropolitan Transportation Authority One Gateway Plaza Los Angeles, CA 9 012-2952 3~ 213-922.2000 Tel metro. net OPERATIONS COMMITTEE NOVEMBER 15, 2007 SUBJECT: CONTRACT C080S, HOIST REPLACEMENT

More information

Green Line Extension to Torrance Supplemental Alternatives Analysis. 2. Purpose and Need 2. PURPOSE AND NEED

Green Line Extension to Torrance Supplemental Alternatives Analysis. 2. Purpose and Need 2. PURPOSE AND NEED 2. PURPOSE AND NEED This chapter characterizes the transportation and mobility problems and identifies project goals, objectives, and evaluation criteria to improve these problems for the Green Line Extension

More information

Community Meetings June 2018

Community Meetings June 2018 Community Meetings June 2018 1 Welcome and Agenda Thank you for joining us! 6:00 pm Open House 6:30 pm Welcome & Presentation 7:00 pm Q&A 7:15 pm Open House Resumes 8:00 pm Meeting Concludes 2 Purpose

More information

Welcome and Agenda. Thank you for joining us! 6:00 pm Open House. 6:30 pm Welcome & Presentation. 7:00 pm Q&A. 7:15 pm Open House Resumes

Welcome and Agenda. Thank you for joining us! 6:00 pm Open House. 6:30 pm Welcome & Presentation. 7:00 pm Q&A. 7:15 pm Open House Resumes 1 Welcome and Agenda Thank you for joining us! 6:00 pm Open House 6:30 pm Welcome & Presentation 7:00 pm Q&A 7:15 pm Open House Resumes 8:00 pm Meeting Concludes 2 Purpose of this Meeting Introduce project

More information

METRO Light Rail Update

METRO Light Rail Update American Society of Highway Engineers METRO Light Rail Update Brian Buchanan Director, Design and Construction October 13, 2009 1 High Capacity Transit System 2 20-Mile Light Rail Line 3 Operations Operations

More information

ALTERNATIVE PROJECT DELIVERY

ALTERNATIVE PROJECT DELIVERY ALTERNATIVE PROJECT DELIVERY Varuna Singh SH 288 IN HARRIS COUNTY SH 288 in Harris County SEGMENT 1: 8 New Tolled Direct Connectors at SH 288 and Beltway 8 Existing traffic uses frontage roads today to

More information

West Santa Ana Branch Transit Corridor. Informational Briefing Gateway Cities Service Council April 13, 2017

West Santa Ana Branch Transit Corridor. Informational Briefing Gateway Cities Service Council April 13, 2017 West Santa Ana Branch Transit Corridor Informational Briefing Gateway Cities Service Council April 13, 2017 Project Study Area 98 square miles 20 individual cities plus unincorporated LA County 1.2 million

More information

Metro OPERATIONS COMMITTEE JANUARY 20,201 1 SUBJECT: CNG ENGINE OIL AWARD CONTRACT FOR CNG ENGINE OIL RECOMMENDATION

Metro OPERATIONS COMMITTEE JANUARY 20,201 1 SUBJECT: CNG ENGINE OIL AWARD CONTRACT FOR CNG ENGINE OIL RECOMMENDATION Metro Los Angeles County Metropolitan Transportation Authority One Gateway Plaza Los Angeles, CA 90012-2952 OPERATIONS COMMITTEE JANUARY 20,201 1 SUBJECT: CNG ENGINE OIL ACTION: AWARD CONTRACT FOR CNG

More information

Restoration of Historic Streetcar Services in Downtown Los Angeles

Restoration of Historic Streetcar Services in Downtown Los Angeles Restoration of Historic Streetcar Services in Downtown Los Angeles Alternatives Analysis Community Update Meeting August 2, 2011 Introduction Key players Local lead agency: Metro Federal lead agency: Federal

More information

Transit Access to the National Harbor

Transit Access to the National Harbor Transit Access to the National Harbor December 2014 Table of Contents Executive Summary... 3 Introduction and Project Purpose... 6 Methodology.. 9 Definition of Alternatives..... 9 Similar Project Implementation

