Proposed Dounreay - Mybster 275 kv / 132 kv
|
|
- Lizbeth Harrell
- 5 years ago
- Views:
Transcription
1 Background Scottish Hydro-Electric Transmission Ltd (SHETL) is proposing a new 275 kilovolt (kv) (1 kilovolt = 1000volts) double circuit overhead line (OHL) between the Dounreay sub station and the new Spittal substation via the new Thurso South substation. This new OHL will replace the existing 132 kv double circuit OHL. In addition SHETL is proposing to construct a new 132 kv OHL which would run in parallel with the existing 132 kv OHL between the new Spittal substation and an extension of the existing Mybster substation. This proposal is part of the reinforcement of the electricity transmission network, envisaged by the National Planning Framework (NPF2) and the Energy Networks Strategy Group. Analysis of the existing transmission network in the north of Scotland identified the need for increased network capacity to facilitate the transmission of renewable generation projects north of Beauly including onshore/offshore wind and marine and tidal generation. This increase in network capacity can only be achieved by undertaking reinforcement of the transmission network in the north of Scotland. The diagrams below provide an indication of the extent of the proposed generation developments in the area. This is one of several elements of work to reinforce and extend the transmission system in the area, referred to collectively as the Caithness, Moray, Shetland (CMS) transmission reinforcements. Other elements include multi-terminal high voltage direct current (HVDC) links. This poster presentation is in relation to the new 275kV and 132kV OHL between Dounreay and Mybster, the new Thurso South substation and the extension works to the existing Mybster substation. Growth in Renewable Energy Generation Offshore Renewable Generation Onshore Renewable Generation Hydro Power Activity (December 2011) Highland Windfarm Development (May 2012) 1
2 Project Description The aim of the project is to strengthen the high voltage network in Caithness with the replacement/upgrade of the existing 132 kv overhead line (OHL) between the substations at Dounreay, Thurso and Mybster with new higher capacity infrastructure. The main elements of the project are as follows: Construction of a new double circuit 275 kv OHL (lattice steel tower) from the Dounreay substation to the proposed 275/132 kv substation and HVDC converter station at Spittal, via a new substation near Thurso (c. 26km). This will replace the existing 132kV OHL between Dounreay and Spittal. Project Overview Map Legend Dounreay to Thurso South 275 kv Thurso South to Spittal 275 kv Spittal to Mybster 132 kv Connection of the new 275 kv OHL to the new 275 kv / 132 kv Gas Insulated Switchgear (GIS) substation at Dounreay, which is currently under construction via a different project. Construction of the new Thurso South 275 kv / 132 kv / 33 kv substation, and associated works to connect the existing 33kV distribution infrastructure to the new substation. Connection of the new 275 kv OHL to the new 275/132 kv substation and HVDC converter station at Spittal, which is currently being progressed via a different project. Construction of a new double circuit 132 kv OHL (lattice steel tower) between the new Spittal 275/132 kv sub station and HVDC converter station and the existing Mybster substation (c. 4km). This will run in parallel with the existing 132 kv OHL between the Spittal substation and the existing Mybster substation. Construction of 132 kv infrastructure at the existing Mybster substation. These works will be adjacent to the north of the existing substation. Connection of the new 132 kv OHL to the new 275/132 kv substation and HVDC converter station at Spittal, and to the new 132 kv infrastructure at the existing Mybster substation. The project overview map is presented opposite. Consultation Process As well as endeavouring to select the best possible route for the proposed overhead line reinforcement, we want to keep everyone affected by the proposal informed of our intentions. We firmly believe that early and regular communication and consultation with those likely to be affected by the proposal forms a critical part of its development. A route for the new overhead lines, shown on the plan above, was selected by undertaking a series of studies to determine technical feasibility, economic viability, land use and any environmental constraints. These were then reviewed together to identify the preferred route that balanced each of these considerations. As part of the environmental studies we are consulting with the Highland Council, statutory and non-statutory bodies and other interested parties to collect many types of baseline information including landscape and visual amenity, nature conservation, cultural heritage, archaeology and land use. We also undertook a similar site selection process to determine the preferred site for the new Thurso South substation. This was presented at a public exhibition held in February Following this event, the proposed site was selected and a Proposal of Application Notice submitted to the Highland Council as part of the Town & Country Planning (Scotland) Act 1997 major development obligations. Have Your Say This exhibition is your opportunity to comment on and ask questions about our proposals so far. We would greatly appreciate it if you would take the time to fill out our short questionnaire