Expo Light Rail Line. Expo Line Project Westside/Central Metro Service Council November 2014

Size: px
Start display at page:

Download "Expo Light Rail Line. Expo Line Project Westside/Central Metro Service Council November 2014"

Transcription

1 Expo Line Project Westside/Central Metro Service Council November 2014

2 2 Expo Line Project Description Phase 2 Expo Line from Culver City to Santa Monica: 6.6 mile corridor 7 new Stations 64,000 Daily Riders by 2030 Estimated Travel Time (Downtown LA to Santa Monica): 46 minutes Estimated Cost: $1.5 billion Final design in now complete Project is 75% complete Major construction started in 2012

3 3 Construction Progress Expo Phase 2 Construction Progress at a Glance 2014 Construction Highlights: Station construction is more than 68% complete All 7 bridges have been completed All 7 stations are under construction Track installation to be completed by fall Roadway widening work and final paving continues

4 4 ROW Construction Progress Construction Update Venice Boulevard Median Construction Rail Welding at the I-10 Box OCS Pole Installation at Northvale Trench Sidewalk Concrete Pour at Overland Avenue

5 5 Palms Station Street view from Exposition Boulevard looking west

6 6 Westwood/Rancho Park Station Street view from Exposition Boulevard looking east

7 7 Expo/Sepulveda Station Street view from Exposition Boulevard looking west

8 8 Expo/Bundy Station Street view from Exposition Boulevard looking east

9 9 26 th Street/Bergamot Station Street view from looking east

10 10 17 th Street/SMC Station Street view looking east

11 11 Downtown Santa Monica Station Street view from Colorado Avenue looking east

12 12 Construction Progress Station Progress thru December 2014 Palms Westwood/ Rancho Park Expo/ Sepulveda Platform foundation work completed Track installation completed Elevator installation nearing completion On-going electrical, train control systems installation Canopy and archway installation Expo/ Bundy Palms Station Platform Paver Installation

13 13 Construction Progress Station Progress thru December 2014 Palms Westwood/ Rancho Park Expo/ Sepulveda Platform foundation work completed Track installation completed Electrical and train control systems installation on-going Canopy installation Expo/ Bundy Westwood Rancho Park Station Platform Pavers

14 14 Construction Progress Station Progress thru December 2014 Palms Westwood/ Rancho Park Expo/ Sepulveda Platform foundation work completed Track installation completed Elevator installation nearing completion Electrical and train control systems installation Canopy and Archway installation Utility Room construction Expo/ Bundy Sepulveda Station Plaza Progress

15 15 Construction Progress Station Progress thru December 2014 Palms Westwood/ Rancho Park Expo/ Sepulveda Platform foundation work completed Track installation completed Elevator installation nearing completion Electrical and train control systems installation Canopy and Archway installation Utility Room construction Expo/ Bundy Bundy Station Elevator Installation Progress

16 16 Construction Activities thru December 2014 Los Angeles Venice Blvd to Motor Ave Venice bridge track installation completed Venice Blvd roadway improvements continue on the north side Traffic signal and street light installation Motor Ave to Military Ave Complete roadway improvements at Overland Ave and Westwood Blvd Traffic signal and street light installation Construction Progress Pico Roadway Improvements Lane closures on Pico Blvd Scheduled to begin: Friday, December 5, 2014 Military Ave to Centinela Ave On-going track installation on ROW Roadway improvements at Pico Blvd and Barrington Ave Traffic signal and street light installation Westwood Boulevard Bus Pad Construction

17 17 Construction Update Expo Right-of-Way (ROW) Construction Progress Santa Monica Rail Installation at 19 th Street Maintenance Facility Building Progress Downtown Santa Monica Station Concrete Pour TPSS Installation at Olympic and Cloverfield

18 18 Construction Progress Station Progress thru December th Street/ Bergamot 17 th Street/ SMC Downtown Santa Monica Foundation work nearing completion On-going electrical and systems installation Canopy and archway installation Platform paver installation has been completed Track installation was completed in June 26 th Street /Bergamot Station Paver Installation

19 19 Construction Progress Station Progress thru December th Street/ Bergamot 17 th Street/ SMC Downtown Santa Monica On-going electrical and systems installation Canopy and archway installation Paver installation has been completed Foundation work is complete Track installation was completed in July 17 th Street /SMC Station Tactile Warning Paver Installation

20 20 Construction Progress Station Progress thru December th Street/ Bergamot 17th Street/ SMC Downtown Santa Monica Foundation work on-going Utility work on-going Electrical Systems Installation Platform paver installation to start in November Track installation to be completed in October Downtown Santa Monica Station Concrete Pour

