COMMITTEE FOR TRANSPORTATION MOBILITY & ACCESSIBILITY WORKSHOP AGENDA

Size: px
Start display at page:

Download "COMMITTEE FOR TRANSPORTATION MOBILITY & ACCESSIBILITY WORKSHOP AGENDA"

Transcription

1 COMMITTEE FOR TRANSPORTATION MOBILITY & ACCESSIBILITY Wednesday, February 1, :00 AM PLEASE NOTE MEETING DATE VTA Conference Room B North First Street San Jose, CA WORKSHOP AGENDA COMMITTEE MISSION: The VTA Committee for Transportation Mobility and Accessibility provides guidance and perspective to the Board of Directors on VTA transit and transportation accessibility matters to help ensure complete access to all users in Santa Clara County, doing so by facilitating dialogue with, representing and advocating the needs of the disabled and senior communities. CALL TO ORDER 1. ROLL CALL 2. INTRODUCTION OF AUDIENCE MEMBERS 3. PUBLIC PRESENTATIONS This portion of the agenda is reserved for persons desiring to address the Committee on any matter not on the agenda, within the Committee s jurisdiction. Speakers are limited to 2 minutes. The law does not permit Committee action or extended discussion on any item not on the agenda except under special circumstances. If Committee action is requested, the matter can be placed on a subsequent agenda. All statements that require a response will be referred to staff for reply in writing. 4. INFORMATION ITEM -Receive information on the recommended contractor for ACCESS Paratransit Services. 5. INFORMATION ITEM -Receive and review the Next Network Paratransit Service Area Analysis North First Street San Jose, CA Administration Customer Service

2 Santa Clara Valley Transportation Authority Committee for Transportation Mobility & Accessibility February 1, DISCUSSION ITEM - Discuss Paratransit Eligibility. (Follow up from the January 12, 2017, CTMA meeting) (Verbal Report) 7. Receive Committee Staff Report. (Verbal Report) (Vogel) VTA s priorities for ANNOUNCEMENTS 9. ADJOURN In accordance with the Americans with Disabilities Act (ADA) and Title VI of the Civil Rights Act of 1964, VTA will make reasonable arrangements to ensure meaningful access to its meetings for persons who have disabilities and for persons with limited English proficiency who need translation and interpretation services. Individuals requiring ADA accommodations should notify the Board Secretary s Office at least 48-hours prior to the meeting. Individuals requiring language assistance should notify the Board Secretary s Office at least 72-hours prior to the meeting. The Board Secretary may be contacted at (408) or board.secretary@vta.org or (408) (TTY only). VTA s home page is or visit us on (408) : 中文 / Español / 日本語 / Çѱ¹¾î / tiếng Việt / Tagalog. All reports for items on the open meeting agenda are available for review in the Board Secretary s Office, 3331 North First Street, San Jose, California, (408) at least 72- hours prior to the meeting. This information is available on VTA s website at and also at the meeting. Page 2

3 Revised Item #4 Date: January 30, 2017 Current Meeting: February 1, 2017 Board Meeting: N/A BOARD MEMORANDUM TO: THROUGH: FROM: SUBJECT: Santa Clara Valley Transportation Authority Committee for Transportation Mobility & Accessibility General Manager, Nuria I. Fernandez Chief Operating Officer, Inez Evans Recommended Contract Award for ACCESS Paratransit Services FOR INFORMATION ONLY BACKGROUND: In accordance with federal regulations, the Santa Clara Valley Transportation Authority (VTA) provides Americans with Disabilities Act (ADA) paratransit services to persons who are unable to independently access or navigate VTA s bus or light rail system due to a physical, visual, or cognitive disability in accordance with ADA. VTA s responsibility to provide ADA paratransit service has been outsourced since On June 24, 2016, VTA s Board of Directors approved a recommendation by VTA s Auditor General to terminate the contract for convenience with its long standing paratransit provider. This action required staff to release a request for proposal for paratransit service. On September 01, 2016, the Paratransit Scope of Work (SOW) was approved by the VTA Board of Directors. On September 2, 2016 a Request for Proposals (RFP) that included the Board approved SOW, was released for VTA ACCESS Paratransit Services. The RFP was developed following community workshops and emphasized providing safe, reliable and high quality services. DISCUSSION: VTA received five proposals from the following firms: Chariot First Transit MV Transportation Ride Right 3331 North First Street San Jose, CA Administration Customer Service

4 Transdev The RFP review board consisted of five members from VTA s Regional Transportation Service department, technology, finance, and operations administration. Proposals were evaluated on the following criteria by each member of the review board: Qualifications of the Firm...25 points Staffing and Project Organization...20 points Work Plan/Project Understanding..35 points Use of Existing Operators and Staff...10 points Cost & Price..30 points The review board evaluated proposals and short-listed two firms deemed most responsive, responsible, and competitive 1) MV Transportation and 2) First Transit. These firms were invited to interviews held December 1, The interviews provided an opportunity for the review board to better understand the firms qualifications, staffing plan and work plan. Based on the combination of the written proposals and oral interviews, the review board requested additional clarifying information from the short-listed firms, which VTA received by the December 22, 2016 due date. The review board conducted reference checks on both firms in January. Once the evaluation process concluded, MV Transportation was deemed the highest ranked firm. MV Transportation is one the largest paratransit providers in the nation and operates locally in San Jose. The company was originally founded in the Bay Area and is now headquartered in Dallas, Texas. MV has significant local knowledge and experience having provided the paratransit service drivers since MV has been VTA s interim service provider for all Paratransit services since November 3, MV has experience providing services where ondemand providers (ODP) are utilized. Their references included strong corporate and technology support which is needed for our current transition. MV s proposal and interview demonstrated the strongest project understanding, staffing plan and Trapeze experience. MV s work plan included important functions for finance, human resources, information technology, and customer service in its proposal. Next Steps: The VTA Board of Directors is scheduled to consider the contract award at their February 2, 2017 meeting. The proposed contract with MV is for four years in the amount of $79,875,047 to provide VTA s ACCESS Paratransit Services. The contract will commence July 1, 2017 and end June 30, Prepared By: Aaron Vogel Memo No Page 2 of 2