and post it in the comments box. Alternatively, you can write to: Lisa Kelly Scottish Hydro Electric Transmission Ltd 10 Henderson Road Inverness IV1 1SN Please submit your comments on the OHL works by Monday 16th July Project program The current programme for the project is shown below: Develop and compare sub station sites / route options Complete Identify preferred sub station sites Complete Undertake public exhibition for preferred sub station sites Complete Submit Proposal of Application Notice for sub station site Complete Identify preferred route for overhead lines Complete Publish consultation document on overhead lines Complete Undertake public exhibition for all project elements July 2012 Refine the preferred route and select a proposed route July 2012 Complete Environmental Impact Assessment October 2012 Apply for consents November 2012 Start Construction Early 2014 Phased completion and commissioning Dismantling of the existing 132 kv lines
3 Overhead Routing Study Process The Route Selection Process We have worked closely with a team of environmental consultants and overhead line engineers to identify a technically feasible (both in terms of constructability and long term maintenance), economically viable, new transmission OHL which gives rise to: least disruption to the amenity of people living and working in the area; least impact on the physical and natural environment, and on nationally important species, habitats and cultural assets; least disruption to current land use and management practices; and least disruption to existing and proposed infrastructure and other economically beneficial uses of land. Legend Dounreay to Thurso South 275 kv Thurso South to Spittal 275 kv Spittal to Mybster 132 kv Dounreay to Thurso South 275 kv A number of 2km wide route corridor options were assessed, taking into account the technical requirements to connect to the existing electricity network. A process of analysis and comparison of potential routes within the 2km corridors was then followed. The assessment has been based on : detailed baseline data on land use and environmental character and sensitivity, obtained from desk sources and site visits; identification of potential effects, to inform strategies for enhancing positive outcomes and for avoiding, reducing, controlling or offsetting potentially undesirable or significant negative outcomes; initial consultations with key stakeholders to inform the above and the subsequent refinement of the routing study and selection of the preferred Thurso South to Spittal 275 kv Spittal to Mybster 132 kv The Preferred Reinforced Transmission Route A preferred route for the proposed reinforcement is shown on the accompanying plans. The final, proposed route will be determined after this detailed consultation and will be subject to an environmental impact assessment. The preferred route has been identified, which on the basis of the route selection process is considered to represent the optimum balance of technical, economic and environmental feasibility. The precise route alignment of the OHL and the location of individual towers will be determined following completion of ongoing detailed surveys to identify engineering, land use or environmental constraints which may require localised modifications to the route. Towers The OHL will be constructed using self-supporting lattice steel towers. The towers used for the 275 kv OHL will vary in height between 32m and 52m to accommodate changes in topography and where the line crosses roads and rivers, although the height will generally be in the region of 40m. The 132kV OHL towers will vary in height between 23m and 38m, although the height will generally be in the region of 28m. The spacing between towers will vary depending on topography, altitude and land usage. The height and distance between towers will be determined later in the design process; however the spacing will be generally in the range of m for the 275 kv towers and m for the 132 kv towers. Construction High voltage OHL construction typically follows a standard sequence of events which are: complete pre-construction surveys, as required by a construction environmental management plan; establish access (including any necessary vegetation management); install tower foundations; assemble and erect towers; erect temporary scaffolds and protection to roads, railways and rivers; erect conductors (wires); dismantle and remove temporary scaffolds and protection; and, re-instate tower sites and remove temporary access tracks It is anticipated that the construction programme will last approximately 34 to 36 months. We would hope to start in January 2014 to allow the completion of construction by December The detailed construction phasing and programme will be subject to change as the design progresses and also due to necessary consents and wayleaves being agreed. On completion of the commissioning the existing lattice steel towers between Dounreay and Spittal will be removed. 3
