Lugo-Victorville RAS. Presentation to RASRS. November 14, Edison Team Members:

Size: px
Start display at page:

Download "Lugo-Victorville RAS. Presentation to RASRS. November 14, Edison Team Members:"

Transcription

1 Lugo-Victorville RAS Edison Team Members: Fernando Benavides, Generation Interconnection Planning Bill Zhang, Protection Engineering Obinna Obah, Power System Controls Larry Wang, Telecomm Presentation to RASRS November 14, 2018

2 OBJECTIVE APPROVAL OF SCE'S LUGO-VICTORVILLE RAS MODIFICATION 2

3 Topics Fernando Benavides Background Purpose/Operating Principles Planning Studies Obinna Obah Power System Controls Larry Wang Telecommunications Bill Zhang Design Commissioning 3

4 LUGO-VICTORVILLE RAS Background Purpose/Operating Principles Fernando Benavides 4

5 BACKGROUND The Lugo-Victorville RAS was last approved by the RASRS in August of 2016 The RAS was designed to protect the Lugo-Victorville 500 kv T/L from an identified thermal overload caused by the N-1 of the Eldorado-Lugo 500 kv T/L The RAS is approved to trip four (4) PV plants in the Eldorado Area: Silver State South Solar (250 MW) Desert Stateline (300 MW) Copper Mountain 2 (92 MW) Copper Mountain 4 (155 MW) The RAS is classified and approved as a LAPS Informational Presentation was given to the RASRS on August 1, 2017 SCE to trip generation within another transmission service providers territory 5

6 BACKGROUND Generation Interconnection Studies have identified the need to trip Eldorado area generation for the loss of the Eldorado-Lugo 500 kv T/L to prevent thermal overloads on the LADWP/SCE jointly owned Lugo-Victorville 500 kv T/L 6

7 AREA MAP OF PARTICIPATING GENERATORS 7

8 BACKGROUND On October 13, 2011 Valley Electric Association (VEA) and the CAISO entered into a Transition Agreement which established the process for VEA to join the CAISO Balancing Authority Area (BAA) In January of 2013, VEA joined the CAISO BAA Primarily consists of 230kV and 138kV facilities 230kV system later acquired by GridLiance West Transco LLC (GWT) As part of the Generation Interconnection Study Process, projects requesting to interconnect within the GWT and VEA Electric Systems are subject to participate in existing RAS s within the SCE Electric System Lugo-Victorville RAS Joint-studies are completed annually between SCE, VEA and the CAISO SCE and VEA are seeking input/approval for a proposed design that would allow the tripping of generation requesting to interconnect within the GWT and VEA Electric Systems as part of the Lugo-Victorville RAS 8

9 BACKGROUND Sunshine Valley Solar Proposed 100 MW Solar Photovoltaic Project Amargosa Valley, Nye County, Nevada Interconnecting to the VEA Valley 138 kv Substation Advanced Rail Energy Storage (ARES)-To be presented at a future date Proposed 44 MW Energy Storage Project Pahrump, Nye County and Clark Counties, Nevada Interconnecting to the GWT Gamebird 230 kv Substation Generation Interconnection Studies have identified these projects as having to participate in the Lugo-Victorville RAS CAISO Queue # Sce Project ID Project Name Point of Interconnection Technology Status ISD Size (MW) Q993/Q994 TOT678/ TOT679 Sunshine Valley Solar Valley 138 kv Solar Photovoltaic IA with VEA 6/1/ Q1064 TOT728 ARES (Future) Gamebird 230 kv Energy Storage UFA with SCE 7/30/

10 Single Line Diagram of Eldorado Area 10

11 Lugo-Victorville RAS Area Map - SCE facilities and Participating Generating Units 11

12 Lugo-Victorville RAS Area Map - VEA facilities and Participating Generating Units 12

13 Lugo-Victorville RAS Operation SCE to send trip signal to each generating facility through planned telecom facilities SCE GWT VEA Signal to open all 34.5 kv CB s at the generating facility Signal to be sent from the SCE Eldorado Substation through telecom facilities placed as part of the planned Bob-Eldorado 230 kv Line 2.5 mile planned intertie 13

14 AREA MAP-Partial Map of GWT and VEA Facilities (New Participants) 14

15 PURPOSE/OPERATING PRINCIPLES The purpose of the Lugo-Victorville RAS is to prevent thermal overloads on the Lugo-Victorville 500 kv T/L, upon loss of the Eldorado-Lugo 500 kv T/L, by tripping selected solar generation projects in the SCE, GWT, and VEA service territories. Contingencies/Actions: A. N-1 of Eldorado-Lugo 500 kv T/L I. Trip generation in the Eldorado Area Existing Generation (797 MW) Sunshine Valley Solar (100 MW)-New Participant ARES (44 MW)-New Participant Total Generation Armed (941 MW) Operating Date: August 11,