5 Date: January 27, 2017 Current Meeting: February 1, 2017 Board Meeting: N/A BOARD MEMORANDUM TO: THROUGH: FROM: SUBJECT: Santa Clara Valley Transportation Authority Committee for Transportation Mobility & Accessibility General Manager, Nuria I. Fernandez Chief Operating Officer, Inez Evans Next Network Paratransit Service Area Analysis FOR INFORMATION ONLY Introduction - VTA s Draft Transit Service Plan: Under the Santa Clara Valley Transportation Authority s (VTA s) Transit Ridership Improvement Program (TRIP) initiated in 2015, VTA began a two-year planning and outreach effort to increase ridership, improve efficiency and control cost through a redesigned transit network. This project, known as the Next Network encompasses the implementation of a new transit service plan to occur concurrent with the opening of BART service to the Milpitas and Berryessa stations. The project aims to engage the community in developing a new bus and light rail transit network reflecting our transit needs and values, increasing ridership, improving farebox recovery, and integrating our new BART service into the transit network. The project's major milestones include: - Late 2015: Independent assessment of VTA s service and market - April 2016: Assessment results reports to VTA Board - Summer 2016: Community outreach Phase 1 - November 2016: VTA Board decision on ridership/coverage allocation (85/15) - January 2017: Draft transit service plan released - January-February 2017: Community outreach Phase 2 - April 2017: Final transit service plan for VTA Board approval - Fall 2017: Service begins (concurrent with the opening of BART Phase 1) The first phase of community outreach was designed to acquaint the community and stakeholders with the results of the independent assessment and outline potential scenarios. Following this public process, the VTA Board of Directors held a November 2016 workshop to discuss the community s input and give staff direction on the ridership/coverage balance for the 3331 North First Street San Jose, CA Administration Customer Service

6 draft transit service plan. At the conclusion of the meeting, the Board voted to direct staff to develop a draft transit service plan that reflects an 85/15 split - that is, a network that allocates 85% of resources to ridership-oriented service and 15% of resources to coverage-oriented service. This direction to pursue a network designed to achieve higher ridership represents a shift from today s network of 70% ridership-oriented service and 30% coverage-oriented service. This change, if implemented, will have the effect of increasing frequency in high ridership transitsupportive corridors and areas while decreasing service in areas with low transit demand. It will promote a design philosophy that embraces a grid of frequent routes with more midday and weekend service. VTA staff has developed a draft transit service plan that reflects the substantial community input received over the summer as well as the VTA Board s guidance on the ridership/coverage balance given at the November 18 Board Workshop. The Next Network draft transit service plan was reviewed by the CTMA at their January 12, 2017 meeting. The draft plan features a redesigned fixed-route transit network that would impact VTA s federal requirements regarding complementary paratransit service. Some network changes would increase VTA s paratransit service obligations, such as new service in previously-unserved geographic areas or an expansion of the hours of service availability in evenings and on weekends. Conversely, some network changes would reduce VTA s paratransit obligations, such as geographic areas that would lose fixed route service entirely. During presentation of the draft transit service plan, the VTA Board has indicated a desire to ensure that the transit service changes do not negatively impact paratransit clients. The options presented below are to determine how to implement the VTA Board s direction. BACKGROUND: Per the Americans with Disabilities Act (ADA), VTA is required to provide paratransit service to areas within ¾ of a mile of a fixed-route transit service during the hours when the transit route is in operation. VTA s current paratransit policy (adopted in 2009) extends the service area a mile beyond the federal minimum such that trips that start and end within 1 ¾ miles of a fixed-route service are eligible for paratransit service. Trips that occur within the ADA-required boundary (¾ mile) have a $4 fare while trips in the extended service area have a $16 fare. Under VTA s current paratransit policy, some paratransit clients would be impacted-in terms of access to paratransit service or the fare paid-by the transit service changes proposed by VTA s Draft Transit Service Plan. The changes are also expected to result in increased costs to operate paratransit service. VTA places special consideration on the transportation needs of disabled residents and is evaluating modifications to the current paratransit policy that would reduce the impacts to paratransit users caused by transit service changes. Since the paratransit service area is defined by the breadth (location and time of operations) of the transit network, the discontinuance or reduction of some transit routes-as is proposed in the Next Network transit redesign-would mean that some current paratransit clients trips would no longer be contained within the paratransit service area or that some clients fares would shift from $4 to $16 under current VTA policy. If fares increase in the future, there will be a Page 2 of 6

7 comparable change to the paratransit fares quoted here. Changes to the transit service plan do not impact the ability of a person to become eligible for paratransit services. Paratransit-eligible individuals whose residences or destinations are outside the service area remain eligible to use paratransit service, provided that they are able to arrange transportation into the paratransit service area. While some paratransit clients would be negatively impacted by the transit service change under the current paratransit policy, others would receive improved service. The proposed expansions in the hours of operation on some transit routes and increase in transit service levels on weekends would extend the hours and days in which paratransit service is available for some clients. This expanded access to paratransit service is expected to result in an overall increased number of paratransit trips, which would result in higher costs to VTA to provide paratransit service. VTA projects about 4% or 21,110 more annual client trips will be taken by paratransit due to the bus and rail improvements. These trips could, depending on the option selected, impact VTA s Operations Budget by $865,510 annually. DISCUSSION: The following analysis projects the impacts for current clients as well as the VTA financial impacts. This analysis assumes client travel patterns do not change. Fremont Paratransit Clients VTA s extension of BART to Santa Clara County and proposed discontinuance of transit routes 120, 140, 180 and 181, that serve the Fremont BART Station, will reduces VTA s need of providing paratransit service in Alameda County. Paratransit users in southern Alameda County would retain access to paratransit service through East Bay Paratransit, which is jointly funded by AC Transit and BART. Paratransit trips between Alameda and Santa Clara Counties would require a coordinated transfer from East Bay Paratransit to ACCESS Paratransit vehicles likely at the Warm Springs or Milpitas BART Stations. A total of 2,853 annual trips made by 371 clients are currently provided by Access Paratransit to Fremont. Of these trips, about 43% are to the Fremont BART Station. For these passengers traveling on BART, they can now access either the Berryessa or Milpitas Stations instead of travelling all the way to Fremont. Page 3 of 6

