Transmission System Bottlenecks & Planning for Mumbai Metropolitan Region

Size: px
Start display at page:

Download "Transmission System Bottlenecks & Planning for Mumbai Metropolitan Region"

Transcription

1 Transmission System Bottlenecks & Planning for Mumbai Metropolitan Region TRANSMISSION GROUP MERC 5 th August 2011

2 2

3 Actual Flows for Mumbai Peak FY12 ( 3209 MW) Tie Line Flows (Amp & MW) during Mumbai Peak FY 12 Generation: 1877 MW Tie Line Interchange: 1027 MW MSEDCL Wheeling Load: 195 MW Normal condition More than 50 % loading Critical Loading 1 Generation: 500 MW 3

4 Tripping of 220kV Kalwa Salsette line Tie Line Flows (Amp & MW) with one 220 KV Kalwa Salsette tripping (Peak FY 12) Generation: 1877 MW Tie Line Interchange: 1027 MW MSEDCL Wheeling Load: 195 MW MSETCL System: Kalwa Mulund and Kalwa Borivli lines are fully loaded Normal condition More than 50 % loading Critical Loading 2 Generation: 500 MW 4

5 Tripping of 220kV BO(T) BO(M) Line Tie Line Flows (Amp & MW) with TATA Bor-MSETCL Bor Line tripping (Peak FY 12) Generation: 1877 MW Tie Line Interchange: 1030 MW MSEDCL Wheeling Load: 195 MW Normal condition More than 50 % loading Critical Loading 3 Generation: 500 MW 5

6 Tripping of Trombay 500MW Unit Tie Line Flows (Amp & MW) considering contingency of 500 MW unit tripping (Peak FY 12) Generation: 1377 MW Generation: 1377 MW Tie Tie Line Interchange: MW MSEDCL Wheeling Load: 195 MW MSETCL System: Kalwa Mulund line is is Overloaded and Kalwa Borivli line is is fully loaded Normal condition More than 50 % loading Critical Loading 4 Generation: 500 MW 6

7 Observations & Remedial measures 220KV Bo(T) Bo(M) line out: Severe condition 220KV D/C Aarey Borivali lines out: simulation does not converge: Mumbai System may not survive. Shifting Aarey S/S load to TPCL S/S to be explored to relieve 220KVAarey Borivali line loading. High reliability Special Protection Schemes (SPS) for automatic LS, be commissioned to avoid cascade tripping. Feasibility of HVDC /Series compensation/svc for 220KV lines DSM/EE by consumers: Pilot Schemes Feasibility of Barge based Generation (250/300MW) to feed North Mumbai Running of TPC Trombay U 4 with additional gas allocation (130 MW) for Mumbai

8 MERC Approved schemes for strengthening of Mumbai Metropolitan Region Sr. No. Utilities Total No. of Schemes Approved Total Estimated Cost (in Rs Cr) 1 TPC T R Infra T MSETCL Total

9 TPC T Sr. No. Scheme Approv ed Cost Rs Cr Approval by MERC Estimated Date of Completion REMARKS kv Trombay Dharavi Salsette Lines 153 May 2007 March 10 Commissioning of line sections in Godrej area and Somaiya plot completed & line section charged Bottlenecks: Permissions from CRZ,Forest Department, Mangrove area. Relocation of hutment dwellers. ROW: Private societies kV GIS RS at Mahalaxmi March 11 Orders for major equipment's like GIS, ICT & Protection panels placed. Bottlenecks: Pending approval of Building Plan with MCGM. 9

10 3 220 kv GIS at SAKI & Upgrading of Transmission lines Dec 2007 March 2010 TPC T Progress: A)GIS: Construction of GIS building : December Balance S/s civil jobs have been completed. Major Equipment Ordered B)220Kv Transmission Line: Out of 28 towers, 10 completed. Construction of terminating arrangement for 220kV line taken up. Bottlenecks: Relocation of Project affected persons kV interconnectio n with MSETCL at Borivali 19.5 June 2007 March 2009 Installation of towers &stringing of conductors completed. 220 kv cable section at GIS end energized. One bay equipment has been commissioned 1st line has been taken in service in Aug nd line is charged from Borivali in April 2011 Gantry for 1 Tower completed and for 2nd Tower in progress. Bottlenecks: Statutory permission for removal of trees for construction of bays /towers delayed. Due to restriction on working hours & movement of trucks imposed by Sanjay Gandhi National Park Authorities, the jobs are in progress at slower pace. 10

11 TPC T kv Backbay Ring System August 2008 March 12 Progress: 220 KV Cable trenching & laying WIP 110Kv Cable diversion at Backbay WIP Bottlenecks: Permission from MCGM, MBPT for cable laying and permissions from CRZ,Forest department, Wigh court for working in mangrove area for erecting overhead lines. 6 Installations of 145 KV GIS at Chembur/ Worli/ Bombay Dying Wadala/ HDIL Kurla/ Mankhurd March 13 Environmental Clearance at Chembur Work to be started Possession of plot to be obtained from SRA 11