4 Proposed Dounreay - Mybster 275 kv / 132 kv Route Selection - Dounreay to Thurso South 275 kv New Thurso South substation This part of the preferred route follows an alignment between the Dounreay substation and the new Thurso South substation at a location near Geiselittle. It runs parallel to and approximately 90 m north of the existing Dounreay-Mybster 132 kv OHL from Dounreay, until it reaches the crossing of the B870 at Moss of Geise. It traverses on to the south side of the existing 132 kv line at this point (the existing 132 kv OHL will ultimately be removed), turning slightly to the north east to cross the railway line and River Thurso at a point approximately 350 m south of the existing 132 kv OHL, terminating at the new Thurso South substation. Route Selection - Thurso South to Spittal 275 kv Route Selection - Spittal to Mybster 132 kv New Thurso South substation New Spittal substation New Spittal substation This part of the preferred route follows a route between the new Thurso South This part of the preferred route runs between the new Spittal substation and the substation near Geiselittle and the new Spittal substation. existing Mybster substation. It initially runs south east from the new Thurso South substation before turning It runs in parallel to the existing Dounreay-Mybster 132 kv OHL, on the east side. southwards at Todholes Farm to cross the railway line and River Thurso. It then turns The existing 132 kv OHL would remain between Spittal and Mybster following to the south east to cross the river again approximately 500 m north of Hoy and Braal construction of the proposed 132 kv OHL. Holdings before turning to run north to south, from where it runs parallel to the existing 132 kv OHL until it reaches the new Spittal substation. 4
5 Thurso South Substation - Background Project Overview Map A new 275/132/33 kv substation is required as part of the Caithness Transmission Reinforcement. The substation will connect the new 275kV OHL to the high voltage 33kV distribution network at the existing Thurso substation. There will be new underground cabling from the substation for the connections into the existing 33kV network. SHETL previously identified four possible sites for the substation, which were the subject of a site selection process. This involved undertaking a series of studies and identifying the most suitable site, balancing technical and environmental issues, effects on local community, land ownership and land use issues, and overall network economics. Discussions were held with the Highland Council, statutory and non statutory bodies in order to gain a greater understanding of the key factors likely to influence development at the site. A public exhibition was also held in February 2012 to seek comments from the other interested parties. Indicative Electrical Layout Indicative Electrical Layout Thurso South Substation Description A new access will be constructed from the A9 to the north-east of the proposed site. The footprint of the proposed substation and associated infrastructure would be approximately 9.1 Hectares including embankments. The construction area would be 21.5 Hectares. The tallest structure within the site will be the proposed control building which would be of an agricultural type structure, approx. 35m x 20m x 10m high. The site would include parking and manoeuvring space for operation and maintenance of the facility. Existing trees will be retained for screening purposes and further landscaping will be placed in appropriate places on site. This will be determined following the landscape and visual assessment. 5
6 Mybster Substation - Background Project Overview Map The new 132 kv infrastructure at the Mybster substation is required as part of the Caithness Transmission Reinforcement, due to generation developer connection requirements to the transmission network. The existing transmission lines between the Mybster substation and the proposed Spittal substation are already at capacity. Reinforcement is required to increase security of supply and to connect new generation to the 275kV network at Spittal rather than install a number of separate overhead lines and/or cables for each connection. The extension of the existing substation as opposed to a new substation is driven by the requirement for the existing developer connections to be diverted onto the new OHL (Spittal to Mybster 132 kv). This also reduces the need for further infrastructure to make the connections to the new OHL. As a result, no site selection process was required. As part of the environmental studies we are consulting with the Highland Council, and other key statutory bodies to collect many types of baseline information including landscape and visual amenity, nature conservation, cultural heritage, archaeology and land use. A pre planning meeting with the Highland Council has been undertaken, and the Proposal of Application Notice (PAN) has been submitted. Mybster Substation Description Indicative Electrical Layout Mybster Extension Works Description The works involve extending the existing 132kV/33KV Mybster substation to the north. A new access will be constructed off the A9. The footprint of the proposed extension will be approximately 3 Hectares. The height of the perimeter fence will be 2.4m, the highest 132kV busbar will be approximately 7m and the highest 132kV tower 40m. The site would include adequate parking and manoeuvring space for operation and maintenance of the facility. The control building would be of an agricultural / industrial type structure, approximately 33m x 20m x 7m high. 6
SUPPLEMENTARY EVIDENCE FROM SCOTTISH AND SOUTHERN ENERGY
SUPPLEMENTARY EVIDENCE FROM SCOTTISH AND SOUTHERN ENERGY Scottish Parliament - Economy, Energy & Tourism Committee National Planning Framework - Evidence Session 14 th January 2009 SHETL Response 1. Key
More informationScottish and Southern Electricity Networks