16 LUGO-VICTORVILLE RAS PROJECT Planning Studies The purpose of the RAS Arming Study is to identify the appropriate RAS arming levels required under all plausible system operating conditions. The power flow cases were developed from the WECC base cases and SCEs transmission expansion base case series representing summer peak and spring off peak load conditions The RAS Arming Study looked at a wide range of load levels, generation levels, and voltage conditions, in order to be compliant with NERC Reliability Standards, WECC Regional Criteria, and CAISO Planning Standards. Through this type of analysis, the RAS Arming Study identifies the appropriate contingencies that need to be monitored by the RAS. The RAS Arming Study also identifies the pre-contingency system conditions that should trigger RAS arming, and what units of generation should be designed to participate in the RAS. 16

17 LUGO-VICTORVILLE RAS PROJECT Planning Studies (Cont.) Identified Issues: Thermal overload Lugo-Victorville 500 kv T/L The planning studies confirmed that the Lugo- Victorville RAS will contribute toward the mitigation When required, the CAISO will congestion manage flows on the Lugo- Victorville T/L (Path 61) such that generation tripped as part of the RAS will eliminate the overload. Congestion management initiated once post-contingency flows on Path 61 approach 3000 A. 17

18 LUGO-VICTORVILLE RAS PROJECT Study Assumptions The table below represents the generation that will be required to participate in the Lugo-Victorville RAS A total of 941 MW will be eligible for tripping ARES to be presented at a future WECC RASRS 18

19 LUGO-VICTORVILLE RAS PROJECT Study Assumptions Power Flow Study The study was based on forecasted load data for 2020 Generation in the study areas modeled at full output New generation modeled at full output East of Lugo stressed under various conditions Path 61 (Lugo-Victorville) modeled at maximum path rating of 2400 MW (east to west) Intermountain Power Plant DC (IPPDC) Line modeled up to 2400 MW (Max) West Of River (Path 46) modeled up to 10,500 MW (Path Rating = 11,200 MW) Analysis included combination of these flows (High IPPDC / Low WOR, Low IPPDC / High WOR, etc.) Transient Stability Studies 4 cycle 3-phase fault for N-1 of Eldorado-Lugo 500 kv T/L 4 cycle 3-phase fault with tripping of generation modeled at 3 seconds after fault is cleared The studies show that the system remains stable following a 4 cycle 3-phase fault and loss of the Eldorado-Lugo 500 kv T/L 19

20 LUGO-VICTORVILLE RAS PROJECT Stability Results: N-1 of Eldorado-Lugo 500 kv T/L Bus Voltage following 4 cycle fault No RAS 20

21 LUGO-VICTORVILLE RAS PROJECT Stability Results: N-1 of Eldorado-Lugo 500 kv T/L Bus Voltage following 4 cycle fault With RAS 21

22 LUGO-VICTORVILLE RAS PROJECT Stability Results: N-1 of Eldorado-Lugo 500 kv T/L Bus Frequency following 4 cycle fault No RAS 22

23 LUGO-VICTORVILLE RAS PROJECT Stability Results: N-1 of Eldorado-Lugo 500 kv T/L Bus Frequency following 4 cycle fault With RAS 23

24 LUGO-VICTORVILLE RAS PROJECT RAS Overview The RAS will be designed to trip generation consistent with the table below Notes: 1. Arming points 1 6 will be under the control of the automatic arming program. 1. Arming points 1 6 will be based on line flows on the Lugo-Victorville 500 kv T/L 2. Arming points 1-6 will be automatically armed whenever the associated generator is on line, and will be automatically disarmed whenever the associated generator is off line. 24

25 LUGO-VICTORVILLE RAS PROJECT RAS Overview Real Time Contingency Analysis (RTCA) CAISO Action Will calculate post-contingency flow on Lugo-Victorville for loss of Eldorado-Lugo RAS will arm generation once post-contingency flows reach 95% of the Lugo-Victorville emergency rating (3000 Amps) Will dynamically calculate how much generation needs to be armed If the RTCA fails for more than the preset time period, the RAS will switch to offline arming equation Magnitude of thermal overload dependent on various factors IPPDC Line Flow WOR Flows Series compensation levels Extended line outages scheduled for the next 2-3 years. Under certain stressed conditions, tripping all Lugo-Victorville RAS generation will not eliminate the overload Congestion management will be initiated anytime the RTCA show that post-contingency flow on Lugo-Victorville is approaching its 3000 Amp limit 25

