welcome to the BC Hydro community open house

Size: px
Start display at page:

Download "welcome to the BC Hydro community open house"

Transcription

1 welcome to the BC Hydro community open house Dawson Creek/ Chetwynd Area Transmission ProjecT Open House

2 welcome Dawson Creek/Chetwynd Area Transmission Project (DCAT) The purpose of this open house is to: Provide information about the DCAT project Answer your questions Get your input on the project and on the transmission line routing options Members of the project team are here to provide information and answer your questions. Please be sure to visit the displays and talk with us. Your opinions are important to us. Please take a few minutes to fill out a comment form before you leave tonight.

3 BC Hydro s TRANSMISSION SYSTEM Electricity is moved throughout the province via an interconnected grid of: Over 18,000 kilometres of transmission lines 100,000 wood poles 22,000 steel towers 292 substations 2 control centres

4 PEACE AREA TRANSMISSION SYSTEM A 230 kv line from GM Shrum generating station provides electricity to several substations east of Chetwynd. Dawson Creek Substation receives electricity from two 138 kv transmission lines. Bear Mountain Terminal connects Bear Mountain Wind Farm to the 138 kv system and also supplies electricity to 138 kv transmission customers.

5 the need Over the next 10 years, the annual rate of load growth in the South Peace is expected to be 10 times greater than for the BC Hydro system as a whole. This demand is primarily driven by industrial developments. Developers for many planned new oil and gas facilities would like to connect to the electricity grid. The Dawson Creek/Chetwynd Area Transmission (DCAT) Project is one of BC Hydro s initiatives to meet the growing need for electricity in the South Peace area.

6 DCAT PROJECT DESCRIPTION The proposed DCAT Project includes: A new substation (Sundance) to be located about 19 km east of Chetwynd, near Highway 97 A new 230 kilovolt (kv) double circuit transmission line, approximately 60 km long, from Sundance Substation to Bear Mountain Terminal (BMT) Expansion of BMT and Dawson Creek Substation (DAW) A new 230 kv double circuit line approximately 12 km long, between BMT and DAW DCAT will double the transmission system capacity in the area. Planned in-service date for DCAT is Fall 2013.

7 DAWSON CREEK/CHETWYND AREA TRANSMISSION PROJECT PRELIMINARY MAP EXISTING 500KV TRANSMISSION LINES EXISTING 230KV TRANSMISSION LINES EXISTING 138KV TRANSMISSION LINES GENERAL LOCATION, PROPOSED NEW 230KV TRANSMISSION LINE PROPOSED NEW STATION EXISTING SUBSTATION HYDRO GENERATING STATION BRITISH COLUMBIA Hwy 97 Hudson s Hope Hwy 29 Fort St.John Taylor Substation GM Shrum Sundance Station Tembec, Chetwynd Operations Substation (Private) Dawson Creek Substation ALBERTA Chetwynd Hwy 97 Dawson Creek Hwy 97 Chetwynd Substation Sukunka Switching Station Bear Mountain Terminal Hwy 2 Hwy KM 10 MI A11-032

8 substations Sundance Substation The new Sundance Substation will be located on Crown Land It will tie into the existing 230 kv and 138 kv transmission systems, extending the 230 kv system to Dawson Creek Bear Mountain Terminal Bear Mountain Terminal will be expanded into a full 230 kv to 138 kv substation Dawson Creek Substation Dawson Creek Substation will be expanded All expansion will be on BC Hydro-owned land

9 DCAT transmission LINE ROUTING Several routing options were developed for the DCAT project, then evaluated using criteria such as: Engineering considerations (for example, types of poles that would need to be used) Construction considerations (such as terrain and soil stability) Access requirements for construction and maintenance Potential impacts on private properties and First Nations Potential impacts on wildlife and riparian habitat Line length and cost In planning the DCAT route, we divided the line into western, central and eastern segments. A proposed reference route the option that best meets our evaluation criteria at this time was then determined for each segment.

