Purple Line Extension Updates on La Cienega and Rodeo Stations January 10, 2018
|
|
- Andrew Cooper
- 5 years ago
- Views:
Transcription
1 Purple Line Extension Updates on La Cienega and Rodeo Stations January 10,
2 Agenda Project Overview Section 1 Construction Updates 2017 Accomplishments Wilshire/La Cienega Station Decking and Jet Grouting Safety Section 2 Pre-Construction Updates 2017 Accomplishments Rodeo Drive Station Geotechnical Borings & Potholing Advance Utility Relocation Demo of former Ace Gallery MOA for Design-Build N. Canon Traffic Study Aesthetic Study Business Interruption Fund Questions & Answers 2
3 Purple Line Extension Project Alignment 3
4 Sections 1, 2 & 3 Status *Subject to change. The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles 2.59 Miles 2.59 Miles New Stations Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega Wilshire/Rodeo Century City/ Constellation Westwood/UCLA Westwood/VA Hospital Pre-Construction Activities Construction Operations
5 2017 Accomplishments Section 1 Completed Wilshire/La Cienega decking weekend closures 5 weekends ahead of schedule Installed 400+ soldier piles for the Wilshire/La Cienega station Completed installation of piles and completed decking weekend closures five weeks ahead of schedule at Wilshire/Fairfax Approximately 40% complete with the excavation for the Wilshire/Fairfax station Approximately 60,000 cubic yards of material have been removed at Wilshire/Fairfax Completed the excavation at the Wilshire/La Brea station, removing approximately 225,000 cubic yards of material Concrete work and preparation for tunneling is underway Started the work to connect to the existing Purple Line at Wilshire/Western Performed jet grouting at 13 locations along the 4-mile construction alignment from
6 Section 1 Wilshire/La Cienega Station 6
7 Wilshire/La Cienega Station Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr 7
8 Wilshire/La Cienega Station *As of January 2018, subject to change 8
9 Wilshire/La Cienega Station Decking Construction Laying and welding deck beams across Wilshire Bl and Gale Dr 9
10 Wilshire/La Cienega Station Weekend Closures Schedule Wilshire Bl/La Cienega Bl Weekend Closures Schedule Approximately 17 weekend closures Scheduled in 3 phases Started September 8, 2017 Phase 1: Wilshire Bl between La Cienega Bl and San Vicente Bl COMPLETE Phase 2: Wilshire/La Cienega intersection COMPLETE 4 weekends Phase 3: Wilshire Bl between La Cienega Bl and San Vicente Bl COMPLETE 11 weekends Started November 3rd 10
11 Wilshire/La Cienega Upcoming Work, June 2018 Work zone removal on Wilshire, between La Cienega and San Vicente, is anticipated in June 2018 Work zone on the north side of Wilshire (concrete barriers, fencing and noise mitigation blankets) will be substantially removed Wilshire: Three Lanes in each direction! Left turn movements on Wilshire are anticipated to return at Hamilton and Gale Location of the current work zone on Wilshire Bl between La Cienega Bl and San Vicente Bl 11
12 Wilshire/La Cienega Upcoming Work, June 2018 Work zone set-up for jet grouting construction on Wilshire between Carson and La Cienega anticipated in June 2018 Center work zone will be installed (with concrete barriers, fencing and noise mitigation blankets) for 8-12 weeks Work zone: Center lanes of Wilshire, with two lanes of traffic in each direction Left turn and thru movements will be restricted from Stanley and Le Doux at Wilshire Work hours: 7am-8pm for drilling activities 8pm -10pm for support activities Intermittent off-peak hour weekday closures and weekend directional closures are anticipated Bus stops will be temporarily relocated and parking will be temporarily restricted on Wilshire between Carson and La Cienega Location of the new work zone that will be installed on Wilshire Bl between Carson Rd and La Cienega Bl 12
13 Wilshire/La Cienega Jet grouting example Example of jet grouting from San Vicente Bl and Wilshire Bl 13
14 Additional Parking Wilshire and La Cienega alignment Repainting of existing red curbs into future grey curbs for added parking. Construction mitigation paid for by Metro. Locations of Re-Painting: Hamilton Dr Gregory Wy Gale Dr Tower Dr N
15 Help Us Keep You Safe Purple Line Extension 24/7 Project Hotline purplelineext@metro.net On Metro Transit See Something, Say Something SAFE (7233) City of Beverly Hills PurpleLine@beverlyhills.org Public Works Customer Service: (310) Construction Safety Awareness Program Glyssa Alcazar, Community Relations Officer alcazarg@metro.net Phone:
16 Section 2 Wilshire/Rodeo Station 16
17 2017 Accomplishments Section 2 Notice To Proceed to Design Builder (TPOG) Advance Utility Relocation ongoing in Century City Advance Utility Relocation Started in Beverly Hills Example of advance utility relocation in Century City on Constellation Bl and Avenue of the Stars 17
18 Purple Line Extension Section 2 Agenda 2017 Accomplishments Rodeo Drive Station Geotechnical Borings & Potholing Advance Utility Relocation Demo of former Ace Gallery MOA for Design-Build N. Canon Traffic Study Aesthetic Study 18
19 Purple Line Extension Section 2 Alignment 19