26 RAS Classification SCE is classifying the Lugo-Victorville RAS as a LAPS for the following reasons: Less than 1,000 MW of generation at risk. No generation at risk due to failure of RAS to operate Thermal overload of Lugo-Victorville T/L would result No voltage violations identified CAISO will dispatch generation and reduce path flow to eliminate overload on Lugo- Victorville following failure of RAS to trip generation Less than 300 MW of load is at risk. No load is served out of Ivanpah, Primm, or Merchant East of Lugo is not a load serving area VEA/GWT Service Territory not impacted by loss of Eldorado-Lugo T/L No violation of TPL-001-WECC-CRT-3.1 SCE requests RASRS concurrence that the Lugo-Victorville RAS is a LAPS 26

27 RAS Classification 27

28 LUGO-VICTORVILLE RAS PROJECT Conclusion The RAS will arm generation once post-contingency flows reach 95% of the Lugo-Victorville emergency rating The RAS will initiate once an outage of the Eldorado-Lugo 500 kv T/L has been detected to prevent thermal overloads on the Lugo-Victorville 500 kv T/L. One new project is required to participate in the RAS Sunshine Valley Solar (100 MW) The RAS will trip a combination of or all of the eligible participating generation to mitigate thermal overloading. Up to 897 MW Once more generation interconnects in the Eldorado Area, the Lugo-Victorville RAS will need to be expanded to include those projects (An additional 44 MW is proposing to interconnect by 7/30/19). Transient stability studies concluded that the system will remain stable under the most stressed condition. 28

29 LUGO-VICTORVILLE RAS Protection Engineering Bill Zhang 29

30 LUGO-VIC RAS PROTECTION ENGINEERING Recap of Previously Approved Scheme Redundant identical systems Diverse redundant communications paths Mitigate for failed mitigation breakers Multiple means of arming Contingency-triggered logic Pre-contingency arming by automatic arming program N60 relays used throughout 30

31 LUGO-VIC RAS PROTECTION ENGINEERING RAS Block Diagram 31

32 LUGO-VIC RAS PROTECTION ENGINEERING What s New New redundant N60 monitoring relays at Mohave to monitor the Lugo-Mohave 500kV line. Existing N60 monitoring relays at Lugo New redundant N60 mitigating relays at Eldorado sending trips to Sunshine Valley Solar New diversely-routed telecomm paths from Eldorado to Sunshine Valley Solar via VEA s Bob Sub New redundant N60 tripping relays at Sunshine Valley Solar 32

33 LUGO-VIC RAS PROTECTION ENGINEERING Line Monitors One N60 relay monitors up to two 500 kv lines Line-Loss Logic: 52b contacts supervised by undercurrent element Separate 52b switches for each breaker Maintenance bypass switches for 52b inputs Alarms Relay Failure Alarm Communication Channel Failure Alarm Direct Device Off-line Direct Ring Break Communication Channel Trouble Alarm Excessive CRC Errors Excessive Unreturned Direct I/O messages CB Disagreement Alarm RAS-A and RAS-B disagree on the open/closed state of a breaker CB Error Alarm 52b switches show both breakers open, but undercurrent function has not operated 33

34 LUGO-VIC RAS PROTECTION ENGINEERING At each Generating Station One Trip output contact for each circuit breaker to be tripped One Trip indication output contact Mitigate for failed tripping breaker At each Breaker failure protection is initiated from RAS operation One Breaker Failure Initiation output contact for each circuit breaker tripped One set of latching output contacts to disable trips and insert a load resistor during Auto-Test Alarms Relay Failure Alarm Communications Channel Failure Alarm Direct Device Off-line Direct Ring Break Communications Channel Trouble Alarm Excessive CRC errors Excessive unreturned message errors 34

35 LUGO-VIC RAS PROTECTION ENGINEERING Relays Sequential Events Records Oscillography GPS clock synchronized Relay alarms Arming status Line-out status RAS Trip alarm 35

36 LUGO-VIC RAS PROTECTION ENGINEERING Commissioning Tests Wiring connections are being verified and tested Inputs and output contacts are being tested Logic functions are being tested Communications circuit is being verified and equipment trip tested Auto-Test is being executed at conclusion of commissioning tests 36

37 LUGO-VICTORVILLE RAS Power System Controls Obinna Obah 37

38 Objectives: LUGO-VICTORVILLE RAS Existing Lugo-Victorville RAS (LVRAS) Automatic Arming Program (AAP) will be modified to add one new participating generator: Sunshine Valley Solar (SVS) 100 MW The automatic arming program will calculate the arming requirement and optimally arm the appropriate amount of generation to be tripped to keep loading on Lugo-Victorville line within limit. Reliability: The automatic arming program runs in the SCE s Energy Management System (EMS), which is a redundant mission-critical system. 38