More information

Community Meetings. January/February 2019

Community Meetings. January/February 2019 Community Meetings January/February 2019 Purpose of Meeting Present evaluation of Valley- Westside concepts Present initial Westside- LAX concepts Gather community feedback 2 Study Process 3 Overview:

More information

2017 MAX Program. Red & Blue Line Platform Extension. John Rhone Vice President, Capital Design & Construction June 22, 2017

2017 MAX Program. Red & Blue Line Platform Extension. John Rhone Vice President, Capital Design & Construction June 22, 2017 2017 MAX Program Red & Blue Line Platform Extension John Rhone Vice President, Capital Design & Construction June 22, 2017 Project Goals and Objectives Increase capacity: Move more passengers by 2021 with

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION

More information

Appendix E. SHPO Correspondence and Determination. Crenshaw/LAX Transit Corridor Project June 2012 Supplemental Environmental Assessment

Appendix E. SHPO Correspondence and Determination. Crenshaw/LAX Transit Corridor Project June 2012 Supplemental Environmental Assessment Appendix E SHPO Correspondence and Determination Crenshaw/LAX Transit Corridor Project June 2012 Supplemental Environmental Assessment 1. Demolition of the Florence Avenue/I-405 railroad bridge and the

More information

Los Angeles World Airports. LAX Landside Transportation Program

Los Angeles World Airports. LAX Landside Transportation Program Los Angeles World Airports LAX Landside Transportation Program 1 Existing Conditions Not Enough Curb Space Mode Conflicts Limited Roadways 2 3 Problem Today All airport users must rely on an inefficient

More information

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments

More information

Sepulveda Pass Corridor Systems Planning Study

Sepulveda Pass Corridor Systems Planning Study Los Angeles County Metropolitan Transportation Authority Sepulveda Pass Corridor Systems Planning Study Streets and Freeways Subcommittee January 17, 2013 1 Sepulveda Pass Study Corridor Extends for 30

More information

Tempe Streetcar. March 2, 2016

Tempe Streetcar. March 2, 2016 Tempe Streetcar March 2, 2016 Tempe Profile 40 sq. miles, highest density in state University Town, center of region Imposed growth boundaries (density increase) Mixed use growth/intensifying land use

More information

Regional Transit Extension Studies. Hampton Roads Transportation Planning Organization Passenger Rail Task Force Meeting December 17, 2013

Regional Transit Extension Studies. Hampton Roads Transportation Planning Organization Passenger Rail Task Force Meeting December 17, 2013 Regional Transit Extension Studies Hampton Roads Transportation Planning Organization Passenger Rail Task Force Meeting December 17, 2013 Topics Virginia Beach Transit Extension Study (VBTES) Naval Station

More information

MOTION NO. M Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion

MOTION NO. M Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion MOTION NO. M2016-66 Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations Committee 07/07/16

More information

MOTION NO. M Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses

MOTION NO. M Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses MOTION NO. M2018-161 Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee PROPOSED ACTION

More information

Clifton Corridor Transit Initiative. Briefing to Great Lakes Community February 11, 2016

Clifton Corridor Transit Initiative. Briefing to Great Lakes Community February 11, 2016 Clifton Corridor Transit Initiative Briefing to Great Lakes Community February 11, 2016 Neighborhood Concerns and Requests Provide a general overview and background of the project What are the different

More information

Muni Forward: Get On Board! Siemens S200 SF Light Rail Vehicle

Muni Forward: Get On Board! Siemens S200 SF Light Rail Vehicle Muni Forward: Get On Board! Siemens S200 SF Light Rail Vehicle 07 15 2014 SAN FRANCISCO, CALIFORNIA 1 The Right Vehicle to Meet Increasing Demand for Rail Transit in the City Meets Central Subway time-table

More information

Clifton Corridor Transit Initiative. Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016

Clifton Corridor Transit Initiative. Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016 Clifton Corridor Transit Initiative Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016 Neighborhood Concerns and Requests Provide a general overview and background of the project

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.5 DIVISION: Transit Services BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Requesting authorization for the SFMTA, through the Director of Transportation,

More information

Metro Highway Program

Metro Highway Program Metro Highway Program ACEC November 2018 I-5 North HOV and Truck Lanes 14 miles of HOV lanes in both directions 2 miles of truck climbing lanes at the south end 7 bridge modifications at: Gavin Canyon