20 2017 Accomplishments Section 2 Notice To Proceed to Design Builder (TPOG) Advance Utility Relocation ongoing in Century City Advance Utility Relocation Started in Beverly Hills Example of advance utility relocation in Century City on Constellation Bl and Avenue of the Stars 20
21 Wilshire/Rodeo Station Rendering shows length of the underground station box on Wilshire Bl from Canon Dr to Beverly Dr 21
22 Geotechnical Site Investigation Purpose of Investigation Gather additional soil information to validate existing data and characterize subsurface conditions for the design and construction of stations, tunnels, and cross passages Cross passages connect the two tunnels and house mechanical and electrical equipment along the alignment Install groundwater monitoring wells and gas probes to be used for monitoring prior to and during construction 8
23 Southern California Edison Red=power
24 Advanced Utility Relocation Wilshire/Rodeo Station Start Dates: SCE Phase 2: January 2018 SCG: February 2018 AT&T: February 2018 Rendering of AUR work 24
25 SCE Phase 2 Cable Pulling: 3 weeks, January 2018 Utility Interruption: Two 2-hour outages per circuit Anticipated January separate circuits impacted Direct engagement to impacted businesses and one residential unit Same traffic plans as SCE Phase 1 25
26 SCE Advanced Utility Relocation Monitoring and Adjustment Sunday 10am-6pm, Monday-Friday 9am-4pm Sun Wed: Wilshire with turn restrictions Thurs-Fri: Reeves or Wilshire with no turn restrictions City of Beverly Hills/Metro traffic engineers will monitor traffic Local Access Only signs Signal and crosswalk timing adjustments Traffic Control Officers (TCO) Beverly Hills Police Department support Any other adjustments as needed to work plans, traffic plans or detours Monitor bus stops and zones 26
27 SCG and AT&T Utility Relocation Combined Traffic Control Starting February 2018 SCG and AT&T will work simultaneously within work zone Will reduce overall duration of work Work is scheduled from February through August 2018 Stage 1-3 will look similar to SCE Work is set up in morning and taken down each night Will accommodate awards season Stage 4-8 will take place behind K-rail K-rail to remain 24/7 and work will take place behind it during approved working hours Set up will take place after awards season (March 5, 2018) 27
28 SCG and AT&T Utility Relocation Stage 1: 16 days / Sun.: 10am-6pm, Mon.-Wed.: 9am-4pm 28
29 SCG and AT&T Utility Relocation Stage 4-7 Traffic Proposal Medians and parking removed from work zone Buses relocated outside of work zone-metro is with the City of Beverly Hills to determine the new locations. Wilshire Bl two lanes each direction from west of Beverly to east of Canon Example on Wilshire Bl 29
30 SCG and AT&T Utility Relocation Stage 4: 34 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm K-Rail 24/7 30
31 Bus Stops Existing Bus Stops near Wilshire/Rodeo Station 31
32 West of Beverly Dr 20/720 WB/ EB Wilshire between Camden Dr and Rodeo Dr Bus Stops Proposed Bus Stops Relocations near Wilshire/Rodeo Station Bus Stop Relocations: East of Beverly Dr 20/720 WB / EB Wilshire between Rexford Dr and Crescent Dr
33 Demolition of 9430 Wilshire Bl Former Ace Gallery, future Construction Staging Yard 33
34 Demolition of 9430 Wilshire Bl Former Ace Gallery *Pending City Council Approval Site Address: 9430 Wilshire Blvd 2-Story Building on the corner of Wilshire Bl and Reeves Dr Schedule Anticipated Start in April 2018 Estimated Duration of Demolition Activities: 5-7 weeks Traffic Impacts Temporary Lane Closure along Wilshire Bl (approximately 2 weeks) Temporary Turn Restriction on Reeves Dr Sidewalk/Partial Lane Closure along Reeves Dr (duration of demolition) Pedestrian protection to be installed 34
35 Demolition of 9430 Wilshire Bl Former Ace Gallery Dust Mitigation Water used to spray demo area Noise Mitigation Equipment installed with low-noise mufflers and noise blankets on fencing around work area Protection of the Park Fencing/barrier around work area including noise control measures Example of noise mitigation blanket 35
36 Noise Barrier Wall Former Ace Gallery Construction of sound wall Work Hours: 7am 5pm Sound Wall: 20 feet 36
37 Purpose of Memorandum of Agreement (MOA) Establish conditions and procedures for construction Minimize impacts to the Community Establish compliance monitor and enforcement process 37
38 Key Terms of the Design-Build MOA Enforcement of Conditions Independent Compliance Monitor Allowable Work Hours Holiday Moratorium Service Interruptions Traffic Impacts Construction Aesthetics On-Street Parking Noise Standards Light Mitigation Traffic Mitigation Conditions Business Mitigation Assistance Notifications Process N. Canon Drive Traffic Study *City Council action Summer
39 MOA Design-Build Holiday Moratorium New Year s Day Martin Luther King Jr. Day President s Day Mother s Day Memorial Day Father s Day Easter Sunday The First Two Days of Passover Independence Day Labor Day Rosh Hashanah Yom Kippur Thanksgiving Day The Friday after Thanksgiving Christmas Day 39
40 MOA Design-Build Business Mitigation Assistance (BMA) 24/7 Hotline with live-person Advertising Eat Shop Play Beverly Hills Coordination with BH Chamber of Commerce and My Beverly Hills campaign Coordination with BH Tourism and Visitors Bureau and Love Beverly Hills campaign Parking Mitigation Banners and signage (Aesthetic Treatment) Communications, Outreach and Engagement 40