39 LUGO-VICTORVILLE RAS AAP Operational Features: LVRAS automatic arming program uses result from EMS Realtime Contingency Analysis (RTCA) application as input to determine appropriate amount of generation to be armed once every 5 minutes. If RTCA becomes unavailable or fails more than a preset time period, the automatic arming program will switch to using offline arming equation from Power flow studies performed by the Electric System Planning (ESP) unit to determine arming requirement. California Independent System Operator (CAISO) will be notified via ICCP of the Total MW of Generation armed for the LVRAS. 39

40 LUGO-VICTORVILLE RAS Remote/Local Manual Arming: In the event Automatic Arming Program is unavailable, the Lugo- Victorville RAS can be manually armed by one of the following two (2) methods: Remotely via Supervisory Control from the EMS by the System Operator at Eldorado Switching Center. Locally via pushbuttons on the front panels of RAS relays at the Eldorado Substation. 40

41 LUGO-VICTORVILLE RAS 41

42 Lugo Victorville RAS Telecommunications Larry Wang 42

43 LUGO VICTORVILLE RAS Telecommunication Element FOLLOWING SLIDES: 1. Overview for RAS A and RAS B Circuits 2. Details for RAS Circuits 3. VEA Network 4. Equipment Redundancy and Reliability 5. System Monitoring and Problem Resolution 43

44 Lugo Victorville RAS Overview w/ Sunshine Valley Solar LEGEND Sunshine Valley Solar Leased Circuit OPGW Microwave Fiber MW Repeater site RAS Circuit location 24 mi 0.5 mi Valley Desert View 57 mi Sawtooth Robs Peak 34 mi 65 mi B (LADWP) Turquoise NVE Northwest Pahrump 35 miles Desert State Line A B IVANPAH 74 mi PRIMM 12 mi Lower Potosi Silver State South 5 miles NIPTON CS Beer Bottle B Bob 25 miles B ELDORADO Opal Christmas Tree Black Metal Big Maria Red Mtn McCollough SDG&E Merchant Copper Mtn 4 Copper Mtn 2 Fiber Optic Node Lane Mtn Blythe DO Colorado River A Red Bluff Quartzite Cal Cap Victor Sub Mira Loma Vista Sub Mirage LUGO 44

45 Eldorado CB Lugo Victorville RAS Circuit System Block Diagram Eldorado DSL JMUX Comm Room 01/XR--/065179/SCE/ 103/T1/ELDO5090/IVAN8363 & 103/T1/IVAN0004/IVAN8363 A 01/XR--/065179/SCE/ JMUX T A 01/XR--/065180/SCE/ Eldorado CB B T /T1/IVAN8363DO1/ELDO Ivanpah DACS 101/T1/IVAN0004/IVAN8363D01 DSL CB B T /XR--/065180/SCE/ 01/SC--/064247/SCE/ 01/XR--/065181/SCE/ Eldorado 220/500 MEER JMUX A 101/T1/ELDO /PRIM8372 & 103/T1/PRIM0001/PRIM8372 SSS JMUX A T /XR--/065181/SCE/ 01/XR--/065182/SCE/ 01/XR--/065427/SCE/ 01/SC--/065429/SCE/ B T /T1/ELDO /PRIM8372D01 Primm DACS 101/T1/PRIM0001/PRIM8372D01 SSS CB B T /XR--/065182/SCE/ 01/SC--/064438/SCE/ 01/XR--/065426/SCE/ 01/SC--/065428/SCE/ Eldorado CB A T Eldorado DACS /T1---P/ELDO5090D01/LUGO5061D01 Lugo DACS 122 Lugo CB A T /XR--/065426/SCE/ 01/SC--/064438/SCE/ 01/SC--/064247/SCE/ 101 Vista DACS 104 Mira Loma DACS Mira Loma CB A T /SC--/065428/SCE/ 102 Eldorado DACS /T1 /ELDO5090D02/LUGO5061 Lugo CB B T /XR--/065427/SCE/ 102 Mira Loma DACS Mira Loma CB B T /SC--/065429/SCE/ 01/SC--/065196/SCE/ 01/SC--/065199/SCE/ 01/XR--/065194/SCE/ Eldorado JMUX A T /T1 /BOUL0002 /ELDO CM2 JMUX A T /XR--/065194/SCE/ 01/XR--/065195/SCE/ Eldorado CB B T /T1 /BOUL0002 /ELDO CM2 CB B T /XR--/065195/SCE/ 01/SC--/065196/SCE/ 01/XR--/065197/SCE/ Eldorado JMUX A T /T1 /BOUL0004 /ELDO CM4 JMUX A T /XR--/065197/SCE/ 01/XR--/065198/SCE/ Eldorado CB B T /T1 /BOUL0004 /ELDO CM4 CB B T /XR--/065198/SCE/ 01/SC--/065199/SCE/ 01/XR--/071140/SCE/ Eldorado CB A T /T1 /BOUL0007 /ELDO Bob SW 101 /T1 /AMAR0001 /BOUL0007 Sunshine Valley Solar ICON A 01/XR--/071140/SCE/ 01/XR--/071141/SCE/ Eldorado CB B T /T1 /BOUL0007 /ELDO Bob SW 102 /T1 /AMAR0001 /BOUL0007 Sunshine Valley Solar ICON B 01/XR--/071141/SCE/ A Route B Route RTU with no diversity requirements 45