Scottish and Southern Electricity Networks Who we are Our licence stipulates that we must develop and maintain an efficient, co-ordinated and economical system of electricity transmission. What is the
More informationChirmorie Wind Farm Grid Connection
Chirmorie Wind Farm Grid Connection Welcome Welcome to this public exhibition regarding our proposals to construct a new 132 kilovolt (kv) overhead line (OHL) supported by wood poles to connect the proposed
More informationThe Grid Link Project. Summary of the Report for the Independent Expert Panel
The Grid Link Project Summary of the Report for the Independent Expert Panel Who are EirGrid - and what do we do? EirGrid is responsible for a safe, secure and reliable supply of electricity: now and in
More informationAberdeen Bay Wind Farm Connection. Consultation November 2016
Bay Wind Connection Consultation November 26 Scottish and Southern Electricity Net Project Overview Offshore Wind Grid Connection Who we are Scottish Hydro Electric Transmission Plc (SHE Transmission)
More informationSPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN
SPN High Value Project PO Route RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN Document History Version Date Details Originator V0.1 20/06/2013 Initial version Chris Winch V0.2
More informationGeneration Connections
Generation Connections An essential guide for generation developers applying to connect to the GB Transmission Network Preparing your application A guide to costs and timescales Your connection offer About
More informationwelcome to the BC Hydro community open house
welcome to the BC Hydro community open house Dawson Creek/ Chetwynd Area Transmission ProjecT Open House welcome Dawson Creek/Chetwynd Area Transmission Project (DCAT) The purpose of this open house is
More informationSubmission on the Wellington Town Belt Bill. Local Government and Environment Select Committee Parliament Buildings Wellington
Wellington Electricity Lines Ltd 2 Submission on the Wellington Town Belt Bill To: Name: Local Government and Environment Select Committee Parliament Buildings Wellington Wellington Electricity Lines Limited
More informationWOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017
WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 TODAY WE LL TALK ABOUT Our challenges and how we re meeting them Why we re building this project Our planning process and considerations
More informationTERRACE TO KITIMAT TRANSMISSION (TKT)
TERRACE TO KITIMAT TRANSMISSION (TKT) January 2014 OVERVIEW The need: Replace transmission lines between Terrace and Kitimat Options being studied by BC Hydro Discussion 2 SITUATION Kitimat area supplied
More informationBohn to Kettle River Transmission Project
April 2012 Why are you receiving this project information package? New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta Electric System Operator
More informationKettle River Transmission Project
April 2012 Why are you receiving this project information package? New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta Electric System Operator
More informationCurrant Lake Transmission Project
Currant Lake Transmission Project September 2010 Why are you receiving this project information package? New transmission facilities are needed in the Monitor area of southeastern Alberta. ATCO Electric
More informationAlberta Electric System Operator Saleski Transmission Project Needs Identification Document
Decision 2013-127 Alberta Electric System Operator Saleski Transmission Project Needs Identification Document ATCO Electric Ltd. Saleski 901S Substation and 144-kV Transmission Line 7L142 Facility Application
More informationPublic Information Centre
Junction Street Wastewater Pumping Station & Forcemain Schedule B Municipal Class Environmental Assessment Study Public Information Centre June 28, 2017. 6:00 to 8:00 pm. The Burlington Performing Arts
More informationVantage to Pomona Heights Transmission Project Frequently asked questions
Vantage to Pomona Heights Transmission Project Frequently asked questions These are some frequently asked questions regarding the proposed Vantage to Pomona Heights transmission line project. General What
More informationWelcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,
Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, is now called the Valley Line. We are here to present
More informationInveraray - Crossaig. Overhead Line Replacement September 2017
Inveraray - Crossaig www.ssen-transmission.co.uk/projects/xxxxx Overhead Line Replacement September 2017 Inveraray - Crossaig: Overhead Line Replacement September 2017 Who we are We are Scottish and Southern
More informationPowering Sydney s Future
Powering Sydney s Future Frequently Asked Questions December 2017 Project background Q: Why is this project needed? A: Inner Sydney is one of the most critical parts of the NSW electricity network. However,
More informationLandfall and Converter Station Site Selection Report Non-Technical Summary
Landfall and Converter Station Site Selection Report Non-Technical Summary Date: Intentionally blank Contents 1.Introduction 4 1.1 What is Viking Link 5 1.2 Purpose of report 6 2. Approach to site selection
More informationSelling PFIFFNER in the UK. Paul Haines
Selling PFIFFNER in the UK. Paul Haines Contents Introduction, Country & Market Overview UK. Accessing the Market Critical Success Factors. Developing the Business Together. Proposed Pfiffner Support.