12 TPC T 7 400/220/33 kv GIS at Vikhroli June 2011 March 13 Progress: negotiations for land acquisition under progress. Bottleneck: Land Acquisition kv Kalwa Salsette third line between MSETCL (KALWA) & TATA Power Salsette R/S with line bays at both the ends June 2007 April 13 Bottle Necks: Permission from CRZ, Forest Department, High court for working in Mangrove area. Permissions from private societies and land owners. 12

13 R Infra T Sr. No. Scheme name Approved Cost by Comission MERC Approval Commissioni ng as per DPR Transmission bottlenecks/ Remarks 1 220KV GIS Chembur 220 Aug 2007 Mar Progressive CC stalled by MCGM Civil work is stopped at Chembur MMRDA permission required 2 220kV GIS at Saki EHV Station Jun e2008 March 2011 Station charged Delay in outages of desired lines during commissioning Heavy monsoon: civil activity As per new norms works could not be taken at night times kV GIS Borivali July 2008 March 2011 Forest clearance for cable from Sanjay Gandhi National park

14 4 220kV Nagari Niwara R Infra T Jan 2008 March 2015 Land acquisition is in process 5 220kV Goregaon EHV station Jan 2008 March 2010 Station charged Heavy monsoon delayed civil activity Non availability of river sand stalled civil works ias per new norms works could not be taken at night times. 6 LILO existing MSETCL Boisar Borivali 220 kv line at Ghodbunder EHV Stn Apr 2010 March 2012 LILO tower erected 220kV cable laying work is in full swing. ROW issues

15 MSETCL Approve Commiss Sr MERC Schemes d cost in ioning.no approval Rs Cr date as per DPR 1 400/220/33 KV Kharghar S/S May, 2007 March 2 (Pl go to next slide) 1)LILO on 220 KV Kharghar Kalwa at Nerul 2)LILO on 220 KV Kharghar Kalwa at Tiffil 3)220 KV M/C line on narrow base M/C towers from LILO point near Nerul to Trombay s/s 4) LILO on 220KV Kalwa Borivali M/C line at Mulund s/s 5) LILO on 220 KV Borivali Boisar M/C line at Tarapur 6)LILO on 220 KV Mulund Borivali line at Bhandup GIS 7)LILO on 220 KV Kharghar Kalwa M/C line at Siemens March, March Installation of addl. 4 x 167 MVA, 400/220/33 kv ICT & Replacement of 3 x 200 MVA, 400/220/33 kv ICT by 3 x 167 MVA, 400/220/33 kv ICT at 400 kv Kalwa Substation March, 2009 March

16 Network Augmentation: MSETCL Conversion of 220 kv Kharghar Kalwa Borivali Boisar D/c line with New Twin Moose Conductor 16

17 MSETCL 4 1. LILO on220kv Mulund Borivali feeder II at Bhandup S/S Dec 2008 March /22 kv Sub Station in Bhiwandi IV,, LILO on 220KV Kalwa Padghe Augmentation of 400 kv Kharghar S/S and Six other EHV S/S (4x167 MVA Xmers ) 1) 220 kv Kharghar Kalwa M/C Line on M/C Narrow base towers 2) 220 kv Kalwa Mulund Borivali M/C Line on M/C Narrow base towers 3) 220 kv Borivali Boisar II M/C Line on M/C Narrow base towers 4) Dismantling of existing D/C on D/C tower line a) 220 kv Kharghar Kalwa Line 26.0 Km b) 220 kv Kalwa Borivali Line 17.0 Km c) 220 kv Borivali Boisar II Line 87.0 Km Dec 2009 March Dec 2009 March Nov 2010 March

18 On going Projects to be completed on Top Priority MSETCL/PGCIL: 220KV M/C Kharghar Kalwa Borivali Boisar line 220KV S/S Bhandup/Bhiwandi (to relive loading on TPC system) 400/220KV S/s at Panvel by PGCIL (connecting to 400KV Vikroli) R Infra LILO of 220KV Borivali Boisar line at Ghodbundar S/s 220KV S/s at Chembur, Borivali, Goregaon, Nagar Niwara Commissioning of 3 rd 220KV Kalwa Salsette line TPC: 2 nd 220KV Bo(T) BO(M) line 220KV Trombay Salsette 3 rd Circuit 220KV Trombay Dharavi Backbay 3 rd Circuit 220KV Trombay Saki & Salsette Saki lines

19 For faster completion of on going Transmission projects Issues to be sorted with other Authorities: ROW Mangroves CRZ Forest Hutment dwellers MCGM permission Private land.

20 Finally Existing Mumbai network is very Fragile. Network Strengthening: to be taken up on top priority. Progress of already approved scheme to be regularly monitored by STU. Improvements for (n 1) compliance as suggested in Dr Khaparde Report needs carried out on priority. Investigate feasibility of the 220 kv D/C Trombay (TPCL) Saki (R Infra) for relieving existing system from critical loading, during peak conditions. Connectivity at 400 kv between Vikhroli (TPCL) and Ghodbunder (R Infra) needs to be checked.

