1 Submission for the ACEC Canada Canadian Consulting Engineering Awards 2016 Western Alberta Transmission Line (WATL) HVDC Project Submitted by Teshmont Consultants LP as a Consultant to AltaLink
2 Attachment 1 Confirmation Receipt from the online Official Entry Form & Project Outline ACEC Canada Canadian Consulting Engineering Awards 2016
3 Phase 2 Bid Evaluation and Contract Award After a three month tendering period, Teshmont performed a comprehensive and detailed review of the bids submitted to evaluate conformance to the specifications and to assess the different offerings from a technical standpoint in order to provide AltaLink with a ranking of the bidders on a technical merit and value basis. The review also included a series of clarification questions and associated responses. Once a preferred bidder was identified, Teshmont supported AltaLink through the contract negotiations and prepared a conformed specification at the end of negotiations, which encapsulated all of the changes to the original specification that were agreed upon during the negotiations. The final contract for the converter stations was awarded to Siemens of Germany. Phase 3 Design, Manufacture, Installation, and Commissioning The third phase of the project was broken down into four distinct stages as follows: Stage 1: Design Review During the design review stage, Siemens was required to submit study reports, drawings, equipment specifications, schedules, plans, and other documents. Teshmont s job was to not only review these documents, checking for conformance to specified requirements but also to manage the flow of these submittals within the AltaLink/Teshmont team to ensure timely responses, which were critical in maintaining the project schedule. Teshmont also reviewed the design of the transmission line, which was being built under separate contracts managed by SNC Lavalin. The line design review included conductor and insulator selection, tower design, as well as minimum electrical clearances. Stage 2: Manufacturing During the manufacturing phase, Teshmont monitored Siemens progress and reviewed factory test plans and subsequent test results of major components. For the most critical components, Teshmont staff attended factory acceptance tests together with AltaLink staff to ensure the quality of the delivered equipment. Stage 3: Installation During site installation of the equipment, Teshmont supported AltaLink by providing feedback to any questions or concerns that arose. Teshmont staff, while not permanently on-site, did make site visit at key times to view progress. Stage 5 Commissioning During final energization and commissioning of the system, Teshmont reviewed the commissioning plan and was on-site for critical first energization and subsequent system testing up to achievement of full power transmission readiness on December 10, In addition to the above, Teshmont provided project management support and coordination throughout the lifecycle of the project, overseeing the effective and time critical flow of information between the various stakeholders. This involved management of the massive amounts of data flowing through the project SharePoint portal between all of the project stakeholders in a timely manner so as not to delay the project 5
4 schedule. Teshmont also had the responsibility of reviewing, vetting, and coordinating comments from various teams of subject matter experts involved in the project. Teshmont worked together with key AltaLink personnel throughout the project for training and technology transfer purposes. This was seen from the outset as a key factor to having a successful project, as this would be the first HVDC project for AltaLink and they would be ultimately be responsible for ongoing operation and maintenance of the system after it was commissioned. Project Complexities and Challenges The WATL Project was a $1.65 billion dollar project with multiple parties involved over a span of five years. Teshmont had to ensure that the technical specifications were clear and concise and that the contractors adhered to the technical specifications while remaining on schedule and within budget. In order to accomplish this, information exchange between stakeholders in a well-organized and timely manner was essential. Teshmont was responsible for setting up and managing a process and system for document submittal and review utilizing Microsoft SharePoint that ultimately was used on over 32,000 documents shared amongst a number of stakeholders over the course of the five year project. WATL also brought particular technical challenges as it was the first HVDC system to be energized in Alberta. Thorough study was essential to ensure that the initial 1000 MW line embedded in the heart of the existing Alberta electric system would not have any adverse effects. Some of the particular technical issues that had to be examined for WATL included: - Effects of commutation failures - Effects of transformer energization - Effects of transient overvoltages - Possible control interactions and power voltage instability - Effects on the rating of existing harmonic filters in other substations Another challenge was the potential impact of the transmission line on the countless pipelines found in the surrounding area. In many instances, HVDC systems are developed utilizing ground electrodes, which allow for the HVDC system to operate in ground current return mode for short periods of time during certain operating conditions. Utilization of a ground electrode allows for a much simpler, smaller, and less expensive design of the HVDC transmission line towers. However, operation utilizing a ground electrode may have undesirable impacts on nearby infrastructure, which would need to be examined and possibly mitigated. Due to the possible safety and operating concerns with the numerous oil and gas pipelines in the region, it was decided to develop the HVDC line with a metallic return conductor and avoid the use of ground electrodes. 6