41 Next Steps Wilshire/Rodeo Station *Subject to change City Council Approvals* Ace Gallery Demo permit April 2018 MOA Design-Build June 2018 Notification process Hand delivered, , website, social media Continued Outreach and Communication Monthly meeting 1 st or 2 nd Wednesday of each month at City of Beverly Hills City Hall Traffic Alert in local newspapers Construction notices Online and social media ads 41
42 N. Canon Drive Study MOA approved by City Council November 21, 2017 Response to stakeholder concerns regarding construction impacts Study the temporary closure of N. Canon Drive Feasibility analysis has been completed 42
43 Canon Study Overview Transportation impact analysis for the potential closure of N. Canon Drive at Wilshire Boulevard during construction Analyzed impacts to nearby intersections during peak morning and afternoon commute hours and midday business hours Studied 15 intersections in the vicinity of the closure Considered Existing and Future (Year 2022) with travel demands from pending development projects and regional growth
44 Impacted Intersections These intersections would experience an increase congestion or delays greater than the City s standards for traffic impacts: Wilshire & Beverly - AM peak hour Wilshire & Crescent - AM and PM peak hours Clifton Way & N. Crescent - AM, midday and PM peak hours Dayton Way & N. Canon Drive - PM peak hour
45 Recommended Improvements Provide Advanced Vehicle Detour Signage to notify drivers to select alternate routes further to the east and west to avoid overly congested locations Update Traffic Signal Timings to accommodate the shift in vehicle flows and provide additional green time to the heaviest turning movements Install Traffic Signal at Clifton Way & N. Crescent Drive Intersection to replace current all-way stop signs
46 Next Steps Provide feedback today Traffic and Parking Commission on February 1 Additional community meeting on February 7 Recommend concept to City Council in March If approved, begin design development Install before decking, remain in place until road reconstruction 46
47 Aesthetic Program MOA approved by City Council November 21, 2017 Contract with firm for Aesthetics Design Program Address stakeholder concerns Mitigate aesthetics-related impacts 47
48 Aesthetics Program: Design Scope Elements K-rail Sound Wall Wayfinding Fencing Light Pole Banners Light Pole Boxes Considerations Pedestrian Experience Vehicular Experience Safety Maintenance Constructability 48
49 Next Steps Provide feedback today Additional community meeting on February 7 Recommendation to City Council in February K-rail installed as early as March 49
50 Helping local businesses as we build. Update as of 1/5/18
51 BIF Information and Eligibility > Financial assistance to small mom & pop businesses with 25 or fewer employees directly impacted by Metro Rail construction along three project areas > Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements > Grant amount determined by loss of business revenue related to period of construction disruption > To date, more than $12.4 million awarded to 268 small businesses along all three project areas
52 BIF Grant Award Update > Purple Line Extension, Section 1 > BIF Grants Awarded: 139 > BIF Grant Amount Awarded: $3,383, > Number of small businesses awarded: 59 > BIF Business Advisor: Brian Lazo > Pacific Coast Regional Small Business Development Corporation (PCR) > Phone:
53 BIF Grant Award Update > Purple Line Extension, Section 2 > BIF Grants Awarded: 1 > BIF Grant Amount Awarded: $50, > Number of small businesses awarded: 1 > BIF Business Advisor: Darrell Smith > Pacific Coast Regional Small Business Development Corporation (PCR) > Phone:
54 Next Community Meeting Beverly Hills Updates on La Cienega and Rodeo Stations Wednesday, February 7 6:30pm 8pm Beverly Hills City Hall Municipal Gallery 455 N Rexford Dr Beverly Hills, CA
55 Next Community Meeting Section 1 Section 1: Construction Community Meeting Thursday, January 18 6pm 7:30pm Petersen Automotive Museum 6060 Wilshire Bl Los Angeles, CA
56 Next Community Meeting Section 2 Section 2: Construction Community Meeting Thursday, February 22 6:30pm 8pm Century Plaza Towers 2029 Century Park East Los Angeles, CA *Parking will be validated 56
57 Stay in Touch 57
Purple Line Extension Updates on La Cienega and Rodeo Stations December 13, 2017
Purple Line Extension Updates on La Cienega and Rodeo Stations December 13, 2017 1 Agenda Project Overview Section 1 Construction Updates Wilshire/La Cienega Station La Cienega Decking Decking Overview
More informationPurple Line Extension. Rodeo Station AUR MOA October 24, 2017
Purple Line Extension Rodeo Station AUR MOA October 24, 2017 1 Agenda Project Overview Section 2 Pre-Construction Updates Rodeo Drive Station Advance Utility Relocation (AUR) SCE Phase I, underway SCE
More informationPurple Line Extension Section 1 Construction Community Meeting January 17, 2019
Purple Line Extension Section 1 Construction Community Meeting January 17, 2019 1 Agenda Section 1 MOW 64 Facility Project Construction Updates: Fossils Project-wide Tunneling Wilshire/Western Wilshire/La