21 21 Construction Progress Ongoing Construction Activities thru December 2014 Santa Monica Centinela Ave to 4th Street Continue with track installation on ROW Traffic signal, street light and train control systems installation Final street improvements Sidewalk installation between Stewart and Cloverfield Irrigation and permanent fence installation OCS Pole and Catenary Wire installation 6th Street Track Installation 6th Street is the only remaining Expo 2 track crossing Scheduled to begin: Wednesday, November 12, 2014 Olympic Bridge Rail Installation Progress

22 22 Bikeway and Maintenance Facility Expo Bikeway Design/Construction Soil removal and grading Irrigation, drainage systems, and curb and gutter Electrical and lighting conduits Maintenance Facility On-going installation of building pre-cast panels Typical Bike Path Design Installation of Main building interior utilities and walls On-site rail installation to start in mid-october Foundation construction for secondary and third buildings continues Maintenance Facility Building Foundation Progress

23 23 Construction Timeline Construction Progress and Timeline Construction Timeline 2011 Pre-Construction Activities 2012 Bridge Construction, Utility Relocation and Guideway Excavation, and Soundwalls Bridge and Station Construction, Utility Relocation, Soundwalls, Track Installation and Street/Roadway Improvements Continue Street/Roadway Improvements, Track Installation, Utility Relocation Station Finishes, Electrical System, Train Control, and Landscaping Installation Continue Street/Roadway Improvements and Landscaping Installation, Systems Testing and Pre-Revenue Operations

24 24 Contacts How to Reach Us Project Website: Sign-up on our homepage to be added to the project database and receive notices via . Project Hotline: EXPO (3976) Community Relations Contacts: Torri Hill SRJV Community Relations Manager or Heather Rozman SRJV Community Relations Coordinator or Social Media:

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015 Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015 Meeting Agenda Phase 2 Construction Update Meeting Meeting Purpose and Format Construction Update Expo Bikeway

More information

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles April 2014

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles April 2014 Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles April 2014 Meeting Agenda Phase 2 Construction Update Meeting Meeting Purpose and Format Construction Update Expo Bikeway Update

More information

Expo Light Rail Line. Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015

Expo Light Rail Line. Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015 Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015 Meeting Purpose and Format Meeting Purpose and Format The purpose of tonight s meeting is to: Provide a final update

More information

Expo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011

Expo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011 Project Status Update Meeting Project Status Update Meeting Holman United Methodist Church January 27, 2011 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report February 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

Exposition Corridor Transit Project

Exposition Corridor Transit Project Exposition Corridor Transit Project Phase 2 Environmental Planning Community Meeting June 9, 2008 Exposition Corridor Transit Project Phase 2 AGENDA Remaining Grade Crossing Recommendations June 9, 2008

More information

3.11 Land Use/Planning

3.11 Land Use/Planning 3.11 Land Use/Planning 3.11.1 Introduction This section identifies existing and future land uses as defined by the land use plans of the local jurisdictions. The section also identifies the existing land

More information

I-405 Sepulveda Pass Improvements Project

I-405 Sepulveda Pass Improvements Project I-405 Sepulveda Pass Improvements Project Community Meeting November 15, 2012 1 Wilshire Segment Overview of Wilshire Segment There are a total of 23 bridges being constructed on this project; almost half

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Project Status Update Meeting West End Corridor Segment C Culver City Senior Center May 27, 2010 Phase 1 Project Description 8.6 mile corridor from Downtown Los Angeles

More information

3.14 Parks and Community Facilities

3.14 Parks and Community Facilities 3.14 Parks and Community Facilities 3.14.1 Introduction This section identifies the park and community facility resources in the study area and examines the potential impacts that the proposed Expo Phase

More information

2. PROJECT ALTERNATIVES

2. PROJECT ALTERNATIVES 2. PROJECT ALTERNATIVES 2.1 Introduction Six alternatives are evaluated in detail in this Draft Final Environmental Impact Report (DFEIR) for the Exposition Corridor Transit Project Phase 2 (Expo Phase

More information

Community Meetings June 2018

Community Meetings June 2018 Community Meetings June 2018 1 Welcome and Agenda Thank you for joining us! 6:00 pm Open House 6:30 pm Welcome & Presentation 7:00 pm Q&A 7:15 pm Open House Resumes 8:00 pm Meeting Concludes 2 Purpose

More information

Welcome and Agenda. Thank you for joining us! 6:00 pm Open House. 6:30 pm Welcome & Presentation. 7:00 pm Q&A. 7:15 pm Open House Resumes

Welcome and Agenda. Thank you for joining us! 6:00 pm Open House. 6:30 pm Welcome & Presentation. 7:00 pm Q&A. 7:15 pm Open House Resumes 1 Welcome and Agenda Thank you for joining us! 6:00 pm Open House 6:30 pm Welcome & Presentation 7:00 pm Q&A 7:15 pm Open House Resumes 8:00 pm Meeting Concludes 2 Purpose of this Meeting Introduce project