10 PROPOSED CENTRAL SEGMENT REFERENCE ROUTE Three routing options were evaluated. The proposed reference route for the Central segment is Option C1. It largely follows the existing 138 kilovolt (kv) transmission line right-of-way (ROW), primarily through privately held lands. Our evaluation showed: While all three options impact private properties, Option C1 impacts the highest number Environmental impacts expected to be highest for Option C3 New access requirements would be highest for C3 At 43 km, C1 is shorter than C2 (56 km) and C3 (48 km) Construction costs for C1 are estimated to be $15 20 million less than C3 and $20 25 million less than C2 BC Hydro is still evaluating sub-options to C1, to route away from homes, where possible, and from pipeline infrastructure. Want more information? Pick up a copy of our Central segment map and evaluation summary from the sign-in table and have a conversation with the project team staff.

11 PROPOSED western SEGMENT REFERENCE ROUTE Two routing options were evaluated. The proposed reference route for the Western segment is Option W1. It runs northeast of the proposed Sundance Substation, paralleling the existing 230 kv transmission line, then turns directly east just before Tembec mill. Our evaluation showed: Both Option W1 and W2 are similar in length (about 13 km) Both have similar access requirements for construction and maintenance Both cross a similar number of private properties Environmental impacts are minimal for both options Construction costs for W1 are estimated at about $4 5 million less than W2 because it is a straighter route Want more information? Pick up a copy of our Western segment map and evaluation summary from the sign-in table and have a conversation with the project team staff.

12 PROPOSED eastern SEGMENT REFERENCE ROUTE Three options were evaluated. The proposed reference route for the Eastern segment is Option E1. It heads west from Dawson Creek Substation, parallels the existing railway corridor, then turns south to Bear Mountain Terminal. Our evaluation showed: Route length similar for all three options (approximately 12 to 14km) Environmental impacts minimal for all three options E1 impacts fewer private properties E1 also has the lowest estimated construction cost; $2 3 million less than Option E2 and $4 5 million less than Option E3 At this time, BC Hydro is still evaluating the sub-option of building north or south of the railway corridor. Want more information? Pick up a copy of our eastern segment map and evaluation summary from the sign-in table, and have a conversation with the project team staff.

13 STRUCTURES AND RIGHT OF WAY DCAT will be a double circuit 230 kv transmission line. The steel structures used will be taller than the existing 138 kv transmission structures. Because the structures are taller, the length of conductor (span) between structures can be much longer. This means that fewer structures are needed. Davit arm structures are used in a wider right-of-way. Compact structures are used in areas where the right-of-way needs to be as narrow as possible.

14 environment DCAT does not trigger assessment under the BC Environmental Assessment Act. At this time, it does not appear to trigger assessment under the Canadian Environmental Assessment Act. Environmental studies are still an important part of planning the project. The following types of studies have been undertaken: Archaeology (non-invasive assessment) Fisheries and aquatics Wildlife habitat and species surveys Vegetation resources, rare plant and ecological community surveys Socio-economic Land use The findings will help us take all practical measures to avoid or minimize impacts in routing and constructing DCAT.

15 regulatory approvals BC Hydro will require approval for the DCAT project from the British Columbia Utilities Commission (BCUC). The BCUC is an independent agency of the Provincial government and regulates BC Hydro, among other Crown corporations and companies. BC Hydro will apply to the BCUC in Spring 2011 for a Certificate of Public Convenience and Necessity (CPCN) for DCAT. The BCUC will examine: The need and justification for the project The alternatives examined The costs to construct and maintain DCAT A number of socio-economic and nonfinancial factors For more information on the BCUC and the CPCN process, please visit the BCUC website at:

16 ongoing TRANSMISSION LINE MAINTENANCE WORK Until the DCAT project is completed in Fall 2013, it is important to ensure that the existing 138 kv transmission circuits in your area are operating as reliably as possible. For this reason, BC Hydro will be undertaking necessary vegetation and pole/line maintenance on the 138 kv circuit until DCAT is fully commissioned and in service. If maintenance work is required on private property, BC Hydro staff or its contractors will make reasonable efforts to contact the owner in advance.