More informationRENEWABLES INTEGRATION STATUS REPORT
RENEWABLES INTEGRATION STATUS REPORT NORTHERN IRELAND ELECTRICITY Ltd SYSTEM OPERATOR FOR NORTHERN IRELAND Ltd. June 2015 1. INTRODUCTION The electricity network in Northern Ireland (NI) is facing an unprecedented
More informationDecision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82
Decision 21447-D01-2016 August 23, 2016 Decision 21447-D01-2016 Proceeding 21447 Application 21447-A001 August 23, 2016 Published by the: Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary,
More informationBrion Energy Corporation
Decision 20907-D01-2015 MacKay River Commercial Project October 29, 2015 Alberta Utilities Commission Decision 20907-D01-2015 MacKay River Commercial Project Proceeding 20907 Application 20907-A001 October
More informationAlberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation
Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta
More informationEnergy Technical Memorandum
Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter
More informationDecision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016
Decision 21481-D01-2016 October 18, 2016 Alberta Utilities Commission Decision 21481-D01-2016 Proceeding 21481 Application 21481-A001 October 18, 2016 Published by the: Alberta Utilities Commission Fifth
More informationOVERVIEW OF UNDERGROUND POWER CABLES AT HIGH/EXTRA HIGH VOLTAGE LEVELS
OVERVIEW OF UNDERGROUND POWER CABLES AT HIGH/EXTRA HIGH VOLTAGE LEVELS 2006 WWW.EUROPACABLE.COM Introduction to Europacable Europacable is The Association of European Cable Manufacturers including ABB,
More informationOn June 11, 2012, the Park Board approved the installation of three electric vehicle charging stations along Beach Avenue.
January 8, 2017 TO: Park Board Chair and Commissioners FROM: General Manager Vancouver Board of Parks and Recreation SUBJECT: Electric Vehicle Charging Stations New Park Board Locations RECOMMENDATION
More informationGIBRALTAR ERDF OPERATIONAL PROGRAMME POST ADOPTION STATEMENT
Intended for Government of Gibraltar Document type Report Date January 2015 GIBRALTAR ERDF OPERATIONAL PROGRAMME 2014-2020 POST ADOPTION STATEMENT GIBRALTAR ERDF OPERATIONAL PROGRAMME 2014-2020 POST ADOPTION
More informationAlberta Energy and Utilities Board. Application to Construct and Operate Transmission Facilities
Alberta Energy and Utilities Board Application to Construct and Operate Transmission Facilities Albian Sands Energy Inc. August 17, 2007 APPLICATION Shell Canada Limited (Shell), as operator, on behalf
More informationRenewable Generation Electrical Infrastructure and Grid Connection Services Provided by Power Systems Project and Consultancy Services (PCS) Ltd
Renewable Generation Electrical Infrastructure and Grid Connection Services Provided by Power Systems Project and Consultancy Services (PCS) Ltd Power Systems Project and Consultancy Services (PCS) Ltd
More informationViking Link Interconnector
Viking Link Interconnector Members Briefing March Introductions Mark Pearce Licence and Consents Manager David Moore Project Manager Liz Wells Consents Officer Daniel James - Offshore Marine Manager Donna
More informationSTRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016
STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit
More informationDecision Blaze Energy Ltd. Application for an Exemption under Section 24 of the Hydro and Electric Energy Act.
Decision 2014-108 Application for an Exemption under Section 24 of the Hydro and Electric Energy Act April 17, 2014 The Alberta Utilities Commission Decision 2014-108: Application for an Exemption under
More informationCity of Palo Alto (ID # 6416) City Council Staff Report
City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building
More informationenvironment briefing02
The Voice of the Networks environment briefing02 transporting electricity Overhead Lines or Underground Cables Introduction The Electricity Act 1989 requires electricity companies both to maintain an efficient
More informationHEARING STATEMENT - PALMERSTON NORTH CITY COUNCIL PLAN CHANGE 15A - RURAL ZONE (GENERAL ISSUES)
11111 TRANSPOWER Keeping Ihe energy flowing Sarah Shand Phone: 04 590 7434 Email: sarah.shand@transool.ler.co.nz Transpower House 96 The Terrace PO Box 1021 Wellington 6140 New Zealand p 6444957000 F 6444957]00
More informationBalancing Mechanism and Connect and Manage Constraint Payments to Windfarms
Balancing Mechanism and Connect and Manage Constraint Payments to Windfarms Briefing Note (Prepared 5 th November 2013, updated 3 rd January 2014) Introduction National Grid (NG) balances supply and demand
More informationUpdated Statement of Community Consultation
Updated Statement of Community Consultation November 2016 Updated Statement of Community Consultation Prepared pursuant to section 47(1) of the Planning Act 2008 and regulation 10 of the Infrastructure
More informationWe Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network:
We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network: Richmond North of Oxford Street Richmond Row Dundas Street
More informationPort Hacking cable crossing project Community engagement and feedback summary August 2016
Port Hacking cable crossing project Community engagement and feedback summary August 2016 For period from April 2016 to 12 August 2016 1 Contents Contents... 2 1 Project background... 3 1.1 Project options...