21 Thank You M:

Maharashtra State Load Despatch Centre. Partial Grid Disturbance in Mumbai system on 18 th Nov-2010 at 17:45 hrs and 21 st Nov-2010 at 17:10 hrs

Maharashtra State Load Despatch Centre. Partial Grid Disturbance in Mumbai system on 18 th Nov-2010 at 17:45 hrs and 21 st Nov-2010 at 17:10 hrs Maharashtra State Load Despatch Centre Partial Grid Disturbance in Mumbai system on 18 th Nov-2010 at 17:45 hrs and 21 st Nov-2010 at 17:10 hrs Maharashtra State Load Despatch Centre Partial Grid Disturbance

More information

TRANSMISSION LICENCE NO. 1 OF 2011 LICENCE FOR TRANSMISSION OF ELECTRICITY IN THE STATE OF MAHARASHTRA

TRANSMISSION LICENCE NO. 1 OF 2011 LICENCE FOR TRANSMISSION OF ELECTRICITY IN THE STATE OF MAHARASHTRA MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th floor, Cuffe Parade, Mumbai - 400 005. Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in

More information

Reengineering of Distribution lines for Power Loss Reduction-Bhiwandi Case Study

Reengineering of Distribution lines for Power Loss Reduction-Bhiwandi Case Study Reengineering of Distribution lines for Power Loss Reduction-Bhiwandi Case Study SHRIRANG KARANDIKAR Vice President (Business Development) Kalpataru Power Transmission Ltd. Santacruz (East), Mumbai-400055

More information

Case No. 112 of In the matter of Application of Tata Power Company Limited for grant of Transmission Licence

Case No. 112 of In the matter of Application of Tata Power Company Limited for grant of Transmission Licence Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/ 65/ 69 Fax 022 22163976 Email: mercindia@merc.gov.in

More information

Report. the feasibility of

Report. the feasibility of Report on the feasibility of Additional Interconnection between India and Bangladesh Joint Technical Team (JTT) of India and Bangladesh July 2016 Contents 1.0 Background 1 2.0 Additional power export to

More information

Valmont India - Utility UTILITY POLES

Valmont India - Utility UTILITY POLES Valmont India - Utility 1 UTILITY POLES Introduction to Utility Poles 2 Traditionally lattice towers common for high voltage transmission lines. Use of steel poles started in late 1960s in US with extensive

More information

Engineers Ireland Site Visit 23 rd March 2010

Engineers Ireland Site Visit 23 rd March 2010 Whitegate Independent Power Plant CER Site Visit 24 th October 2008 CER Site Visit 24 th October 2008nt Engineers Ireland Site Visit 23 rd March 2010 Agenda Presentation of project and progress to date.

More information

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010 FINAL FACILITY STUDY 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1 September 10, 2010 I. Introduction This is a revised facility study performed for Transmission Queue Request 2009

More information

CONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012

CONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012 CONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012 TRANSMISSION SECTOR GROWTH HIGHLIGHTS Source - POWERLINE Transmission line length

More information

PCDO. Jan Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project

PCDO. Jan Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project PCDO Jan-2018 Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project Northern Railway vuqjkx dqekj lpku vkbzvkj,lb Anurag Kumar Sachan

More information

TRANSMISSION CAPACITY ADDITION PROGRAMME DURING No. 1 Introduction 1

TRANSMISSION CAPACITY ADDITION PROGRAMME DURING No. 1 Introduction 1 TRANSMISSION CAPACITY ADDITION PROGRAMME DURING 2006-07 Sl. No. Contents Page No. 1 Introduction 1 2 Chapter 1 Transmission Capacity Additions During 2005-06 of 10 th plan period 3 Chapter 2 Construction

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Distribution lines Overload Control to Increase Reliability and Power Loss Reduction

Distribution lines Overload Control to Increase Reliability and Power Loss Reduction Distribution lines Overload Control to Increase Reliability and Power Loss Reduction SHRIRANG KARANDIKAR Vice President (Business Development) Kalpataru Power Transmission Ltd. Santacruz (East), Mumbai-400055

More information

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th Alex Bettencourt Managing Director National Association Made Up of Entire Industry Utilities Industry Academia / R&D

More information

Transmission Planning for Wind Energy Resources in the Eastern United States. Dale Osborn

Transmission Planning for Wind Energy Resources in the Eastern United States. Dale Osborn Transmission Planning for Wind Energy Resources in the Eastern United States Dale Osborn Layered Design Typical utility planning Distribution delivery to loads Lower voltage transmission delivery from

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Implementation Status & Results India Mumbai Urban Transport Project (P050668)

Implementation Status & Results India Mumbai Urban Transport Project (P050668) Public Disclosure Authorized Public Disclosure Authorized losure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results India Mumbai Urban Transport Project (P050668) Operation