More information

Project Scoping Report Appendix B Project Web Site. APPENDIX B Project Web Site

Project Scoping Report Appendix B Project Web Site. APPENDIX B Project Web Site Project Scoping Report Appendix B Project Web Site APPENDIX B Project Web Site WESTSIDE EXTENSION TRANSIT CORRIDOR STUDY February 4, 2008 News and Info of 1 http://metro.net/projects_programs/westside/news_info.htm#topofpage

More information

4.1 Traffic, Circulation, and Parking

4.1 Traffic, Circulation, and Parking 4.1 Traffic, This section describes the existing transportation and parking conditions within and adjacent to the project area. A traffic report describing the potential impacts of the proposed project

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate

More information

Community Meetings. January/February 2019

Community Meetings. January/February 2019 Community Meetings January/February 2019 Purpose of Meeting Present evaluation of Valley- Westside concepts Present initial Westside- LAX concepts Gather community feedback 2 Study Process 3 Overview:

More information

I-405 Sepulveda Pass Improvements Project. Community Advisory Committee July 28, 2011

I-405 Sepulveda Pass Improvements Project. Community Advisory Committee July 28, 2011 I-405 Sepulveda Pass Improvements Project Community Advisory Committee July 28, 2011 1 Wilshire Segment 2 Wilshire Segment (National to Waterford) Ramp and Wall Construction at Sepulveda/Wilshire Intersection

More information

I-225 Rail Line. 13 th Avenue Station Information Meeting. July 25, 2013

I-225 Rail Line. 13 th Avenue Station Information Meeting. July 25, 2013 I-225 Rail Line 13 th Avenue Station Information Meeting July 25, 2013 FasTracks and I-225 Rail Line Update Chuck Culig I-225 Rail Line Project Manager 2 The RTD FasTracks Plan 122 miles of rail 18 miles

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Laura Cornejo, DEO Regional Planner Regional Operator Metro is LA County s Regional Builder/Funder Rail Bus Service (Metro/Muni/Local)

More information

Project Scoping Open House Welcome

Project Scoping Open House Welcome Scoping Meeting Project Scoping Open House Welcome Alternatives Analysis (AA) and Draft Environmental Impact Statement/Draft Environmental Impact Report (DEIS/DEIR) Project Purpose Purpose of the Project

More information

CONFEDERATION LINE EAST SEGMENT

CONFEDERATION LINE EAST SEGMENT The O-Train Confederation Line project is the first stage in Ottawa s future light rail network. The 12.5 kilometre electric rail system will replace existing diesel powered buses, providing rapid transit

More information

EXECUTIVE SUMMARY. Introduction. Project Purpose. Executive Summary

EXECUTIVE SUMMARY. Introduction. Project Purpose. Executive Summary EXECUTIVE SUMMARY Introduction The Exposition Metro Line Construction Authority (Expo Authority) has prepared this Draft Final Environmental Report (DFEIR) in order to extend high -capacity, high -frequency

More information

30-Day Look Ahead Summary August 2011

30-Day Look Ahead Summary August 2011 Wilshire Segment 30-Day Look Ahead Summary August 2011 DWP and SCE Utility Relocation Sepulveda reduced to one lane in each direction, Constitution to Ohio, 9pm to 6am Westbound Wilshire reduced to one

More information

Study Area, Related Projects and Travel Markets

Study Area, Related Projects and Travel Markets Study Area, Related Projects and Travel Markets Study area and related projects Travel between Valley and Westside North San Fernando Valley BRT (Alignment TBD) East San Fernando Valley Transit Corridor

More information

Orange Line Bus Rapid Transit (BRT) Improvements San Fernando Valley Service Council April 3, 2019

Orange Line Bus Rapid Transit (BRT) Improvements San Fernando Valley Service Council April 3, 2019 Orange Line Bus Rapid Transit (BRT) Improvements San Fernando Valley Service Council April 3, 2019 1 Measure M Transit Projects in San Fernando Valley 2 1 2 Measure M Transit Projects Schedule Project

More information

Appendix L-1: Traffic Impact Analysis MOU

Appendix L-1: Traffic Impact Analysis MOU Appendix L-1: Traffic Impact Analysis MOU TRAFFIC STUDY - MEMORANDUM OF UNDERSTANDING (MOU) This MOU acknowledges that the traffic study for the following project will be prepared in accordance with the

More information

Purple Line Extension Section 1 Construction Community Meeting January 17, 2019

Purple Line Extension Section 1 Construction Community Meeting January 17, 2019 Purple Line Extension Section 1 Construction Community Meeting January 17, 2019 1 Agenda Section 1 MOW 64 Facility Project Construction Updates: Fossils Project-wide Tunneling Wilshire/Western Wilshire/La

More information

8/18/2014. Peoria Station Meeting. August 14, Project Update. Tina Jaquez RTD Aurora Line/I-225 Rail Public Information Manager