46 LUGO VICTORVILLE RAS A & B PATH B Quartzite Lane Turquoise Lower Potosi Red Mtn McCollough Fiber Optic Cable Lugo SCE Microwave Path Eldorado Eldorado 500/220kV LADWP Microwave Path Big Maria/ Christmas Mira Loma Vista Blythe DO Opal Black Metal Tree A DSL DSL Ivanpah A Eldorado Ivanpah Nipton CS B Eldorado 500/220kV Primm Eldorado 500/220kV Primm Beer Bottle CS Red Mtn CS Eldorado Eldorado 500/220kV SSS SSS A CM2 OPGW ADSS Merchant OPGW UG Eldorado Comm Room ELD-017-SM ELD-018-SM Eldorado 500/220kV B CM2 OPGW ADSS Merchant OPGW UG Eldorado Comm Room ELD-017-SM ELD-018-SM Eldorado 500/220kV A CM4 OPGW ADSS Merchant OPGW UG Eldorado Comm Room ELD-017-SM ELD-018-SM Eldorado 500/220kV B CM4 OPGW ADSS Merchant OPGW UG Eldorado Comm Room ELD-017-SM ELD-018-SM Eldorado 500/220kV A Bob Sw/ OPGW SVS Rob s ADSS OPGW ADSS Eldorado Valley Sawtooth Pahrump Sloan Peak 500/220kV Canyon B SVS UG Valley ADSS/OPGW Desert View OPGW NW LEASED OC-3 CKT Bob Sw/ Sloan Canyon UG Eldorado 500/220kV 46

47 RAS CIRCUIT INTERFACE VEA SCE LW/CH RAS-A (ICON) 101 /T1 /AMAR0001 /BOUL0007 VEA NETWORK FOR RAS-A PATH LW/CH (ICON) 101 /T1 /BOUL0007/ELDO / LW TRAN (DMXTEND) LW TRANSPORT (DMXTEND) 01/XR--/071138/ /SCE / T1 Connection CH EQPT RAS-A (ZHONE800) 01/XR--/071140/ /SCE / 01/XR--/071138/ /SCE / 01/XR--/071140/ /SCE / Sunshine Valley Solar Gen Bob Sw (Sloan Canyon) Eldorado Sub (AMAR0001) (BOUL0007) (ELDO ) LW/CH RAS-B (ICON) 102 /T1 /AMAR0001 /BOUL0007 VEA NETWORK FOR RAS-B PATH LW/CH (ICON) 102 /T1 /BOUL0007/ELDO / LW TRAN (DMXTEND) LW TRANSPORT (DMXTEND) 01/XR--/071139/ /SCE / 01/XR--/071141/ /SCE / T1 Connection CH EQPT RAS-A (ZHONE800) 01/XR--/071139/ /SCE / 01/XR--/071141/ /SCE / 01/XR--/071138/ /SCE / 01/XR--/071140/ /SCE / ELDORADO TO SUNSHINE VLY SOLAR IVANPAH AREA RAS A ELDORADO TO SUNSHINE VLY SOLAR LUGO-VICT RAS A 01/XR--/071139/ /SCE / 01/XR--/071141/ /SCE / ELDORADO TO SUNSHINE VLY SOLAR IVANPAH AREA RAS B ELDORADO TO SUNSHINE VLY SOLAR LUGO-VICT RAS B 47

48 VEA Network 48

49 VEA Network 49

50 VEA Network 50

51 Equipment Redundancy SCE Network TABLE: IVANPAH AREA RAS Equipment Redundancy Equipment Description Manufacture Model Redundancy Channel Bank Zhone IMACS 800 CPU, Power Supply, T1 Module OHSU IEEE C Channel Unit Zhone None DACS Sycamore DNX 11 All Critical Electronics 1:1 SONET Alcatel Lucent DMX Access Multiplexer 1:1 SONET Alcatel Lucent DMXtend Access Multiplexer 1:1 SONET Alcatel Lucent 1850 Transport Service Switch (TSS1:1 SONET General Electric JungleMUX (OC 12) Optical, Power Supplies, DS1 & VT modules Microwave Radio Alcatel MDR 8000 Hot Standby, transmitters and receivers M13 Multiplexer TelCo Systems EdgeLink 100 1:1 T1 Channel Service Unit Kentrox T-SMART None VEA Network TABLE: VEA Telecom Equipment Redundancy Equipment Description Manufacturer Model Redundancy SONET SEL SEL ICON Power Supply, Optical Line module NX64 C37.94 MM SEL None Microwave Radio Nokia MPR9500 Hot Standby TX/RX, DS-1 Tributary, Power Supply 51