8 Santa Clara County Paratransit Impacts and Options The following chart shows the current number of clients and paratransit trips both for the existing service and the new Next Network transit service plan. It also depicts how many of the clients and trips are within the ADA required service area of ¾ mile and how many are in the extended service area. Existing Next Network Inside of 3/4-mile ($4) Extended Service Area ($16) Outside of Extended Service Area Outside of Extended & Not Fremont Trips 527,595 2,549 NA NA Number of clients 7, NA NA Trips 518,030 6,486 5,633 2,780 Number of clients 7, Currently each client in the ADA service area averages 35 round trips annually or about three per a month. The average paratransit client trip costs VTA $45. Ten percent of the cost is covered by paratransit client fares. The remaining balance is roughly: local funds (70%), federal funds (15%) and state funds (5%). The entire paratransit program costs VTA about $23.9 million annually. Policy Considerations Option 1: Continue existing paratransit policy so that paratransit service area is defined by the extent (hours, area) of the fixed-route transit network, with $4 charged for a regular-area fare and $16 charged for the extended-area fare. This option would continue to exceed ADA requirements by including the extended service area at the $16 fare. Under an 85/15 split and the proposed discontinuance of some routes in the Draft Transit Service Plan, 95 current paratransit clients accounting for 2,780 annual trips would no longer be within any paratransit service area. These clients average 29 trips each annually or about one round trip per month. 222 clients, accounting for 3,937 annual trips would shift from the regular fare area to the extended fare area. This would result in $47,244 in additional fares being collected by VTA assuming the same numbers are taken at the increased fare and clients do not arrange transportation within the paratransit service area. Page 4 of 6

9 The estimated overall financial impact of Option 1 for one year is shown below: Projected usage increase due to extended hours $865, clients no longer in service area (net decrease after fares) ($80,620) Additional fare revenue collected from 222 clients ($47,244) Net change in one year operating cost $737,646 The estimated financial impact of Option 1 for three years is shown below with the 4% escalation for client ridership increases and software cost inflation per year: Option 1 Year 1 Year 2 Year 3 Cumulative total Change in operating cost $737,646 $772,266 $808,272 $2,318,184 (additional) Option 2: This option continues the current policy identified in Option 1 and grandfathers paratransit service for the 95 paratransit clients whose trips would fall outside the paratransit service area under the Draft Transit Service Plan. This option would further maintain those 95 clients at their current fare for one year. This option exceeds ADA requirements. Since the grandfathering would last for one year, no cost savings due to a decrease in client trips would be recognized during that period. Modifying the paratransit management software to accommodate grandfathering clients is expected to result in a reoccurring cost of $70,000 to VTA. Projected usage increase due to extended hours $865,510 Additional fare revenue collected from 222 clients ($47,244) Software upgrade $70,000 Net change in one year operating cost $888,266 The estimated financial impact of Option 2 if continued for three years is shown below with the 4% escalation for client ridership increases and software cost inflation per year: Option 2 Year 1 Year 2 Year 3 Cumulative total Change in operating cost $888,266 $925,686 $964,604 $2,778,556 (additional) Option 3: This option takes what is covered in Option 2 and further grandfathers the existing paratransit clients that would otherwise move from the regular fare area to the extended service area (a total of 222 clients) and maintains them at their current fare of $4 per trip. This results in 222 clients paying $4 and 225 clients paying the $16 fare within the Extended Service area. This option exceeds ADA requirements. Since the grandfathering would last for one year, no cost savings due to a decrease in client Page 5 of 6

10 trips would be recognized during that period. Modifying the paratransit management software to accommodate grandfathering clients is expected to result in a reoccurring cost of $90,000 to VTA for additional clients from option 2. Projected usage increase due to extended hours $865,510 Software upgrade $90,000 Net change in one year operating cost $955,510 The estimated financial impact of Option 3 if continued for three years is shown below with the 4% escalation for client ridership increases and software cost inflation per year: Option 3 Year 1 Year 2 Year 3 Cumulative total Change in operating cost $955,510 $993,730 $1,033,480 $2,982,720 (additional) Summary of Options Net Increase One Year Three Years* Option 1: Continue Existing Policy $737,646 $2,318,184 Option 2: Grandfather Clients that fall outside of any service area $888,266 $2,778,556 Option 3: Grandfather Clients that fall outside of any service area & those impacted by paying the Extended Service surcharge $955,510 $2,982,720 * 4% escalation per year Next Steps: This item will be presented for review at the Committee for Transportation Mobility and Accessibility (CTMA) on February 1, 2017 and March 09, 2017 for CTMA recommendation to the Board. This item will be heard by Board Standing Committees with a final approval by the Board of Directors. Prepared By: Aaron Vogel Memo No Page 6 of 6

2019 New Transit Service Plan

2019 New Transit Service Plan Agenda Item 7.2 2019 New Transit Service Plan Draft Proposal VTA Board of Directors January 2019 Background: Next Network Plan and Today s Plan Early 2016 Transit Choices report and the ridership-coverage

More information

1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS

1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS 1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS The Transit Committee recommends the adoption of the recommendations contained in the

More information

COMMUNITY REPORT FISCAL YEAR We are making progress, are you on board? GOLD COAST TRANSIT DISTRICT

COMMUNITY REPORT FISCAL YEAR We are making progress, are you on board? GOLD COAST TRANSIT DISTRICT FISCAL YEAR 178 GOLD COAST TRANSIT DISTRICT COMMUNITY REPORT We are making progress, are you on board? OJAI OXNARD PORT HUENEME VENTURA COUNTY OF VENTURA GENERAL MANAGER S MESSAGE STEVEN P. BROWN DEAR

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Peninsula Corridor Electrification Project Cost / Schedule Update