More information

R.S.USHA CHIEF ENGINEER/ PLANNING & RC. Encl: Report and detailed estimate. To The Chief Engineer/D/Madurai Region

R.S.USHA CHIEF ENGINEER/ PLANNING & RC. Encl: Report and detailed estimate. To The Chief Engineer/D/Madurai Region TAMIL NADU GENERATION AND DISTRIBUTION CORPORATION LTD ABSTRACT --------------------------------------------------------------------------------------------------------- Electricity - Madurai Region -

More information

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007 High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services

More information

(i) Establishment of 400kV Pooling Station at Fatehgarh (with a provision to upgrade at 765kV level)

(i) Establishment of 400kV Pooling Station at Fatehgarh (with a provision to upgrade at 765kV level) Annex-I Corrigendum to Minutes of the 36 th meeting of the Empowered Committee on Transmission held on 26 th July, 2016 at 3:30 PM at Conference Room of CEA, 2 nd Floor, Sewa Bhawan, R.K. Puram, New Delhi

More information

LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST

LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST Cleco Power LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST OASIS 71956063 0 Rev Issue Date Description of Revision Table of Contents 1. Purpose...3 2. System Impact Study Conclusions...3 2.1 The Pineville

More information

FINANCIAL HIGHLIGHTS AND BUDGET ESTIMATES

FINANCIAL HIGHLIGHTS AND BUDGET ESTIMATES FINANCIAL HIGHLIGHTS AND BUDGET ESTIMATES A) The summarized actual income and expenditure for the financial year 2014-2015 are as under :- (Rs. in Crores) *Electric Supply *Transport Whole Undertaking

More information

RFP Corrigendum No. 01

RFP Corrigendum No. 01 RFP Corrigendum 01 The RFP document for selection of Transmission Service provider for the Package- 1 against tender specification ESD-765/4 has been modified to the extent below: S. Clause / Page 1. Definition

More information

Commercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow

Commercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 2,038 2,922 4,089 4,349 6,256 7,124 8,885 8,885 8,885 8,885 8,885 8,885 9,107

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

System Improvement Scheme(R&M) : FY

System Improvement Scheme(R&M) : FY GUJARAT ENERGY TRANSMISSION CORPORATION LTD System Improvement Scheme(R&M) : FY 2012-13 In GETCO network, large number of substations and lines are quite old, some of its equipments viz. CT s, PT s, Breakers,

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized SOUTH ASIA India Transport & ICT Global Practice IBRD/IDA Specific Investment Loan FY 2010 Seq No: 13 ARCHIVED on 23-Sep-2015 ISR20247 Implementing Agencies: Public Disclosure

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014 1 BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada IEEE PES Meeting July 2014 General BC Hydro Overview Crown Corporation Serving about 95% of province and 1.9 million customers

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Western Alberta Transmission Line (WATL) HVDC Project

Western Alberta Transmission Line (WATL) HVDC Project Submission for the ACEC Canada Canadian Consulting Engineering Awards 2016 Western Alberta Transmission Line (WATL) HVDC Project Submitted by Teshmont Consultants LP as a Consultant to AltaLink Attachment

More information

Evacuation of Wind Power in Kadapa, Anantapur and Kurnool districts of Andhra Pradesh. Revised Administrative Approval - Accorded

Evacuation of Wind Power in Kadapa, Anantapur and Kurnool districts of Andhra Pradesh. Revised Administrative Approval - Accorded TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED Evacuation of Wind Power in Kadapa, Anantapur and Kurnool districts of Andhra Pradesh. Revised Administrative Approval - Accorded T.O.O.{CE-Constructionl400kV)

More information

SSF Section Location of Change SSF Issue Change(s) Comments Chapter Part B All Multiple Formatting, spelling and minor Changes applied -

SSF Section Location of Change SSF Issue Change(s) Comments Chapter Part B All Multiple Formatting, spelling and minor Changes applied - SSF Update December 2017 Summary of Changes This table only mentions SSF chapters that were updated. All other SSF chapters were checked and confirmed as still being uptodate. SSF Section Location of Change

More information

Distribution Capacity Impacts of Plug In Electric Vehicles. Chris Punt, P.E. MIPSYCON 2014

Distribution Capacity Impacts of Plug In Electric Vehicles. Chris Punt, P.E. MIPSYCON 2014 Distribution Capacity Impacts of Plug In Electric Vehicles Chris Punt, P.E. MIPSYCON 2014 1 Outline EV Benefits EV Growth Where are we today? Where are we going? Potential Distribution Capacity Issues

More information

DDG 51 Program. Sea, Air, Space Exposition Washington, DC 04 April Presented by: CAPT Casey Moton, USN DDG 51 Program Manager PMS 400D

DDG 51 Program. Sea, Air, Space Exposition Washington, DC 04 April Presented by: CAPT Casey Moton, USN DDG 51 Program Manager PMS 400D Sea, Air, Space Exposition Washington, DC 04 April 2017 DDG 51 Program Presented by: CAPT Casey Moton, USN DDG 51 Program Manager PMS 400D 1 Agenda DDG 51 Shipbuilding Profile DDG 113-123 Production Status