52 System Monitoring and Problem Resolution SCE Network SONET employs element management systems All sites have point alarms for equipment & environmental alarms Telecom Control Center (TCC) monitors 24/7/365, using Spectrum TCC responsible for coordination and dispatch of repair personnel Comm. Techs based throughout service territory; spare parts stored at several key locations Priority 1 problems have 2 hour response time, and 4 hour repair time VEA Network: Dispatch Center monitor electrical grid status and conditions throughout VEA s service territory on a 24x7 basis Dispatch personnel are responsible for problem analysis and dispatch of VEA Telecommunications technicians and outside plant forces to resolve problems in the event of a communications system alarm condition 52

53 Questions 53

54 SCE is requesting approval of Modifications to Lugo-Victorville RAS to add the following project: Sunshine Valley Solar 100 MW 54

55 Thank You! 55

56 Backup Slides 56

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

APPENDIX F: Project Need and Description

APPENDIX F: Project Need and Description APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JULY 2015) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (OCTOBER 2016) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report San Diego Gas & Electric, a Sempra Energy Utility SDGE HVDC Phase 1 Project No. 101512 Revision 01 11/29/2018 SDG&E High

More information

March 7, Subject: Southern California Edison 2011 Annual Progress Report

March 7, Subject: Southern California Edison 2011 Annual Progress Report March 7, 2011 Mr. Kyle Kohne Mr. Kent Bolton Chair, WECC Technical Studies Subcommittee WECC Technical Staff Bonneville Power Administration University of Utah Research Park P.O. Box 61409 615 Arapeen

More information

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection Feasibility Study Customer Kingman Area Photovoltaic Generation Project Interconnection October, 2009 October 2009 i EXECUTIVE SUMMARY CONCLUSION Customer has requested network resource interconnection

More information

TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis

TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis July 25, 2018 Table of Contents 1. Introduction... 5 1.1. Project Description and

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications Supplement to 2013-2014 ISO Transmission Plan Harry Allen-Eldorado Project Description and Functional Specifications Description and Functional Specifications of Proposed Economically Driven Harry Allen

More information

APPENDIX G: Contingencies on the ISO System that may Impact Adjacent Systems

APPENDIX G: Contingencies on the ISO System that may Impact Adjacent Systems 2016-2017 ISO Transmission Plan March 17, 2017 APPENDIX G: Contingencies on the ISO System that may Impact Adjacent Systems California ISO/MID G-1 2016-2017 ISO Transmission Plan March 17, 2017 Intentionally

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

for DRECP Alternatives

for DRECP Alternatives Transmission Technical Group Conceptual Transmission Plan for DRECP Alternatives DRECP WebEx Meeting January 9, 2013 Overview Purpose, Participants, and Timeline Generation Assumptions Transmission Assumptions

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JULY 2014) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,

More information

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655) - (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility

More information

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013 Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in 2015 Stakeholder Webconference February 28, 2013 Page 2 Merced Irrigation District (Merced) Background Merced Irrigation

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

The Long-Range Transmission Plan

The Long-Range Transmission Plan The Long-Range Transmission Plan 2015 2025 Matt Koenig Presentation to ESPWG / TPAS October 29 th, 2015 Long-Range Transmission Plan Driver of the Plan is to maintain local reliability 10-year planning

More information

Q0044 interconnection at

Q0044 interconnection at Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2014 Annual Ten-Year Transmission Plan Assessment Report November 20, 2014 For information or questions regarding this Transmission Assessment Report,

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1 Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System

More information

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management Southern Company Interconnection Process Dexter Lewis Research Engineer Research and Technology Management Southern Company Outline Southern Company GPC Solar Interconnection Process Application requirements

More information

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES: TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design

More information

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS July 15, 2004 TABLE OF CONTENTS Page No. 1. Description of Pasadena s Transmission Lines and Facilities...1 A. Overview:... 1 B.

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Interconnection Feasibility Study

Interconnection Feasibility Study Interconnection Feasibility Study Mount Mabel Wind Energy Project Report No: T&S Planning 2015-054 December 2015 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2015.