5 The project schedule was another challenge. Despite the five year duration, a number of key activities throughout the project had very short timelines in order to meet key milestone dates. The initial front-end engineering study, design, specification, bid, review, negotiate, and award process for the converter stations was completed within six months compared with a more typical duration of eight to twelve months. Construction of the transmission line was also a challenge due to the relatively tight construction schedule. In order to expedite construction of the line, helicopters were used to assist with not only tower erection as shown in Figure 4, but also stringing of the line as shown in Figure 5. Figure 4: Tower Assembly Using a Helicopter Air Crane Figure 5: Conductor Stringing using a Helicopter 7
6 Innovation and Application of Technology The selection of HVDC transmission technology for interconnecting the major Alberta load centres of Calgary and Edmonton was made based on studies results that showed the technical advantages of HVDC over a similarly rated AC option were of higher benefit. Any HVDC project is technically complex and involves careful study and planning to ensure that the HVDC technology is properly applied and the WATL project was no exception. Power system analysis performed by Teshmont indicated that there were potential issues with interactions between the planned converter station and the Alberta interconnected electric system at the Crossings Converter Station near Langdon. In order to mitigate the identified issues, the project implementation required a STATCOM, which is a fast power electronic based regulating device used to provide precise voltage regulation. The STATCOM at Crossings Converter Station minimizes the impact on the AC system when the HVDC system s filter banks required to absorb the harmonics generated by the converters are switched in and out. The converters are controlled by state of the art high speed advanced control and protection systems, which are able to precisely regulate the amount and direction of power flow through the HVDC system. The control and protection systems are also able to quickly respond to disturbances in the adjoining AC network to help operators maintain system control and stability during outages. Another major application of advanced technology on the project was in the method of testing these control and protection systems in the factory. These tests took over two months and were performed in Siemens factory in Germany utilizing a power system real time digital simulator (RTDS). The RTDS is an advanced parallel processing super computer that, when loaded with a model of the power system, is able to simulate the response of a power grid to HVDC controls in real time. When connected to the simulator, the HVDC controls behave and respond as if they were in operation in the real power grid. This method allows for very accurate testing to be performed and modifications to be carried out on the HVDC controls without the risk of causing problems, including blackouts, in the real power system. While initially installed and commissioned for two terminal operation at 1000 MegaWatts (MW) maximum power transfer capability, the HVDC line has been designed to be upgraded to 3000 MW with no additional structures or conductors required. As well, the system has also been developed to support the potential future addition of more converter stations to form a multi-terminal scheme. Multi-terminal HVDC transmission is highly complicated from a HVDC control and protection perspective and currently there are only two such systems in operation in the world. Social/Economic/Environmental Impact As noted previously, HVDC technology was selected for a number of reasons, including the reduction of electrical power loses. As a result of these lower losses, the project is estimated to reduce carbon emissions by approximately 350,000 tonnes, which is the equivalent of removing 65,000 vehicles from Alberta s roads. 8
7 By selecting HVDC to interconnect the two largest load centres in the province, WATL will help to improve the overall reliability of electricity supply to consumers in these centres and in the province. Secure and dependable supply of electricity helps maintain a high quality of life, security, and productivity for the people of Alberta. The project also relieves transmission system congestion that existed in the existing AC network and that limited consumers access to the generator facility owners. As Alberta is the only truly deregulated energy market in North America, with consumers having choice in their electricity provider, unrestricted access to electricity generators results in increased competition and ultimately lower energy costs to consumers. The selection of HVDC also resulted in a transmission line whose towers are smaller in size and therefore take up less space than a similarly rated AC transmission line. This reduction in tower size results in less land being required for the line right-of-way and is less visually obstructive than a comparable AC transmission line. Finally, the application of HVDC has no observed negative effects on potential health impacts resulting from electric or magnetic fields. Conclusions The WATL project was significant and historic for both AltaLink, as well as the electric power system in Alberta. Teshmont was instrumental in helping AltaLink throughout the five years of development and implementation of the project by working closely to provide technical leadership, guidance, advice, and training for the successful operation of the WATL HVDC Project. Thanks in large part to Teshmont s extensive involvement in the project, the WATL HVDC Project will provide environmental, economic, and societal benefits for all Albertans throughout its life. 9
8 Attachment 4 Photographs ACEC Canada Canadian Consulting Engineering Awards 2016
Part 3 Agreement Programs for 2017 and Greenhouse Gas Reduction (Renewable and Low Carbon Fuel Requirements) Act
Part 3 Agreement Programs for 2017 and 2018 Greenhouse Gas Reduction (Renewable and Low Carbon Fuel Requirements) Act Ministry of Energy, Mines and Petroleum Resources Government of British Columbia August
CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.
25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context indicates otherwise, this section and 25.212 of this title (relating to Technical Requirements
Inactive Well Compliance Program (IWCP)
Inactive Well Compliance Program (IWCP) Year Two Final Report In addition to Bulletin 2014-19, Alberta Energy Regulator (AER) July 2017 The Alberta Energy Regulator s (AER) Inactive Well Compliance Program
welcome to the BC Hydro community open house
welcome to the BC Hydro community open house Dawson Creek/ Chetwynd Area Transmission ProjecT Open House welcome Dawson Creek/Chetwynd Area Transmission Project (DCAT) The purpose of this open house is
Reliable, economical and safe siemens.com/rail-electrification
AC Traction Power Supply Reliable, economical and safe siemens.com/rail-electrification More people, new challenges, one solution: Integrated mobility. Demographic change, urbanization and climate change:
ABB POWER SYSTEMS CONSULTING
ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February
ABB life cycle services Uninterruptible power supplies
ABB life cycle services Uninterruptible power supplies 2 ABB Life cycle brochure UPS service portfolio Life cycle services for uninterruptible power supplies As your service partner, ABB guarantees you
Evaluating Stakeholder Engagement
Evaluating Stakeholder Engagement Peace River October 17, 2014 Stakeholder Engagement: The Panel recognizes that although significant stakeholder engagement initiatives have occurred, these efforts were
WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017
WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 TODAY WE LL TALK ABOUT Our challenges and how we re meeting them Why we re building this project Our planning process and considerations
Low and medium voltage service. Power Care Customer Support Agreements
Low and medium voltage service Power Care Customer Support Agreements Power Care Power Care is the best, most convenient and guaranteed way of ensuring electrification system availability and reliability.
California Energy Storage Policies. Carla Peterman Commissioner, California Public Utilities Commission December 2016
California Energy Storage Policies Carla Peterman Commissioner, California Public Utilities Commission December 2016 California Storage Law and Policy l California has supported energy storage through
TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008
NB Power Customer Service and Distribution June 2008 Prepared by: Steven Wilcox Revised by: Steven Wilcox TABLE OF CONTENTS 1.0 Introduction 4 2.0 NB Power Policy on Independent Power Production 4 3.0
Modernising the Great Western railway
Report by the Comptroller and Auditor General Department for Transport and Network Rail Modernising the Great Western railway HC 781 SESSION 2016-17 9 NOVEMBER 2016 4 Key facts Modernising the Great Western
Civil Engineer. Tasks
Civil Engineer Are you ready to be a technology pioneer? Oil and gas factories 3000 meters underwater, heavy locomotive traction motors, electric vehicle chargers that deliver 100kw in 30 minutes... you
Interconnection System Impact Study Report Request # GI
Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010
Comhairle Cathrach Chorcaí Cork City Council
Transportation Division City Hall Cork Response to the Consultation Paper on the ESBN Electric Vehicle Pilot & Associated Assets Reference CER/16/286 Introduction welcomes the opportunity to respond to
REGIONAL TRANSMISSION ORGANIZATIONS / INDEPENDENT SYSTEM OPERATORS AND THE ENERGY IMBALANCE MARKET: AN OVERVIEW OF THE PICTURE IN THE WEST
REGIONAL TRANSMISSION ORGANIZATIONS / INDEPENDENT SYSTEM OPERATORS AND THE ENERGY IMBALANCE MARKET: AN OVERVIEW OF THE PICTURE IN THE WEST MEGAN O REILLY COALITION FOR CLEAN AFFORDABLE ENERGY EPE IRP STAKEHOLDER
Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers
Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,
2015 Grid of the Future Symposium
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,
15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
Environment and Infrastructure Services
Agenda Item 5 Staff Report for Committee of the Whole Meeting Department: Division: Subject: Environment and Infrastructure Services Environment Services Waste Collection Contract Purpose: To provide Council
JCP&L Verbatim Response to Middletown Township s Questions
JCP&L Verbatim Response to Middletown Township s Questions Township officials sent 13 questions about the proposed Monmouth County Reliability Project to JCP&L on June 10 th. JCP&L provided direct responses
Summary of survey results on Assessment of effectiveness of 2-persons-in-the-cockpit recommendation included in EASA SIB
Summary of survey results on Assessment of effectiveness of 2-persons-in-the-cockpit recommendation included in EASA SIB 2015-04 23 May 2016 EXECUTIVE SUMMARY The European Aviation Safety Agency (EASA)
Modular Standardized Electrical and Control Solutions for Fast Track Projects
Modular Standardized Electrical and Control Solutions for Supporting fast track projects ABB is the leading supplier of electrical and control equipment for power plants. The company offers a comprehensive
Request for Assistance (RFA)
Request for Assistance (RFA) RFA #: FY15-Consultant Canvas Development - 2 Issued on: July 13, 2017 For: Development services to support the implementation of an open-source instance of the Canvas LMS
Genting Plantations Berhad
Particulars About Your Organisation Organisation Name Genting Plantations Berhad Corporate Website Address http://www.gentingplantations.com Primary Activity or Product Oil Palm Growers Related Company(ies)
WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM
1 1 The Latest in the MIT Future of Studies Recognizing the growing importance of energy issues and MIT s role as an honest broker, MIT faculty have undertaken a series of in-depth multidisciplinary studies.
Transmission s Future Today. High Capacity High Efficiency Low Profile
Transmission s Future Today High Capacity High Efficiency Low Profile BOLD TM Breakthrough in Overhead Line Design BOLD is a compact transmission line design that combines the advantages of higher capacity,
Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program
Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program As part of our commitment to support renewable energy, Kissimmee Utility Authority
Unitil Energy Demand Response Demonstration Project Proposal October 12, 2016
Unitil Energy Demand Response Demonstration Project Proposal October 12, 2016 Fitchburg Gas and Electric Light Company d/b/a Unitil ( Unitil or the Company ) indicated in the 2016-2018 Energy Efficiency
Decision Blaze Energy Ltd. Application for an Exemption under Section 24 of the Hydro and Electric Energy Act.
Decision 2014-108 Application for an Exemption under Section 24 of the Hydro and Electric Energy Act April 17, 2014 The Alberta Utilities Commission Decision 2014-108: Application for an Exemption under
15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
APPENDIX F: Project Need and Description
APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was
Oil Palm Growers Operational Profile 1.1 Please state your main activities as a palm oil grower Palm oil grower & miller Operations and Certification
Particulars About Your Organisation Organisation Name Corporate Website Address Primary Activity or Product Oil Palm Growers Related Company(ies) Company Primary Activity RSPO Member PT Arta Prigel Oil
Looking Towards the Future: Advantages of 765-kV Transmission Technology
Looking Towards the Future: Advantages of 765-kV Transmission Technology In the electric transmission business, design plays a key role in the efficiency and productivity of the nation s energy delivery
Guidelines for connection of generators:
Guidelines for connection of generators: Greater than 30 kva, and not greater than 10 MW, to the Western Power distribution network January, 2017. EDM 32419002 / DM 13529244 Page 1 of 14 Contents 1 INTRODUCTION...
Reliability is our profession
Reliability is our profession Drive components for wind turbines Siemens AG Am Industriepark 2 46562 Voerde Germany Phone +49 2871 92-4 Fax +49 2871 92-2487 E-Mail info@winergy-group.com www.winergy-group.com
Fund and 2015 revenue bonds Est. State and Local Taxes: $2,810,000
PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 6b ACTION ITEM Date of Meeting August 4, 2015 DATE: TO: FROM: Dave Soike, Director, Aviation Facilities and Capital Programs Wayne Grotheer, Director,
June Safety Measurement System Changes
June 2012 Safety Measurement System Changes The Federal Motor Carrier Safety Administration s (FMCSA) Safety Measurement System (SMS) quantifies the on-road safety performance and compliance history of
ABB Wind Power Solution
Feng Li, Wind ISI, CNABB, November, 2016 ABB Wind Power Solution November 13, 2016 Slide 1 ABB deliveries from A to Z into the wind industry Wind power generation, transmission and integration, control
Transmission Grid Reinforcement with Embedded VSC-HVDC. Jonatan Danielsson, Sugam Patel, Jiuping Pan, Reynaldo Nuqui
Transmission Grid Reinforcement with Embedded VSC-HVDC Jonatan Danielsson, Sugam Patel, Jiuping Pan, Reynaldo Nuqui Outline Introduction HVDC-Light Transmission Technologies Embedded VSC-HVDC for AC Grid
Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station
Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station East Asian Alternative Energy Futures Workshop By the Nonproliferation Policy Education Center
GE Energy Management. GE s electrification and automation business
GE Energy Management GE s electrification and automation business MODERNIZING THE GRID FROM THE POWER PLANT TO THE POWER CONSUMER Who We Are Digital Energy, a division of GE Energy Management, is a global
Full-Scale Medium-Voltage Converters for Wind Power Generators up to 7 MVA
Full-Scale Medium-Voltage Converters for Wind Power Generators up to 7 MVA Philippe Maibach, Alexander Faulstich, Markus Eichler, Stephen Dewar ABB Switzerland Ltd CH-5300 Turgi, Switzerland Phone: +41
Green Line LRT: Beltline Recommendation Frequently Asked Questions
Green Line LRT: Beltline Recommendation Frequently Asked Questions June 2017 Quick Facts Administration has evaluated several alignment options that would connect the Green Line in the Beltline to Victoria
INDUSTRIAL AGRARIA LA PALMA LIMITADA-INDUPALMA LTDA
Particulars About Your Organisation Organisation Name INDUSTRIAL AGRARIA LA PALMA Corporate Website Address www.indupalma.com Primary Activity or Product Oil Palm Growers Processor and/or Trader Related
Supplemental Report on the NCTPC Collaborative Transmission Plan
Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for
Request for Qualifications. for
ST. VINCENT ELECTRICITY SERVICES LIMITED and THE ROCKY MOUNTAIN INSTITUTE CARBON WAR ROOM Request for Qualifications for Mayreau Microgrid Project Engineering, Procurement and Construction Contract for
ELECTRIC TRANSMISSION 101: Operational Characteristics. Wayne Galli, Ph.D., P.E. Executive Vice President Clean Line Energy Partners LLC
ELECTRIC TRANSMISSION 101: Operational Characteristics Wayne Galli, Ph.D., P.E. Executive Vice President Clean Line Energy Partners LLC Objectives Primary objective is to understand how the power system*
RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES
RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES Last Revised Date: October 15, 2015 Contents Chapter 1 - Purpose and Scope 2 Chapter 2 - Application of Rules 2 Chapter 3 - Definitions
A Recommended Approach to Pipe Stress Analysis to Avoid Compressor Piping Integrity Risk
A Recommended Approach to Pipe Stress Analysis to Avoid Compressor Piping Integrity Risk by: Kelly Eberle, P.Eng. Beta Machinery Analysis Calgary, AB Canada keberle@betamachinery.com keywords: reciprocating
Guri Dam. Ingenuity and energy
Guri Dam Modernization of the Guri hydroelectric plant s control, protection and instrumentation system Eduardo Colmenares, Daniel Rubinstein, Miguel Florez In 2005, ABB was awarded a contract to design,
PT Perkebunan Nusantara IV (PERSERO)
Particulars About Your Organisation Organisation Name PT Perkebunan Nusantara IV (PERSERO) Corporate Website Address http://www.ptpn4.co.id Primary Activity or Product Oil Palm Growers Related Company(ies)
Solar-Wind Specific Request for Proposals
Program Description Solar-Wind Specific Request for Proposals Power Production from Green Resources in North Carolina 04/19/2006 NC GreenPower (NCGP) is a statewide program designed to improve the quality
DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY
DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION
HVDC Back-to-Back Interconnections Enabling reliable integration of power system
HVDC Back-to-Back Interconnections Enabling reliable integration of power system Dr Liliana Oprea FICHTNER GmbH&Co KG Swiss Chapter of IEEE PES Baden-Dättwil, 4 September 2013 Table of Contents Need for
Operational Profile 1.1 Please state your main activities as a palm oil grower Palm oil grower (no mill) Operations and Certification Progress T
Agrofinanz GmbH Particulars Organisation Name Corporate Website Address Primary Activity or Product Related Company(ies) Country Operations Agrofinanz GmbH www.agrofinanz.de None Ecuador Membership Number
HVDC. TMT&D provides the best and most economical HVDC system.
HVDC TMT&D HVDC TMT&D provides the best and most economical HVDC system. In 1955, TMT&D started the development of HVDC and is the leading HVDC supplier in Japan. TMT&D has continued to develop HVDC technology
Montreal Metro s AZUR Cars
Montreal Metro s AZUR Cars 2017 Canadian Consulting Engineering Awards Groupement DST ii What s Inside Project Overview... 1 Innovation... 3 Complexity... 4 Social and Economic Benefits... 6 Environmental
2 x 25 kv ac / 1 x 25 kv ac Grounding and Bonding
2 x 25 kv ac / 1 x 25 kv ac Grounding and Bonding By George Ardavanis, PhD Keywords: overhead catenary system (OCS), electric multiple unit (EMU), grounding and bonding (G&B), overhead contact line (OCL),
40kW (and under) Solar/Inverter Installations Generation Interconnection Application to Minnesota Power
40kW (and under) Solar/Inverter Installations Generation Interconnection Application to Minnesota Power WHO SHOULD FILE THIS APPLICATION: Anyone expressing interest to install generation which will interconnect
MANAGING NEW CONNECTIONS FOR YOUR BUSINESS
e-guide MANAGING NEW CONNECTIONS FOR YOUR BUSINESS A guide to establishing a new electricity supply 2/16 Co-ordinating your new connections effectively Progressing from your first supply request to finally
Operational Profile 1.1 Please state your main activities as a palm oil grower Palm oil grower & miller Operations and Certification Progress To
PT Bukit Barisan Indah Prima Particulars Organisation Name PT Bukit Barisan Indah Prima Corporate Website Address Primary Activity or Product Related Company(ies) Company Primary Activity RSPO Member PT
TABLE OF CONTENTS SECTION TITLE PAGE NUMBER
WORKER FATALLY INJURED IN HAUL TRUCK COLLISION IN MINE Type of Incident: Fatality Date of Incident: November 23, 2009 TABLE OF CONTENTS SECTION TITLE PAGE NUMBER 1.0 DATE AND TIME OF INCIDENT 3 2.0 NAME
Electrical District No. 3 SOLAR Q & A
D3 Electrical District No. 3 SOLAR Q & A What are some things I should consider before going solar? Leasing verses owning: Know the Pros and Cons of each, as well as the Short-term and Long-Term effects
The role of Transmission System Operator in Belgium and in Europe. Vlerick Alumni Event 26 January 2016
The role of Transmission System Operator in Belgium and in Europe Vlerick Alumni Event 26 January 2016 Agenda Introduction Infrastructure management Controlling the system Developing the EU Market 1/25/2016
Omaha Public Power District. Distributed Generation (DG) Manual
Omaha Public Power District Distributed Generation (DG) Manual A Guide to the Interconnection of Distributed Generation with the OPPD System This document is subject to change without notice. Please contact
Power Transmission Division Erlangen, April 29, Siemens Completes Installation of Second HVDC Converter Platform for TenneT
Energy Sector Press Power Transmission Division Erlangen, April 29, 2014 Siemens Completes Installation of Second HVDC Converter Platform for TenneT Major step forward for the offshore expansion of the
CONTACT: Mike Hedge Hedge & Company, Inc. Public Relations (cell) FOR: Planning Perspectives, Inc.
FOR: Planning Perspectives, Inc. Birmingham, MI HOLD FOR RELEASE UNTIL 12:01 a.m. EDT MONDAY, May 23, 2011 CONTACT: Mike Hedge Hedge & Company, Inc. Public Relations 248-789-8976 (cell) mhedge@hedgeco.com
Engineers Journal I Volume 60: Issue 10 I December 2006
CPD helps ABB Dundalk establish profitable, stand-alone business The successful undertaking by ABB Ltd (Dundalk) of its international parent company s entire actuator business countered a global rationalisation
Green Line LRT: Beltline Segment Update April 19, 2017
Green Line LRT: Beltline Segment Update April 19, 2017 Quick Facts On April 11, 2017, City Council approved Administration s recommendation for the Green Line to be underground in the Beltline from 2 Street
INTERCONNECT CHALLENGES IN THE DEVELOPING WORLD S DISTRIBUTED GENERATION INFANCY. David C. Oehl, P.E. President MAVEN POWER
INTERCONNECT CHALLENGES IN THE DEVELOPING WORLD S DISTRIBUTED GENERATION INFANCY David C. Oehl, P.E. President MAVEN POWER September 2006 TABLE OF CONTENTS OVERVIEW...3 PROJECT BACKGROUND...4 POWER PLANT
BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014
1 BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada IEEE PES Meeting July 2014 General BC Hydro Overview Crown Corporation Serving about 95% of province and 1.9 million customers
The Grid Link Project. Summary of the Report for the Independent Expert Panel
The Grid Link Project Summary of the Report for the Independent Expert Panel Who are EirGrid - and what do we do? EirGrid is responsible for a safe, secure and reliable supply of electricity: now and in
EVSE Permitting and Inspection Best Practices
EVSE Permitting and Inspection Best Practices The Permitting and Inspection Process for Plug-in Electric Vehicle Charging EVITP EV Community Readiness Seminar [Photo Courtesy: General Electric] This report
Cigre SC B4 Activities Towards HVDC Grids. HVDC Grid Workshop Belgium
Cigre SC B4 Activities Towards HVDC Grids Bjarne Andersen Chairman of Cigre Study Committee B4 HVDC and Power Electronics HVDC Grid Workshop Belgium 2014 1 Contents Why build HVDC Grids? Types of HVDC
Background. If It Ain t Broke CASE STUDY
Pratt & Whitney unlocks new capabilities and value by streamlining their infrastructure with an upgrade and consolidation from MCA v7 and SPM v9 to SPM v11 solution Pratt & Whitney When Pratt & Whitney
ABB low voltage wind turbine converters Reliable technology for wind power
ABB low voltage wind turbine converters Reliable technology for wind power Profile The wind power market continues to expand Today s wind turbine manufacturers and wind farm owners are experiencing steady
Guidelines for Safety Training of Overhead Crane Operators and Supervisors
Guidelines for Safety Training of Overhead Crane Operators and Supervisors Purpose These guidelines present minimum recommended safety requirements for ensuring the safe and efficient operation of overhead
Smart Grid A Reliability Perspective
Khosrow Moslehi, Ranjit Kumar - ABB Network Management, Santa Clara, CA USA Smart Grid A Reliability Perspective IEEE PES Conference on Innovative Smart Grid Technologies, January 19-21, Washington DC
A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution
A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Electrical.1_ UFSS#p A:_. DAVID/ IC, L re Mechanical Civil Protection & Control an LAND& 4^ Transmission & Distribution Telecontrol System Planning
Bharat Heavy Electricals Limited, Electronics Division, Bangalore, India.
Document: BHEL/EDN/SCPV/D91/EOI Revision: 01 Date: 12-Oct-2009 EXPRESSION OF INTEREST (EOI) FOR TECHNOLOGY PARTNERSHIP IN SEMICONDUCTOR DEVICE MANUFACTURING (IGBT Encapsulation Technology, Expansion of
REQUIREMENTS FOR APPROVAL OF AN ONLINE - DEFENSIVE DRIVING COURSE (O-DDC) Defensive Driving. Course. Online. Online DDC December 2007 Page 1 of 11
Defensive Driving Course Online Online DDC December 2007 Page 1 of 11 Alberta Transportation Alberta Transportation Driver Programs & Licensing Standards Driver Programs & Licensing Standards 1 st Floor,
Powering Sydney s Future
Powering Sydney s Future Frequently Asked Questions December 2017 Project background Q: Why is this project needed? A: Inner Sydney is one of the most critical parts of the NSW electricity network. However,
STAFF REPORT ACTION REQUIRED
nsert TTC logo here STAFF REPORT ACTION REQUIRED Gap Between Subway Trains and Platforms Date: November 13, 2017 To: From: TTC Board Chief Executive Officer Summary This report is in response to an October
commercial epc services
commercial epc services commercial epc services With our origins in O&M, SunSystem Technology gained a great deal of insight into underproductive solar construction and developed a comprehensive set of
Electric Transmission 101 or Everything You Wanted to Know About the Grid But Were Afraid to Ask. Gerald Deaver Manager Regional Transmission Policy
Electric Transmission 101 or Everything You Wanted to Know About the Grid But Were Afraid to Ask Gerald Deaver Manager Regional Transmission Policy Some Xcel Energy Statistics Transmission Business 19,000
Refurbishment & Upgrade of the Celilo HVdc Converter Station
1 Refurbishment & Upgrade of the Celilo HVdc Converter Station Mark A Reynolds, PE Sr. Project Manager, POWER Engineers mark.reynolds@powereng.com Karl A Mitsch, P.E. Sr. Project Manager USDOE Bonneville
Technical Support for Electric Vehicle Charging Requirements in the Building Code that are in effect January 1, 2018
Technical Support for Electric Vehicle Charging Requirements in the Building Code that are in effect January 1, 2018 Non-residential Buildings Questions and Answers Provided on December 19, 2017 This document
100 MW Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility
ABB Group August 27, 2010 Slide 1
Michael Bahrman P.E., ABB Grid Systems, August 31, 2010, Asia Pacific Clean Energy Summit 2010, Honolulu Integration of Variable Renewable Energy for Hawaii Transmission of Isolated Resources August 27,
PHILIPPINE DISTRIBUTION CODE 2017 EDITION
PHILIPPINE DISTRIBUTION CODE 2017 EDITION PDC 2017- Background Revised the PDC 2001 Starts of revision in 2010 April 18 and 24, 2012 conducted a series of expository presentation for Visayas and Mindanao
LAJKONIK SNACKS SP Z.O.O
Particulars About Your Organisation Organisation Name LAJKONIK SNACKS SP Z.O.O Corporate Website Address Primary Activity or Product Manufacturer Related Company(ies) Membership Membership Number Membership
Sections: Monitoring your motors Where to look for savings Power factor improvement Voltage unbalance The Bottom Line...
TABLE OF CONTENTS 1. GENERAL LABOUR COSTS EQUIPMENT COSTS...2
TABLE OF CONTENTS 1. GENERAL...2 2. LABOUR COSTS...2 3. EQUIPMENT COSTS...2 4. DISTRIBUTION MATERIAL COSTS (EDS AND OIL AND GAS FIELD SERVICE MODELS)..3 5. STREET LIGHTING...3 6. TRANSMISSION LINES...3
B kv T&D GAS INSULATED SWITCHGEAR
GAS INSULATED SWITCHGEAR B 105 170 300 kv The increasing demand for electrical power in cities and industrial centers necessitates the installation of a compact and efficient distribution and transmission
AEP Ohio Distribution Reliability and Technology Programs
AEP Ohio Distribution Reliability and Technology Programs Overview of Technologies and Reliability Plans gridsmart Phase II Case No. 13-1939-EL-RDR Advanced Metering Infrastructure (AMI) Distribution Automation
Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System
Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Adopted Based on State and Tariff Interconnection Rules Applicable to Northern States Power,
SYSTEM INTEGRATION. Railway and urban transport electrification Energy-efficient and reliable solutions
SYSTEM INTEGRATION Railway and urban transport electrification Energy-efficient and reliable solutions 2 R A I LWAY & U R B A N T R A N S P O R T E L E C T R I F I C AT I O N S O L U T I O N S ABB s substation
Power Transmission Division Erlangen, April 29, 2014
Energy Sector Press Power Transmission Division Erlangen, April 29, 2014 Siemens Completes Installation of Second HVDC Converter Platform for TenneT Major step forward for the offshore expansion of the