More informationPurple Line Extension Section 1 Construction Community Meeting April 19, 2018
Purple Line Extension Section 1 Construction Community Meeting April 19, 2018 1 Agenda Section 1 MOW 64 Facility Project Construction Updates: Wilshire/Western Wilshire/La Brea Wilshire/Fairfax Wilshire/La
More informationPurple Line Extension, Section 2 Southern California Edison, Phase I
Purple Line Extension, Section 2 Southern California Edison, Phase I 1 Agenda Advance Utility Relocation (AUR) Schedule Southern California Edison (SCE) overview Street Impacts Sunday work: 10am-6pm Left
More informationPurple Line Extension, Section 2 Southern California Edison, Phase I June 7, 2017
Purple Line Extension, Section 2 Southern California Edison, Phase I June 7, 2017 Agenda Advance Utility Relocation (AUR) Schedule Southern California Edison (SCE) overview Street Impacts Sunday work:
More informationPurple Line Extension Section 1 Construction Community Meeting January 18, 2018
Purple Line Extension Section 1 Construction Community Meeting January 18, 2018 1 Agenda Section 1 2017 Accomplishments TBM Art and Naming Contest MOW 64 Facility Project Construction Updates: Wilshire/Western
More information2.4 Build Alternatives
Table 2-1. Future Transit Network Changes between No Build and TSM Alternatives Operator Route Group No. Route ID and Description Peak Headway (min) No Build Off-peak Headway (min) Peak Headway (min) TSM
More informationPurple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations November 7, 2018
Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations November 7, 2018 1 Agenda Project Overview Section 1 Construction Updates Wilshire/La Cienega Station Excavation Metro Art Eat Shop
More informationExpo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011
Project Status Update Meeting Project Status Update Meeting Holman United Methodist Church January 27, 2011 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor
More informationWESTSIDE SUBWAY EXTENSION PROJECT. Construction Traffic Analysis Report
PROJECT Construction Traffic Analysis Report August 2011 Table of Contents 1.0 2.0 3.0 4.0 Table of Contents INTRODUCTION... 1-1 1.1 Objectives of the Report... 1-1 1.2 Project Overview... 1-1 1.3 Approach...
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Project Status Update Meeting West End Corridor Segment C Culver City Senior Center May 27, 2010 Phase 1 Project Description 8.6 mile corridor from Downtown Los Angeles
More informationWESTSIDE SUBWAY EXTENSION PROJECT. Updated Off-street Parking Analysis Memorandum
WESTSIDE SUBWAY EXTENSION PROJECT Updated Off-street Analysis Memorandum April 2011 Table of Contents 1.0 INTRODUCTION... 1 2.0 DATA SOURCE... 1 3.0 OFF-STREET LAND USE & PARKING ANALYSIS... 2 3.1 Station
More informationPomona Rotary December 19, 2017
Pomona Rotary December 19, 2017 Los Angeles County s population will grow by 5.9% to 10.7 million by 2024 During that same period, the San Gabriel Valley will grow by 7.6% to more than 1.5 million; taking
More informationW&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237)
W&OD TRAIL BRIDGE OVER LEE HIGHWAY A COMPONENT OF THE I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) October 11, 2018 Bill Cuttler, PE
More informationExpo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles April 2014
Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles April 2014 Meeting Agenda Phase 2 Construction Update Meeting Meeting Purpose and Format Construction Update Expo Bikeway Update
More informationWestside Subway Extension Final EIS/EIR. January 2011 Community Update Meetings
Westside Subway Extension Final EIS/EIR January 2011 Community Update Meetings Purpose of Tonight s Meeting Background information on planning to date Clarify Locally Preferred Alternative (LPA) under
More informationProject Scoping Report Appendix B Project Web Site. APPENDIX B Project Web Site
Project Scoping Report Appendix B Project Web Site APPENDIX B Project Web Site WESTSIDE EXTENSION TRANSIT CORRIDOR STUDY February 4, 2008 News and Info of 1 http://metro.net/projects_programs/westside/news_info.htm#topofpage
More informationI-405 Sepulveda Pass Improvements Project
I-405 Sepulveda Pass Improvements Project Community Meeting November 15, 2012 1 Wilshire Segment Overview of Wilshire Segment There are a total of 23 bridges being constructed on this project; almost half
More informationCITY OF BEVERLY HILLS STAFF REPORT
Meeting Date: July 7, 2011 To: From: Subject: CITY OF BEVERLY HILLS STAFF REPORT Honorable Mayor & City Council Pamela Mottice Muller, Director of Emergency Management 405 Closure Attachments: 1. 1-405
More informationI-405 Sepulveda Pass Improvements Project
I-405 Sepulveda Pass Improvements Project 26, 2012 Click to edit Master title January style Community Advisory Committee 1 Community Meeting Schedule for 2012 26-Jan CAC, Final Meeting Feb 22-Mar Community
More informationConstruction Staging Area 4 Avenue Road
REPORT FOR ACTION Construction Staging Area 4 Avenue Road Date: September 27, 2017 To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto and East York District
More informationBEVERLY HILLS STAFF REPORT