17 draft schedule Milestone First Nations and Public Consultation Date (subject to change) Spring ongoing Environmental study work Summer Fall 2010 Submit application for CPCN Spring 2011 CPCN process Spring Spring 2012 Right-of-way/land acquisition 2011 Construction Spring Summer 2013 In-service Fall 2013

18 THANK YOU FOR COMING Your feedback will be considered as we continue to plan the project. Please take a moment to fill out a comment form. If you would like to receive updates on the DCAT project, please include your contact information on your comment form. Project consultation is ongoing. You can provide input by contacting our Stakeholder Relations Department: Phone: Toll free: Fax: stakeholderengagement@bchydro.com

TERRACE TO KITIMAT TRANSMISSION PROJECT OPEN HOUSE 5 P.M. 8 P.M. GDS14-027

TERRACE TO KITIMAT TRANSMISSION PROJECT OPEN HOUSE 5 P.M. 8 P.M. GDS14-027 TERRACE TO KITIMAT TRANSMISSION PROJECT OPEN HOUSE 5 P.M. 8 P.M. WELCOME! Take a look at the storyboards and maps to learn more about the Terrace to Kitimat Transmission Project Why it is needed What options

More information

Bohn to Kettle River Transmission Project

Bohn to Kettle River Transmission Project April 2012 Why are you receiving this project information package? New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta Electric System Operator

More information

Kettle River Transmission Project

Kettle River Transmission Project April 2012 Why are you receiving this project information package? New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta Electric System Operator

More information

Currant Lake Transmission Project

Currant Lake Transmission Project Currant Lake Transmission Project September 2010 Why are you receiving this project information package? New transmission facilities are needed in the Monitor area of southeastern Alberta. ATCO Electric

More information

Included in this Stakeholder Information Package:

Included in this Stakeholder Information Package: Who can you contact for more information? Yellowhead Area Transmission Reinforcement: TERA Environmental Consultants Dave Sare Phone: 403-538-5734 Email: dsare@teraenv.com Drayton Valley Area AltaLink

More information

WELCOME. New Septage Waste Haulage Receiving Station Municipal Class Environmental Assessment (Class EA)

WELCOME. New Septage Waste Haulage Receiving Station Municipal Class Environmental Assessment (Class EA) WELCOME New Septage Waste Haulage Receiving Station Municipal Class Environmental Assessment (Class EA) Public Information Centre (PIC) No. 1 Thursday November 9 th, 2017 6:00pm-8:00pm Please SIGN IN to

More information

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 TODAY WE LL TALK ABOUT Our challenges and how we re meeting them Why we re building this project Our planning process and considerations

More information

Alternatives for meeting the need for transmission improvement described

Alternatives for meeting the need for transmission improvement described Alternatives for meeting the need for transmission improvement described 240 kv Alternative Looped System Southern Alberta Transmission Reinforcement For more information please contact the AESO at 1.888.866.2959,

More information

conversation SHAPE the May 2015 The AUC

conversation SHAPE the May 2015 The AUC SHAPE the conversation May 2015 Thickwood Hills Transmission PROJECT The Thickwood Hills Transmission Project is needed to connect planned critical transmission infrastructure, that will reinforce the

More information

Proposed Dounreay - Mybster 275 kv / 132 kv

Proposed Dounreay - Mybster 275 kv / 132 kv Background Scottish Hydro-Electric Transmission Ltd (SHETL) is proposing a new 275 kilovolt (kv) (1 kilovolt = 1000volts) double circuit overhead line (OHL) between the Dounreay sub station and the new

More information

Chirmorie Wind Farm Grid Connection

Chirmorie Wind Farm Grid Connection Chirmorie Wind Farm Grid Connection Welcome Welcome to this public exhibition regarding our proposals to construct a new 132 kilovolt (kv) overhead line (OHL) supported by wood poles to connect the proposed

More information

BC Hydro System 2011 Annual Progress Report

BC Hydro System 2011 Annual Progress Report March 1, 2011 Mr. Kyle R. Kohne, Chairman WECC Technical Studies Subcommittee Bonneville Power Administration P.O. Box 491 MS, TPP-OPP-3 Vancouver, WA 98666 Mr. Kent Bolton WECC Technical Staff 155 North

More information

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document Decision 2013-127 Alberta Electric System Operator Saleski Transmission Project Needs Identification Document ATCO Electric Ltd. Saleski 901S Substation and 144-kV Transmission Line 7L142 Facility Application

More information

SH 249 IN GRIMES COUNTY. Open House April 3, 2014

SH 249 IN GRIMES COUNTY. Open House April 3, 2014 SH 249 IN GRIMES COUNTY Open House April 3, 2014 Meeting Agenda Purpose of Meeting Today: Review the purpose and need for the SH 249 Grimes County project Review the proposed project and alternatives Discuss