More information

David Martin, Director of Planning and Community Development. Establishment of LAX FlyAway Stop in Santa Monica

David Martin, Director of Planning and Community Development. Establishment of LAX FlyAway Stop in Santa Monica Information Item Date: January 31, 2014 To: From: Subject: Mayor and City Council David Martin, Director of Planning and Community Development Establishment of LAX FlyAway Stop in Santa Monica Introduction

More information

Peninsula Corridor Electrification Project Cost / Schedule Update

Peninsula Corridor Electrification Project Cost / Schedule Update Peninsula Corridor Electrification Project Cost / Schedule Update LPMG Meeting November 20, 2014 Context Caltrain/high-speed rail blended system - Primarily 2 track system - Minimize impacts - Shared system

More information

Northeast Corridor Alternatives Analysis. Public Involvement Round 2 Input on Alternatives for Further Study

Northeast Corridor Alternatives Analysis. Public Involvement Round 2 Input on Alternatives for Further Study Northeast Corridor Alternatives Analysis Public Involvement Round 2 Input on Alternatives for Further Study Feb. 7-9, 2012 Agenda Review project background Progress summary Recommended alternatives for

More information

APPROVE CONTRACT MODIFICATION AWARD

APPROVE CONTRACT MODIFICATION AWARD 5 One Gateway Plaza Los Angeles, CA 9 012.2952 213.922.2000 Tel metro. net SYSTEM SAFETY AND OPERATIONS COMMITTEE SEPTEMBER 20, 2012 SUBJECT: ACTION: ENGINE REBUILD KITS APPROVE CONTRACT MODIFICATION AWARD

More information

Comprehensive Regional Goods Movement Plan and Implementation Strategy Goods Movement in the 2012 RTP/SCS

Comprehensive Regional Goods Movement Plan and Implementation Strategy Goods Movement in the 2012 RTP/SCS Comprehensive Regional Goods Movement Plan and Implementation Strategy Goods Movement in the 2012 RTP/SCS Annie Nam Southern California Association of Governments September 24, 2012 The Goods Movement

More information

Utility work, road construction substantially done on Fourth Street

Utility work, road construction substantially done on Fourth Street November 2010 Fourth Street in downtown is reopen to vehicle traffic between Minnesota and Broadway streets. Utility relocation and road construction are substantially complete there. Utility work, road

More information

Expo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011

Expo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011 Project Status Update Meeting Project Status Update Meeting Holman United Methodist Church January 27, 2011 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor

More information

STAFF REPORT ACTION REQUIRED

STAFF REPORT ACTION REQUIRED STAFF REPORT ACTION REQUIRED Procurement Authorization Amendment Purchase of 18 Forty Foot Low Floor Clean Diesel City Buses Date: July 29, 215 To: From: TTC Board Chief Executive Officer Summary This

More information

Converting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada

Converting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada Converting BRT to LRT in the Nation s Capital Ottawa, Canada John Manconi City of Ottawa Ottawa, Canada 1 The Challenge *Mackenzie King Bridge Ottawa, AM peak period 2 The Challenge Ottawa s population

More information

MOTION No. M Purchase of Five 40-foot Buses PROPOSED ACTION

MOTION No. M Purchase of Five 40-foot Buses PROPOSED ACTION MOTION No. M2015-71 Purchase of Five 40-foot Buses MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee 08/06/2015 Final Action Bonnie Todd, Executive Director of Operations

More information

METRO CNG Program Phase I Update. Customer Service Committee April 2014

METRO CNG Program Phase I Update. Customer Service Committee April 2014 METRO CNG Program Phase I Update Customer Service Committee April 2014 METRO CNG Program Background Bus purchase Short term solutions Long term plans Bus purchase options 2 METRO CNG Program April 2011

More information

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018 NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3 April 19, 2018 NHHIP OVERVIEW NHHIP divided into 3 Segments: Segment 1: I-45: Beltway 8 to I-610 (9 mi) 45 Segment 2: I-45: I-610 to I-10 (3