8/18/2014. Peoria Station Meeting. August 14, Project Update. Tina Jaquez RTD Aurora Line/I-225 Rail Public Information Manager Peoria Station Meeting August 14, 2014 1 Project Update Tina Jaquez RTD Aurora Line/I-225 Rail Public Information Manager 2 1 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles

More information

Community Open Houses November 29 December 7, 2017

Community Open Houses November 29 December 7, 2017 Community Open Houses November 29 December 7, 2017 1 Community Open House Agenda 6:00 PM Open House 6:30-7:30 PM Presentation and Q&A 7:30-8:00 PM Open House Resumes after the presentation and Q&A Thank

More information

engineering phase and during the procurement of design build contracts.

engineering phase and during the procurement of design build contracts. CONSIDERATION OF ALTERNATIVES Below-grade trench alignment along Aviation Boulevard, adjacent to LAX south runways. miles. MOS-Century would extend from the Metro Exposition Line to the Aviation/ Century

More information

COST ESTIMATES: Curb-Running

COST ESTIMATES: Curb-Running COST ESTIMATES: Curb-Running PROJECT FEASIBILITY COST ESTIMATE SUMMARY Geary Bus Rapid Transit Study Alternative: Side Lane (Curb Running) Date: 4/12/07 Percent Cost Total Project Capital Outlay I- Roadway

More information

East San Fernando Valley Transit Corridor. TAC Briefing December 4, 2013

East San Fernando Valley Transit Corridor. TAC Briefing December 4, 2013 East San Fernando Valley Transit Corridor TAC Briefing December 4, 2013 Overview Measure R Project Long Range Transportation Plan Reserves $170.1 Million 2018 Revenue Operations Date Coordination with

More information

Utility work, road construction substantially done on Fourth Street

Utility work, road construction substantially done on Fourth Street November 2010 Fourth Street in downtown is reopen to vehicle traffic between Minnesota and Broadway streets. Utility relocation and road construction are substantially complete there. Utility work, road

More information

III. CORRECTIONS AND ADDITIONS TO THE DRAFT EIR

III. CORRECTIONS AND ADDITIONS TO THE DRAFT EIR III. CORRECTIONS AND ADDITIONS TO THE DRAT EIR DRAT EIR I. INTRODUCTION/SUMMARY In response to Comment No. 2.1 on the Draft EIR, the following mitigation measure is added to Table I- 1, Summary of Environmental

More information

Sepulveda Pass Corridor Systems Planning Study Update

Sepulveda Pass Corridor Systems Planning Study Update Los Angeles County Metropolitan Transportation Authority Sepulveda Pass Corridor Systems Planning Study Update June 20, 2012 Measure R Transit Corridors One of 12 Measure R Transit Corridors approved by

More information

Draft Date: February 9, 2018 DRAFT RESOLUTION

Draft Date: February 9, 2018 DRAFT RESOLUTION Draft Date: February 9, 2018 DRAFT RESOLUTION A RESOLUTION OF THE COUNCIL OF THE CITY OF LOS ANGELES, CALIFORNIA, TO ADOPT FINDINGS PURSUANT TO THE MITIGATION FEE ACT, TO UPDATE TRANSPORTATION IMPACT FEES,

More information

We re using a giant machine to dig tunnels for trains.

We re using a giant machine to dig tunnels for trains. metro.net/crenshaw We re using a giant machine to dig tunnels for trains. crenshaw/lax transit project Tunnel Boring Machine Fun Facts #CrenshawTBM What is a Tunnel Boring Machine (TBM)? A TBM is like

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS B. TRAFFIC AND CIRCULATION

IV. ENVIRONMENTAL IMPACT ANALYSIS B. TRAFFIC AND CIRCULATION IV. ENVIRONMENTAL IMPACT ANALYSIS B. TRAFFIC AND CIRCULATION 1. INTRODUCTION This section is based on the technical report, Traffic Study for 10131 Constellation Boulevard Residential Project, prepared

More information

Elected Officials Briefing North Metro Rail Line Update. November 10, 2016

Elected Officials Briefing North Metro Rail Line Update. November 10, 2016 Elected Officials Briefing North Metro Rail Line Update November 10, 2016 Dave Genova, RTD General Manager and CEO Five lines opening in 2016 Flatiron Flyer, Jan. 3 University of Colorado A Line, April

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS N. TRANSPORTATION AND TRAFFIC

IV. ENVIRONMENTAL IMPACT ANALYSIS N. TRANSPORTATION AND TRAFFIC IV. ENVIRONMENTAL IMPACT ANALYSIS N. TRANSPORTATION AND TRAFFIC The following section summarizes the information provided in the traffic report entitled Traffic Impact Analysis for a Proposed Residential

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS J. TRANSPORTATION AND TRAFFIC