More information

Appendix E Water Supply Modeling

Appendix E Water Supply Modeling Supply Modeling Modesto Irrigation District Treatment Plant Expansion Project Modeling I. Introduction The Modesto Irrigation District (MID) is situated adjacent to and north of the Tuolumne River. Over

More information

2018 Annual Progress Report to WECC Pacific Gas and Electric Company

2018 Annual Progress Report to WECC Pacific Gas and Electric Company 2018 Annual Progress Report to WECC Pacific Gas and Electric Company Waiver of Significant Transmission Project Status Table 1 and 2 update the planned transmission and generation projects, respectively,

More information

Date Event or Holiday :Sun, 2:Mon North Orchard Delong Preschool North Orchard Delong Preschool

Date Event or Holiday :Sun, 2:Mon North Orchard Delong Preschool North Orchard Delong Preschool 2018 6 1 1:Sun, 2:Mon 2018-2019 Date Event or Holiday Aug 16 Board Meeting 6pm Aug 23 Open House June 2018 July 2018 August 2018 Sep 06 Board Meeting 6pm Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th

More information

PROCUREMENT PLAN RENEWABLE ENERGY INTEGRATION PROJECT (REIP)

PROCUREMENT PLAN RENEWABLE ENERGY INTEGRATION PROJECT (REIP) Public Disclosure Authorized PROCUREMENT PLAN RENEWABLE ENERGY INTEGRATION PROJECT (REIP) Revision 4.0 Public Disclosure Authorized I. General 1. Project Information Country Borrower Project Name Loan

More information

Offshore Wind: Grid Connection & Technology Options. Dietmar Retzmann Focus on. CO 2 Reduction Green Energy Megacities Security of Supply

Offshore Wind: Grid Connection & Technology Options. Dietmar Retzmann Focus on. CO 2 Reduction Green Energy Megacities Security of Supply Offshore Wind: Grid Connection & Technology Options Dietmar Retzmann 1 10-2011 E T PS S/Re Focus on CO 2 Reduction Green Energy Megacities Security of Supply 2 10-2011 E T PS S/Re 1 EWEA s 2030 Offshore

More information

Need Assessment Document (NAD) DDUGJY

Need Assessment Document (NAD) DDUGJY Need Assessment Document (NAD) DDUGJY Index SNo. Details Page No. 1.0 General Instruction 3 2.0 Objectives of DDUGJY 5 3.0 Scope of works 7 4.0 General information of project area 10 5.0 Details of existing

More information

Agenda for Connectivity and Long Term (Open) Access of IPP Generation Projects in Odisha of Eastern Region

Agenda for Connectivity and Long Term (Open) Access of IPP Generation Projects in Odisha of Eastern Region Agenda for Connectivity and Long Term (Open) Access of IPP Generation Projects in Odisha of Eastern Region 1.0 Applications for Connectivity and Long Term (Open) Access. Applications for grant of Connectivity

More information

Smarter Network Storage UK first multi-purpose application of grid scale storage. Dr. Panos Papadopoulos, PhD, CEng

Smarter Network Storage UK first multi-purpose application of grid scale storage. Dr. Panos Papadopoulos, PhD, CEng Smarter Network Storage UK first multi-purpose application of grid scale storage Dr. Panos Papadopoulos, PhD, CEng UK Power Networks GENERATION TRANSMISSION DISTRIBUTION SUPPLY INDUSTRIAL COMMERCIAL RESIDENTIAL

More information

HVDC Systems in India

HVDC Systems in India HVDC Systems in India Outline Introduction HVDC Systems presently in operation Main Data/Salient Features Upcoming Projects Future Challenges Transmission Network - Present 765kV/400kV lines: about 1,03,000

More information

Mobilehome Park Utility Upgrade Program

Mobilehome Park Utility Upgrade Program Mobilehome Park Utility Upgrade Program A new opportunity for mobilehome communities PLEASE NOTE: Information reflects current advice letter filed with but not yet approved by the CPUC Commission Approves

More information

Additional Agenda for 31 st Standing Committee Meeting of Power System Planning for Northern Region

Additional Agenda for 31 st Standing Committee Meeting of Power System Planning for Northern Region Additional Agenda for 31 st Standing Committee Meeting of Power System Planning for Northern Region a) Power Supply to M/s Noida Power Company Limited (NPCIL) NPCL has applied to CTU for connectivity for

More information

Algebra II Pacing Guide

Algebra II Pacing Guide Unit 13: Exploring a Business Venture (10 days) 8 May 13 - May 24 n/a MISD Pacing Guide Date Range Unit 01: Introduction to Functions in 15 Aug. 21 - Sept. 11 Sept. 12 Unit 02: Absolute Value Functions,,