More information

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta

More information

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA Submission of Indicated New York Transmission Owners For Authority to Construct and Operate Electric Transmission Facilities in Multiple Counties in New York Case 13-M-0457 Edic to New Scotland 345 kv

More information

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit

More information

Public Information Workshop

Public Information Workshop Public Information Workshop Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 29, 2018 Welcome to the Public Information Workshop for Harborview Road Project Development and Environment (PD&E)

More information

BC Hydro System 2016 Annual Progress Report

BC Hydro System 2016 Annual Progress Report March 11, 2016 Philip Augustin, P.E. Chair, Technical Studies Subcommittee 503-464-7783 philip.augustin@pgn.com Mr. Enoch Davies WECC Technical Staff 155 North 400 West, Suite 200 Salt Lake City, UT 84103-1114

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82 Decision 21447-D01-2016 August 23, 2016 Decision 21447-D01-2016 Proceeding 21447 Application 21447-A001 August 23, 2016 Published by the: Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary,

More information

We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network:

We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network: We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network: Richmond North of Oxford Street Richmond Row Dundas Street

More information

FOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT

FOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT FOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT Proposed 138kV Transmission Line Photo courtesy of The City of Calgary Project Overview The demand for power is increasing as Calgary continues

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, is now called the Valley Line. We are here to present

More information

Vantage to Pomona Heights Transmission Project Frequently asked questions

Vantage to Pomona Heights Transmission Project Frequently asked questions Vantage to Pomona Heights Transmission Project Frequently asked questions These are some frequently asked questions regarding the proposed Vantage to Pomona Heights transmission line project. General What

More information

Grizzly Bear Creek Wind Power Plant Connection Needs Identification Document

Grizzly Bear Creek Wind Power Plant Connection Needs Identification Document APPENDIX C AESO PIP Grizzly Bear Creek Wind Power Plant Connection Needs Identification Document 1.0 Participant Involvement Program (PIP) From December 2015 to May 2016, the AESO conducted a Participant

More information

Frequently Asked Questions Leander-Round to Rock 138-kV Transmission Line Project Williamson County

Frequently Asked Questions Leander-Round to Rock 138-kV Transmission Line Project Williamson County Frequently Asked Questions Leander-Round to Rock 138-kV Transmission Line Project Williamson County Q. What is the Leander-Round Rock 138-kV Transmission Line Project? A. The Leander-Round Rock project

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY

More information

FOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT

FOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT FOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT Proposed 138kV Transmission Line Photo courtesy of The City of Calgary Project Overview The demand for power is increasing as Calgary continues

More information

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th Alex Bettencourt Managing Director National Association Made Up of Entire Industry Utilities Industry Academia / R&D

More information

Kake - Petersburg Intertie Update

Kake - Petersburg Intertie Update Kake - Petersburg Intertie Update September 18, 2013 Sitka Southeast Conference Annual Meeting Trey Acteson CEO, SEAPA Mark Schinman, P.E. Commonwealth Associates There is a Need for the Intertie Kake

More information

SOUTHWEST CALGARY RING ROAD (SWCRR)

SOUTHWEST CALGARY RING ROAD (SWCRR) PROJECT OVERVIEW Alberta Transportation has started planning for the construction of the SW portion of the road that will complete the Calgary Ring Road. The completion of the SWCRR requires the relocation

More information

Black Hills Project Summary

Black Hills Project Summary 2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission

More information

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal TransWest Express Transmission AC and DC Project 2018 2019 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission

More information

Powering Sydney s Future

Powering Sydney s Future Powering Sydney s Future Frequently Asked Questions December 2017 Project background Q: Why is this project needed? A: Inner Sydney is one of the most critical parts of the NSW electricity network. However,

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016 Decision 21481-D01-2016 October 18, 2016 Alberta Utilities Commission Decision 21481-D01-2016 Proceeding 21481 Application 21481-A001 October 18, 2016 Published by the: Alberta Utilities Commission Fifth

More information

Waco Rapid Transit Corridor (RTC) Feasibility Study

Waco Rapid Transit Corridor (RTC) Feasibility Study Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM

More information

Willingdon Substation Decommission

Willingdon Substation Decommission November 2012 Why are you receiving this project information package? New transmission facilities have been proposed in central east Alberta. As a result, some existing facilities are no longer needed.