IV. ENVIRONMENTAL IMPACT ANALYSIS J. TRANSPORTATION AND TRAFFIC IV. ENVIRONMENTAL IMPACT ANALYSIS J. TRANSPORTATION AND TRAFFIC This Section summarizes the information provided in the Traffic Study for the Santa Monica College Bundy Campus Master Plan (Traffic Study),

More information

Countdown to the Closure Extended 53-Hour Closure of I-405 Freeway Between U.S. 101 and I-10 Planned in Mid-July for Mulholland Bridge Demolition

Countdown to the Closure Extended 53-Hour Closure of I-405 Freeway Between U.S. 101 and I-10 Planned in Mid-July for Mulholland Bridge Demolition Countdown to the Closure Extended 3-Hour Closure of I-40 Freeway Between U.S. 0 and I-0 Planned in Mid-July for Mulholland Bridge Demolition Work Los Angeles, Calif. Plan Ahead, Avoid The Area, Or Stay

More information

Federal Way Link Extension

Federal Way Link Extension Federal Way Link Extension Draft EIS Summary Route & station alternatives and impacts Link Light Rail System Map Lynnwood Mountlake Terrace Lynnwood Link Extension Shoreline 14th Northgate 40 Northgate

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item 44 Program Management Project Budget and Schedule Status Project Schedules* Project 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Expo Phase I Orange Line Extension I-405 Sepulveda

More information

Chief Capital Management Officer s Report

Chief Capital Management Officer s Report Item 40 Chief Capital Management Officer s Report Construction Committee April 15, 2010 1 Metro Gold Line Eastside Extension Project Update April 2010 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6

More information

50TH STREET CONCEPTUAL DESIGN

50TH STREET CONCEPTUAL DESIGN NUE NUE NUE 51 AVE REET 5.49 A-A SECTION 50TH STREET - STA 0+560 1.2 33.46 19.10 8.75 1.00 3.00 3.00 1.00 CN SPUR IF NECESSARY, GRADING ON PRIVATE TO BE BUS STOP 3697 IVE IVE BUS STOP 2279 4.25 REET REMOVE

More information

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018 NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3 April 19, 2018 NHHIP OVERVIEW NHHIP divided into 3 Segments: Segment 1: I-45: Beltway 8 to I-610 (9 mi) 45 Segment 2: I-45: I-610 to I-10 (3

More information

Clifton Corridor Transit Initiative. Briefing to Great Lakes Community February 11, 2016

Clifton Corridor Transit Initiative. Briefing to Great Lakes Community February 11, 2016 Clifton Corridor Transit Initiative Briefing to Great Lakes Community February 11, 2016 Neighborhood Concerns and Requests Provide a general overview and background of the project What are the different

More information

APTA RAIL CONFERENCE June 20, 2016

APTA RAIL CONFERENCE June 20, 2016 APTA RAIL CONFERENCE June 20, 2016 Hawaiian Islands Mainland Honolulu, Hawaii: Some of the Worst Traffic Congestion in the Nation Island of Oahu: 600-square miles Oahu s congestion ranked second in the

More information

I-225 Rail Line Iliff and Florida Stations Information Meeting

I-225 Rail Line Iliff and Florida Stations Information Meeting I-225 Rail Line Iliff and Florida Stations Information Meeting May 15, 2013 FasTracks and I-225 Rail Line Update Chuck Culig I-225 Rail Line Project Manager Chris Hinton I-225 Rail Line Deputy Project

More information

Crenshaw-Prairie Transit Corridor Study Public Meetings

Crenshaw-Prairie Transit Corridor Study Public Meetings Crenshaw-Prairie Transit Corridor Study Public Meetings Darby Park: Wednesday, February 20, 2008 6:30 8:00 PM US Bank Community Room: Thursday, February 21, 2008 6:30 8:00 PM Nate Holden Performing Arts

More information

2.4 Build Alternatives

2.4 Build Alternatives Table 2-1. Future Transit Network Changes between No Build and TSM Alternatives Operator Route Group No. Route ID and Description Peak Headway (min) No Build Off-peak Headway (min) Peak Headway (min) TSM

More information

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1 Executive Summary Introduction The Eastside Transit Corridor Phase 2 Project is a vital public transit infrastructure investment that would provide a transit connection to the existing Metro Gold Line

More information

Ravenswood Avenue Railroad Crossing Project City Council Meeting Study Session April 4, Ravenswood Avenue Railroad Crossing Project

Ravenswood Avenue Railroad Crossing Project City Council Meeting Study Session April 4, Ravenswood Avenue Railroad Crossing Project Ravenswood Avenue Railroad Crossing Project City Council Meeting Study Session April 4, 2017 1 Presentation Outline Project Background Review Current Alternatives City Council Requests Council Direction