Peninsula Corridor Electrification Project Cost / Schedule Update Peninsula Corridor Electrification Project Cost / Schedule Update LPMG Meeting November 20, 2014 Context Caltrain/high-speed rail blended system - Primarily 2 track system - Minimize impacts - Shared system

More information

RON ROBERTS SUPERVISOR, FOURTH DISTRICT SAN DIEGO COUNTY BOARD OF SUPERVISORS

RON ROBERTS SUPERVISOR, FOURTH DISTRICT SAN DIEGO COUNTY BOARD OF SUPERVISORS DATE: June 14, 2005 RON ROBERTS SUPERVISOR, FOURTH DISTRICT SAN DIEGO COUNTY BOARD OF SUPERVISORS AGENDA ITEM TO: SUBJECT: Board of Supervisors SUMMARY: Overview Today s action will direct a letter of

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

Improving Accessibility of Regional Bus Stops and Pathways

Improving Accessibility of Regional Bus Stops and Pathways Customer Service and Operations Committee Board Information Item III-A March 13, 2014 Improving Accessibility of Regional Bus Stops and Pathways Page 3 of 17 Washington Metropolitan Area Transit Authority

More information

BART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010

BART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010 BART Silicon Valley Berryessa Extension Project Community Update October 27, 2010 1 Agenda Welcome and Introductions Program and Project Background Project Status Project and Station Details Current and

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) APPLICATION

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) APPLICATION BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Great Oaks Water Company (U-162-W for an Order establishing its authorized cost of capital for the period from July 1, 2019

More information

Board of Directors authorization is required for all goods and services contracts obligating TriMet to pay in excess of $500,000.

Board of Directors authorization is required for all goods and services contracts obligating TriMet to pay in excess of $500,000. Date: April 11, 2012 To: From: Board of Directors Neil McFarlane Subject: RESOLUTION 12-04-30 OF THE TRI-COUNTY METROPOLITAN TRANSPORTATION DISTRICT OF OREGON (TRIMET) AUTHORIZING A CONTRACT WITH SIEMENS

More information

Request for Proposal for Trolley Security Services

Request for Proposal for Trolley Security Services Request for Proposal for Trolley Security Services April 6, 2018 Trolley Security Support Services The Loop Trolley Company The Loop Trolley Company (LTC) is requesting proposals for armed on-board security

More information

Central Transportation Paratransit Policies

Central Transportation Paratransit Policies Updated: 8/22/18 POINT PLUS Central Transportation Paratransit Policies Service Description Central Transportation offers a Paratransit service program to individuals with qualifying disabilities. Paratransit

More information

Greater Cleveland Regional Transit Authority

Greater Cleveland Regional Transit Authority Greater Cleveland Regional Transit Authority Summary of Proposed Award Vanpool Program Presented to: Operations Committee August 2, 2016 What is a Vanpool? A vanpool is a group of people (larger than 5)

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

US 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017

US 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017 US 29 Bus Rapid Transit Planning Board Briefing February 16, 2017 Project Goals Improve the quality of transit service Improve mobility opportunities and choices Enhance quality of life Support master

More information

CITY OF LOS ANGELES DEPARTMENT OF AIRPORTS

CITY OF LOS ANGELES DEPARTMENT OF AIRPORTS CITY OF LOS ANGELES DEPARTMENT OF AIRPORTS COMPRESSED NATURAL GAS 35-FOOT TRANSIT BUSES CONTRACT NUMBER ML09032 FINAL REPORT APRIL 2015 SUBMITTED BY: LOS ANGELES WORLD AIRPORTS MAINTENANCE DIVISION Prepared

More information

Too Good to Throw Away Implementation Strategy

Too Good to Throw Away Implementation Strategy Too Good to Throw Away Implementation Strategy Council Briefing by Sanitation Services October 4, 2006 Purpose of Briefing Summarize preparations for Too Good To Throw Away recycling services FY07 Recommend

More information

Office of Transportation Bureau of Traffic Management Downtown Parking Meter District Rate Report

Office of Transportation Bureau of Traffic Management Downtown Parking Meter District Rate Report Office of Transportation Bureau of Traffic Management 1997 Downtown Parking Meter District Rate Report Introduction The City operates approximately 5,600 parking meters in the core area of downtown. 1

More information

MOTION NO. M Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses

MOTION NO. M Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses MOTION NO. M2018-161 Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee PROPOSED ACTION

More information

Draft Results and Recommendations

Draft Results and Recommendations Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Recommendations Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System

More information

STAFF REPORT ACTION REQUIRED

STAFF REPORT ACTION REQUIRED STAFF REPORT ACTION REQUIRED Procurement Authorization Amendment Purchase of 18 Forty Foot Low Floor Clean Diesel City Buses Date: July 29, 215 To: From: TTC Board Chief Executive Officer Summary This

More information

APPROVE VANPOOL VEHICLE SUPPLIER BENCH CONTRACTS

APPROVE VANPOOL VEHICLE SUPPLIER BENCH CONTRACTS One Gateway Plaza Lo s Angeles, CA 90012-2952 2 13.9 2 2.200 0 Tel metro. net 55 REGULAR BOARD MEETING May 23,2013 SUBJECT: ACTION: METRO VANPOOL PROGRAM APPROVE VANPOOL VEHICLE SUPPLIER BENCH CONTRACTS

More information

P. SUMMARY: The Southeastern Power Administration (SEPA) establishes Rate Schedules JW-

P. SUMMARY: The Southeastern Power Administration (SEPA) establishes Rate Schedules JW- This document is scheduled to be published in the Federal Register on 08/29/2016 and available online at http://federalregister.gov/a/2016-20620, and on FDsys.gov 6450-01-P DEPARTMENT OF ENERGY Southeastern

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION

More information

5. OPPORTUNITIES AND NEXT STEPS

5. OPPORTUNITIES AND NEXT STEPS 5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours

More information

Vehicle Replacement Policy - Toronto Police Service

Vehicle Replacement Policy - Toronto Police Service STAFF REPORT June 21, 2000 To: From: Subject: Policy and Finance Committee Chairman, Toronto Police Services Board and City Auditor Vehicle Replacement Policy - Toronto Police Service Purpose: The purpose

More information

The Commonwealth of Massachusetts

The Commonwealth of Massachusetts The Commonwealth of Massachusetts DEPARTMENT OF PUBLIC UTILITIES D.P.U. 16-64-H November 6, 2017 Investigation of the Department of Public Utilities, on its own Motion, Commencing a Rulemaking pursuant

More information

CEDAR AVENUE TRANSITWAY Implementation Plan Update

CEDAR AVENUE TRANSITWAY Implementation Plan Update CEDAR AVENUE TRANSITWAY Implementation Plan Update EECUTIVE SUMMARY DECEMBER 2015 Executive Summary In 2013, the Twin Cities metropolitan area s first bus rapid transit (BRT) line, the METRO Red Line,

More information

2/1/2018. February 1, Item #1 CITIZENS PARTICIPATION

2/1/2018. February 1, Item #1 CITIZENS PARTICIPATION February 1, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments

More information

REPORT CARD FOR CALIFORNIA S INFRASTRUCTURE WHAT YOU SHOULD KNOW ABOUT CALIFORNIA S TRANSIT FACILITIES

REPORT CARD FOR CALIFORNIA S INFRASTRUCTURE WHAT YOU SHOULD KNOW ABOUT CALIFORNIA S TRANSIT FACILITIES TRANSIT GRADE: C- WHAT YOU SHOULD KNOW ABOUT TRANSIT FACILITIES California needs robust, flexible and reliable transit systems to reduce peak congestion on our highways, provide options for citizens who

More information

Alternatives to an Open Competitive Commercial Collection Program Presented by Robert Craggs RAM/SWANA Conference

Alternatives to an Open Competitive Commercial Collection Program Presented by Robert Craggs RAM/SWANA Conference Alternatives to an Open Competitive Commercial Collection Program Presented by Robert Craggs RAM/SWANA Conference October 2018 Burns & McDonnell Our Mission: Make Our Clients Successful Full Service Consulting

More information

Sean P. McBride, Executive Director Kalamazoo Metro Transit. Presentation to Michigan Transportation Planning Association July 13, 2016

Sean P. McBride, Executive Director Kalamazoo Metro Transit. Presentation to Michigan Transportation Planning Association July 13, 2016 Sean P. McBride, Executive Director Kalamazoo Metro Transit Presentation to Michigan Transportation Planning Association July 13, 2016 Metro Transit in Kalamazoo County Square Miles = 132 Urbanized Population:

More information

DRAFT Subject to modifications

DRAFT Subject to modifications TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M DRAFT To: Council Members AGENDA ITEM 7A From: Date: Subject: Staff September 17, 2010 Council Meeting High Speed Rail Update Introduction The

More information

METRO CNG Program Phase I Update. Customer Service Committee April 2014

METRO CNG Program Phase I Update. Customer Service Committee April 2014 METRO CNG Program Phase I Update Customer Service Committee April 2014 METRO CNG Program Background Bus purchase Short term solutions Long term plans Bus purchase options 2 METRO CNG Program April 2011

More information

Draft Agenda. Item Subject Responsible Time. 4. GAS INFORMATION SERVICES PROJECT IMO 10 min. 5. OPTIONS FOR GAS BULLETIN BOARD SYSTEM IMO 15 min

Draft Agenda. Item Subject Responsible Time. 4. GAS INFORMATION SERVICES PROJECT IMO 10 min. 5. OPTIONS FOR GAS BULLETIN BOARD SYSTEM IMO 15 min Gas Advisory Board Draft Agenda Meeting No. 1 Location: Parmelia Hilton, Swan B Room 14 Mill Street, Perth WA 6000 Date: 20 December 2011 Time: 11:15am 12:15pm Item Subject Responsible Time 1. WELCOME

More information

The Engineering Department recommends Council receive this report for information.

The Engineering Department recommends Council receive this report for information. CORPORATE REPORT NO: R161 COUNCIL DATE: July 23, 2018 REGULAR COUNCIL TO: Mayor & Council DATE: July 19, 2018 FROM: General Manager, Engineering FILE: 8740-01 SUBJECT: Surrey Long-Range Rapid Transit Vision

More information

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments

More information

AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, :30 P.M. 1) APPROVAL OF AGENDA 1 min.

AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, :30 P.M. 1) APPROVAL OF AGENDA 1 min. AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, 2016 5:30 P.M. CALL TO ORDER 1) APPROVAL OF AGENDA 1 min. 2) INTRODUCTIONS 5 min. A. Welcome City of Yelm Councilmember Molly Carmody B. Welcome

More information

A Transit Plan for the Future. Draft Network Plan

A Transit Plan for the Future. Draft Network Plan A Transit Plan for the Future Draft Network Plan Project Overview and Status Completed Market Analysis and Service Evaluation. Developed Plan Framework and Guiding Principles. Developed a draft Five Year

More information

ENERGY STRATEGY FOR YUKON. Net Metering Policy DRAFT FOR CONSULTATION

ENERGY STRATEGY FOR YUKON. Net Metering Policy DRAFT FOR CONSULTATION ENERGY STRATEGY FOR YUKON Net Metering Policy DRAFT FOR CONSULTATION February 2011 Page 1 of 4 BACKGROUND The Yukon government released the Energy Strategy for Yukon in January 2009. The Energy Strategy

More information

Thursday, August 15, 2013 MINUTES

Thursday, August 15, 2013 MINUTES \ TRANSIT PLANNING & OPERATIONS COMMITTEE Thursday, August 15, 2013 MINUTES CALL TO ORDER The Regular Meeting of the Transit Planning and Operations (TP&O) Committee was called to order at 4:08 p.m. by

More information

SAFETY, SECURITY, AND TRANSIT PLANNING AND OPERATIONS AGENDA

SAFETY, SECURITY, AND TRANSIT PLANNING AND OPERATIONS AGENDA SAFETY, SECURITY, AND TRANSIT PLANNING AND OPERATIONS Friday, October 20, 2017 12:00 PM VTA Conference Room B-106 3331 North First Street San Jose, CA AGENDA CALL TO ORDER 1. ROLL CALL 2. PUBLIC PRESENTATIONS:

More information

Solar-Wind Specific Request for Proposals

Solar-Wind Specific Request for Proposals Program Description Solar-Wind Specific Request for Proposals Power Production from Green Resources in North Carolina 04/19/2006 NC GreenPower (NCGP) is a statewide program designed to improve the quality

More information

MARTA s blueprint for the future. COFFEE AND CONVERSATION Kyle Keahey, More MARTA Atlanta Dec. 5, 2018

MARTA s blueprint for the future. COFFEE AND CONVERSATION Kyle Keahey, More MARTA Atlanta Dec. 5, 2018 MARTA s blueprint for the future COFFEE AND CONVERSATION Kyle Keahey, More MARTA Atlanta Dec. 5, 2018 TODAY S AGENDA About MARTA Economic development/local impact More MARTA Atlanta program Program summary/timeline

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: March 26, 2014 SUBJECT: COMMUNITY BUS SERVICES ACTION ITEM RECOMMENDATION It is recommended that the Board not approve any routing

More information

SUBJECT: CONTRACT C080S, HOIST REPLACEMENT AT BUS MAINTENANCE DIVISIONS 3, 5, 9, 10, AND 18, PETERSON HYDRAULICS AND ROTARY LIFT, A JOINT VENTURE

SUBJECT: CONTRACT C080S, HOIST REPLACEMENT AT BUS MAINTENANCE DIVISIONS 3, 5, 9, 10, AND 18, PETERSON HYDRAULICS AND ROTARY LIFT, A JOINT VENTURE æ Metro Metropolitan Transportation Authority One Gateway Plaza Los Angeles, CA 9 012-2952 3~ 213-922.2000 Tel metro. net OPERATIONS COMMITTEE NOVEMBER 15, 2007 SUBJECT: CONTRACT C080S, HOIST REPLACEMENT

More information

Chapter 7. Transportation Capital Improvement Projects. Chapter 7

Chapter 7. Transportation Capital Improvement Projects. Chapter 7 Chapter 7 Transportation Capital Improvement Projects Chapter 7 81 Chapter 7 Transportation Capital Improvement Projects Local Transportation Sales Tax Programs For over three decades, Santa Clara County

More information

Washington Metropolitan Area Transit Authority Board Action/Information Summary

Washington Metropolitan Area Transit Authority Board Action/Information Summary Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: Resolution: Yes No TITLE: LRT and Streetcar Interoperability Study PURPOSE: To brief the

More information

Draft Results and Open House

Draft Results and Open House Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi

More information

Parking Management Element

Parking Management Element Parking Management Element The State Transportation Planning Rule, adopted in 1991, requires that the Metropolitan Planning Organization (MPO) area implement, through its member jurisdictions, a parking

More information

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit Sound Transit Long-Range Plan Update Issue Paper S.1: Tacoma Link Integration with Central Link Prepared for: Sound Transit Prepared by: Quade & Douglas, Inc. FINAL March 2005 Foreword This issue paper

More information

B. Approval of the Statement of Proceedings/Minutes for the meeting of October 24, 2017.

B. Approval of the Statement of Proceedings/Minutes for the meeting of October 24, 2017. COUNTY OF SAN DIEGO AIR POLLUTION CONTROL BOARD REGULAR MEETING MEETING AGENDA WEDNESDAY, NOVEMBER 15, 2017, 9:00 AM BOARD OF SUPERVISORS NORTH CHAMBER 1600 PACIFIC HIGHWAY SAN DIEGO, CA 92101 A. Roll

More information

ACTION: ESTABLISH LIFE-OF-PROJECT BUDGET FOR UP TO 100 NEW COMPO BUSES

ACTION: ESTABLISH LIFE-OF-PROJECT BUDGET FOR UP TO 100 NEW COMPO BUSES QD Metro Los Angeles County Metropolitan Transportation Authority One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro.net oplo OPERATIONS COMMITTEE June 16, 2011 SUBJECT: PURCHASE REPLACEMENT

More information

Caltrain Modernization EMU Procurement

Caltrain Modernization EMU Procurement Caltrain Modernization EMU Procurement Boarding Height CAC Meeting May 20, 2015 Context 2 1 Riders (Boardings) Average Weekday Ridership Since 2004 143% increase 60,000 55,000 50,000 45,000 40,000 35,000

More information

Martha s Vineyard Regional Transit Authority

Martha s Vineyard Regional Transit Authority Martha s Vineyard Regional Transit Authority Annual Report Fiscal Year 2005 Martha s Vineyard Transit Authority Fiscal Year ending June 30, 2005 Annual Report Angela E. Grant, Administrator Advisory Board

More information

Muni Forward: Get On Board! Siemens S200 SF Light Rail Vehicle

Muni Forward: Get On Board! Siemens S200 SF Light Rail Vehicle Muni Forward: Get On Board! Siemens S200 SF Light Rail Vehicle 07 15 2014 SAN FRANCISCO, CALIFORNIA 1 The Right Vehicle to Meet Increasing Demand for Rail Transit in the City Meets Central Subway time-table

More information

COMMITTEE FOR TRANSPORTATION MOBILITY & ACCESSIBILITY AGENDA

COMMITTEE FOR TRANSPORTATION MOBILITY & ACCESSIBILITY AGENDA COMMITTEE FOR TRANSPORTATION MOBILITY & ACCESSIBILITY Thursday, September 13, 2018 10:00 AM VTA Conference Room B-106 3331 North First Street San Jose, CA AGENDA COMMITTEE MISSION The VTA Committee for

More information

NOTICE OF REGULARLY SCHEDULED BOARD MEETINGS

NOTICE OF REGULARLY SCHEDULED BOARD MEETINGS NOTICE OF REGULARLY SCHEDULED BOARD MEETINGS NEW JERSEY TRANSIT CORPORATION NJ TRANSIT RAIL OPERATIONS, INC. NJ TRANSIT BUS OPERATIONS, INC. NJ TRANSIT MERCER, INC. NJ TRANSIT MORRIS, INC. TO WHOM IT MAY

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS FREQUENTLY ASKED QUESTIONS 2018 What is the More MARTA Atlanta program? The More MARTA Atlanta program is a collaborative partnership between MARTA and the City of Atlanta to develop and implement a program

More information

CITY HALL 455 North Rexford Drive 4th. Floor Conference Room A Beverly Hills, CA Thursday, November 30, :00 AM AGENDA

CITY HALL 455 North Rexford Drive 4th. Floor Conference Room A Beverly Hills, CA Thursday, November 30, :00 AM AGENDA Beverly Hills City Council Liaison I Public Works Commission Committee will conduct a Special Meeting, at the following time and place, and will address the agenda listed below: CITY HALL 455 North Rexford

More information

Waco Rapid Transit Corridor (RTC) Feasibility Study

Waco Rapid Transit Corridor (RTC) Feasibility Study Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM

More information

Dear New Clean Cities Stakeholder:

Dear New Clean Cities Stakeholder: Dear New Clean Cities Stakeholder: I am writing to invite you to join the Florida Gold Coast Clean Cities Coalition. We are a voluntary public and private partnership, which is dedicated to reducing the

More information

Overview of Transit Funding and Planning in the PACTS Region

Overview of Transit Funding and Planning in the PACTS Region Overview of Transit Funding and Planning in the PACTS Region Presentation to PACTS Transit Committee and Federal Transit Administration Representatives February 8, 2018 Transit Agencies Agency Communities

More information

End-of-Year Performance Report FY Community Relations Committee December 5, 2018

End-of-Year Performance Report FY Community Relations Committee December 5, 2018 End-of-Year Performance Report FY 2018 Community Relations Committee December 5, 2018 Annual Summary Shuttles Ridership All Modes Performance Statistics Highlights All Modes Initiatives 2 Bus Ridership

More information

Westchester County Department of Public Works and Transportation First and Last Mile Connections TNC Partnership Study

Westchester County Department of Public Works and Transportation First and Last Mile Connections TNC Partnership Study Westchester County Department of Public Works and Transportation First and Last Mile Connections TNC Partnership Study Mobility Advisory Forum December 11, 2018 Naomi Klein, Director of Planning Craig

More information

MEMORANDUM. Proposed Town of Chapel Hill Green Fleets Policy

MEMORANDUM. Proposed Town of Chapel Hill Green Fleets Policy AGENDA #4k MEMORANDUM TO: FROM: SUBJECT: Mayor and Town Council W. Calvin Horton, Town Manager Proposed Town of Chapel Hill Green Fleets Policy DATE: June 15, 2005 The attached resolution would adopt the

More information

APPROVE CONTRACT MODIFICATION AWARD

APPROVE CONTRACT MODIFICATION AWARD 5 One Gateway Plaza Los Angeles, CA 9 012.2952 213.922.2000 Tel metro. net SYSTEM SAFETY AND OPERATIONS COMMITTEE SEPTEMBER 20, 2012 SUBJECT: ACTION: ENGINE REBUILD KITS APPROVE CONTRACT MODIFICATION AWARD

More information

East San Fernando Valley Transit Corridor. Information Session, October 10, 2017

East San Fernando Valley Transit Corridor. Information Session, October 10, 2017 East San Fernando Valley Transit Corridor Information Session, October 10, 2017 1 Welcome and Meeting Purpose Introductions Metro Transit Corridors Planning Metro Real Estate Metro Community Relations

More information

Policy Note. Vanpools in the Puget Sound Region The case for expanding vanpool programs to move the most people for the least cost.

Policy Note. Vanpools in the Puget Sound Region The case for expanding vanpool programs to move the most people for the least cost. Policy Note Vanpools in the Puget Sound Region The case for expanding vanpool programs to move the most people for the least cost Recommendations 1. Saturate vanpool market before expanding other intercity

More information

High Speed Rail Conference

High Speed Rail Conference High Speed Rail Conference Denver, October 23, 2012 FAST START PROJECT FOR PENINSULA HIGH-SPEED RAIL Kern Jacobson InfraConsult LLC Objective Evaluate incremental approach to expedite high-speed rail to

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: May 28, 2009 SUBJECT: DON MILLS STATION ACTION ITEM RECOMMENDATIONS It is recommended that the Commission: 1. Endorse the

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

SAN FRANCISCO TO SAN JOSE PROJECT UPDATE

SAN FRANCISCO TO SAN JOSE PROJECT UPDATE SAN FRANCISCO TO SAN JOSE PROJECT UPDATE San Francisco County Transportation Authority Tuesday, April 25, 2017 Ben Tripousis, Northern California Regional Director HIGH-SPEED RAIL: Connecting California

More information

Policy Advisory Committee Meeting November 13, 2013

Policy Advisory Committee Meeting November 13, 2013 Midtown Corridor Alternatives ti Analysis Policy Advisory Committee Meeting November 13, 2013 Today s Agenda Introductions Follow up from September meeting Alternatives review Process update Key evaluation

More information

DART Priorities Overview

DART Priorities Overview City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee

More information

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1 Executive Summary Introduction The Eastside Transit Corridor Phase 2 Project is a vital public transit infrastructure investment that would provide a transit connection to the existing Metro Gold Line

More information

What We Heard Report - Metro Line NW LRT

What We Heard Report - Metro Line NW LRT What We Heard Report - Metro Line NW LRT by Metro Line NW LRT Project Team LRT Projects City of Edmonton April 11, 2018 Project / Initiative Background Name Date Location Metro Line Northwest Light Rail

More information

SamTrans Business Plan Update May 2018

SamTrans Business Plan Update May 2018 SamTrans Business Plan Update May 2018 SamTrans Business Plan Core Principles: 1. Sustain and enhance services for the transit-dependent 2. Expand and innovate mobility services 3. Promote programs that

More information

ADA Policy Deviated Fixed Route Procedures

ADA Policy Deviated Fixed Route Procedures 2014 ADA Policy Deviated Fixed Route Procedures Shirley Lyons Manager 807 E Main, P.O. Box 517 Molalla, OR 97038 Phone: 503-829-7000 Email: slyons@sctd.org South Clackamas Transportation District Americans

More information

Matters Arising from 13rd Annual General Meeting

Matters Arising from 13rd Annual General Meeting Communications Regulators Association of Southern Africa (CRASA) The 14th Annual General Meeting Birchwood Hotel - Boksburg Johannesburg, South Africa 29 to 30 March 2011 Matters Arising from 13rd Annual

More information

MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Recommend to Board. Final Action

MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Recommend to Board. Final Action MOTION NO. M2018-160 Purchase of Thirteen 42-foot Double Deck Expansion Buses MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations Committee PROPOSED ACTION 12/06/2018 12/20/2018 Recommend to Final

More information

EMU Procurement Seats/Standees/Bikes/Bathroom

EMU Procurement Seats/Standees/Bikes/Bathroom EMU Procurement Seats/Standees/Bikes/Bathroom LPMG May 28, 2015 Purpose Seats / standees / bikes / bathroom balance Develop framework for Draft EMU RFP Feedback on car configuration and range of increased

More information

SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE JULY 17, 2014 PURCHASE OF HYBRID SEDANS APPROVE CONTRACT AWARD ACTION: RECOMMENDATION

SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE JULY 17, 2014 PURCHASE OF HYBRID SEDANS APPROVE CONTRACT AWARD ACTION: RECOMMENDATION One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE JULY 17, 2014 SUBJECT: ACTION: PURCHASE OF HYBRID SEDANS APPROVE CONTRACT AWARD

More information

BART s Transbay Core Capacity Project

BART s Transbay Core Capacity Project BART s Transbay Core Capacity Project Duncan Watry, Principal Planner Bay Area Rapid Transit Oakland, CA dwatry@bart.gov Donald Emerson, Principal Consultant WSP Parsons Brinckerhoff San Francisco, CA

More information

Environment and Infrastructure Services

Environment and Infrastructure Services Agenda Item 5 Staff Report for Committee of the Whole Meeting Department: Division: Subject: Environment and Infrastructure Services Environment Services Waste Collection Contract Purpose: To provide Council

More information

Georgetown Transit ADA Plan

Georgetown Transit ADA Plan Georgetown Transit ADA Plan INTRODUCTION The Americans with Disabilities Act of 1990 (ADA) requires that public entities that operate non-commuter fixed route transportation services also provide complementary

More information

National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA )

National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA ) National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA ) Presenter: National Treasury 18 November 2015 90 day Action Plan In November 2014, the Ministers

More information

Memorandum. To: The Arlington County Board Date: June 29, 2018 From: Subject:

Memorandum. To: The Arlington County Board Date: June 29, 2018 From: Subject: OFFICE OF THE COUNTY MANAGER 2100 Clarendon Boulevard, Suite 302, Arlington, VA 22201 TEL 703.228.3120 FAX 703.228.3218 TTY 703.228.4611 www.arlingtonva.us Memorandum To: The Arlington County Board Date:

More information

ADA Paratransit Service Guidelines

ADA Paratransit Service Guidelines ADA Paratransit Service Guidelines The Mountain Express PO Box 3482 803 Butte Ave. Crested Butte, CO 81224 p (970) 349-5616 f (970) 349-7214 www.mtnexp.org EFFECTIVE DATE December 2017 1 Table of Contents

More information

Alternative and Renewable Fuel and Vehicle Technology Program. Advisory Committee Meeting

Alternative and Renewable Fuel and Vehicle Technology Program. Advisory Committee Meeting Alternative and Renewable Fuel and Vehicle Technology Program Advisory Committee Meeting December 4, 2012 California Energy Commission Hearing Room A 1 Meeting Agenda 10:00 Introductions and Opening Remarks

More information

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014

Arterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014 Arterial Bus Rapid Transit System Policy Oversight Committee April 7, 2014 1 Meeting Agenda Welcome and Introductions A Line - Project Status Shelter and Pylon Development Arterial BRT Branding Update

More information

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of November 18, 2017

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of November 18, 2017 ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of November 18, 2017 DATE: November 7, 2017 SUBJECT: Six-Month Extension of car2go Demonstration Study Agreement C. M. RECOMMENDATIONS: 1. Authorize

More information

Speaker Information Tweet about this presentation #TransitGIS

Speaker Information Tweet about this presentation #TransitGIS Making the Case for Transit: the Transit Competitiveness Index Title William E. Walter, GISP Speaker Information Tweet about this presentation #TransitGIS Understanding Conditions in Each Travel Market

More information

4 COSTS AND OPERATIONS

4 COSTS AND OPERATIONS 4 COSTS AND OPERATIONS 4.1 INTRODUCTION This chapter summarizes the estimated capital and operations and maintenance (O&M) costs for the Modal and High-Speed Train (HST) Alternatives evaluated in this

More information

Energy Technical Memorandum

Energy Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter

More information

At-A-Glance MEDIA INFORMATION GUIDE

At-A-Glance MEDIA INFORMATION GUIDE At-A-Glance MEDIA INFORMATION GUIDE THEN & NOW HISTORY On February 18, 1964, the Pennsylvania General Assembly established the Southeastern Pennsylvania Transportation Authority (SEPTA) to provide public

More information

PS 127 Abnormal / Indivisible Loads Policy

PS 127 Abnormal / Indivisible Loads Policy PS 127 Abnormal / Indivisible Loads Policy June 2017 Version 1.5 Statement of legislative compliance This document has been drafted to comply with the general and specific duties in the Equality Act 2010;

More information

GIBRALTAR ERDF OPERATIONAL PROGRAMME POST ADOPTION STATEMENT

GIBRALTAR ERDF OPERATIONAL PROGRAMME POST ADOPTION STATEMENT Intended for Government of Gibraltar Document type Report Date January 2015 GIBRALTAR ERDF OPERATIONAL PROGRAMME 2014-2020 POST ADOPTION STATEMENT GIBRALTAR ERDF OPERATIONAL PROGRAMME 2014-2020 POST ADOPTION

More information

MOTION NO. M Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion

MOTION NO. M Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion MOTION NO. M2016-66 Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations Committee 07/07/16

More information