More information

Leadership NC. November 8, 2018

Leadership NC. November 8, 2018 v Leadership NC November 8, 2018 Planning for our region s growth The Triangle is one of the fastestgrowing regions in the nation. More than 2 million people are already part of the equation, and the

More information

AWARD CONTRACT FOR LINE BREAKERS

AWARD CONTRACT FOR LINE BREAKERS @ Metro Metropolitan Transportation Authority 45 One Gateway Plaza 213.922.2000 Los Angeles, CA 90012-2952 metro.net OPERATIONS COMMITTEE JULY 16,2009 SUBJECT: LINE BREAKERS ACTION: AWARD CONTRACT FOR

More information

Request for Qualification for Comprehensive Plan Services RFQ#

Request for Qualification for Comprehensive Plan Services RFQ# Request for Qualification for Comprehensive Plan Services RFQ#16-2001-05 City of Texarkana, Texas Planning and Community Development 220 Texas Boulevard Texarkana, TX 75501 Page 2 of 10 RFQ COMPREHENSIVE

More information

Exposition Corridor Transit Project

Exposition Corridor Transit Project Exposition Corridor Transit Project Phase 2 Environmental Planning Community Meeting June 9, 2008 Exposition Corridor Transit Project Phase 2 AGENDA Remaining Grade Crossing Recommendations June 9, 2008

More information

Los Angeles County One Gateway Plaza q.200n Tpl Metropolitan Transportation Authority Los Angeles, CA metro.4 I

Los Angeles County One Gateway Plaza q.200n Tpl Metropolitan Transportation Authority Los Angeles, CA metro.4 I Los Angeles County One Gateway Plaza 213.92q.200n Tpl Metropolitan Transportation Authority Los Angeles, CA 90012-2952 metro.4 I Metro 1 I 48 I I SYSTEM SAFETY AND OPERATIONS COMMITTEE MARCH 15,2012 SUBJECT:

More information

Caltrain Modernization EMU Procurement

Caltrain Modernization EMU Procurement Caltrain Modernization EMU Procurement Boarding Height CAC Meeting May 20, 2015 Context 2 1 Riders (Boardings) Average Weekday Ridership Since 2004 143% increase 60,000 55,000 50,000 45,000 40,000 35,000

More information

Tel metro. net

Tel metro. net One Gateway Plaza Los Angeles, CA 90012-2952 34 213.922.2000 Tel metro. net SYSTEM SAFETY AND OPERATIONS COMMITTEE FEBRUARY 21, 2013 SUBJECT: ACTION: ELECTRIC FAN SYSTEM APPROVE CONTRACT AWARD RECOMMENDATION

More information

Waco Rapid Transit Corridor (RTC) Feasibility Study

Waco Rapid Transit Corridor (RTC) Feasibility Study Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM

More information

Committee Report. Transportation Committee. Business Item No

Committee Report. Transportation Committee. Business Item No Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope

More information

Positive Train Control (PTC)

Positive Train Control (PTC) Positive Train Control (PTC) PTC at a glance FasTracks systems have Positive Train Control (PTC) technology called I-ETMS. This is a complex GPS-and-communications-based system that reduces the risk of

More information

Policy Advisory Committee Meeting November 13, 2013

Policy Advisory Committee Meeting November 13, 2013 Midtown Corridor Alternatives ti Analysis Policy Advisory Committee Meeting November 13, 2013 Today s Agenda Introductions Follow up from September meeting Alternatives review Process update Key evaluation

More information

5. OPPORTUNITIES AND NEXT STEPS

5. OPPORTUNITIES AND NEXT STEPS 5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours

More information

NET TOLL REVENUE REINVESTMENT GRANT PROGRAM. South Bay Service Council

NET TOLL REVENUE REINVESTMENT GRANT PROGRAM. South Bay Service Council NET TOLL REVENUE REINVESTMENT GRANT PROGRAM South Bay Service Council MARCH 13, 2015 NET TOLL REVENUE REINVESTMENT PROGRAM Metro ExpressLanes toll revenues fund: Direct program expenses (Operations & Maintenance)

More information

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation

More information

DRAFT Subject to modifications

DRAFT Subject to modifications TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M DRAFT To: Council Members AGENDA ITEM 7A From: Date: Subject: Staff September 17, 2010 Council Meeting High Speed Rail Update Introduction The