More informationMAR1011. West Birmingham Bus Network Review March 2010
MAR1011 West Birmingham Bus Network Review March 2010 West Birmingham Bus Network Review In December 2008, Centro published a strategy document entitled Transforming Bus Travel (TBT) which sets out a vision
More informationEyre Peninsula electricity supply options investigation
20 November 2017 South Australia s electricity transmission specialist Eyre Peninsula electricity supply options investigation Project Assessment Draft Report Port Lincoln Public Forum electranet.com.au
More informationWelcome to Viking Link
Welcome to Viking Link Viking Link is a proposed 1,400 Mega Watt (MW) high voltage direct current (DC) electricity link between the British and Danish transmission systems connecting at Bicker Fen substation
More informationESIA Study for 1,050MW Coal Fired Power Plant, Lamu County, Kenya Need for the Project. 3 Need for the project... 2
Contents 3 Need for the project... 2 3.1. Project Background... 2 3.2. Energy mix and demand forecast... 2 3.3. 5000+ Project... 4 List of tables Table 3-1: Electric power generation sources and energy
More informationABB POWER SYSTEMS CONSULTING
ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February
More informationcommittee report General Permitted Development Order SPT response to consultation
committee report General Permitted Development Order SPT response to consultation Committee Strategy and Programmes Date of meeting 24 June 2011 Date of report 1 June 2011 Report by Assistant Chief Executive
More informationBC Hydro Undergrounding for 100 Avenue Widening Between King George Boulevard and 140 Street
CORPORATE REPORT NO: R191 COUNCIL DATE: September 17, 2018 REGULAR COUNCIL TO: Mayor & Council DATE: September 13, 2018 FROM: General Manager, Engineering FILE: 1717-054/H SUBJECT: BC Hydro Undergrounding
More informationGrizzly Bear Creek Wind Power Plant Connection Needs Identification Document
APPENDIX C AESO PIP Grizzly Bear Creek Wind Power Plant Connection Needs Identification Document 1.0 Participant Involvement Program (PIP) From December 2015 to May 2016, the AESO conducted a Participant
More informationTERRACE TO KITIMAT TRANSMISSION PROJECT OPEN HOUSE 5 P.M. 8 P.M. GDS14-027
TERRACE TO KITIMAT TRANSMISSION PROJECT OPEN HOUSE 5 P.M. 8 P.M. WELCOME! Take a look at the storyboards and maps to learn more about the Terrace to Kitimat Transmission Project Why it is needed What options
More informationGeneration Connections Industry Workshop 2017
Generation Connections Industry Workshop 2017 1 Introduction- Topics to be covered Background: SONI & NIE Networks Generation Connections Guide Renewable Generation Update Phase 1 Review UR Connections
More informationEnvironmental Report for Laois-Kilkenny Reinforcement Project
2 INTRODUCTION 2.1 PREAMBLE This Environmental Report has been prepared to accompany a planning application by EirGrid plc to An Bord Pleanála for approval to develop the Laois Kilkenny Reinforcement Project.
More informationThe Grid West project - Summary of the report for the Independent Expert Panel
The Grid West project - Summary of the report for the Independent Expert Panel 1. Glossary Glossary AC AC is a type of electrical current, in which the direction of the flow of electrons switches back
More informationOverview Gas Insulated Switchgear Modular and flexible, kV. ABB Group April 17, 2009 Slide 1
Overview Gas Insulated Switchgear Modular and flexible, 52-1100kV April 17, 2009 Slide 1 Tradition and Innovation Milestones from more than 40 Years of Experience Pioneer & Leader in GIS-Technology 1956
More informationDecision on Merced Irrigation District Transition Agreement
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation
More informationOverview Gas Insulated Switchgear Modular and flexible, kV. ABB Group May 15, 2013 Slide 1
Overview Gas Insulated Switchgear Modular and flexible, 52-1100kV May 15, 2013 Slide 1 Tradition and Innovation Milestones from more than 40 Years of Experience Pioneer & Leader in GIS-Technology 1956
More informationYUKON DEVELOPMENT CORPORATION
YUKON DEVELOPMENT CORPORATION 2 http://www.ydc.yk.ca YUKON DEVELOPMENT CORPORATION ANNUAL REPORT 2016 TABLE OF CONTENTS Message from the Chair...4 Message from the President and Chief Executive Office...
More informationMAP OR PHOTO. Public Meeting & Open House July 23, Project Roadway Limits From: FM 1957 To: FM 471. Counties Bexar & Medina
Public Meeting & Open House July 23, 2013 Project Roadway Limits From: FM 1957 To: FM 471 MAP OR PHOTO Counties Bexar & Medina 1 I. Project History II. III. IV. Project Overview Project Alternatives Response
More informationThis page is intentionally left blank.