More information

PRESENTATION ON STRATEGIC APPROACH TOWARDS WIND SOLAR HYBRID SYSTEMS (SWES) FOR REMOTE TELECOM SITES IN INDIA & CASE STUDY OF RAJASTHAN

PRESENTATION ON STRATEGIC APPROACH TOWARDS WIND SOLAR HYBRID SYSTEMS (SWES) FOR REMOTE TELECOM SITES IN INDIA & CASE STUDY OF RAJASTHAN PRESENTATION ON STRATEGIC APPROACH TOWARDS WIND SOLAR HYBRID SYSTEMS (SWES) FOR REMOTE TELECOM SITES IN INDIA & CASE STUDY OF RAJASTHAN WORKSHOP ON SMALL WIND ENERGY AND HYBRID SYSTEMS & ITS RELEVANCE

More information

TURKISH POWER SYSTEM OVERVIEW AND INTERCONNECTION WITH GEORGIAN POWER SYSTEM TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

TURKISH POWER SYSTEM OVERVIEW AND INTERCONNECTION WITH GEORGIAN POWER SYSTEM TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS) TURKISH POWER SYSTEM OVERVIEW AND INTERCONNECTION WITH GEORGIAN POWER SYSTEM TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS) 1 CONTENT MAIN FUNCTIONS OF TEIAS TURKISH POWER SYSTEM OVERVIEW EXISTING

More information

CABLE INSTALLATION PROJECTS

CABLE INSTALLATION PROJECTS SPPA Contract No. 9120482 - Supply & Installation of 230kV XLPE Power, Auxiliary & Accessories (NDC 122 - Route A & C) 10.5km Jun 2015 Viscas Engineering Singapore SPPA Contract No. 9120326 - Supply &

More information

Seabrook Substation Reliability Improvement Project

Seabrook Substation Reliability Improvement Project New England Division Seabrook Substation Reliability Improvement Project 1. Project Summary Description Seabrook Substation is critical to ISO-New England as a Pool Transmission Facility, to grid availability

More information

CHAPTER 9 POWER SUPPLY, SYSTEM OF TRACTION AND POWER TARIFF

CHAPTER 9 POWER SUPPLY, SYSTEM OF TRACTION AND POWER TARIFF CHAPTER 9 POWER SUPPLY, SYSTEM OF TRACTION AND POWER TARIFF 9.1 POWER REQUIREMENTS 9.2 NEED FOR HIGH RELIABILITY OF POWER SUPPLY 9.3 SELECTION OF TRACTION SYSTEM 9.4 SOURCES OF POWER SUPPLY 9.5 AUXILIARY

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 TODAY WE LL TALK ABOUT Our challenges and how we re meeting them Why we re building this project Our planning process and considerations

More information

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN SPN High Value Project PO Route RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN Document History Version Date Details Originator V0.1 20/06/2013 Initial version Chris Winch V0.2

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

7th Grade Social Studies Pacing Guide Units of Instruction MISD Pacing Guide Days Date Range Test Date

7th Grade Social Studies Pacing Guide Units of Instruction MISD Pacing Guide Days Date Range Test Date 7th Grade Social Studies MISD Pacing Guide Date Range Test Date Unit 01: Thinking Like a Historian (5 days for the entire unit) 5 Aug 27-31 Unit 02: Natural Texas and Its People 1200s-1800s (5 days for

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Pacific Gas and Electric Company s Revised 2016 Annual Progress

Pacific Gas and Electric Company s Revised 2016 Annual Progress March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric

More information

Minutes of the 19 th meeting of the Standing committee on transmission system of Northern Region held at Amritsar on 01/10/05.

Minutes of the 19 th meeting of the Standing committee on transmission system of Northern Region held at Amritsar on 01/10/05. Minutes of the 19 th meeting of the Standing committee on transmission system of Northern Region held at Amritsar on 01/10/05. 1. List of the participants is enclosed at Annex - I. Member (PS) CEA welcomed

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

FORTISBC INC. PRUDENCY REVIEW KETTLE VALLEY SUBSTATION EXHIBIT A2 5

FORTISBC INC. PRUDENCY REVIEW KETTLE VALLEY SUBSTATION EXHIBIT A2 5 ALANNA GILLIS ACTING COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, BC CANADA V6Z 2N3 TELEPHONE: (604) 660 4700 BC TOLL

More information

PJM Generation Interconnection Request Queue #A55 Lakewood 230kV Facilities Study Report

PJM Generation Interconnection Request Queue #A55 Lakewood 230kV Facilities Study Report PJM Generation Interconnection Request Queue #A55 Lakewood 230kV Facilities Study Report 155697 September 2001 Table of Contents DESCRIPTION PAGE 1.0 Introduction 3 2.0 Description of Facilities Included

More information

Mobility Management: Caltrain

Mobility Management: Caltrain Mobility Management: Caltrain Community Relations Committee October 4, 2017 Agenda Item 7 Presentation Outline Operating Statistics Ridership On-time Performance Fleet Reliability Capital Program Review