BEVERLY HILLS STAFF REPORT Meeting Date: June 17, 2014 To: From: Honorable Mayor & City Council Aaron Kunz, Deputy Director of Transportation Martha Eros, Transportation Planner Subject: Request by Councilmembers
More informationCrenshaw-Prairie Transit Corridor Study Public Meetings
Crenshaw-Prairie Transit Corridor Study Public Meetings Darby Park: Wednesday, February 20, 2008 6:30 8:00 PM US Bank Community Room: Thursday, February 21, 2008 6:30 8:00 PM Nate Holden Performing Arts
More informationProject Status Update January 2017
Project Status Update January 2017 1 What is the Purple Line? A new 16 mile east-west light rail line Operates mostly on the surface with 21 stations Connects New Carrollton in Prince George s County and
More informationMobility Corridor Updates. Transit & Active Transportation Projects
Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate
More informationFixing the Line s Canarsie Tunnel. Manhattan CB6 11/5/2018
Fixing the Line s Canarsie Tunnel Manhattan CB6 11/5/2018 Interborough Bus Service 80+ buses in the peak hour in the peak direction over the Williamsburg Bridge Projected to carry 17% of riders 1 Bus Priority
More informationSOUTH ACCESS TO THE GOLDEN GATE BRIDGE DOYLE DRIVE DOYLE DRIVE. Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009
DOYLE DRIVE Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009 Presentation Overview Introduction Project Acceleration Construction Contracts Construction Activities Lane and Road
More informationChapter 2 Alternatives Considered
Beverly Center Area Station Figure 2-54. Santa Monica/San Vicente Station This station would be under San Vicente Boulevard, extending from just south of Gracie Allen Drive to south of Third Street (Figure
More informationCity of Beverly Hills North Santa Monica Blvd Reconstruction. Traffic & Parking Commission June 04, 2015
City of Beverly Hills North Santa Monica Blvd Reconstruction Traffic & Parking Commission June 04, 2015 1 Overview of June 4 TPC Overview of Possible Traffic Mitigation Measures Toolbox During Construction
More informationMobility Corridor Updates. Transit & Active Transportation Projects
Mobility Corridor Updates Transit & Active Transportation Projects Laura Cornejo, DEO Regional Planner Regional Operator Metro is LA County s Regional Builder/Funder Rail Bus Service (Metro/Muni/Local)
More informationAttachment D Environmental Justice and Outreach
Attachment D Environmental Justice and Outreach ATTACHMENT D Environmental Justice and Outreach Indicate whether the project will have disproportionately high and adverse impacts on minority or low income
More informationMEMORANDUM CITY OF BEVERLY HILLS
MEMORANDUM CITY OF BEVERLY HILLS TO: FROM: City Council and Traffic and Parking Commission Liaison Committee Chad Lynn, Assistant Public Works Director Genevieve Row, Parking Services Manager Judi Tamasi,
More informationSOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015
SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment
More informationCorridor Management Committee. March 7, 2012
Corridor Management Committee March 7, 2012 2 Today s Topics SWLRT Project Office Update Engineering Services Procurement Update Legislative Leadership Tour Annual New Starts Report Update on Proposed
More informationOttawa LRT Stage 2. McKellar Park Information Session
Ottawa LRT Stage 2 McKellar Park Information Session Stage 2 Background Approved unanimously by Ottawa City Council in July 2015 East to Place d Orléans, west to Bayshore and Baseline, and south to Bowesville
More informationClick to edit Master text styles
I-405 Sepulveda Pass Improvements Project Quarterly Community Meeting November 17, 2011 1 Wilshire Segment 2 Quarterly Community Meetings 2012 Month Meeting(s) February 16 May 17 Quarterly Quarterly August
More informationExpo Light Rail Line. Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015
Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015 Meeting Purpose and Format Meeting Purpose and Format The purpose of tonight s meeting is to: Provide a final update
More informationCrenshaw/LAX Transit Corridor. Transit Coalition Meeting June 26, 2012
Transit Coalition Meeting June 26, 2012 Measure R Projects 8 ½ mile light rail line from Exposition/Crenshaw Blvds. to Metro Green Line s Aviation/LAX station Six stations with two optional stations carried
More informationLane Closure Manual. Route Report Index: US12-A US12-03 (WB) US12-01 (EB WB) US12-02 (EB)
Route Report Index: US1-A?A@ 15 %&'( 94?A@ 5?A@?A@ 95 +, 16 9?A@?A@ 47 %&'( 95 5?A@ 65 +, 8 +, 1 5 %&'( 94 %&'( 69 4 %&'( 5 W %&'( 5 E +, 61?A@ 95 %&'( %&'( 69 4 9 4 %&'( 94 %&'( 49 4 NOTE: Lane closures
More information04sk042. istorical. Calendar
C T A 04sk042 istorical Calendar The 9000-9599 series buses, delivered in 1975-1976, featured air-inflated or balloon bumpers, air-conditioning and anti-skid brakes. Pictured here is an impressive line-up
More informationCentral Park Drives Traffic Management Overview
Central Park Drives Traffic Management Overview Spring 2015 New York City Department of Transportation Existing Traffic Management From Labor Day thru Last Day of NYC Public School: 8-10 AM weekdays (Southbound)
More informationCommunity Open Houses November 29 December 7, 2017