This page is intentionally left blank. Bipole III Southern Ground Electrode Line Route Selection Introduction Manitoba Hydro has recently selected a route for the southern ground electrode line (Map 1).
More informationWelcome to Open House #5 Scarborough Rapid Transit
Welcome to Open House #5 Scarborough Rapid Transit Welcome to the Scarborough Rapid Transit (SRT) Conversion and Extension Study, including Kennedy Station improvements. Tonight s event provides details
More informationEast Avenue and Queen City Substation Improvement Project
East Avenue & Queen City Substation Improvement Project VIA FIRST CLASS MAIL August 29, 2017 Judith C. Whitney, Clerk Vermont Public Utility Commission 112 State Street, 4 th Floor Montpelier, VT 05620-2701
More informationRwanda Biofuels Limited. Powering Rwanda s Development
Rwanda Biofuels Limited Powering Rwanda s Development 1. Global Bio-Fuel Industry Trans esterification of vegetable oil was conducted as early as 1853, many years prior to the first diesel engine. Trans
More informationUpdated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers
Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,
More informationCITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6
2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS
More informationJoint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment
Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment For NPCC Governmental / Regulatory Affairs Advisory Group May 21 st, 2009 ON IT Executive Summary Engineers from Con
More informationMerger of the generator interconnection processes of Valley Electric and the ISO;
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric
More informationCushman & Adams Substations MOU March 28, Cushman & Adams Substations April, 1937
Cushman & Adams Substations MOU March 28, 2018 Cushman & Adams Substations April, 1937 Joint Staff Task Force Terry Coggins, Tacoma Power Ward Groves, Legal Jennifer Hines, Real Property Services Peter
More informationTibin Joseph Marie Curie Early Stage Researcher Institute of Energy Cardiff University
Tibin Joseph Marie Curie Early Stage Researcher Institute of Energy Cardiff University Contents Introduction Planned Network Reinforcement for 2020 The Three Machine Generic Model Subsynchronous Resonance
More informationEuropean technology leadership to address infrastructure bottlenecks
European technology leadership to address infrastructure bottlenecks Presentation tot&d and Smart Grids Europe 2012 Dr. Volker Wendt, Director Public Affairs Amsterdam, 10 October 2012 Europacable, Boulevard
More informationControlled Parking Zones Commentary
Controlled Parking Zones Commentary November 2012 Residents Association Controlled Parking Zones Commentary 244884 TPN ITQ 001 C http://localhost:3579/ahjycdovl0vvtkfqau1tl0rpq1vnru5uly9ilw FjdGlvbiUzYV9hX2FmaW5kaXRlbWluZm9hY3Rpb25fYWl0ZW1fY19hMT
More informationWATFORD LOCAL PLAN PART 2. Review of Car Parking Policy and Standards. Evidence Base. February 2012
WATFORD LOCAL PLAN PART 2 Review of Car Parking Policy and Standards Evidence Base February 2012 1.0 Background 1.1 The Watford District Plan 2000 contains various policies relating to the provision of
More informationCoalspur Mines (Operations) Ltd.
Decision 22744-D01-2017 Application for an Exemption Under Section 24 of the Hydro and Electric Energy Act October 5, 2017 Alberta Utilities Commission Decision 22744-D01-2017 Application for an Exemption
More informationTABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:
TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design
More informationDr.-Ing. Ervin Spahi, Wadden Sea Forum, Bremerhaven Electric grid on and off-shore: current status, obstacles and new developments
Dr.-Ing. Ervin Spahi, Wadden Sea Forum, Bremerhaven 26.11.09 Electric grid on and off-shore: current status, obstacles and new developments November 26, 2009 Slide 1 Transmission grid The challenges Optimal
More informationSOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015
SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment
More informationYukon s Independent Power Production Policy
Yukon s Independent Power Production Policy Updated October 2018 BACKGROUND The Government of Yukon (YG) released the Energy Strategy for Yukon in January 2009. The strategy sets out YG s energy priorities,
More informationTransmission s Future Today. High Capacity High Efficiency Low Profile
Transmission s Future Today High Capacity High Efficiency Low Profile BOLD TM Breakthrough in Overhead Line Design BOLD is a compact transmission line design that combines the advantages of higher capacity,
More informationThe Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Testimony of. David M. Campilii, P.E.