More information

Aurora Line/I-225 Rail Project Update Public Meeting. June 4, 2014

Aurora Line/I-225 Rail Project Update Public Meeting. June 4, 2014 Aurora Line/I-225 Rail Project Update Public Meeting June 4, 2014 FasTracks and I-225 Rail Line Update Danielle Smith I-225 Rail Line Design/Build Coordination Manager 2 The RTD FasTracks Plan 122 miles

More information

Denver Metro Association of Realtors

Denver Metro Association of Realtors Denver Metro Association of Realtors North Metro Rail Line October 2, 2014 1 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new Park-n-Rides;

More information

Welcome. Please Sign In

Welcome. Please Sign In Welcome South Bay Bus Rapid Transit (BRT) Draft Environmental Impact Report (DEIR) Public Meeting Please Sign In Please comment in any of the following manners: 1. Submit a comment form 2. Provide verbal

More information

METRO Orange Line BRT American Boulevard Station Options

METRO Orange Line BRT American Boulevard Station Options METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN

More information

West Santa Ana Branch Transit Corridor. Informational Briefing Gateway Cities Service Council April 13, 2017

West Santa Ana Branch Transit Corridor. Informational Briefing Gateway Cities Service Council April 13, 2017 West Santa Ana Branch Transit Corridor Informational Briefing Gateway Cities Service Council April 13, 2017 Project Study Area 98 square miles 20 individual cities plus unincorporated LA County 1.2 million

More information

Mobility Management: Caltrain

Mobility Management: Caltrain Mobility Management: Caltrain Community Relations Committee October 4, 2017 Agenda Item 7 Presentation Outline Operating Statistics Ridership On-time Performance Fleet Reliability Capital Program Review

More information

Pomona Rotary December 19, 2017

Pomona Rotary December 19, 2017 Pomona Rotary December 19, 2017 Los Angeles County s population will grow by 5.9% to 10.7 million by 2024 During that same period, the San Gabriel Valley will grow by 7.6% to more than 1.5 million; taking

More information

Crenshaw/LAX Transit Corridor. Transit Coalition Meeting June 26, 2012

Crenshaw/LAX Transit Corridor. Transit Coalition Meeting June 26, 2012 Transit Coalition Meeting June 26, 2012 Measure R Projects 8 ½ mile light rail line from Exposition/Crenshaw Blvds. to Metro Green Line s Aviation/LAX station Six stations with two optional stations carried

More information

BIDDER'S PROPOSAL (continued) CITY OF BERKELEY BID PROPOSAL ITEM NO. A: BASE BID

BIDDER'S PROPOSAL (continued) CITY OF BERKELEY BID PROPOSAL ITEM NO. A: BASE BID SPECIFICATION 16-11031-C CITY OF BERKELEY BID PROPOSAL A: BASE BID 1 MOBILIZATION 1 LS 2 TRAFFIC CONTROL 1 LS 3 CONTRACTOR INFORMATION SIGN 2 EA 4 CONSTRUCTION AREA SIGN 18 EA 5 PROJECT IDENTIFICATION

More information

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives 3.0 What preliminary alternatives are being evaluated? The alternatives for the East San Fernando Valley Transit Corridor project that were considered for screening include the No Build Alternative, Transportation

More information

Purple Line Extension. Rodeo Station AUR MOA October 24, 2017

Purple Line Extension. Rodeo Station AUR MOA October 24, 2017 Purple Line Extension Rodeo Station AUR MOA October 24, 2017 1 Agenda Project Overview Section 2 Pre-Construction Updates Rodeo Drive Station Advance Utility Relocation (AUR) SCE Phase I, underway SCE

More information

Community Meetings Welcome

Community Meetings Welcome Community Meetings Welcome Thank you for joining us! Community Meetings Agenda 6pm Open House 6:30pm Welcome & Presentation 7pm Q&A 7:15pm Open House Resumes 8pm Meeting Concludes Community Meetings Agenda

More information

Clifton Corridor Transit Initiative. Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016

Clifton Corridor Transit Initiative. Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016 Clifton Corridor Transit Initiative Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016 Neighborhood Concerns and Requests Provide a general overview and background of the project

More information

Develop ground transportation improvements to make the Airport a multi-modal regional

Develop ground transportation improvements to make the Airport a multi-modal regional Project Overview TRANSPORTATION IMPROVEMENTS WHAT ARE THE PROJECT GOALS? Transportation transportation hub. Develop ground transportation improvements to make the Airport a multi-modal regional Land Use

More information

Metro Transit Update. Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office. John Dillery, Senior Transit Planner

Metro Transit Update. Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office. John Dillery, Senior Transit Planner Metro Transit Update Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office John Dillery, Senior Transit Planner Metro Transit Service Development May 16, 2013 1 Transit Planning

