ICT Strategic Transmission Expansion Plan (ISTEP) Report. ICT Planning

Size: px
Start display at page:

Download "ICT Strategic Transmission Expansion Plan (ISTEP) Report. ICT Planning"

Transcription

1 ICT Strategic Transmission Expansion Plan (ISTEP) Report ICT Planning PUBLISHED: 12/04/2007

2 Table of Contents Table of Contents...1 I. Executive Summary...2 II. Objectives...4 III. A. Improving Load-Serving Capability...4 B. Improving Inter-Regional Transfer Capability...4 C. Improving Load Pockets/Load Centers...4 D. Relieving Constraining Flowgates...4 System Overview...5 A. Current Issues on the Entergy Transmission System...5 IV. Study Assumptions...10 A. Modeling Assumptions...10 V. Proposed Upgrade Discussion...12 VI. VII. A. Overview of Proposed Upgrades...12 B. Amite South Upgrades...13 C. Acadiana Upgrades...16 D. Monroe Area 230 kv...20 E. Southeast Arkansas 230 kv...22 F. Ozarks EHV...24 G. South LA Bulk...28 H. Western Region...30 I. Northwest LA Bulk...32 J. South MS 230 kv...34 K. SOCO/SMEPA Interface Improvement...36 L. North LA 230 kv...38 M. Northshore 230 kv...40 N. North MS Bulk...41 O. Central Arkansas 230 kv...43 P. Brinkley East...47 Q. Central Arkansas Bulk...48 R. Jackson Area...50 S. Central MS Bulk...52 T. Short-term Project: McAdams Series Reactor...54 U. Short-term Project: Mt. Olive Hartburg Series Compensation...55 Summary...56 Next Steps...61 A. Stakeholder Input...61 B. Proposed Timeline...62 December 5,

3 I. Executive Summary On November 17, 2006 the ICT initiated its duties laid out in Attachment A of the ICT Agreement and further defined in Attachments S and T of Entergy s OATT. The ICT has developed the ICT Strategic Expansion Plan (ISTEP) recognizing that a long-term analysis is needed to encourage transmission expansion on the Entergy transmission system beyond the three-year window provided by Attachment T. Section 3.2 of Attachment T states: The ICT will assess whether a proposed upgrade should be considered a Base Plan Upgrade or Supplemental Upgrade. For purposes of this Section 3.2, the ICT will consider only upgrades in the then-current Base Plan for which construction is to be initiated within the next 3 years. The Attachment S language, relocated to Attachment K due to modifications imposed by FERC Order 890, provides additional guidance in the development of transmission expansion projects. Another duty of the ICT, as outlined in Section 14 of Entergy s proposed Attachment K, is that of identifying potential economic upgrades. Section 14 of Attachment K states: The ICT will identify such upgrades based on screening criteria, which may include considerations such as frequent transmission loading relief events, frequently constrained flowgates in the Available Flowgate Capability process or the Weekly Procurement Process (WPP), flowgates with high congestion costs as identified in the WPP process, and commonly invoked must-run operating guides. The projects identified in the ISTEP are proposed outside the scope of the ICT Base Plan. The expectation is that such facility upgrades will provide reliability and economic benefits to Entergy transmission system users. The ISTEP is not an evaluation Entergy Transmission System compliance with NERC Transmission Planning Standards, which allow for the use of operating guides, redispatch, breaker operation, or other mitigation plans. These mitigation plans have not been taken into account in this analysis. The 2015 Summer Peak Model is the basis for this analysis which will be further referred to as the ISTEP Phase 1. A primary purpose of this Plan is to promote EHV expansion on the Entergy transmission system by identifying problem areas and developing long-term strategic solutions. This first phase was developed using thermal and voltage analysis tools in PSS/E, MUST, and Powerworld software. Phase 1 of the ISTEP has been developed and is presented herein. The areas of focus in this first phase are the following: Improving Load-Serving Capability, Improving Inter- Regional Transfer Capability, Improving Load Pockets/Load Centers, and Relieving Constraining Flowgates. December 5,

4 Twenty ISTEP projects are presented in this report, with each consisting of one or more transmission system upgrades. These projects are grouped by geographic area, and focus on creating new, higher-voltage transmission in order to address system expansion and performance needs on the Entergy Transmission System, as opposed to upgrading the underlying lower-voltage systems. Because of the high-level nature of this Plan, no cost estimates or proposed in-service dates are provided in phase I. The ISTEP is being presented at a high-level in this document, with the intent that it will be further developed with the input from interested parties in the coming months. The ICT welcomes feedback from interested parties on this plan, and feedback mechanisms and timelines are discussed in Part VII of this report. December 5,

5 II. Objectives The ISTEP was created with several key objectives driving the projects that compose the Plan. Those objectives are: Improving Load-Serving Capability, Improving Inter- Regional Transfer Capability, Improving Load Pockets/Load Centers, and Relieving Constraining Flowgates. These objectives combine in order to provide a more robust transmission system that is capable of both reliable service and the economic delivery of power across the transmission system. Each objective is discussed in further detail below. A. Improving Load-Serving Capability The ISTEP projects are designed to enhance the reliability of the transmission system by improving its ability to serve load. The upgrades accomplish this task by providing increased voltage, increased thermal capacity, and additional paths from the generation to the load. B. Improving Inter-Regional Transfer Capability The Entergy Transmission System interfaces with 19 control areas, including both SERC and SPP members. The ISTEP includes projects that improve the ability to move power between Entergy and neighboring systems. C. Improving Load Pockets/Load Centers The Entergy Transmission System has several recognized load pockets. These are areas of high load, with limited local generation, and are dependent upon transmission lines in order to move power into the area. Several of the load pockets on the Entergy Transmission System have generation that is designated as must-run, dependent upon system conditions. One focus of the ISTEP is to increase the import capability into these load pockets, such that generation must-run requirements within those areas can be relaxed or removed improving reliability and economics. D. Relieving Constraining Flowgates Under certain system conditions, flowgates can become constrained during real-time operations. When this occurs, the ICT will institute congestion management procedures, often in the form of Transmission Loading Relief (TLR). TLR procedures have a number of levels, and can result in the curtailment of non-firm and/or firm transmission service. In addition to the operational issues, there are a number of flowgates that frequently constrain the sale of transmission service. The ISTEP includes upgrades that are intended to address some of the current most constraining flowgates, from both a TLR and a transmission service perspective. December 5,

6 III. System Overview A. Current Issues on the Entergy Transmission System 1. Operational Limitations TLR s are used to curtail transmission service and help prevent instability, uncontrolled separation, or cascading outages. NERC prescribes eight levels of TLR s. The higher the level of the TLR, the more critical the potential problem on the transmission system is. Actions taken by the ICT Reliability Coordinator on TLR s level one through four include curtailment or holding of Non-Firm transmission service. Reallocation, curtailment or holding of firm transmission service occurs when TLR s reach levels five or above. The ICT, as the Reliability Coordinator for the Entergy Transmission System, has called 213 TLRs, resulting in the curtailment of 340,181 MWh of Firm and Non Firm transmission service between January and October of A breakdown of the MWhs curtailed, by month, is displayed below in Table 1. Table 2 displays the number of TLR events, by level. Month (2007) Firm Non Firm Total Jan Feb Mar April May June July Aug Sept Oct Nov n/a n/a n/a Dec n/a n/a n/a Total 49, , ,181 Table 1 - TLR Monthly MWh Curtailed December 5,

7 Month (2007) Level One Level Two Level Three Level Four Level Five Jan Feb Mar April May June July Aug Sept Oct Nov n/a n/a n/a n/a n/a Dec n/a n/a n/a n/a n/a Total Table 2 - Total TLR Monthly Number of Events by Level December 5,

8 The 213 TLR events in 2007 were called on 37 flowgates. Those flowgates are listed below. Flowgate Description Adams Creek-Bogalusa3 230kV FTLO Adams Creek-Bogalusa2 Addis-Tiger 230kV for loss of Dow Meter Point-Air Liquid Tap 230kV Addis-Tiger 230kV FTLO BigCajun-Webre500kV Baxter Wilson-Ray Braswell FTLO Grand Gulf-Franklin Brookhaven-Wesson FTLO Grand Gulf-Baxter Wilson 500KV Byram-Terry 115KV FTLO Grand Gulf-Franklin 500KV Cecelia-Moril 138 kv for loss of Flanders-Hopkins 138 kv Coly-Vignes for loss of Willow Glen-Waterford Conway- Donaghey 161KV FTLO Pleasant Hills-Greenbrier 161KV El Dorado-Sheridan 500KV FTLO McNeil-Etta 500KV Fancy Auto 500/230kv (flo) McKnight-Coly 500kv Hartburg-Inland Orange 230 KV FTLO Hartburg-Cypress 500KV Hot Springs-Bismarck 115KV FTLO Dolet Hills-SWShreveport 345KV Hot Springs-Bismarck for loss of El Dorado-Longwood Keo - West Memphis 500kv (flo) Shelby - Dell 500kv Mabelvale-Bryant for the loss of Sheridan - El Dorado Mabelvale-Sheridan for loss of White Bluff-Sheridan Mabelvale - Bryant 115kv (flo) White Bluff Sheridan 500kv Mayflower-Morgan 115 ftlo Mayflower-Sylvan Hills 115 McAdams for loss of McAdams-Lakeover Meaux-Judice 138KV FTLO Flanders-Hopkins 138KV Morrilton East-Gleason 161 kv ftlo Pleasant Hills-Mayflower 500 kv Mt. Olive - Hartburg for the loss of Webre - Wells Nelson 500/230 XFMR T1 ftlo Hartburg-Cypress 500 kv Nelson-Lake Charles Bulk 138kV 1 FTLO Nelson-Lake Charles Bulk 138kV 2 Ray Braswell 500/115 AT1 FTLO Ray Braswell-Lakeover 500KV Richard - Colonial Academy 138 Russellville E-Russellville S 161kV FTLO ANO-FT. Smith 500kV Scott-Bonin 138 kv for loss of TJ Labbe-Bonin 230 kv Terrebonne-Greenwood for loss of Webre-Wells Thomas-Louisiana Station 138 kv ftlo Webre-Wells 500 kv White Bluff-KEO 500KV FTLO Sheridan-Mabelvale 500KV White Bluff-Keo 500KV FTLO Wrightsville-Keo 500KV White Bluff-Sheridan for loss of Mabelvale-Sheridan Wilbert-Livonia for loss of Webre-Wells Willow Glenn-Addis 138KV FTLO Webre-Wells 500KV Willow Glen AT2 500/230 (flo) Fancy AT1 500/230 Table 3 - Flowgates Having TLR Events Transfer Capability Limitations Short-term transmission service is evaluated through the Available Flowgate Capacity system, which determines what capacity is available on a select list of flowgates. There are a number of these flowgates which are more limiting to service than others. The table below illustrates which flowgates are most limiting to transmission service. This December 5,

9 list is based on AFC Logs from 10/1/06 to 10/1/07. A flowgate is counted as a limit if any time point of any Top 15 flowgate did not have the full capacity available. Flowgate # Flowgate Description SCBSEM_WLPNT 2304 Scott-Semere 138 Ftlo Wells-Pont Des Mouton 230 SCBSEM_PNTBO 2185 Scott-Semere 138 Ftlo Pont Des Mouton-Bonin 230 NRCSCB_WLPNT 1873 North Crowley-Scott 138 Ftlo Well-Pont Des Mouton 230 RAYBAX_GGFRA 1799 Baxter Wilson-Ray Braswell 500 Ftlo Grand Gulf-Franklin MCADXF_LAKOV 1565 McAdams 500/230 Ftlo McAdams-Lakeover 500 BONCEC_RICCO 1495 Bonin-Cecelia 138 Ftlo Richard-Colonial Academy 138 BONXF_FLNHPK 1388 Bonin 230/138 Ftlo Flanders-Hopkins 138 SCBBON_WLPNT 1075 Scott-Bonin 138 Ftlo Wells-Pont Des Mouton 230 Nelson-Lake Charles Bulk 138 #1 Ftlo Nelson-Lake Charles Bulk 138 #2 NELLC_NELLCB 1010 LASTHM_WEBWL 885 Thomas-La. Station 138 Ftlo Webre-Wells 500 DODDAN_HARMT 830 Dodson-Danville 115 Ftlo Mt. Olive-Hartburg 500 TBOGRN_WEBWL 694 Terrebonne-Greenwood Ftlo Webre-Wells 500 BONXF_RICSCB 692 Bonin 230/138 Ftlo Richard-Scott 138 SCBSEM_WELXF 655 Scott-Semere 138 Ftlo Wells 500/230 AMRN_TIECAPE 528 Export Limit For Amrn Interface GRIMTZ_WDN 514 Grimes-Mt. Zion 138 Ftlo Grimes-Walden 138 NCRSCB_RICHR 488 North Crowley-Scott 138 Ftlo Richard-Scott 138 MTOHTB_WEBWL 479 Mt. Olive-Hartburg 500 Ftlo Webre-Wells 500 WATGYP_WATGP 457 Waterford-Little Gypsy 230 #1 Ftlo Waterford-Little Gypsy 230 #2 CLYWIG_WGWAT 454 Coly-Vignes 230 Ftlo Willow Glen-Waterford 500 LEPA_TIECAPI 439 Import Limit For Lepa Interface AMRN_TIECAPI 425 Import Limit For Amrn Interface SCBSEM_BOCEC 409 Scott-Semere 138 Ftlo Bonin-Cecelia 138 LASTHM_WEBCJ 406 Thomas-La. Station 138 Ftlo Cajun-Webre 500 WHBSHE_MABEL 376 White Bluff-Sheridan Ftlo Mabelvale-Sheridan 500 MABSH_WBSH 338 Mablevale-Sheridan 500 Ftlo White Bluff-Sheridan LAKXF_RABLO 265 Lakeover115/500 Ftlo Lakeover-Ray Braswell 500 ELDAT1_MCNAT 260 El Dorado 500/115 Ftlo McNeil 500/115 HAYBLY_NMDEL 247 Hayti-Blytheville Interstate 161 Ftlo New Madrid-Dell 500 Table 4 - Limiting AFC Flowgates 3. Reliability Issues The base case used for ISTEP studies identified 235 lines that were overloaded under contingency conditions, and 414 buses that had low voltage under contingency conditions. The numbers above are not an indication Entergy Transmission System compliance with NERC Transmission Planning Standards, which allow for the use of operating December 5,

10 guides, redispatch, breaker operation, or other mitigation plans. These mitigation plans have not been taken into account in this analysis. 4. Must-Run Generation There are a number of load pockets on the Entergy Transmission System where the load cannot be served using a normal merit-order dispatch, due to transmission limitations. Under certain system conditions, generators within these load pockets must be run out of merit order to serve the load. These generators are designated as Reliability Must-Run (RMR) generation. The requirement for these units to generate out of merit-order can result in a higher cost for energy in the Entergy system. Projects are included in the ISTEP to reduce or remove must-run requirements; however, these projects are not specifically identified because information on RMR units has not been made publicly available. December 5,

11 IV. Study Assumptions A. Modeling Assumptions The 2015 Summer model was used as the starting point for ISTEP studies. Several additional dispatch scenarios were run in order to simulate system conditions that would cause a flowgate to show up as overloaded under contingency, that do not show up given the dispatch in the base case model. Upgrades from Entergy s Construction Plan were included in the model. There were no Base Plan upgrades included in the models. Those upgrades are listed below. Construction Plan (Approved) o Port Hudson 69 kv Bus Upgrade o Beaumont 69 kv Upgrades o Bluewater 69 kv capacitor bank o WESCO 230 kv Reconfiguration o Upgrade 138 kv Alchem Monochem o Hilltop 161 kv station o Winn 69 kv capacitor bank o Hanks Kolbs 230 kv Upgrade o Grimes Bus Reconfiguration o Sterlington Perryville CKT 2 o Ray Braswell 500/230 kv transformer #2 o Upgrade Monroe Walnut Grove 115 kv o Convert Amite Hammond 115 kv to 230 kv o McManus 69 kv capacitor bank o McComb 115 kv capacitor bank o Upgrade Liberty Gloster 115 kv o Senatobia capacitor bank o Expand 69 kv Calvert capacitor bank o North Bastrop 115 kv reconfiguration o Alliance - Happy Jack 115 kv o Amite South Phase II o Amite South Phase III o DSG Phase III o Coly Hammond 230 kv o Grambling Winnfield 230 kv o Madison Ridgeland 230 kv Construction Plan (Proposed) o Napoleonville 115 kv capacitor bank o Lawtag Jennings 69 kv upgrade o Cabot 500/115 kv station December 5,

12 o Sarepta 345/115 kv station o Upgrade Lafayette Holiday 69 kv o Upgrade Chlomal Lacassine 69 kv o Peters Rd. Oakville 230 kv o Oakville Alliance 230 kv o Horn Lake o Restore Patterson December 5,

13 V. Proposed Upgrade Discussion A. Overview of Proposed Upgrades The ISTEP upgrades include over 1400 miles of 500 kv lines, over 1000 miles of 230 kv lines, and over 50 transformers. The upgrades are presented in detail below, in groups by geographic region or project. Figure 1, below shows all of the upgrades included in the ISTEP. 500 kv line 345 kv line 230 kv line Transformer Figure 1 - ISTEP Upgrade Overview December 5,

14 B. Amite South Upgrades Figure 2 - Amite South Upgrades 1. Description The proposed Amite South upgrades include the creation of a 500 kv circuit around the New Orleans area. The proposed projects are listed below in Table 5. December 5,

15 Project Description Voltage Mileage Tap Daniel McKnight, loop into Bogalusa Convert Waterford 9 Mile 230 kv to 500 kv /230 kv transformer at 9 Mile 500/230 9 Mile Michoud 500 kv /230 kv transformer at Michoud 500/230 Michoud Bogalusa 500 kv nd 500/230 kv transformer at Bogalusa 500/230 Adams Creek Bogalusa CKT Table 5 - Amite South ISTEP Upgrades The upgrades include tapping the Daniel to McKnight 500 kv line near the Bogalusa substation, and building 22 miles of 500 kv line to tie Daniel to McKnight into Bogalusa. In order to facilitate the new connections at Bogalusa, an additional 500/230 kv transformer is needed, as well as another 230 kv line between Adams Creek and Bogalusa. The project also includes the conversion of the existing Waterford to 9 Mile line to 500 kv operation, terminating with a 500/230 kv transformer at 9 Mile. A new 500 kv line from 9 Mile to Michoud, along with a 500/230 kv transformer at Michoud is also included. To complete the circuit, a new 500 kv line from Bogalusa to Michoud would be built. 2. Project Selection The projects were selected to improve import capability into the Amite South and DSG load pockets, and to reduce generation requirements in the load pocket. A portion of Waterford 9 Mile is built to 500 kv, but the line is operated at 230 kv. 3. Alternatives Considered None 4. Benefits The Amite South projects result in an increase in import capability of approximately 1000 MW. This increase in import capability into the Amite South region could reduce the requirements to have generation online in the load pocket. December 5,

16 Without Amite South Upgrades With Amite South Upgrades Available Transfer Capability (Entergy - Amite South) Table 6 - Transfer Capability Results: Amite South Upgrades In addition to the enhancement in transfer capability, the upgrades provide relief on some of the flowgates listed below: Flowgate Type Flowgate Name AFC WATGYP_WATGP AFC CLYWIG_WGWAT TLR Coly-Vignes for loss of Willow Glen-Waterford Table 7 - Flowgates Relieved by Amite South Upgrades December 5,

17 C. Acadiana Upgrades Table 8 - Acadiana Upgrades 1. Description The Acadiana upgrade plan involves creating strong 230 kv connections to the south of the Acadiana Load Pocket. The proposed upgrades are listed below in Table 9. December 5,

18 Project Description Voltage Mileage Wells - Scott 230 kv Scott - Bonin 230 kv Scott - Sellers Rd. 230 kv Sellers Rd. - Meaux 230 kv Meaux 230/138 kv transformer 230/138 Sellers Rd. - Richard 230 kv Richard 500/230 kv transformer 500/230 Sellers Rd. - Moril 230 kv Moril 230/138 kv transformer 230/138 Reconfigure 138 kv lines near Bonin 138 Table 9 - Acadiana ISTEP Upgrades The proposed upgrades include construction of a new 230 kv line from Wells Scott, along with a new 230 kv switching station at Scott. The lines from Scott Bonin and Bonin Cecelia would be joined at a new 138 kv switching station near the Labbe station, with a single 138 kv line from Bonin to the new switching station. A new 230 kv line from Scott Bonin would be constructed. A second 230 kv station would be constructed between Scott and Meaux, named Sellers Rd. From Sellers Rd, lines would be built to Meaux, Moril, Richard and Scott. 2. Project Selection The Acadiana projects have been selected, based upon the results of discussions amongst Cleco, Entergy, Lafayette and the ICT. The projects were selected in order to provide increased reliability, such that the Acadiana Load Pocket would be secure for the loss of a generator and a transmission line. The projects are also intended to address the flowgates that have had TLRs called recently. 3. Alternatives Considered ICT Acadiana Plan Webre 500/230 kv transformer Webre Cecelia 230 kv line Wells Cecelia 230 kv line Cecelia Moril 230 kv line Upgrade Bonin Cecelia 138 kv line Upgrade Cecelia Moril 138 kv line Upgrade Moril Dubion 138 kv line Moril Leblanc 138 kv line December 5,

19 Cleco Richard and Wells Plan Build a new 230 kv Richard Substation (500/230 kv Auto) Build a new 230 kv Meaux Substation (230/138 kv Auto) Build a new 230 kv Moril Station (230/138 kv Auto) Build a new 230 kv Station Where the Habetz to Flanders and Judice to Meaux lines Cross (Sellers Rd) Build a new Richard to Andrew 230 kv line Build a new Sellers Rd to Meaux 230 kv line Build a new Sellers Rd to Moril 230 kv line Build a new Wells to Bonin 230 kv line Build a new Sellers Rd to Bonin 230 kv line Disconnect Scott - Bonin and Bonin - Cecelia from Bonin (Bonin Bypass) Add a second 230 Auto at Bonin (230/69 or 230/138) Add Capacitor Banks Cleco Richard and Webre Plan Build a new 230 kv Richard Substation (500/230 kv Auto) Build a new 230 kv Meaux Substation (230/138 kv Auto) Build a new 230 kv Moril Station (230/138 kv Auto) Build a new 230 kv Webre Station (500/230 kv Auto) Build a new 230 kv Station Where the Habetz to Flanders and Judice to Meaux lines Cross (Andrew) Build a new Richard to Andrew 230 kv line Build a new Andrew to Meaux 230 kv line Build a new Andrew to Moril 230 kv line Build a new Moril to Webre 230 kv line Build a new Andrew to Bonin 230 kv line Disconnect Scott - Bonin and Bonin - Cecelia from Bonin (Bonin Bypass) Add a second 230 Auto at Bonin (230/69 or 230/138) Add Capacitor Banks Wells Meaux Project Wells Scott 230 kv Scott Bonin 230 kv Scott Meaux 230 kv Reconfigure 138 kv lines near Bonin 4. Benefits The Acadiana ISTEP upgrade would result in improved load-serving capability for the Acadiana Load Pocket, ensuring that the load pocket could sustain the loss of a generating unit and a transmission line. December 5,

20 Transfer capability into the load pocket is also increased by over 700 MW. Available Transfer Capability (Entergy -> Acadiana Load Pocket) Without Acadiana Upgrades Table 10 - Transfer Capability Results: Acadiana Upgrades With Acadiana Upgrades In addition, this project addresses several flowgates that are constraining to transmission service, and have had TLRs issued on. The flowgates that are relieved by these upgrades are listed below. Flowgate Type Flowgate Name TLR Meaux-Judice 138KV FTLO Flanders-Hopkins 138KV TLR Cecelia-Moril 138 kv for loss of Flanders-Hopkins 138 kv TLR Scott-Bonin 138 kv for loss of TJ Labbe-Bonin 230 kv TLC Richard - Colonial Academy 138 AFC SCBSEM_WLPNT AFC SCBSEM_PNTBO AFC NRCSCB_WLPNT AFC RAYBAX_GGFRA AFC MCADXF_LAKOV AFC BONCEC_RICCO AFC BONXF_FLNHPK AFC SCBBON_WLPNT AFC BONXF_RICSCB AFC SCBSEM_WELXF AFC NCRSCB_RICHR AFC SCBSEM_BOCEC Table 11 - Flowgates Relieved by Acadiana Upgrades December 5,

21 D. Monroe Area 230 kv Figure 3 - Monroe Area 230 kv Upgrades 1. Description These upgrades constitute a 230 kv loop around the Monroe/West Monroe area. The upgrades are described below in Table 12. December 5,

22 Project Description Voltage Mileage Sterlington 500/230 kv transformer 500/230 Convert Sterlington - Drew to 230 kv Convert Drew - Cheniere to 230 kv Convert Cheniere - Riser to 230 kv Convert Riser - Frostkraft to 230 kv Frostkraft 230/115 kv transformer 230/115 Convert Frostkraft - Rilla to 230 kv Tap Frostkraft - Rilla at Buckhorn Buckhorn 230/69 kv transformer 230/69 Rilla 230/115 kv transformer 230/115 Convert Rilla Selman Field to 230 kv Convert Selman Field - Sterlington to 230 kv Selman Field 230/69 kv transformer 230/69 Grambling - Rilla 230 kv Table 12 - Monroe Area 230 kv ISTEP Upgrades Complete a 230 kv loop around Monroe/West Monroe by converting existing 115 kv lines to 230 kv operation. Tap Frostkraft Rilla where the line passes by the Buckhorn 69 kv station, and install a step-down transformer there. 2. Project Selection Projects are driven by potential low voltage in the Monroe area with limited generation resources online. Several of the lines included in the upgrade package are built to 230 kv, but operated at 115 kv. The Grambling Rilla line was selected in order to have a secondary source to the 230 kv network constructed. 3. Alternatives Considered None 4. Benefits These projects provide an improvement to load-serving capability in the local area in the form of additional voltage support, in addition to reducing loading on the Sterlington 500/115 kv transformers. December 5,

23 E. Southeast Arkansas 230 kv Figure 4 - Southeast Arkansas 230 kv Upgrades 1. Description This project consists of the conversion of a 115 kv circuit in Southeast Arkansas to 230 kv operations. The upgrades are listed below in Table 13. Project Description Voltage Mileage Convert Woodward - Pinebergen - Glendale Monticello E. to 230 kv Monticello E. 230/115 kv transformer 230/115 Convert Monticello E. - Lacey - Crossett Crossroad - Crosset N. to 230 kv Convert Crosset N. - Hamburg - Mist - Montrose - Montrose E. - Bagby to 230 kv Table 13 - Southeast Arkansas 230 kv ISTEP Upgrades December 5,

24 The project involves the conversion of a 115 kv circuit from Woodward, through Monticello to Bagby to 230 kv operation. 2. Project Selection Projects were selected to provide improved load-serving capability. These lines were selected due to the lines being constructed for 230 kv, but operated at 115 kv. 3. Alternatives Considered Build a parallel 230 kv circuit from Woodward to Monticello to Bagby 4. Benefits The upgrades provide some relief to loading, as well as an increase in voltage in the local area, contributing to improved load-serving capability in the area. December 5,

25 F. Ozarks EHV Figure 5 - Ozarks EHV Upgrades 1. Description This set of projects would create a new 500 kv network, supporting the Ozarks region of Northwest Arkansas and Southwest Missouri. The upgrades are listed below in Table 14. December 5,

26 Project Description Voltage Mileage McNeil Couch 500 kv Couch 500/115 kv transformer 500/115 Couch - NW Texarkana 500 kv NW Texarkana - Ft. Smith 500 kv Ft. Smith Flint Creek 500 kv Flint Creek 500/ /161 Flint Creek - Table Rock 500 kv Table Rock 500/ /161 Table Rock - ISES 500 kv Brookline - Table Rock 500 kv Brookline 500/ /345 Lacygne - Brookline 500 kv Lacygne 500/ /345 Table 14 - Ozarks EHV ISTEP Upgrades Create a 500 kv circuit that connects from McNeil through NW Texarkana, to Ft. Smith, to Flint Creek, to Table Rock, and onto ISES. The project also includes several lines in the SPP region, bringing a 500 kv line down from LaCygne to Brookline to Table Rock. 2. Project Selection These projects were originally proposed in the SPP EHV Overlay study. They are included here due to the benefits in transfer capability between the Entergy and SPP systems. 3. Alternatives Considered SPP Ozark Study Option A o ANO - S Fayetteville 500kV o E Centerton - Osage Creek - S Fayetteville - Chamber Springs 345kV o Flint Creek - Chouteau 345kV o GRDA1 - Flint Creek 345kV rating increase o Tontitown - Elm Springs 161kV rating increase o Tontitown - Dyess 161kV rating increase o Clarksville - Chamber Springs 345kV increase CT o Chamber Springs - Tontitown 161kV Reconductor o Flint Creek - Chamber Springs 345kV o Flint Creek - E Centerton 161kV Reconductor o S Fayetteville to E Fayetteville 161kV o Chamber Springs - Farmington 161kV Reconductor o Neosho SPA - Neosho EDME 161kV Reconductor o Monett 345/161kV Transformer o Monett - Chesapeak 161kV o Compton 161kV Tie o Compton Tie - Table Rock 161kV Reconductor December 5,

27 o Omaha 161kV Tie o Huben 345/161kV Transformer o Willow Springs - Mansfield 161kV o Norfork - Midway 161kV Reconductor o Hilltop Mountain View 161kV o Batesville N - ISES 161kV Reconductor o Searcy Price 500/161kV Transformer o Searcy Price 161/115kV Transformer o Datto 161kV Tie o Corning - TX Eastern 8 115kV Reconductor o Gobbler Knob 161kV Tie o Green Forest - Gobbler Knob 161kV Reconductor o Asherville - Idalia 161kV Reconductor o Jonesboro 500/161kV Transformer o Jonesboro - Jonesboro SPA 161kV Rebuild o Jonesboro - Hergett 161kV Reconductor o Harrisburg Tap - Truman 161kV Reconductor o Batesville 161kV Tie o Brookline - Summit - Table Rock - Osage Creek 500kV o Table Rock - Bull Shoals - Norfork - Independence 500kV SPP Ozark Study Option B o ANO - S Fayetteville 500kV o E Centerton - Osage Creek - S Fayetteville - Chamber Springs 345kV o Flint Creek - Chouteau 345kV o GRDA1 - Flint Creek 345kV rating increase o Tontitown - Elm Springs 161kV rating increase o Tontitown - Dyess 161kV rating increase o Clarksville - Chamber Springs 345kV increase CT o Chamber Springs - Tontitown 161kV Reconductor o Flint Creek - Chamber Springs 345kV o Flint Creek - E Centerton 161kV Reconductor o S Fayetteville to E Fayetteville 161kV o Chamber Springs - Farmington 161kV Reconductor o Neosho SPA - Neosho EDME 161kV Reconductor o Monett 345/161kV Transformer o Monett - Chesapeak 161kV o Compton 161kV Tie o Compton Tie - Table Rock 161kV Reconductor o Omaha 161kV Tie o Huben 345/161kV Transformer o Willow Springs - Mansfield 161kV o Norfork - Midway 161kV Reconductor o Hilltop Mountain View 161kV o Batesville N - ISES 161kV Reconductor o Searcy Price 500/161kV Transformer o Searcy Price 161/115kV Transformer December 5,

28 o Datto 161kV Tie o Corning - TX Eastern 8 115kV Reconductor o Gobbler Knob 161kV Tie o Green Forest - Gobbler Knob 161kV Reconductor o Asherville - Idalia 161kV Reconductor o Jonesboro 500/161kV Transformer o Jonesboro - Jonesboro SPA 161kV Rebuild o Jonesboro - Hergett 161kV Reconductor o Harrisburg Tap - Truman 161kV Reconductor o Batesville 161kV Tie o Brookline - Summit - Table Rock - Osage Creek 345kV o Table Rock - Bull Shoals - Norfork - Thayer - Gobbler Knob 345kV o E Centerton - Tontitown 161kV o Asherville - Poplar Bluff 161kV Reconductor o Heber Springs N - Pangburn 161kV 4. Benefits The Ozarks EHV project provides an improvement in transfer capability between the Entergy and SPP systems. It also provides additional support to a rapidly growing Northwest Arkansas region. Without Ozarks Upgrades With Ozarks Upgrades Transfer From Transfer To Available Transfer Capability Available Transfer Capability Entergy AECI Entergy AEPW Entergy EMDE Entergy OKGE 0 97 Entergy SWPA 0 44 Entergy TVA AECI Entergy AEPW Entergy 0 0 EMDE Entergy LAFA Entergy OKGE Entergy SMEPA Entergy SWPA Entergy Table 15 - Transfer Capability Results: Ozarks Upgrades December 5,

29 G. South LA Bulk Figure 6 - South LA Bulk Upgrades 1. Description Table 16, below, lists the upgrades included in the South LA Bulk project. Project Description Voltage Mileage Fancy Point Hartburg 500 kv Table 16 - South LA Bulk ISTEP Upgrades This upgrade consists of building a new 500 kv line from Fancy Point Hartburg 500 kv. 2. Project Selection This project was selected in order to address several constraining flowgates, notably Webre Wells and Mt. Olive - Hartburg. 3. Alternatives Considered Fancy Point Richard McKnight Hartburg ICT Acadiana Project Cleco Richard and Webre Plan December 5,

30 4. Benefits The South LA Bulk project provides additional import capability into the WOTAB region of the Entergy Transmission System. The project should provide relief on several flowgates that are limiting to transfer capability and have TLRs called on them; those flowgates are listed below. Flowgate Type Flowgate Name AFC LASTHM_WEBWL AFC DODDAN_HARMT AFC TBOGRN_WEBWL AFC LASTHM_WEBCJ TLR Wilbert-Livonia for loss of Webre-Wells TLR Mt. Olive - Hartburg for the loss of Webre - Wells TLR Thomas-Louisiana Station 138 kv ftlo Webre-Wells 500 TLR Terrebonne-Greenwood for loss of Webre-Wells TLR Willow Glenn-Addis 138KV FTLO Webre-Wells 500KV Table 17 - Flowgates Relieved by South LA Bulk Upgrades December 5,

31 H. Western Region Figure 7 - Western Region Upgrades 1. Description The Western Region project consists of a 500 kv loop into Western Region, in addition to the strengthening of ties from the West. The upgrades included in this project are presented below in Table 18. Project Description Voltage Mileage Cypress Lewis Creek 500 kv /138 kv transformer at Lewis Creek 500/138 Hartburg Sabine 500 kv /230 kv transformer at Sabine 500/230 Sabine Porter 500 kv /230 kv transformer at Porter 500/230 Porter Lewis Creek 500 kv Lewis Creek Grimes 500 kv Grimes 500/138 transformer 500/138 Porter - Goslin 230 kv Goslin 230/138 kv transformer 230/138 Tap Crockett - Grimes near Rivtrin (Quarry) 345 Quarry - Rivtrin 345 kv /138 kv transformer at Rivtrin 345/138 Table 18 - Western Region ISTEP Upgrades December 5,

32 The upgrades include extending 500 kv from Cypress to Lewis Creek, through Porter, to Sabine, and returning to Hartburg. In addition to these lines, a 500 kv line from Grimes to Lewis Creek is included. Additionally, bringing a 345 kv line into Rivtrin, by tapping the Crockett Grimes 345 kv line is included. 2. Project Selection The projects are based on Entergy Western Region expansion plans, and then modifying and increasing the capacity of those upgrades. The projects are focused on providing additional import capability into Western Region. 3. Alternatives Considered Entergy Western Region Phase III, IIIA, IV Western Region Phase III o Convert Jacinto Lewis Creek to 230 kv o Build a 230 kv line from Cypress Jacinto o Add a 230/138 kv Auto at Lewis Creek Western Region Phase IIIA o Tap Grimes Crockett 345 kv near Rivtrin (Quarry) o Quarry Rivtrin 345 kv o Add a 345/138 kv transformer at Rivtrin Western Region Phase IV o Build a 230 kv line from Lewis Creek - Porter 4. Benefits This project results in increased transfer capability into Western Region. In addition to the increase in transfer capability, line loadings are reduced, and voltage is improved in the area. Available Transfer Capability (Entergy -> Western Region) Without Western Region Upgrades With Western Region Upgrades Table 19 - Transfer Capability Results: Western Region Upgrades December 5,

33 I. Northwest LA Bulk Figure 8 - Northwest LA Bulk Upgrades 1. Description This project involves the construction of one new 500 kv line, one 345 kv line, and installing a new step-down station. Details are below in Table 20. Project Description Voltage Mileage Sarepta - Dolet Hills 345 kv Sterlington - Mt. Olive 500 kv Messick Tap 500 Messick 500/230 kv transformer 500/230 Table 20 - Northwest LA Bulk ISTEP Upgrades Entergy s Construction Plan includes tapping El Dorado Longwood 345 kv at Sarepta, and installing a 345/115 kv transformer. This project builds from that, and includes a 345 kv line south to Dolet Hills from Sarepta. Also included is a 500 kv line from Sterlington Mt. Olive. The last portion of the project is to tap Mt. Olive Hartburg near Messick, and install a 500/230 kv transformer. December 5,

34 2. Project Selection The Messick project was selected in order to improve transfer capability between Entergy and Cleco, and also to help relieve the stability limitations on Mt. Olive Hartburg, by splitting the line into smaller sections. The Sarepta Dolet hills line was selected in order to improve transfer capability between Entergy and Cleco, and to enhance an existing Construction Plan project. Installing a Mt. Olive Sterlington 500 kv line was chosen in order to improve transfer capability into the WOTAB Region. 3. Alternatives Considered McNeil Sarepta 500 kv Sarepta Messick 345 kv 4. Benefits This project should relax the stability limitations on the Mt. Olive Hartburg line by effectively shortening the line. Interface capacity between Entergy, Cleco and AEP is also improved. The projects also address several flowgates related to transfer capability and TLRs. Those flowgates are listed below. Flowgate Type AFC AFC TLR Flowgate Name DODDAN_HARMT MTOHTB_WEBWL Mt. Olive - Hartburg for the loss of Webre - Wells Table 21 - Flowgates Relieved by North LA Upgrades December 5,

35 J. South MS 230 kv Figure 9 - South MS 230 kv Upgrades 1. Description The South MS 230 kv project involves the construction of a 230 kv line parallel to the existing 115 kv line between Jackson and Amite. The upgrades are listed below in Table 22. December 5,

36 Project Description Voltage Mileage Ray Braswell - Terry 230 kv Terry 230/115 kv transformer 230/115 Terry - Brookhaven 230 kv Brookhaven - Franklin 230 kv Brookhaven 230/115 kv transformer 230/115 McComb - Amite 230 kv Natchez Ind. Franklin 230 kv Natchez Ind. 230/115 kv transformer 230/115 Franklin 500/230 kv transformer 500/230 Franklin - McComb 230 kv McComb 230/115 kv transformer 230/115 Table 22 - South MS 230 ISTEP Upgrades The project includes a new 230 kv line from Ray Braswell to Terry, continuing to Brookhaven. A new 230 kv line from Franklin into McComb substation is included, as well as a line between Franklin and Natchez Industrial. 2. Project Selection Projects were selected in order to improve load-serving capability in the local area. 3. Alternatives Considered Jackson South Terry 230 kv 4. Benefits This project provides improved load-serving capability to the region, by improving voltage, and reducing overloads in the area. The project also addresses several flowgates associated with transmission service and TLRs. Those flowgates are listed below. Flowgate Type TLR TLR Flowgate Name Brookhaven-Wesson FTLO Grand Gulf-Baxter Wilson 500KV Byram-Terry 115KV FTLO Grand Gulf-Franklin 500KV Table 23 - Flowgates Relieved by South MS Projects December 5,

37 K. SOCO/SMEPA Interface Improvement Figure 10 - SOCO/SMEPA Interface Improvement Upgrades 1. Description This project consists of two new 230 kv lines to tie with the Southern/SMEPA systems. Project Description Voltage Mileage Rankin - Magee 230 kv Magee 230/115 kv transformer 230/115 Magee - Hattiesburg 230 kv Brookhaven - Magee 230 kv Table 24 - SOCO/SMEPA Interface Improvement ISTEP Upgrades 2. Project Selection Southern Company s Regional Planning Stakeholders Group (RPSG) recommended the construction of a Rankin Sweatt 230 kv and Rankin Hattiesburg 230 kv in order to improve transfer capability between Southern and Entergy. These projects were selected as a modification of the Southern proposal. December 5,

38 3. Alternatives Considered Rankin Sweatt 230 kv Rankin Hattiesburg 230 kv 4. Benefits These upgrades tie in with the South MS 230 kv ISTEP upgrades, and improve the transfer capability between Southern, SMEPA and Entergy. Without SOCO/SMEPA Upgrades With SOCO/SMEPA Upgrades Available Transfer Capability (Entergy - SOCO) Available Transfer Capability (Entergy - SMEPA) Table 25 - Transfer Capability Results: SOCO/SMEPA Upgrades December 5,

39 L. North LA 230 kv Figure 11 - North LA 230 kv Upgrades 1. Description This project consists of the conversion of several 115 kv lines in North Louisiana, and one new 230 kv line. Details are below Table 26. December 5,

40 Project Description Voltage Mileage Convert Natchez Industrial - Plantation - S. Ferriday - Red Gum 115kV to 230kV Plantation 230/115kV transformer 230/115 S. Ferriday 230/115kV transformer 230/115 Red Gum 230/115kV transformer 230/115 Convert Winnfield - Standard to 230kV /115kV transformer at Standard 230/115 Convert Standard - Red Gum to 230 kv Tap Baxter Wilson - Perryville at Tallulah Tallulah 500/115 kv transformer 500/115 Red Gum - Tallulah 230kV Tallulah 500/230 kv transformer 500/230 Table 26 - North LA 230 ISTEP Upgrades This project involves the conversion of existing 115 kv lines from Winnfield, through Red Gum, to Natchez to 230 kv. Also included is a tapping Baxter Wilson Perryville 500 kv line at Tallulah, and building a new 230 kv line from Tallulah to Red Gum. 2. Project Selection These projects are driven by improving load-serving capability in the local area. Some of the lines included in this project are built to 230 kv, but operated at 115 kv. 3. Alternatives Considered Red Gum Natchez SES 230 Grand Gulf Natchez SES 500 kv 4. Benefits This project provides an enhancement to improving load-serving capability in the local area. December 5,

41 M. Northshore 230 kv Figure 12 - Northshore 230 kv Upgrades 1. Description This project consists of the conversion of existing 115 kv lines to 230 kv. Project details are below in Table 27. Project Description Voltage Mileage Convert Amite - Chicken Farm - Franklinton - Bogalusa to 230kV Franklinton 230/115 kv transformer 230/115 Table 27 - Northshore 230 kv ISTEP Upgrades 2. Project Selection Projects were selected to improve load-serving capability in the local area. 3. Alternatives Considered None 4. Benefits This project provides an improvement to load-serving capability in the local area. December 5,

42 N. North MS Bulk Figure 13 - North MS Bulk Upgrades December 5,

43 1. Description This project consists of a new 500 kv line from Freeport to McAdams. Details of the upgrades included are presented in Table 28. Project Description Voltage Mileage Freeport - Batesville 500kV Batesville 500/115 kv transformer 500/115 Tillatoba - Batesville 500 kv Tillatoba 500/230kV transformer 500/230 Tillatoba - McAdams 500 kv Indianola - Moon Lake 230kV Tap Indianola - Tillatoba 230, bring into Greenwood Greenwood 230/115 kv transformer 230/115 Table 28 - North MS Bulk ISTEP Upgrades 2. Project Selection The projects were selected primarily to relieve issues with flowgates on the Entergy TVA interface, particularly the McAdams 500/230 kv transformer. The addition of the 230 kv line to Greenwood is designed to provide improved load-serving capability in the local area. 3. Alternatives Considered Batesville Ritchie 500 kv 4. Benefits This project results in an improvement in transfer capability between the Entergy and TVA systems. Also, with these upgrades in place, a reduction in post-contingent loading is seen on the 500/230 kv transformer at McAdams. Without North MS Upgrades With North MS Upgrades Available Transfer Capability (Entergy -> TVA) Table 29 - Transfer Capability Results: North MS Bulk December 5,

44 O. Central Arkansas 230 kv Figure 14 - Central Arkansas 230: Conway Upgrades Figure 15 - Central Arkansas 230: Little Rock Upgrades December 5,

45 Figure 16 - Central Arkansas 230: Hot Springs Upgrades 1. Description This project involves the creation of new 230 kv networks in the cities of Conway, Little Rock, and Hot Springs in Arkansas. Details for the upgrades for Conway are below in Table 30, for Little Rock in Table 31, and Hot Springs in Table 32. Project Description Voltage Mileage Cabot 500/230 kv transformer 500/230 Cabot - Gold Creek 230 kv Gold Creek 230/115 kv transformer 230/115 Gold Creek - Conway Ind. 230 kv Conway Ind. 230/115 kv transformer 230/115 Conway Ind. - Conway W. 230 kv Conway W. 230/115 kv 230/115 Tap Mayflower - Pleasant Hill Near Gleason Gleason 500/230 kv 500/230 Gleason - Conway W. 230 kv Table 30 - Central Arkansas 230 kv: Conway ISTEP Upgrades December 5,

46 Project Description Voltage Mileage Wrightsville 500/230 kv transformer 500/230 Mabelvale 500/230 kv transformer 500/230 Wrightsville - Little Rock South 230 kv Little Rock South 230/115 kv transformer 230/115 Convert Little Rock South - Rock Creek to 230 kv Convert LR Rock Creek - LR Boyle to 230 kv Convert LR Boyle - LR West to 230 kv Convert LR West - LR Markham to 230 kv Convert LR Markham - Kanis to 230 kv Kanis 230/115 kv transformer 230/115 Kanis - Mabelvale 230 kv Convert LR West - LR 8th & Woodrow to 230 kv Convert LR 8 th & Woodrow - LR Gaines to 230 kv LR Gaines 230/ /115 Table 31 - Central Arkansas 230 kv: Little Rock ISTEP Upgrades Project Description Voltage Mileage Cheetah 230/115 kv transformer 230/115 Mablevale - Cheetah 230 kv Cheetah - Mt. Pine South Mt. Pine South - Carpenter 230 kv Carpenter 230/115 kv transformer 230/115 Carpenter - Hot Springs EHV 230 kv Hot Springs EHV 500/230 kv transformer 500/230 Hot Springs - Cheetah 230 kv Mt. Pine South 230/115 kv transformer 230/115 Table 32 - Central Arkansas 230 kv: Hot Springs ISTEP Upgrades 2. Project Selection These projects were selected in order to provide improved load-serving capability to these load centers in Central Arkansas. Additionally, the upgrades near Conway were selected in order to reduce TLR events on Morrilton East Gleason and Pleasant Hill Greenbrier. 3. Alternatives Considered Tapping Mablevale Mayflower at Pinnacle, install 500/115 kv transformer Mabelvale LR South 500 kv Cabot Mayflower 500 kv December 5,

47 4. Benefits The upgrades result in reductions in loading and increased voltage in the Little Rock, Conway, and Hot Springs. The upgrades should also result in a reduction in TLRs on Morrliton East Gleason. Flowgate Type TLR TLR Flowgate Name Morrilton East-Gleason 161 kv ftlo Pleasant Hills-Mayflower 500 kv Conway- Donaghey 161KV FTLO Pleasant Hills-Greenbrier 161KV Table 33 - Flowgates Relieved by Central Arkansas 230 Upgrades December 5,

48 P. Brinkley East Figure 17 - Brinkley East Upgrades 1. Description The Brinkley East project involves tapping West Memphis Keo near Brinkley East, and installing a 500/230 kv transformer. Details are below in Table 34. Project Description Voltage Mileage Tap Keo - West Memphis at Brinkley East /230 kv transformer at Brinkley East 500/230 Table 34 - Brinkley East ISTEP Upgrades 2. Project Selection The project was selected to provide an improvement to load-serving capability in the local area. 3. Alternatives Considered Tap Keo West Memphis 500 kv at Moses 4. Benefits This project provides an improvement to load-serving capability in the local area. December 5,

49 Q. Central Arkansas Bulk Figure 18 - Central Arkansas Bulk Upgrades 1. Description This project involves the construction of a new 500 kv line between Wrightsville White Bluff. Details are below in Table 35. Project Description Voltage Mileage Wrightsville - White Bluff 500 kv Table 35 - Central Arkansas Bulk ISTEP Upgrades 2. Project Selection This project was selected in order to address TLR issues on the White Bluff Keo and Sheridan Mabelvale flowgates. 3. Alternatives Considered White Bluff Mabelvale 500 kv 4. Benefits This project will reduce TLR events, and increase AFC on several flowgates, as well as increasing transfer capability to other systems. The increase in transfer capability is shown below. December 5,

50 Without Central AR Upgrades With Central AR Upgrades Available Transfer Capability (Entergy - TVA) Available Transfer Capability (Entergy - AMRN) Table 36 - Transfer Capability Results: Central Arkansas Upgrades The flowgates that are relieved by this project are below. Flowgate Type Flowgate Name AFC WHBSHE_MABEL AFC MABSH_WBSH TLR White Bluff-KEO 500KV FTLO Sheridan-Mabelvale 500KV TLR White Bluff-Keo 500KV FTLO Wrightsville-Keo 500KV TLR White Bluff-Sheridan for loss of Mabelvale-Sheridan TLR Mabelvale-Sheridan for loss of White Bluff-Sheridan Table 37 - Flowgates Relieved by Central Arkansas Bulk Upgrades December 5,

51 R. Jackson Area Figure 19 - Jackson Area Upgrades 1. Description These projects involve building a new 230 kv switching station and 230 kv line North of Jackson, MS. Project Description Voltage Mileage Tap Lakeover - McAdams, where it crosses Pickens Canton 500 Tap station 500/230 kv transformer 500/230 Bozeman - Lakeover 230 kv Table 38 - Jackson Area ISTEP Upgrades December 5,

52 2. Project Selection These projects were selected in order to improve load-serving capability in the local area, and to reduce TLR events on McAdams Lakeover. 3. Alternatives Considered McAdams Pickens 500 kv 500/230 kv transformer at Attala 4. Benefits These projects provide an improvement to load-serving capability in the local area. TLR events would be reduced on the McAdams 500/230 kv transformer. December 5,

53 S. Central MS Bulk Figure 20 - Central MS Bulk Upgrades 1. Description The Central MS Bulk project is the construction of a new 500 kv line from Ray Braswell Grand Gulf. Details are below in Table 39. Project Description Voltage Mileage Ray Braswell - Grand Gulf 500 kv Table 39 - Central MS Bulk ISTEP Upgrades 2. Project Selection Projects were selected in order to improve transfer capability on the Entergy Transmission System. 3. Alternatives Considered Grand Gulf Natchez SES 500 kv Natchez SES Fancy Point 500 kv December 5,

54 4. Benefits The benefits from this project include improved internal transfer capability. Flowgates relieved by this project are listed below. Flowgate Type TLR TLR Flowgate Name Ray Braswell 500/115 AT1 FTLO Ray Braswell-Lakeover 500KV RAYBAX_GGFRA Table 40 - Flowgates Relieved by Central MS Bulk Upgrades December 5,

ICT Strategic Transmission Plan (ISTEP) Review and Status Update

ICT Strategic Transmission Plan (ISTEP) Review and Status Update ICT Strategic Transmission Plan (ISTEP) Review and Status Update Entergy Transmission Summit July 29, 2008 Astor Crown Plaza New Orleans, Louisiana Douglas Bowman, PE Lead Engineer, ICT Planning 501-688-1640

More information

SPP Reliability Coordinator TLR 5 Analysis Report for the ICT Reliability Area

SPP Reliability Coordinator TLR 5 Analysis Report for the ICT Reliability Area SPP Reliability Coordinator TLR 5 Analysis Report for the ICT Reliability Area MAINTAINED BY SPP Reliability Coordinator PUBLISHED: 10/11/2010 LATEST REVISION: 10/12/2010 Copyright 2010 by Southwest Power

More information

1. Administrative Items... SPP. 2. Stakeholder Web-Presentation... ABB

1. Administrative Items... SPP. 2. Stakeholder Web-Presentation... ABB Southwest Power Pool, Inc. ENTERGY REGIONAL STATE COMMITTEE MINIMIZING BULK POWER COSTS STUDY STAKEHOLDER MEETING Face-to-face & Web-conference Hyatt Regency DFW DFW Airport, TX Room: Maverick AGENDA July

More information

Market Congestion Planning Study (South)- Robustness Analysis. Economic Planning Users Group Meeting August 11 th, 2017

Market Congestion Planning Study (South)- Robustness Analysis. Economic Planning Users Group Meeting August 11 th, 2017 Market Congestion Planning Study (South)- Robustness Analysis Economic Planning Users Group Meeting August 11 th, 2017 Key Takeaways The benefit calculations were updated due to a flowgate rating correction

More information

Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects

Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 13, 2006 1 Approved 2006 2010 ELL-South Transmission

More information

Cleco Power - Lafayette Utilities System- SPP/SPPICT-Entergy Joint Transmission Planning Study

Cleco Power - Lafayette Utilities System- SPP/SPPICT-Entergy Joint Transmission Planning Study October 20, 2008 DRAFT Cleco Power - Lafayette Utilities System- SPP/SPPICT-Entergy Joint Transmission Planning Study RELIABILITY AND ECONOMIC STUDY FOR THE 2008 TRANSMISSION EXPANSION PLAN OF THE ACADIANA

More information

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 14, 2005 1 2004-06 EGSI-TX Transmission Western Region Reliability

More information

Stability Study for the Mt. Olive Hartburg 500 kv Line

Stability Study for the Mt. Olive Hartburg 500 kv Line Stability Study for the Mt. Olive Hartburg 500 kv Line Peng Yu Sharma Kolluri Transmission & Distribution Planning Group Energy Delivery Organization Entergy Sevices Inc April, 2011 New Orleans, LA 1.

More information

TEXAS ECONOMIC STUDY REPORT ICTES INFORMATIONAL ONLY

TEXAS ECONOMIC STUDY REPORT ICTES INFORMATIONAL ONLY TEXAS ECONOMIC STUDY REPORT ICTES-2011-001 INFORMATIONAL ONLY Prepared for: Entergy Service, Inc. (SPO) American Electric Power Service Corporation (AEPSC) GDS Associates, Inc. (GDS), as agent of East

More information

Southwest Power Pool, Inc. Entergy ENTERGY SPP RTO REGIONAL PLANNING PROCESS MEETING May 24, 2012 NET CONFERENCE AGENDA 10:00 AM 12:00 PM

Southwest Power Pool, Inc. Entergy ENTERGY SPP RTO REGIONAL PLANNING PROCESS MEETING May 24, 2012 NET CONFERENCE AGENDA 10:00 AM 12:00 PM Southwest Power Pool, Inc. Entergy ENTERGY SPP RTO REGIONAL PLANNING PROCESS MEETING May 24, 2012 NET CONFERENCE AGENDA 10:00 AM 12:00 PM 1. Administrative A. Introductions... All B. SPP Antitrust Guidelines...

More information

System Impact Study PID MW Plant

System Impact Study PID MW Plant System Impact Study PID 257 252 MW Plant Prepared by: Southwest Power Pool Independent Coordinator of Transmission 415 N. McKinley, Suite140 Little Rock, AR 72205 Rev Issue Date Description of Revision

More information

SERTP rd Quarter Meeting

SERTP rd Quarter Meeting 2015 SERTP SERTP 2015 3 rd Quarter Meeting 2nd RPSG Meeting September 24 th, 2015 APC Headquarters Birmingham, AL 2015 SERTP Process Information The SERTP process is a transmission planning process. Please

More information

Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects

Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects Entergy Texas, Inc. Transmission 2014 2018 Draft Construction Plan Update 1 Projects 1 2014-2018 ETI Draft Construction Plan Update 1 Projects Completed in the Fall of 2012 & 2013 to date 1) Cedar Hill

More information

Transmission Planning using Production Cost Simulation & Power Flow Analysis

Transmission Planning using Production Cost Simulation & Power Flow Analysis ABB Transmission Planning using Production Cost Simulation & Power Flow Analysis Jinxiang Zhu, Ph.D. Senior Principal, ABB Power Consulting ABB Group January 16, 2018 Slide 1 Power System Studies TECHNICAL

More information

SPP-RTO: Operational Characteristics

SPP-RTO: Operational Characteristics SPP-RTO: Operational Characteristics Derek Hawkins, Supervisor Real Time Support May 23, 2018 SouthwestPowerPool SPPorg southwest-power-pool 2 The SPP Footprint: Members in 14 States Arkansas Kansas Iowa

More information

CIL/CEL Values and Study Timeline

CIL/CEL Values and Study Timeline 2019-2020 CIL/CEL Values and Study Timeline LOLEWG 9/11/2018 Updated 10/3/2018 1 Purpose and Key Takeaways Purpose Inform stakeholders of Draft 2019-20 Capacity Import and Export Limits. Key Takeaways

More information

MTEP13 SPM #2- Central Region. March 25, 2013

MTEP13 SPM #2- Central Region. March 25, 2013 MTEP13 SPM #2- Central Region Ameren Missouri March 25, 2013 Ameren Missouri Project Review Central Region: Ameren Missouri Ameren Missouri has a total of 10 project proposals that are recommended for

More information

SERTP rd Quarter Meeting

SERTP rd Quarter Meeting 2014 SERTP SERTP 2014 3 rd Quarter Meeting 2 nd RPSG Meeting September 30 th, 2014 APC Headquarters Birmingham, AL 2014 SERTP Process Information The SERTP process is a transmission planning process. Please

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Southwest Power Pool, Inc TPL Stability Study. MAINTAINED BY SOUTHWEST POWER POOL ENIGINEERING GROUP Modeling Group

Southwest Power Pool, Inc TPL Stability Study. MAINTAINED BY SOUTHWEST POWER POOL ENIGINEERING GROUP Modeling Group Southwest Power Pool, Inc. 2011 TPL Stability Study MAINTAINED BY SOUTHWEST POWER POOL ENIGINEERING GROUP Modeling Group PUBLISHED: 12/19/2011 Approved by TWG: 12/19/2011 2 2011 Stability Study Revisions

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

APPENDIX F: Project Need and Description

APPENDIX F: Project Need and Description APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was

More information

Monthly Construction Plan Project Status Report Report Date: 1/16/2014

Monthly Construction Plan Project Status Report Report Date: 1/16/2014 Monthly Construction Plan Report Report Date: 1/16/2014 EAI EMI ELL ENOI EGSL ETI EGSL/ELL ELL/ENOI ALL General Major Updates Added fifteen transmission reliability projects (SPOF and Under rated breakers).

More information

2013 SERTP. Welcome. SERTP rd Quarter Meeting. 2 nd RPSG Meeting

2013 SERTP. Welcome. SERTP rd Quarter Meeting. 2 nd RPSG Meeting 2013 SERTP Welcome SERTP 2013 3 rd Quarter Meeting 2 nd RPSG Meeting 1 2013 SERTP The SERTP process is a transmission planning process. Please contact the respective transmission provider for questions

More information

2015 Grid of the Future Symposium

2015 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Kiwanis International

Kiwanis International Page 1 of 11 Missouri-Arkansas 01 Division 1 K01274 Canton MO 21 21 21 21 21 21 21 21 21 21 21 0.00 K02289 Hannibal MO 60 60 59 59 59 59 58 59 62 62 62 3.33 +2 K08858 Hannibal, Early Birds MO 40 42 41

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Highly Constrained Elements Within ATC Footprint

Highly Constrained Elements Within ATC Footprint Highly Constrained Elements Within ATC Footprint Feb. 21, 2008 Presented by Dale Burmester Compiled by ATC Economic Planning Team: Tom Dagenais, Todd Tadych, Arash Ghodsian, Chris Hagman Solutions to Market

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

Southeastern Regional Transmission Planning (SERTP)

Southeastern Regional Transmission Planning (SERTP) Southeastern Regional Transmission Planning (SERTP) December 2014 Regional Transmission Planning Analyses I. Overview of Regional Analyses SERTP sponsors plan and expand the transmission system to reliably

More information

FACILITIES STUDY TRANSMISSION SERVICE REQUESTS OASIS

FACILITIES STUDY TRANSMISSION SERVICE REQUESTS OASIS TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:EGSI -LA CUSTOMER: NRG FACILITIES STUDY EJO # F4PPGS0411 TRANSMISSION SERVICE REQUESTS OASIS 1521373 Revision: 0 Issue Revised Project Rev Description of Revision

More information

PSE Attachment K Puget Sound Area Transmission Meeting

PSE Attachment K Puget Sound Area Transmission Meeting PSE Attachment K Puget Sound Area Transmission Meeting Stephanie Lu Senior Engineer December 15, 2011 Agenda Attachment K Review Economic Studies Process PSE Planning Process and Assumptions PSE Projects

More information

Entergy Draft Construction Plan Update 1

Entergy Draft Construction Plan Update 1 Entergy 2014-2018 Draft Construction Plan Update 1 Construction Plan Projects Relating To: Regulatory Transmission Service Economic Enhanced Transmission Reliability Customer Driven Generation Interconnection

More information

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Status of PNM s Completed Transmission Construction Projects 11/30/2017 Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information

More information

Entergy Final Construction Plan

Entergy Final Construction Plan Introduction Entergy 2012-2016 Final Construction Plan Project Driver Project Description Cost Allocation Guideline Project Category Block load addition Projects needed to accommodate the addition of block

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

2010 SERTP. Welcome. SERTP rd Quarter Meeting. 2 nd RPSG Meeting 9:00 AM 3:00 PM

2010 SERTP. Welcome. SERTP rd Quarter Meeting. 2 nd RPSG Meeting 9:00 AM 3:00 PM 2010 SERTP Welcome SERTP 2010 3 rd Quarter Meeting 2 nd RPSG Meeting 9:00 AM 3:00 PM 1 2010 SERTP Purposes & Goals of the Meeting Preliminary Economic Planning Results SERC Regional Model Development Update

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012 First Energy Generator Deactivation Request - January 2012 Deactivation Study Results and Required Upgrades April 25, 2012 General PJM received a notice on January 26, 2012 from FirstEnergy of its intent

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection

More information

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee February 7, 2013 1 Issues Tracking 2 Issues Tracking Open Issues None New Issues 3 2013 RTEP Scenario Analysis 4 RTEP Scenario Analysis 2012 North Carolina Transmission

More information

Market Efficiency Planning Study

Market Efficiency Planning Study Market Efficiency Planning Study West SPM June 12, 2013 SPM : Market Efficiency Planning Study Update March 25, 2012 Market Efficiency Planning Study Recap Objective is to execute an annual structured

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Impacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities

Impacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities Impacts of MISO DPP-2016-February (West, ATC, MI, South) 1. MISO generators studied: Projects on PJM Facilities Net MW size (Summer) Net MW size (Winter) Service DPP Project Type Region Fuel Type POI J432

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

Key to Status Fields in the Project List

Key to Status Fields in the Project List Key to Fields in the Project List Load Growth Interconnection Economic Reliability Concept Proposed Planned Under Construction In Cancelled N/A Backstop Too early TO Update Base case Increasing load served

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

THE TRES AMIGAS PROJECT

THE TRES AMIGAS PROJECT UNITING THE NATION S ELECTRIC POWER GRID THE TRES AMIGAS PROJECT Project Development, Business Case, and Benefits -ERCOT Presentation Jan 22, 2010 Agenda Project Overview Project Objective Project Description,

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

Transmission Planning for Wind Energy Resources in the Eastern United States. Dale Osborn

Transmission Planning for Wind Energy Resources in the Eastern United States. Dale Osborn Transmission Planning for Wind Energy Resources in the Eastern United States Dale Osborn Layered Design Typical utility planning Distribution delivery to loads Lower voltage transmission delivery from

More information

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis Terry Blackwell Page 1 of 5 Education 1977 North Carolina State University BS, Electrical Engineering Power Systems emphasis Professional Qualifications 1977 PE-Professional Engineer Business Experience

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic July 26, 2016 Reliability Analysis Update MetEd Transmission Zone N-1 First Energy Planning Criteria (FERC Form 715): The North Boyertown West Boyertown 69 kv is

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

Entergy Final Construction Plan

Entergy Final Construction Plan Introduction Entergy 2013-2017 Final Construction Plan Project Driver Project Description Cost Allocation Guideline Project Category Block load addition Projects needed to accommodate the addition of block

More information

Transmission Expansion Advisory Committee Meeting 2014 Market Efficiency Analysis

Transmission Expansion Advisory Committee Meeting 2014 Market Efficiency Analysis Transmission Expansion Advisory Committee Meeting 2014 Market Efficiency Analysis September 02, 2014 Objectives To review simulated congestion results for all Market Efficiency study years To provide an

More information

FACILITIES STUDY CONSTELLATION ENERGY TRANSMISSION SERVICE REQUEST OASIS

FACILITIES STUDY CONSTELLATION ENERGY TRANSMISSION SERVICE REQUEST OASIS TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:EAI CUSTOMER: CONSTELLATION ENERGY FACILITIES STUDY EJO # F4PPAR0434 ICTT-2007-177 CONSTELLATION ENERGY TRANSMISSION SERVICE REQUEST OASIS 1498122 Revision:

More information

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Local Transmission Plan. October 11, 2013 Revised August 25, 2014 Local Transmission Plan October 11, 2013 Revised August 25, 2014 2 Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated

More information

Sub Regional RTEP Committee - Southern. August 19, 2011

Sub Regional RTEP Committee - Southern. August 19, 2011 Sub Regional RTEP Committee - Southern August 19, 2011 2011 RTEP Analysis Summary 2010 2015 Project Updates 2016 Analysis NERC Category A, B NERC Category C (N-1-1 in progress) Load Deliverability Generator

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC

More information

FACILITIES STUDY TRANSMISSION SERVICE REQUEST OASIS

FACILITIES STUDY TRANSMISSION SERVICE REQUEST OASIS TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:EAI CUSTOMER: CARTHAGE WATER & ELECTRIC FACILITIES STUDY EJO # F4PPAR0436 ICTT-2007-179 TRANSMISSION SERVICE REQUEST OASIS 1498226 Revision: 1 Rev Issue Date

More information

Transmission Planning Attachment K Public Input Meeting

Transmission Planning Attachment K Public Input Meeting Transmission Planning Attachment K Public Input Meeting FERC 890 6 th Quarter Meeting May 25, 2011 Agenda Mountain Time Topic Presenter 1:00 1:15 Greetings and Introduction Dennis Desmarais 1:15 1:30 Attachment

More information

DPP February 2015 South System Impact Study Report 09/26/2016

DPP February 2015 South System Impact Study Report 09/26/2016 DPP February 205 South System Impact Study Report 09/26/206 Prepared by Resource Interconnection and Planning Midcontinent Independent System Operator Lakeway Two 3850 N. Causeway Blvd. Suite 442 Metairie,

More information

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Western Region ATSI Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

APPENDIX E: Project Need and Description

APPENDIX E: Project Need and Description APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Tyler 60 kv Shunt Capacitor Installation of a 2x10 MVAR capacitor bank at Tyler 60 kv bus Objectives

More information

South Dakota 890 Study

South Dakota 890 Study South Dakota 890 Study September 16, 2011 South Dakota 890 Study Presentation of 890 Study results from 2011 Includes WAPA suggested system improvements and timelines Stakeholder Feedback Questions? 2

More information

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC OCTOBER 17, 2018 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC

More information

Jay Caspary Director Research, Development & Tariff Services

Jay Caspary Director Research, Development & Tariff Services Interconnection Seams Study Update CIGRE GOTF October 23, 2017 Jay Caspary Director Research, Development & Tariff Services jcaspary@spp.org 2 Disclaimer This deck includes materials which were presented

More information

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M of Need In-service Cost Alternatives Service Projects in PG&E Service Territory Mare Island - Ignacio 115 kv NERC Category 2010 Reconductor the limiting 19 $19M Connect Highway May 2012 Line re-rates and

More information

Market Efficiency Update

Market Efficiency Update Market Efficiency Update Transmission Expansion Advisory Committee July 13, 2017 Agenda Where we are in the process Interregional Projects Status RPM Projects Status Reevaluation Analysis Status Next Steps

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

2018 Annual Progress Report to WECC Pacific Gas and Electric Company

2018 Annual Progress Report to WECC Pacific Gas and Electric Company 2018 Annual Progress Report to WECC Pacific Gas and Electric Company Waiver of Significant Transmission Project Status Table 1 and 2 update the planned transmission and generation projects, respectively,

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT

More information

SPP Notification to Construct

SPP Notification to Construct SPP Notification to Construct SPP-NTC-20123 February 14, 2011 Mr. Sam McGarrah Empire District Electric Company PO Box 127 Joplin, MO 64802 RE: Notification to Construct Approved Reliability Network Upgrades

More information

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff

More information

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016 New Transmission Line November 15, 2016 The enclosed information is proprietary to PSE&G and is provided solely for your use. It should not be copied, reproduced, or shared with others without PSE&G s

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Western Area Power Administration

Western Area Power Administration 2014/15 Integrated System (IS) 890 Local Planning Stakeholder Meeting #2 Western Area Power Administration Upper Great Plains Region Transmission Planning Stakeholder Meeting Wednesday, December 10 th,

More information

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04 Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

New Mexico Transmission Expansion Concepts For Wind Resources

New Mexico Transmission Expansion Concepts For Wind Resources New Mexico Transmission Expansion Concepts For Wind Resources May 2008 Update Electric Services Transmission Operations FOREWORD This document contains PNM s latest concepts for expanding the transmission

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information