More information

Transient Stability Analysis Tool (TSAT) Update April 11, Hongming Zhang EMS Network Applications Manager

Transient Stability Analysis Tool (TSAT) Update April 11, Hongming Zhang EMS Network Applications Manager Transient Stability Analysis Tool (TSAT) Update April 11, 2016 Hongming Zhang EMS Network Applications Manager Agenda Peak Online TSAT Introduction: Where we are on Wide-wide System Model (WSM) -TSAT online

More information

PUD ELECTRIC SYSTEM INTERCONNECTION

PUD ELECTRIC SYSTEM INTERCONNECTION APPENDIX A PROCEDURES & REQUIREMENTS for OKANOGAN PUD ELECTRIC SYSTEM INTERCONNECTION Version 4.0 December 2011 Version 4.0 12/28/2011 Page 1 of 15 TABLE OF CONTENTS DEFINITIONS 1.0 Introduction 2.0 Procedures

More information

HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY BOARD

HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY BOARD SCHEDULED ITEM TO: FROM: HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY BOARD GEORGE F. MORROW, DIRECTOR OF UTILITIES DATE: JANUARY 28, 2013 SUBJECT: APPROVAL OF POWER SALES AGREEMENT ( PSA ) WITH

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region Western Area Power Administration Sierra Nevada Region 2013 Annual Ten-Year Transmission Plan Assessment Report December 1, 2013 For information or questions regarding this Transmission Assessment Report,

More information

Project #94. Generation Interconnection System Impact Study Report Revision

Project #94. Generation Interconnection System Impact Study Report Revision Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection

More information

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC

More information

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving

More information

Introduction and Overview

Introduction and Overview Introduction and Overview Neil Millar Generation Deliverability Assessment Methodology Proposal Call December 18, 2018 Generation Deliverability Methodology Revision Process November 16, 2018: CAISO presented

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Distributed Energy Resources

Distributed Energy Resources Distributed Energy Resources WECC Data Subcommittee Rich Hydzik, Avista (ERSWG/DER Subgroup Lead) June 29, 2018 Why Are We Concerned About DER? Concern about changing generation fleet Large coal fired

More information

SDG&E Valley-Rainbow Project

SDG&E Valley-Rainbow Project SDG&E Valley-Rainbow Project Presentation to Grid Reliability/Operations Committee Steven Mavis ISO Grid Planning Department May 24, 2000 1 Background SDG&E s 1999 Expansion Plan for 2000-2004 indicated

More information

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M of Need In-service Cost Alternatives Service Projects in PG&E Service Territory Mare Island - Ignacio 115 kv NERC Category 2010 Reconductor the limiting 19 $19M Connect Highway May 2012 Line re-rates and

More information

Small Generator Interconnection Program Interconnection Technical Requirements

Small Generator Interconnection Program Interconnection Technical Requirements General Program Information What is the purpose of the PGE Small Generator Interconnection Program? How do I initiate a distribution interconnection request for my project? The purpose of our Small Generator

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Full Network Model Scope for FNM DB59

Full Network Model Scope for FNM DB59 Transmission Projects PG&E SCE 1. Cottle 230 kv Ring Bus Project 2. Carrizo Plain Solar Generation 3. Calpine Russell City Energy Center (Eastshore - San Mateo & Dumbarton-Newark) 4. Bridgeville Bk. #2

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

Pacific Gas and Electric Company s Revised 2015 Annual Progress

Pacific Gas and Electric Company s Revised 2015 Annual Progress March 02, 2015 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Avista PO Box 3727 MSC-16 1411 East Mission Ave Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff 155 North 400 West

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

Table of Contents. Purpose. Eldorado Intertie and System (Eldorado- Moenkopi) Scheduling at Willow Beach. Operating Procedure

Table of Contents. Purpose. Eldorado Intertie and System (Eldorado- Moenkopi) Scheduling at Willow Beach. Operating Procedure No. 6930 Table of Contents Purpose... 1 1. Limits, Ratings, & Effectiveness Factors... 2 2. Contingency Operations... 2 2.1 Transmission Lines Outages... 2 2.2 APS Terminal Equipment Outages... 2 2.3 SCE

More information

Valley - Rainbow Interconnection Project Feasibility Study Report

Valley - Rainbow Interconnection Project Feasibility Study Report Attachment A Valley - Rainbow Interconnection Project Feasibility Study Report A Joint Study Effort of San Diego Gas & Electric (SDG&E) and Southern California Edison (SCE) in Cooperation with the California

More information

GENERATING FACILITY INTERCONNECTION APPLICATION. Part 1 Introduction and Overview

GENERATING FACILITY INTERCONNECTION APPLICATION. Part 1 Introduction and Overview Part 1 Introduction and Overview A. Applicability: This Generating Facility Interconnection Application (Application) is used to request the interconnection of a Generating Facility to Southern California

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC OCTOBER 17, 2018 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

2016 SDG&E Grid Assessment Results

2016 SDG&E Grid Assessment Results 2016 SDG&E Grid Assessment Results CAISO Stakeholder Meeting September 22, 2016 Matthew Belden Engineer II San Diego Gas & Electric Email: MBelden@semprautilities.com 2016 Study Windows One to Five-Year