More information

THE WILSHIRE CORRIDOR: RAIL AND ITS ALTERNATIVES. Prepared By: Jacki Murdock Transportation and Environmental Planner

THE WILSHIRE CORRIDOR: RAIL AND ITS ALTERNATIVES. Prepared By: Jacki Murdock Transportation and Environmental Planner THE WILSHIRE CORRIDOR: RAIL AND ITS ALTERNATIVES Prepared By: Jacki Murdock Transportation and Environmental Planner December 13 th, 2012 Overview Characteristics of Wilshire Boulevard Overview of the

More information

Delta Kappa Gamma January 22, 2018

Delta Kappa Gamma January 22, 2018 Delta Kappa Gamma January 22, 2018 Los Angeles County s population will grow by 5.9% to 10.7 million by 2024 During that same period, the San Gabriel Valley will grow by 7.6% to more than 1.5 million;

More information

35 One Gateway Plaza Los Angeles, CA

35 One Gateway Plaza Los Angeles, CA 35 One Gateway Plaza Los Angeles, CA 90012-2952 2 13-9 2 2.2000 Tel metro. net SYSTEM SAFETY AND OPERATIONS COMMITTEE FEBRUARY 21, 2013 SUBJECT: ACTION: TURBOCHARGERS APPROVE CONTRACT AWARDS RECOMMENDATION

More information

VC ACADEMIC CALENDAR. Sun Mon Tue Wed Thu Fri Sat. Sum 10 Wk. & Sum II Final Exams. Cancel Fall 16 wk. & Fall I Non-Pays

VC ACADEMIC CALENDAR. Sun Mon Tue Wed Thu Fri Sat. Sum 10 Wk. & Sum II Final Exams. Cancel Fall 16 wk. & Fall I Non-Pays August 2017 1 SLC Registration Fall 2017 2 3 4 5 Sum 10 Wk. & Sum II Final Exams Commencement (No Ceremony) 6 7 Grades Due Sum 10wk & Sum II 9:00 am 8 Final Fall CC 5:00 pm Pay Day 6:00 pm 9 10 11 Cancel

More information

The Denton County Transportation Authority Thomas M. LeBeau Vice President Rail Development

The Denton County Transportation Authority Thomas M. LeBeau Vice President Rail Development The Denton County Transportation Authority Thomas M. LeBeau Vice President Rail Development Historical Timeline 2001-2004: Governance and Organization House Bill 3323/Chapter 460 Initial Service Plan Developed

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Project Status Update Meeting West End Corridor Segment C Culver City Senior Center May 27, 2010 Phase 1 Project Description 8.6 mile corridor from Downtown Los Angeles

More information

ATTACHMENT [B] PROJECT DESCRIPTION REQUESTED CITY OF LOS ANGELES ACTIONS

ATTACHMENT [B] PROJECT DESCRIPTION REQUESTED CITY OF LOS ANGELES ACTIONS ATTACHMENT [B] PROJECT DESCRIPTION REQUESTED CITY OF LOS ANGELES ACTIONS I. Project Location The Los Angeles International Airport (LAX) Landside Access Modernization Program ( Project ) comprises approximately

More information

3. PRELIMINARY DEFINITION OF ALTERNATIVES

3. PRELIMINARY DEFINITION OF ALTERNATIVES 3. PRELIMINARY DEFINITION OF ALTERNATIVES The purpose of the Preliminary Definition of Alternatives is to introduce the alternatives, including modes and off- and on-airport routes that will be carried

More information

Airport Metro Connector. Technical Refinement Study of Alternatives Final

Airport Metro Connector. Technical Refinement Study of Alternatives Final Airport Metro Connector October 14, 2013 In Association with: Hatch Mott MacDonald Lea+Elliott Fehr & Peers Leighton Terry A. Hayes Associates Inc. Epic Land Solutions Ted Tanaka VCA Engineers, Inc. D

More information

2016 PSRC REGIONAL & KING COUNTYWIDE EASTSIDE FUNDING AWARDS. Eastside Transportation Partnership September 9, 2016

2016 PSRC REGIONAL & KING COUNTYWIDE EASTSIDE FUNDING AWARDS. Eastside Transportation Partnership September 9, 2016 2016 PSRC REGIONAL & KING COUNTYWIDE EASTSIDE FUNDING AWARDS Eastside Transportation Partnership September 9, 2016 1 2 PSRC 2016 Project Selection Process 2018-2020 Estimated FHWA Funds Available: (Summary)

More information

Greater Cleveland Regional Transit Authority

Greater Cleveland Regional Transit Authority Greater Cleveland Regional Transit Authority Summary of Proposed Award Vanpool Program Presented to: Operations Committee August 2, 2016 What is a Vanpool? A vanpool is a group of people (larger than 5)

More information

APTA 2CA0le1 nd 7 Ar

APTA 2CA0le1 nd 7 Ar APTA Calendar 2017 APTA conference schedule 2017 Cover photo: SORTA/Metro/CB Connector, Cincinnati, OH Photographer: Ronny Salerno apta.com 2017 Conference Schedule APTA S VISION STATEMENT February 11-14

More information

Help shape your community investment in Wake Transit. Fiscal Year 2019 Draft Work Plan Summary

Help shape your community investment in Wake Transit. Fiscal Year 2019 Draft Work Plan Summary Help shape your community investment in Wake Transit Fiscal Year 2019 Draft Work Plan Summary Wake County, growth and transit The Triangle is one of the fastest-growing regions in the nation. Wake County

More information

Peninsula Corridor Electrification Project (PCEP)

Peninsula Corridor Electrification Project (PCEP) Peninsula Corridor Electrification Project (PCEP) Q4 Quarterly Update #11 April 1 June 30, 2017 JPB Board Meeting August 3, 2017 Agenda Item # 8a Electrification - Infrastructure Design Build Contract

More information

MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Recommend to Board. Final Action

MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Recommend to Board. Final Action MOTION NO. M2018-160 Purchase of Thirteen 42-foot Double Deck Expansion Buses MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations Committee PROPOSED ACTION 12/06/2018 12/20/2018 Recommend to Final

More information

Green Line LRT: Beltline Recommendation Frequently Asked Questions

Green Line LRT: Beltline Recommendation Frequently Asked Questions Green Line LRT: Beltline Recommendation Frequently Asked Questions June 2017 Quick Facts Administration has evaluated several alignment options that would connect the Green Line in the Beltline to Victoria

More information

Sepulveda Pass Corridor Systems Planning Study Update

Sepulveda Pass Corridor Systems Planning Study Update Los Angeles County Metropolitan Transportation Authority Sepulveda Pass Corridor Systems Planning Study Update June 20, 2012 Measure R Transit Corridors One of 12 Measure R Transit Corridors approved by

More information

Targeted Group Business and Veteran- Owned Small Business Programs

Targeted Group Business and Veteran- Owned Small Business Programs This document is made available electronically by the Minnesota Legislative Reference Library as part of an ongoing digital archiving project. http://www.leg.state.mn.us/lrl/lrl.asp Targeted Group Business

More information

Washington Metropolitan Area Transit Authority

Washington Metropolitan Area Transit Authority Washington Metropolitan Area Transit Authority BUS PROCUREMENT PROGRAM REPROGRAMMING OF FUNDING P D E C PLANNING DEVELOPMENT ENGINEERING CONSTRUCTION Presented to the Board of Directors: Budget Committee

More information

2/1/2018. February 1, Item #1 CITIZENS PARTICIPATION

2/1/2018. February 1, Item #1 CITIZENS PARTICIPATION February 1, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments

More information

Draft Results and Open House

Draft Results and Open House Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi

More information

Project Scoping Open House Welcome

Project Scoping Open House Welcome Scoping Meeting Project Scoping Open House Welcome Alternatives Analysis (AA) and Draft Environmental Impact Statement/Draft Environmental Impact Report (DEIS/DEIR) Project Purpose Purpose of the Project

More information

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report ORANGE COUNTY TRANSPORTATION AUTHORITY Agreement to Purchase Compressed Natural Gas Articulated Staff Report November 8, 2012 To: From: Subject: Transit Committee Will Kempton, Chief Executive Officer

More information