More information

Alberta Energy and Utilities Board. Application to Construct and Operate Transmission Facilities

Alberta Energy and Utilities Board. Application to Construct and Operate Transmission Facilities Alberta Energy and Utilities Board Application to Construct and Operate Transmission Facilities Albian Sands Energy Inc. August 17, 2007 APPLICATION Shell Canada Limited (Shell), as operator, on behalf

More information

Electric system improvements near you

Electric system improvements near you Electric system improvements near you Red Deer Area Transmission Development Stage 1 substation upgrades April 2011 Volume 1 Did you know? The average four-person family in Alberta today has 20 instant-on

More information

The Grid Link Project. Summary of the Report for the Independent Expert Panel

The Grid Link Project. Summary of the Report for the Independent Expert Panel The Grid Link Project Summary of the Report for the Independent Expert Panel Who are EirGrid - and what do we do? EirGrid is responsible for a safe, secure and reliable supply of electricity: now and in

More information

West Kelowna Transmission Project. Public Consultation June 20 July 27, 2016

West Kelowna Transmission Project. Public Consultation June 20 July 27, 2016 West Kelowna Transmission Project Public Consultation June 20 July 27, 2016 1 Welcome On February 5, 2015, the Province of British Columbia and BC Hydro announced the West Kelowna Transmission Project.

More information

APPENDIX C - AESO PIP SUMMARY

APPENDIX C - AESO PIP SUMMARY APPENDIX C - AESO PIP SUMMARY Whitla Wind Facility Connection PIP Summary 1.0 Participant Involvement Program (PIP) 1.1 PIP Design The AESO s Participant Involvement Program (PIP) is designed to notify

More information

Harlem Avenue between 63 rd and 65 th

Harlem Avenue between 63 rd and 65 th Harlem Avenue between 63 rd and 65 th Public Meeting #2 March 13, 2018 Summit Park District Welcome to the second Public Meeting for the preliminary engineering and environmental studies of Illinois 43

More information

Welcome. Public Open House Schedule. Super 8 West Kelowna 1655 Westgate Rd, West Kelowna. West Kelowna. Wednesday, March 2, :00 p.m. 8:00 p.m.

Welcome. Public Open House Schedule. Super 8 West Kelowna 1655 Westgate Rd, West Kelowna. West Kelowna. Wednesday, March 2, :00 p.m. 8:00 p.m. Welcome Thank you for attending this Community Engagement on improvements to the Boucherie Road and Westlake Road intersections on Highway 97 in the Central Okanagan. Public Open House Schedule Location

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Decision Blaze Energy Ltd. Application for an Exemption under Section 24 of the Hydro and Electric Energy Act.

Decision Blaze Energy Ltd. Application for an Exemption under Section 24 of the Hydro and Electric Energy Act. Decision 2014-108 Application for an Exemption under Section 24 of the Hydro and Electric Energy Act April 17, 2014 The Alberta Utilities Commission Decision 2014-108: Application for an Exemption under

More information

Welcome. Highway 23 Gap New London to Paynesville. Open House. - Please Sign In -

Welcome. Highway 23 Gap New London to Paynesville. Open House. - Please Sign In - Highway Gap New London to Paynesville Welcome Highway Gap New London to Paynesville Open House - Please Sign In - There is no formal presentation, but representatives are available to answer your questions.

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

MAP OR PHOTO. Public Meeting & Open House July 23, Project Roadway Limits From: FM 1957 To: FM 471. Counties Bexar & Medina

MAP OR PHOTO. Public Meeting & Open House July 23, Project Roadway Limits From: FM 1957 To: FM 471. Counties Bexar & Medina Public Meeting & Open House July 23, 2013 Project Roadway Limits From: FM 1957 To: FM 471 MAP OR PHOTO Counties Bexar & Medina 1 I. Project History II. III. IV. Project Overview Project Alternatives Response

More information

Electricity industry structure and key players

Electricity industry structure and key players Electricity industry structure and key players Growth in capacity, production and consumption, 2006 2017 Expected demand and addition to generation capacity, 2018 2027 Growth in transmission network and

More information

Open House. Highway212. Meetings. Corridor Access Management, Safety & Phasing Plan. 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition

Open House. Highway212. Meetings. Corridor Access Management, Safety & Phasing Plan. 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition Welcome Meetings 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition 6:30 to 8:00 p.m. - Open House Why is Highway 212 Project Important? Important Arterial Route Local Support Highway 212

More information

Transit Vehicle (Trolley) Technology Review

Transit Vehicle (Trolley) Technology Review Transit Vehicle (Trolley) Technology Review Recommendation: 1. That the trolley system be phased out in 2009 and 2010. 2. That the purchase of 47 new hybrid buses to be received in 2010 be approved with

More information

STH 60 Northern Reliever Route Feasibility Study Report

STH 60 Northern Reliever Route Feasibility Study Report #233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development

More information

PROJECTS $500K AND OVER FOR 2012

PROJECTS $500K AND OVER FOR 2012 EB-0-0 Page of PROJECTS $00K AND OVER FOR 0 EXTERNALLY INITIATED PLANT RELOCATIONS PORTFOLIO Table : Externally Initiated Plant Relocations Projects Estimate Estimated Cost Project Title Number ($ Millions)

More information

Western Alberta Transmission Line (WATL) HVDC Project

Western Alberta Transmission Line (WATL) HVDC Project Submission for the ACEC Canada Canadian Consulting Engineering Awards 2016 Western Alberta Transmission Line (WATL) HVDC Project Submitted by Teshmont Consultants LP as a Consultant to AltaLink Attachment

More information

Wainwright 51S Substation Connection Enhancement Needs Identification Document

Wainwright 51S Substation Connection Enhancement Needs Identification Document APPENDIX C AESO PIP Wainwright 51S Substation Connection Enhancement Needs Identification Document 1.0 Participant Involvement Program (PIP) From October 2015 to July 2016 the AESO conducted a Participant

More information

US 81 Bypass of Chickasha Environmental Assessment Public Meeting

US 81 Bypass of Chickasha Environmental Assessment Public Meeting US 81 Bypass of Chickasha Environmental Assessment Public Meeting March 14, 2013 Introductions ODOT FHWA SAIC Meeting Purpose Present need for bypass Provide responses to 10/04/11 public meeting comments

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE

5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE 5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE The Rapid Transit Public/Private Partnership Steering Committee recommends the

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

STATE OF MINNESOTA ENVIRONMENTAL QUALITY BOARD

STATE OF MINNESOTA ENVIRONMENTAL QUALITY BOARD STATE OF MINNESOTA ENVIRONMENTAL QUALITY BOARD In the Matter of Xcel Energy s Application for a Route Permit for a 345- kv High Voltage Transmission Line and a 115-kV High-Voltage Transmission Line in

More information

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment For NPCC Governmental / Regulatory Affairs Advisory Group May 21 st, 2009 ON IT Executive Summary Engineers from Con

More information

Technical Report TR-22. Appendix Q

Technical Report TR-22. Appendix Q Technical Report TR-22 Vancouver Fraser Port Authority Development Permit Application Consultation Summary Westridge Marine Terminal Appendix Q Trans Mountain Expansion Project Trans Mountain Expansion

More information

Peninsula Corridor Electrification Project (PCEP)

Peninsula Corridor Electrification Project (PCEP) Peninsula Corridor Electrification Project (PCEP) Q4 Quarterly Update #11 April 1 June 30, 2017 JPB Board Meeting August 3, 2017 Agenda Item # 8a Electrification - Infrastructure Design Build Contract

More information

ROCKY MOUNTAIN POWER A DIVISION OF PACIFICORP

ROCKY MOUNTAIN POWER A DIVISION OF PACIFICORP ROCKY MOUNTAIN POWER A DIVISION OF PACIFICORP January 29, 2014 201 South Main, Suite 2300 Salt Lake City, Utah 84111 VIA ELECTROl.fiC FILI1VG AND OVERNIGHT DELIVERY Wyoming Public Service Commission 2515

More information

THE WAY WE MOVE LRT FOR EVERYONE

THE WAY WE MOVE LRT FOR EVERYONE THE WAY WE MOVE LRT FOR EVERYONE 2 LRT for Everyone LRT FOR EVERYONE Light rail is about more than transit; it s about transforming Edmonton. As the city grows, so do its transportation needs. LRT is an