(Interstate Reliability Project) RIPUC Dkt. No. 0 Testimony of David M. Campilii, P.E. November, 0 -v RIPUC Dkt. No. 0 PREFILED TESTIMONY OF DAVID M. CAMPILII 0 0 INTRODUCTION Q. Please state your name
More informationTHE PROTEAN AND POC-MAST DESIGN
THE PROTEAN AND POC-MAST DESIGN Contents 1. The changing landscape of generation for power transmission and distribution. 2. The Holford rules and recommendations for OHL routing and design. 3. The current
More informationEyre Peninsula Electricity Supply Options
Eyre Peninsula Electricity Supply Options RIT-T Project Specification Consultation Report ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box, 7096, Hutt Street
More informationENERGY STRATEGY FOR YUKON. Independent Power Production Policy
ENERGY STRATEGY FOR YUKON Independent Power Production Policy May 20, 2014 Page 2 of 11 BACKGROUND The Government of Yukon released the Energy Strategy for Yukon in January 2009. The strategy sets out
More informationIt will be of particular interest to those potentially affected by the Government s proposals for high speed rail.
HIGH SPEED TWO INFORMATION PAPER F1: ROLLING STOCK DEPOT AND STABLING STRATEGY This paper outlines the reasons for the proposed depot and stabling strategy for the HS2 passenger rolling stock. It will
More informationENERGY STRATEGY FOR YUKON. Net Metering Policy DRAFT FOR CONSULTATION
ENERGY STRATEGY FOR YUKON Net Metering Policy DRAFT FOR CONSULTATION February 2011 Page 1 of 4 BACKGROUND The Yukon government released the Energy Strategy for Yukon in January 2009. The Energy Strategy
More informationWillingdon Substation Decommission
November 2012 Why are you receiving this project information package? New transmission facilities have been proposed in central east Alberta. As a result, some existing facilities are no longer needed.
More informationProposed Private Plan Change 46 Development Concept Plan for Inghams Enterprises (NZ) Pty Ltd
Proposed Private Plan Change 46 Development Concept Plan for Inghams Enterprises (NZ) Pty Ltd Summary of Submissions and Copy of Submissions Received Contents Summary of Submissions Submission Submitter
More informationOHL AC Cable DC Cable Submarine
OHL AC Cable DC Cable Submarine HVAC Innovative Applications Focus on reliability and safety From high energy city links to regional reinforcements John Owen Business Development Manager Nexans - Land
More informationClean Harbors Canada, Inc.
Clean Harbors Canada, Inc. Proposed Lambton Landfill Expansion Environmental Assessment Terms of Reference Transportation Assessment St. Clair Township, Ontario September 2009 itrans Consulting Inc. 260
More informationCREATING CONNECTIONS IN WATERLOO REGION
CREATING CONNECTIONS IN WATERLOO REGION GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE CHRIS BURKE, DIRECTOR, SERVICE PLANNING ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX
More informationInnovative technologies ready for the Supergrid
Innovative technologies ready for the Supergrid The Roadmap to the Supergrid Technologies EEF lunchtime discussion Feb 6, 2013 in Strasbourg Presented by Dr. Magnus Callavik, ABB (Convenor of WG 2 - Technology)
More informationbest to you all Gail Carbiener Page 1 of 5
Please accept this attachment as my up dated response to the B2H DEIS. If this is not acceptable, please let me know. Nice meeting last Monday in Boardman. 300316 best to you all Gail Carbiener 2 Page
More informationWestern NY Public Policy Transmission Planning Report
Western NY Public Policy Transmission Planning Report Dawei Fan Supervisor, Public Policy and Interregional Planning Business Issues Committee September 12, 2017 Operating Committee September 15, 2017
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:
More informationWELCOME. New Septage Waste Haulage Receiving Station Municipal Class Environmental Assessment (Class EA)
WELCOME New Septage Waste Haulage Receiving Station Municipal Class Environmental Assessment (Class EA) Public Information Centre (PIC) No. 1 Thursday November 9 th, 2017 6:00pm-8:00pm Please SIGN IN to
More informationJoint Operating Procedures for First Nations Consultation on Energy Resource Activities
Joint Operating Procedures for First Nations Consultation on Energy Resource Activities October 31, 2018 Contents Revision History... iv Definitions of Key Terms... v 1 Background... 1 2 Roles and Responsibilities...
More informationGreen Power Feasibility Study Econet Lesotho
Green Power This document has been written to provide information to mobile operators who are considering or planning to deploy green renewable power resources for base station and transmission sites.
More informationGreen Line LRT: Beltline Recommendation Frequently Asked Questions
Green Line LRT: Beltline Recommendation Frequently Asked Questions June 2017 Quick Facts Administration has evaluated several alignment options that would connect the Green Line in the Beltline to Victoria
More informationInterconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS
Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia