Santa Clara-Alum Rock Bus Rapid Transit (BRT) Project. Project Update July 2014
|
|
- Charlene Shelton
- 5 years ago
- Views:
Transcription
1 Santa Clara-Alum Rock Bus Rapid Transit (BRT) Project Project Update July 2014
2 Today Overview of Santa Clara-Alum Rock Bus Rapid Transit and update on Construction Shelter Design Updates Construction Mitigation Business Incentive Program Station Art Enhancements VTA and Public Art US. 101 Improvements Program BART Stations BART Transit Integration Plan 2 Santa Clara -Alum Rock BRT
3 Background What is BRT? Specialized Vehicles Unique Branding Dedicated Lanes Bulb out Stations Enhanced Stations Faster Boarding Transit Signal Priority 3 Santa Clara -Alum Rock BRT
4 Project Alignment and Station Locations Santa Clara -Alum Rock BRT 4
5 Santa Clara/Alum Rock Project Santa Clara Street BRT station bulb outs and sidewalk platforms Five station locations Arena Downtown City Hall 17 th 24th Enhanced lighting near station areas 5 Santa Clara -Alum Rock BRT
6 Santa Clara/Alum Rock Project Alum Rock Avenue Exclusive median bus lanes Two median BRT stations: King, Jackson New paving and LED street lights along Alum Rock New signals at 34 th, Eastgate and Scharff Avenue 6 Santa Clara -Alum Rock BRT
7 Santa Clara/Alum Rock Project Capitol Expressway Curbside stations Three station locations Alum Rock Story Ocala + Eastridge 7 Santa Clara -Alum Rock BRT
8 Station Rendering: WB Arena, Downtown, City Hall 8 Santa Clara -Alum Rock BRT
9 Station Rendering: WB Arena, Downtown, City Hall Santa Clara -Alum Rock BRT 9
10 10 Station Rendering: EB Arena, 17 th, 24 th, Alum Rock, Story, and Ocala
11 Median Bus Lanes Dedicated bus lanes on Alum Rock Avenue. 11 Santa Clara -Alum Rock BRT
12 Typical Median BRT Station on Alum Rock 12 Santa Clara -Alum Rock BRT
13 13 Public Art Enhancement
14 14
15 15
16 16
17 17
18 18
19 19
20 20
21 Sample: Alum Rock Windscreen 21 Santa Clara -Alum Rock BRT
22 22
23 Sample: Story Windscreen 23 Santa Clara -Alum Rock BRT
24 24
25 Sample: Ocala Windscreen 25 Santa Clara -Alum Rock BRT
26 26
27 Eastridge Transit Center Rendering Santa Clara -Alum Rock BRT 27
28 U.S. 101 Interchange Project, Tully/Capitol Expressway/Yerba Buena Road Intersections 28
29 U.S. 101 Interchange Project, Tully/Capitol Expressway/Yerba Buena Road Intersections 29
30 U.S. 101 Interchange Project, Tully/Capitol Expressway/Yerba Buena Road Intersections 30
31 U.S. 101 Interchange Project, Tully/Capitol Expressway/Yerba Buena Road Intersections 31
32 U.S. 101 Interchange Project, Tully/Capitol Expressway/Yerba Buena Road Intersections 32
33 Santa Clara/Alum Rock Project Project Updates: 33 Santa Clara -Alum Rock BRT
34 VTA Planning for BART Warm Springs/South Fremont station opening 2015, Milpitas & Berryessa 2017 Berryessa Connectors: 323 Stevens Creek every 10 min Downtown Limited Stop every 15 min Berryessa Connector Study (completed 2013) recommended new frequent services between Berryessa and Downtown San Jose BART Transit Integration Plan (BTIP) service planning for all BART connections and related service Fares and transfer policies separate analyses 34
35 BART Transit Integration Plan (BTIP) Service and related capital improvements (e.g., stops) Connections to BART but also a fresh look at service network Relationship of Great Mall/Main Transit Center to Milpitas BART Station Fremont Express services to be addressed in advance of others due to Warm Springs opening earlier Completion by mid-2015 (Warm Springs recommendation earlier) 35
36 Service Included in Study Light rail service Santa Clara/Alum Rock Rapid & Berryessa Connector corridor (not incl. 22) Milpitas/Berryessa Local Milpitas/Berryessa Express & Limited Stop Fremont Express 36
37 Fremont Express Services: Initial Findings Key question: Move to new stations, eliminate, or keep some? Consider ~500 boardings per day at non-bart stops in Fremont, higher ridership on
38 BTIP Timeline Summer 38 Fremont data collection First round of public participation Fall Alternatives development (Fremont first, followed by rest of study area) Winter/Early Spring Alternatives Assessment return for your input
Draft Supplemental Transportation Analysis Santa Clara - Alum Rock Transit Corridor APPENDIX A TRAFFIX Level of Service Calculation Sheets 2012 BRT 20
Draft Supplemental Transportation Analysis Santa Clara - Alum Rock Transit Corridor APPENDIX A TRAFFIX Level of Service Calculation Sheets 202 BRT 2030 BRT 2030 BRT Mitigation COMPARE Wed May 8 2:02: 20
More informationBUS RAPID TRAN SIT. Institute of Tra nsporta tion Engineers October 17, 2013
Institute of Tra nsporta tion Engineers October 17, 2013 Why is VTA d oing BRT? Building a transit network for today and future Fast, frequent core network Focus improvements in growing corridors Pursuing
More informationBART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010
BART Silicon Valley Berryessa Extension Project Community Update October 27, 2010 1 Agenda Welcome and Introductions Program and Project Background Project Status Project and Station Details Current and
More informationChapter 7. Transportation Capital Improvement Projects. Chapter 7
Chapter 7 Transportation Capital Improvement Projects Chapter 7 81 Chapter 7 Transportation Capital Improvement Projects Local Transportation Sales Tax Programs For over three decades, Santa Clara County
More informationSanta Clara Valley Transportation Authority 2013 PROGRESS REPORT
VTA looks to the future and is ready to keep Silicon Valley moving forward. Santa Clara Valley Transportation Authority 2013 PROGRESS REPORT nyone who has run a relay race knows the importance of making
More information3.15 SAFETY AND SECURITY
3.15 SAFETY AND SECURITY Introduction This section describes the environmental setting and potential effects of the alternatives analyzed in this EIR with regard to safety and security in the SantaClara-Alum
More informationState Avenue Corridor Bus Rapid Transit (BRT)
State Avenue Corridor Bus Rapid Transit (BRT) Moving Forward Incrementally April 2010 State Ave. BRT Update Bus Rapid Transit Overview State Ave. Alternatives Analysis Results What s Coming Up Right Away!
More informationCTfastrak Expansion. Stakeholder Meeting #4 Manchester Town Hall June 3, 2016
CTfastrak Expansion Stakeholder Meeting #4 Manchester Town Hall June 3, 2016 Today s Agenda Phase I Update 2016 Service Plan Implementation Schedule & Cost Update Phase II Services Timeline Market Analysis
More informationFuture of VTA Light Rail
Future of VTA Light Rail SPUR Presentation 11/12/2014 Light Rail System: Guadalupe & Almaden Guadalupe Opening: 1987-1991 19.6 miles 29 stations Almaden Opening: 1991 1.1 miles 2 stations Light Rail System:
More informationSERVICE DESIGN GUIDELINES
VTA TRANSIT SUSTAINABILITY POLICY: APPENDIX A SERVICE DESIGN GUIDELINES Adopted February 2007 COMMUNITYBUS LOCALBUS EXPRESSBUS BUSRAPIDTRANSIT LIGHTRAILTRANSIT STATIONAREAS S A N T A C L A R A Valley Transportation
More information5. OPPORTUNITIES AND NEXT STEPS
5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours
More informationSnelling Bus Rapid Transit. May 13, 2013 Technical Advisory Committee Meeting #1
Snelling Bus Rapid Transit May 13, 2013 Technical Advisory Committee Meeting #1 1 Today s meeting TAC Introductions Project Overview Arterial BRT Concept Background Snelling Corridor Plan, Funding & Schedule
More information2019 New Transit Service Plan
Agenda Item 7.2 2019 New Transit Service Plan Draft Proposal VTA Board of Directors January 2019 Background: Next Network Plan and Today s Plan Early 2016 Transit Choices report and the ridership-coverage
More informationSection 2 Project Description
Section 2 Project Description 2.1 INTRODUCTION The Santa Clara Valley Transportation Authority (VTA) is considering alternatives for improving direct transit service in the Santa Clara-Alum Rock Corridor
More informationI-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results. Public Meeting. Wulf Grote, Director Project Development Rick Pilgrim, Project Manager
I-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results Public Meeting Wulf Grote, Director Project Development Rick Pilgrim, Project Manager March 4 & 5, 2008 Today s Agenda Overview of Alternatives
More informationARTERIAL BRT OVERVIEW
ARTERIAL BRT OVERVIEW Key Question: Could arterial Bus Rapid Transit (BRT) routes improve near-term mobility in the northwest area until rail can be built? Key Findings: 6 arterial BRT routes have been
More informationDowntown Transit Connector. Making Transit Work for Rhode Island
Downtown Transit Connector Making Transit Work for Rhode Island 3.17.17 Project Evolution Transit 2020 (Stakeholders identify need for better transit) Providence Core Connector Study (Streetcar project
More informationPublic Meeting. June 15, :30 7:30 p.m.
Public Meeting June 15, 2017 5:30 7:30 p.m. Welcome 2015 Naval Station Norfolk Transit Extension Study 2015 Naval Station Norfolk Transit Extension Study 2017 Norfolk Westside Transit Study HRT and the
More informationDevelopment of a Mode Choice Model for Bus Rapid Transit in Santa Clara County, California
Development of a Mode Choice Model for Bus Rapid Transit in Santa Clara County, CA Editor's Note: An inadvertent error was made in the last issue that misidentified the authors of this paper on the cover
More informationWaco Rapid Transit Corridor (RTC) Feasibility Study
Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM
More informationSemi-Annual Report June Measure A Program
Semi-Annual Report June 2017 2000 Measure A Program 2000 Measure A Program Semi-Annual Report June 2017 Table of Contents TABLE OF CONTENTS Section Title Page 1 EXECUTIVE SUMMARY AND PROJECT COSTS A.
More informationMilpitas BART Station Transportation Impact Analysis, Hexagon Transportation Consultants, Inc., December 23, 2008.
4.2 TRANSPORTATION 4.2.1 INTRODUCTION This section includes an updated traffic analysis that entirely replaces the transportation section in the SEIR-1. This existing and future transportation conditions
More informationTRANSIT IDEA STRATEGIC INITIATIVE On BUS RAPID TRANSIT (BRT)
TRANSIT IDEA STRATEGIC INITIATIVE On BUS RAPID TRANSIT (BRT) The panel for the Transit IDEA program has endorsed a Bus Rapid Transit (BRT) strategic initiative and focus area as part of the Transit IDEA
More informationWhat IS BRT, Really? Not BRT and RNY
What IS BRT, Really? 2007 Winter TexITE Meeting Presented by Jeff Arndt, TTI Not BRT and RNY 1 What is Bus Rapid Transit? A flexible, rubber-tired from of rapid transit that combines stations, vehicles,
More informationMETRO Orange Line BRT American Boulevard Station Options
METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN
More informationComprehensive Operations Analysis. Proposed Service Operating Plan May 2007
Comprehensive Operations Analysis Proposed Service Operating Plan May 2007 1 1 COA Milestones and Products Policy Development October 2006 COA/TSP Core Principles Data Collection & Analysis August 2006
More informationColumbia Pike Transit Stations
Public Open House Arlington County Department of Environmental Services April 28, 2015 1 Meeting Purpose Review project goals Update on project status and scope of current work Address next steps and timeline
More informationWhere will. BRT run? BRT will serve 20 stations along the line, connecting to bus routes and serving major destinations. How often will service run?
Where will 32 65 87 223 Rosedale Transit Center 225 227 264 801 ROSEVILLE 65 Snelling & County Road B BRT run? Snelling & Roselawn FALCON HEIGHTS BRT will serve 20 stations along the line, connecting to
More informationMetro Transit Update. Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office. John Dillery, Senior Transit Planner
Metro Transit Update Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office John Dillery, Senior Transit Planner Metro Transit Service Development May 16, 2013 1 Transit Planning
More informationPreliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives
3.0 What preliminary alternatives are being evaluated? The alternatives for the East San Fernando Valley Transit Corridor project that were considered for screening include the No Build Alternative, Transportation
More informationPlanning for Tomorrow
1 Regional Growth Planning for Tomorrow City of Des Moines Transportation Master Plan Connect Downtown What did Des Moines residents have to say? 4 Non-rider survey feedback Is public transit important
More informationPoint A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017
Fulton County Board of Commissioners and Mayors Meeting December 14, 2017 Master Plan Overview Phase 1 Community Vision and Existing Transit Conditions Phase 2 Scenario Development Phase 3 Transit Master
More informationHDR Engineering. HART North / South. Tampa Bay Applications Group Meeting May 14, 2009
HDR Engineering HART North / South BRT Corridor PD&E Tampa Bay Applications Group Meeting May 14, 2009 1 Agenda Update on Project Development and Environment (PD&E) Study Project Overview System Branding
More informationTroost Corridor Transit Study
Troost Corridor Transit Study May 23, 2007 Kansas City Area Transportation Authority Agenda Welcome Troost Corridor Planning Study Public participation What is MAX? Survey of Troost Riders Proposed Transit
More informationTempe Streetcar. March 2, 2016
Tempe Streetcar March 2, 2016 Tempe Profile 40 sq. miles, highest density in state University Town, center of region Imposed growth boundaries (density increase) Mixed use growth/intensifying land use
More informationService Quality: Higher Ridership: Very Affordable: Image:
Over the past decade, much attention has been placed on the development of Bus Rapid Transit (BRT) systems. These systems provide rail-like service, but with buses, and are typically less expensive to
More information4.1 Land Use. SECTION CONTENTS Land Use Transit Transportation Technology
4 FUTURE CHANGES IN THE CORRIDOR Over the next 30 years, Santa Clara County will grow by roughly 637,000 residents and 303,500 jobs increases of 31 percent and 43 percent, respectively. 1 Changes in land
More informationEast Bay Bus Rapid Transit Project. Downtown Oakland to San Leandro International Blvd to East 14 th St
East Bay Bus Rapid Transit Project 1 AC Transit at a Glance EAST BAY AREA S LARGEST PUBLIC TRANSIT PROVIDER RIDERSHIP Daily (weekday) 178,851* Annual 54,987,132 Paratransit (daily) 1,994 ** * Includes
More informationAPPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY]
APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY] Jackson/Teton Integrated Transportation Plan 2015 Appendix I. Fixed-Guideway Transit Feasibility Jackson/Teton County Integrated Transportation Plan v2
More informationArterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014
Arterial Bus Rapid Transit System Policy Oversight Committee April 7, 2014 1 Meeting Agenda Welcome and Introductions A Line - Project Status Shelter and Pylon Development Arterial BRT Branding Update
More informationWelcome. Please Sign In
Welcome South Bay Bus Rapid Transit (BRT) Draft Environmental Impact Report (DEIR) Public Meeting Please Sign In Please comment in any of the following manners: 1. Submit a comment form 2. Provide verbal
More informationPublic Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development
Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation
More informationThursday, August 15, 2013 MINUTES
\ TRANSIT PLANNING & OPERATIONS COMMITTEE Thursday, August 15, 2013 MINUTES CALL TO ORDER The Regular Meeting of the Transit Planning and Operations (TP&O) Committee was called to order at 4:08 p.m. by
More informationBus Rapid Transit: Basic Design for Non-Transit Planners
Bus Rapid Transit: Basic Design for Non-Transit Planners Paul Bignardi, AICP - Principal Planner San Francisco Municipal Transportation Agency Graham Carey, PE Principal careybrt Consulting Peter Gabancho,
More informationPhysical construction of VTA s BART Silicon Valley Phase I Extension. BART Silicon Valley Update
BART Silicon Valley Update Station Construction Static Testing Dynamic Testing Integration Testing Safety Certification Passenger Service TEST TEST Complete landscaping, station interiors and exteriors
More informationHigh Speed Rail Conference
High Speed Rail Conference Denver, October 23, 2012 FAST START PROJECT FOR PENINSULA HIGH-SPEED RAIL Kern Jacobson InfraConsult LLC Objective Evaluate incremental approach to expedite high-speed rail to
More informationBrian Pessaro, AICP National Bus Rapid Transit Institute
Brian Pessaro, AICP National Bus Rapid Transit Institute Source: WCVB TV, Boston BRT is an enhanced bus system that operates on bus lanes or other transitways in order to combine the flexibility of buses
More informationAn Overview of Rapid Transit Typical Characteristics. Date April 30, 2009
An Overview of Rapid Transit Typical Characteristics Date April 30, 2009 Land Use and Transportation Is there a link? Streetcar Suburbs were the result of land developers creating streetcar lines in order
More informationEUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT
EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT (BRIEF) Table of Contents EUGENE-SPRINGFIELD, OREGON (USA)... 1 COUNTY CONTEXT AND SYSTEM DESCRIPTION... 1 SYSTEM OVERVIEW... 1 PLANNING
More informationWe Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network:
We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network: Richmond North of Oxford Street Richmond Row Dundas Street
More informationDraft Results and Open House
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi
More informationUS 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017
US 29 Bus Rapid Transit Planning Board Briefing February 16, 2017 Project Goals Improve the quality of transit service Improve mobility opportunities and choices Enhance quality of life Support master
More informationProject Scoping Open House Welcome
Scoping Meeting Project Scoping Open House Welcome Alternatives Analysis (AA) and Draft Environmental Impact Statement/Draft Environmental Impact Report (DEIS/DEIR) Project Purpose Purpose of the Project
More informationKendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study
Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What
More information1.0 Detailed Definition of Alternatives
1.0 Detailed Definition of Alternatives 1.1 Introduction This chapter provides supplemental information on the four alternatives, including both physical and operational characteristics (e.g. service plans)
More informationI-20 EAST TRANSIT INITIATIVE Tier 1 and Tier 2 Alternatives Screening Report EXECUTIVE SUMMARY
EXECUTIVE SUMMARY The purpose of this report is to document the results of the Tier 1 and Tier 2 Screening of alternatives for the I-20 East Transit Initiative. The two-tier screening process presented
More informationCHAPTER 3.0: ALTERNATIVES
CHAPTER 3.0: ALTERNATIVES 3.1 INTRODUCTION Three alternatives are evaluated in this Final Environmental Impact Statement/Environmental Impact Report (EIS/EIR) for the Silicon Valley Rapid Transit Corridor
More informationA Transit Plan for the Future. Draft Network Plan
A Transit Plan for the Future Draft Network Plan Project Overview and Status Completed Market Analysis and Service Evaluation. Developed Plan Framework and Guiding Principles. Developed a draft Five Year
More information6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION
June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments
More informationDevelopment and Overview of the NY 5 Bus Rapid Transit Corridor. New York State MPO Conference June 5, 2009
Development and Overview of the NY 5 Bus Rapid Transit Corridor New York State MPO Conference June 5, 2009 Bus Rapid Transit (BRT) n Enhancement of ordinary bus route to offer high quality transit at low
More informationBROWARD BOULEVARD CORRIDOR TRANSIT STUDY
BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,
More informationDETAILED DEFINITION OF ALTERNATIVES. July 2014 FINAL
DETAILED DEFINITION OF ALTERNATIVES July 2014 Table of Contents 1.0 Introduction... 1 1.1 Detailed Mode Alternatives... 1 1.2 Detailed Alignment Alternatives... 1 1.3 Key Physical and Service Elements...
More informationCOMMITTEE FOR TRANSPORTATION MOBILITY & ACCESSIBILITY WORKSHOP AGENDA
COMMITTEE FOR TRANSPORTATION MOBILITY & ACCESSIBILITY Wednesday, February 1, 2017 10:00 AM PLEASE NOTE MEETING DATE VTA Conference Room B-106 3331 North First Street San Jose, CA WORKSHOP AGENDA COMMITTEE
More informationSAN FRANCISCO TO SAN JOSE PROJECT UPDATE
SAN FRANCISCO TO SAN JOSE PROJECT UPDATE San Francisco County Transportation Authority Tuesday, April 25, 2017 Ben Tripousis, Northern California Regional Director HIGH-SPEED RAIL: Connecting California
More informationArterial BRT Quarterly Update
Arterial BRT Quarterly Update Transportation Committee June 24, 2013 Katie Roth, AICP Senior Planner, BRT/Small Starts 612-349-7772 Charles Carlson Senior Manager, BRT/Small Starts 612-349-7639 1 Arterial
More informationEnd-of-Year Performance Report FY Community Relations Committee December 5, 2018
End-of-Year Performance Report FY 2018 Community Relations Committee December 5, 2018 Annual Summary Shuttles Ridership All Modes Performance Statistics Highlights All Modes Initiatives 2 Bus Ridership
More informationFREQUENTLY ASKED QUESTIONS
FREQUENTLY ASKED QUESTIONS 2018 What is the More MARTA Atlanta program? The More MARTA Atlanta program is a collaborative partnership between MARTA and the City of Atlanta to develop and implement a program
More informationRecommendation for 2017 PSRC Funding Transportation Policy Board - June 8, 2017
Recommendation for 2017 PSRC Funding Transportation Policy Board - June 8, 2017 Background PSRC s 2017 funding: Rural Town Centers and Corridor program Regional FTA competition May - Board released projects
More informationLeveraging Land Use Changes through Transportation Funding
Leveraging Land Use Changes through Transportation Funding Railvolution 2005 September 10, 2005 James Corless Senior Planner What is the MTC region? 9 7 101 26 San Francisco Bay Area counties Million people;
More informationBART s Transbay Core Capacity Project
BART s Transbay Core Capacity Project Duncan Watry, Principal Planner Bay Area Rapid Transit Oakland, CA dwatry@bart.gov Donald Emerson, Principal Consultant WSP Parsons Brinckerhoff San Francisco, CA
More informationI-225 Rail Line. 13 th Avenue Station Information Meeting. July 25, 2013
I-225 Rail Line 13 th Avenue Station Information Meeting July 25, 2013 FasTracks and I-225 Rail Line Update Chuck Culig I-225 Rail Line Project Manager 2 The RTD FasTracks Plan 122 miles of rail 18 miles
More informationNortheast Corridor Alternatives Analysis. Public Involvement Round 2 Input on Alternatives for Further Study
Northeast Corridor Alternatives Analysis Public Involvement Round 2 Input on Alternatives for Further Study Feb. 7-9, 2012 Agenda Review project background Progress summary Recommended alternatives for
More informationmo'c Physics Applied
Energy Study SANTA CLARA/ALUM ROC K CORRIDOR Santa Clara Valley Transportation Authority June 30, 2008 [revised] mo'c Physics Applied 228 Hamilton Avenue, Suite 300 Palo Alto, California 94301 (650) 968-5793
More informationProgram Overview. February 2018
Program Overview February 2018 Nashville is growing 2 and traffic is getting worse 5 Nashville spoke; we listened Transit Improvement Program Frequent Transit Bus AccessRide and Mobility on Demand Neighborhood
More informationFINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit
Sound Transit Long-Range Plan Update Issue Paper S.1: Tacoma Link Integration with Central Link Prepared for: Sound Transit Prepared by: Quade & Douglas, Inc. FINAL March 2005 Foreword This issue paper
More informationCHAPTER 2.0: RECOMMENDED PROJECT
CHAPTER 2.0: RECOMMENDED PROJECT 2.1 BART EXTENSION ALTERNATIVE The BART Extension Alternative (BART Alternative) consists of a BART heavy rail transit line partially constructed on the former UPRR right-of-way
More informationI-405 and SR 522/NE 145th Bus Rapid Transit. Elected Leadership Groups Meeting November 30, 2018
I-405 and SR 522/NE 145th Bus Rapid Transit Elected Leadership Groups Meeting November 30, 2018 Agenda Welcome and Introductions Public Comment BRT Connection in Bothell Common Elements: Bus base, Station
More informationWAKE TRANSIT PLAN Summer 2018
WAKE TRANSIT PLAN Summer 2018 Planning for growth WAKE COUNTY s population already exceeds ONE MILLION and grows by more than 60 people a day. That s 23,000 people a year or basically another Morrisville.
More informationHelp shape your community investment in Wake Transit. Fiscal Year 2019 Draft Work Plan Summary
Help shape your community investment in Wake Transit Fiscal Year 2019 Draft Work Plan Summary Wake County, growth and transit The Triangle is one of the fastest-growing regions in the nation. Wake County
More informationTransit on the New NY Bridge
Transit on the New NY Bridge TZB Cross Section North bridge incorporating 12ft shared use path and space for future bus lane South bridge with space for a future bus lane Gap between the two decks for
More informationEast San Fernando Valley Transit Corridor. Community Meetings April/May, 2012
East San Fernando Valley Transit Corridor Community Meetings April/May, 2012 Meeting Format Sign-In/Open-House 6:00 P.M. to 6:30 P.M. Welcome/Presentation 6:30 P.M. to 7 P.M. Open-House 7:00 P.M. to 8:00
More information350 W. TRIMBLE 120K-160K SF AVAILABLE
A UNIQUE MIXED-USE CAMPUS HIGHLY FLEXIBLE MARKET-READY UNDERWAY 350 W. TRIMBLE 120K-160K SF AVAILABLE UP TO 1M SF OF EXPANSION FUTURE 100K SF OF RETAIL SPACE NORTH TOWN ADVANTAGE 350 WEST TRIMBLE: A BUILDING
More informationDenver Metro Association of Realtors
Denver Metro Association of Realtors North Metro Rail Line October 2, 2014 1 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new Park-n-Rides;
More informationMetropolitan Council Budget Overview SFY
Metropolitan Council Budget Overview SFY 2016-2017 H T t ti C itt House Transportation Committee February 4, 2015 Transit connects us to the places that matter Transportation Needs Grow as the Region Grows
More informationSan Francisco Mobility, Access & Pricing Study
San Francisco Mobility, Access & Pricing Study SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY Summer Workshops 2010 Downtown Growth Projections + 24,000 hsg units + 107,000 jobs +184,000 auto trips +88,000
More informationRail alignment and benefits (rab) study
Rail alignment and benefits (rab) study previously known as railyard alternatives & i-280 boulevard study May 22, 2018 CONNECTING CALIFORNIA 4,300 lane miles + 115 Airport gates would be needed to create
More informationVan Ness Transit Corridor Improvement Project. Engineering, Maintenance and Safety Committee March 25, 2015
Van Ness Transit Corridor Improvement Project Engineering, Maintenance and Safety Committee March 25, 2015 Project Need 16,000 daily passenger boardings within the project corridor Average bus speed 8
More informationBus Rapid Transit in Asia: From Quantity to Quality. What is a Bus Rapid Transit system?
Bus Rapid Transit in Asia: From Quantity to Quality Dario Hidalgo, PhD Senior Transport Engineer EMBARQ, The WRI Center for Sustainable Transport TRB Annual Meeting Washington DC, January 2009 What is
More informationSpeaker Information Tweet about this presentation #TransitGIS
Making the Case for Transit: the Transit Competitiveness Index Title William E. Walter, GISP Speaker Information Tweet about this presentation #TransitGIS Understanding Conditions in Each Travel Market
More informationDraft Results and Recommendations
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Recommendations Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System
More informationGreater Cleveland Regional Transit Authority. Joe Calabrese CEO/General Manager
Greater Cleveland Regional Transit Authority Joe Calabrese CEO/General Manager Greater Cleveland RTA Overview Service Area Population of 1.5 million Customers Served 200,000 on a typical weekday 1.6 million
More informationInformal Business Discussion Minutes Tuesday, May 3, :00 PM 1. Transportation
Official Informal Business Discussion Minutes Tuesday, May 3, 2016 3:00 PM Present: Charlotte J. Nash, Jace Brooks, Lynette Howard, Tommy Hunter, John Heard 1. Transportation Comprehensive Transportation
More informationWEST CONTRA COSTA HIGH-CAPACITY TRANSIT STUDY TASK NUMBER 13.2: REFINED PRELIMINARY SCREENING COST ESTIMATE
TASK NUMBER 13.2: REFINED PRELIMINARY SCREENING COST ESTIMATE PRELIMINARY ESTIMATE OF PROBABLE CONSTRUCTION COST (AN OPINION OF PROBABLE CONSTRUCTION COST) BASED ON DRAFT TM #11 ALTERNATIVE REFINEMENT
More informationDevelop ground transportation improvements to make the Airport a multi-modal regional
Project Overview TRANSPORTATION IMPROVEMENTS WHAT ARE THE PROJECT GOALS? Transportation transportation hub. Develop ground transportation improvements to make the Airport a multi-modal regional Land Use
More informationTECHNICAL ADVISORY COMMITTEE **PLEASE NOTE MEETING DAY, TIME AND LOCATION** WORKSHOP AGENDA
TECHNICAL ADVISORY COMMITTEE Wednesday, January 11, 2017 1:30 PM **PLEASE NOTE MEETING DAY, TIME AND LOCATION** CALL TO ORDER 1. ROLL CALL 2. PUBLIC PRESENTATIONS: VTA Auditorium 3331 North First Street
More informationEMU Procurement Seats/Standees/Bikes/Bathroom
EMU Procurement Seats/Standees/Bikes/Bathroom LPMG May 28, 2015 Purpose Seats / standees / bikes / bathroom balance Develop framework for Draft EMU RFP Feedback on car configuration and range of increased
More informationExecutive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009.
Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009 Background As the Treasure Valley continues to grow, high-quality transportation connections
More informationNeeds and Community Characteristics
Needs and Community Characteristics Anticipate Population and Job Growth in the City Strongest density of population and jobs in Ann Arbor are within the Study Area Population expected to grow 8.4% by
More informationAMERICA. rides the BUS
AMERICA rides the BUS This brochure provides information on the positive development and direction of the bus industry today, as well as on the broad-based need the bus industry fills in American communities.
More informationDraft Station Plan. Tuesday, November 17th
Draft Station Plan Comments on this draft plan can be submitted to brtprojects@metrotransit.org. The public is also invited to attend upcoming open houses to provide input and learn more about the C Line
More information