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: MAY 6, 2010 SUBJECT: SCARBOROUGH RAPID TRANSIT TRANSIT PROJECT ASSESSMENT STUDY RECOMMENDATIONS ACTION ITEM RECOMMENDATION

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

BLUMENORT TRANSMISSION PROJECT

BLUMENORT TRANSMISSION PROJECT APPLICATION TO THE ALBERTA UTILITIES COMMISSION BLUMENORT TRANSMISSION PROJECT March 2014 10035-105 Street P.O. Box 2426 Station Main Edmonton, Alberta T5J 2V6 INDEX OF ATTACHMENTS 1 THROUGH 13 ATTACHMENT

More information

Tank Farm Additional Storage Site Layout

Tank Farm Additional Storage Site Layout MONTREAL TRUDEAU INTERNATIONAL AIRPORT MIFFC Fuel Committee Meeting Montreal Airport Marriott Hotel, June 15, 2017 Tank Farm Additional Storage Site Layout 1 Tank Farm Additional Storage - Construction

More information

Market Efficiency Update

Market Efficiency Update Market Efficiency Update Transmission Expansion Advisory Committee July 13, 2017 Agenda Where we are in the process Interregional Projects Status RPM Projects Status Reevaluation Analysis Status Next Steps

More information

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, 2006 SUBJECT: Scarborough Rt Strategic Plan RECOMMENDATIONS It is recommended that the Commission: 1. Endorse

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Western NY Public Policy Transmission Planning Report

Western NY Public Policy Transmission Planning Report Western NY Public Policy Transmission Planning Report Dawei Fan Supervisor, Public Policy and Interregional Planning Business Issues Committee September 12, 2017 Operating Committee September 15, 2017

More information

Yukon s Independent Power Production Policy

Yukon s Independent Power Production Policy Yukon s Independent Power Production Policy Updated October 2018 BACKGROUND The Government of Yukon (YG) released the Energy Strategy for Yukon in January 2009. The strategy sets out YG s energy priorities,

More information

Pacific Northwest/Canada To Northern California Transmission Feasibility Study

Pacific Northwest/Canada To Northern California Transmission Feasibility Study Pacific Nthwest/Canada To Nthern Califnia Transmission Feasibility Study Technical Analysis Committee Presentation By Ben Mris, PG&E 1 December 12, 2006 Topics Study Objectives Alternatives Considered

More information

Welcome to Open House #5 Scarborough Rapid Transit

Welcome to Open House #5 Scarborough Rapid Transit Welcome to Open House #5 Scarborough Rapid Transit Welcome to the Scarborough Rapid Transit (SRT) Conversion and Extension Study, including Kennedy Station improvements. Tonight s event provides details

More information

Green Stocking Transmission Project

Green Stocking Transmission Project August 2010 Green Stocking Transmission Project Why are you receiving this project information package? New transmission facilities are needed in northeastern Alberta. ATCO Electric has direction from

More information

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy ENERGY STRATEGY FOR YUKON Independent Power Production Policy May 20, 2014 Page 2 of 11 BACKGROUND The Government of Yukon released the Energy Strategy for Yukon in January 2009. The strategy sets out

More information

New West Partnership Deliverables July 2011/2012 Reporting

New West Partnership Deliverables July 2011/2012 Reporting Area 1 - Vehicle Weights and Dimensions Steering Axle Weight Limits July 2011 Changes to vehicle design and It is Alberta s position, jointly agreed upon by other New West additional required equipment

More information

SECTION 1 DESCRIPTION OF THE PROPOSED PROJECT

SECTION 1 DESCRIPTION OF THE PROPOSED PROJECT SECTION 1 DESCRIPTION OF THE PROPOSED PROJECT Supplemental Municipal Consultation Filing The Interstate Reliability Project 1. DESCRIPTION OF THE PROPOSED PROJECT The Connecticut Light and Power Company

More information

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04 Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch

More information

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014 1 BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada IEEE PES Meeting July 2014 General BC Hydro Overview Crown Corporation Serving about 95% of province and 1.9 million customers

More information

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Western Region ATSI Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these

More information

The Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Testimony of. David M. Campilii, P.E.

The Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Testimony of. David M. Campilii, P.E. (Interstate Reliability Project) RIPUC Dkt. No. 0 Testimony of David M. Campilii, P.E. November, 0 -v RIPUC Dkt. No. 0 PREFILED TESTIMONY OF DAVID M. CAMPILII 0 0 INTRODUCTION Q. Please state your name

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

TERRACE TO KITIMAT TRANSMISSION (TKT)

TERRACE TO KITIMAT TRANSMISSION (TKT) TERRACE TO KITIMAT TRANSMISSION (TKT) January 2014 OVERVIEW The need: Replace transmission lines between Terrace and Kitimat Options being studied by BC Hydro Discussion 2 SITUATION Kitimat area supplied

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC

More information

Mississauga Bus Rapid Transit Preliminary Design Project

Mississauga Bus Rapid Transit Preliminary Design Project Mississauga Bus Rapid Transit Preliminary Design Project PUBLIC INFORMATION CENTRE OCTOBER 2008 WELCOME The Mississauga Bus Rapid Transit (BRT) Project Thank you for attending this Public Information Centre.

More information

NEW ECTOR COUNTY NORTH TO MOSS 138 kv TRANSMISSION LINE PROJECT PUBLIC OPEN HOUSE MEETING

NEW ECTOR COUNTY NORTH TO MOSS 138 kv TRANSMISSION LINE PROJECT PUBLIC OPEN HOUSE MEETING NEW ECTOR COUNTY NORTH TO MOSS 138 kv TRANSMISSION LINE PROJECT PUBLIC OPEN HOUSE MEETING TUESDAY AUGUST 17, 2010 4:00 PM 8:00 PM CAVAZOS ELEMENTARY SCHOOL CAFETERIA 9301 WEST 16 TH STREET ODESSA, TEXAS

More information

Aberdeen Bay Wind Farm Connection. Consultation November 2016

Aberdeen Bay Wind Farm Connection. Consultation November 2016 Bay Wind Connection Consultation November 26 Scottish and Southern Electricity Net Project Overview Offshore Wind Grid Connection Who we are Scottish Hydro Electric Transmission Plc (SHE Transmission)

More information

SunZia Southwest Transmission Project

SunZia Southwest Transmission Project SunZia Southwest Transmission Project SunZia Project Update for the Southern Arizona Economic Development Group September 12, 2017 SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 0 SouthWestern

More information

ASX RELEASE. PAK receives drilling permit for Elko Coking coal project. Summary

ASX RELEASE. PAK receives drilling permit for Elko Coking coal project. Summary ASX RELEASE ASX Release Tuesday 24 April 2018 ASX Code PAK About Us Pacific American Coal Limited (the Company) is focused on the production, development and exploration of metallurgical coal assets in

More information

Appendix A-M Public Information Centre 4 Materials

Appendix A-M Public Information Centre 4 Materials Appendix A-M Public Information Centre 4 Materials NOTICE OF PUBLIC INFORMATION CENTRE #4 RAPID TRANSIT CORRIDORS MASTER PLAN ENVIRONMENTAL ASSESSMENT STUDY The City of London is entering a new chapter

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

NORTH SLOPE BOROUGH Department of Public Works P.O. Box 350 Barrow, Alaska 99723

NORTH SLOPE BOROUGH Department of Public Works P.O. Box 350 Barrow, Alaska 99723 NORTH SLOPE BOROUGH Department of Public Works P.O. Box 350 Barrow, Alaska 99723 Phone: 907-852-0489 Fax: 907-852-0251 Charlie Sakeagak, Director ATQASUK TRANSMISSION LINE PROJECT INTRODUCTION The continuing

More information

STATE OF NEW HAMPSHIRE Inter-Department Communication

STATE OF NEW HAMPSHIRE Inter-Department Communication STATE OF NEW HAMPSHIRE Inter-Department Communication DATE: February 11, 2010 AT (OFFICE): NHPUC FROM: Torn Frantz Director, Electric Division SUBJECT: DE 09-277: Petition by Public Service Company of

More information

Michigan Thumb Loop Transmission Line Project

Michigan Thumb Loop Transmission Line Project Michigan Thumb Loop Transmission Line Project ITC Holdings Corp. Simon Whitelocke VP., Regulatory and External Affairs October 30, 2013 What is Transmission? The electric transmission system is the network

More information