Community Open Houses November 29 December 7, 2017 1 Community Open House Agenda 6:00 PM Open House 6:30-7:30 PM Presentation and Q&A 7:30-8:00 PM Open House Resumes after the presentation and Q&A Thank
More informationPeninsula Corridor Electrification Update Meeting
Peninsula Corridor Electrification Update Meeting Brisbane City Council September 6, 2018 Agenda Caltrain System Overview Project Overview Electric Multiple Unit (EMU) Design Brisbane Construction Activities
More informationPhone (602) Toll Free (800) Fax (602) CALENDAR OF FILING DEADLINES AND SEC HOLIDAYS
2018 CALENDAR OF FILING S AND SEC HOLIDAYS S FOR QUARTERLY AND ANNUAL REPORTS 10-K LARGE ACCELERATED FILERS ACCELERATED FILERS NON-ACCELERATED FILERS 60 Days from Fiscal Year End 75 Days from Fiscal Year
More informationLandside Access Modernization Program (LAMP)
Landside Access Modernization Program (LAMP) LAX Los Angeles International Airport is the 2 nd busiest airport in the United States and is the largest airport in California. Since the start of the economic
More informationIV. ENVIRONMENTAL IMPACT ANALYSIS N. TRANSPORTATION AND TRAFFIC
IV. ENVIRONMENTAL IMPACT ANALYSIS N. TRANSPORTATION AND TRAFFIC The following section summarizes the information provided in the traffic report entitled Traffic Impact Analysis for a Proposed Residential
More informationCREATING CONNECTIONS IN THE CITY OF WATERLOO
CREATING CONNECTIONS IN THE CITY OF WATERLOO GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX METROLINX PRESENTATION TO
More informationS M T W T F S B C D E F G A A B C D E F G G A B C D E F F G A B C D E
New Year s Day January 2006 * 1 2 3 4 5 6 7 P rior to the extension of Blue Line service from Jefferson Park to O Hare International Airport in 1984, CTA provided service to the airport from Jefferson
More informationCapital Metro Downtown Multimodal Station
Capital Metro Downtown Multimodal Station Stakeholder Briefing December 11, 2015 Agenda 1 2 3 4 5 Project Summary Downtown Station Concept Evaluation 4 th Street Traffic Analysis 5 th Street Traffic Analysis
More informationRevised Strategy for Downtown Parking
Revised Strategy for Downtown Parking December 4, 2017 Council Workshop Presented by Jennifer McCoy, P.E., City Traffic Engineer City-Owned Parking Today 3,500 metered parking spaces Parking meters charge
More informationCTfastrak Expansion. Stakeholder Meeting #4 Manchester Town Hall June 3, 2016
CTfastrak Expansion Stakeholder Meeting #4 Manchester Town Hall June 3, 2016 Today s Agenda Phase I Update 2016 Service Plan Implementation Schedule & Cost Update Phase II Services Timeline Market Analysis
More informationAppendix H - Response to Comments. March 2012 Page H
593-1 Your support for Alternative 3 (Santa Monica Extension) has been noted. On October 28, 2010, the Metro Board of Directors identified Alternative 2 (Westwood/VA Hospital Extension) as the Locally
More informationCommunity Meetings June 2018
Community Meetings June 2018 1 Welcome and Agenda Thank you for joining us! 6:00 pm Open House 6:30 pm Welcome & Presentation 7:00 pm Q&A 7:15 pm Open House Resumes 8:00 pm Meeting Concludes 2 Purpose
More informationWelcome and Agenda. Thank you for joining us! 6:00 pm Open House. 6:30 pm Welcome & Presentation. 7:00 pm Q&A. 7:15 pm Open House Resumes
1 Welcome and Agenda Thank you for joining us! 6:00 pm Open House 6:30 pm Welcome & Presentation 7:00 pm Q&A 7:15 pm Open House Resumes 8:00 pm Meeting Concludes 2 Purpose of this Meeting Introduce project
More informationWAKE TRANSIT PLAN Summer 2018
WAKE TRANSIT PLAN Summer 2018 Planning for growth WAKE COUNTY s population already exceeds ONE MILLION and grows by more than 60 people a day. That s 23,000 people a year or basically another Morrisville.
More informationWESTSIDE SUBWAY EXTENSION. Final Smart Growth Evaluation Report
Final Smart Growth Evaluation Report August 2010 Table of Contents Table of Contents 1.0 INTRODUCTION... 1-1 1.1 4Ds... 1-2 1.2 Direct Ridership Model (DRM)... 1-2 2.0 4DS... 2-1 2.1 Inputs... 2-1 2.2
More informationOrange Line Bus Rapid Transit (BRT) Improvements San Fernando Valley Service Council April 3, 2019
Orange Line Bus Rapid Transit (BRT) Improvements San Fernando Valley Service Council April 3, 2019 1 Measure M Transit Projects in San Fernando Valley 2 1 2 Measure M Transit Projects Schedule Project
More informationExpo Light Rail Line. Expo Line Project Westside/Central Metro Service Council November 2014
Expo Line Project Westside/Central Metro Service Council November 2014 2 Expo Line Project Description Phase 2 Expo Line from Culver City to Santa Monica: 6.6 mile corridor 7 new Stations 64,000 Daily
More informationSouth Gloucestershire Challenge Fund and Cycle Ambition Fund
South Gloucestershire Challenge Fund and Cycle Ambition Fund The Challenge Fund A4174 scheme is coordinated and delivered by South Gloucestershire Council who were awarded 14 million pounds from the Department
More informationCREATING CONNECTIONS IN WATERLOO REGION
CREATING CONNECTIONS IN WATERLOO REGION GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE CHRIS BURKE, DIRECTOR, SERVICE PLANNING ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX
More informationHowever, due to the location, all garage parkers will need to continue to use the South end garage for entrance and exit.