More information

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

CEO PROGRAM September 2018

CEO PROGRAM September 2018 CEO PROGRAM September 2018 1 Sept 17th: ALL! CEO High Orientation (Kiva 6pm 7:30pm) 2 3 4 5 6 7 8 Sept 18th: ALL! CEO Orientation (Kiva 6pm 7:30pm) 9 10 11 12 13 14 15 *Parents please drop off/pick up

More information

ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL BACKGROUND

ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL BACKGROUND ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL Project Manager: Chris Hayes BACKGROUND Kraft Foods 35 Reduction of Energy Costs Over The Next 5 Yrs. (5 Benchmark) Kraft Foods Financial Model

More information

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES 1 PRESENTATION OUTLINE Generation System Demand Outlook Existing Generation Resources Transmission System National Interconnected

More information

Transmission Corporation of Telangana, Jawaharlal Nehru Technological University Hyderabad

Transmission Corporation of Telangana, Jawaharlal Nehru Technological University Hyderabad ENHANCEMENT OF POWER TRANSFER CAPABILITY OF TRANSMISSION LINES USING HTLS CONDUCTOR 1 M.SHESHAGIRI, 2 B.V.SANKER RAM Transmission Corporation of Telangana, Jawaharlal Nehru Technological University Hyderabad

More information

Inventory Levels - All Prices. Inventory Levels - By Price Range

Inventory Levels - All Prices. Inventory Levels - By Price Range Inventory Levels - All Prices Idaho Falls Bonneville Total 7-Apr-17 154 111 265 6-Apr-18 113 91 204-23% Inventory Levels - By Price Range 7-Apr-17 6-Apr-18 0-100,000 36 10 100,001-125,000 13 9 125,001-150,000

More information

January William W. Winpisinger Education and Technology Center. Sunday Monday Tue sday Wednesday Thursday Friday Saturday

January William W. Winpisinger Education and Technology Center. Sunday Monday Tue sday Wednesday Thursday Friday Saturday January 2019 Dec 2018 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 22 23 24 25 26 27 28 29 30 31 1 New Years Day 2 3 4 5 6 7 8 9 10 11 12 Negotiation Prep of Bargaining Committee- PKL/ LL 582 & LL

More information

MONTHLY RIDERSHIP AND PERFORMANCE REPORT. July 2018 Monthly Performance Report

MONTHLY RIDERSHIP AND PERFORMANCE REPORT. July 2018 Monthly Performance Report MONTHLY RIDERSHIP AND PERFORMANCE REPORT July 2018 Monthly Performance Report JULY, 2018 MONTHLY PERFORMANCE REPORT Ridership Ridership for the month of July increased 1% when compared to July of 2017.

More information

Final Written Examination.

Final Written Examination. Benha University Semester (3 th year Power &Control) Faculty of Engineering Electrical Power Systems (E1331) Electrical Engineering Department Semester 2015-2016 Final Written Examination. 10/1/2016 Time

More information

Line using HTLS Conductors to increase

Line using HTLS Conductors to increase Upgradation of 132kV Transmission Line using HTLS Conductors to increase the load transfer capacity. By Srikrushna S. Navlakhe Executive Engineer, EHV Construction cum Operation and Maintenance Zone, MSETCL,

More information

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PSE&G System Characteristics New Jersey utility characterized by densely populated

More information

State Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009

State Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009 State Regulatory Affairs and Local Relations Update ATC Customer Meeting November 19, 2009 Project Certification Steve Parker Manager State Regulatory Affairs CA/CPCN Applications (Filed/Ordered/Under

More information

TECHNICAL SERVICE BULLETIN

TECHNICAL SERVICE BULLETIN TECHNICAL SERVICE BULLETIN To: Minuteman Dealers and Customers From: Minuteman Technical Support Date: 1/12/2011 Subject: TSB for the KIT # K-FRSPEEDSWT. For the FR17115, FR17220, FR20115 and FR20220 models.

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

Proposed Dounreay - Mybster 275 kv / 132 kv

Proposed Dounreay - Mybster 275 kv / 132 kv Background Scottish Hydro-Electric Transmission Ltd (SHETL) is proposing a new 275 kilovolt (kv) (1 kilovolt = 1000volts) double circuit overhead line (OHL) between the Dounreay sub station and the new

More information

Public Works Department, Capital Improvement Program Project Tracking

Public Works Department, Capital Improvement Program Project Tracking Community Facilities Name CF-01 Eastshore State Park/Powell Street Bioswale Seeking grant funding. TT CF-02 South Bayfront Bridge and Horton Landing Park CF-03 / - 04 Transit Center Updated plans are being

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

BC Hydro System 2017 Annual Progress Report

BC Hydro System 2017 Annual Progress Report March 14, 2017 Philip Augustin, P.E. Chair, Technical Studies Subcommittee 503-464-7783 philip.augustin@pgn.com Mr. Enoch Davies WECC Technical Staff 155 North 400 West, Suite 200 Salt Lake City, UT 84103-1114

More information

Mohammad Alauddin Deputy Secretary Power Division Ministry of Power, Energy & Mineral Resources Govt. of the People s Republic of Bangladesh

Mohammad Alauddin Deputy Secretary Power Division Ministry of Power, Energy & Mineral Resources Govt. of the People s Republic of Bangladesh Mohammad Alauddin Deputy Secretary Power Division Ministry of Power, Energy & Mineral Resources Govt. of the People s Republic of Bangladesh mohammad_alauddin4124@yahoo.com December 19, 2013 Total area

More information

ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL December 2008 BACKGROUND

ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL December 2008 BACKGROUND ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL December 2008 Project Manager: Chris Hayes Advisor: Paul I-Hai Lin 1 BACKGROUND Kraft Foods 35 uction of Energy Costs Over The Next 5 Yrs. (2005

More information

Units of Instruction MISD Pacing Guide Days Date Range Test Date

Units of Instruction MISD Pacing Guide Days Date Range Test Date MISD Pacing Guide Date Range Test Date Introduction: Processes of Investigations (1 day) Aug. 21 Unit 01: Matter (12 days) Aug. 22-Sept. 7 Sep. 10 Unit 02: Atomic Structure and the Periodic Table (15 days)

More information

JAMMU AND KASHMIR STATE POWER DEVELOPMENT CORPORATION LIMITED PUBLIC NOTICE

JAMMU AND KASHMIR STATE POWER DEVELOPMENT CORPORATION LIMITED PUBLIC NOTICE JAMMU AND KASHMIR STATE POWER DEVELOPMENT CORPORATION LIMITED PUBLIC NOTICE Objections/ comments invited from various stakeholders on ARR filing and Tariff Petition of Hydro Electric Stations, Gas Turbine

More information

Sub Regional RTEP Committee South

Sub Regional RTEP Committee South Sub Regional RTEP Committee South October 30, 2017 Baseline Reliability and Supplemental Projects First Preliminary Review 2 Dominion: Baseline Violation 115 kv Line #43 Staunton to Harrisonburg End of

More information

MONTHLY RIDERSHIP AND PERFORMANCE REPORT. August 2018 Monthly Performance Report

MONTHLY RIDERSHIP AND PERFORMANCE REPORT. August 2018 Monthly Performance Report MONTHLY RIDERSHIP AND PERFORMANCE REPORT August 2018 Monthly Performance Report Ridership AUGUST, 2018 MONTHLY PERFORMANCE REPORT Ridership for the month of August decreased 2.6% when compared to August

More information

Refurbishment & Upgrade of the Celilo HVdc Converter Station

Refurbishment & Upgrade of the Celilo HVdc Converter Station 1 Refurbishment & Upgrade of the Celilo HVdc Converter Station Mark A Reynolds, PE Sr. Project Manager, POWER Engineers mark.reynolds@powereng.com Karl A Mitsch, P.E. Sr. Project Manager USDOE Bonneville

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

ELECTRIC SERVICE RATE SCHEDULES. Effective November 1, 2017

ELECTRIC SERVICE RATE SCHEDULES. Effective November 1, 2017 ELECTRIC SERVICE RATE SCHEDULES Effective November 1, 2017 SCHEDULE 100 RESIDENTIAL SERVICE Residential Customers for all domestic uses. CHARACTER OF SERVICE: Alternating current, sixty-hertz 120/240 volts

More information

Glendale Water & Power Smart Grid Project

Glendale Water & Power Smart Grid Project Glendale Water & Power Smart Grid Project Key Dates in Project History Key Dates Project History On July 10, 2007, City Council directed GWP to develop a long term plan for smart meters On October 23,

More information

Pacific Gas and Electric Company s Revised 2015 Annual Progress

Pacific Gas and Electric Company s Revised 2015 Annual Progress March 02, 2015 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Avista PO Box 3727 MSC-16 1411 East Mission Ave Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff 155 North 400 West

More information

received 1. Shyang (3 MW)- Completed 2. Tangling (5 MW)- Completed 3. Shaung (interim) (3 MW)--completed 4 Brua (Interim) (9 MW) - Completed

received 1. Shyang (3 MW)- Completed 2. Tangling (5 MW)- Completed 3. Shaung (interim) (3 MW)--completed 4 Brua (Interim) (9 MW) - Completed Agenda for discussions in the 44 th meeting of the STU Coordination Committee to be held under the chairmanship of Addl. Chief Secretary (MPP & Power) Sr. No. A 1.2. Progress Review of Transmission Projects

More information

System Status Briefing

System Status Briefing System Status Briefing Phakamani Hadebe Interim Group Chief Executive 3 May 2018 Contents 1 Performance summary 2 Operational highlights 3 Generation performance 4 Distribution overview 5 Transmission

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee March 6, 2014 1 2014 RTEP Update 2 2014 RTEP Update Initial 2019 Summer base case and corresponding machine list update complete PJM staff has been reviewing and

More information