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

Use of High-Power Thyristor Technology for Short-Circuit Current Limitation in High Voltage Systems

Use of High-Power Thyristor Technology for Short-Circuit Current Limitation in High Voltage Systems Advanced Power Transmission Solutions Power Transmission and Distribution Use of High-Power Thyristor Technology for Short-Circuit Current Limitation in Systems s Development of Power Markets Increasing

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS El Paso Electric Company El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS 2015 2024 A Review on System Performance Following Extreme Bulk Electric System Events of the

More information

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PSE&G System Characteristics New Jersey utility characterized by densely populated

More information

PACI RAS Updates. Vahid Madani Pacific Gas and Electric Co. August 2, 2017

PACI RAS Updates. Vahid Madani Pacific Gas and Electric Co. August 2, 2017 1 PACI RAS Updates Vahid Madani Pacific Gas and Electric Co. August 2, 2017 2 Outline PACI RAS Pacific AC Intertie RAS Overview of PACI RAS Mosher New Substation & Stagg Updates Gates Substation 230kV

More information

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER 1 Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER Lisa Dangelmaier Hawaii Electric Light lisa.dangelmaier@hawaiielectriclight.com Hawai'i Electric Light System Overview

More information

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006 Final System Impact Study for Sierra Pacific Industries 31 MW Generation Project Mount Vernon, WA November 16, 2006 Puget Sound Energy, Inc. Electric Transmission Department 1 1. Introduction On October

More information

Interconnection System Impact Study Final Report February 19, 2018

Interconnection System Impact Study Final Report February 19, 2018 Interconnection System Impact Study Final Report February 19, 2018 Generator Interconnection Request No. TI-17-0225 248.4 MW (Alternate Project Output of 217.35 MW) Wind Energy Generating Facility In Goshen

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Connection Engineering Study Report for AUC Application: AESO Project # 1674 APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System

More information

What is Smart Grid? R.W. Beck Inc.

What is Smart Grid? R.W. Beck Inc. ELG4126: Smart Grid The Smart Grid Uses telecommunication and information technologies to improve how electricity travels from power plants to consumers. Allows consumers to interact with the grid. Integrates

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

PSE Attachment K Puget Sound Area Transmission Meeting

PSE Attachment K Puget Sound Area Transmission Meeting PSE Attachment K Puget Sound Area Transmission Meeting Stephanie Lu Senior Engineer December 15, 2011 Agenda Attachment K Review Economic Studies Process PSE Planning Process and Assumptions PSE Projects

More information

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions. March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

Implementing a Microgrid Using Standard Utility Control Equipment

Implementing a Microgrid Using Standard Utility Control Equipment Implementing a Microgrid Using Standard Utility Control Equipment Tom Fenimore Duke Energy Andy Gould and Larry Wright Schweitzer Engineering Laboratories, Inc. Copyright Duke Energy and SEL 2016 Overview

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04 Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch

More information

Pacific Gas and Electric Company s Revised 2016 Annual Progress

Pacific Gas and Electric Company s Revised 2016 Annual Progress March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric

More information

North Oregon Coast Area Study. Adam Lint

North Oregon Coast Area Study. Adam Lint North Oregon Coast Area Study Adam Lint PAGE 2 North Oregon Coast System Overview - Clatsop Study Covers: Transmission Switching Stations (Clatsop District): Astoria Lewis and Clark 115 kv Distribution

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd Embedded Generation - Technical Access Standards Embedded Generation - 5 MW or Greater ELE SP 0003 Public 1 October 2014 TABLE OF CONTENTS TABLE OF CONTENTS Abbreviations...

More information

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project. Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project April 23, 2003 Introduction Eurus originally requested an interconnection

More information

Laboratory Scale Microgrid Test-Bed Hardware Implementation

Laboratory Scale Microgrid Test-Bed Hardware Implementation Laboratory Scale Microgrid Test-Bed Hardware Implementation Joyer Benedict Lobo Ameya Chandrayan Peter Idowu, Ph.D. In Partnership with: Outline Features of a Microgrid Microgrid Test Bed at Penn State

More information

NERC-led Review Panel Decision on the Request of City of Pasadena Water and Power

NERC-led Review Panel Decision on the Request of City of Pasadena Water and Power NERC-led Review Panel Decision on the Request of City of Pasadena Water and Power The North American Electric Reliability Corporation (NERC)-led Review Panel (Panel) has completed its evaluation of the

More information

Load Modeling for Power System Studies

Load Modeling for Power System Studies Load Modeling for Power System Studies WECC Load Modeling Task Force Dmitry Kosterev Bonneville Power Administration Transmission Planning Timescale of Interest Our primary interest is the fast dynamic

More information

Falcon-Midway 115 kv Line Uprate Project Report

Falcon-Midway 115 kv Line Uprate Project Report Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50

More information