More information

Purple Line Extension, Section 2 Southern California Edison, Phase I

Purple Line Extension, Section 2 Southern California Edison, Phase I Purple Line Extension, Section 2 Southern California Edison, Phase I 1 Agenda Advance Utility Relocation (AUR) Schedule Southern California Edison (SCE) overview Street Impacts Sunday work: 10am-6pm Left

More information

Purple Line Extension, Section 2 Southern California Edison, Phase I June 7, 2017

Purple Line Extension, Section 2 Southern California Edison, Phase I June 7, 2017 Purple Line Extension, Section 2 Southern California Edison, Phase I June 7, 2017 Agenda Advance Utility Relocation (AUR) Schedule Southern California Edison (SCE) overview Street Impacts Sunday work:

More information

H/Benning Phase 2 Construction. December 17, 2012

H/Benning Phase 2 Construction. December 17, 2012 H/Benning Phase 2 Construction December 17, 2012 Agenda I. Construction Schedule II. Elements of Construction III. Policy and Enforcement IV. Ongoing Communication Construction Schedule Phase 1 (completed

More information

Why coordinate the Van Nuys and Sepulveda Pass project studies together?

Why coordinate the Van Nuys and Sepulveda Pass project studies together? Southern California's Leading Transit Advocacy Group P.O. Box 567 * San Fernando, CA 91341-0567 Voice: 818.362.7997 * Fax: 818.364.2508 www.transitcoalition.org The Transit Coalition (a project of LACBC)

More information

I-405 Sepulveda Pass Improvements Project

I-405 Sepulveda Pass Improvements Project I-405 Sepulveda Pass Improvements Project 26, 2012 Click to edit Master title January style Community Advisory Committee 1 Community Meeting Schedule for 2012 26-Jan CAC, Final Meeting Feb 22-Mar Community

More information

3.17 Energy Resources

3.17 Energy Resources 3.17 Energy Resources 3.17.1 Introduction This section characterizes energy resources, usage associated with the proposed Expo Phase 2 project, and the net energy demand associated with changes to the

More information

METRO Light Rail Update

METRO Light Rail Update American Society of Highway Engineers METRO Light Rail Update Brian Buchanan Director, Design and Construction October 13, 2009 1 High Capacity Transit System 2 20-Mile Light Rail Line 3 Operations Operations

More information

Traffic Engineering Study

Traffic Engineering Study Traffic Engineering Study Bellaire Boulevard Prepared For: International Management District Technical Services, Inc. Texas Registered Engineering Firm F-3580 November 2009 Executive Summary has been requested

More information

Landside Access Modernization Program (LAMP)

Landside Access Modernization Program (LAMP) Landside Access Modernization Program (LAMP) LAX Los Angeles International Airport is the 2 nd busiest airport in the United States and is the largest airport in California. Since the start of the economic

More information

IMPROVEMENT CONCEPTS

IMPROVEMENT CONCEPTS IMPROVEMENT CONCEPTS for the South Novato Transit Hub Study Prepared by: January 11, 2010 DKS Associates With Wilbur Smith Associates IMPROVEMENT CONCEPTS Chapter 1: Introduction 1. INTRODUCTION The strategic

More information

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE DOYLE DRIVE DOYLE DRIVE. Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE DOYLE DRIVE DOYLE DRIVE. Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009 DOYLE DRIVE Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009 Presentation Overview Introduction Project Acceleration Construction Contracts Construction Activities Lane and Road

More information

East San Fernando Valley Transit Corridor. Information Session, October 10, 2017

East San Fernando Valley Transit Corridor. Information Session, October 10, 2017 East San Fernando Valley Transit Corridor Information Session, October 10, 2017 1 Welcome and Meeting Purpose Introductions Metro Transit Corridors Planning Metro Real Estate Metro Community Relations

More information

SANTA MONICA VENICE MARINA DEL REY PLAYA VISTA WESTCHESTER EL SEGUNDO. Wilshire Arizona Santa Monica Blvd. 4th

SANTA MONICA VENICE MARINA DEL REY PLAYA VISTA WESTCHESTER EL SEGUNDO. Wilshire Arizona Santa Monica Blvd. 4th LINCOLN BLVD 4th F Wilshire Santa Monica Blvd SANTA MONICA not to scale E 5th 6th Santa Monica High School Olympic High School Lincoln Broadway California VENICE Pico Marina Pointe MARINA DEL REY Westchester

More information

Section III Transportation and Stormwater Projects Receiving Additional Funding Project Detail Sheets Alphabetical Listing by Project Name Five Year

Section III Transportation and Stormwater Projects Receiving Additional Funding Project Detail Sheets Alphabetical Listing by Project Name Five Year Section III Transportation and Stormwater Projects Receiving Additional Funding Project Detail Sheets Alphabetical Listing by Project Name Five Year Capital Improvement Plan FY2015/2016 through FY2020

More information

Business Advisory Committee. July 7, 2015

Business Advisory Committee. July 7, 2015 Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS L. TRAFFIC, TRANSPORTATION, AND PARKING

IV. ENVIRONMENTAL IMPACT ANALYSIS L. TRAFFIC, TRANSPORTATION, AND PARKING IV. NVIRONMNTAL IMPACT ANALYSIS L. TRAFFIC, TRANSPORTATION, AND PARKING INTRODUCTION The following summarizes the information provided in the traffic report prepared by Hirsch/Green Transportation Consulting,

More information

CITY OF BEVERLY HILLS STAFF REPORT

CITY OF BEVERLY HILLS STAFF REPORT Meeting Date: July 7, 2011 To: From: Subject: CITY OF BEVERLY HILLS STAFF REPORT Honorable Mayor & City Council Pamela Mottice Muller, Director of Emergency Management 405 Closure Attachments: 1. 1-405

More information

Business Advisory Committee. November 3, 2015

Business Advisory Committee. November 3, 2015 Business Advisory Committee November 3, 2015 1 Today s Topics DEIS Cost Estimate 2 Assumptions Revised Cost Estimate Revised Project Scope Cost Estimate Overview Position Statement Discussion Municipal

More information

Peninsula Corridor Electrification Update Meeting

Peninsula Corridor Electrification Update Meeting Peninsula Corridor Electrification Update Meeting Brisbane City Council September 6, 2018 Agenda Caltrain System Overview Project Overview Electric Multiple Unit (EMU) Design Brisbane Construction Activities

More information

SC Highway 41 Existing Conditions

SC Highway 41 Existing Conditions SC Highway 41 Existing Conditions Existing Typical Cross Section purposes only and does not replace the required NEPA process necessary for alignment The NEPA process is anticipated to begin in the next

More information

Purple Line Extension Updates on La Cienega and Rodeo Stations January 10, 2018

Purple Line Extension Updates on La Cienega and Rodeo Stations January 10, 2018 Purple Line Extension Updates on La Cienega and Rodeo Stations January 10, 2018 1 Agenda Project Overview Section 1 Construction Updates 2017 Accomplishments Wilshire/La Cienega Station Decking and Jet

More information

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015 Transportation Committee Revised Project Scope and Cost Estimate November 23, 2015 1 Today s Topics Revised Project Scope Revised Cost Estimate Municipal Approval Action 2 3 Revised Project Scope Project

More information

Sidewalk Working Group Update October 22, 2018

Sidewalk Working Group Update October 22, 2018 Sidewalk Working Group Update October 22, 2018 The Neighborhood Sidewalk Repair Program & The Sidewalk Gap Program Improving Mobility Freedom in Denver Neighborhood Sidewalk Repair Program: Repairing hazardous

More information

City of Houston Fondren Road Paving and Drainage

City of Houston Fondren Road Paving and Drainage City of Houston Fondren Road Paving and Drainage From Braeswood Boulevard to Creekbend Drive TRC Meeting March 2016 Location and Vicinity Maps City Council District K Key Map 530 Z, 530 Y Land Use Commercial

More information

Purple Line Extension Section 1 Construction Community Meeting April 19, 2018

Purple Line Extension Section 1 Construction Community Meeting April 19, 2018 Purple Line Extension Section 1 Construction Community Meeting April 19, 2018 1 Agenda Section 1 MOW 64 Facility Project Construction Updates: Wilshire/Western Wilshire/La Brea Wilshire/Fairfax Wilshire/La

More information

Mid-Coast Corridor Transit Project

Mid-Coast Corridor Transit Project San Diego Transportation Development Association Mid Coast Construction Update June 11, 2018 Mid-Coast Corridor Transit Project Mid-Coast Project 11-mile extension of Trolley Blue Line New LRT Infrastructure:

More information

STANDARD DRAWING INDEX

STANDARD DRAWING INDEX ATTACHMENT B STANDARD DRAWING INDEX DESCRIPTION EXISTING DRAWING NO. GENERAL Typical Layout for Improvement Plans City of Stockton Standard Border and Title Block for 8 1/2 x11 Sheet City of Stockton Standard

More information

Project Status Update January 2017

Project Status Update January 2017 Project Status Update January 2017 1 What is the Purple Line? A new 16 mile east-west light rail line Operates mostly on the surface with 21 stations Connects New Carrollton in Prince George s County and

More information

BART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010

BART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010 BART Silicon Valley Berryessa Extension Project Community Update October 27, 2010 1 Agenda Welcome and Introductions Program and Project Background Project Status Project and Station Details Current and

More information

Metro. Board Report. File #: , File Type:Informational Report

Metro. Board Report. File #: , File Type:Informational Report Metro Board Report Los Angeles County Metropolitan Transportation Authority One Gateway Plaza 3rd Floor Board Room Los Angeles, CA File #:2017-0407, File Type:Informational Report SYSTEM SAFETY, SECURITY

More information