We apologize for any inconvenience that this construction may cause and appreciate your patience while we work hard to improve The Crescent for our customers. Effective Tuesday, July 28 Shoring for the
More informationCINCINNATI PARKING INFRACTION (CPI)
CINCINNATI PARKING INFRACTION (CPI) Reference: Procedure 12.205 - Traffic Enforcement Procedure 12.270 - Impounding, Moving, and Release of Vehicles Procedure 12.445 - Complaint Report Form 305 Purpose:
More informationWest Broadway Reconstruction/LRT Design. March 19, 2015
West Broadway Reconstruction/LRT Design March 19, 2015 1 Meeting Agenda 6:05 6:30 PM Brief presentation What we heard Project overview 6:30 8:00 PM Visit Six Topic Areas Road and LRT design elements Pedestrian
More informationCREATING CONNECTIONS IN THE CITY OF KITCHENER
CREATING CONNECTIONS IN THE CITY OF KITCHENER GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS KITCHENER CITY COUNCIL SEPTEMBER 25, 2017 CONGESTION
More informationEast San Fernando Valley Transit Corridor. TAC Briefing December 4, 2013
East San Fernando Valley Transit Corridor TAC Briefing December 4, 2013 Overview Measure R Project Long Range Transportation Plan Reserves $170.1 Million 2018 Revenue Operations Date Coordination with
More informationDAYTON FIREFIGHTERS FEDERAL CREDIT UNION
DAYTON FIREFIGHTERS FEDERAL CREDIT UNION 338 South Patterson Blvd. Dayton, Ohio 45402 Phone: (937) 228-64 FAX: 228-0068 Monday Friday 0 AM - 6 PM HOME AUDIO LINK -800-285-2947 www.dffcu.org VISA -800-558-3424
More informationIMPROVEMENT CONCEPTS
IMPROVEMENT CONCEPTS for the South Novato Transit Hub Study Prepared by: January 11, 2010 DKS Associates With Wilbur Smith Associates IMPROVEMENT CONCEPTS Chapter 1: Introduction 1. INTRODUCTION The strategic
More informationExposition Corridor Transit Project
Exposition Corridor Transit Project Phase 2 Environmental Planning Community Meeting June 9, 2008 Exposition Corridor Transit Project Phase 2 AGENDA Remaining Grade Crossing Recommendations June 9, 2008
More informationBest Wishes for a Happy & Prosperous 2015! 2014 Calendars & More
Best Wishes for a Happy & Prosperous 2015! Notes In a gentle way you can shake the world. Mahatma Gandhi NOVEMBER JANUARY 1 December 1 2 3 2 3 4 5 6 7 8 4 5 6 7 8 9 10 9 10 11 12 13 15 11 12 13 14 15 16
More informationExecutive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1
Executive Summary Introduction The Eastside Transit Corridor Phase 2 Project is a vital public transit infrastructure investment that would provide a transit connection to the existing Metro Gold Line
More informationTraffic Engineering Study
Traffic Engineering Study Bellaire Boulevard Prepared For: International Management District Technical Services, Inc. Texas Registered Engineering Firm F-3580 November 2009 Executive Summary has been requested
More informationCITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM
CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM Date: April 11, 2018 To: The Honorable City Council c/o City Clerk, Room 395, City Hall Attention: Honorable Mike Bonin, Chair, Transportation Committee
More informationStittsville OC Transpo Services
Stittsville OC Transpo Services Transportation Services Department March 22, 2018 0 Ottawa s Transit Challenge 1 1 What s Coming in 2018 O-Train Network 2 2 Confederation Line - Alignment 3 3 VEHICLE AND
More informationTable Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily
5.8 TRAFFIC, ACCESS, AND CIRCULATION This section describes existing traffic conditions in the project area; summarizes applicable regulations; and analyzes the potential traffic, access, and circulation
More information2019 SEC Filing Calendar
C ALENDAR 2019 SEC Filing Calendar EDGAR filing deadlines, peak periods and holidays DFINsolutions.com 2019 FEDERAL HOLIDAYS 2019 SEC Filing Dates New Year s Day January 1 Martin Luther King, Jr. Day
More informationNOTICE OF PUBLIC HEARING ANAHEIM PUBLIC UTILITES BOARD IS HOLDING A PUBLIC HEARING ON THE FORMATION OF UNDERGROUND DISTRICT No. 66 (BEACH) TO UNDERGROUND OVERHEAD FACILTIIES, INCLUDING POWER AND COMMUNICATION
More informationPeninsula Corridor Electrification Project (PCEP)
Peninsula Corridor Electrification Project (PCEP) Q4 Quarterly Update #11 April 1 June 30, 2017 JPB Board Meeting August 3, 2017 Agenda Item # 8a Electrification - Infrastructure Design Build Contract
More informationWESTSIDE SUBWAY EXTENSION. Traffic Analysis Impact Report
Traffic Analysis Impact Report August 2010 Table of Contents Table of Contents 1.0 INTRODUCTION/SUMMARY...1-1 1.1 Existing (Year 2006) Setting... 1-1 1.2 Future (Year 2035) Setting... 1-2 2.0 PROJECT
More informationVan Ness Transit Corridor Improvement Project. Engineering, Maintenance and Safety Committee March 25, 2015
Van Ness Transit Corridor Improvement Project Engineering, Maintenance and Safety Committee March 25, 2015 Project Need 16,000 daily passenger boardings within the project corridor Average bus speed 8
More informationDecember Individual Quality Review Calendar FY 18 FY 19. Mon Tues Wed Thu Fri Sat. Sun METRO1 SAMPLE TO REGION
December 2017 Sun Mon Tues Wed Thu Fri Sat 1 2 3 4 5 6 7 8 9 METRO1 SAMPLE TO REGION 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Christmas METRO1 Schedules issued to IQR Updated 1/5/18
More information,ILLS CITY OF BEVERLY HILLS TRAFFIC AND PARKING COMMISSION. July 12, 2018 TO: Traffic and Parking Commission FROM: Transportation Staff SUBJECT:
Transportation Staff TO: FROM: Traffic and Parking Commission July 12, 2018 A. Preferential Parking Permit Test District Survey and FAQ Sheet All businesses and households located within 1,000 feet of
More informationAgenda Cover Memorandum
Agenda Cover Memorandum Meeting Date: August 21, 2017 Meeting Type: COW (Committee of the Whole) City Council Budget Workshop Item Title: Final approval of an Ordinance amending various sections of Article
More informationRail alignment and benefits (rab) study
Rail alignment and benefits (rab) study previously known as railyard alternatives & i-280 boulevard study May 22, 2018 CONNECTING CALIFORNIA 4,300 lane miles + 115 Airport gates would be needed to create
More informationIPS Supported Employment: Recovery Through Work
~ IPS Supported Employment: Recovery Through Work 2012 ~ Some days I have to walk to work, four miles each way, but work is really important to me. ~ Tyler IPS supported employment is well-researched.
More information5. OPPORTUNITIES AND NEXT STEPS
5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours
More informationArterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014
Arterial Bus Rapid Transit System Policy Oversight Committee April 7, 2014 1 Meeting Agenda Welcome and Introductions A Line - Project Status Shelter and Pylon Development Arterial BRT Branding Update
More informationJanice Fortunato Senior Director Business Partnerships
Janice Fortunato Senior Director Business Partnerships What are Megaprojects? They are large-scale projects distinguished by cost, complexity and the potential impact on the community. Collectively, these
More informationFREQUENTLY ASKED QUESTIONS
THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on
More information10605 Central Ave NW Albuquerque, NM For Reservations call (505) Direct Line (505) ext.1000
10605 Central Ave NW Albuquerque, NM 87121 For Reservations call (505) 407-8046 Direct Line (505) 242-1108 ext.1000 Calendar Design - Stephanie Berg For more information log onto www.herreracoach.com January
More informationWheaton Fund Communications Calendar
Wheaton Fund 2018 2019 Communications Calendar AUGUST 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Move-in Day 26 27 28 Classes begin & Convocation 29 30 31 Receive your final class
More informationCountdown to the Closure Extended 53-Hour Closure of I-405 Freeway Between U.S. 101 and I-10 Planned in Mid-July for Mulholland Bridge Demolition
Countdown to the Closure Extended 3-Hour Closure of I-40 Freeway Between U.S. 0 and I-0 Planned in Mid-July for Mulholland Bridge Demolition Work Los Angeles, Calif. Plan Ahead, Avoid The Area, Or Stay
More informationLos Angeles World Airports. LAX Landside Transportation Program
Los Angeles World Airports LAX Landside Transportation Program 1 Existing Conditions Not Enough Curb Space Mode Conflicts Limited Roadways 2 3 Problem Today All airport users must rely on an inefficient
More informationBusiness Advisory Committee. July 7, 2015
Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS
More informationDallas CBD Second Light Rail Alignment (D2)
Dallas CBD Second Light Rail Alignment (D2) Subway Project Refinement Stakeholder Meeting December 7, 2016 Discussion Items Background Schedule Public/Stakeholder Involvement Comments/Questions from Audience
More informationEast San Fernando Valley Transit Corridor. Information Session, October 10, 2017
East San Fernando Valley Transit Corridor Information Session, October 10, 2017 1 Welcome and Meeting Purpose Introductions Metro Transit Corridors Planning Metro Real Estate Metro Community Relations
More informationWest Santa Ana Branch Transit Corridor. Informational Briefing Gateway Cities Service Council April 13, 2017
West Santa Ana Branch Transit Corridor Informational Briefing Gateway Cities Service Council April 13, 2017 Project Study Area 98 square miles 20 individual cities plus unincorporated LA County 1.2 million
More informationMETRO Orange Line BRT American Boulevard Station Options
METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN
More information30-Day Look Ahead Summary August 2011
Wilshire Segment 30-Day Look Ahead Summary August 2011 DWP and SCE Utility Relocation Sepulveda reduced to one lane in each direction, Constitution to Ohio, 9pm to 6am Westbound Wilshire reduced to one
More informationSAN RAFAEL CITY COUNCIL AGENDA REPORT
Agenda Item No: 8.b Meeting Date: December 19, 2016 Department: PUBLIC WORKS SAN RAFAEL CITY COUNCIL AGENDA REPORT Prepared by: Bill Guerin, Public Works Director City Manager Approval: File No.: 18.01.79
More information